SlideShare a Scribd company logo
1 of 61
Download to read offline
Dr Tobias Bischof-Niemz
Chief Engineer
Electricity Scenarios for South Africa
Presentation to the Portfolio Committee on Energy
CSIR
Cape Town, 21 February 2017
Pre-submission to the PC on Energy on 14 February 2017
2
CSIR delegation
Dr Rachel Chikwamba Group Executive: Strategic Alliances and Communication
Dr Tobias Bischof-Niemz Manager: Energy Centre
Crescent Mushwana Research Group Leader: Energy Systems
Jarrad Wright Principal Engineer: Energy Planning
Joanne Calitz Senior Engineer: Energy Planning
Mamahloko Senatla Researcher: Energy Planning
Tendani Tsedu Group Manager: Communications
Azeza Fredericks Parliamentary Liaison
3
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
IRP Results and Least-cost Scenario
Summary
4
World:
In 2016, 124 GW of new wind and solar PV capacity installed globally
4
4 0
46
39
7
2008
33
2000
7
0
2001
7
7
51
40
2013
73
35
2011
71
41
30
2010
9
8
1
2002
8
120
63
57
2014
91
38
2012
76
45
31
Total South African
power system
(approx. 45 GW)
2016
9
8
1
2003 2005
13
12
1
2004
0
7
2007
22
20
124
54
70
2015
27
3
2006
17
15
2
56
39
17
2009
Wind
Solar PV
Sources: GWEC; EPIA; BNEF; CSIR analysis
Global annual new capacity in GW/yr
This is all very new: Roughly 80% of the globally existing
solar PV capacity was installed during the last five years
5
World:
Significant cost reductions materialised in the last 5-8 years
100%
27
7
2003
33
2007
22
20
3
12
17
15
2
9
8
2006
1
2005
1
2004
13
65%
0
120
46
70
7
Total South African
power system
(approx. 45 GW)
3156
30
2016
63
2015
51
35
91
45
76
2013
40
39 41
71
2012
38
73
57
20142009
22%
124
54
2010
39
17
20112008
4
0
2002
7
2000
7
0
7
2001
18
9
4
8
Wind
Solar PV costSolar PV
Wind cost
Sources: IEA; GWEC; EPIA; BNEF; CSIR analysis
Subsidies Cost competitive
Global annual new capacity in GW/yr
6
560
1 075
1 460
210
960
965
1 474
257
1 520
2013
3 134
+520
+1 094
467
200
2015
2 040
2014
+1 053
20202019201820172016
Wind
Solar PV
CSP
Supply
Sources
Notes: RSA = Republic of South Africa. Solar PV capacity = capacity at point of common coupling. Wind includes Eskom’s Sere wind farm (100 MW)
Sources: Eskom; DoE IPP Office
South Africa:
From 2013 to 2016, 3.1 GW of wind, solar PV and CSP commissioned
Capacity
online in MW
(end of year)
7
2.2
1.1
1.1
2013
0.1
3.7
4.7
2.5
2.2
2014
2.6
0.5
6.9
202020192018201720162015
0.01 0.05
Wind
Solar PV
CSP
Notes: Wind includes Eskom’s Sere wind farm (100 MW)
Sources: Eskom; DoE IPP Office
Annual energy
produced in TWh
South Africa:
In 2016, almost 7 TWh electricity produced from wind, solar PV & CSP
Supply
Sources
8
2016: Wind, solar PV and CSP supplied 3% of the total RSA system load
Actuals captured in wholesale market for Jan-Dec 2016 (i.e. without self-consumption of embedded plants)
CSP
Annual
electricity
in TWh
0.5 (0.2%) 238.2
Residual Load
231.3
System Load
(domestic and
export load)
Solar PV
2.6 (1.1%)
Wind
3.7 (1.6%)
Notes: Wind includes Eskom’s Sere wind farm (100 MW)
Sources: Eskom; DoE IPP Office
9
Significant reductions in actual tariffs …
Actual tariffs: new wind/solar PV 40% cheaper than new coal in RSA
Results of Department of Energy’s RE IPP Procurement Programme (REIPPPP) and Coal IPP Proc. Programme
0.62
0.87
3.65
0.620.69
0.87
1.19
1.51
0
1
2
3
4
5
-83%
-59%
Nov
2015
Aug
2014
Aug
2013
1.17
Mar
2012
2.18
Nov
2011
Wind
Solar PV
Notes: Exchange rate of 14 USD/ZAR assumed Sources: http://www.energy.gov.za/files/renewable-energy-status-report/Market-Overview-and-Current-Levels-of-Renewable-Energy-
Deployment-NERSA.pdf; http://www.saippa.org.za/Portals/24/Documents/2016/Coal%20IPP%20factsheet.pdf; http://www.ee.co.za/wp-
content/uploads/2016/10/New_Power_Generators_RSA-CSIR-14Oct2016.pdf; StatsSA on CPI; CSIR analysis
1.03
0.620.62
-40%
Baseload
Coal IPP
Wind IPPSolar PV IPP
… have made new solar PV & wind power 40%
cheaper than new coal in South Africa today
Actual average tariffs
in R/kWh (Apr-2016-R)
Actual average tariffs
in R/kWh (Apr-2016-R)
12
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
IRP Results and Least-cost Scenario
Summary
13
Integrated Resource Plan (IRP) aims for optimal electricity mix for RSA
In-principle process of IRP planning and implementation
IRP Model
(PLEXOS)
(techno-economical
least-cost optimisation)
Output
• Capacity exp. plan
• After policy
adjustment: “IRP”
Planning /
simulation
world
Actuals /
real world
Procurement
(competitive tender
e.g. REIPPPP, coal IPPPP)
Inputs
• Ministerial
Determinations based
on IRP capacities
Inputs
• Demand forecast
• Technology costs
assumptions
• CO2 limits
• Etc.
Outcomes
• Preferred bidders
• MW allocation
• Technology costs
actuals (Ø Tariffs)
Sources: CSIR analysis
Installed capacity
80
100
60
40
20
0
4.8
9.2
1.2
8.4
2025202020152010
42.2
35.9
2.4
1.8
2.1
Total installed
net capacity in GW
Solar PV
2030
85.7
41.1
2.4
7.3
9.6
+1.8
Coal
Gas
Peaking
Nuclear
Hydro
Wind
CSP
14
IRP process as described in the Department of Energy’s Draft IRP 2016
document: least-cost Base Case is derived from technical planning facts
Least Cost
Base Case
Scenario 2
Scenario 1
Scenario 3
Case Cost
Base Case Base
Scenario 1 Base + Rxx bn/yr
Scenario 2 Base + Ryy bn/yr
Scenario 3 Base + Rzz bn/yr
… …
Constraint:
RE limits
Constraint:
Forcing in
of nuclear,
CSP, biogas,
hydro, others
Constraint:
Advanced CO2
cap decline
1) Public consultation
on costed scenarios
2) Policy adjustment
of Base Case
3) Final IRP
Planning
Facts
Sources: based on Department of Energy’s Draft IRP 2016, page 7; http://www.energy.gov.za/IRP/2016/Draft-IRP-2016-Assumptions-Base-Case-and-Observations-Revision1.pdf
15
The CSIR has embarked on power-system analyses to determine the
least-cost expansion path for the South African electricity system
The Integrated Resource Plan (IRP) is the expansion plan for the South African power system until 2050
• Starting point of the IRP Base Case: pure techno-economic analysis to determine least-cost way to supply electricity
• Later process steps: least-cost mix can be policy adjusted to cater for aspects not captured in techno-economic model
Draft IRP 2016 Base Case entails a limitation: Amount of wind and solar PV capacity that the model is allowed to build per
year is limited, which is neither technically nor economically justified/explained (no techno-economical reason provided)
The CSIR is therefore conducting a study to determine the Least Cost electricity mix in RSA until 2050
• Majority of assumptions kept exactly as per the Draft IRP 2016 Base Case
• First and most important deviation from IRP 2016: no new-build limits on renewables (wind/solar PV)
• Second (smaller) deviation: costing for solar PV and wind until 2030 aligned with latest IPP tariff results
• Scope of the CSIR study: purely techno-economical optimisation of the costs directly incurred in the power system
Two scenarios from the Draft IRP 2016 are compared with the Least Cost case
• “Draft IRP 2016 Base Case” – new coal, new nuclear
• “Draft IRP 2016 Carbon Budget” – significant new nuclear
• “Least Cost” – least-cost without constraints
An hourly capacity expansion and dispatch model (incl. unit commitment) using PLEXOS
is run for all scenarios to test for technical adequacy  same software platform as by Eskom/DoE for the IRPSources: CSIR analysis
16
Co-optimisation of long-term investment & operational
decisions in hourly time resolution from today to 2050
• What mix to build?
• How to operate the mix once built?
• Objective function: least cost, subject to an
adequate (i.e. reliable) power system
Key technical limitations of power generators covered
• Maximum ramp rates (% of installed capacity/h)
• Minimum operating levels (% of installed capacity)
• Minimum up & down times (h btw start/stop)
• Start-up and shut-down profiles
CSIR uses an industry standard software package for expansion
planning of the power system – same package as used by DoE/Eskom
Costs covered in the model include
• All capacity-related costs of all power generators
‒ CAPEX of new power plants (R/kW)
‒ Fixed Operation and Maintenance (FOM)
cost (R/kW/yr)
• All energy-related costs of all power generators
‒ Variable Operation and Maintenance (VOM)
cost (R/kWh)
‒ Fuel cost (R/GJ)
• Efficiency (heat rate) losses due to more flexible
operation
• Reserves provision (included in capacity costs)
Costs not covered in the model currently used are
• Any grid-related costs (note: transmission-level
grid costs typically ~10-15% of generation costs)
• Costs related to add. system services (e.g. inertia
requirements, black-start and reactive power)
Commercial software used by DoE & CSIR … … covers all key cost drivers of a power system
Sources: CSIR analysis
17
CSIR team has significant expertise from power system planning,
system operation and grid perspective
Dr Tobias Bischof-Niemz
• Head of the CSIR Energy Centre
• Member of the Ministerial Advisory Council
on Energy (MACE)
• Member of IRP2010/2013 team at Eskom,
energy planning in Europe for large utilities
Jarrad Wright
• Principal Engineer: Energy Planning
(CSIR Energy Centre)
• Commissioner: National Planning
Commission (NPC)
• Former Africa Manager of PLEXOS
Robbie van Heerden
• Senior Specialist: Energy Systems
(CSIR Energy Centre)
• Former General Manager and long-time
head of System Operations at Eskom
Crescent Mushwana
• Research Group Leader: Energy Systems
(CSIR Energy Centre)
• Former Chief Engineer at Eskom strategic
transmission grid planning
Mamahloko Senatla
• Researcher: Energy Planning
(CSIR Energy Centre)
• Previously with the Energy Research
Centre at University of Cape Town
Joanne Calitz
• Senior Engineer: Energy Planning
(CSIR Energy Centre)
• Previously with Eskom Energy Planning
• Medium-Term Outlook and IRP for RSA
18
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
IRP Results and Least-cost Scenario
Summary
19
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
• Cost inputs for solar PV and wind
• Limitations on build-out rates for solar PV and wind
IRP Results and Least-cost Scenario
Summary
22
IRP 2010 forecasted steep cost decline for solar PV from 2010 to 2030
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
Assumptions: IRP 2010 - low
Assumptions: IRP 2010 - high
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
23
Actual solar PV tariffs quickly moved below IRP 2010 cost assumptions
0.62
3.65
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.91
1.17
2.18
Actuals: REIPPPP (BW1-4Exp)
Assumptions: IRP 2010 - low
Assumptions: IRP 2010 - high
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
∑ = 2.8 GW
BW1  BW 4 (Expedited)
24
IRP 2016 increases cost assumptions for solar PV compared to IRP 2010
0.62
3.65
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.91
1.17
2.18
Actuals: REIPPPP (BW1-4Exp)
Assumptions: IRP 2016 - low
Assumptions: IRP 2016 - high
Assumptions: IRP 2010 - low
Assumptions: IRP 2010 - high
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
∑ = 2.8 GW
BW1  BW 4 (Expedited)
25
IRP 2010 forecasted small cost decline for wind from 2010 to 2030
