SlideShare a Scribd company logo
1 of 32
0
Dr Tobias Bischof-Niemz
Chief Engineer
Planning for future energy systems : A mini-IRP
for the CSIR campus in Pretoria
Peter Mukoma
Principal Engineer, CSIR
Mamahloko Senatla (Msenatla@csir.co.za)
Henerica Tazvinga (HTazvinga@csir.co.za)
Enose Moholisa (Emoholisa@csir.co.za)
NCPC Industrial Efficiency Conference 2017
Cape Town, 15 September 2017
1
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
• Conclusion
2
Objectives of the study
Background
• Future energy systems will largely be based on Distributed
Energy Resources (DER) – a combination of Variable
Renewable Energy (VRE), storage and demand response
technologies
• Technology and systems innovations are required to design,
build and operate such energy systems in an optimal manner
• The business model of utilities will also be affected
Response: Energy-Autonomous Campus Programme
The CSIR has established a programme where it implements its
research findings as a test bed for future energy systems
• Demonstrate how to cost-efficiently design and operate an
energy system based on DER
• Integration of energy storage in form of batteries & hydrogen
• Energy savings and demand response measures
• Key outcomes: System design/operations,
technology demonstration, future utility
business model
3
Objectives of the study
The objective of the study was to determine least cost generation capacity mix for
CSIR’s Pretoria campus between 2016 and 2022 by considering the following energy
usage scenarios:
1) Business as usual (BAU) scenario
 Increasing the electrical energy consumption by 0.7% per annum until 2022
2) Energy Efficiency (EE) scenario
 Decreasing the electrical energy consumption by 20% by the year 2022. 5%
decrease annually starting in 2018
1. The normal load increase is 0.7%, therefore the net decrease is 4.3%
1
30.4 GWhr
6 MW
3 MW
R31 m (24% Demand Charges)
2016 Energy usage
Maximum Demand
Base load
Total cost
4
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
• Conclusion
5
Scope
1) The modelling timeframe is from 2016 – 2022
2) Includes existing power plants (single axis, dual axis and rooftop in bldg. 17), approximately 1.011 MW
3) The supply technology options considered for optimization in this iteration of the model are:
 PV
 Wind
 Biogas and
 Tshwane supply
4) Tshwane’s Megaflex tariff as Variable operating and maintenance costs for
 Energy tariff increasing at 9.43% annually and peak demand charge increasing at 0.7% annually
6
Boundary conditions within which optimisation was based on
 The modelling considers the time of use tariff from Tshwane as is in 2016 and the structure is assumed not
to change until 2022. The only change is the increasing cost of electricity and peak demand charges
(R/MWh and R/MW).
 This means that this modelling does not consider the SSEG tariff which will be implemented once NERSA
approves it.
 The optimization assumes balancing of demand for the CSIR campus, excess demand is allowed but by its
nature PLEXOS will minimize overcapacity, hence minimizing generation of excess energy
 The excess energy is not given any value, assumed to be wasted
 Tshwane is providing unlimited supply to the campus
7
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
• Conclusion
8
Study Methodology
Modelling
framework
(PLEXOS®)
LT1 techno-economic
least-cost optimisation in
long term horizon
MT/ST2 production cost
testing detailed
generation dispatch in
short and long term
horizon
Outputs
For Business-As-Usual scenario:
 Total generation costs
 Capacity expansion (MW)
 Energy share (MWh)
For EE scenario:
 Weekly typical generation profiles
Inputs
1) 2 Demand Forecasts
 BAU with 0.7% growth
 EE with 4.3% reduction
2) Existing and committed plants:
 Committed plants (2.011 MW)
 Plant performance
3) New Supply Options:
 Wind, PV rooftop, biogas, batteries
 Plant costs assumptions
 Plant performance
4) Tshwane Tariff:
Megaflex (Time of Use)
 Peak (P)
 Standard (S)
 Off_Peak (O)
1 LT = Long-term
2 MT/ST = Medium-term/Short-term
O
P
S
The peak demand charges are done after optimising system for energy.
9
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
• Conclusion
10
Demand Forecasts: modelled demand for both BAU and EE Scenarios
0
5
10
15
20
25
30
35
40
2006 2008 2010 2012 2014 2016 2018 2020 2022
24,6
31,7
30,4
Energy (GWh)
Energy Efficiency (EE) HistoricalBusiness as usual (BAU)
For BAU Scenario, energy
consumptions increases by
0.7% annually starting in 2017
For EE Scenario, energy
consumptions increases by
0.7% and also decreases by
5% starting in 2018. resulting
in overall annual decrease of
4.3%.
The difference between BAU
scenario and EE scenario is 7
GWh
11
Plant Performance characteristics:
12
Wind resource performance: Wind profile shows a very low load factor
of (16%)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0,4
0,5
0,6
0,7
0,8
0,9
0,0
1,0
1,1
0,2
0,1
0,3
Normalisedwindprofile(1MW)
Average weekly generationWeekly generation
Unlike what the aggregation study from CSIR showed, where on average
South Africa has wind load factor around 38%. The campus is one of the low
wind sites with only 16% load factor. This means for every 1 MW of wind
installed, only 0.16 MW is useful to generate power.
13
Typical weekly generation profile of a single tracking system in Pretoria
campus
The average capacity factor
for single tracking system is
21%.
The average capacity factor
for dual axis tracking
system 31%.
The average capacity factor
for rooftop PV is 17%.
15
Time of use tariff in a typical week in winter and summer of 2016 and 2022
0 2 4 6 8 10 12 14 16 18 20 22 24
0,5
1,5
2,0
2,5
0,0
1,0
3,0
0,63
Hours
1,02
0,44
Tariff(R/kWh)
0 2 4 6 8 10 12 14 16 18 20 22 24
3,0
2,5
2,0
1,5
1,0
0,5
0,0 Hours
0,95
0,52
2,78
Tariff(R/kWh)
SundaySaturdayWeekday
Summer 2016
Winter 2016
0 2 4 6 8 10 12 14 16 18 20 22 24
2
3
0
5
4
1
Hours
0,76
1,08
1,75
Tariff(R/kWh)
0 2 4 6 8 10 12 14 16 18 20 22 24
5
3
4
1
2
0
1,63
4,77
0,89
Hours
Tariff(R/kWh)
Weekday Saturday Sunday
Summer 2022
Winter 2022
9.43%
17
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
• Conclusion
18
Results presentation format
As-is capacity case assumes a case where the
