SlideShare a Scribd company logo
1 of 3
Download to read offline
Mashel III Cost Amendment Memo 1 | P a g e
Memorandum
Subject: SRFB Cost Amendment Request
PROJECT: 15-1231 RST, MASHEL EATONVILLE RESTORATION PHASE III
To: Ashley Von Essen (WRIA 11 LE Coordinator) and Elizabeth Butler (RCO)
From: Brian Combs, SPSSEG
Date: August 24, 2016
Request Summary: South Puget Sound Salmon Enhancement Group (SPSSEG) is
requesting a $180,000 cost increase for the Mashel Eatonville Restoration Phase III Project
(the project) to afford:
 habitat design improvements (described below)
 changes resulting from the SRFB review panel comment process
 additional road access needs
 project planting, and
 higher construction costs resulting from recent industry economic trends.
Additional NWIFC PCSRF matching funds in the amount of $110,000 are being provided by
the Nisqually Indian Tribe to contribute to the additional costs and to meet the additional match
need.
Background:
An earlier Preliminary Design was completed for the project in 2009. The project was selected
for advancement in 2015 and was ranked as a high priority within the watershed. During the
Review Panel site visit in 2015 several requests were made by the Panel to address possible
project improvements. These requests included looking at armor removal to allow broader
channel migration, addressing the need for side channel improvements, further analysis of the
landslide, and addressing general design improvements. An initial project budget was
submitted with the grant application which relied on an estimate of project needs and projected
costs at that time however an additional funding need was identified during the Preliminary
Design stage which has led to this amendment request.
This project represents the third phase of reach-scale treatments within the Mashel River. The
proposed restoration measures for the project site (Reach 7) include the construction of
several Engineered Log Jams (ELJ’s) and Large Woody Debris elements (LWD), side channel
activation, armor removal, and re-vegetation. This project and previous phases were identified
in the 2004 assessment by Watershed Professionals Network which provided the restoration
prescription for multiple reaches. The Nisqually Chinook Recovery Plan identified the Mashel
River as a high priority for restoration (specifically improving habitat complexity) because of its
Mashel III Cost Amendment Memo 2 | P a g e
importance for life history diversity. In the draft Nisqually Steelhead Recovery Plan, the Mashel
River ranked highest for restoration, overall, followed by the Nisqually River mainstem, when
considering abundance and productivity.
The additional estimated costs are associated with the following elements:
 Rip-rap armor removal to allow better channel migration (requested by the Review
Panel). Modelling and design work enabled us to see a pathway for adding this element
however a flood containment berm is needed to reduce flood risk.
 Flood containment berm: this is needed to reduce flood risk resulting from the rip-rap
armor removal.
 Improved LWD elements: the type and location of the ELJ’s and LWD has been
updated to maximize habitat gain. These concepts were “approved” by the review
panel during the preliminary-concept discussion.
 As-built survey: this was accidentally not included in the initial cost estimate.
 Updated planting costs for 6 acres of floodplain planting and ELJ planting.
 Updated road access costs: these costs include road improvements needed to access
the site from the north access and/or improvements to the existing south access.
 2016-17 dollars: The overall cost estimate was updated to reflect current economic
conditions, which have changed in the last two years with increased economic activity
(i.e. costs have gone up). To provide context, SPSSEG has received “high” bids on
three projects in 2016 and reports from our partners indicate that in general bids are
going up with the increased economic activity seen across the region. Thus, cost
estimates from even one or two years ago may now be inaccurate.
Match: The Nisqually Indian Tribe is providing an additional $110,000 in PCSRF funds (to be
awarded through the NWIFC) and $10,000 of in-kind match to supplement the requested
SRFB funds. These additional matching funds will exceed the original 15% commitment and
fully fund the estimate of construction costs. Based on the current estimate, the project will
also have a leverage surplus of $45,250 beyond the required match.
Timing: The project was initially slated for construction in 2016 however it was delayed in
order to finish the design work, geo-physical assessments, modelling, and planning. Currently
the project is slated for construction in 2017. Considerable progress has been made in
developing the project and with Preliminary Designs now complete, the 2017 construction time
frame should be achievable. Delaying the project further could lead to additional cost
increases resulting from changing economic trends and the prolonged costs of managing the
project. It would be incredibly inefficient to put the construction on hold only to be at the mercy
of the bidding environment in 2018 or beyond. The requested $180,000 has been approved by
the Lead Entity Work Group which has made room for this amendment in their annual
planning. Funding availability could decrease in subsequent years as the watershed priorities
and funding allotments change. As such, we feel confident that approving this cost
amendment now is reasonable and allows for a high chance of project success. Delaying the
project would lead to a higher risk situation.
Mashel III Cost Amendment Memo 3 | P a g e
Funding Request Table
Source Original Proposed
RCO Grant Agreement $1,190,000 $1,370,000
Sponsor Match $210,060 $295,000
Sponsor Non-match $45,250
Total: $1,400,060 $1,665,000
Supporting Attachments in PRISM:
• Preliminary Design
• Cost Estimate
• Model Output: “Mashel River Reach 7 Alternative 2 Water Surface Elevation (WSE)
Differences for 100-year Flood Event”
• “Mashel River Reach 7 Landslide Geomorphic Assessment”
• “Seismic Refraction Survey Report” (geophysical survey of subsurface conditions near
the proposed ELJs and along the lower half of the landslide.