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
Assumptions: IRP 2010
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
26
Actual wind tariffs quickly moved below IRP 2010 assumptions
0.62
0.69
1.19
1.52
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.87
Assumptions: IRP 2010
Actuals: REIPPPP (BW1-4Exp)
∑ = 4.0 GW
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
BW1  BW 4 (Expedited)
27
IRP 2016 increases cost assumptions for wind compared to IRP 2010
0.62
0.69
1.19
1.52
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.87
Assumptions: IRP 2010
Actuals: REIPPPP (BW1-4Exp)
Assumptions: IRP 2016 - low
Assumptions: IRP 2016 - high
∑ = 4.0 GW
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
BW1  BW 4 (Expedited)
29
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
• Cost inputs for solar PV and wind
• Limitations on build-out rates for solar PV and wind
IRP Results and Least-cost Scenario
Summary
30
Draft IRP 2016 limits the annual build-out rates for solar PV and wind
The imposed new-build limits for solar PV and wind mean that the IRP model is not allowed in any given
year to add more solar PV and wind capacity to the system than these limits
No such limits are applied for any other technology. No techno-economical reason/justification is provided
for these limits. No explanation given why the limits are constant until 2050 while the power system grows
Year System Peak
Load in MW (as
per Draft IRP)
New-build limit
Solar PV in MW/yr
(as per Draft IRP)
Relative new-build
limit Solar PV
(derived from IRP)
New-build limit Wind
in MW/yr
(as per Draft IRP)
Relative new-build
limit Wind
(derived from IRP)
2020 44 916 1 000 2.2% 1 600 3.6%
2025 51 015 1 000 2.0% 1 600 3.1%
2030 57 274 1 000 1.7% 1 600 2.8%
2035 64 169 1 000 1.6% 1 600 2.5%
2040 70 777 1 000 1.4% 1 600 2.3%
2045 78 263 1 000 1.3% 1 600 2.0%
2050 85 804 1 000 1.2% 1 600 1.9%
Note: Relative new-build limit = New-build limit / system peak load
Sources: IRP 2016 Draft; CSIR analysis
31
Today: Both leading and follower countries are installing more new
solar PV capacity per year than South Africa’s IRP limits for 2030/2050
2%
3%
4%
10%
9%9%
5%
2%
4%
2%
4%
1% 1%
1%
3%
7%
4%
1%
0%
6%
3%
3%
3%
2%
1%
0%0%
7%
6%
4%
1%
1%
1%0%0%
2%
2%2%
1%
0%
0%0%0%
1%
1%
1%
0%
0%0%0% 0%
2%
2007
3%
0%
2014
0%
3%
0%
2008
0%
1%
0%
2013
2%
0%
2012
2%
1%
2011
1%
17%
3%
2010
0%
1%
2009
2050 (1.2%)
2030 (1.7%)
2015
India
South Africa
China
Japan
Australia
UK
Italy
Spain
GermanyAnnual new solar PV
capacity relative to
system peak load
RSA’s IRP relative
new-build limit
decreases
over time
Leader
Follower
Follower
2nd wave
Sources: SolarPowerEurope; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis
RSA new-build limits
in 2030 and 2050
32
Today: Both leading and follower countries are installing more new
wind capacity per year than South Africa’s IRP limits for 2030/2050
7%
6%
4%
3%
2%
2%
2%
2%2%
3%
6%
8%
3%3%
6%
3%
4%
5%5%
7%
3%
4%
6%
5%
5%
8%
4%
4%
3%
3%
4%
3%
3%
2%
2%
2%
1%
2%2%
2%
2%
5%
4%
2%
2%
1%
1%0%
0%0%
0%
3%
1%
2%
20092008
2%
0%
2014
1%
2011
1%
0%
2012
1%
0%
2013 2016
2050 (1.9%)
2030 (2.8%)
2015
1%
2%
2010
1%
2007
1%
1%
2006
0%
0%
2%
Brazil
South Africa
India
China
Ireland
Spain
Germany
RSA’s IRP relative
new-build limit
decreases
over time
Leader
RSA new-build limits
in 2030 and 2050
Sources: GWEC; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis
Follower
Annual new wind
capacity relative to
system peak load
33
Solar PV penetration in leading countries today is 2.5 times that of
South Africa’s Draft IRP 2016 Base Case for the year 2050
0%
10%
20%
30%
40%
50%
60%
70%
2005 2010 2015 2020 2025 2030 2035 2040 2045 2050
TotalsolarPVcapacity
relativetosystempeakload
Year
Spain
UK
Italy
Japan
Germany
Australia
China
South Africa
India
South Africa IRP 2016 Base Case
Sources: SolarPowerEurope; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis
Leader
Follower
Follower
2nd wave
34
Wind penetration in leading countries today is 1.7-1.8 times that of
South Africa’s Draft IRP 2016 Base Case for the year 2050
0%
10%
20%
30%
40%
50%
60%
70%
2005 2010 2015 2020 2025 2030 2035 2040 2045 2050
Totalwindcapacity
relativetosystempeakload
Year
Spain
Germany
Ireland
Brazil
India
China
South Africa IRP 2016 Base Case
South Africa
Sources: GWEC; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis
Leader
Follower
35
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
IRP Results and Least-cost Scenario
Summary
36
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
IRP Results and Least-cost Scenario
• Input Assumptions
• Results
Summary
37
550
500
450
400
350
300
250
200
150
100
50
0
2020 2030 2040 2050
Electricity
in TWh/yr
2016
522
428
344
280
244
Input as per IRP 2016: Demand is forecasted to double by 2050
Forecasted demand for the South African electricity system from 2016 to 2050
Sources: DoE (IRP 2016); Eskom MTSAO 2016-2021; StatsSA; World Bank; CSIR analysis
Note: by 2050 the electricity
demand per capita would still be
less than that of Australia today
Demand
38
550
500
0
200
150
100
50
400
300
250
350
450
2016 2040
82
2030
174
259
Electricity
in TWh/yr
20502020
Input as per IRP 2016: Decommissioning schedule for existing plants
Decommissioning schedule for the South African electricity system from 2016 to 2050
Solar PV
CSP
Wind
Other
Peaking
Gas (CCGT)
Hydro+PS
Nuclear
Coal
Decommissioning of
Eskom’s coal fleet
All power plants considered for
“existing fleet” that are either:
1) Existing in 2016
2) Under construction
3) Procured (preferred bidder)
Demand
Sources: DoE (IRP 2016); Eskom MTSAO 2016-2021; StatsSA; World Bank; CSIR analysis
Existing supply
39
Demand grows, existing fleet phases out – gap needs to be filled
Forecasted supply and demand balance for the South African electricity system from 2016 to 2050
350
450
200
250
300
400
500
550
0
50
100
150
428
254
522
2040
439
2030
Electricity
in TWh/yr
344
2016
84
2020 2050
Other
Coal
Peaking
Gas (CCGT)
Hydro+PS
Nuclear
CSP
Solar PV
Wind
Supply gap
Decommissioning of
Eskom’s coal fleet
The IRP model fills the supply
gap in the least-cost manner,
subject to any constraints
imposed on the model
Demand
Note: All power plants considered for “existing fleet” that are either Existing in 2016, Under construction, or Procured (preferred bidder)
Sources: DoE (IRP 2016); Eskom MTSAO 2016-2021; StatsSA; World Bank; CSIR analysis
41
0.620.62
Gas (OCGT)
3.69
Diesel (OCGT)
2.89
Mid-merit CoalGas (CCGT)
1.41
Nuclear
1.41
1.09
Baseload
Coal (PF)
1.00
WindSolar PV
Variable
(Fuel)
Fixed
(Capital,
O&M)
Inputs as per IRP 2016:
Key resulting LCOE from cost assumptions for new supply technologies
50%90% 50% 10%Assumed capacity factor2  10%
Lifetime cost
per energy unit1
(LCOE) in R/kWh
(Apr-2016-R)
1 Lifetime cost per energy unit is only presented for brevity. The model inherently includes the specific cost structures of each technology i.e. capex, Fixed O&M, variable O&M, fuel costs etc.
2 Changing full-load hours for new-build options drastically changes the fixed cost components per kWh (lower full-load hours  higher capital costs and fixed O&M costs per kWh);
Assumptions: Average efficiency for CCGT = 55%, OCGT = 35%; nuclear = 33%; IRP costs from Jan-2012 escalated to May-2016 with CPI; assumed EPC CAPEX inflated by 10% to convert EPC/LCOE
into tariff; Sources: IRP 2013 Update; Doe IPP Office; StatsSA for CPI; Eskom financial reports for coal/diesel fuel cost; EE Publishers for Medupi/Kusile; Rosatom for nuclear capex; CSIR analysis
82%
Same assumptions used
as per IRP 2016
0 0 1 000 0 1 000400 600 600
CO2 in kg/MWh
43
IRP 2016 increases cost assumptions for solar PV compared to IRP 2010
0.62
3.65
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.91
1.17
2.18
Actuals: REIPPPP (BW1-4Exp)
Assumptions: IRP 2016 - low
Assumptions: IRP 2016 - high
Assumptions: IRP2010 - low
Assumptions: IRP2010 - high
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
∑ = 2.8 GW
BW1  BW 4 (Expedited)
44
CSIR study cost input assumptions for solar PV:
Future cost assumptions for solar PV aligned with IRP 2010
0.490.520.62
3.65
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
0.91
2.18
1.17
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.56
Assumptions: IRP 2016 - high
Assumptions: IRP 2016 - low
Assumptions: IRP2010 - low
Actuals: REIPPPP (BW1-4Exp)
Assumptions: IRP2010 - high
Assumptions for this study
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
∑ = 2.8 GW
BW1  BW 4 (Expedited)
45
IRP 2016 increases cost assumptions for wind compared to IRP 2010
0.62
0.69
1.19
1.52
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.87
Assumptions: IRP2010
Actuals: REIPPPP (BW1-4Exp)
Assumptions: IRP 2016 - low
Assumptions: IRP 2016 - high
∑ = 4.0 GW
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
BW1  BW 4 (Expedited)
46
CSIR study cost input assumptions for wind:
Future cost assumptions for wind aligned with results of Bid Window 4
0.62
0.62
0.620.62
0.69
1.19
1.52
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
0.87
Assumptions: IRP2010
Actuals: REIPPPP (BW1-4Exp)
Assumptions for this study
Assumptions: IRP 2016 - low
Assumptions: IRP 2016 - high
∑ = 4.0 GW
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
BW1  BW 4 (Expedited)
47
CSIR study cost input assumptions for CSP:
Today’s latest tariff as starting point, same cost decline as per IRP 2010
1.201.201.20
3.55
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
Tariff in R/kWh
(Apr-2016-Rand)
Year
2.02
2.90
3.11
3.32
Assumptions: IRP2010 - high
Actuals: REIPPPP (BW1-4Exp)
Assumptions: IRP2010 - low
Assumptions for this study
Assumptions: IRP2016 - high
Assumptions: IRP2016 - low
For bid window 3, 3.5 and 4 Exp,
weighted average tariff of base
and peak tariff calculated on the
assumption of 64%/36%
base/peak tariff utilisation ratio
Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013;
BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
BW1  BW 4 (Expedited)
48
200
250
0
50
100
150
200
250
300
2010 2015 2020 2025 2030 2035 2040 2045 2050
CO2 Emissions Cap
(electricity sector)
[Mt/yr]
275275
CO2 emissions constrained by RSA’s Peak-Plateau-Decline objective
PPD that constrains CO2 emission from electricity sector
PPD = Peak Plateau Decline
Sources: DoE (IRP 2010-2030 Update); StatsSA; CSIR analysis
49
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
IRP Results and Least-cost Scenario
• Input Assumptions
• Results
Summary
50
Draft IRP 2016
Base Case
Overview of scenarios available for comparison
Scenario
Difference to
Draft IRP 2016 Base CaseSource
Draft IRP 2016
Carbon Budget
Draft IRP 2016
“Unconstrained
Base Case”
Least Cost
Department of Energy
Draft IRP 2016 as of November 2016
Department of Energy
Draft IRP 2016 as of November 2016
Department of Energy
Scenario run by DoE/Eskom as per
request of the Ministerial Advisory
Council on Energy (MACE)
CSIR
Draft Least Cost as of February 2017
N/A
Tighter carbon reduction targets
No constraints on solar PV and wind
• No constraints on solar PV/wind
