Public Information Meeting to inform the public about the completed and upcoming work on the new Champlain Bridge corridor project on L’Île-des-Soeurs including anticipated impacts and mitigation measures.
2. New Champlain Bridge Corridor Project
To inform you about
the completed and upcoming work on the
new Champlain Bridge corridor project
on L’Île-des-Soeurs
-----------
including anticipated impacts
and mitigation measures
------------
and to answer your questions
Meeting Objective
2
3. New Champlain Bridge Corridor Project
Agenda
• Welcome
• Review of the project and our technical solution
• Context specific to L’Île-des-Soeurs
• Key activities
First 6 months
Next 12 months
• Impacts and mitigation measures
• Communications
• Question period
3
4. New Champlain Bridge Corridor Project
Jean-François Parenteau
Mayor of the Borough of Verdun
Welcome
4
5. New Champlain Bridge Corridor Project
Daniel Genest
Director Coordination
Signature on the Saint-Laurent
Marthe Robitaille
Director Environment
Signature on the Saint-Laurent
5
6. New Champlain Bridge Corridor Project
Challenges of the Project
• Very large, complex site
Urban setting
Near residents
Over water
Winter conditions
Environmental considerations
• Numerous partners and stakeholders : importance of
providing information well ahead of time to ensure proper
collaboration and coordination
• Construction of Champlain Bridge : 42 months
(now 37 months remaining)
6
8. New Champlain Bridge Corridor Project
Sectors and
Sequence of Construction
West Approach
26 spans : WA - W02
Cable-stayed Bridge
4 spans : W02 - E02
East Approach
9 spans : E02 - EA
1
W4 W3 W2 W1 MST E1 E2
321 121 24
8
Execution of works in three sectors, in parallel
9. New Champlain Bridge Corridor Project
Bridge Construction Strategy
Steel superstructure
Steel pier caps
Concrete pier
Concrete footing
Concrete deck
9
• Maximize pre-fabrication of concrete components, with the option of cast-in-
place when more practical :
Footings : West Jetty
Piers and deck : Drummondville
• Pre-assembly of steel pier caps and superstructure : three jetties
• Delivery, installation and assembly by barge and catamaran
10. New Champlain Bridge Corridor Project
Context Specific
to L’Île-des-Soeurs
• Gateway to one of the largest infrastructure projects in North America
• Construction of the new Champlain Bridge :
West Jetty : pre-fabrication of footings and pre-assembly of pier caps and
superstructure
West Approach : marine excavation, installation of footings, piers and pier caps, and
assembly of superstructure
• Reconfiguration of the road corridor :
Demolition and reconstruction of the Île-des-Sœurs bridge
Reconfiguration of Highway 15
• Presence of the Project Team office (8 Place du Commerce) and largest project
site facilities (Pointe-Nord)
10
12. New Champlain Bridge Corridor Project
• Major communication efforts
• Detailed design
• Construction of large-scale temporary works : two large jetties completed and
a third underway
• Start of the construction of the main pylon of the new Champlain Bridge
• May Street demolition
• Site facilities in the Pointe-Nord sector of L’Île-des-Sœurs and south of the
Gaétan-Laberge interchange
• Transfer of responsibility for operation and maintenance of the A15 and A10
road links, from JCCBI to SSL
Major Project Activities
Since Our Selection in mid-April
12
13. New Champlain Bridge Corridor Project
West Jetty : Pre-fabrication
and Pre-assembly Facilities
13
14. New Champlain Bridge Corridor Project
West Jetty :
Look Back at the Construction
• Work :
Jetty: June 15 to August 19, 2015
Pre-fabrication and pre-assembly facilities: underway since August 20, 2015
• Trucking related to jetty construction :
212,000 m³ / 435,780 tons of rock
13,017 truck trips
277 trips per day, on average
• Limited impact on traffic
