SlideShare a Scribd company logo
1 of 44
Download to read offline
Good Neighbourly Relations Committee Meeting
City of Brossard: September 21, 2016
New Champlain Bridge Corridor Project
Centre communautaire Nathalie Croteau
New Champlain Bridge Corridor Project 2
Committee Members
Residents
Luis Oscar Corrales
Ginette Dufresne
Marc Gagné
Nabil Halouani
Jacques Picard
Jaime Reis
Marc Turcotte – Representative from a community organization
Éric Jutras – Member of the business community
Partners
Dan Genest – The Signature on the Saint-Laurent team
Benoît Fillion – City of Brossard
Vincent Jarry – Infrastructure Canada
New Champlain Bridge Corridor Project
1. Provide information about the work that has been
completed, is underway and planned between now and
January 2017
2. Follow up on the various files under the responsibility of
Infrastructure Canada
3. Answer questions, find potential solutions and discuss
the issues
Objectives of the Meeting
3
New Champlain Bridge Corridor Project
Agenda
4
Series Item Duration Time
1. Opening 10 min. 7:00 to 7:10 pm
2.
Work completed, underway and to come
• Eastern approach area
• Hwy-10 area
• Cable-stayed bridge area
40 min. 7:10 to 7:50 pm
3. Committee question period 20 min. 7:50 to 8:10 pm
4. Follow up on the various files under the
responsibility of Infrastructure Canada
20 min. 8:10 to 8:30 pm
5. Committee question period 10 min. 8:30 to 8:40 pm
6. Varia 10 min. 8:40 to 8:50 pm
7. General public question period 20 min. 8:50 to 9:10 pm
8. Adjournment: next meeting and topic 5 min. 9:10 to 9:15 pm
New Champlain Bridge Corridor Project
● Complex project, on many « fronts » at the same time, with an extremely tight
schedule
● Each new manufacturing and construction activity requires a normal learning
period, as well as adjustments
● First important challenge: adapt the transport strategy for the pieces coming
from Québec or from the United States
● Reduction of the risk profile
 Bridge conception almost completed
 Major procurement completed
 Manufacturing has begun
 « We are emerging from water »
● High level of public interest for the bridge construction: a very visible and public
project
Observations
5
New Champlain Bridge Corridor Project
Work Completed over the Past Few Months
New Champlain Bridge Corridor Project
• Summer season: solid work progress
on the East Approach
 Pile caisson drilling and concret
East Approach
 Installation of cofferdams and e
 Formwork and concreting of the
of pier bases
 Abutment start
• Concerns with regards to access to t
construction site and to the safety of
• Very few complaints
Overview of Completed Works
7
New Champlain Bridge Corridor Project
Complaints Handling
(April 29 to September 20, 2016)
Topic
Sector
Brossard
Closed Open Total
Noise 1 - 1
Air quality 1 1 2
Traffic - 1 1
Vibrations - - -
Brightness - - -
Other 3 1 4
Total 5 3 8
8
New Champlain Bridge Corridor Project
Main Priorities for the Upcoming Months -
South Shore
New Champlain Bridge Corridor Project
Location of Work Areas
City of Brossard
Cable-stayed
bridge
New Champlain Bridge Corridor Project
Highway 10
• Soil management
• Earthworks at the East Abutment
East Approach of the New Champlain Bridge
• Completion of the construction of footings and pier bases
• Continue the construction of the east abutment, including the building housing
the electric systems
• Beginning of installation of prefabricated segments of piers and pier caps
Cable-stayed bridge
• Construction of main pylon and rear span
South Shore
Priorities: September 2016 to January 2017
11
New Champlain Bridge Corridor Project
Description of Activity
Approximate Duration of Works
Planned Work Period
Legend: Work and Impacts
• Traffic and Public Transportation:
• Proximity of Residential Areas:
• Boating:
• Bike Paths:
Minor impact