More Related Content

What's hot

Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportHonolulu Civil Beat
 
Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...
Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...
Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...Fairfax County
 
IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16Graeme Donaldson
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christijeshaml10
 
Finding Balance Between Regulation, Management and Property Rights in the Cen...
Finding Balance Between Regulation, Management and Property Rights in the Cen...Finding Balance Between Regulation, Management and Property Rights in the Cen...
Finding Balance Between Regulation, Management and Property Rights in the Cen...The Texas Network, LLC
 
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...The Piedmont Environmental Council
 

What's hot (20)

Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
 
Wp mp-update-col riverconvey-april_25_2013
Wp   mp-update-col riverconvey-april_25_2013Wp   mp-update-col riverconvey-april_25_2013
Wp mp-update-col riverconvey-april_25_2013
 
Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...
Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...
Request to Use Draft Embark Land Use (BRT Scenario) in the Regional Cooperati...
 
Fort Bragg, NC
Fort Bragg, NCFort Bragg, NC
Fort Bragg, NC
 
Moore
MooreMoore
Moore
 
San Antonio Vista Ridge Project
San Antonio Vista Ridge ProjectSan Antonio Vista Ridge Project
San Antonio Vista Ridge Project
 
December 9, 2010
December 9, 2010December 9, 2010
December 9, 2010
 
Wp special master-plan[071113]
Wp special master-plan[071113]Wp special master-plan[071113]
Wp special master-plan[071113]
 
Master Plan
Master PlanMaster Plan
Master Plan
 
January 10, 2013
January 10, 2013January 10, 2013
January 10, 2013
 
Final master plan - wp workshop 5-16-13
Final   master plan - wp workshop 5-16-13Final   master plan - wp workshop 5-16-13
Final master plan - wp workshop 5-16-13
 
IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christi
 
Puducherry
Puducherry Puducherry
Puducherry
 
Wp [final]master plan may 16 workshop summary
Wp   [final]master plan may 16 workshop summaryWp   [final]master plan may 16 workshop summary
Wp [final]master plan may 16 workshop summary
 
DOPWIC Program Year 2018 Applicant Workshop
DOPWIC Program Year 2018 Applicant WorkshopDOPWIC Program Year 2018 Applicant Workshop
DOPWIC Program Year 2018 Applicant Workshop
 
316b Booklet for S&L
316b Booklet for S&L316b Booklet for S&L
316b Booklet for S&L
 
Finding Balance Between Regulation, Management and Property Rights in the Cen...
Finding Balance Between Regulation, Management and Property Rights in the Cen...Finding Balance Between Regulation, Management and Property Rights in the Cen...
Finding Balance Between Regulation, Management and Property Rights in the Cen...
 
