CARP ASSESSMENT STATUS
                                      HANGAR ONE RE-SIDING PROJECT
                                            REPORT NO. IG-11-020
                                       OFFICE OF INSPECTOR GENERAL
                                   http://oig.nasa.gov/audits/reports/FY11/

                                               Conclusion
  While we do not dispute that historic preservation is a worthy consideration, we question whether
     expending more than $32 million to re-side a hangar that has no prospects for reuse for the
  foreseeable future and would require substantial additional investment to make it habitable is the
 best use of NASA’s limited construction resources. Moreover, dedicating funds to Hangar One means
that other critical renovation and repair projects will be delayed, which could result in unsafe working
  conditions, higher annual maintenance costs, and damage to Agency equipment. Given these risks,
    we believe NASA should analyze the full range of options before taking further action regarding
                                              Hangar One.

                           Options Required for the CARP Regarding Hangar One
• Re-side Hangar One as described in the Budget Request and determine the annual maintenance cost assuming no
intended use;
•   Re-side Hangar One and make the necessary upgrades and repairs to enable use as a hangar;
•   Re-side Hangar One and make the necessary upgrades and repairs to enable public assemblies;
•   Demolish Hangar One and carry out historic preservation mitigation actions; and
•   Transfer Hangar One to another government entity under the Historic Surplus Property Program.
CARP
                    Condition Assessment and Rehabilitation Plan for Hangar One

                                                STATUS
                                            November 3, 2011




Objectives:
The project is a study that investigates current conditions and the expected condition after the
remediation project by the Navy of Hangar One, as well as cost estimates for potential rehabilitation
options.



The study will include:
• All Options as required by the OIG, however, the CARP does not include the assessment of transfer
options.
CARP
                         Condition Assessment and Rehabilitation Plan for Hangar One


Options
Option A. Basic Re-Skinning, Maintain Existing Occupancy as a Hangar
• Re-skinning for future use and for preservation of the historic building.
• Structural modifications only where necessary due to hazardous conditions.
• Provide basic services such as lighting, power and toilet rooms to continue use as a hangar.


Option B. Re-Skinning with structural and other upgrades for re-use as a Hangar
• Provides all items noted in Option A.
• In addition, analyze geotechnical improvements and structural upgrades per Life Safety performance levels.


Option C. Re-Skinning with structural and other upgrades for re-use as a Hangar
• Provides all items noted in Option B.
• In addition, calls for rehabilitation with historic considerations required by California Historic Building Code.


Option D. Adaptive Re-Use, Re-Skinning with Upgrades (Geotechnical, Structural) and Re-Use as a
higher Occupancy Level (from Hangar to Assembly, or Mixed Use)
• Provides all items noted in Option C
• In addition, complies with all California codes for life safety aspects for higher occupancy use, such as sporting fields,
training space, temporary movie sets, office space, museum, conventions and retail space, etc.
CARP
                       Condition Assessment and Rehabilitation Plan for Hangar One



Options

Option E1. Layaway Plan (maintenance without occupants) after re-skinning
• Includes annual cost and maintenance requirements associated with the re-skinned hangar per Option A.
            - Electrical power for basic lighting and hangar door operation, annual roof inspection, etc.


Option E2. Layaway Plan (maintenance without occupants) while structure is exposed
• Includes annual cost and maintenance requirements associated with the un-skinned hangar based on the exposed,
steel structure remaining in place.
             - Ground maintenance for vegetation and weed control, potential ongoing remediation of
       sediment ponds, etc.


Option F. Demolition Costs
• Following remediation efforts currently in progress by the Navy, the remaining portion of the facility requiring
demolition includes the existing steel frame, concrete foundation, concrete slab, hangar doors and components
(motors, trucks, pivots), miscellaneous site utilities plus the contaminate materials.
CARP
                     Condition Assessment and Rehabilitation Plan for Hangar One

                                                    STATUS

                                              CARP Schedule
                                       Early July 2011 - Kick-off Meeting
                                        Mid October - Draft for Review
                                            November - Completion


                                          CARP Current Status:
The 95% draft submittal have been received and the contractors are working to the required objectives. The CARP is
  progressing per the IG audit to be completed by the end of November and once it is approved by NASA, it will be
                                           made available to the public.