Medium impact
Major impact
Indication by level colour code
12
New Champlain Bridge Corridor Project
Key Activities Underway and to Come -
East Approach
Design and planning underway so modifications are possible
New Champlain Bridge Corridor Project
Objective: Construction of East Approach of the new Champlain Bridge
Upcoming work:
• Completion of the forming and concreting of footings and pier bases
• Continue the construction of the abutment, including the building housing the
electric systems
• Placement of prefabricated segments of piers and pier caps
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic
are too significant
East Approach Area
14
New Champlain Bridge Corridor Project
Nov
2015
May Nov
2016
May Nov.
2017
Nov
2018
May
East Approach: Timetable
15
Feb
2016
Aug Feb
2017
Aug. Feb.
2018
Aug.
Construction of
footings and pier
bases
Installation of
piers and pier
caps
Assembly of superstructure and
deck
Finishing work
New Champlain Bridge Corridor Project
Works and Impacts: East Approach
Construction of footings and pier bases
Duration: eight months
Projected period: February to November 2016
16
17 out of 20 footings of the East
Approach were concreted, and 10 are
completed with pier bases
New Champlain Bridge Corridor Project
Works and Impacts: East Approach
Placement of prefabricated segments
of piers and pier caps
Duration: eight months
Projected period: Mid-October to Spring 2017
17
New Champlain Bridge Corridor Project
Works and Impacts: East Approach
Construction of East Abutment’s building
Duration: four months
Projected period: September to December 2016
18
New Champlain Bridge Corridor Project
Works and
Impacts: La
Riveraine Bike
Path
19
Detour of La Riveraine
bike path until the summer
of 2019
DETOUR OF
LA RIVERAINE
BIKE PATH
New Champlain Bridge Corridor Project
Works and Impacts:
East Approach Work Site Exit
20
Worker
Parking
Daily flow of traffic
• 20 heavy trucks
•150 light vehicles
Entrance
Exit
New Champlain Bridge Corridor Project
Key Activities Underway and to Come
Highway 10
Design and planning underway so modifications are possible
New Champlain Bridge Corridor Project
Highway 10 Area
22
Objective: Area reserved for soil management for the work site and preparatory
work for the reconfiguration of highway links
Upcoming work:
• Soil storage
• Earthworks at the eastern abutment
• Creation of a retaining basin for permanent drainage
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Night-time trucking from the West Approach to the East Approach
New Champlain Bridge Corridor Project
Works and Impacts: Highway 10
Soil management and creation of a retaining basin
Duration: throughout the project
Projected period: 2016 to 2019
23
New Champlain Bridge Corridor Project
Works and Impacts: Highway 10
Earthworks at the eastern abutment
Duration: one year
Projected period: April 2016 to Spring 2017
24
New Champlain Bridge Corridor Project
Key Activities Underway and to Come
Cable-stayed Bridge
Design and planning underway so modifications are possible
New Champlain Bridge Corridor Project
Cable-stayed Bridge: Timetable
26
2. Pylon foundations
October 2015 to April 20161. Jetty
August to October 2015
7. Main span
March 2017 to June 2018
3. Rear span
November 2015 to March 2017
6. Upper pylon
November 2016 to
October 2017
4. Lower pylon
May to October 2016
5. Lower crossbeam
October to December 2016
New Champlain Bridge Corridor Project
Key Activities Since the Spring of 2016
27
Two footings and pier basis of the main pylon of
cable-stayed bridge were concreted
New Champlain Bridge Corridor Project
Transportation of the First Segments
of the Main Pylon
28
1 2 3
4
1. Arrival of the segments by van at the Port
de Sorel, from St-Eugène
2. Laoding of the segments on the barge
3. The barge leaves the Port de Sorel
