SlideShare a Scribd company logo
1 of 7
Download to read offline
PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date JANUARY 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
PREPARED BY:
……………………………………….
HASNIZAM MD SAAD
SAFETY & HEALTH OFFICER
REVIEW BY:
……………………………….
MOHD SYAFIQ EZZUDDIN
MANAGER ESH
APPROVE BY:
…………………………………….
LEE JUIN LIAN
SR PROJECT MANAGER
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
Design of Formwork Structure
1. All formwork structures (including but not limited to beam, slab, wall, column, Cantilevered,
curved and sloped formwork) shall be capable of withstanding the total dead Load, live load and
impact load imposed on it with a minimum safety factor.
2. A Professional Engineer shall be engaged to design a formwork structure that is:
a. supporting a slab or beam to be cast that is greater than 300 mm thick;
b. greater than 9 m in height; or
c. Constructed in 2 or more tiers. (Annex A)
3. The Professional Engineer who designs the formwork structure shall take, so far as is Reasonably
practicable, such measures to ensure that his design can be executed safely by Any person who
constructs or uses the formwork structure according to his design.
4. The Professional Engineer’s design should include the following considerations, but not limited to:-
a. Vertical and horizontal formwork components;
b. Bracing members; Connections; and
c. Support on which the formwork rest.
5. The formwork design should encompass all sides, corners and bends supporting the Concrete
to be cast. Bracing and coupling details should be provided in the design to ensure Clarity. (Annex
B)
6. The Professional Engineer who designs the formwork shall also provide to any Person
constructing the formwork structure all design documentation, including all relevant Calculations,
drawings and construction (erecting, dismantling and reshoring) procedures to Facilitate the proper
construction and dismantling of the formwork structure according to his Design.
7. The drawings of the formwork structure should also include the safe means of Access and
escape routes for workers involved with the formwork structure. These should be clearly shown on
the drawing plan.
SAFE OPERATING PROCEDURE
PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date JANUARY 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
PREPARED BY:
……………………………………….
HASNIZAM MD SAAD
SAFETY & HEALTH OFFICER
REVIEW BY:
……………………………….
MOHD SYAFIQ EZZUDDIN
MANAGER ESH
APPROVE BY:
…………………………………….
LEE JUIN LIAN
SR PROJECT MANAGER
Erection of Formwork Structure
1. The Occupier shall ensure that every formwork structure shall
a. be of sound material, good construction and adequate strength;
b. be free from patent defect;
c. be suitable and safe for the purpose for which it is intended; and
d. be properly braced or tied together so as to maintain position and shape.
2. Formwork components used to erect the formwork structure shall be of good condition and
free from corrosion. Steel formwork structures should be galvanized for
Corrosion protection and not painted. (Annex C)
3. As the structural capacity of the formwork structure is expected to be reduced over time, for
example due to corrosion, Occupiers may consider, as an additional safety precautionary
measure, conduct a load test (in the testing laboratory) to verify the design assumptions of
the strength of the formwork structure and their supporting bases, especially for casting of
significant structures.
4. Couplers used for bracing and tying the formwork structure together shall be fit-for purpose, ie.
Right-angled couplers used for perpendicular members and swivel couplers used for bracing. Using
the wrong components could reduce the structural capacity of the formwork structure. (Annex
D)
5. Responsible persons shall establish and implement a Fall Prevention Plan to ensure that their
workers who are erecting and dismantling formwork structures are prevented from falling from
height. Measures may include provisions of safe work platforms with proper guard-rails and
personal fall arrest system, complete with safe and secure anchorages.
6. Where it is a requirement for a Professional Engineer to design a formwork structure, the formwork
