SlideShare a Scribd company logo
Agenda
• Project
• Operational Work
• Project Management
• Program
• Portfolio
• Project Management Office (PMO)
• Objectives
Agenda
• Constraints
• Stakeholders
• Organizational Structure
• Life Cycle
• Lessons Learned
Definition of Project
Project
• Temporary endeavor with a beginning and an
end
• Creates a unique product, service or result
Enroll in this course: http://goo.gl/LxhZqP
Why are Projects Initiated?
• Market Demand
• Strategic Opportunity/Business Need
• Social Need
• Environmental Consideration
• Customer Request
• Technological Advance
• Legal Requirement
Example of Project
• Construction of Bosphorus Bridge.
• Beginning: 20 Feb
1970
• End: 1 June 1973
• Temporary
• Unique
Definition of Operational Work
• Most of the work being done in organizations
• Ongoing
• Repetitive
Enroll in this course: http://goo.gl/LxhZqP
Example of Operational Work
• Yearly maintenance of Bosphorus Bridge
• Repetitive
(yearly)
Initiating Planning Executing
Monitoring
and
Controlling
Closing
What is Project Management?
• Project management is the application of
knowledge, skills, tools and techniques to project
activities to meet the project requirements.
• Profession growing rapidly
• Follows systematic process
• Processes of project management:
What is Project Management?
Knowledge Areas:
• Project Management Framework
• Project Management Processes
• Integration Management
• Scope Management
• Time Management
• Cost Management
Enroll in this course:
http://goo.gl/LxhZqP
What is Project Management?
Knowledge Areas:
• Quality Management
• Human Resource Management
• Communications Management
• Risk Management
• Procurement Management
• Stakeholder Management
Definition of Program
• Group of projects
• Management is coordinated because they are
related
Enroll in this course: http://goo.gl/LxhZqP
Example of Program
• Manufacturing a new Airbus Airplane
Projects:
• Avionic Systems
• Communication
Systems
• Entertainment System
• Security System
• ….
Definition of Portfolio
• Group of programs to achieve a business
goal.
• Programs might not be related.
• It is important to serve for same business
goal.
Enroll in this course: http://goo.gl/LxhZqP
Example of Portfolio
• Airbus will develop 3 new airplane versions in
6 years.
• Strategic goal: to be the world’s most
passenger carrying airplane company.
Enroll in this course: http://goo.gl/LxhZqP
Project, Program, Portfolio…
6 Year Airplane
Manufacturing
Portfolio
Airbus 921 Program
Avionic Systems Project
…
Airbus 922 Program
Communication Systems
Project
…
Airbus 923 Program
Entertainment System
Project
…
Comparative Overview (Project,
Program, Portfolio)
Comparative Overview (Project,
Program, Portfolio)
Project Management Office (PMO)
Department centralizes the management of projects
PMO Structures:
1. Supportive: Supplies templates, best practices,
training, lessons learned…etc. Acts as repository.
(Low degree of control)
2. Controlling: Supports and requires compliance
to tools, methods. (Moderate degree of control)
3. Directive: Directly manages the projects. (High
degree of control)
Project Management Office (PMO)
PMO May:
• Manage interdependencies between projects
• Help provide resources
• Terminate projects
• Monitor compliance with organizational
processes
• Gather lessons learned
Project Management Office (PMO)
PMO May:
• Provide templates
• Provide guidance
• Provide centralized communication about the
projects
• Be part of change control board
• Be a stakeholder
Enroll in this course:
http://goo.gl/LxhZqP
Role of the Project Manager
• Person assigned by the organization to lead
the team that is responsible for achieving
project objectives.
• Depending on the type of organization
Project Manager can report to
Functional Manager
Program Manager
Portfolio Manager
Enroll in this course:
http://goo.gl/LxhZqP
Role of the Project Manager
• Link between strategy and team.
• Project Manager should have following
competencies:
Knowledge (about project management)
Performance (how he applies knowledge)
Personal (behavior)
Enroll in this course: http://goo.gl/LxhZqP
Interpersonal Skills of a Project
Manager
• Leadership
• Team building
• Motivation
• Communication
• Influencing
• Decision Making
• Political & Cultural
Awarenes
• Negotiation
• Trust building
• Conflict Management
• Coaching
Objectives
• What needs to be achieved as a result of
project.
• For example: Constructing Bosphorus Bridge:
• Objectives:
6 lanes in total (3+3)
Must carry at least 2,500,000 kgs
Must resist at least 8.5 Richter Earth-Quake
Important Points - Objectives
• Projects are considered complete when
objectives are met
• A reason for terminating a project before
completion is that the project objectives
cannot be met
• Meeting project objectives is under Project
Manager’s responsibility.
Important Points - Objectives
• Quality activities are for checking project
meets its objectives.
• There is a trade-off between requirements &
objectives.
Enroll in this course: http://goo.gl/LxhZqP
Management by Objectives (MBO)
• A management philosophy
1. Establish clear & realistic objectives
2. Periodically evaluate if objectives are met
3. Implement corrective action
Enroll in this course: http://goo.gl/LxhZqP
Constraints Cost
Scope
Quality
Customer
Satisfaction
Risk
Resources
Time
Constraints
• If there is a change on one constraint,
evaluate its effect on other constraints
• For example, if your schedule is shortened,
there might be
 Additional resources (cost increase)
 Faster completion (risk increase, quality
decrease)
Organizational Process Assets
• Plans, processes, policies, procedures and
knowledge bases specific to and used by the
performing organization.
• Includes lessons learned and historical info.
• Input to most planning processes.
• Corporate knowlede base is for storing and
retreiving information.
Enterprise Environmental Factors
• Conditions, not under control of the project
team, that influence, constrain or direct the
project.
• Input to most planning processes.
• Examples:
Organizational culture, structure, and governance
Government or Industry Standards
Political Climate
Marketplace Conditions
Stakeholders
• People whose interests may be positively or
negatively impacted by the project.
• Includes all members of the project team.
• Identifying stakeholders, understanding their
relative degree of influence on a project, and
balancing their demands, needs and