5 6
4. The barge arrives at the Port de Montréal
5. The winched barge is used to go up the
rapids of the Île Notre-Dame
6. Arrival of the segments at the jetty
New Champlain Bridge Corridor Project
Key Activities Since the Spring of 2016
Installation of the first prefabricated segments of
the main pylon of the cable-stayed bridge
New Champlain Bridge Corridor Project
Works and Impacts:
Seaway Bike Path
30
Ponctual and short term closings in the course of the fall
New Champlain Bridge Corridor Project
Anticipated Impacts
New Champlain Bridge Corridor Project
Anticipated impacts
• Road traffic
• Noise
• Air quality
32
New Champlain Bridge Corridor Project
Traffic
• Fall JCCBI blitz:
 September 10/11: Closed towards the South Shore
 September 17/18: Closed towards Montréal
 October 1/2: Closed towards the South Shore
 October 15/16: Closed towards Montréal
• Disruptions to come this fall
• Upcoming major disruptions for the Spring 2017:
installation of superstructure and deck above Highway
132 traffic lanes
33
Configuration – Disruptions Schedule Duration
Removal of traffic signs on Marie-Victorin Boul. (East
and West)
October 2016 2 nights
Dismantling of jerseys – Road 132 Early November 2016 1 week
Passage of pier caps pieces End November 2016 8 nights
New Champlain Bridge Corridor Project
Passage of Pier Caps Pieces
34
New Champlain Bridge Corridor Project
Steel Pier Caps
35
New Champlain Bridge Corridor Project
Passage of Pier Caps Pieces
36
New Champlain Bridge Corridor Project37
Passage des chevêtres
37
New Champlain Bridge Corridor Project 38
B1: Turenne area
B2: Voltaire area
B3: Tisserand area
Noise Management
Area
Activity
Period
J/S/N
Exposed
sensitive
area
Ambient
noise
dBA
Criterion
dBA
Estimated
noise dBA
Required
measures
Forming and concreting of
footings and pier bases J B1/B2 60/62 75 68/66 Not required
Construction
of eastern abutment
J B1/B2 60/62 75 62/66 Not required
Placement of prefabricated
segments of piers and
pier caps
J B1/B2 60/62 75 61/64 Not required
A10
Earthworks at the Eastern
Abutment
J B2 62 75 73 Monitoring
required
Cable-
stayed
Miscellaneous work J B1/B2 60/62 75 61/63 Not required
EastApproach
To comeTo comeConstruction
of building
J B2 62 75
New Champlain Bridge Corridor Project
Air Quality Management
• Migitation measures : Frequent water spaying and cleaning
• Additional measures taken after exceeding levels during the
summer of 2016 : seeding, asphalting, wheel cleaning bassins,
continuous cleaning and increased environmental surveillance
• Regulatory framework : Contractual environmental obligations and
Clean Air Regulation (CAR)
Applicable MDDELCC standards
MDDELCC CAR
PMt PM2.5
120 ug/m3 30 ug/m3
39
New Champlain Bridge Corridor Project
Follow-up on Interventions
40
SSL
• Date for the installations of anti-noise walls
City of Brossard
• State of the pavement on the detour of the La Riveraine bike path :
observations and interventions
• Extension of the anti-noise walls
Infrastructure Canada (will be discussed in the next presentation)
• GHG file
• Interactions with the REM Project
• Follow-up with the MTQ on luminosity
• Frequency of periodic revisions and acoustic studies by SSL
New Champlain Bridge Corridor Project
Next Meetings
New Champlain Bridge Corridor Project
• Good Neighbourly Relations Committee: January 25 (TBC)
 Topic: none projected
• No public information meeting is planned for the time being
Next meetings (for discussion)
42
New Champlain Bridge Corridor Project
• Newsletter: sign up online
• Information sheets delivered to residents’ homes, if required, and
notices in local newspapers
• Sign up / contact us:
 Website: www.newchamplain.ca
 Email: info@sslc.ca
 Phone us at: (514) 876-1020
 Twitter: @NOUV_CHAMPLAIN
Communication
43
New Champlain Bridge Corridor Project