• No incidents with cyclists or pedestrians
• Noise management and air quality : prescribed thresholds respected
• Rapid reaction to residents’ complaints : calls returned and corrective
measures taken
14
17. New Champlain Bridge Corridor Project
Key Activities for Next 12 Months :
West Approach
Design and planning underway
therefore modifications are possible
18. New Champlain Bridge Corridor Project
Underway : Construction of pre-fabrication and pre-assembly facilities
Next :
• Step 1 : Pre-fabrication of footings and pre-assembly of pier caps and
superstructure - November 2015 to April 2018
• Step 2 : Marine excavation - November 2015 to September 2016
• Step 3 : Installation of footings - April 2016 to July 2017
• Step 4 : Installation of piers and pier caps - May 2016 to August 2017
• Step 5 : Assembly of superstructure and deck - August 2016 to July 2018
• Step 6 : Finishing work - June 2017 to October 2018
Approach :
• Work done mainly during the day, except for pre-fabrication, which will take
place day and night
West Approach : Key Activities
18
19. New Champlain Bridge Corridor Project
Nov
2015
May Nov
2016
May Nov
2017
Nov
2018
May
Pre-fabrication and pre-assembly
Marine excavation
Installation of footings
Installation of piers and pier caps
Assembly of superstructure and deck
Finishing work
West Approach : Schedule
19
Feb
2016
Aug Feb
2017
Aug Feb
2018
Aug
20. New Champlain Bridge Corridor Project 20
Pre-assembly area
for steel superstructure
Pre-assembly area
for steel pier caps
Pre-fabrication area
for concrete footings
Loading facilities
Pre-fabrication
and Pre-assembly Facilities
21. New Champlain Bridge Corridor Project
Concrete Footing
and Pier Starter Segment
21
Concrete pier
starter segment
Concrete footing
Work platform
32. New Champlain Bridge Corridor Project
Installation of Pier Caps,
Superstructure and Deck
32
33. New Champlain Bridge Corridor Project
Key Activities for Next 12 Months :
A15 Corridor
Design and planning underway
therefore modifications are possible
34. New Champlain Bridge Corridor Project
Underway : Preparatory work for demolition of Île-des-Sœurs Bridge, including
construction of a jetty from the west bank of the channel
Next :
• Demolition of Île-des-Sœurs Bridge - November 2015 to April 2016
• Construction of new Île-des-Sœurs Bridge - March 2016 to September 2017
• Demolition of south-bound direction of existing overpass over Boul. de L’Île-des-
Sœurs - April to May 2016
• Construction of south-bound direction of new overpass over Boul. de L’Île-des-
Sœurs - May 2016 to April 2017
Approach :
• Demolition work during the day only, with debris collection activities in the
evening and at night
• Construction work during the day and night
A15 Corridor : Key Activities
34
35. New Champlain Bridge Corridor Project
Demolition of Île-des-Sœurs Bridge
and Boul. de L’Île-des-Sœurs Overpass
35
Phase 1 : Demolition of
the bridge superstructure
Phase 2 : Demolition
of the piers
Phase 3 : Demolition of
the overpass
36. New Champlain Bridge Corridor Project
Construction
of new Île-des-Sœurs Bridge
• Construction from a jetty and barges
• Construction period : March 2016 to September 2017
• Construction priority : south-bound direction, which will be open
to traffic in July 2017
36
37. New Champlain Bridge Corridor Project
Gaétan-Laberge Boulevard
• Vision : an urban boulevard leading to downtown
• Desire expressed to not create a « highway-type » interchange
37
38. New Champlain Bridge Corridor Project
Anticipated Impacts
and Mitigation Measures
39. New Champlain Bridge Corridor Project
Anticipated Impacts
and Mitigation Measures
• Traffic
• Noise
• Air quality
39
40. New Champlain Bridge Corridor Project
Traffic Management
• Create and maintain safe conditions for
all users of the road network, cyclists
and pedestrians