expectations are critical to success of the
project.
Stakeholders
Stakeholders of Boshphorus Bridge
Project
• Everybody who worked in the project
• Government
• Sea transporters
• People residing closer to
the bridge
• ….
Project Governance
• Provides the project manager and team with
structure, processes, decision-making models
and tools for managing the project.
• Involves stakeholders, documented
procedures, and standards, responsibilities
and authorities.
Enroll in this course: http://goo.gl/LxhZqP
Project Team
• Project Manager and the group of individuals
who perform the project work.
• Project Manager is the leader of the team,
and his authority is over the project
members.
Enroll in this course: http://goo.gl/LxhZqP
Organizational Structure
• One of the main factors affecting projects in
an organization.
Three types of organizations:
• Functional
• Projectized
• Matrix
Functional
• Most common form
• Grouped by areas of specialization
Marketing, Human Resources, IT, Sales… etc.
• Requests and information is transmitted
through head of departments
• Team members do
(project work)+(departmental work)
Functional
Projectized
• Entire company is organized by projects.
• Project Managers have control of projects.
• No departments for resources.
• When project is over, personnel is either
assigned to a new project, or need to find a
new job.
Enroll in this course: http://goo.gl/LxhZqP
Projectized
Matrix (Projectized+Functional)
• Attempt to get strengths of projectized and
functional organization.
• Team members report to project manager
and functional manager.
Team Member
Project Manager
Functional Manager
(Software Development
Manager)
Matrix (Projectized+Functional)
• Team members do
(project work)+(departmental work)
Strong Matrix Balanced Matrix Weak Matrix
Power of Project Manager Power of Functional Manager
P
O
W
E
R
Matrix (Projectized+Functional)
• In weak matrix organization, Project
Managers are:
Project Expediter: acts as staff assistant and
communications coordinator.
Cannot make any decision.
Project Coordinator: acts like Project Expediter,
but has some power and can take some
decisions.
Weak Matrix
Balanced Matrix
Strong Matrix
Advantages of Functional Organization
• Easier management of specialists
• Team members report to only one supervisor
• Similar resources are centralized
(e.g., software developers to IT department)
• Clearly defined career paths in areas of
specialization
Developer  Senior Developer  Expert
Developer  Architect… etc.
Disadvantages of Functional Organization
• People place more emphasis on their
functional specialty to the detriment of the
project.
• No career path in project management
• The project manager has little or no
authority.
Advantages of Projectized Organization
• Efficient project organization
• Loyalty to the project
• More effective communications than
functional
Enroll in this course: http://goo.gl/LxhZqP
Disadvantages of Projectized
Organization
• No “home” when project is finished
• Lack of professionalism in disciplines
• Duplication of facilities and job functions
• Less efficient use of resources
Advantages of Matrix Organization
• Highly visible project objectives
• Improved project manager control over
resources
• More support from functional areas
• Maximum utilization of scarce resources
• Better coordination
• Better horizontal and vertical dissemination of
information
• Team member maintain a “home”
Disadvantages of Matrix Organization
• Extra administration is required
• More then one boss for project teams
• More complex to monitor and control
• Tougher problems with resource allocation
• Need extensive policies and procedures
• Functional managers may have different priorities
than project managers
• Higher potential for conflict
Comparative Overview of Organizational
Structures
Life Cycle
• Progression through a series of differing stages
of development
• Generic
Life Cycle
for all
projects
Life Cycle
• Impact of Variable Based on Project Time
Product Life Cycle
• Starts from conception of a new product to its
withdrawal
• A Product can require many projects over its life
• Determine
customer’s need
(conception)
• Analyze
competition
(maturity)
Project Life Cycle
• Changes depending on the industry or
organization’s preferences.
Construction:
Feasibility Planning Design Production Turnover Startup
Project Life Cycle
Information Technology (IT):
High Level
Design
Detailed
Design
Coding Testing Installation Conversion
Turnover
to
Operations
Enroll in this course: http://goo.gl/LxhZqP
Project Management Process Groups
• Project Management Process includes:
Initiating
Planning
Execution
Monitoring & Controlling
Closing
• Life cycle can change from project to project, but
project management process groups are same.
Project Management Process
Project Life Cycle in a Small Project
Project Life Cycle in a Large Project
Lessons Learned
• Includes
What was done right
What was done wrong
What would be done if the project could be re-done
• Should cover:
Technical aspects of the project
Project Management (WBS, risk planning, etc.)
Management (communications, leadership)
Enroll in this course:
http://goo.gl/LxhZqP
Role of Lessons Learned
Enroll in this course: http://goo.gl/LxhZqP
Question #1
A project manager is trying to complete a software
development project, but cannot get enough attention for
the project. Resources are focused on completing process-
related work and the project manager has little authority
to properly assign resources. What form of organization
must the project manager be working in?
A-) Functional
B-) Matrix
C-) Expediter
D-) Coordinator
Question #1
A project manager is trying to complete a software
development project, but cannot get enough attention for
the project. Resources are focused on completing process-
related work and the project manager has little authority
to properly assign resources. What form of organization
must the project manager be working in?
A-) Functional
B-) Matrix
C-) Expediter
D-) Coordinator
Enroll in this course:
http://goo.gl/LxhZqP
Question #2
The project life cycle differs from the product life
cycle in that the project life cycle:
A-) Does not incorporate a methodology
B-) Is different for each industry
C-) Can spawn many projects
D-) Describes project management activities
Question #2
The project life cycle differs from the product life
cycle in that the project life cycle:
A-) Does not incorporate a methodology