CSIR is not doing any new installations of supply
options. In this case, the analysis is interested in
the annual cost and the net present value of the
total system from 2016 to 2022.
Capacity case 1:
 As-is
Demand scenarios
 BAU
 EE
Capacity case 2:
 Optimized
Demand scenarios
 BAU
 EE
The Optimized case assumes that there are
some new investments allowed in the supply
side and then the analysis is interested in the
capacity to be installed (MW), the total annual
energy cost and the net present value of the
total system from 2016 to 2022
250
203
558
558
250
558
2016
1.011
2015
203
1.000
2.011
2017/8
Single axis tracker
Dual axis tracker
Rooftop PV
Rooftop 2
+
2017/8
CommittedandBuilt
2,011
Any new
least cost
build
options
19
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
 As – is capacity case
 Optimized capacity case
• Conclusion
20
As-is under BAU demand scenario
20
60
50
40
30
0
10
2022
57
47
3
7
2021
51
41
3
7
2020
46
36
3
7
2019
41
31
3
6
2018
37
27
3
6
2017
34
25
2
7
2016
31
23
Total cost (R million)
1
7
TshwanePVPeak demand cost
Tshwane energy tariff increases from R23 million
to R47 million by 2022 if CSIR decides to install
only 2.011 MW of PV (as the system is)
The peak demand charge costs, decreases by R1
million in 2018, when the 1 MW rooftop PV is
introduced into the system and starts to increase
by R1 million in 2020, due to increase peak
demand charges
The cost of generating electricity using PV
increases from R1 million in 2016 to R3 million in
2022
The total system cost (bill) increases from R31
million in 2016 to R57 million in 2022.
21
As-is under EE demand growth scenario
25
20
15
10
5
0
30
45
40
35
2022
43
35
3
5
2021
41
32
3
5
2020
39
30
3
5
2019
35
26
3
6
2017
34
25
2
7
36
31
23
1
7
28
3
6
Total cost (R million)
20182016
TshwanePeak demand cost PV
The peak demand charge costs, decreases by R1
million in 2018, when the 1 MW rooftop PV is
introduced into the system and starts to increase
by R1 million in 2020, due to increase peak
demand charges
24
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
 As – is capacity case
 Optimized capacity case
• Conclusion
25
BAU demand scenario new least cost capacity
2 2 2 2
2
4 4 4
2
1
1
0
1
2
3
4
5
6
7
20172016 2022
6
2021
6
2020
6
2018 2019
4
Installedcapacity(MW)
New PV
Commited/Approved
26
EE demand scenario new least cost capacity
2 2 2 2
2
3 3 3
2
1
1
4,0
5,5
5,0
4,5
1,5
3,5
3,0
2,5
2,0
1,0
0,5
0,0
Installedcapacity(MW)
20172016 2019
4
5
2020
5 5
20222018 2021
Commited/Approved
New PV
27
Optimised BAU demand scenario
40
35
30
25
50
20
45
15
10
5
0
3
2017
34
25
2
7
2016
31
23
1
7
Total cost (R million)
6
2018
5
37
27
2022
50
36
8
6
2021
45
31
8
5
2020
40
27
8
5
2019
38
27
6
PV TshwanePeak demand cost
Under the optimized capacity case,
the total system cost increases from
R31 million in 2016 to R50 million in
2022
PV generation cost increases from R1
million in 2016 to R8 million in 2022.
This is due to increased capacity
equalling 6 MW by 2022.
28
Optimized EE demand scenario
25
5
30
0
35
10
20
50
15
45
40
2022
6
10
2 4
8
Total cost (R million)
2021
4
7
27
48
45
25
7
4
2020
41
23
7
4
2019
39
24
6
5
2018
37
26
3
6
2017
34
25
2
7
2016
31
23
1
7
EE cost
PV
Tshwane
Peak demand cost
Under the optimized capacity case,
the total system cost increases from
R31 million in 2016 to R48 million in
2022
In comparison to the BAU demand
scenario, the EE optimized case is
cheaper than the BAU optimized by
R2 million (This R50 – R48)
29
0
1
2
3
4
5
6
7
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
126
131
136
141
146
151
156
161
166
Demand(MW)
2016 PV Supply
Tshwane
Demand
Monday Tuesda Wednesday Thursday Friday
Saturday
Sunday
Typical generation in a week in 2016 with only 558 kWp of dual axis
Hours
30
0
1
2
3
4
5
6
7
1
5
9
13
17
21
25
29
33
37
41
45
49
53
57
61
65
69
73
77
81
85
89
93
97
101
105
109
113
117
121
125
129
133
137
141
145
149
153
157
161
165
Demand(MW)
Hours
2018 Excess
PV Supply
Tshwane
Demand
SundaySaturdayFridayThursdayWednesdayTuesdayMonday
Typical generation in a week in 2018 after installing 2.011 MW of PV
31
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
126
131
136
141
146
151
156
161
166
Demand(MW)
Hours
2022 Excess
PV Supply
Tshwane
Demand
Monday Thursday SaturdayFriday SundayTuesday Wednesday
Even during times of excess generation, energy is not wasted everyday
32
Total discounted system cost over the study period
300
250
200
150
100
50
0
Total cost (R )
Optimized
BAU scenario
274
196
37
41
As-is BAU
scenario
295
230
19
46
As-is EE
scenario
258
198
19
41
242
172
33
Optimized
EE scenario
37
Pead demand cost
PV
Tshwane
If the CSIR decides not to investment in power
plants any further and does not invest in EE
measures, the organization will pay a total
amount of R295 million between 2016 and
2022. If it decides not to invest, but improve
the energy system by implement EE measures,
CSIR will pay R258 million (excluding DSM
investment costs).
Therefore its economic to install an additional 3
MW and 4 MW in both the cases where
demand is decreasing and increasing.
By investing in PV, the CSIR will respectively
save between R16 and R21 million for the cases
where efficiency measures are implemented
and when efficiency measures are not
implemented
33
Agenda
• Objectives of the study
• Scope and boundary conditions
• Methodology
• Input data and assumptions
• Results
• Conclusion
34
Conclusions and way forward
 Leaving the campus energy consumption as it is today will be costly for the CSIR in the next
5 years
 The least cost additional new generation capacity to install in the campus is 4 MW for
Business as usual scenario
 The least cost additional new generation capacity to install in the campus is 3 MW for
Energy Efficiency scenario
 The Optimised EE scenario is the most economic option saving R53m against BAU
 Biogas and wind are not economic during the modelled timeframe
 Energy audits to continue to identify and implement Energy Efficiency and Demand
Response measures
51
Thank you
Re a leboga
Siyathokoza
Enkosi
Siyabonga
Re a leboha
Ro livhuha
Ha Khensa
Dankie
Note: “Thank you” in all official languages of the Republic of South Africa