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
 
Bill mullican
Bill mullicanBill mullican
Bill mullican
 

Viewers also liked

Viewers also liked (9)

Nisqually Thin Project
Nisqually Thin ProjectNisqually Thin Project
Nisqually Thin Project
 
Nisqually River Council
Nisqually River CouncilNisqually River Council
Nisqually River Council
 
Salmon Recovery Funding Board - 2010 Proposals
Salmon Recovery Funding Board - 2010 ProposalsSalmon Recovery Funding Board - 2010 Proposals
Salmon Recovery Funding Board - 2010 Proposals
 
Producer Responsibility: A Tool to Manage Toxic Garbage
Producer Responsibility: A Tool to Manage Toxic GarbageProducer Responsibility: A Tool to Manage Toxic Garbage
Producer Responsibility: A Tool to Manage Toxic Garbage
 
Benthic Trawl Studies in the South Sound: 1987 vs. 2014/2015
Benthic Trawl Studies in the South Sound: 1987 vs. 2014/2015Benthic Trawl Studies in the South Sound: 1987 vs. 2014/2015
Benthic Trawl Studies in the South Sound: 1987 vs. 2014/2015
 
Wolf Conservation and Management Plan
Wolf Conservation and Management PlanWolf Conservation and Management Plan
Wolf Conservation and Management Plan
 
Amendment Requests for Whitewater Reach Protection Project
Amendment Requests for Whitewater Reach Protection ProjectAmendment Requests for Whitewater Reach Protection Project
Amendment Requests for Whitewater Reach Protection Project
 
Nisqually River Foundation
Nisqually River FoundationNisqually River Foundation
Nisqually River Foundation
 
Wolf Haven International
Wolf Haven InternationalWolf Haven International
Wolf Haven International
 

Similar to Mashel III Cost Amendment Request

Public meeting # 1 for website
Public meeting # 1   for websitePublic meeting # 1   for website
Public meeting # 1 for websitepixellence
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)Sunil Satish
 
San Jose Water Company Letter 506
San Jose Water Company Letter 506San Jose Water Company Letter 506
San Jose Water Company Letter 506Rishi Kumar
 
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Fairfax County
 
2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bond2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bondF. X. Flinn
 
Water-Resources-ZBR-Report-PFC2016-0660
Water-Resources-ZBR-Report-PFC2016-0660Water-Resources-ZBR-Report-PFC2016-0660
Water-Resources-ZBR-Report-PFC2016-0660John Carty
 
Executive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsExecutive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsRiverFirst Initiative
 
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...Harry Black
 
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdfPasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdfABLoveria
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentationSCVTA
 
2017 general assembly guide.docx
2017 general assembly guide.docx2017 general assembly guide.docx
2017 general assembly guide.docxSOPEC
 
Alamo Heights Council Meeting 04.08.19 Agenda Item #6 ppt AH Pool Engineer
Alamo Heights Council Meeting 04.08.19 Agenda Item #6  ppt AH Pool EngineerAlamo Heights Council Meeting 04.08.19 Agenda Item #6  ppt AH Pool Engineer
Alamo Heights Council Meeting 04.08.19 Agenda Item #6 ppt AH Pool Engineerahcitycouncil
 
Harbour Redevlopment - Town Hall - 2016-02-27
Harbour Redevlopment - Town Hall - 2016-02-27Harbour Redevlopment - Town Hall - 2016-02-27
Harbour Redevlopment - Town Hall - 2016-02-27kingstonyc
 