structure shall be constructed in accordance with the design and drawings of the Professional
Engineer.
7. No alteration shall be made or allowed to be made to a formwork structure designed by the
Professional Engineer unless its design and drawings have been reviewed and endorsed by a
Professional Engineer.
8. After erection, the Professional Engineer appointed by the Occupier to oversee the construction of
the formwork structure, shall take so far as is reasonably practicable, such measures as are
necessary to ensure that the formwork structure is constructed in accordance with the design of
the Professional Engineer who designed it.
PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date JANUARY 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
PREPARED BY:
……………………………………….
HASNIZAM MD SAAD
SAFETY & HEALTH OFFICER
REVIEW BY:
……………………………….
MOHD SYAFIQ EZZUDDIN
MANAGER ESH
APPROVE BY:
…………………………………….
LEE JUIN LIAN
SR PROJECT MANAGER
Concreting
1. Every responsible person undertaking any work including erecting/dismantling the formwork
structure, installing steel reinforcement or concreting works is reminded to conduct a thorough risk
assessment on his work processes and implement the necessary preventive measures to ensure
that his undertaking can be and is carried out safely.
2. Formwork structures are to have suitable edge protection to prevent formwork and concreting
workers from falling from height. Measures to prevent falling from height as highlighted in the Fall
Prevention Plan are to be implemented.
3. Where a formwork structure is designed by a Professional Engineer, placement of concrete
shall not commence unless the formwork structure, including any alteration thereto, has been
inspected and certified safe for its intended use by a Professional Engineer.
4. During concreting, the formwork system should be regularly monitored by the formwork
supervisor for movement, stability and soundness. The formwork supervisor and any other workers
should not work under or in close vicinity of the formwork structure while the pouring of concrete
is in progress. Proper risk assessment shall be conducted to ensure that the formwork supervisor
watching the formwork is not exposed to the risk from formwork structure collapse.
5. If, during concreting, any weakness develops and the formwork shows any undue settlement
or distortion, all work shall be stopped immediately. Prior to the commencement of any
adjustment, strengthening or repair works, a thorough assessment of risk shall be conducted
and all necessary measures to be taken to ensure that workers will not be exposed to risks
from formwork structure collapse. Dismantling of Formwork Structure.
6. A formwork structure should only be dismantled after the concrete has sufficiently set and after a
period of time as determined by the Qualified Person (Design).
7. The manner of dismantling a formwork structure should be in accordance to the Professional
Engineer’s dismantling procedures, taking into account that the formwork structure could be
unstable during dismantling.
PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date JANUARY 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
PREPARED BY:
……………………………………….
HASNIZAM MD SAAD
SAFETY & HEALTH OFFICER
REVIEW BY:
……………………………….
MOHD SYAFIQ EZZUDDIN
MANAGER ESH
APPROVE BY:
…………………………………….
LEE JUIN LIAN
SR PROJECT MANAGER
PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date JANUARY 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
PREPARED BY:
……………………………………….
HASNIZAM MD SAAD
SAFETY & HEALTH OFFICER
REVIEW BY:
……………………………….
MOHD SYAFIQ EZZUDDIN
MANAGER ESH
APPROVE BY:
…………………………………….
LEE JUIN LIAN
SR PROJECT MANAGER
PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date JANUARY 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
PREPARED BY:
……………………………………….
HASNIZAM MD SAAD
SAFETY & HEALTH OFFICER
REVIEW BY:
……………………………….
MOHD SYAFIQ EZZUDDIN
MANAGER ESH
APPROVE BY:
…………………………………….
LEE JUIN LIAN
SR PROJECT MANAGER
PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date JANUARY 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
PREPARED BY:
……………………………………….
HASNIZAM MD SAAD
SAFETY & HEALTH OFFICER
REVIEW BY:
……………………………….
MOHD SYAFIQ EZZUDDIN
MANAGER ESH
APPROVE BY:
…………………………………….
LEE JUIN LIAN
SR PROJECT MANAGER