More Related Content

What's hot

Meeting of the verdun sud ouest good neighbourly relations committee - febru...
Meeting of the verdun  sud ouest good neighbourly relations committee - febru...Meeting of the verdun  sud ouest good neighbourly relations committee - febru...
Meeting of the verdun sud ouest good neighbourly relations committee - febru...Pont Samuel-De Champlain Bridge
 
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...Pont Samuel-De Champlain Bridge
 
Details of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlainDetails of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlainPont Samuel-De Champlain Bridge
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Pont Samuel-De Champlain Bridge
 
Meeting minutes brossard good neighbourly relations commitee - may 17 2017
Meeting minutes   brossard good neighbourly relations commitee - may 17 2017Meeting minutes   brossard good neighbourly relations commitee - may 17 2017
Meeting minutes brossard good neighbourly relations commitee - may 17 2017Pont Samuel-De Champlain Bridge
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Pont Samuel-De Champlain Bridge
 
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...Pont Samuel-De Champlain Bridge
 
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...Pont Samuel-De Champlain Bridge
 
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...Pont Samuel-De Champlain Bridge
 
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...Pont Samuel-De Champlain Bridge
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...Pont Samuel-De Champlain Bridge
 
Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Crosstown TO
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 

What's hot (20)

Meeting of the verdun sud ouest good neighbourly relations committee - febru...
Meeting of the verdun  sud ouest good neighbourly relations committee - febru...Meeting of the verdun  sud ouest good neighbourly relations committee - febru...
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
 
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...
 
Details of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlainDetails of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlain
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
 
Meeting minutes brossard good neighbourly relations commitee - may 17 2017
Meeting minutes   brossard good neighbourly relations commitee - may 17 2017Meeting minutes   brossard good neighbourly relations commitee - may 17 2017
Meeting minutes brossard good neighbourly relations commitee - may 17 2017
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
 
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
 
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
 
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
 
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
 
Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 

Viewers also liked

Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...
Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...
Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...Pont Samuel-De Champlain Bridge
 
Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017
Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017
Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017Pont Samuel-De Champlain Bridge
 
Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016
Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016
Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016Pont Samuel-De Champlain Bridge
 
Travaux marins en securité (19 mai 2016) - Nouveau pont Champlain
Travaux marins en securité  (19 mai 2016) - Nouveau pont ChamplainTravaux marins en securité  (19 mai 2016) - Nouveau pont Champlain
Travaux marins en securité (19 mai 2016) - Nouveau pont ChamplainPont Samuel-De Champlain Bridge
 
Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...
Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...
Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...Pont Samuel-De Champlain Bridge
 
Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016
Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016
Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016Pont Samuel-De Champlain Bridge
 
Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...
Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...
Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...Pont Samuel-De Champlain Bridge
 

Viewers also liked (9)

Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...
Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...
Présentation Infrastructure Canada - Comité bon voisinage Brossard - 21 septe...
 
Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017
Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017
Nouveau pont champlain - Présentation École Polytechnique - 9 fevrier 2017
 
Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016
Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016
Présentation à l'association des gens d'affaires de brossard - 7 decembre 2016
 
Brief media nouveau pont champlain - 25 aout 2016
Brief media nouveau pont champlain - 25 aout 2016Brief media nouveau pont champlain - 25 aout 2016
Brief media nouveau pont champlain - 25 aout 2016
 
Travaux marins en securité (19 mai 2016) - Nouveau pont Champlain
Travaux marins en securité  (19 mai 2016) - Nouveau pont ChamplainTravaux marins en securité  (19 mai 2016) - Nouveau pont Champlain
Travaux marins en securité (19 mai 2016) - Nouveau pont Champlain
 
Comité de bon voisinage Brossard - 25 janvier 2017
Comité de bon voisinage Brossard - 25 janvier 2017Comité de bon voisinage Brossard - 25 janvier 2017
Comité de bon voisinage Brossard - 25 janvier 2017
 
Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...
Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...
Présentation LED et murs anti-bruit - Infrastructure Canada - Comité de bon v...
 
Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016
Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016
Présentation comité de bon voisinage Verdun - Le Sud-Ouest - 8 fevrier 2016
 
Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...
Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...
Présentation Infrastructure Canada - Comite de bon voisinage Verdun - 08 fevr...
 

Similar to Meeting of the brossard good neighbourly relations committee september 21 2016

Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingVDOT Northern Virginia
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 finalToronto Public Consultation Unit
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014WaterfrontTO
 
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Fairfax County
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 

Similar to Meeting of the brossard good neighbourly relations committee september 21 2016 (20)

Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
Review of work in 2016
Review of work in 2016Review of work in 2016
Review of work in 2016
 
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Queen street station tunnel or throat development rodger querns
Queen street station tunnel or throat development  rodger quernsQueen street station tunnel or throat development  rodger querns
Queen street station tunnel or throat development rodger querns
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
 
Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014
 
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 

More from Pont Samuel-De Champlain Bridge

Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...Pont Samuel-De Champlain Bridge
 
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...Pont Samuel-De Champlain Bridge
 
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...Pont Samuel-De Champlain Bridge
 
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...Pont Samuel-De Champlain Bridge
 
Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019Pont Samuel-De Champlain Bridge
 
Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019Pont Samuel-De Champlain Bridge
 
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018Pont Samuel-De Champlain Bridge
 
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...Pont Samuel-De Champlain Bridge
 
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019Pont Samuel-De Champlain Bridge
 
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...Pont Samuel-De Champlain Bridge
 
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...Pont Samuel-De Champlain Bridge
 
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...Pont Samuel-De Champlain Bridge
 
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019Pont Samuel-De Champlain Bridge
 
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...Pont Samuel-De Champlain Bridge
 
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018Pont Samuel-De Champlain Bridge
 
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...Pont Samuel-De Champlain Bridge
 
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...Pont Samuel-De Champlain Bridge
 
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...Pont Samuel-De Champlain Bridge
 
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...Pont Samuel-De Champlain Bridge
 
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...Pont Samuel-De Champlain Bridge
 

More from Pont Samuel-De Champlain Bridge (20)

Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
 
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
 
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
 
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
 
Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019
 
Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019
 
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
 
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
 
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
 
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
 
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
 
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
 
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
 
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
 
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
 
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
 
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
 
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
 
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
 
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 

Meeting of the brossard good neighbourly relations committee september 21 2016

  • 1. Good Neighbourly Relations Committee Meeting City of Brossard: September 21, 2016 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau
  • 2. New Champlain Bridge Corridor Project 2 Committee Members Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Jaime Reis Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada
  • 3. New Champlain Bridge Corridor Project 1. Provide information about the work that has been completed, is underway and planned between now and January 2017 2. Follow up on the various files under the responsibility of Infrastructure Canada 3. Answer questions, find potential solutions and discuss the issues Objectives of the Meeting 3
  • 4. New Champlain Bridge Corridor Project Agenda 4 Series Item Duration Time 1. Opening 10 min. 7:00 to 7:10 pm 2. Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area 40 min. 7:10 to 7:50 pm 3. Committee question period 20 min. 7:50 to 8:10 pm 4. Follow up on the various files under the responsibility of Infrastructure Canada 20 min. 8:10 to 8:30 pm 5. Committee question period 10 min. 8:30 to 8:40 pm 6. Varia 10 min. 8:40 to 8:50 pm 7. General public question period 20 min. 8:50 to 9:10 pm 8. Adjournment: next meeting and topic 5 min. 9:10 to 9:15 pm
  • 5. New Champlain Bridge Corridor Project ● Complex project, on many « fronts » at the same time, with an extremely tight schedule ● Each new manufacturing and construction activity requires a normal learning period, as well as adjustments ● First important challenge: adapt the transport strategy for the pieces coming from Québec or from the United States ● Reduction of the risk profile  Bridge conception almost completed  Major procurement completed  Manufacturing has begun  « We are emerging from water » ● High level of public interest for the bridge construction: a very visible and public project Observations 5