B-) Is different for each industry
C-) Can spawn many projects
D-) Describes project management activities
Question #3
Your management has decided that all orders will be treated as “projects” and
that project managers will be used to update orders daily, to resolve issues,
and to ensure that the customer formally accepts the product within 30 days
of completion. Revenue from the individual orders can vary from $100 to
$150,000. The project manager will not be required to perform planning or
provide documentation other than daily status. How would you define this
situation?
A-) Because each individual order is a “temporary endeavor”, each order is a
project.
B-) This is program management since there are multiple projects involved.
C-) This is a recurring process.
D-) Orders incurring revenue over $100,000 would be considered projects and
would involve project management.
Question #3
Your management has decided that all orders will be treated as “projects” and
that project managers will be used to update orders daily, to resolve issues,
and to ensure that the customer formally accepts the product within 30 days
of completion. Revenue from the individual orders can vary from $100 to
$150,000. The project manager will not be required to perform planning or
provide documentation other than daily status. How would you define this
situation?
A-) Because each individual order is a “temporary endeavor”, each order is a
project.
B-) This is program management since there are multiple projects involved.
C-) This is a recurring process.
D-) Orders incurring revenue over $100,000 would be considered projects and
would involve project management.
Question #4
The previous project manager for your project managed it
without much project organization. There is a lack of
management control and no clearly defined project deliverables.
Which of the following would be the BEST choice for getting your
project better organized?
A-) Adopt a life cycle approach to the project
B-) Develop lessons learned for each phase
C-) Develop specific work plans for each work package
D-) Develop a description of the product of the project.
Question #4
The previous project manager for your project managed it
without much project organization. There is a lack of
management control and no clearly defined project deliverables.
Which of the following would be the BEST choice for getting your
project better organized?
A-) Adopt a life cycle approach to the project
B-) Develop lessons learned for each phase
C-) Develop specific work plans for each work package
D-) Develop a description of the product of the project.
Question #5
A company is making an effort to improve its project
performance and create historical records of past
projects. What is the BEST way to accomplish this?
A-) Create project management plans
B-) Create lessons learned
C-) Create network diagrams
D-) Create status reports Enroll in this course:
http://goo.gl/LxhZqP
Question #5
A company is making an effort to improve its project
performance and create historical records of past
projects. What is the BEST way to accomplish this?
A-) Create project management plans
B-) Create lessons learned
C-) Create network diagrams
D-) Create status reports Enroll in this course:
http://goo.gl/LxhZqP
Question #6
One of your team members informs you that he does
not know which of the many projects he is working on is
the most important. Who should determine the
priorities among projects in a company?
A-) The project manager
B-) The project management team
C-) The project management office (PMO)
D-) The team
Question #6
One of your team members informs you that he does
not know which of the many projects he is working on is
the most important. Who should determine the
priorities among projects in a company?
A-) The project manager
B-) The project management team
C-) The project management office (PMO)
D-) The team
Question #7
A market demand, a business need, and/or legal
requirement are examples of:
A-) Reasons to hire a project manager
B-) Reasons projects are initiated
C-) Reasons people or businesses become stakeholders.
D-) Reasons to sponsor a project.
Enroll in this course: http://goo.gl/LxhZqP
Question #7
A market demand, a business need, and/or legal
requirement are examples of:
A-) Reasons to hire a project manager
B-) Reasons projects are initiated
C-) Reasons people or businesses become stakeholders.
D-) Reasons to sponsor a project.
Question #8
Consideration of ongoing operations and maintenance is
crucially important to products of projects. Ongoing
operations and maintenance should:
A-) Be included as activities to be performed during project
closure
B-) Have a separate phase in the project life cycle, because a
large portion of life cycle costs is devoted to maintenance
and operations
C-) Not be viewed as part of a project. A project is
temporary with a definite beginning and end.
D-) Be viewed as a separate project.
Question #8
Consideration of ongoing operations and maintenance is
crucially important to products of projects. Ongoing
operations and maintenance should:
A-) Be included as activities to be performed during project
closure
B-) Have a separate phase in the project life cycle, because a
large portion of life cycle costs is devoted to maintenance
and operations
C-) Not be viewed as part of a project. A project is
temporary with a definite beginning and end.
D-) Be viewed as a separate project.
Question #9
Lessons learned are BEST completed by:
A-) The project manager
B-) The team
C-) The sponsor
D-) The stakeholders
Enroll in this course: http://goo.gl/LxhZqP
Question #9
Lessons learned are BEST completed by:
A-) The project manager
B-) The team
C-) The sponsor
D-) The stakeholders
Question #10
A manager and the head of engineering discuss a
change to a major work package. After the meeting, the
manager contacts you and tells you to complete the
paperwork to make the change. This is an example of:
A-) Management attention to scope management.
B-) Management planning.
C-) A project expediter position.
D-) A change control system.
Question #10
A manager and the head of engineering discuss a
change to a major work package. After the meeting, the
manager contacts you and tells you to complete the
paperwork to make the change. This is an example of:
A-) Management attention to scope management.
B-) Management planning.
C-) A project expediter position.
D-) A change control system.