• Solar PV, wind and CSP costing
aligned with latest IPP results
• Demand response by 2050 in
residential warm water provision
51
Common reporting layout applied to all scenarios by DoE and by CSIR
Determine total operational capacity per year
• Add existing fleet & its decommissioning schedule
• Decommission new power plants at the end of
their economic life (wind = 20, solar PV = 25 years)
Determine energy balances with typical load factors for
different technologies and calibrate with IRP numbers
… are analysed with respect to total installed
capacity (GW) and energy balance (TWh/yr)
Scenarios of the Draft IRP 2016 show the annual
new installed capacity per year per technology
Sources: Draft IRP 2016, http://www.energy.gov.za/IRP/irp-presentaions/IRP-Update-Presentation-22-Nov-2016.pdf; CSIR analysis
0
300
550
500
450
400
350
250
200
150
100
50
22
2030
344
235
2050
23
36
13
2016
248
13
207
15
17
523
159
(30%)
165
(32%)
33
(6%)
39
(7%)
93
(18%)
28
(5%)
2040
33
431
229
35
34
66
Total electricity
produced in TWh/yr
Coal
Nuclear
Hydro+PS
Gas (CCGT)
Peaking
Wind
CSP
Solar PV
IRP scenarios as published by the DoE …
52
Draft IRP 2016 Base Case is a mix of roughly 1/3 coal, nuclear, RE each
Draft IRP 2016 Base Case
50
150
250
0
300
200
500
350
400
450
550
100
33
(6%)
165
(32%)
2040
39
(7%)
28
(5%)
93
(18%)
523
15
Total electricity
produced in TWh/yr
431
229
35
159
(30%)
34
33
66
20502030
344
235
13
23
22
13
2016
248
207
17
36
Wind
Peaking
Gas (CCGT)
Hydro+PS
Nuclear
CoalCSP
Solar PV
Sources: DoE Draft IRP 2016; CSIR analysis
As per Draft IRP 2016
More stringent
carbon limits
53
Draft IRP 2016 Carbon Budget case: 40% nuclear energy share by 2050
Draft IRP 2016 Base Case Draft IRP 2016 Carbon Budget
50
150
250
0
300
200
500
350
400
450
550
100
33
(6%)
165
(32%)
2040
39
(7%)
28
(5%)
93
(18%)
523
15
Total electricity
produced in TWh/yr
431
229
35
159
(30%)
34
33
66
20502030
344
235
13
23
22
13
2016
248
207
17
36
Wind
Peaking
Gas (CCGT)
Hydro+PS
Nuclear
CoalCSP
Solar PV
300
450
500
550
50
0
100
400
250
200
150
350
345
161
433
2030
103
44
(8%)
85
2040
33
134
109
(21%)
17
39
29
Total electricity
produced in TWh/yr
2050
15
35
(7%)
206
(39%)
63
(12%)
525
207
23
248
2016
23
63
57
63
(12%)
As per Draft IRP 2016
More stringent
carbon limits
Sources: DoE Draft IRP 2016; CSIR analysis
No RE limits, reduced wind/solar PV costing, warm water demand flexibility
54
Least Cost case is largely based on wind and solar PV
Draft IRP 2016 Base Case Least CostDraft IRP 2016 Carbon Budget
50
150
250
0
300
200
500
350
400
450
550
100
33
(6%)
165
(32%)
2040
39
(7%)
28
(5%)
93
(18%)
523
15
Total electricity
produced in TWh/yr
431
229
35
159
(30%)
34
33
66
20502030
344
235
13
23
22
13
2016
248
207
17
36
Wind
Peaking
Gas (CCGT)
Hydro+PS
Nuclear
CoalCSP
Solar PV
300
450
500
550
50
0
100
400
250
200
150
350
345
161
433
2030
103
44
(8%)
85
2040
33
134
109
(21%)
17
39
29
Total electricity
produced in TWh/yr
2050
15
35
(7%)
206
(39%)
63
(12%)
525
207
23
248
2016
23
63
57
63
(12%)
350
200
0
50
250
400
550
500
450
100
150
300
15
83
433
2040
130
(25%)
22
87
189
9
16
282
(54%)
44
(8%)
2050
49
22
15
527
15
Total electricity
produced in TWh/yr
20
(4%)
36
(7%)
346
2030
17
207
248
2016
35
212
As per Draft IRP 2016
More stringent
carbon limits
No RE limits, reduced wind/solar PV costing, warm water demand flexibility
Sources: DoE Draft IRP 2016; CSIR analysis
55
Least Cost means no new coal and no new nuclear until 2050,
instead 90 GW of wind and 70 GW of solar PV plus flexible capacities
Draft IRP 2016 Base Case Least CostDraft IRP 2016 Carbon Budget
250
200
150
100
50
0
2050
135
25
20
8
22
13
30
16
2040
111
33
5 8
17
12
21
12
2030
85
39
2 6
8
11
7
2016
51
37
5 3
Total installed
net capacity in GW
Coal
Nuclear
Hydro+PS
Gas (CCGT)
Peaking
Wind
CSP
Solar PV
250
0
200
150
100
50
Total installed
net capacity in GW
2050
149
10
26
8
33
10
36
25
2040
129
19
17
8
19
8
34
22
2030
98
34
7
8
10
20
13
2016
51
37
5 3
100
0
50
250
150
200
60
52
2030
100
31
34
2050
5
10
18
237
2016
Total installed
net capacity in GW
7
2040
178
19
25
73
5
37
2
19
22
93
51
5
37
16
3
As per Draft IRP 2016
More stringent
carbon limits
Plus 25 GW demand
response from residential
warm water provision
Note: REDZ = Renewable Energy Development Zones
Current REDZ cover 7% of South Africa‘s land mass
Sources: DoE Draft IRP 2016; CSIR analysis
No RE limits, reduced wind/solar PV costing, warm water demand flexibility
535 GW
1 782 GW
Technical
potential
in REDZ
only
56
On request by the Ministerial Advisory Council on Energy (MACE) the
DoE re-ran the IRP 2016 Base Case without constraining solar PV/wind
Source: MACE’s presentation during the IRP public consultations on 7 December 2016 in Johannesburg
Sources: http://www.energy.gov.za/IRP/irp-presentaions/Comments-on-IRP-2016-Draft-KabiSolar.pdf
57
The DoE’s “Unconstrained Base Case” is similar to the CSIR’s Least Cost
Source: MACE’s presentation during the IRP public consultations on 7 December 2016 in Johannesburg
Sources: http://www.energy.gov.za/IRP/irp-presentaions/Comments-on-IRP-2016-Draft-KabiSolar.pdf
58
Demand and
Supply in GW
110
120
90
60
70
80
30
40
50
100
0
10
20
Draft IRP 2016 Base Case:
Nuclear and coal dominate the supply mix in 2050
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Sources: CSIR analysis, based on DoE‘s Draft IRP 2016
DemandNuclear
Coal
Gas (CCGT)
Hydro
Peaking
Wind
Solar PV
Exemplary Week under Draft IRP 2016 Base Case (2050)
59
Demand and
Supply in GW
60
50
40
30
20
10
0
120
110
100
90
80
70
Draft IRP 2016 Carbon Budget:
Nuclear dominates the supply mix in 2050, gas required for balancing
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
DemandNuclear
Coal
Gas (CCGT)
Hydro
Peaking
Wind
Solar PV
Exemplary Week under Draft IRP 2016 Carbon Budget (2050)
Sources: CSIR analysis, based on DoE‘s Draft IRP 2016
60
Demand and
Supply in GW
10
50
60
80
90
70
120
110
100
30
20
0
40
Least Cost:
Solar PV and wind dominate supply mix in 2050, with excess at times
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Sources: CSIR analysis
DemandWindCurtailed solar PV and wind
Solar PV Peaking
Hydro
Gas (CCGT)
Coal
Nuclear
Exemplary Week under Least Cost (2050)
61
Total cost of power generation: Draft IRP 2016 Base Case R86 bn/year
more expensive by 2050 than Least Cost (without cost of CO2)
522
398
286
132
518
413
300
436
359
262
2010 2020 2030 2040 2050
200
0
50
250
300
350
400
150
550
450
100
500
Total cost of power
generation in bR/yr
(constant 2016 Rand)
+86
(+20%)
Draft IRP 2016 Carbon Budget
Draft IRP 2016 Base Case
Least Cost
Sources: CSIR analysis
2016
Note: Medium-term from 2016 to 2030 not in the main focus of a long-term IRP study
and therefore only indicative. Will be investigated in more detail in a separate sub-study.
62
Average tariff (without cost of CO2):
Draft IRP Base Case tariff 17 cents/kWh higher than Least Cost by 2050
1.13
1.22
1.291.25
1.17
1.13
1.06
1.13
0.83
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
2010 2020 2030 2040 2050
+0.17
(+15%)
Average tariff in R/kWh
(constant 2016 Rand)
Draft IRP 2016 Carbon Budget
Least Cost
Draft IRP 2016 Base Case
Note: Average tariff projections include 0.30 R/kWh for transmission, distribution and customer service (today‘s average cost for these items) Sources: Eskom on Tx, Dx cost; CSIR analysis
Note: Medium-term from 2016 to 2030 not in the main focus of a long-term IRP study
and therefore only indicative. Will be investigated in more detail in a separate sub-study.
2016
63
Average tariff (with cost of CO2):
Draft IRP Base Case tariff 20 cents/kWh higher than Least Cost by 2050
1.34
1.14
0.95
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
1.4
2010 2020 2030 2040 2050
+0.20
(+17%)
Average tariff in R/kWh
(constant 2016 Rand)
Least Cost
Draft IRP 2016 Carbon Budget
Draft IRP 2016 Base Case
Note: Average tariff projections include 0.30 R/kWh for transmission, distribution and customer service (today‘s average cost for these items) Sources: Eskom on Tx, Dx cost; CSIR analysis
2016
Note: Medium-term from 2016 to 2030 not in the main focus of a long-term IRP study
and therefore only indicative. Will be investigated in more detail in a separate sub-study.
64
Least Cost without renewables limits is R82-86 billion/yr cheaper by
2050 than IRP 2016 Base Case and IRP 2016 Carbon Budget case
Draft IRP 2016 Base Case Least CostDraft IRP 2016 Carbon Budget
R518 billion/yr
Ø tariff = 1.29 R/kWh
R436 billion/yr
Ø tariff = 1.13 R/kWh
100 Mt/yr 70 Mt/yr
16 bn l/yr 9 bn l/yr
R522 billion/yr
Ø tariff = 1.29 R/kWh
200 Mt/yr
38 bn l/yr
Note: Average tariff projections include 0.30 R/kWh for transmission, distribution and customer service (today‘s average cost for these items) Sources: Eskom on Tx, Dx cost; CSIR analysis
As per Draft IRP 2016
18%
32%
7%
1%
30%
5%
6%
21%
1%
12%
7%
39%
12%
8% 7%
2%
4%
1%
25% 8%
54%
~525 TWh/yr ~525 TWh/yr ~525 TWh/yr
Nuclear Hydro + Pumped Storage WindGas (CCGT) OtherCoal CSP Solar PVPeaking
65
200
220
20
0
-20
-40
160
180
140
120
100
80
60
40
Annual cost delta of
Draft IRP – Least Cost
by 2050 in bR/yr
86
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
Today (2016)
Study assumptions (2020-2050)
Relative
RE/nuclear cost
(Today:
RE = 0.62 R/kWh,
Nuclear = 1.09 R/kWh
 0.57)
Relative
RE/coal cost
(Today:
RE = 0.62 R/kWh,
Coal = 1.00 R/kWh
 0.62)
Sensitivity on cost difference: Even if RE were 50% more expensive
than assumed, Least Cost is still cheaper than Draft IRP 2016 Base Case
Sources: CSIR analysis
66
Agenda
Background
CSIR’s Approach and Project Team
Comments on IRP Assumptions
IRP Results and Least-cost Scenario
Summary
67
Summary:
A mix of solar PV, wind and flexible power generators is least cost
Solar PV, wind & flexible power generators (e.g. gas, CSP, hydro, biogas, demand res.) is the cheapest new-
build mix for the RSA power system. It is cost-optimal to aim for >70% renewable energy share by 2050
This “Least Cost” mix is > R80 billion per year cheaper by 2050 than the current Draft IRP 2016 Base Case
Additionally, Least Cost mix reduces CO2 emissions by 65% (-130 Mt/yr) over the Draft IRP 2016 Base Case
Therefore: Avoiding CO2 emissions and least-cost is not a trade-off anymore – South Africa can de-
carbonise its electricity sector at negative carbon-avoidance cost
The IRP and this analysis factor in all first-order cost drivers within the boundaries of the electricity system,
but not external costs and benefits of certain electricity mixes that occur outside of the electricity system
Deviations from the Least Cost electricity mix can be quantified to inform policy adjustments
(e.g. forcing in of certain technologies not selected by the least-cost mix like
coal, nuclear, hydro, CSP, biogas, biomass, etc.)
Note: Wind and solar PV would have to be 50% more expensive than assumed before the IRP Base Case and the Least Cost case break even
Sources: CSIR analysis
68
Thank you
Re a leboga
Siyathokoza
Enkosi
Siyabonga
Re a leboha
Ro livhuha
Ha Khensa
Dankie
Note: „Thank you“ in all official languages of the Republic of South Africa