More Related Content

What's hot

Introducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIntroducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIEA-ETSAP
 
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...IEA-ETSAP
 
Techno-Economic Modelling of Cogeneration Options for the South African Sugar...
Techno-Economic Modelling of Cogeneration Options for the South African Sugar...Techno-Economic Modelling of Cogeneration Options for the South African Sugar...
Techno-Economic Modelling of Cogeneration Options for the South African Sugar...IEA-ETSAP
 
TIMES Course for Master Students in DTU: Reflections and Way Forward
TIMES Course for Master Students in DTU: Reflections and Way ForwardTIMES Course for Master Students in DTU: Reflections and Way Forward
TIMES Course for Master Students in DTU: Reflections and Way ForwardIEA-ETSAP
 
Planning a reliable power system with a high share of renewables in France by...
Planning a reliable power system with a high share of renewables in France by...Planning a reliable power system with a high share of renewables in France by...
Planning a reliable power system with a high share of renewables in France by...IEA-ETSAP
 
Modelling flexible electric vehicle charging in local energy communities
Modelling flexible electric vehicle charging in local energy communitiesModelling flexible electric vehicle charging in local energy communities
Modelling flexible electric vehicle charging in local energy communitiesIEA-ETSAP
 
Modelling global macroeconomic impacts of a carbon constrained energy system ...
Modelling global macroeconomic impacts of a carbon constrained energy system ...Modelling global macroeconomic impacts of a carbon constrained energy system ...
Modelling global macroeconomic impacts of a carbon constrained energy system ...IEA-ETSAP
 
Addressing climate change uncertainty with a monte carloversion of TIMES
Addressing climate change uncertainty with a monte carloversion of TIMESAddressing climate change uncertainty with a monte carloversion of TIMES
Addressing climate change uncertainty with a monte carloversion of TIMESIEA-ETSAP
 
GHG emission reduction due to energy efficiency measures under climate policy
GHG emission reduction due to energy efficiency measures under climate policyGHG emission reduction due to energy efficiency measures under climate policy
GHG emission reduction due to energy efficiency measures under climate policyIEA-ETSAP
 
Status of US CCS projects and data available
Status of US CCS projects and data availableStatus of US CCS projects and data available
Status of US CCS projects and data availableIEA-ETSAP
 
Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...
Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...
Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...IEA-ETSAP
 
Integrative Smart City Planning – Energy system modelling for the city of Evora
Integrative Smart City Planning – Energy system modelling for the city of EvoraIntegrative Smart City Planning – Energy system modelling for the city of Evora
Integrative Smart City Planning – Energy system modelling for the city of EvoraIEA-ETSAP
 
IEA Bioenergy TCP: preparing the role of bioenergy in the future energy system
IEA Bioenergy TCP: preparing the role of bioenergy in the future energy systemIEA Bioenergy TCP: preparing the role of bioenergy in the future energy system
IEA Bioenergy TCP: preparing the role of bioenergy in the future energy systemIEA-ETSAP
 
eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...
eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...
eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...Gianmarco Rossi
 
Residential heat pumps in the future Danish energy system
Residential heat pumps in the future Danish energy systemResidential heat pumps in the future Danish energy system
Residential heat pumps in the future Danish energy systemIEA-ETSAP
 
The Italian White Certificates Scheme - D.Rotiroti, GSE
The Italian White Certificates Scheme - D.Rotiroti, GSE The Italian White Certificates Scheme - D.Rotiroti, GSE
The Italian White Certificates Scheme - D.Rotiroti, GSE Gestore dei Servizi Energetici
 
Load pattern and the deployment of renewables in Taiwan within the TIMES fram...
Load pattern and the deployment of renewables in Taiwan within the TIMES fram...Load pattern and the deployment of renewables in Taiwan within the TIMES fram...
Load pattern and the deployment of renewables in Taiwan within the TIMES fram...IEA-ETSAP
 

What's hot (20)

Introducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIntroducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling Framework
 
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
 
Techno-Economic Modelling of Cogeneration Options for the South African Sugar...
Techno-Economic Modelling of Cogeneration Options for the South African Sugar...Techno-Economic Modelling of Cogeneration Options for the South African Sugar...
Techno-Economic Modelling of Cogeneration Options for the South African Sugar...
 