Euclid integrated planning opportunity rev12
Euclid integrated planning opportunity rev12Euclid integrated planning opportunity rev12
Euclid integrated planning opportunity rev12Kelly Quinn Sands
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16Tim Bail
 
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationPublic Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationAGC of California
 
Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)AGC of California
 
Item # 6 - Freese & Nichols Normandy Storm Drain
Item # 6 - Freese & Nichols Normandy Storm DrainItem # 6 - Freese & Nichols Normandy Storm Drain
Item # 6 - Freese & Nichols Normandy Storm Drainahcitycouncil
 
DOE PSH RFI Reponses
DOE PSH RFI ReponsesDOE PSH RFI Reponses
DOE PSH RFI ReponsesNate Sandvig
 

Similar to Mashel III Cost Amendment Request (20)

Public meeting # 1 for website
Public meeting # 1   for websitePublic meeting # 1   for website
Public meeting # 1 for website
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)
 
San Jose Water Company Letter 506
San Jose Water Company Letter 506San Jose Water Company Letter 506
San Jose Water Company Letter 506
 
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
 
2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bond2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bond
 
Water-Resources-ZBR-Report-PFC2016-0660
Water-Resources-ZBR-Report-PFC2016-0660Water-Resources-ZBR-Report-PFC2016-0660
Water-Resources-ZBR-Report-PFC2016-0660
 
Executive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsExecutive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next Steps
 
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
City of Cincinnati Capital Acceleration Plan Presentation 012716 final [compa...
 
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdfPasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentation
 
2017 general assembly guide.docx
2017 general assembly guide.docx2017 general assembly guide.docx
2017 general assembly guide.docx
 
Alamo Heights Council Meeting 04.08.19 Agenda Item #6 ppt AH Pool Engineer
Alamo Heights Council Meeting 04.08.19 Agenda Item #6  ppt AH Pool EngineerAlamo Heights Council Meeting 04.08.19 Agenda Item #6  ppt AH Pool Engineer
Alamo Heights Council Meeting 04.08.19 Agenda Item #6 ppt AH Pool Engineer
 
Harbour Redevlopment - Town Hall - 2016-02-27
Harbour Redevlopment - Town Hall - 2016-02-27Harbour Redevlopment - Town Hall - 2016-02-27
Harbour Redevlopment - Town Hall - 2016-02-27
 
Euclid integrated planning opportunity rev12
Euclid integrated planning opportunity rev12Euclid integrated planning opportunity rev12
Euclid integrated planning opportunity rev12
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16
 
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationPublic Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
 
Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)
 
Item # 6 - Freese & Nichols Normandy Storm Drain
Item # 6 - Freese & Nichols Normandy Storm DrainItem # 6 - Freese & Nichols Normandy Storm Drain
Item # 6 - Freese & Nichols Normandy Storm Drain
 
DOPWIC Program Year 2019 Applicant Workshop
DOPWIC Program Year 2019 Applicant WorkshopDOPWIC Program Year 2019 Applicant Workshop
DOPWIC Program Year 2019 Applicant Workshop
 
DOE PSH RFI Reponses
DOE PSH RFI ReponsesDOE PSH RFI Reponses
DOE PSH RFI Reponses
 

More from Nisqually River Council

Nisqually Watershed Stewardship Report 8.16.19
Nisqually Watershed Stewardship Report 8.16.19Nisqually Watershed Stewardship Report 8.16.19
Nisqually Watershed Stewardship Report 8.16.19Nisqually River Council
 
Nisqually River Education Project - NOAA ELG Presentation 2019
Nisqually River Education Project - NOAA ELG Presentation 2019Nisqually River Education Project - NOAA ELG Presentation 2019
Nisqually River Education Project - NOAA ELG Presentation 2019Nisqually River Council
 
Dynamic Habitat Models for Estuary-Dependent Species
Dynamic Habitat Models for Estuary-Dependent SpeciesDynamic Habitat Models for Estuary-Dependent Species
Dynamic Habitat Models for Estuary-Dependent SpeciesNisqually River Council
 