• Minimize impact on users of the road
network, cyclists and pedestrians
• Continue the approach already in place
40
41. New Champlain Bridge Corridor Project
Noise Management
NOISE CRITERIA
• Day (7 a.m. to 7 p.m.) : 75 decibels or 5 decibels above
ambient noise level
• Evening and night (7 p.m. to 7 a.m.) : 5 decibels above
ambient noise level
Source: MTQ Turcot Project Presentation of November 18, 2014 41
A few basic concepts
Audibility
threshold
Sleep
threshold
Disturbing
noise
Irritating
noise
Harmful
noise
Pain
threshold
55 dBA and -
change barely perceptible
change perceptible
doubles or halves the audio intensity
recognized as an acceptable sound level
Sound levels do not compound in a linear fashion
Doubling the sources of noise doubling the noise level
42. New Champlain Bridge Corridor Project
Noise Management
42
Noise-sensitive Zones
West
Approach
Île-des-Sœurs
Bridge
43. New Champlain Bridge Corridor Project
Activity
Work
period
Most
exposed
sensitive
zone
Ambient
noise
in dba
(May 2015)
Criterion
in dba
Estimated
noise in dba
(October
2015)
Specific
mitigation
measures
West Approach -
Construction
of loading facilities
D I2 / I3 64 / 57 75 65 No
West Approach -
Pre-fabrication of footings
D
E
N
I2 / I3
64 / 57
59 / 52
57 / 52
75
64 / 57
62 / 57
60
57
57
No
West Approach -
Marine excavation
D I2 / I3 64 / 57 75 64 No
L’Île-des-Sœurs -
Construction of West Jetty
D I1 57 75 66 No
L’Île-des-Sœurs -
Demolition of existing bridge
D I1 57 75 73 No
L’Île-des-Sœurs -
Demolition of overpass
D I1 57 75 69 No
Sound Management Plan
(up to end March 2016)
43
I1 : Sax
I2 : Evolo
I3 : Cours des Fougères
No specific mitigation measure required
Follow-up required
44. New Champlain Bridge Corridor Project
• Main mitigation measures for the entire work site:
Use variable-intensity back-up alarms
Organize traffic to minimize backing up
Control production of impact noise (truck tailgates)
Make site supervisors and workers aware of the need to comply with noise
mitigation measures
• Monitor noise levels during construction
At the beginning of critical activities, for verification purposes
Once or twice every two weeks
Check when there are complaints
Noise Management
44
45. New Champlain Bridge Corridor Project
Air Quality Management
Regulatory framework
Contractual environmental obligations
Clean Air Regulation (CAR)
Applicable MDDELCC Standards
MDDELCC CAR
PMT PM2.5
120 ug/m3 30 ug/m3
45
46. New Champlain Bridge Corridor Project
Air Quality Management
• No expected impact on sensitive zones
• Main mitigation measures for the entire work site:
Transport of materials in dump trucks with tarp covers
Appropriate maximum speed for vehicles, to reduce dust emissions on access roads
or jetty
Spraying water on surfaces
Regular cleaning of the streets used by vehicles and machinery in order to remove
any accumulation of movable material and other debris
If necessary, application of dust suppressant
• Monitoring to be done mainly for demolition activities
46
47. New Champlain Bridge Corridor Project
• Public information meetings : One per year, on average, per sector
L’Île-des-Sœurs (June 8), Verdun / Sud-Ouest (September 14) and Brossard (October 14)
• CINPA : Verdun / Sud-Ouest
Selection process underway
Kick-off meeting by the end of November
First CINPA “open session” meeting in January
• Newsletter available soon : suscribe through our web site
• Door delivered notices to residents, when needed, and local newspaper notices
• Site visit planned for this fall, has been postponed to May / June 2016
• Subscribe / contact us at :
Website : www.newchamplain.ca
Email : info@sslc.ca
Phone : (514) 876-1020
Twitter : @NOUV_CHAMPLAIN
Communications
47
48. New Champlain Bridge Corridor Project
Blitz : 6 to 9 November 2015
(A15N Closure)
48
Detour
through Verdun
Autoroute Bonaventure
open