TIMES Course for Master Students in DTU: Reflections and Way Forward
TIMES Course for Master Students in DTU: Reflections and Way ForwardTIMES Course for Master Students in DTU: Reflections and Way Forward
TIMES Course for Master Students in DTU: Reflections and Way Forward
 
Planning a reliable power system with a high share of renewables in France by...
Planning a reliable power system with a high share of renewables in France by...Planning a reliable power system with a high share of renewables in France by...
Planning a reliable power system with a high share of renewables in France by...
 
Modelling flexible electric vehicle charging in local energy communities
Modelling flexible electric vehicle charging in local energy communitiesModelling flexible electric vehicle charging in local energy communities
Modelling flexible electric vehicle charging in local energy communities
 
Modelling global macroeconomic impacts of a carbon constrained energy system ...
Modelling global macroeconomic impacts of a carbon constrained energy system ...Modelling global macroeconomic impacts of a carbon constrained energy system ...
Modelling global macroeconomic impacts of a carbon constrained energy system ...
 
Addressing climate change uncertainty with a monte carloversion of TIMES
Addressing climate change uncertainty with a monte carloversion of TIMESAddressing climate change uncertainty with a monte carloversion of TIMES
Addressing climate change uncertainty with a monte carloversion of TIMES
 
ICF_Report_Gas_Conservation_Potential_Study
ICF_Report_Gas_Conservation_Potential_StudyICF_Report_Gas_Conservation_Potential_Study
ICF_Report_Gas_Conservation_Potential_Study
 
GHG emission reduction due to energy efficiency measures under climate policy
GHG emission reduction due to energy efficiency measures under climate policyGHG emission reduction due to energy efficiency measures under climate policy
GHG emission reduction due to energy efficiency measures under climate policy
 
Wind power forecasting accuracy and uncertainty in Finland
Wind power forecasting accuracy and uncertainty in FinlandWind power forecasting accuracy and uncertainty in Finland
Wind power forecasting accuracy and uncertainty in Finland
 
Status of US CCS projects and data available
Status of US CCS projects and data availableStatus of US CCS projects and data available
Status of US CCS projects and data available
 
Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...
Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...
Mitigation strategies for transitioning towards ‘net-zero’ energy systems in ...
 
Integrative Smart City Planning – Energy system modelling for the city of Evora
Integrative Smart City Planning – Energy system modelling for the city of EvoraIntegrative Smart City Planning – Energy system modelling for the city of Evora
Integrative Smart City Planning – Energy system modelling for the city of Evora
 
Monitoring information for EU reporting
Monitoring information for EU reportingMonitoring information for EU reporting
Monitoring information for EU reporting
 
IEA Bioenergy TCP: preparing the role of bioenergy in the future energy system
IEA Bioenergy TCP: preparing the role of bioenergy in the future energy systemIEA Bioenergy TCP: preparing the role of bioenergy in the future energy system
IEA Bioenergy TCP: preparing the role of bioenergy in the future energy system
 
eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...
eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...
eni_Rossi Gianmarco - Energy Management System for the Optimization of the Up...
 
Residential heat pumps in the future Danish energy system
Residential heat pumps in the future Danish energy systemResidential heat pumps in the future Danish energy system
Residential heat pumps in the future Danish energy system
 
The Italian White Certificates Scheme - D.Rotiroti, GSE
The Italian White Certificates Scheme - D.Rotiroti, GSE The Italian White Certificates Scheme - D.Rotiroti, GSE
The Italian White Certificates Scheme - D.Rotiroti, GSE
 
Load pattern and the deployment of renewables in Taiwan within the TIMES fram...
Load pattern and the deployment of renewables in Taiwan within the TIMES fram...Load pattern and the deployment of renewables in Taiwan within the TIMES fram...
Load pattern and the deployment of renewables in Taiwan within the TIMES fram...
 

Similar to NCPC IE Conference 2017 P Mukoma

IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Implementing Agreement (IA)
 
Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent
Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sentElectricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent
Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sentLouis Oelofsen
 
Soft-linking of the TIMES-Italy model to a power and gas system model
Soft-linking of the TIMES-Italy model to a power and gas system modelSoft-linking of the TIMES-Italy model to a power and gas system model
Soft-linking of the TIMES-Italy model to a power and gas system modelIEA-ETSAP
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyTransGrid AU
 
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...IEA-ETSAP
 
"Taking on TIAM" a new user´s experience and lessons learned
"Taking on TIAM" a new user´s experience and lessons learned"Taking on TIAM" a new user´s experience and lessons learned
"Taking on TIAM" a new user´s experience and lessons learnedIEA-ETSAP
 
Renewable Energy Technology integration for the island of Cyprus: A cost-opti...
Renewable Energy Technology integration for the island of Cyprus: A cost-opti...Renewable Energy Technology integration for the island of Cyprus: A cost-opti...
Renewable Energy Technology integration for the island of Cyprus: A cost-opti...IEA-ETSAP
 
Drivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketDrivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketLeonardo ENERGY
 
KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016sfact
 
Annual Technology Baseline-2022 Electricity Update.pdf
Annual Technology Baseline-2022 Electricity Update.pdfAnnual Technology Baseline-2022 Electricity Update.pdf
Annual Technology Baseline-2022 Electricity Update.pdfMehmetEren26
 
Overview of solar power generation in india
Overview of solar power generation in indiaOverview of solar power generation in india
Overview of solar power generation in indiaBinit Das
 
jguijarro_Dc4cities_DCDC_Abril15
jguijarro_Dc4cities_DCDC_Abril15jguijarro_Dc4cities_DCDC_Abril15
jguijarro_Dc4cities_DCDC_Abril15Jordi Guijarro
 
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgridMethodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgridSustainableEnergyAut
 

Similar to NCPC IE Conference 2017 P Mukoma (20)

IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
 
Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent
Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sentElectricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent
Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent
 
Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
Enabling low-temperature renewable district energy in cities
Enabling low-temperature renewable district energy in citiesEnabling low-temperature renewable district energy in cities
Enabling low-temperature renewable district energy in cities
 
Soft-linking of the TIMES-Italy model to a power and gas system model
Soft-linking of the TIMES-Italy model to a power and gas system modelSoft-linking of the TIMES-Italy model to a power and gas system model
Soft-linking of the TIMES-Italy model to a power and gas system model
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering Sydney
 
9th IWERN Meeting Presentation
9th IWERN Meeting Presentation9th IWERN Meeting Presentation
9th IWERN Meeting Presentation
 
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
 
"Taking on TIAM" a new user´s experience and lessons learned
"Taking on TIAM" a new user´s experience and lessons learned"Taking on TIAM" a new user´s experience and lessons learned
"Taking on TIAM" a new user´s experience and lessons learned
 
Renewable Energy Technology integration for the island of Cyprus: A cost-opti...
Renewable Energy Technology integration for the island of Cyprus: A cost-opti...Renewable Energy Technology integration for the island of Cyprus: A cost-opti...
Renewable Energy Technology integration for the island of Cyprus: A cost-opti...
 
SHAMS Dubai
SHAMS DubaiSHAMS Dubai
SHAMS Dubai
 
Drivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketDrivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP market
 
KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016
 
Techno-economic assessment and global sensitivity analysis for biomass-based ...
Techno-economic assessment and global sensitivity analysis for biomass-based ...Techno-economic assessment and global sensitivity analysis for biomass-based ...
Techno-economic assessment and global sensitivity analysis for biomass-based ...
 
Annual Technology Baseline-2022 Electricity Update.pdf
Annual Technology Baseline-2022 Electricity Update.pdfAnnual Technology Baseline-2022 Electricity Update.pdf
Annual Technology Baseline-2022 Electricity Update.pdf
 
Overview of solar power generation in india
Overview of solar power generation in indiaOverview of solar power generation in india
Overview of solar power generation in india
 
jguijarro_Dc4cities_DCDC_Abril15
jguijarro_Dc4cities_DCDC_Abril15jguijarro_Dc4cities_DCDC_Abril15
jguijarro_Dc4cities_DCDC_Abril15
 
Energy in Schools by John Dolan
Energy in Schools by John DolanEnergy in Schools by John Dolan
Energy in Schools by John Dolan
 
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgridMethodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
 

More from 7391456

Proudly SA
Proudly SAProudly SA
Proudly SA7391456
 
Cecilia Kinuthia Njenga
Cecilia Kinuthia NjengaCecilia Kinuthia Njenga
Cecilia Kinuthia Njenga7391456
 
WWF Klaudia NCPC - 14 September 2017
WWF Klaudia NCPC - 14 September 2017WWF Klaudia NCPC - 14 September 2017
WWF Klaudia NCPC - 14 September 20177391456
 
New Edition Bridget Fundikwa - Green Cape
New Edition Bridget Fundikwa - Green CapeNew Edition Bridget Fundikwa - Green Cape
New Edition Bridget Fundikwa - Green Cape7391456
 
Henry Roman
Henry RomanHenry Roman
Henry Roman7391456
 
Chantal Ramcharan Kotze
Chantal Ramcharan KotzeChantal Ramcharan Kotze
Chantal Ramcharan Kotze7391456
 
Harro von Blotnitz
Harro von BlotnitzHarro von Blotnitz
Harro von Blotnitz7391456
 
Pippa Notten
Pippa NottenPippa Notten
Pippa Notten7391456
 
Nick Tandi
Nick TandiNick Tandi
Nick Tandi7391456
 
Claire Pengelly
Claire PengellyClaire Pengelly
Claire Pengelly7391456
 
David Ball - Hulamin
David Ball - HulaminDavid Ball - Hulamin
David Ball - Hulamin7391456
 
Dr Mathias Scluep Presentation
Dr Mathias Scluep PresentationDr Mathias Scluep Presentation
Dr Mathias Scluep Presentation7391456
 
Nydia Suppen
Nydia SuppenNydia Suppen
Nydia Suppen7391456
 
Helen Davies
Helen DaviesHelen Davies
Helen Davies7391456
 
Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...
Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...
Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...7391456
 
Marten Jansen van Rensburg
Marten Jansen van RensburgMarten Jansen van Rensburg
Marten Jansen van Rensburg7391456
 
Linda Godfrey - Circular Economy NCPC-SA
Linda Godfrey - Circular Economy NCPC-SALinda Godfrey - Circular Economy NCPC-SA
Linda Godfrey - Circular Economy NCPC-SA7391456
 