More Related Content

What's hot

Implementing PMO
Implementing PMOImplementing PMO
Implementing PMOTURKI , PMP
 
Pmp handbook
Pmp handbookPmp handbook
Project Management With Scrum
Project Management With ScrumProject Management With Scrum
Project Management With Scrum
Tommy Norman
 
01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-mao01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-mao
mao-osman73
 
Project management
Project managementProject management
Project management
Yasir Afzal Rajput
 
Lições Aprendidas
Lições AprendidasLições Aprendidas
Lições Aprendidas
Paulo Cunha
 
What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...
Invensis Learning
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
JustAcademy
 
Project Plan And Estimation
Project Plan And EstimationProject Plan And Estimation
Project Plan And Estimation
Rajan Srivastava
 
PMP MINDMAP
PMP MINDMAPPMP MINDMAP
PMP MINDMAP
SamDesuza2
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
Anand Bobade
 
Agile Placemat v9
Agile Placemat v9Agile Placemat v9
Agile Placemat v9Chris Webb
 
Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016
Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016
Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016
Taller Negócio Digitais
 
An introduction to workforce planning
An introduction to workforce planningAn introduction to workforce planning
An introduction to workforce planning
Orgvue
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesMurilo Juchem
 
PMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts Overview
PMOfficers PMOAcademy
 
Agile transformation Explanined
Agile transformation ExplaninedAgile transformation Explanined
Agile transformation Explanined
LeadingAgile
 
Estrategia Agil de Negocios
Estrategia Agil de NegociosEstrategia Agil de Negocios
Estrategia Agil de Negocios
Mariana Zaparolli Martins
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
Ahmad Maharma, PMP,RMP
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
Syed Zaid Irshad
 

What's hot (20)

Implementing PMO
Implementing PMOImplementing PMO
Implementing PMO
 
Pmp handbook
Pmp handbookPmp handbook
Pmp handbook
 
Project Management With Scrum
Project Management With ScrumProject Management With Scrum
Project Management With Scrum
 
01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-mao01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-mao
 
Project management
Project managementProject management
Project management
 
Lições Aprendidas
Lições AprendidasLições Aprendidas
Lições Aprendidas
 
What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Project Plan And Estimation
Project Plan And EstimationProject Plan And Estimation
Project Plan And Estimation
 
PMP MINDMAP
PMP MINDMAPPMP MINDMAP
PMP MINDMAP
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Agile Placemat v9
Agile Placemat v9Agile Placemat v9
Agile Placemat v9
 
Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016
Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016
Kanban no Fluxo Unificado de Portfolio de Projetos - Agile Brazil 2016
 
An introduction to workforce planning
An introduction to workforce planningAn introduction to workforce planning
An introduction to workforce planning
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of Processes
 
PMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts Overview
 
Agile transformation Explanined
Agile transformation ExplaninedAgile transformation Explanined
Agile transformation Explanined
 
Estrategia Agil de Negocios
Estrategia Agil de NegociosEstrategia Agil de Negocios
Estrategia Agil de Negocios
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
 

Viewers also liked

How to Apply PMI PMP Certification Exam
How to Apply PMI PMP Certification ExamHow to Apply PMI PMP Certification Exam
How to Apply PMI PMP Certification Exam
Resit Gulec, MBA, PMP®, ITIL®
 
Path to PMP!
Path to PMP!Path to PMP!
Path to PMP!
Edureka!
 
50 secrets-of-the-pmp-exam-white-paper
50 secrets-of-the-pmp-exam-white-paper50 secrets-of-the-pmp-exam-white-paper
50 secrets-of-the-pmp-exam-white-paper
Achintya Kumar
 
Pmp presentation v7 evelyn copy
Pmp presentation v7 evelyn   copyPmp presentation v7 evelyn   copy
Pmp presentation v7 evelyn copy
Evelyn Millhouse-Fort, PMP
 
Inter national standards for project management - fitsilis
Inter national standards for project management - fitsilisInter national standards for project management - fitsilis
Inter national standards for project management - fitsilisPanos Fitsilis
 
Pmp capm exam preparation
Pmp capm exam preparationPmp capm exam preparation
Pmp capm exam preparationFreedom Monk
 
Pmp taking first attempt public
Pmp taking first attempt  publicPmp taking first attempt  public
Pmp taking first attempt public
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Adekunle Adeniyi PMI-(PMP, RMP, SP, ACP, PBA) MCTS
 
PMESN: Step-by-step guide to filling PMP application
PMESN: Step-by-step guide to filling PMP applicationPMESN: Step-by-step guide to filling PMP application
PMESN: Step-by-step guide to filling PMP application
PMExamSmartNotes
 
Project scope management
Project scope managementProject scope management
Project scope management
ANOOP S NAIR
 

Viewers also liked (13)

Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
How to Apply PMI PMP Certification Exam
How to Apply PMI PMP Certification ExamHow to Apply PMI PMP Certification Exam
How to Apply PMI PMP Certification Exam
 
The Self-Winding Clock_On the (Credit) Hour
The Self-Winding Clock_On the (Credit) HourThe Self-Winding Clock_On the (Credit) Hour
The Self-Winding Clock_On the (Credit) Hour
 
Path to PMP!
Path to PMP!Path to PMP!
Path to PMP!
 