More Related Content

What's hot

Pre proposal meeting - supervisory consultancy
Pre proposal meeting  - supervisory consultancyPre proposal meeting  - supervisory consultancy
Pre proposal meeting - supervisory consultancyRiaz Zalil
 
PEC Project Management Planning Achievements
PEC Project Management  Planning AchievementsPEC Project Management  Planning Achievements
PEC Project Management Planning AchievementsVernonRowe
 
Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...
Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...
Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...CIFOR-ICRAF
 
Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010Hayley Pallister
 
Petroleum Site 14 Update
Petroleum Site 14 UpdatePetroleum Site 14 Update
Petroleum Site 14 UpdateSteve Williams
 
GreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedGreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedJose Calderon Garcia
 
IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16Graeme Donaldson
 
Guidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient LandscapeGuidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient LandscapeFujita64g
 
Navy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost EstimateNavy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost EstimateSteve Williams
 
Giles Run Pump Station Rehabilitation
Giles Run Pump Station RehabilitationGiles Run Pump Station Rehabilitation
Giles Run Pump Station RehabilitationFairfax County
 
DFCs Demystified and GMA Status Update, Bill Hutchison
DFCs Demystified and GMA Status Update, Bill HutchisonDFCs Demystified and GMA Status Update, Bill Hutchison
DFCs Demystified and GMA Status Update, Bill HutchisonTXGroundwaterSummit
 

What's hot (19)

Pre proposal meeting - supervisory consultancy
Pre proposal meeting  - supervisory consultancyPre proposal meeting  - supervisory consultancy
Pre proposal meeting - supervisory consultancy
 
December 9, 2010
December 9, 2010December 9, 2010
December 9, 2010
 
PEC Project Management Planning Achievements
PEC Project Management  Planning AchievementsPEC Project Management  Planning Achievements
PEC Project Management Planning Achievements
 
ORP FY13 Budget Workshop
ORP FY13 Budget WorkshopORP FY13 Budget Workshop
ORP FY13 Budget Workshop
 
NJCCV_2016
NJCCV_2016NJCCV_2016
NJCCV_2016
 
Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...
Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...
Reducing Ship Emissions: a Review of Potential Practical Improvements in the ...
 
Gec97
Gec97Gec97
Gec97
 
Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010Kapileshwari and Robison- Gulf Coast Green 2010
Kapileshwari and Robison- Gulf Coast Green 2010
 
Petroleum Site 14 Update
Petroleum Site 14 UpdatePetroleum Site 14 Update
Petroleum Site 14 Update
 
GreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedGreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimized
 
IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16
 
Summary of Joint Planning to Date for GMAs 2,3,7, 11, and 13
Summary of Joint Planning to Date for GMAs 2,3,7, 11, and 13 Summary of Joint Planning to Date for GMAs 2,3,7, 11, and 13
Summary of Joint Planning to Date for GMAs 2,3,7, 11, and 13
 
Guidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient LandscapeGuidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient Landscape
 
Navy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost EstimateNavy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost Estimate
 
Bco2 Lfg Ver Project Us
Bco2 Lfg Ver Project UsBco2 Lfg Ver Project Us
Bco2 Lfg Ver Project Us
 
Paul Helliker - BDCP
Paul Helliker - BDCPPaul Helliker - BDCP
Paul Helliker - BDCP
 
Giles Run Pump Station Rehabilitation
Giles Run Pump Station RehabilitationGiles Run Pump Station Rehabilitation
Giles Run Pump Station Rehabilitation
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
DFCs Demystified and GMA Status Update, Bill Hutchison
DFCs Demystified and GMA Status Update, Bill HutchisonDFCs Demystified and GMA Status Update, Bill Hutchison
DFCs Demystified and GMA Status Update, Bill Hutchison
 

Similar to NASA Condition Assessment and Rehabilitation Plan for Hangar One

Lead Process Engineer
Lead Process EngineerLead Process Engineer
Lead Process EngineerJuber Loharia
 
Environmental clearance of airports
Environmental clearance of airportsEnvironmental clearance of airports
Environmental clearance of airportsAbhishek Kumar Sinha
 
NASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldNASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldSteve Williams
 
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016Alan Carolissen
 
DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014Piyush Sharma
 
Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...
Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...
Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...Steve Williams
 