Henry Nuwarinda - NCPC-SA
Henry Nuwarinda - NCPC-SAHenry Nuwarinda - NCPC-SA
Henry Nuwarinda - NCPC-SA7391456
 
Eco Match - MCPC Conference- Craig
Eco Match - MCPC Conference- CraigEco Match - MCPC Conference- Craig
Eco Match - MCPC Conference- Craig7391456
 

More from 7391456 (20)

Proudly SA
Proudly SAProudly SA
Proudly SA
 
Sanedi
SanediSanedi
Sanedi
 
Cecilia Kinuthia Njenga
Cecilia Kinuthia NjengaCecilia Kinuthia Njenga
Cecilia Kinuthia Njenga
 
WWF Klaudia NCPC - 14 September 2017
WWF Klaudia NCPC - 14 September 2017WWF Klaudia NCPC - 14 September 2017
WWF Klaudia NCPC - 14 September 2017
 
New Edition Bridget Fundikwa - Green Cape
New Edition Bridget Fundikwa - Green CapeNew Edition Bridget Fundikwa - Green Cape
New Edition Bridget Fundikwa - Green Cape
 
Henry Roman
Henry RomanHenry Roman
Henry Roman
 
Chantal Ramcharan Kotze
Chantal Ramcharan KotzeChantal Ramcharan Kotze
Chantal Ramcharan Kotze
 
Harro von Blotnitz
Harro von BlotnitzHarro von Blotnitz
Harro von Blotnitz
 
Pippa Notten
Pippa NottenPippa Notten
Pippa Notten
 
Nick Tandi
Nick TandiNick Tandi
Nick Tandi
 
Claire Pengelly
Claire PengellyClaire Pengelly
Claire Pengelly
 
David Ball - Hulamin
David Ball - HulaminDavid Ball - Hulamin
David Ball - Hulamin
 
Dr Mathias Scluep Presentation
Dr Mathias Scluep PresentationDr Mathias Scluep Presentation
Dr Mathias Scluep Presentation
 
Nydia Suppen
Nydia SuppenNydia Suppen
Nydia Suppen
 
Helen Davies
Helen DaviesHelen Davies
Helen Davies
 
Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...
Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...
Thabo - Waste Mgt Research & Incentives - Industrial Efficiency Conference (S...
 
Marten Jansen van Rensburg
Marten Jansen van RensburgMarten Jansen van Rensburg
Marten Jansen van Rensburg
 
Linda Godfrey - Circular Economy NCPC-SA
Linda Godfrey - Circular Economy NCPC-SALinda Godfrey - Circular Economy NCPC-SA
Linda Godfrey - Circular Economy NCPC-SA
 
Henry Nuwarinda - NCPC-SA
Henry Nuwarinda - NCPC-SAHenry Nuwarinda - NCPC-SA
Henry Nuwarinda - NCPC-SA
 
Eco Match - MCPC Conference- Craig
Eco Match - MCPC Conference- CraigEco Match - MCPC Conference- Craig
Eco Match - MCPC Conference- Craig
 

Recently uploaded

BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Servicesdollysharma2066
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)RaviPrajapat11
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...Cluster TWEED
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Bookingtanu pandey
 
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...Amil baba
 
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130Suhani Kapoor
 
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...Call Girls in Nagpur High Profile
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Standkumarajju5765
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abrahamssuserbb03ff
 

Recently uploaded (20)

Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCREscort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
 
Green Banking
Green Banking Green Banking
Green Banking
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
 
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort serviceyoung Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
 
E Waste Management
E Waste ManagementE Waste Management
E Waste Management
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
 
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
 
Call Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls ServicesGandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
 