Nisqually Watershed Management Plan 2019 Addendum - Appendices
Nisqually Watershed Management Plan 2019 Addendum - AppendicesNisqually Watershed Management Plan 2019 Addendum - Appendices
Nisqually Watershed Management Plan 2019 Addendum - AppendicesNisqually River Council
 
Nisqually Watershed Management Plan 2019 Addendum - Figures
Nisqually Watershed Management Plan 2019 Addendum - FiguresNisqually Watershed Management Plan 2019 Addendum - Figures
Nisqually Watershed Management Plan 2019 Addendum - FiguresNisqually River Council
 
Nisqually Watershed Management Plan 2019 Addendum
Nisqually Watershed Management Plan 2019 Addendum Nisqually Watershed Management Plan 2019 Addendum
Nisqually Watershed Management Plan 2019 Addendum Nisqually River Council
 
2018 Nisqually Water Planning Unit Working Agreement
2018 Nisqually Water Planning Unit Working Agreement2018 Nisqually Water Planning Unit Working Agreement
2018 Nisqually Water Planning Unit Working AgreementNisqually River Council
 
Evaluating Biodiversity in the Salish Sea at Two Levels
Evaluating Biodiversity in the Salish Sea at Two LevelsEvaluating Biodiversity in the Salish Sea at Two Levels
Evaluating Biodiversity in the Salish Sea at Two LevelsNisqually River Council
 
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft Presentation
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft PresentationNisqually Watershed Stewardship Plan: Status Report 2018 Draft Presentation
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft PresentationNisqually River Council
 
Nisqually Indian Tribe Food Sovereignty Assessment
Nisqually Indian Tribe Food Sovereignty AssessmentNisqually Indian Tribe Food Sovereignty Assessment
Nisqually Indian Tribe Food Sovereignty AssessmentNisqually River Council
 

More from Nisqually River Council (20)

Yil Me Hu Summer 2022
Yil Me Hu Summer 2022Yil Me Hu Summer 2022
Yil Me Hu Summer 2022
 
Yil Me Hu Winter 2021
Yil Me Hu Winter 2021Yil Me Hu Winter 2021
Yil Me Hu Winter 2021
 
I-5 Study Report 2020
I-5 Study Report 2020I-5 Study Report 2020
I-5 Study Report 2020
 
Nisqually Watershed Stewardship Report 8.16.19
Nisqually Watershed Stewardship Report 8.16.19Nisqually Watershed Stewardship Report 8.16.19
Nisqually Watershed Stewardship Report 8.16.19
 
Nisqually River Education Project - NOAA ELG Presentation 2019
Nisqually River Education Project - NOAA ELG Presentation 2019Nisqually River Education Project - NOAA ELG Presentation 2019
Nisqually River Education Project - NOAA ELG Presentation 2019
 
Kayak Nisqually
Kayak Nisqually Kayak Nisqually
Kayak Nisqually
 
Dynamic Habitat Models for Estuary-Dependent Species
Dynamic Habitat Models for Estuary-Dependent SpeciesDynamic Habitat Models for Estuary-Dependent Species
Dynamic Habitat Models for Estuary-Dependent Species
 
Tacoma Metro Parks Public Engagement
Tacoma Metro Parks Public EngagementTacoma Metro Parks Public Engagement
Tacoma Metro Parks Public Engagement
 
Nisqually Watershed Management Plan 2019 Addendum - Appendices
Nisqually Watershed Management Plan 2019 Addendum - AppendicesNisqually Watershed Management Plan 2019 Addendum - Appendices
Nisqually Watershed Management Plan 2019 Addendum - Appendices
 
Nisqually Watershed Management Plan 2019 Addendum - Figures
Nisqually Watershed Management Plan 2019 Addendum - FiguresNisqually Watershed Management Plan 2019 Addendum - Figures
Nisqually Watershed Management Plan 2019 Addendum - Figures
 