More Related Content

What's hot

Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...IEA-ETSAP
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologiesLeonardo ENERGY
 
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...IEA-ETSAP
 
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...IEA-ETSAP
 
Network Theory Integrated Life Cycle Assessment for an Electric Power System
Network Theory Integrated Life Cycle Assessment for an Electric Power SystemNetwork Theory Integrated Life Cycle Assessment for an Electric Power System
Network Theory Integrated Life Cycle Assessment for an Electric Power SystemHeetae Kim
 
Energy Research and the Swiss Energy Strategy 2050
Energy Research and the Swiss Energy Strategy 2050Energy Research and the Swiss Energy Strategy 2050
Energy Research and the Swiss Energy Strategy 2050IEA-ETSAP
 
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...IEA-ETSAP
 
Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...
Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...
Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...Université de Liège (ULg)
 
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...IEA-ETSAP
 
Assessment of off-shore wind turbines for application in Saudi Arabia
Assessment of off-shore wind turbines for application  in Saudi Arabia Assessment of off-shore wind turbines for application  in Saudi Arabia
Assessment of off-shore wind turbines for application in Saudi Arabia IJECEIAES
 
Integration of Renewables in the Swiss Energy System
Integration of Renewables in the Swiss Energy SystemIntegration of Renewables in the Swiss Energy System
Integration of Renewables in the Swiss Energy SystemIEA-ETSAP
 
IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...
IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...
IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...IRJET Journal
 
Grid Features in the TIMES-based Japan Model
Grid Features in the TIMES-based Japan ModelGrid Features in the TIMES-based Japan Model
Grid Features in the TIMES-based Japan ModelIEA-ETSAP
 
Methodology to estimate energy savings in buildings within ETSAP-TIAM
Methodology to estimate energy savings in buildings within ETSAP-TIAMMethodology to estimate energy savings in buildings within ETSAP-TIAM
Methodology to estimate energy savings in buildings within ETSAP-TIAMIEA-ETSAP
 
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy InstituteOngoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy InstituteIEA-ETSAP
 
Economic and Environmental Analysis of Renewable Energy Systems
Economic and Environmental Analysis of Renewable Energy SystemsEconomic and Environmental Analysis of Renewable Energy Systems
Economic and Environmental Analysis of Renewable Energy Systemslenses
 
A Spatio-temporal Optimization Model for the Analysis of Future Energy System...
A Spatio-temporal Optimization Model for the Analysis of Future Energy System...A Spatio-temporal Optimization Model for the Analysis of Future Energy System...
A Spatio-temporal Optimization Model for the Analysis of Future Energy System...IEA-ETSAP
 
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...IEA-ETSAP
 
ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...
ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...
ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...Ankur Tyagi
 

What's hot (20)

L010437380
L010437380L010437380
L010437380
 
Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologies
 
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
 
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
 
Network Theory Integrated Life Cycle Assessment for an Electric Power System
Network Theory Integrated Life Cycle Assessment for an Electric Power SystemNetwork Theory Integrated Life Cycle Assessment for an Electric Power System
Network Theory Integrated Life Cycle Assessment for an Electric Power System
 
Energy Research and the Swiss Energy Strategy 2050
Energy Research and the Swiss Energy Strategy 2050Energy Research and the Swiss Energy Strategy 2050
Energy Research and the Swiss Energy Strategy 2050
 
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
 
Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...
Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...
Harnessing the Potential of Power-to-Gas Technologies. Insights from a prelim...
 
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
 
Assessment of off-shore wind turbines for application in Saudi Arabia
Assessment of off-shore wind turbines for application  in Saudi Arabia Assessment of off-shore wind turbines for application  in Saudi Arabia
Assessment of off-shore wind turbines for application in Saudi Arabia
 
Integration of Renewables in the Swiss Energy System
Integration of Renewables in the Swiss Energy SystemIntegration of Renewables in the Swiss Energy System
Integration of Renewables in the Swiss Energy System
 
IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...
IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...
IRJET-System Analysis and Optimization of Photovoltaic –Wind Hybrid System: R...
 
Grid Features in the TIMES-based Japan Model
Grid Features in the TIMES-based Japan ModelGrid Features in the TIMES-based Japan Model
Grid Features in the TIMES-based Japan Model
 
Methodology to estimate energy savings in buildings within ETSAP-TIAM
Methodology to estimate energy savings in buildings within ETSAP-TIAMMethodology to estimate energy savings in buildings within ETSAP-TIAM
Methodology to estimate energy savings in buildings within ETSAP-TIAM
 
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy InstituteOngoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
 
Economic and Environmental Analysis of Renewable Energy Systems
Economic and Environmental Analysis of Renewable Energy SystemsEconomic and Environmental Analysis of Renewable Energy Systems
Economic and Environmental Analysis of Renewable Energy Systems
 
A Spatio-temporal Optimization Model for the Analysis of Future Energy System...
A Spatio-temporal Optimization Model for the Analysis of Future Energy System...A Spatio-temporal Optimization Model for the Analysis of Future Energy System...
A Spatio-temporal Optimization Model for the Analysis of Future Energy System...
 
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
 
ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...
ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...
ESTIMATION AND COMPARISION OF COST OF COAL POWER GENERATION WITH EXTERNAL COS...
 

Viewers also liked

Инновационные модели обучения по М.В.Кларину
Инновационные модели обучения по М.В.КларинуИнновационные модели обучения по М.В.Кларину
Инновационные модели обучения по М.В.КларинуТатьяна Ганф Ganf
 
Bluetooth based home appliances control
Bluetooth based home appliances controlBluetooth based home appliances control
Bluetooth based home appliances controlPROJECTRONICS
 
Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)
Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)
Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)Bear Analytics
 
Los signos del zodiaco
Los signos del zodiacoLos signos del zodiaco
Los signos del zodiacoisabela garces
 
Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...
Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...
Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...Asters
 
Associations and home remedies
Associations and home remediesAssociations and home remedies
Associations and home remediesMarta Martín
 
Sunderbans mangrove trees losing capacity to absorb co2 study
Sunderbans mangrove trees losing capacity to absorb co2  studySunderbans mangrove trees losing capacity to absorb co2  study
Sunderbans mangrove trees losing capacity to absorb co2 studyAbhijit Mitra
 
Lição 12 os antepassados de jesus cristo
Lição 12   os antepassados de jesus cristoLição 12   os antepassados de jesus cristo
Lição 12 os antepassados de jesus cristoÉder Tomé
 

Viewers also liked (15)

Острова вечной весны
Острова вечной весныОстрова вечной весны
Острова вечной весны
 
Инновационные модели обучения по М.В.Кларину
Инновационные модели обучения по М.В.КларинуИнновационные модели обучения по М.В.Кларину
Инновационные модели обучения по М.В.Кларину
 
tecnologia e informatica
tecnologia e informaticatecnologia e informatica
tecnologia e informatica
 
Quiz about the water
Quiz about the waterQuiz about the water
Quiz about the water
 
Bluetooth based home appliances control
Bluetooth based home appliances controlBluetooth based home appliances control
Bluetooth based home appliances control
 
Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)
Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)
Accelerating Event ROI via Advanced Data Analytics (MATSO 2017 Presentation)
 
365 D
365 D365 D
365 D
 
What is Stress?
What is Stress?What is Stress?
What is Stress?
 