50 secrets-of-the-pmp-exam-white-paper
50 secrets-of-the-pmp-exam-white-paper50 secrets-of-the-pmp-exam-white-paper
50 secrets-of-the-pmp-exam-white-paper
 
Sample PMP Interest Mini-Round v2
Sample PMP Interest Mini-Round v2Sample PMP Interest Mini-Round v2
Sample PMP Interest Mini-Round v2
 
Pmp presentation v7 evelyn copy
Pmp presentation v7 evelyn   copyPmp presentation v7 evelyn   copy
Pmp presentation v7 evelyn copy
 
Inter national standards for project management - fitsilis
Inter national standards for project management - fitsilisInter national standards for project management - fitsilis
Inter national standards for project management - fitsilis
 
Pmp capm exam preparation
Pmp capm exam preparationPmp capm exam preparation
Pmp capm exam preparation
 
Pmp taking first attempt public
Pmp taking first attempt  publicPmp taking first attempt  public
Pmp taking first attempt public
 
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
 
PMESN: Step-by-step guide to filling PMP application
PMESN: Step-by-step guide to filling PMP applicationPMESN: Step-by-step guide to filling PMP application
PMESN: Step-by-step guide to filling PMP application
 
Project scope management
Project scope managementProject scope management
Project scope management
 

Similar to Online PMP Exam Certification Training - 35 Hours

Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
Yesica Adicondro
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
agathamarlinee
 
01 introductiontoframework
01 introductiontoframework01 introductiontoframework
01 introductiontoframework
Dhamo daran
 
Session 2-Introduction to PPM -b.pdf
Session 2-Introduction to PPM -b.pdfSession 2-Introduction to PPM -b.pdf
Session 2-Introduction to PPM -b.pdf
NyakanaJoseph1
 
1-Introduction to PM.pptx
1-Introduction to PM.pptx1-Introduction to PM.pptx
1-Introduction to PM.pptx
std27233
 
1. introduction
1. introduction1. introduction
1. introduction
BhuWan Khadka
 
Chapter-4.pptx
Chapter-4.pptxChapter-4.pptx
Chapter-4.pptx
ssuser2a57a3
 
PROJECT MANAGEMNET LECTURE 1.ppt
PROJECT MANAGEMNET LECTURE 1.pptPROJECT MANAGEMNET LECTURE 1.ppt
PROJECT MANAGEMNET LECTURE 1.ppt
Omar91305
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
Ahmed Elshaboury,PMP,LEED GA
 
Project management
Project managementProject management
Project managementobsession56
 
Lecture 27 Projects (03-11-20).pptx
Lecture 27 Projects (03-11-20).pptxLecture 27 Projects (03-11-20).pptx
Lecture 27 Projects (03-11-20).pptx
chikuverma1
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
Rasan Samarasinghe
 
2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf
2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf
2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf
EduardoFuenzalida10
 
Spm lecture-2
Spm lecture-2Spm lecture-2
Spm lecture-2
Sulman Ahmed
 
Module 1.pptx
Module 1.pptxModule 1.pptx
Module 1.pptx
Vinish P
 
INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT
Harihara puthiran
 
Chapter 1- Overview of Project Management.pdf
Chapter 1- Overview of Project Management.pdfChapter 1- Overview of Project Management.pdf
Chapter 1- Overview of Project Management.pdf
LuvamBiz
 
PMI-PMP6 Lecture 02: Project Management Framework_v1.0
PMI-PMP6 Lecture 02: Project Management Framework_v1.0PMI-PMP6 Lecture 02: Project Management Framework_v1.0
PMI-PMP6 Lecture 02: Project Management Framework_v1.0
PhuocNT (Fresher.VN)
 

Similar to Online PMP Exam Certification Training - 35 Hours (20)

Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
 
01 introductiontoframework
01 introductiontoframework01 introductiontoframework
01 introductiontoframework
 
Session 2-Introduction to PPM -b.pdf
Session 2-Introduction to PPM -b.pdfSession 2-Introduction to PPM -b.pdf
Session 2-Introduction to PPM -b.pdf
 
1-Introduction to PM.pptx
1-Introduction to PM.pptx1-Introduction to PM.pptx
1-Introduction to PM.pptx
 
1. introduction
1. introduction1. introduction
1. introduction
 
Chapter-4.pptx
Chapter-4.pptxChapter-4.pptx
Chapter-4.pptx
 
PROJECT MANAGEMNET LECTURE 1.ppt
PROJECT MANAGEMNET LECTURE 1.pptPROJECT MANAGEMNET LECTURE 1.ppt
PROJECT MANAGEMNET LECTURE 1.ppt
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
Project management
Project managementProject management
Project management
 
Lecture 27 Projects (03-11-20).pptx
Lecture 27 Projects (03-11-20).pptxLecture 27 Projects (03-11-20).pptx
Lecture 27 Projects (03-11-20).pptx
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf
2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf
2-INTRODUCTION _ ENVIRONMENTS IN WHICH PROJECTS OPERATE_v4.pdf
 