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
 
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abraham
 

NCPC IE Conference 2017 P Mukoma

  • 1. 0 Dr Tobias Bischof-Niemz Chief Engineer Planning for future energy systems : A mini-IRP for the CSIR campus in Pretoria Peter Mukoma Principal Engineer, CSIR Mamahloko Senatla (Msenatla@csir.co.za) Henerica Tazvinga (HTazvinga@csir.co.za) Enose Moholisa (Emoholisa@csir.co.za) NCPC Industrial Efficiency Conference 2017 Cape Town, 15 September 2017
  • 2. 1 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results • Conclusion
  • 3. 2 Objectives of the study Background • Future energy systems will largely be based on Distributed Energy Resources (DER) – a combination of Variable Renewable Energy (VRE), storage and demand response technologies • Technology and systems innovations are required to design, build and operate such energy systems in an optimal manner • The business model of utilities will also be affected Response: Energy-Autonomous Campus Programme The CSIR has established a programme where it implements its research findings as a test bed for future energy systems • Demonstrate how to cost-efficiently design and operate an energy system based on DER • Integration of energy storage in form of batteries & hydrogen • Energy savings and demand response measures • Key outcomes: System design/operations, technology demonstration, future utility business model
  • 4. 3 Objectives of the study The objective of the study was to determine least cost generation capacity mix for CSIR’s Pretoria campus between 2016 and 2022 by considering the following energy usage scenarios: 1) Business as usual (BAU) scenario  Increasing the electrical energy consumption by 0.7% per annum until 2022 2) Energy Efficiency (EE) scenario  Decreasing the electrical energy consumption by 20% by the year 2022. 5% decrease annually starting in 2018 1. The normal load increase is 0.7%, therefore the net decrease is 4.3% 1 30.4 GWhr 6 MW 3 MW R31 m (24% Demand Charges) 2016 Energy usage Maximum Demand Base load Total cost
  • 5. 4 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results • Conclusion
  • 6. 5 Scope 1) The modelling timeframe is from 2016 – 2022 2) Includes existing power plants (single axis, dual axis and rooftop in bldg. 17), approximately 1.011 MW 3) The supply technology options considered for optimization in this iteration of the model are:  PV  Wind  Biogas and  Tshwane supply 4) Tshwane’s Megaflex tariff as Variable operating and maintenance costs for  Energy tariff increasing at 9.43% annually and peak demand charge increasing at 0.7% annually
  • 7. 6 Boundary conditions within which optimisation was based on  The modelling considers the time of use tariff from Tshwane as is in 2016 and the structure is assumed not to change until 2022. The only change is the increasing cost of electricity and peak demand charges (R/MWh and R/MW).  This means that this modelling does not consider the SSEG tariff which will be implemented once NERSA approves it.  The optimization assumes balancing of demand for the CSIR campus, excess demand is allowed but by its nature PLEXOS will minimize overcapacity, hence minimizing generation of excess energy  The excess energy is not given any value, assumed to be wasted  Tshwane is providing unlimited supply to the campus
  • 8. 7 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results • Conclusion
  • 9. 8 Study Methodology Modelling framework (PLEXOS®) LT1 techno-economic least-cost optimisation in long term horizon MT/ST2 production cost testing detailed generation dispatch in short and long term horizon Outputs For Business-As-Usual scenario:  Total generation costs  Capacity expansion (MW)  Energy share (MWh) For EE scenario:  Weekly typical generation profiles Inputs 1) 2 Demand Forecasts  BAU with 0.7% growth  EE with 4.3% reduction 2) Existing and committed plants:  Committed plants (2.011 MW)  Plant performance 3) New Supply Options:  Wind, PV rooftop, biogas, batteries  Plant costs assumptions  Plant performance 4) Tshwane Tariff: Megaflex (Time of Use)  Peak (P)  Standard (S)  Off_Peak (O) 1 LT = Long-term 2 MT/ST = Medium-term/Short-term O P S The peak demand charges are done after optimising system for energy.
  • 10. 9 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results • Conclusion
  • 11. 10 Demand Forecasts: modelled demand for both BAU and EE Scenarios 0 5 10 15 20 25 30 35 40 2006 2008 2010 2012 2014 2016 2018 2020 2022 24,6 31,7 30,4 Energy (GWh) Energy Efficiency (EE) HistoricalBusiness as usual (BAU) For BAU Scenario, energy consumptions increases by 0.7% annually starting in 2017 For EE Scenario, energy consumptions increases by 0.7% and also decreases by 5% starting in 2018. resulting in overall annual decrease of 4.3%. The difference between BAU scenario and EE scenario is 7 GWh
  • 13. 12 Wind resource performance: Wind profile shows a very low load factor of (16%) 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 0,4 0,5 0,6 0,7 0,8 0,9 0,0 1,0 1,1 0,2 0,1 0,3 Normalisedwindprofile(1MW) Average weekly generationWeekly generation Unlike what the aggregation study from CSIR showed, where on average South Africa has wind load factor around 38%. The campus is one of the low wind sites with only 16% load factor. This means for every 1 MW of wind installed, only 0.16 MW is useful to generate power.
  • 14. 13 Typical weekly generation profile of a single tracking system in Pretoria campus The average capacity factor for single tracking system is 21%. The average capacity factor for dual axis tracking system 31%. The average capacity factor for rooftop PV is 17%.
  • 15. 15 Time of use tariff in a typical week in winter and summer of 2016 and 2022 0 2 4 6 8 10 12 14 16 18 20 22 24 0,5 1,5 2,0 2,5 0,0 1,0 3,0 0,63 Hours 1,02 0,44 Tariff(R/kWh) 0 2 4 6 8 10 12 14 16 18 20 22 24 3,0 2,5 2,0 1,5 1,0 0,5 0,0 Hours 0,95 0,52 2,78 Tariff(R/kWh) SundaySaturdayWeekday Summer 2016 Winter 2016 0 2 4 6 8 10 12 14 16 18 20 22 24 2 3 0 5 4 1 Hours 0,76 1,08 1,75 Tariff(R/kWh) 0 2 4 6 8 10 12 14 16 18 20 22 24 5 3 4 1 2 0 1,63 4,77 0,89 Hours Tariff(R/kWh) Weekday Saturday Sunday Summer 2022 Winter 2022 9.43%
  • 16. 17 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results • Conclusion