Análise sensorial
Análise sensorialAnálise sensorial
Análise sensorial
 
Los signos del zodiaco
Los signos del zodiacoLos signos del zodiaco
Los signos del zodiaco
 
Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...
Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...
Конкурентне право. Вертикальні обмеження. Концентрація - Правнича школа EBA-A...
 
Associations and home remedies
Associations and home remediesAssociations and home remedies
Associations and home remedies
 
Sunderbans mangrove trees losing capacity to absorb co2 study
Sunderbans mangrove trees losing capacity to absorb co2  studySunderbans mangrove trees losing capacity to absorb co2  study
Sunderbans mangrove trees losing capacity to absorb co2 study
 
Lição 12 os antepassados de jesus cristo
Lição 12   os antepassados de jesus cristoLição 12   os antepassados de jesus cristo
Lição 12 os antepassados de jesus cristo
 
Desarrollo humedal
Desarrollo humedalDesarrollo humedal
Desarrollo humedal
 

Similar to Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent

IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Implementing Agreement (IA)
 
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Leonardo ENERGY
 
Drivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketDrivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketLeonardo ENERGY
 
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...OECD Environment
 
Development of a National Energy System Model for collaborative analysis of e...
Development of a National Energy System Model for collaborative analysis of e...Development of a National Energy System Model for collaborative analysis of e...
Development of a National Energy System Model for collaborative analysis of e...IEA-ETSAP
 
Meghalaya Wind Energy
Meghalaya Wind Energy Meghalaya Wind Energy
Meghalaya Wind Energy Siraj Ahmed
 
How costs affect deployment of low carbon technologies - analysis with JRC-EU...
How costs affect deployment of low carbon technologies - analysis with JRC-EU...How costs affect deployment of low carbon technologies - analysis with JRC-EU...
How costs affect deployment of low carbon technologies - analysis with JRC-EU...IEA-ETSAP
 
Wind energy projects integration in electricity grids portugal and med tso e...
Wind energy projects integration in electricity grids  portugal and med tso e...Wind energy projects integration in electricity grids  portugal and med tso e...
Wind energy projects integration in electricity grids portugal and med tso e...RCREEE
 
Value of CSP with TES november 2014
Value of CSP with TES november 2014Value of CSP with TES november 2014
Value of CSP with TES november 2014Daniel Schwab
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyTransGrid AU
 
Bankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa caseBankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa caseLeonardo ENERGY
 
Bankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GWBankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GWLeonardo ENERGY
 
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...Global CCS Institute
 
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...Global CCS Institute
 
Show & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdf
Show & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdfShow & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdf
Show & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdfSIFOfgem
 
Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...Leonardo ENERGY
 
Building A Zero Carbon Internet
Building A Zero Carbon InternetBuilding A Zero Carbon Internet
Building A Zero Carbon InternetBill St. Arnaud
 
Global Renewable Hydrogen Potentials for the TIAM Model
Global Renewable Hydrogen Potentials for the TIAM ModelGlobal Renewable Hydrogen Potentials for the TIAM Model
Global Renewable Hydrogen Potentials for the TIAM ModelIEA-ETSAP
 

Similar to Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent (20)

IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
 
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
 
Drivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketDrivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP market
 
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
CCXG Oct 2019 Electricity sector opportunities for more ambitious NDCs - Mand...
 
Development of a National Energy System Model for collaborative analysis of e...
Development of a National Energy System Model for collaborative analysis of e...Development of a National Energy System Model for collaborative analysis of e...
Development of a National Energy System Model for collaborative analysis of e...
 
Meghalaya Wind Energy
Meghalaya Wind Energy Meghalaya Wind Energy
Meghalaya Wind Energy
 
How costs affect deployment of low carbon technologies - analysis with JRC-EU...
How costs affect deployment of low carbon technologies - analysis with JRC-EU...How costs affect deployment of low carbon technologies - analysis with JRC-EU...
How costs affect deployment of low carbon technologies - analysis with JRC-EU...
 
Wind energy projects integration in electricity grids portugal and med tso e...
Wind energy projects integration in electricity grids  portugal and med tso e...Wind energy projects integration in electricity grids  portugal and med tso e...
Wind energy projects integration in electricity grids portugal and med tso e...
 
Value of CSP with TES november 2014
Value of CSP with TES november 2014Value of CSP with TES november 2014
Value of CSP with TES november 2014
 
9th IWERN Meeting Presentation
9th IWERN Meeting Presentation9th IWERN Meeting Presentation
9th IWERN Meeting Presentation
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering Sydney
 
Bankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa caseBankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa case
 
Bankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GWBankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GW
 
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
 
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
Webinar: The cost effectiveness of natural gas combined cycle power plants wi...
 
Show & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdf
Show & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdfShow & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdf
Show & Tell - Data & Digitalisation, Weather & Predictive Analytics.pdf
 
Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...
 
VTT wind and solar innovation activities and offering, Matti Paljakka VTT
VTT wind and solar innovation activities and offering, Matti Paljakka VTTVTT wind and solar innovation activities and offering, Matti Paljakka VTT
VTT wind and solar innovation activities and offering, Matti Paljakka VTT
 
Building A Zero Carbon Internet
Building A Zero Carbon InternetBuilding A Zero Carbon Internet
Building A Zero Carbon Internet
 
Global Renewable Hydrogen Potentials for the TIAM Model
Global Renewable Hydrogen Potentials for the TIAM ModelGlobal Renewable Hydrogen Potentials for the TIAM Model
Global Renewable Hydrogen Potentials for the TIAM Model
 

Recently uploaded

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Electricity scenarios-for-rsa-csir-pc energy-21_feb2017_sent