Spm lecture-2
Spm lecture-2Spm lecture-2
Spm lecture-2
 
Module 1.pptx
Module 1.pptxModule 1.pptx
Module 1.pptx
 
INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT
 
Chapter 1- Overview of Project Management.pdf
Chapter 1- Overview of Project Management.pdfChapter 1- Overview of Project Management.pdf
Chapter 1- Overview of Project Management.pdf
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
 
PM LnL
PM LnLPM LnL
PM LnL
 
PMI-PMP6 Lecture 02: Project Management Framework_v1.0
PMI-PMP6 Lecture 02: Project Management Framework_v1.0PMI-PMP6 Lecture 02: Project Management Framework_v1.0
PMI-PMP6 Lecture 02: Project Management Framework_v1.0
 

Recently uploaded

Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Po-Chuan Chen
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 

Recently uploaded (20)

Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 

Online PMP Exam Certification Training - 35 Hours

  • 1.
  • 2. Agenda • Project • Operational Work • Project Management • Program • Portfolio • Project Management Office (PMO) • Objectives
  • 3. Agenda • Constraints • Stakeholders • Organizational Structure • Life Cycle • Lessons Learned
  • 4. Definition of Project Project • Temporary endeavor with a beginning and an end • Creates a unique product, service or result Enroll in this course: http://goo.gl/LxhZqP
  • 5. Why are Projects Initiated? • Market Demand • Strategic Opportunity/Business Need • Social Need • Environmental Consideration • Customer Request • Technological Advance • Legal Requirement
  • 6. Example of Project • Construction of Bosphorus Bridge. • Beginning: 20 Feb 1970 • End: 1 June 1973 • Temporary • Unique
  • 7. Definition of Operational Work • Most of the work being done in organizations • Ongoing • Repetitive Enroll in this course: http://goo.gl/LxhZqP
  • 8. Example of Operational Work • Yearly maintenance of Bosphorus Bridge • Repetitive (yearly)
  • 9. Initiating Planning Executing Monitoring and Controlling Closing What is Project Management? • Project management is the application of knowledge, skills, tools and techniques to project activities to meet the project requirements. • Profession growing rapidly • Follows systematic process • Processes of project management:
  • 10. What is Project Management? Knowledge Areas: • Project Management Framework • Project Management Processes • Integration Management • Scope Management • Time Management • Cost Management Enroll in this course: http://goo.gl/LxhZqP
  • 11. What is Project Management? Knowledge Areas: • Quality Management • Human Resource Management • Communications Management • Risk Management • Procurement Management • Stakeholder Management
  • 12. Definition of Program • Group of projects • Management is coordinated because they are related Enroll in this course: http://goo.gl/LxhZqP
  • 13. Example of Program • Manufacturing a new Airbus Airplane Projects: • Avionic Systems • Communication Systems • Entertainment System • Security System • ….
  • 14. Definition of Portfolio • Group of programs to achieve a business goal. • Programs might not be related. • It is important to serve for same business goal. Enroll in this course: http://goo.gl/LxhZqP
  • 15. Example of Portfolio • Airbus will develop 3 new airplane versions in 6 years. • Strategic goal: to be the world’s most passenger carrying airplane company. Enroll in this course: http://goo.gl/LxhZqP
  • 16. Project, Program, Portfolio… 6 Year Airplane Manufacturing Portfolio Airbus 921 Program Avionic Systems Project … Airbus 922 Program Communication Systems Project … Airbus 923 Program Entertainment System Project …
  • 19. Project Management Office (PMO) Department centralizes the management of projects PMO Structures: 1. Supportive: Supplies templates, best practices, training, lessons learned…etc. Acts as repository. (Low degree of control) 2. Controlling: Supports and requires compliance to tools, methods. (Moderate degree of control) 3. Directive: Directly manages the projects. (High degree of control)
  • 20. Project Management Office (PMO) PMO May: • Manage interdependencies between projects • Help provide resources • Terminate projects • Monitor compliance with organizational processes • Gather lessons learned
  • 21. Project Management Office (PMO) PMO May: • Provide templates • Provide guidance • Provide centralized communication about the projects • Be part of change control board • Be a stakeholder Enroll in this course: http://goo.gl/LxhZqP
  • 22. Role of the Project Manager • Person assigned by the organization to lead the team that is responsible for achieving project objectives. • Depending on the type of organization Project Manager can report to Functional Manager Program Manager Portfolio Manager Enroll in this course: http://goo.gl/LxhZqP
  • 23. Role of the Project Manager • Link between strategy and team. • Project Manager should have following competencies: Knowledge (about project management) Performance (how he applies knowledge) Personal (behavior) Enroll in this course: http://goo.gl/LxhZqP
  • 24. Interpersonal Skills of a Project Manager • Leadership • Team building • Motivation • Communication • Influencing • Decision Making • Political & Cultural Awarenes • Negotiation • Trust building • Conflict Management • Coaching
  • 25. Objectives • What needs to be achieved as a result of project. • For example: Constructing Bosphorus Bridge: • Objectives: 6 lanes in total (3+3) Must carry at least 2,500,000 kgs Must resist at least 8.5 Richter Earth-Quake
  • 26. Important Points - Objectives • Projects are considered complete when objectives are met • A reason for terminating a project before completion is that the project objectives cannot be met • Meeting project objectives is under Project Manager’s responsibility.
  • 27. Important Points - Objectives • Quality activities are for checking project meets its objectives. • There is a trade-off between requirements & objectives. Enroll in this course: http://goo.gl/LxhZqP
  • 28. Management by Objectives (MBO) • A management philosophy 1. Establish clear & realistic objectives 2. Periodically evaluate if objectives are met 3. Implement corrective action Enroll in this course: http://goo.gl/LxhZqP
  • 30. Constraints • If there is a change on one constraint, evaluate its effect on other constraints • For example, if your schedule is shortened, there might be  Additional resources (cost increase)  Faster completion (risk increase, quality decrease)