  • 6. New Champlain Bridge Corridor Project Work Completed over the Past Few Months
  • 7. New Champlain Bridge Corridor Project • Summer season: solid work progress on the East Approach  Pile caisson drilling and concret East Approach  Installation of cofferdams and e  Formwork and concreting of the of pier bases  Abutment start • Concerns with regards to access to t construction site and to the safety of • Very few complaints Overview of Completed Works 7
  • 8. New Champlain Bridge Corridor Project Complaints Handling (April 29 to September 20, 2016) Topic Sector Brossard Closed Open Total Noise 1 - 1 Air quality 1 1 2 Traffic - 1 1 Vibrations - - - Brightness - - - Other 3 1 4 Total 5 3 8 8
  • 9. New Champlain Bridge Corridor Project Main Priorities for the Upcoming Months - South Shore
  • 10. New Champlain Bridge Corridor Project Location of Work Areas City of Brossard Cable-stayed bridge
  • 11. New Champlain Bridge Corridor Project Highway 10 • Soil management • Earthworks at the East Abutment East Approach of the New Champlain Bridge • Completion of the construction of footings and pier bases • Continue the construction of the east abutment, including the building housing the electric systems • Beginning of installation of prefabricated segments of piers and pier caps Cable-stayed bridge • Construction of main pylon and rear span South Shore Priorities: September 2016 to January 2017 11
  • 12. New Champlain Bridge Corridor Project Description of Activity Approximate Duration of Works Planned Work Period Legend: Work and Impacts • Traffic and Public Transportation: • Proximity of Residential Areas: • Boating: • Bike Paths: Minor impact Medium impact Major impact Indication by level colour code 12
  • 13. New Champlain Bridge Corridor Project Key Activities Underway and to Come - East Approach Design and planning underway so modifications are possible
  • 14. New Champlain Bridge Corridor Project Objective: Construction of East Approach of the new Champlain Bridge Upcoming work: • Completion of the forming and concreting of footings and pier bases • Continue the construction of the abutment, including the building housing the electric systems • Placement of prefabricated segments of piers and pier caps Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant East Approach Area 14
  • 15. New Champlain Bridge Corridor Project Nov 2015 May Nov 2016 May Nov. 2017 Nov 2018 May East Approach: Timetable 15 Feb 2016 Aug Feb 2017 Aug. Feb. 2018 Aug. Construction of footings and pier bases Installation of piers and pier caps Assembly of superstructure and deck Finishing work
  • 16. New Champlain Bridge Corridor Project Works and Impacts: East Approach Construction of footings and pier bases Duration: eight months Projected period: February to November 2016 16 17 out of 20 footings of the East Approach were concreted, and 10 are completed with pier bases
  • 17. New Champlain Bridge Corridor Project Works and Impacts: East Approach Placement of prefabricated segments of piers and pier caps Duration: eight months Projected period: Mid-October to Spring 2017 17
  • 18. New Champlain Bridge Corridor Project Works and Impacts: East Approach Construction of East Abutment’s building Duration: four months Projected period: September to December 2016 18
  • 19. New Champlain Bridge Corridor Project Works and Impacts: La Riveraine Bike Path 19 Detour of La Riveraine bike path until the summer of 2019 DETOUR OF LA RIVERAINE BIKE PATH
  • 20. New Champlain Bridge Corridor Project Works and Impacts: East Approach Work Site Exit 20 Worker Parking Daily flow of traffic • 20 heavy trucks •150 light vehicles Entrance Exit
  • 21. New Champlain Bridge Corridor Project Key Activities Underway and to Come Highway 10 Design and planning underway so modifications are possible
  • 22. New Champlain Bridge Corridor Project Highway 10 Area 22 Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links Upcoming work: • Soil storage • Earthworks at the eastern abutment • Creation of a retaining basin for permanent drainage • Installation of permanent anti-noise walls Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Night-time trucking from the West Approach to the East Approach
  • 23. New Champlain Bridge Corridor Project Works and Impacts: Highway 10 Soil management and creation of a retaining basin Duration: throughout the project Projected period: 2016 to 2019 23
  • 24. New Champlain Bridge Corridor Project Works and Impacts: Highway 10 Earthworks at the eastern abutment Duration: one year Projected period: April 2016 to Spring 2017 24