More Related Content

What's hot

17 traffic operations working on live roads risk assessment templates
17 traffic operations   working on live roads risk assessment templates17 traffic operations   working on live roads risk assessment templates
17 traffic operations working on live roads risk assessment templatesDwarika Bhushan Sharma
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolitionManthan Vaghasiya
 
Lifting plan
Lifting planLifting plan
Lifting plantnsv22
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingWilliam York
 
Construction safety lecture-3
Construction safety  lecture-3Construction safety  lecture-3
Construction safety lecture-3Saleem Malik
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015John Newquist
 
Cause of accident and prevention in construction industry
Cause of accident and prevention in construction industryCause of accident and prevention in construction industry
Cause of accident and prevention in construction industryYASMINE HASLAN
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templatesDwarika Bhushan Sharma
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputGaurav Singh Rajput
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPTLuke D'Arcy
 
HSE construction waste management plan
HSE construction waste management planHSE construction waste management plan
HSE construction waste management planDwarika Bhushan Sharma
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations Amol Pawar
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templatesDwarika Bhushan Sharma
 
Rebar cutting hazards
Rebar cutting hazardsRebar cutting hazards
Rebar cutting hazardsconstruction
 
Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1Dwarika Bhushan Sharma
 

What's hot (20)

17 traffic operations working on live roads risk assessment templates
17 traffic operations   working on live roads risk assessment templates17 traffic operations   working on live roads risk assessment templates
17 traffic operations working on live roads risk assessment templates
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety Training
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Construction Safety Training
Construction Safety TrainingConstruction Safety Training
Construction Safety Training
 
Construction safety lecture-3
Construction safety  lecture-3Construction safety  lecture-3
Construction safety lecture-3
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015
 
Cause of accident and prevention in construction industry
Cause of accident and prevention in construction industryCause of accident and prevention in construction industry
Cause of accident and prevention in construction industry
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPT
 
HSE construction waste management plan
HSE construction waste management planHSE construction waste management plan
HSE construction waste management plan
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 
Rebar cutting hazards
Rebar cutting hazardsRebar cutting hazards
Rebar cutting hazards
 
Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1
 

Similar to Formwork Safety Procedures

En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17bert vanden eynde
 
ROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdf
ROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdfROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdf
ROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdfLuisRequenaFarfan
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015HaGun Gunawan
 
Steel building-erection-manual
Steel building-erection-manualSteel building-erection-manual
Steel building-erection-manualPradipat Bubpachat
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docxKaty A. Beitia G.
 
Management science
Management scienceManagement science
Management sciencew ss
 
Erection method statement
Erection method statementErection method statement
Erection method statementkanalbiru
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Motorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project ReportMotorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project ReportOlusegun. B Adekoya
 
Lifting approval and permit to-work
Lifting approval and permit to-workLifting approval and permit to-work
Lifting approval and permit to-workHASNIZAM BIN MD SAAD
 
Design and analysis of jig and welding fixture
Design and analysis of jig and welding fixtureDesign and analysis of jig and welding fixture
Design and analysis of jig and welding fixturesagmech24
 
Zeonn Koh 4 page CV
Zeonn Koh 4 page CVZeonn Koh 4 page CV
Zeonn Koh 4 page CVZeonn Koh
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxalutarep1
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxalutarep1
 
Resume for Schane Schuh
Resume for Schane SchuhResume for Schane Schuh
Resume for Schane SchuhSchane Schuh
 

Similar to Formwork Safety Procedures (20)

Duties lifting supervisors
Duties lifting supervisorsDuties lifting supervisors
Duties lifting supervisors
 
En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17
 
ROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdf
ROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdfROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdf
ROSALES_LUIS_Y_VILCHEZ_DANTE_SEGURIDAD_SALUD_OBRA_CONSTRUCCION.pdf
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
 
Steel building-erection-manual
Steel building-erection-manualSteel building-erection-manual
Steel building-erection-manual
 
Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
 
Management science
Management scienceManagement science
Management science
 
Erection method statement
Erection method statementErection method statement
Erection method statement
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Motorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project ReportMotorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project Report
 
Lifting approval and permit to-work
Lifting approval and permit to-workLifting approval and permit to-work
Lifting approval and permit to-work
 
Detailed engineering-design-phase
Detailed engineering-design-phaseDetailed engineering-design-phase
Detailed engineering-design-phase
 
Birhanu
BirhanuBirhanu
Birhanu
 
tm13_project2
tm13_project2tm13_project2
tm13_project2
 
Design and analysis of jig and welding fixture
Design and analysis of jig and welding fixtureDesign and analysis of jig and welding fixture
Design and analysis of jig and welding fixture
 