Hwange Project Implementation Guidelines (Nampower Presentation)
Hwange Project Implementation Guidelines (Nampower Presentation)Hwange Project Implementation Guidelines (Nampower Presentation)
Hwange Project Implementation Guidelines (Nampower Presentation)Kudakwashe Mareya, Pr.Eng
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptxPradeepKumar504728
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
C2. Functional Requirements of FPSO
C2. Functional Requirements of FPSOC2. Functional Requirements of FPSO
C2. Functional Requirements of FPSODavid Seow
 
Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013gobindkhiani
 

Similar to NASA Condition Assessment and Rehabilitation Plan for Hangar One (20)

Lead Process Engineer
Lead Process EngineerLead Process Engineer
Lead Process Engineer
 
Environmental clearance of airports
Environmental clearance of airportsEnvironmental clearance of airports
Environmental clearance of airports
 
NASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldNASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett Field
 
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
The Management of Used Fuel-Key Mandate of NRWDI AC 14 DEC 2016
 
DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014
 
part 1 .pdf.pdf
part 1 .pdf.pdfpart 1 .pdf.pdf
part 1 .pdf.pdf
 
wsa
wsawsa
wsa
 
wsa
wsawsa
wsa
 
wsa
wsawsa
wsa
 
Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...
Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...
Moffett Restoration Advisory Board Hangar One Re-Siding Project NASA OIG Repo...
 
Hwange Project Implementation Guidelines (Nampower Presentation)
Hwange Project Implementation Guidelines (Nampower Presentation)Hwange Project Implementation Guidelines (Nampower Presentation)
Hwange Project Implementation Guidelines (Nampower Presentation)
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
API 610 pumps .pdf
API 610 pumps .pdfAPI 610 pumps .pdf
API 610 pumps .pdf
 
Eugene Jose
Eugene JoseEugene Jose
Eugene Jose
 
C2. Functional Requirements of FPSO
C2. Functional Requirements of FPSOC2. Functional Requirements of FPSO
C2. Functional Requirements of FPSO
 
Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013Aims presentation on Western Region NACE Conference at Victoria 2013
Aims presentation on Western Region NACE Conference at Victoria 2013
 
projects
projectsprojects
projects
 
How to avoid pit falls in design basis rev 3
How to avoid pit falls in design basis rev 3How to avoid pit falls in design basis rev 3
How to avoid pit falls in design basis rev 3
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 

More from Steve Williams

RAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationRAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationSteve Williams
 
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28Steve Williams
 
RAB Community Presentation
RAB Community PresentationRAB Community Presentation
RAB Community PresentationSteve Williams
 
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Steve Williams
 
NASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardNASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardSteve Williams
 
Moffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateMoffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateSteve Williams
 
Moffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanMoffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanSteve Williams
 
EPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationEPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationSteve Williams
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewSteve Williams
 
Orion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentOrion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentSteve Williams
 
Epa vi and source investigation rab mtg update august 7 2014rv1
Epa vi  and source investigation rab mtg update    august 7 2014rv1Epa vi  and source investigation rab mtg update    august 7 2014rv1
Epa vi and source investigation rab mtg update august 7 2014rv1Steve Williams
 
Moffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateMoffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateSteve Williams
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateSteve Williams
 
Moffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesMoffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesSteve Williams
 
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013Steve Williams
 
Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Steve Williams
 
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...Steve Williams
 
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesHazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesSteve Williams
 
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Steve Williams
 

More from Steve Williams (20)

RAB NASA Update
RAB NASA UpdateRAB NASA Update
RAB NASA Update
 
RAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationRAB Vapor Intrusion Mitigation
RAB Vapor Intrusion Mitigation
 
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
 
RAB Community Presentation
RAB Community PresentationRAB Community Presentation
RAB Community Presentation
 
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
 
NASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardNASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory Board
 
Moffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateMoffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area Update
 
Moffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanMoffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management Plan
 
EPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationEPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source Investigation
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year Review
 
Orion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentOrion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume Assessment
 
Epa vi and source investigation rab mtg update august 7 2014rv1
Epa vi  and source investigation rab mtg update    august 7 2014rv1Epa vi  and source investigation rab mtg update    august 7 2014rv1
Epa vi and source investigation rab mtg update august 7 2014rv1
 
Moffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateMoffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion Update
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion Update
 
Moffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesMoffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental Activities
 
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
 
Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013
 
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
 
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesHazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
 
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
 

Recently uploaded

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Recently uploaded (20)

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

NASA Condition Assessment and Rehabilitation Plan for Hangar One

  • 1. CARP ASSESSMENT STATUS HANGAR ONE RE-SIDING PROJECT REPORT NO. IG-11-020 OFFICE OF INSPECTOR GENERAL http://oig.nasa.gov/audits/reports/FY11/ Conclusion While we do not dispute that historic preservation is a worthy consideration, we question whether expending more than $32 million to re-side a hangar that has no prospects for reuse for the foreseeable future and would require substantial additional investment to make it habitable is the best use of NASA’s limited construction resources. Moreover, dedicating funds to Hangar One means that other critical renovation and repair projects will be delayed, which could result in unsafe working conditions, higher annual maintenance costs, and damage to Agency equipment. Given these risks, we believe NASA should analyze the full range of options before taking further action regarding Hangar One. Options Required for the CARP Regarding Hangar One • Re-side Hangar One as described in the Budget Request and determine the annual maintenance cost assuming no intended use; • Re-side Hangar One and make the necessary upgrades and repairs to enable use as a hangar; • Re-side Hangar One and make the necessary upgrades and repairs to enable public assemblies; • Demolish Hangar One and carry out historic preservation mitigation actions; and • Transfer Hangar One to another government entity under the Historic Surplus Property Program.
  • 2. CARP Condition Assessment and Rehabilitation Plan for Hangar One STATUS November 3, 2011 Objectives: The project is a study that investigates current conditions and the expected condition after the remediation project by the Navy of Hangar One, as well as cost estimates for potential rehabilitation options. The study will include: • All Options as required by the OIG, however, the CARP does not include the assessment of transfer options.
  • 3. CARP Condition Assessment and Rehabilitation Plan for Hangar One Options Option A. Basic Re-Skinning, Maintain Existing Occupancy as a Hangar • Re-skinning for future use and for preservation of the historic building. • Structural modifications only where necessary due to hazardous conditions. • Provide basic services such as lighting, power and toilet rooms to continue use as a hangar. Option B. Re-Skinning with structural and other upgrades for re-use as a Hangar • Provides all items noted in Option A. • In addition, analyze geotechnical improvements and structural upgrades per Life Safety performance levels. Option C. Re-Skinning with structural and other upgrades for re-use as a Hangar • Provides all items noted in Option B. • In addition, calls for rehabilitation with historic considerations required by California Historic Building Code. Option D. Adaptive Re-Use, Re-Skinning with Upgrades (Geotechnical, Structural) and Re-Use as a higher Occupancy Level (from Hangar to Assembly, or Mixed Use) • Provides all items noted in Option C • In addition, complies with all California codes for life safety aspects for higher occupancy use, such as sporting fields, training space, temporary movie sets, office space, museum, conventions and retail space, etc.
  • 4. CARP Condition Assessment and Rehabilitation Plan for Hangar One Options Option E1. Layaway Plan (maintenance without occupants) after re-skinning • Includes annual cost and maintenance requirements associated with the re-skinned hangar per Option A. - Electrical power for basic lighting and hangar door operation, annual roof inspection, etc. Option E2. Layaway Plan (maintenance without occupants) while structure is exposed • Includes annual cost and maintenance requirements associated with the un-skinned hangar based on the exposed, steel structure remaining in place. - Ground maintenance for vegetation and weed control, potential ongoing remediation of sediment ponds, etc. Option F. Demolition Costs • Following remediation efforts currently in progress by the Navy, the remaining portion of the facility requiring demolition includes the existing steel frame, concrete foundation, concrete slab, hangar doors and components (motors, trucks, pivots), miscellaneous site utilities plus the contaminate materials.
  • 5. CARP Condition Assessment and Rehabilitation Plan for Hangar One STATUS CARP Schedule Early July 2011 - Kick-off Meeting Mid October - Draft for Review November - Completion CARP Current Status: The 95% draft submittal have been received and the contractors are working to the required objectives. The CARP is progressing per the IG audit to be completed by the end of November and once it is approved by NASA, it will be made available to the public.