  • 31. Organizational Process Assets • Plans, processes, policies, procedures and knowledge bases specific to and used by the performing organization. • Includes lessons learned and historical info. • Input to most planning processes. • Corporate knowlede base is for storing and retreiving information.
  • 32. Enterprise Environmental Factors • Conditions, not under control of the project team, that influence, constrain or direct the project. • Input to most planning processes. • Examples: Organizational culture, structure, and governance Government or Industry Standards Political Climate Marketplace Conditions
  • 33. Stakeholders • People whose interests may be positively or negatively impacted by the project. • Includes all members of the project team. • Identifying stakeholders, understanding their relative degree of influence on a project, and balancing their demands, needs and expectations are critical to success of the project.
  • 35. Stakeholders of Boshphorus Bridge Project • Everybody who worked in the project • Government • Sea transporters • People residing closer to the bridge • ….
  • 36. Project Governance • Provides the project manager and team with structure, processes, decision-making models and tools for managing the project. • Involves stakeholders, documented procedures, and standards, responsibilities and authorities. Enroll in this course: http://goo.gl/LxhZqP
  • 37. Project Team • Project Manager and the group of individuals who perform the project work. • Project Manager is the leader of the team, and his authority is over the project members. Enroll in this course: http://goo.gl/LxhZqP
  • 38. Organizational Structure • One of the main factors affecting projects in an organization. Three types of organizations: • Functional • Projectized • Matrix
  • 39. Functional • Most common form • Grouped by areas of specialization Marketing, Human Resources, IT, Sales… etc. • Requests and information is transmitted through head of departments • Team members do (project work)+(departmental work)
  • 41. Projectized • Entire company is organized by projects. • Project Managers have control of projects. • No departments for resources. • When project is over, personnel is either assigned to a new project, or need to find a new job. Enroll in this course: http://goo.gl/LxhZqP
  • 43. Matrix (Projectized+Functional) • Attempt to get strengths of projectized and functional organization. • Team members report to project manager and functional manager. Team Member Project Manager Functional Manager (Software Development Manager)
  • 44. Matrix (Projectized+Functional) • Team members do (project work)+(departmental work) Strong Matrix Balanced Matrix Weak Matrix Power of Project Manager Power of Functional Manager P O W E R
  • 45. Matrix (Projectized+Functional) • In weak matrix organization, Project Managers are: Project Expediter: acts as staff assistant and communications coordinator. Cannot make any decision. Project Coordinator: acts like Project Expediter, but has some power and can take some decisions.
  • 49. Advantages of Functional Organization • Easier management of specialists • Team members report to only one supervisor • Similar resources are centralized (e.g., software developers to IT department) • Clearly defined career paths in areas of specialization Developer  Senior Developer  Expert Developer  Architect… etc.
  • 50. Disadvantages of Functional Organization • People place more emphasis on their functional specialty to the detriment of the project. • No career path in project management • The project manager has little or no authority.
  • 51. Advantages of Projectized Organization • Efficient project organization • Loyalty to the project • More effective communications than functional Enroll in this course: http://goo.gl/LxhZqP
  • 52. Disadvantages of Projectized Organization • No “home” when project is finished • Lack of professionalism in disciplines • Duplication of facilities and job functions • Less efficient use of resources
  • 53. Advantages of Matrix Organization • Highly visible project objectives • Improved project manager control over resources • More support from functional areas • Maximum utilization of scarce resources • Better coordination • Better horizontal and vertical dissemination of information • Team member maintain a “home”
  • 54. Disadvantages of Matrix Organization • Extra administration is required • More then one boss for project teams • More complex to monitor and control • Tougher problems with resource allocation • Need extensive policies and procedures • Functional managers may have different priorities than project managers • Higher potential for conflict
  • 55. Comparative Overview of Organizational Structures
  • 56. Life Cycle • Progression through a series of differing stages of development • Generic Life Cycle for all projects
  • 57. Life Cycle • Impact of Variable Based on Project Time
  • 58. Product Life Cycle • Starts from conception of a new product to its withdrawal • A Product can require many projects over its life • Determine customer’s need (conception) • Analyze competition (maturity)
  • 59. Project Life Cycle • Changes depending on the industry or organization’s preferences. Construction: Feasibility Planning Design Production Turnover Startup
  • 60. Project Life Cycle Information Technology (IT): High Level Design Detailed Design Coding Testing Installation Conversion Turnover to Operations Enroll in this course: http://goo.gl/LxhZqP
  • 61. Project Management Process Groups • Project Management Process includes: Initiating Planning Execution Monitoring & Controlling Closing • Life cycle can change from project to project, but project management process groups are same.
  • 63. Project Life Cycle in a Small Project
  • 64. Project Life Cycle in a Large Project
  • 65. Lessons Learned • Includes What was done right What was done wrong What would be done if the project could be re-done • Should cover: Technical aspects of the project Project Management (WBS, risk planning, etc.) Management (communications, leadership) Enroll in this course: http://goo.gl/LxhZqP
  • 66. Role of Lessons Learned Enroll in this course: http://goo.gl/LxhZqP
  • 67. Question #1 A project manager is trying to complete a software development project, but cannot get enough attention for the project. Resources are focused on completing process- related work and the project manager has little authority to properly assign resources. What form of organization must the project manager be working in? A-) Functional B-) Matrix C-) Expediter D-) Coordinator