Zeonn Koh 4 page CV
Zeonn Koh 4 page CVZeonn Koh 4 page CV
Zeonn Koh 4 page CV
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
Resume for Schane Schuh
Resume for Schane SchuhResume for Schane Schuh
Resume for Schane Schuh
 

More from HASNIZAM BIN MD SAAD (20)

SHASSIC KV.pdf
SHASSIC KV.pdfSHASSIC KV.pdf
SHASSIC KV.pdf
 
KV Segamat SHASSIC.pdf
KV Segamat SHASSIC.pdfKV Segamat SHASSIC.pdf
KV Segamat SHASSIC.pdf
 
Machinery Inspection.pdf
Machinery Inspection.pdfMachinery Inspection.pdf
Machinery Inspection.pdf
 
HASNIZAM SHASSIC CIS 10 2020 (CIDB).pdf
HASNIZAM SHASSIC CIS 10 2020 (CIDB).pdfHASNIZAM SHASSIC CIS 10 2020 (CIDB).pdf
HASNIZAM SHASSIC CIS 10 2020 (CIDB).pdf
 
SHASSIC HASNIZAM.pdf
SHASSIC HASNIZAM.pdfSHASSIC HASNIZAM.pdf
SHASSIC HASNIZAM.pdf
 
Latihan Asas Pengawal Bendera
 Latihan Asas Pengawal Bendera Latihan Asas Pengawal Bendera
Latihan Asas Pengawal Bendera
 
Heat Stroke
Heat StrokeHeat Stroke
Heat Stroke
 
HEALTH EFFECTS OF CIGARETTE SMOKING.pdf
HEALTH EFFECTS OF CIGARETTE SMOKING.pdfHEALTH EFFECTS OF CIGARETTE SMOKING.pdf
HEALTH EFFECTS OF CIGARETTE SMOKING.pdf
 
SHASSIC CIS 10 2020
SHASSIC CIS 10 2020SHASSIC CIS 10 2020
SHASSIC CIS 10 2020
 
Standard Industri Pembinaan cis 10 2020
Standard Industri Pembinaan cis 10 2020Standard Industri Pembinaan cis 10 2020
Standard Industri Pembinaan cis 10 2020
 
Handbook for rigger signalman hasnizam
Handbook for rigger signalman hasnizamHandbook for rigger signalman hasnizam
Handbook for rigger signalman hasnizam
 
SHASSIC CIS 10 : 2018
SHASSIC CIS 10 : 2018SHASSIC CIS 10 : 2018
SHASSIC CIS 10 : 2018
 
Sila pakai topeng muka
Sila pakai topeng mukaSila pakai topeng muka
Sila pakai topeng muka
 
Prosidur standard operasi (sop) kebenaran pkp
Prosidur standard operasi (sop) kebenaran pkpProsidur standard operasi (sop) kebenaran pkp
Prosidur standard operasi (sop) kebenaran pkp
 
Garispanduan pkp pembinaan
Garispanduan pkp pembinaanGarispanduan pkp pembinaan
Garispanduan pkp pembinaan
 
Covid 19 guidance for the workplace
Covid 19 guidance for the workplaceCovid 19 guidance for the workplace
Covid 19 guidance for the workplace
 
Sohelp
SohelpSohelp
Sohelp
 
Working at height
Working at heightWorking at height
Working at height
 
Mrcb forklift training
Mrcb forklift trainingMrcb forklift training
Mrcb forklift training
 
Lifting using excavator
Lifting using excavatorLifting using excavator
Lifting using excavator
 

Recently uploaded

Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 

Recently uploaded (20)

Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 

Formwork Safety Procedures

  • 1. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2 TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1) Doc. No. SUKE/CA2/ESH/SOP/01 Rev. No. 0 Rev. Date JANUARY 2020 SAFE OPERATING PROCEDURE _______________________________________________________________________________ MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T) PREPARED BY: ………………………………………. HASNIZAM MD SAAD SAFETY & HEALTH OFFICER REVIEW BY: ………………………………. MOHD SYAFIQ EZZUDDIN MANAGER ESH APPROVE BY: ……………………………………. LEE JUIN LIAN SR PROJECT MANAGER SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES Design of Formwork Structure 1. All formwork structures (including but not limited to beam, slab, wall, column, Cantilevered, curved and sloped formwork) shall be capable of withstanding the total dead Load, live load and impact load imposed on it with a minimum safety factor. 2. A Professional Engineer shall be engaged to design a formwork structure that is: a. supporting a slab or beam to be cast that is greater than 300 mm thick; b. greater than 9 m in height; or c. Constructed in 2 or more tiers. (Annex A) 3. The Professional Engineer who designs the formwork structure shall take, so far as is Reasonably practicable, such measures to ensure that his design can be executed safely by Any person who constructs or uses the formwork structure according to his design. 4. The Professional Engineer’s design should include the following considerations, but not limited to:- a. Vertical and horizontal formwork components; b. Bracing members; Connections; and c. Support on which the formwork rest. 5. The formwork design should encompass all sides, corners and bends supporting the Concrete to be cast. Bracing and coupling details should be provided in the design to ensure Clarity. (Annex B) 6. The Professional Engineer who designs the formwork shall also provide to any Person constructing the formwork structure all design documentation, including all relevant Calculations, drawings and construction (erecting, dismantling and reshoring) procedures to Facilitate the proper construction and dismantling of the formwork structure according to his Design. 7. The drawings of the formwork structure should also include the safe means of Access and escape routes for workers involved with the formwork structure. These should be clearly shown on the drawing plan. SAFE OPERATING PROCEDURE
  • 2. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2 TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1) Doc. No. SUKE/CA2/ESH/SOP/01 Rev. No. 0 Rev. Date JANUARY 2020 SAFE OPERATING PROCEDURE _______________________________________________________________________________ MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T) PREPARED BY: ………………………………………. HASNIZAM MD SAAD SAFETY & HEALTH OFFICER REVIEW BY: ………………………………. MOHD SYAFIQ EZZUDDIN MANAGER ESH APPROVE BY: ……………………………………. LEE JUIN LIAN SR PROJECT MANAGER Erection of Formwork Structure 1. The Occupier shall ensure that every formwork structure shall a. be of sound material, good construction and adequate strength; b. be free from patent defect; c. be suitable and safe for the purpose for which it is intended; and d. be properly braced or tied together so as to maintain position and shape. 2. Formwork components used to erect the formwork structure shall be of good condition and free from corrosion. Steel formwork structures should be galvanized for Corrosion protection and not painted. (Annex C) 3. As the structural capacity of the formwork structure is expected to be reduced over time, for example due to corrosion, Occupiers may consider, as an additional safety precautionary measure, conduct a load test (in the testing laboratory) to verify the design assumptions of the strength of the formwork structure and their supporting bases, especially for casting of significant structures. 4. Couplers used for bracing and tying the formwork structure together shall be fit-for purpose, ie. Right-angled couplers used for perpendicular members and swivel couplers used for bracing. Using the wrong components could reduce the structural capacity of the formwork structure. (Annex D) 5. Responsible persons shall establish and implement a Fall Prevention Plan to ensure that their workers who are erecting and dismantling formwork structures are prevented from falling from height. Measures may include provisions of safe work platforms with proper guard-rails and personal fall arrest system, complete with safe and secure anchorages. 6. Where it is a requirement for a Professional Engineer to design a formwork structure, the formwork structure shall be constructed in accordance with the design and drawings of the Professional Engineer. 7. No alteration shall be made or allowed to be made to a formwork structure designed by the Professional Engineer unless its design and drawings have been reviewed and endorsed by a Professional Engineer. 8. After erection, the Professional Engineer appointed by the Occupier to oversee the construction of the formwork structure, shall take so far as is reasonably practicable, such measures as are necessary to ensure that the formwork structure is constructed in accordance with the design of the Professional Engineer who designed it.