  • 17. 18 Results presentation format As-is capacity case assumes a case where the CSIR is not doing any new installations of supply options. In this case, the analysis is interested in the annual cost and the net present value of the total system from 2016 to 2022. Capacity case 1:  As-is Demand scenarios  BAU  EE Capacity case 2:  Optimized Demand scenarios  BAU  EE The Optimized case assumes that there are some new investments allowed in the supply side and then the analysis is interested in the capacity to be installed (MW), the total annual energy cost and the net present value of the total system from 2016 to 2022 250 203 558 558 250 558 2016 1.011 2015 203 1.000 2.011 2017/8 Single axis tracker Dual axis tracker Rooftop PV Rooftop 2 + 2017/8 CommittedandBuilt 2,011 Any new least cost build options
  • 18. 19 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results  As – is capacity case  Optimized capacity case • Conclusion
  • 19. 20 As-is under BAU demand scenario 20 60 50 40 30 0 10 2022 57 47 3 7 2021 51 41 3 7 2020 46 36 3 7 2019 41 31 3 6 2018 37 27 3 6 2017 34 25 2 7 2016 31 23 Total cost (R million) 1 7 TshwanePVPeak demand cost Tshwane energy tariff increases from R23 million to R47 million by 2022 if CSIR decides to install only 2.011 MW of PV (as the system is) The peak demand charge costs, decreases by R1 million in 2018, when the 1 MW rooftop PV is introduced into the system and starts to increase by R1 million in 2020, due to increase peak demand charges The cost of generating electricity using PV increases from R1 million in 2016 to R3 million in 2022 The total system cost (bill) increases from R31 million in 2016 to R57 million in 2022.
  • 20. 21 As-is under EE demand growth scenario 25 20 15 10 5 0 30 45 40 35 2022 43 35 3 5 2021 41 32 3 5 2020 39 30 3 5 2019 35 26 3 6 2017 34 25 2 7 36 31 23 1 7 28 3 6 Total cost (R million) 20182016 TshwanePeak demand cost PV The peak demand charge costs, decreases by R1 million in 2018, when the 1 MW rooftop PV is introduced into the system and starts to increase by R1 million in 2020, due to increase peak demand charges
  • 21. 24 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results  As – is capacity case  Optimized capacity case • Conclusion
  • 22. 25 BAU demand scenario new least cost capacity 2 2 2 2 2 4 4 4 2 1 1 0 1 2 3 4 5 6 7 20172016 2022 6 2021 6 2020 6 2018 2019 4 Installedcapacity(MW) New PV Commited/Approved
  • 23. 26 EE demand scenario new least cost capacity 2 2 2 2 2 3 3 3 2 1 1 4,0 5,5 5,0 4,5 1,5 3,5 3,0 2,5 2,0 1,0 0,5 0,0 Installedcapacity(MW) 20172016 2019 4 5 2020 5 5 20222018 2021 Commited/Approved New PV
  • 24. 27 Optimised BAU demand scenario 40 35 30 25 50 20 45 15 10 5 0 3 2017 34 25 2 7 2016 31 23 1 7 Total cost (R million) 6 2018 5 37 27 2022 50 36 8 6 2021 45 31 8 5 2020 40 27 8 5 2019 38 27 6 PV TshwanePeak demand cost Under the optimized capacity case, the total system cost increases from R31 million in 2016 to R50 million in 2022 PV generation cost increases from R1 million in 2016 to R8 million in 2022. This is due to increased capacity equalling 6 MW by 2022.
  • 25. 28 Optimized EE demand scenario 25 5 30 0 35 10 20 50 15 45 40 2022 6 10 2 4 8 Total cost (R million) 2021 4 7 27 48 45 25 7 4 2020 41 23 7 4 2019 39 24 6 5 2018 37 26 3 6 2017 34 25 2 7 2016 31 23 1 7 EE cost PV Tshwane Peak demand cost Under the optimized capacity case, the total system cost increases from R31 million in 2016 to R48 million in 2022 In comparison to the BAU demand scenario, the EE optimized case is cheaper than the BAU optimized by R2 million (This R50 – R48)
  • 26. 29 0 1 2 3 4 5 6 7 1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121 126 131 136 141 146 151 156 161 166 Demand(MW) 2016 PV Supply Tshwane Demand Monday Tuesda Wednesday Thursday Friday Saturday Sunday Typical generation in a week in 2016 with only 558 kWp of dual axis Hours
  • 29. 32 Total discounted system cost over the study period 300 250 200 150 100 50 0 Total cost (R ) Optimized BAU scenario 274 196 37 41 As-is BAU scenario 295 230 19 46 As-is EE scenario 258 198 19 41 242 172 33 Optimized EE scenario 37 Pead demand cost PV Tshwane If the CSIR decides not to investment in power plants any further and does not invest in EE measures, the organization will pay a total amount of R295 million between 2016 and 2022. If it decides not to invest, but improve the energy system by implement EE measures, CSIR will pay R258 million (excluding DSM investment costs). Therefore its economic to install an additional 3 MW and 4 MW in both the cases where demand is decreasing and increasing. By investing in PV, the CSIR will respectively save between R16 and R21 million for the cases where efficiency measures are implemented and when efficiency measures are not implemented
  • 30. 33 Agenda • Objectives of the study • Scope and boundary conditions • Methodology • Input data and assumptions • Results • Conclusion
  • 31. 34 Conclusions and way forward  Leaving the campus energy consumption as it is today will be costly for the CSIR in the next 5 years  The least cost additional new generation capacity to install in the campus is 4 MW for Business as usual scenario  The least cost additional new generation capacity to install in the campus is 3 MW for Energy Efficiency scenario  The Optimised EE scenario is the most economic option saving R53m against BAU  Biogas and wind are not economic during the modelled timeframe  Energy audits to continue to identify and implement Energy Efficiency and Demand Response measures
  • 32. 51 Thank you Re a leboga Siyathokoza Enkosi Siyabonga Re a leboha Ro livhuha Ha Khensa Dankie Note: “Thank you” in all official languages of the Republic of South Africa

Editor's Notes

  1. The actual LCOE for single tracking system is R1.28/kWh assuming 30 year lifetime.
  2. These are the actual costs and are not the same with the costs modelled in the mini IRP
  3. The tariff is assumed to grow by 9.43% annually from 2016 to 2022.
  4. In case there is a need to defend the high assumed tariff growth rate of 9.43%, you can show this slide.
  5. Starting in 2018, the average tariff from Tshwane starts to be higher than the cost of producing power with PV
  6. Although the wind LCOE is lower than Tshwane, it is available mostly during off-peak periods when Tshwane electricity is cheaper than electricity from wind as shown in slide 20