  • 25. New Champlain Bridge Corridor Project Key Activities Underway and to Come Cable-stayed Bridge Design and planning underway so modifications are possible
  • 26. New Champlain Bridge Corridor Project Cable-stayed Bridge: Timetable 26 2. Pylon foundations October 2015 to April 20161. Jetty August to October 2015 7. Main span March 2017 to June 2018 3. Rear span November 2015 to March 2017 6. Upper pylon November 2016 to October 2017 4. Lower pylon May to October 2016 5. Lower crossbeam October to December 2016
  • 27. New Champlain Bridge Corridor Project Key Activities Since the Spring of 2016 27 Two footings and pier basis of the main pylon of cable-stayed bridge were concreted
  • 28. New Champlain Bridge Corridor Project Transportation of the First Segments of the Main Pylon 28 1 2 3 4 1. Arrival of the segments by van at the Port de Sorel, from St-Eugène 2. Laoding of the segments on the barge 3. The barge leaves the Port de Sorel 5 6 4. The barge arrives at the Port de Montréal 5. The winched barge is used to go up the rapids of the Île Notre-Dame 6. Arrival of the segments at the jetty
  • 29. New Champlain Bridge Corridor Project Key Activities Since the Spring of 2016 Installation of the first prefabricated segments of the main pylon of the cable-stayed bridge
  • 30. New Champlain Bridge Corridor Project Works and Impacts: Seaway Bike Path 30 Ponctual and short term closings in the course of the fall
  • 31. New Champlain Bridge Corridor Project Anticipated Impacts
  • 32. New Champlain Bridge Corridor Project Anticipated impacts • Road traffic • Noise • Air quality 32
  • 33. New Champlain Bridge Corridor Project Traffic • Fall JCCBI blitz:  September 10/11: Closed towards the South Shore  September 17/18: Closed towards Montréal  October 1/2: Closed towards the South Shore  October 15/16: Closed towards Montréal • Disruptions to come this fall • Upcoming major disruptions for the Spring 2017: installation of superstructure and deck above Highway 132 traffic lanes 33 Configuration – Disruptions Schedule Duration Removal of traffic signs on Marie-Victorin Boul. (East and West) October 2016 2 nights Dismantling of jerseys – Road 132 Early November 2016 1 week Passage of pier caps pieces End November 2016 8 nights
  • 34. New Champlain Bridge Corridor Project Passage of Pier Caps Pieces 34
  • 35. New Champlain Bridge Corridor Project Steel Pier Caps 35
  • 36. New Champlain Bridge Corridor Project Passage of Pier Caps Pieces 36
  • 37. New Champlain Bridge Corridor Project37 Passage des chevêtres 37
  • 38. New Champlain Bridge Corridor Project 38 B1: Turenne area B2: Voltaire area B3: Tisserand area Noise Management Area Activity Period J/S/N Exposed sensitive area Ambient noise dBA Criterion dBA Estimated noise dBA Required measures Forming and concreting of footings and pier bases J B1/B2 60/62 75 68/66 Not required Construction of eastern abutment J B1/B2 60/62 75 62/66 Not required Placement of prefabricated segments of piers and pier caps J B1/B2 60/62 75 61/64 Not required A10 Earthworks at the Eastern Abutment J B2 62 75 73 Monitoring required Cable- stayed Miscellaneous work J B1/B2 60/62 75 61/63 Not required EastApproach To comeTo comeConstruction of building J B2 62 75
  • 39. New Champlain Bridge Corridor Project Air Quality Management • Migitation measures : Frequent water spaying and cleaning • Additional measures taken after exceeding levels during the summer of 2016 : seeding, asphalting, wheel cleaning bassins, continuous cleaning and increased environmental surveillance • Regulatory framework : Contractual environmental obligations and Clean Air Regulation (CAR) Applicable MDDELCC standards MDDELCC CAR PMt PM2.5 120 ug/m3 30 ug/m3 39
  • 40. New Champlain Bridge Corridor Project Follow-up on Interventions 40 SSL • Date for the installations of anti-noise walls City of Brossard • State of the pavement on the detour of the La Riveraine bike path : observations and interventions • Extension of the anti-noise walls Infrastructure Canada (will be discussed in the next presentation) • GHG file • Interactions with the REM Project • Follow-up with the MTQ on luminosity • Frequency of periodic revisions and acoustic studies by SSL
  • 41. New Champlain Bridge Corridor Project Next Meetings
  • 42. New Champlain Bridge Corridor Project • Good Neighbourly Relations Committee: January 25 (TBC)  Topic: none projected • No public information meeting is planned for the time being Next meetings (for discussion) 42
  • 43. New Champlain Bridge Corridor Project • Newsletter: sign up online • Information sheets delivered to residents’ homes, if required, and notices in local newspapers • Sign up / contact us:  Website: www.newchamplain.ca  Email: info@sslc.ca  Phone us at: (514) 876-1020  Twitter: @NOUV_CHAMPLAIN Communication 43
  • 44. New Champlain Bridge Corridor Project