Nisqually Watershed Management Plan 2019 Addendum
Nisqually Watershed Management Plan 2019 Addendum Nisqually Watershed Management Plan 2019 Addendum
Nisqually Watershed Management Plan 2019 Addendum
 
2018 Nisqually Water Planning Unit Working Agreement
2018 Nisqually Water Planning Unit Working Agreement2018 Nisqually Water Planning Unit Working Agreement
2018 Nisqually Water Planning Unit Working Agreement
 
Yil Me Hu Winter 2018-19
Yil Me Hu Winter 2018-19Yil Me Hu Winter 2018-19
Yil Me Hu Winter 2018-19
 
Remembering Medicine Creek
Remembering Medicine CreekRemembering Medicine Creek
Remembering Medicine Creek
 
Evaluating Biodiversity in the Salish Sea at Two Levels
Evaluating Biodiversity in the Salish Sea at Two LevelsEvaluating Biodiversity in the Salish Sea at Two Levels
Evaluating Biodiversity in the Salish Sea at Two Levels
 
Nisqually Stream Stewards Map 2018
Nisqually Stream Stewards Map 2018Nisqually Stream Stewards Map 2018
Nisqually Stream Stewards Map 2018
 
2018 SRFB PSAR Project Ranked List
2018 SRFB PSAR Project Ranked List2018 SRFB PSAR Project Ranked List
2018 SRFB PSAR Project Ranked List
 
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft Presentation
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft PresentationNisqually Watershed Stewardship Plan: Status Report 2018 Draft Presentation
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft Presentation
 
2018 SRFB PSAR Project List for
2018 SRFB PSAR Project List for2018 SRFB PSAR Project List for
2018 SRFB PSAR Project List for
 
Nisqually Indian Tribe Food Sovereignty Assessment
Nisqually Indian Tribe Food Sovereignty AssessmentNisqually Indian Tribe Food Sovereignty Assessment
Nisqually Indian Tribe Food Sovereignty Assessment
 

Recently uploaded

(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书mbetknu
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxHenryBriggs2
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证mbetknu
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012rehmti665
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urgesnarwatsonia7
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.pptsilvialandin2
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…nishakur201
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Christina Parmionova
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhellokittymaearciaga
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...narwatsonia7
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...narwatsonia7
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...Christina Parmionova
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Servicenarwatsonia7
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26JSchaus & Associates
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageTechSoup
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...narwatsonia7
 

Recently uploaded (20)

(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptx
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptx
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized Storage
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
 