  • 3. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2 TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1) Doc. No. SUKE/CA2/ESH/SOP/01 Rev. No. 0 Rev. Date JANUARY 2020 SAFE OPERATING PROCEDURE _______________________________________________________________________________ MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T) PREPARED BY: ………………………………………. HASNIZAM MD SAAD SAFETY & HEALTH OFFICER REVIEW BY: ………………………………. MOHD SYAFIQ EZZUDDIN MANAGER ESH APPROVE BY: ……………………………………. LEE JUIN LIAN SR PROJECT MANAGER Concreting 1. Every responsible person undertaking any work including erecting/dismantling the formwork structure, installing steel reinforcement or concreting works is reminded to conduct a thorough risk assessment on his work processes and implement the necessary preventive measures to ensure that his undertaking can be and is carried out safely. 2. Formwork structures are to have suitable edge protection to prevent formwork and concreting workers from falling from height. Measures to prevent falling from height as highlighted in the Fall Prevention Plan are to be implemented. 3. Where a formwork structure is designed by a Professional Engineer, placement of concrete shall not commence unless the formwork structure, including any alteration thereto, has been inspected and certified safe for its intended use by a Professional Engineer. 4. During concreting, the formwork system should be regularly monitored by the formwork supervisor for movement, stability and soundness. The formwork supervisor and any other workers should not work under or in close vicinity of the formwork structure while the pouring of concrete is in progress. Proper risk assessment shall be conducted to ensure that the formwork supervisor watching the formwork is not exposed to the risk from formwork structure collapse. 5. If, during concreting, any weakness develops and the formwork shows any undue settlement or distortion, all work shall be stopped immediately. Prior to the commencement of any adjustment, strengthening or repair works, a thorough assessment of risk shall be conducted and all necessary measures to be taken to ensure that workers will not be exposed to risks from formwork structure collapse. Dismantling of Formwork Structure. 6. A formwork structure should only be dismantled after the concrete has sufficiently set and after a period of time as determined by the Qualified Person (Design). 7. The manner of dismantling a formwork structure should be in accordance to the Professional Engineer’s dismantling procedures, taking into account that the formwork structure could be unstable during dismantling.
  • 4. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2 TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1) Doc. No. SUKE/CA2/ESH/SOP/01 Rev. No. 0 Rev. Date JANUARY 2020 SAFE OPERATING PROCEDURE _______________________________________________________________________________ MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T) PREPARED BY: ………………………………………. HASNIZAM MD SAAD SAFETY & HEALTH OFFICER REVIEW BY: ………………………………. MOHD SYAFIQ EZZUDDIN MANAGER ESH APPROVE BY: ……………………………………. LEE JUIN LIAN SR PROJECT MANAGER
  • 5. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2 TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1) Doc. No. SUKE/CA2/ESH/SOP/01 Rev. No. 0 Rev. Date JANUARY 2020 SAFE OPERATING PROCEDURE _______________________________________________________________________________ MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T) PREPARED BY: ………………………………………. HASNIZAM MD SAAD SAFETY & HEALTH OFFICER REVIEW BY: ………………………………. MOHD SYAFIQ EZZUDDIN MANAGER ESH APPROVE BY: ……………………………………. LEE JUIN LIAN SR PROJECT MANAGER
  • 6. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2 TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1) Doc. No. SUKE/CA2/ESH/SOP/01 Rev. No. 0 Rev. Date JANUARY 2020 SAFE OPERATING PROCEDURE _______________________________________________________________________________ MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T) PREPARED BY: ………………………………………. HASNIZAM MD SAAD SAFETY & HEALTH OFFICER REVIEW BY: ………………………………. MOHD SYAFIQ EZZUDDIN MANAGER ESH APPROVE BY: ……………………………………. LEE JUIN LIAN SR PROJECT MANAGER
  • 7. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE) : PACKAGE CA2 TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1) Doc. No. SUKE/CA2/ESH/SOP/01 Rev. No. 0 Rev. Date JANUARY 2020 SAFE OPERATING PROCEDURE _______________________________________________________________________________ MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T) PREPARED BY: ………………………………………. HASNIZAM MD SAAD SAFETY & HEALTH OFFICER REVIEW BY: ………………………………. MOHD SYAFIQ EZZUDDIN MANAGER ESH APPROVE BY: ……………………………………. LEE JUIN LIAN SR PROJECT MANAGER