  • 68. Question #1 A project manager is trying to complete a software development project, but cannot get enough attention for the project. Resources are focused on completing process- related work and the project manager has little authority to properly assign resources. What form of organization must the project manager be working in? A-) Functional B-) Matrix C-) Expediter D-) Coordinator Enroll in this course: http://goo.gl/LxhZqP
  • 69. Question #2 The project life cycle differs from the product life cycle in that the project life cycle: A-) Does not incorporate a methodology B-) Is different for each industry C-) Can spawn many projects D-) Describes project management activities
  • 70. Question #2 The project life cycle differs from the product life cycle in that the project life cycle: A-) Does not incorporate a methodology B-) Is different for each industry C-) Can spawn many projects D-) Describes project management activities
  • 71. Question #3 Your management has decided that all orders will be treated as “projects” and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from $100 to $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation? A-) Because each individual order is a “temporary endeavor”, each order is a project. B-) This is program management since there are multiple projects involved. C-) This is a recurring process. D-) Orders incurring revenue over $100,000 would be considered projects and would involve project management.
  • 72. Question #3 Your management has decided that all orders will be treated as “projects” and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from $100 to $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation? A-) Because each individual order is a “temporary endeavor”, each order is a project. B-) This is program management since there are multiple projects involved. C-) This is a recurring process. D-) Orders incurring revenue over $100,000 would be considered projects and would involve project management.
  • 73. Question #4 The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables. Which of the following would be the BEST choice for getting your project better organized? A-) Adopt a life cycle approach to the project B-) Develop lessons learned for each phase C-) Develop specific work plans for each work package D-) Develop a description of the product of the project.
  • 74. Question #4 The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables. Which of the following would be the BEST choice for getting your project better organized? A-) Adopt a life cycle approach to the project B-) Develop lessons learned for each phase C-) Develop specific work plans for each work package D-) Develop a description of the product of the project.
  • 75. Question #5 A company is making an effort to improve its project performance and create historical records of past projects. What is the BEST way to accomplish this? A-) Create project management plans B-) Create lessons learned C-) Create network diagrams D-) Create status reports Enroll in this course: http://goo.gl/LxhZqP
  • 76. Question #5 A company is making an effort to improve its project performance and create historical records of past projects. What is the BEST way to accomplish this? A-) Create project management plans B-) Create lessons learned C-) Create network diagrams D-) Create status reports Enroll in this course: http://goo.gl/LxhZqP
  • 77. Question #6 One of your team members informs you that he does not know which of the many projects he is working on is the most important. Who should determine the priorities among projects in a company? A-) The project manager B-) The project management team C-) The project management office (PMO) D-) The team
  • 78. Question #6 One of your team members informs you that he does not know which of the many projects he is working on is the most important. Who should determine the priorities among projects in a company? A-) The project manager B-) The project management team C-) The project management office (PMO) D-) The team
  • 79. Question #7 A market demand, a business need, and/or legal requirement are examples of: A-) Reasons to hire a project manager B-) Reasons projects are initiated C-) Reasons people or businesses become stakeholders. D-) Reasons to sponsor a project. Enroll in this course: http://goo.gl/LxhZqP
  • 80. Question #7 A market demand, a business need, and/or legal requirement are examples of: A-) Reasons to hire a project manager B-) Reasons projects are initiated C-) Reasons people or businesses become stakeholders. D-) Reasons to sponsor a project.
  • 81. Question #8 Consideration of ongoing operations and maintenance is crucially important to products of projects. Ongoing operations and maintenance should: A-) Be included as activities to be performed during project closure B-) Have a separate phase in the project life cycle, because a large portion of life cycle costs is devoted to maintenance and operations C-) Not be viewed as part of a project. A project is temporary with a definite beginning and end. D-) Be viewed as a separate project.
  • 82. Question #8 Consideration of ongoing operations and maintenance is crucially important to products of projects. Ongoing operations and maintenance should: A-) Be included as activities to be performed during project closure B-) Have a separate phase in the project life cycle, because a large portion of life cycle costs is devoted to maintenance and operations C-) Not be viewed as part of a project. A project is temporary with a definite beginning and end. D-) Be viewed as a separate project.
  • 83. Question #9 Lessons learned are BEST completed by: A-) The project manager B-) The team C-) The sponsor D-) The stakeholders Enroll in this course: http://goo.gl/LxhZqP
  • 84. Question #9 Lessons learned are BEST completed by: A-) The project manager B-) The team C-) The sponsor D-) The stakeholders
  • 85. Question #10 A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of: A-) Management attention to scope management. B-) Management planning. C-) A project expediter position. D-) A change control system.
  • 86. Question #10 A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of: A-) Management attention to scope management. B-) Management planning. C-) A project expediter position. D-) A change control system.