  • 1. Dr Tobias Bischof-Niemz Chief Engineer Electricity Scenarios for South Africa Presentation to the Portfolio Committee on Energy CSIR Cape Town, 21 February 2017 Pre-submission to the PC on Energy on 14 February 2017
  • 2. 2 CSIR delegation Dr Rachel Chikwamba Group Executive: Strategic Alliances and Communication Dr Tobias Bischof-Niemz Manager: Energy Centre Crescent Mushwana Research Group Leader: Energy Systems Jarrad Wright Principal Engineer: Energy Planning Joanne Calitz Senior Engineer: Energy Planning Mamahloko Senatla Researcher: Energy Planning Tendani Tsedu Group Manager: Communications Azeza Fredericks Parliamentary Liaison
  • 3. 3 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions IRP Results and Least-cost Scenario Summary
  • 4. 4 World: In 2016, 124 GW of new wind and solar PV capacity installed globally 4 4 0 46 39 7 2008 33 2000 7 0 2001 7 7 51 40 2013 73 35 2011 71 41 30 2010 9 8 1 2002 8 120 63 57 2014 91 38 2012 76 45 31 Total South African power system (approx. 45 GW) 2016 9 8 1 2003 2005 13 12 1 2004 0 7 2007 22 20 124 54 70 2015 27 3 2006 17 15 2 56 39 17 2009 Wind Solar PV Sources: GWEC; EPIA; BNEF; CSIR analysis Global annual new capacity in GW/yr This is all very new: Roughly 80% of the globally existing solar PV capacity was installed during the last five years
  • 5. 5 World: Significant cost reductions materialised in the last 5-8 years 100% 27 7 2003 33 2007 22 20 3 12 17 15 2 9 8 2006 1 2005 1 2004 13 65% 0 120 46 70 7 Total South African power system (approx. 45 GW) 3156 30 2016 63 2015 51 35 91 45 76 2013 40 39 41 71 2012 38 73 57 20142009 22% 124 54 2010 39 17 20112008 4 0 2002 7 2000 7 0 7 2001 18 9 4 8 Wind Solar PV costSolar PV Wind cost Sources: IEA; GWEC; EPIA; BNEF; CSIR analysis Subsidies Cost competitive Global annual new capacity in GW/yr
  • 6. 6 560 1 075 1 460 210 960 965 1 474 257 1 520 2013 3 134 +520 +1 094 467 200 2015 2 040 2014 +1 053 20202019201820172016 Wind Solar PV CSP Supply Sources Notes: RSA = Republic of South Africa. Solar PV capacity = capacity at point of common coupling. Wind includes Eskom’s Sere wind farm (100 MW) Sources: Eskom; DoE IPP Office South Africa: From 2013 to 2016, 3.1 GW of wind, solar PV and CSP commissioned Capacity online in MW (end of year)
  • 7. 7 2.2 1.1 1.1 2013 0.1 3.7 4.7 2.5 2.2 2014 2.6 0.5 6.9 202020192018201720162015 0.01 0.05 Wind Solar PV CSP Notes: Wind includes Eskom’s Sere wind farm (100 MW) Sources: Eskom; DoE IPP Office Annual energy produced in TWh South Africa: In 2016, almost 7 TWh electricity produced from wind, solar PV & CSP Supply Sources
  • 8. 8 2016: Wind, solar PV and CSP supplied 3% of the total RSA system load Actuals captured in wholesale market for Jan-Dec 2016 (i.e. without self-consumption of embedded plants) CSP Annual electricity in TWh 0.5 (0.2%) 238.2 Residual Load 231.3 System Load (domestic and export load) Solar PV 2.6 (1.1%) Wind 3.7 (1.6%) Notes: Wind includes Eskom’s Sere wind farm (100 MW) Sources: Eskom; DoE IPP Office
  • 9. 9 Significant reductions in actual tariffs … Actual tariffs: new wind/solar PV 40% cheaper than new coal in RSA Results of Department of Energy’s RE IPP Procurement Programme (REIPPPP) and Coal IPP Proc. Programme 0.62 0.87 3.65 0.620.69 0.87 1.19 1.51 0 1 2 3 4 5 -83% -59% Nov 2015 Aug 2014 Aug 2013 1.17 Mar 2012 2.18 Nov 2011 Wind Solar PV Notes: Exchange rate of 14 USD/ZAR assumed Sources: http://www.energy.gov.za/files/renewable-energy-status-report/Market-Overview-and-Current-Levels-of-Renewable-Energy- Deployment-NERSA.pdf; http://www.saippa.org.za/Portals/24/Documents/2016/Coal%20IPP%20factsheet.pdf; http://www.ee.co.za/wp- content/uploads/2016/10/New_Power_Generators_RSA-CSIR-14Oct2016.pdf; StatsSA on CPI; CSIR analysis 1.03 0.620.62 -40% Baseload Coal IPP Wind IPPSolar PV IPP … have made new solar PV & wind power 40% cheaper than new coal in South Africa today Actual average tariffs in R/kWh (Apr-2016-R) Actual average tariffs in R/kWh (Apr-2016-R)
  • 10. 12 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions IRP Results and Least-cost Scenario Summary
  • 11. 13 Integrated Resource Plan (IRP) aims for optimal electricity mix for RSA In-principle process of IRP planning and implementation IRP Model (PLEXOS) (techno-economical least-cost optimisation) Output • Capacity exp. plan • After policy adjustment: “IRP” Planning / simulation world Actuals / real world Procurement (competitive tender e.g. REIPPPP, coal IPPPP) Inputs • Ministerial Determinations based on IRP capacities Inputs • Demand forecast • Technology costs assumptions • CO2 limits • Etc. Outcomes • Preferred bidders • MW allocation • Technology costs actuals (Ø Tariffs) Sources: CSIR analysis Installed capacity 80 100 60 40 20 0 4.8 9.2 1.2 8.4 2025202020152010 42.2 35.9 2.4 1.8 2.1 Total installed net capacity in GW Solar PV 2030 85.7 41.1 2.4 7.3 9.6 +1.8 Coal Gas Peaking Nuclear Hydro Wind CSP
  • 12. 14 IRP process as described in the Department of Energy’s Draft IRP 2016 document: least-cost Base Case is derived from technical planning facts Least Cost Base Case Scenario 2 Scenario 1 Scenario 3 Case Cost Base Case Base Scenario 1 Base + Rxx bn/yr Scenario 2 Base + Ryy bn/yr Scenario 3 Base + Rzz bn/yr … … Constraint: RE limits Constraint: Forcing in of nuclear, CSP, biogas, hydro, others Constraint: Advanced CO2 cap decline 1) Public consultation on costed scenarios 2) Policy adjustment of Base Case 3) Final IRP Planning Facts Sources: based on Department of Energy’s Draft IRP 2016, page 7; http://www.energy.gov.za/IRP/2016/Draft-IRP-2016-Assumptions-Base-Case-and-Observations-Revision1.pdf
  • 13. 15 The CSIR has embarked on power-system analyses to determine the least-cost expansion path for the South African electricity system The Integrated Resource Plan (IRP) is the expansion plan for the South African power system until 2050 • Starting point of the IRP Base Case: pure techno-economic analysis to determine least-cost way to supply electricity • Later process steps: least-cost mix can be policy adjusted to cater for aspects not captured in techno-economic model Draft IRP 2016 Base Case entails a limitation: Amount of wind and solar PV capacity that the model is allowed to build per year is limited, which is neither technically nor economically justified/explained (no techno-economical reason provided) The CSIR is therefore conducting a study to determine the Least Cost electricity mix in RSA until 2050 • Majority of assumptions kept exactly as per the Draft IRP 2016 Base Case • First and most important deviation from IRP 2016: no new-build limits on renewables (wind/solar PV) • Second (smaller) deviation: costing for solar PV and wind until 2030 aligned with latest IPP tariff results • Scope of the CSIR study: purely techno-economical optimisation of the costs directly incurred in the power system Two scenarios from the Draft IRP 2016 are compared with the Least Cost case • “Draft IRP 2016 Base Case” – new coal, new nuclear • “Draft IRP 2016 Carbon Budget” – significant new nuclear • “Least Cost” – least-cost without constraints An hourly capacity expansion and dispatch model (incl. unit commitment) using PLEXOS is run for all scenarios to test for technical adequacy  same software platform as by Eskom/DoE for the IRPSources: CSIR analysis
  • 14. 16 Co-optimisation of long-term investment & operational decisions in hourly time resolution from today to 2050 • What mix to build? • How to operate the mix once built? • Objective function: least cost, subject to an adequate (i.e. reliable) power system Key technical limitations of power generators covered • Maximum ramp rates (% of installed capacity/h) • Minimum operating levels (% of installed capacity) • Minimum up & down times (h btw start/stop) • Start-up and shut-down profiles CSIR uses an industry standard software package for expansion planning of the power system – same package as used by DoE/Eskom Costs covered in the model include • All capacity-related costs of all power generators ‒ CAPEX of new power plants (R/kW) ‒ Fixed Operation and Maintenance (FOM) cost (R/kW/yr) • All energy-related costs of all power generators ‒ Variable Operation and Maintenance (VOM) cost (R/kWh) ‒ Fuel cost (R/GJ) • Efficiency (heat rate) losses due to more flexible operation • Reserves provision (included in capacity costs) Costs not covered in the model currently used are • Any grid-related costs (note: transmission-level grid costs typically ~10-15% of generation costs) • Costs related to add. system services (e.g. inertia requirements, black-start and reactive power) Commercial software used by DoE & CSIR … … covers all key cost drivers of a power system Sources: CSIR analysis
  • 15. 17 CSIR team has significant expertise from power system planning, system operation and grid perspective Dr Tobias Bischof-Niemz • Head of the CSIR Energy Centre • Member of the Ministerial Advisory Council on Energy (MACE) • Member of IRP2010/2013 team at Eskom, energy planning in Europe for large utilities Jarrad Wright • Principal Engineer: Energy Planning (CSIR Energy Centre) • Commissioner: National Planning Commission (NPC) • Former Africa Manager of PLEXOS Robbie van Heerden • Senior Specialist: Energy Systems (CSIR Energy Centre) • Former General Manager and long-time head of System Operations at Eskom Crescent Mushwana • Research Group Leader: Energy Systems (CSIR Energy Centre) • Former Chief Engineer at Eskom strategic transmission grid planning Mamahloko Senatla • Researcher: Energy Planning (CSIR Energy Centre) • Previously with the Energy Research Centre at University of Cape Town Joanne Calitz • Senior Engineer: Energy Planning (CSIR Energy Centre) • Previously with Eskom Energy Planning • Medium-Term Outlook and IRP for RSA
  • 16. 18 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions IRP Results and Least-cost Scenario Summary
  • 17. 19 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions • Cost inputs for solar PV and wind • Limitations on build-out rates for solar PV and wind IRP Results and Least-cost Scenario Summary
  • 18. 22 IRP 2010 forecasted steep cost decline for solar PV from 2010 to 2030 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year Assumptions: IRP 2010 - low Assumptions: IRP 2010 - high Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
  • 19. 23 Actual solar PV tariffs quickly moved below IRP 2010 cost assumptions 0.62 3.65 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 0.91 1.17 2.18 Actuals: REIPPPP (BW1-4Exp) Assumptions: IRP 2010 - low Assumptions: IRP 2010 - high Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis ∑ = 2.8 GW BW1  BW 4 (Expedited)
  • 20. 24 IRP 2016 increases cost assumptions for solar PV compared to IRP 2010 0.62 3.65 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 0.91 1.17 2.18 Actuals: REIPPPP (BW1-4Exp) Assumptions: IRP 2016 - low Assumptions: IRP 2016 - high Assumptions: IRP 2010 - low Assumptions: IRP 2010 - high Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis ∑ = 2.8 GW BW1  BW 4 (Expedited)
  • 21. 25 IRP 2010 forecasted small cost decline for wind from 2010 to 2030 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year Assumptions: IRP 2010 Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis
  • 22. 26 Actual wind tariffs quickly moved below IRP 2010 assumptions 0.62 0.69 1.19 1.52 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 0.87 Assumptions: IRP 2010 Actuals: REIPPPP (BW1-4Exp) ∑ = 4.0 GW Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis BW1  BW 4 (Expedited)
  • 23. 27 IRP 2016 increases cost assumptions for wind compared to IRP 2010 0.62 0.69 1.19 1.52 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 0.87 Assumptions: IRP 2010 Actuals: REIPPPP (BW1-4Exp) Assumptions: IRP 2016 - low Assumptions: IRP 2016 - high ∑ = 4.0 GW Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis BW1  BW 4 (Expedited)
  • 24. 29 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions • Cost inputs for solar PV and wind • Limitations on build-out rates for solar PV and wind IRP Results and Least-cost Scenario Summary
  • 25. 30 Draft IRP 2016 limits the annual build-out rates for solar PV and wind The imposed new-build limits for solar PV and wind mean that the IRP model is not allowed in any given year to add more solar PV and wind capacity to the system than these limits No such limits are applied for any other technology. No techno-economical reason/justification is provided for these limits. No explanation given why the limits are constant until 2050 while the power system grows Year System Peak Load in MW (as per Draft IRP) New-build limit Solar PV in MW/yr (as per Draft IRP) Relative new-build limit Solar PV (derived from IRP) New-build limit Wind in MW/yr (as per Draft IRP) Relative new-build limit Wind (derived from IRP) 2020 44 916 1 000 2.2% 1 600 3.6% 2025 51 015 1 000 2.0% 1 600 3.1% 2030 57 274 1 000 1.7% 1 600 2.8% 2035 64 169 1 000 1.6% 1 600 2.5% 2040 70 777 1 000 1.4% 1 600 2.3% 2045 78 263 1 000 1.3% 1 600 2.0% 2050 85 804 1 000 1.2% 1 600 1.9% Note: Relative new-build limit = New-build limit / system peak load Sources: IRP 2016 Draft; CSIR analysis
  • 26. 31 Today: Both leading and follower countries are installing more new solar PV capacity per year than South Africa’s IRP limits for 2030/2050 2% 3% 4% 10% 9%9% 5% 2% 4% 2% 4% 1% 1% 1% 3% 7% 4% 1% 0% 6% 3% 3% 3% 2% 1% 0%0% 7% 6% 4% 1% 1% 1%0%0% 2% 2%2% 1% 0% 0%0%0% 1% 1% 1% 0% 0%0%0% 0% 2% 2007 3% 0% 2014 0% 3% 0% 2008 0% 1% 0% 2013 2% 0% 2012 2% 1% 2011 1% 17% 3% 2010 0% 1% 2009 2050 (1.2%) 2030 (1.7%) 2015 India South Africa China Japan Australia UK Italy Spain GermanyAnnual new solar PV capacity relative to system peak load RSA’s IRP relative new-build limit decreases over time Leader Follower Follower 2nd wave Sources: SolarPowerEurope; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis RSA new-build limits in 2030 and 2050
  • 27. 32 Today: Both leading and follower countries are installing more new wind capacity per year than South Africa’s IRP limits for 2030/2050 7% 6% 4% 3% 2% 2% 2% 2%2% 3% 6% 8% 3%3% 6% 3% 4% 5%5% 7% 3% 4% 6% 5% 5% 8% 4% 4% 3% 3% 4% 3% 3% 2% 2% 2% 1% 2%2% 2% 2% 5% 4% 2% 2% 1% 1%0% 0%0% 0% 3% 1% 2% 20092008 2% 0% 2014 1% 2011 1% 0% 2012 1% 0% 2013 2016 2050 (1.9%) 2030 (2.8%) 2015 1% 2% 2010 1% 2007 1% 1% 2006 0% 0% 2% Brazil South Africa India China Ireland Spain Germany RSA’s IRP relative new-build limit decreases over time Leader RSA new-build limits in 2030 and 2050 Sources: GWEC; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis Follower Annual new wind capacity relative to system peak load
  • 28. 33 Solar PV penetration in leading countries today is 2.5 times that of South Africa’s Draft IRP 2016 Base Case for the year 2050 0% 10% 20% 30% 40% 50% 60% 70% 2005 2010 2015 2020 2025 2030 2035 2040 2045 2050 TotalsolarPVcapacity relativetosystempeakload Year Spain UK Italy Japan Germany Australia China South Africa India South Africa IRP 2016 Base Case Sources: SolarPowerEurope; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis Leader Follower Follower 2nd wave
  • 29. 34 Wind penetration in leading countries today is 1.7-1.8 times that of South Africa’s Draft IRP 2016 Base Case for the year 2050 0% 10% 20% 30% 40% 50% 60% 70% 2005 2010 2015 2020 2025 2030 2035 2040 2045 2050 Totalwindcapacity relativetosystempeakload Year Spain Germany Ireland Brazil India China South Africa IRP 2016 Base Case South Africa Sources: GWEC; CIGRE; websites of System Operators; IRP 2016 Draft; CSIR analysis Leader Follower
  • 30. 35 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions IRP Results and Least-cost Scenario Summary
  • 31. 36 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions IRP Results and Least-cost Scenario • Input Assumptions • Results Summary
  • 32. 37 550 500 450 400 350 300 250 200 150 100 50 0 2020 2030 2040 2050 Electricity in TWh/yr 2016 522 428 344 280 244 Input as per IRP 2016: Demand is forecasted to double by 2050 Forecasted demand for the South African electricity system from 2016 to 2050 Sources: DoE (IRP 2016); Eskom MTSAO 2016-2021; StatsSA; World Bank; CSIR analysis Note: by 2050 the electricity demand per capita would still be less than that of Australia today Demand
  • 33. 38 550 500 0 200 150 100 50 400 300 250 350 450 2016 2040 82 2030 174 259 Electricity in TWh/yr 20502020 Input as per IRP 2016: Decommissioning schedule for existing plants Decommissioning schedule for the South African electricity system from 2016 to 2050 Solar PV CSP Wind Other Peaking Gas (CCGT) Hydro+PS Nuclear Coal Decommissioning of Eskom’s coal fleet All power plants considered for “existing fleet” that are either: 1) Existing in 2016 2) Under construction 3) Procured (preferred bidder) Demand Sources: DoE (IRP 2016); Eskom MTSAO 2016-2021; StatsSA; World Bank; CSIR analysis Existing supply
  • 34. 39 Demand grows, existing fleet phases out – gap needs to be filled Forecasted supply and demand balance for the South African electricity system from 2016 to 2050 350 450 200 250 300 400 500 550 0 50 100 150 428 254 522 2040 439 2030 Electricity in TWh/yr 344 2016 84 2020 2050 Other Coal Peaking Gas (CCGT) Hydro+PS Nuclear CSP Solar PV Wind Supply gap Decommissioning of Eskom’s coal fleet The IRP model fills the supply gap in the least-cost manner, subject to any constraints imposed on the model Demand Note: All power plants considered for “existing fleet” that are either Existing in 2016, Under construction, or Procured (preferred bidder) Sources: DoE (IRP 2016); Eskom MTSAO 2016-2021; StatsSA; World Bank; CSIR analysis
  • 35. 41 0.620.62 Gas (OCGT) 3.69 Diesel (OCGT) 2.89 Mid-merit CoalGas (CCGT) 1.41 Nuclear 1.41 1.09 Baseload Coal (PF) 1.00 WindSolar PV Variable (Fuel) Fixed (Capital, O&M) Inputs as per IRP 2016: Key resulting LCOE from cost assumptions for new supply technologies 50%90% 50% 10%Assumed capacity factor2  10% Lifetime cost per energy unit1 (LCOE) in R/kWh (Apr-2016-R) 1 Lifetime cost per energy unit is only presented for brevity. The model inherently includes the specific cost structures of each technology i.e. capex, Fixed O&M, variable O&M, fuel costs etc. 2 Changing full-load hours for new-build options drastically changes the fixed cost components per kWh (lower full-load hours  higher capital costs and fixed O&M costs per kWh); Assumptions: Average efficiency for CCGT = 55%, OCGT = 35%; nuclear = 33%; IRP costs from Jan-2012 escalated to May-2016 with CPI; assumed EPC CAPEX inflated by 10% to convert EPC/LCOE into tariff; Sources: IRP 2013 Update; Doe IPP Office; StatsSA for CPI; Eskom financial reports for coal/diesel fuel cost; EE Publishers for Medupi/Kusile; Rosatom for nuclear capex; CSIR analysis 82% Same assumptions used as per IRP 2016 0 0 1 000 0 1 000400 600 600 CO2 in kg/MWh
  • 36. 43 IRP 2016 increases cost assumptions for solar PV compared to IRP 2010 0.62 3.65 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 0.91 1.17 2.18 Actuals: REIPPPP (BW1-4Exp) Assumptions: IRP 2016 - low Assumptions: IRP 2016 - high Assumptions: IRP2010 - low Assumptions: IRP2010 - high Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis ∑ = 2.8 GW BW1  BW 4 (Expedited)
  • 37. 44 CSIR study cost input assumptions for solar PV: Future cost assumptions for solar PV aligned with IRP 2010 0.490.520.62 3.65 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 2010 2015 2020 2025 2030 2035 2040 2045 2050 0.91 2.18 1.17 Tariff in R/kWh (Apr-2016-Rand) Year 0.56 Assumptions: IRP 2016 - high Assumptions: IRP 2016 - low Assumptions: IRP2010 - low Actuals: REIPPPP (BW1-4Exp) Assumptions: IRP2010 - high Assumptions for this study Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis ∑ = 2.8 GW BW1  BW 4 (Expedited)
  • 38. 45 IRP 2016 increases cost assumptions for wind compared to IRP 2010 0.62 0.69 1.19 1.52 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 0.87 Assumptions: IRP2010 Actuals: REIPPPP (BW1-4Exp) Assumptions: IRP 2016 - low Assumptions: IRP 2016 - high ∑ = 4.0 GW Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis BW1  BW 4 (Expedited)
  • 39. 46 CSIR study cost input assumptions for wind: Future cost assumptions for wind aligned with results of Bid Window 4 0.62 0.62 0.620.62 0.69 1.19 1.52 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 0.87 Assumptions: IRP2010 Actuals: REIPPPP (BW1-4Exp) Assumptions for this study Assumptions: IRP 2016 - low Assumptions: IRP 2016 - high ∑ = 4.0 GW Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis BW1  BW 4 (Expedited)
  • 40. 47 CSIR study cost input assumptions for CSP: Today’s latest tariff as starting point, same cost decline as per IRP 2010 1.201.201.20 3.55 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 2010 2015 2020 2025 2030 2035 2040 2045 2050 Tariff in R/kWh (Apr-2016-Rand) Year 2.02 2.90 3.11 3.32 Assumptions: IRP2010 - high Actuals: REIPPPP (BW1-4Exp) Assumptions: IRP2010 - low Assumptions for this study Assumptions: IRP2016 - high Assumptions: IRP2016 - low For bid window 3, 3.5 and 4 Exp, weighted average tariff of base and peak tariff calculated on the assumption of 64%/36% base/peak tariff utilisation ratio Notes: REIPPPP = Renewable Energy Independant Power Producer Programme; BW = Bid Window; bid submissions for the different BWs: BW1 = Nov 2011; BW2 = Mar 2012; BW 3 = Aug 2013; BW 4 = Aug 2014; BW 4 (Expedited) = Nov 2015 Sources: StatsSA for CPI; IRP 2010; South African Department of Energy (DoE); DoE IPP Office; CSIR analysis BW1  BW 4 (Expedited)
  • 41. 48 200 250 0 50 100 150 200 250 300 2010 2015 2020 2025 2030 2035 2040 2045 2050 CO2 Emissions Cap (electricity sector) [Mt/yr] 275275 CO2 emissions constrained by RSA’s Peak-Plateau-Decline objective PPD that constrains CO2 emission from electricity sector PPD = Peak Plateau Decline Sources: DoE (IRP 2010-2030 Update); StatsSA; CSIR analysis
  • 42. 49 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions IRP Results and Least-cost Scenario • Input Assumptions • Results Summary
  • 43. 50 Draft IRP 2016 Base Case Overview of scenarios available for comparison Scenario Difference to Draft IRP 2016 Base CaseSource Draft IRP 2016 Carbon Budget Draft IRP 2016 “Unconstrained Base Case” Least Cost Department of Energy Draft IRP 2016 as of November 2016 Department of Energy Draft IRP 2016 as of November 2016 Department of Energy Scenario run by DoE/Eskom as per request of the Ministerial Advisory Council on Energy (MACE) CSIR Draft Least Cost as of February 2017 N/A Tighter carbon reduction targets No constraints on solar PV and wind • No constraints on solar PV/wind • Solar PV, wind and CSP costing aligned with latest IPP results • Demand response by 2050 in residential warm water provision