Mashel III Cost Amendment Request

  • 1. Mashel III Cost Amendment Memo 1 | P a g e Memorandum Subject: SRFB Cost Amendment Request PROJECT: 15-1231 RST, MASHEL EATONVILLE RESTORATION PHASE III To: Ashley Von Essen (WRIA 11 LE Coordinator) and Elizabeth Butler (RCO) From: Brian Combs, SPSSEG Date: August 24, 2016 Request Summary: South Puget Sound Salmon Enhancement Group (SPSSEG) is requesting a $180,000 cost increase for the Mashel Eatonville Restoration Phase III Project (the project) to afford:  habitat design improvements (described below)  changes resulting from the SRFB review panel comment process  additional road access needs  project planting, and  higher construction costs resulting from recent industry economic trends. Additional NWIFC PCSRF matching funds in the amount of $110,000 are being provided by the Nisqually Indian Tribe to contribute to the additional costs and to meet the additional match need. Background: An earlier Preliminary Design was completed for the project in 2009. The project was selected for advancement in 2015 and was ranked as a high priority within the watershed. During the Review Panel site visit in 2015 several requests were made by the Panel to address possible project improvements. These requests included looking at armor removal to allow broader channel migration, addressing the need for side channel improvements, further analysis of the landslide, and addressing general design improvements. An initial project budget was submitted with the grant application which relied on an estimate of project needs and projected costs at that time however an additional funding need was identified during the Preliminary Design stage which has led to this amendment request. This project represents the third phase of reach-scale treatments within the Mashel River. The proposed restoration measures for the project site (Reach 7) include the construction of several Engineered Log Jams (ELJ’s) and Large Woody Debris elements (LWD), side channel activation, armor removal, and re-vegetation. This project and previous phases were identified in the 2004 assessment by Watershed Professionals Network which provided the restoration prescription for multiple reaches. The Nisqually Chinook Recovery Plan identified the Mashel River as a high priority for restoration (specifically improving habitat complexity) because of its
  • 2. Mashel III Cost Amendment Memo 2 | P a g e importance for life history diversity. In the draft Nisqually Steelhead Recovery Plan, the Mashel River ranked highest for restoration, overall, followed by the Nisqually River mainstem, when considering abundance and productivity. The additional estimated costs are associated with the following elements:  Rip-rap armor removal to allow better channel migration (requested by the Review Panel). Modelling and design work enabled us to see a pathway for adding this element however a flood containment berm is needed to reduce flood risk.  Flood containment berm: this is needed to reduce flood risk resulting from the rip-rap armor removal.  Improved LWD elements: the type and location of the ELJ’s and LWD has been updated to maximize habitat gain. These concepts were “approved” by the review panel during the preliminary-concept discussion.  As-built survey: this was accidentally not included in the initial cost estimate.  Updated planting costs for 6 acres of floodplain planting and ELJ planting.  Updated road access costs: these costs include road improvements needed to access the site from the north access and/or improvements to the existing south access.  2016-17 dollars: The overall cost estimate was updated to reflect current economic conditions, which have changed in the last two years with increased economic activity (i.e. costs have gone up). To provide context, SPSSEG has received “high” bids on three projects in 2016 and reports from our partners indicate that in general bids are going up with the increased economic activity seen across the region. Thus, cost estimates from even one or two years ago may now be inaccurate. Match: The Nisqually Indian Tribe is providing an additional $110,000 in PCSRF funds (to be awarded through the NWIFC) and $10,000 of in-kind match to supplement the requested SRFB funds. These additional matching funds will exceed the original 15% commitment and fully fund the estimate of construction costs. Based on the current estimate, the project will also have a leverage surplus of $45,250 beyond the required match. Timing: The project was initially slated for construction in 2016 however it was delayed in order to finish the design work, geo-physical assessments, modelling, and planning. Currently the project is slated for construction in 2017. Considerable progress has been made in developing the project and with Preliminary Designs now complete, the 2017 construction time frame should be achievable. Delaying the project further could lead to additional cost increases resulting from changing economic trends and the prolonged costs of managing the project. It would be incredibly inefficient to put the construction on hold only to be at the mercy of the bidding environment in 2018 or beyond. The requested $180,000 has been approved by the Lead Entity Work Group which has made room for this amendment in their annual planning. Funding availability could decrease in subsequent years as the watershed priorities and funding allotments change. As such, we feel confident that approving this cost amendment now is reasonable and allows for a high chance of project success. Delaying the project would lead to a higher risk situation.
  • 3. Mashel III Cost Amendment Memo 3 | P a g e Funding Request Table Source Original Proposed RCO Grant Agreement $1,190,000 $1,370,000 Sponsor Match $210,060 $295,000 Sponsor Non-match $45,250 Total: $1,400,060 $1,665,000 Supporting Attachments in PRISM: • Preliminary Design • Cost Estimate • Model Output: “Mashel River Reach 7 Alternative 2 Water Surface Elevation (WSE) Differences for 100-year Flood Event” • “Mashel River Reach 7 Landslide Geomorphic Assessment” • “Seismic Refraction Survey Report” (geophysical survey of subsurface conditions near the proposed ELJs and along the lower half of the landslide.