  • 44. 51 Common reporting layout applied to all scenarios by DoE and by CSIR Determine total operational capacity per year • Add existing fleet & its decommissioning schedule • Decommission new power plants at the end of their economic life (wind = 20, solar PV = 25 years) Determine energy balances with typical load factors for different technologies and calibrate with IRP numbers … are analysed with respect to total installed capacity (GW) and energy balance (TWh/yr) Scenarios of the Draft IRP 2016 show the annual new installed capacity per year per technology Sources: Draft IRP 2016, http://www.energy.gov.za/IRP/irp-presentaions/IRP-Update-Presentation-22-Nov-2016.pdf; CSIR analysis 0 300 550 500 450 400 350 250 200 150 100 50 22 2030 344 235 2050 23 36 13 2016 248 13 207 15 17 523 159 (30%) 165 (32%) 33 (6%) 39 (7%) 93 (18%) 28 (5%) 2040 33 431 229 35 34 66 Total electricity produced in TWh/yr Coal Nuclear Hydro+PS Gas (CCGT) Peaking Wind CSP Solar PV IRP scenarios as published by the DoE …
  • 45. 52 Draft IRP 2016 Base Case is a mix of roughly 1/3 coal, nuclear, RE each Draft IRP 2016 Base Case 50 150 250 0 300 200 500 350 400 450 550 100 33 (6%) 165 (32%) 2040 39 (7%) 28 (5%) 93 (18%) 523 15 Total electricity produced in TWh/yr 431 229 35 159 (30%) 34 33 66 20502030 344 235 13 23 22 13 2016 248 207 17 36 Wind Peaking Gas (CCGT) Hydro+PS Nuclear CoalCSP Solar PV Sources: DoE Draft IRP 2016; CSIR analysis As per Draft IRP 2016 More stringent carbon limits
  • 46. 53 Draft IRP 2016 Carbon Budget case: 40% nuclear energy share by 2050 Draft IRP 2016 Base Case Draft IRP 2016 Carbon Budget 50 150 250 0 300 200 500 350 400 450 550 100 33 (6%) 165 (32%) 2040 39 (7%) 28 (5%) 93 (18%) 523 15 Total electricity produced in TWh/yr 431 229 35 159 (30%) 34 33 66 20502030 344 235 13 23 22 13 2016 248 207 17 36 Wind Peaking Gas (CCGT) Hydro+PS Nuclear CoalCSP Solar PV 300 450 500 550 50 0 100 400 250 200 150 350 345 161 433 2030 103 44 (8%) 85 2040 33 134 109 (21%) 17 39 29 Total electricity produced in TWh/yr 2050 15 35 (7%) 206 (39%) 63 (12%) 525 207 23 248 2016 23 63 57 63 (12%) As per Draft IRP 2016 More stringent carbon limits Sources: DoE Draft IRP 2016; CSIR analysis No RE limits, reduced wind/solar PV costing, warm water demand flexibility
  • 47. 54 Least Cost case is largely based on wind and solar PV Draft IRP 2016 Base Case Least CostDraft IRP 2016 Carbon Budget 50 150 250 0 300 200 500 350 400 450 550 100 33 (6%) 165 (32%) 2040 39 (7%) 28 (5%) 93 (18%) 523 15 Total electricity produced in TWh/yr 431 229 35 159 (30%) 34 33 66 20502030 344 235 13 23 22 13 2016 248 207 17 36 Wind Peaking Gas (CCGT) Hydro+PS Nuclear CoalCSP Solar PV 300 450 500 550 50 0 100 400 250 200 150 350 345 161 433 2030 103 44 (8%) 85 2040 33 134 109 (21%) 17 39 29 Total electricity produced in TWh/yr 2050 15 35 (7%) 206 (39%) 63 (12%) 525 207 23 248 2016 23 63 57 63 (12%) 350 200 0 50 250 400 550 500 450 100 150 300 15 83 433 2040 130 (25%) 22 87 189 9 16 282 (54%) 44 (8%) 2050 49 22 15 527 15 Total electricity produced in TWh/yr 20 (4%) 36 (7%) 346 2030 17 207 248 2016 35 212 As per Draft IRP 2016 More stringent carbon limits No RE limits, reduced wind/solar PV costing, warm water demand flexibility Sources: DoE Draft IRP 2016; CSIR analysis
  • 48. 55 Least Cost means no new coal and no new nuclear until 2050, instead 90 GW of wind and 70 GW of solar PV plus flexible capacities Draft IRP 2016 Base Case Least CostDraft IRP 2016 Carbon Budget 250 200 150 100 50 0 2050 135 25 20 8 22 13 30 16 2040 111 33 5 8 17 12 21 12 2030 85 39 2 6 8 11 7 2016 51 37 5 3 Total installed net capacity in GW Coal Nuclear Hydro+PS Gas (CCGT) Peaking Wind CSP Solar PV 250 0 200 150 100 50 Total installed net capacity in GW 2050 149 10 26 8 33 10 36 25 2040 129 19 17 8 19 8 34 22 2030 98 34 7 8 10 20 13 2016 51 37 5 3 100 0 50 250 150 200 60 52 2030 100 31 34 2050 5 10 18 237 2016 Total installed net capacity in GW 7 2040 178 19 25 73 5 37 2 19 22 93 51 5 37 16 3 As per Draft IRP 2016 More stringent carbon limits Plus 25 GW demand response from residential warm water provision Note: REDZ = Renewable Energy Development Zones Current REDZ cover 7% of South Africa‘s land mass Sources: DoE Draft IRP 2016; CSIR analysis No RE limits, reduced wind/solar PV costing, warm water demand flexibility 535 GW 1 782 GW Technical potential in REDZ only
  • 49. 56 On request by the Ministerial Advisory Council on Energy (MACE) the DoE re-ran the IRP 2016 Base Case without constraining solar PV/wind Source: MACE’s presentation during the IRP public consultations on 7 December 2016 in Johannesburg Sources: http://www.energy.gov.za/IRP/irp-presentaions/Comments-on-IRP-2016-Draft-KabiSolar.pdf
  • 50. 57 The DoE’s “Unconstrained Base Case” is similar to the CSIR’s Least Cost Source: MACE’s presentation during the IRP public consultations on 7 December 2016 in Johannesburg Sources: http://www.energy.gov.za/IRP/irp-presentaions/Comments-on-IRP-2016-Draft-KabiSolar.pdf
  • 51. 58 Demand and Supply in GW 110 120 90 60 70 80 30 40 50 100 0 10 20 Draft IRP 2016 Base Case: Nuclear and coal dominate the supply mix in 2050 Monday Tuesday Wednesday Thursday Friday Saturday Sunday Sources: CSIR analysis, based on DoE‘s Draft IRP 2016 DemandNuclear Coal Gas (CCGT) Hydro Peaking Wind Solar PV Exemplary Week under Draft IRP 2016 Base Case (2050)
  • 52. 59 Demand and Supply in GW 60 50 40 30 20 10 0 120 110 100 90 80 70 Draft IRP 2016 Carbon Budget: Nuclear dominates the supply mix in 2050, gas required for balancing Monday Tuesday Wednesday Thursday Friday Saturday Sunday DemandNuclear Coal Gas (CCGT) Hydro Peaking Wind Solar PV Exemplary Week under Draft IRP 2016 Carbon Budget (2050) Sources: CSIR analysis, based on DoE‘s Draft IRP 2016
  • 53. 60 Demand and Supply in GW 10 50 60 80 90 70 120 110 100 30 20 0 40 Least Cost: Solar PV and wind dominate supply mix in 2050, with excess at times Monday Tuesday Wednesday Thursday Friday Saturday Sunday Sources: CSIR analysis DemandWindCurtailed solar PV and wind Solar PV Peaking Hydro Gas (CCGT) Coal Nuclear Exemplary Week under Least Cost (2050)
  • 54. 61 Total cost of power generation: Draft IRP 2016 Base Case R86 bn/year more expensive by 2050 than Least Cost (without cost of CO2) 522 398 286 132 518 413 300 436 359 262 2010 2020 2030 2040 2050 200 0 50 250 300 350 400 150 550 450 100 500 Total cost of power generation in bR/yr (constant 2016 Rand) +86 (+20%) Draft IRP 2016 Carbon Budget Draft IRP 2016 Base Case Least Cost Sources: CSIR analysis 2016 Note: Medium-term from 2016 to 2030 not in the main focus of a long-term IRP study and therefore only indicative. Will be investigated in more detail in a separate sub-study.
  • 55. 62 Average tariff (without cost of CO2): Draft IRP Base Case tariff 17 cents/kWh higher than Least Cost by 2050 1.13 1.22 1.291.25 1.17 1.13 1.06 1.13 0.83 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 2010 2020 2030 2040 2050 +0.17 (+15%) Average tariff in R/kWh (constant 2016 Rand) Draft IRP 2016 Carbon Budget Least Cost Draft IRP 2016 Base Case Note: Average tariff projections include 0.30 R/kWh for transmission, distribution and customer service (today‘s average cost for these items) Sources: Eskom on Tx, Dx cost; CSIR analysis Note: Medium-term from 2016 to 2030 not in the main focus of a long-term IRP study and therefore only indicative. Will be investigated in more detail in a separate sub-study. 2016
  • 56. 63 Average tariff (with cost of CO2): Draft IRP Base Case tariff 20 cents/kWh higher than Least Cost by 2050 1.34 1.14 0.95 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 2010 2020 2030 2040 2050 +0.20 (+17%) Average tariff in R/kWh (constant 2016 Rand) Least Cost Draft IRP 2016 Carbon Budget Draft IRP 2016 Base Case Note: Average tariff projections include 0.30 R/kWh for transmission, distribution and customer service (today‘s average cost for these items) Sources: Eskom on Tx, Dx cost; CSIR analysis 2016 Note: Medium-term from 2016 to 2030 not in the main focus of a long-term IRP study and therefore only indicative. Will be investigated in more detail in a separate sub-study.
  • 57. 64 Least Cost without renewables limits is R82-86 billion/yr cheaper by 2050 than IRP 2016 Base Case and IRP 2016 Carbon Budget case Draft IRP 2016 Base Case Least CostDraft IRP 2016 Carbon Budget R518 billion/yr Ø tariff = 1.29 R/kWh R436 billion/yr Ø tariff = 1.13 R/kWh 100 Mt/yr 70 Mt/yr 16 bn l/yr 9 bn l/yr R522 billion/yr Ø tariff = 1.29 R/kWh 200 Mt/yr 38 bn l/yr Note: Average tariff projections include 0.30 R/kWh for transmission, distribution and customer service (today‘s average cost for these items) Sources: Eskom on Tx, Dx cost; CSIR analysis As per Draft IRP 2016 18% 32% 7% 1% 30% 5% 6% 21% 1% 12% 7% 39% 12% 8% 7% 2% 4% 1% 25% 8% 54% ~525 TWh/yr ~525 TWh/yr ~525 TWh/yr Nuclear Hydro + Pumped Storage WindGas (CCGT) OtherCoal CSP Solar PVPeaking
  • 58. 65 200 220 20 0 -20 -40 160 180 140 120 100 80 60 40 Annual cost delta of Draft IRP – Least Cost by 2050 in bR/yr 86 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 Today (2016) Study assumptions (2020-2050) Relative RE/nuclear cost (Today: RE = 0.62 R/kWh, Nuclear = 1.09 R/kWh  0.57) Relative RE/coal cost (Today: RE = 0.62 R/kWh, Coal = 1.00 R/kWh  0.62) Sensitivity on cost difference: Even if RE were 50% more expensive than assumed, Least Cost is still cheaper than Draft IRP 2016 Base Case Sources: CSIR analysis
  • 59. 66 Agenda Background CSIR’s Approach and Project Team Comments on IRP Assumptions IRP Results and Least-cost Scenario Summary
  • 60. 67 Summary: A mix of solar PV, wind and flexible power generators is least cost Solar PV, wind & flexible power generators (e.g. gas, CSP, hydro, biogas, demand res.) is the cheapest new- build mix for the RSA power system. It is cost-optimal to aim for >70% renewable energy share by 2050 This “Least Cost” mix is > R80 billion per year cheaper by 2050 than the current Draft IRP 2016 Base Case Additionally, Least Cost mix reduces CO2 emissions by 65% (-130 Mt/yr) over the Draft IRP 2016 Base Case Therefore: Avoiding CO2 emissions and least-cost is not a trade-off anymore – South Africa can de- carbonise its electricity sector at negative carbon-avoidance cost The IRP and this analysis factor in all first-order cost drivers within the boundaries of the electricity system, but not external costs and benefits of certain electricity mixes that occur outside of the electricity system Deviations from the Least Cost electricity mix can be quantified to inform policy adjustments (e.g. forcing in of certain technologies not selected by the least-cost mix like coal, nuclear, hydro, CSP, biogas, biomass, etc.) Note: Wind and solar PV would have to be 50% more expensive than assumed before the IRP Base Case and the Least Cost case break even Sources: CSIR analysis
  • 61. 68 Thank you Re a leboga Siyathokoza Enkosi Siyabonga Re a leboha Ro livhuha Ha Khensa Dankie Note: „Thank you“ in all official languages of the Republic of South Africa