Objectives of the Meeting
- Provide information about the work that has been completed, is underway and planned between now and fall 2017
- Answer questions, find potential solutions and discuss the issues
Brossard Good Neighbourly Relations Committee - May 17, 2017
1. Good Neighbourly Relations Committee
Meeting
City of Brossard : May 17 2017
New Champlain Bridge Corridor Project
Centre communautaire Nathalie Croteau
Please note that the English version is used
only for refernce purposes. In case of
disrepancy between the English and French
versions, the French version shall prevail.
2. Projet de corridor du nouveau pont Champlain 2
Committee Members
Residents
Luis Oscar Corrales
Ginette Dufresne
Marc Gagné
Nabil Halouani
Jacques Picard
Goreti Fernandes
Marc Turcotte – Representative from a community
organization
Éric Jutras – Member of the business community
Partners
Dan Genest – The Signature on the Saint-Laurent team
Benoît Fillion – City of Brossard
Vincent Jarry – Infrastructure Canada
3. Projet de corridor du nouveau pont Champlain
1. Provide information about the work that has been
completed, is underway and planned between now and fall
2017
2. Answer questions, find potential solutions and discuss the
issues
Objectives of the Meeting
3
4. Projet de corridor du nouveau pont Champlain
Agenda
4
Série Item Durée Heure
1. Opening 10 min. 19h00 à 19h10
2. Work completed, underway and to come
• Eastern approach area
• Hwy-10 area
• Cable-stayed bridge area
40 min. 19h10
à 19h50
3. Question period 20 min. 19h50 à 20h10
4. Varia 15 min. 20h10 à 20h25
5. Adjournment: next meeting and topic 5 min. 20h25 à 20h30
5. Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
6. Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
• Winter season: good work progress in general on
the East Approach
End of the earthworks of the east abutment
More than 75% of the piers segments were installed
(70 out of 90)
Beginning of the pre-assembly of girders
Two complaints since January 25
• First partial closure of the 132 highway and the
Blvd. Marie-Victorin
7. Projet de corridor du nouveau pont Champlain
Main Priorities for the Upcoming Months-
South Shore
8. Projet de corridor du nouveau pont Champlain 8
South Shore: Overview
Works mainly completed at the opening of the
New Champlain Bridge in late 2018
Adjustment of ramps for
access and exit to the New
Champlain Bridge
New Champlain Bridge
Construction
Construction of a new bike access to
the New Champlain Bridge
9. Projet de corridor du nouveau pont Champlain
Location of Work Areas
City of Brossard
Cable-stayed
bridge
10. Projet de corridor du nouveau pont Champlain
Highway 10
• Soil management
• Preparatory works for the configuration of the highway 10
East Approch
• Installation of prefabricated segments of piers and pier caps
• Construction of the east abutment, including the building housing the electric
systems
• Preparations for the construction of the span above Route 132
Cable-stayed bridge
• Construction of main pylon, rear and principal spans
South Shore
Priorities : May to September 2017
10
11. Projet de corridor du nouveau pont Champlain
Description of Activity
Approximate Duration of Works
Planned Work Period
Legend: Work and Impacts
• Traffic and Public Transportation:
• Proximity of Residential Areas:
• Boating:
• Bike Paths:
Minor impact
Medium impact
Major impact
Indication by level colour code
11
12. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come -
East Approach
Design and planning underway so modifications are possible
13. Projet de corridor du nouveau pont Champlain
Objective: Construction of East Approach of the new Champlain Bridge
Travaux en cours et à venir :
• Placement of prefabricated segments of piers and pier caps
• Continue the construction of the abutment, including the building housing the
electric systems
• Preparatory works for the construction of the span above Highway 132
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels)
are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic are
too significant
East Approach Area
13
14. Projet de corridor du nouveau pont Champlain
Nov
2015
May Nov
2016
May Nov.
2017
Nov
2018
May
East Approach: Timetable
14
Feb
2016
Aug Feb
2017
Aug. Feb.
2018
Aug.
Construction of
footings and pier
bases
Installation of piers and pier
caps
Assembly of superstructure and
deck
Finishing work
15. Projet de corridor du nouveau pont Champlain 15
Placement of prefabricated segments
of piers and pier caps
Duration: 15 months
Projected period: October 2016 to January 2018
Works and Impacts: East Approach
16. Projet de corridor du nouveau pont Champlain 16
Construction of East Abutment’s building
Duration: three months
Projected period: May to July 2017
Works and Impacts: East Approach
17. Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
Preparatory works for the construction of the span
above Highway 132
Duration : four months
Projected period: Fall 2017
17
18. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Highway 10
Conception et planification en développement
donc des modifications sont possibles
19. Projet de corridor du nouveau pont Champlain
Highway 10 Area
19
Objective: Area reserved for soil management for the work site and preparatory
work for the reconfiguration of highway links
Work underway:
• Soil storage
• Creation of a retaining basin for permanent drainage
• Earthworks at the eastern abutment
Upcoming Works
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Night-time trucking from the West Approach to the East Approach
20. Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Soil management and creation of a retaining basin
Duration: throughout the project
Projected period: 2016 to 2019
20
21. Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Installation of permanent anti-noise walls
Duration : three months
Projected period: fall 2017
21
22. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Cable-stayed Bridge
Design and planning underway so modifications are possible
23. Projet de corridor du nouveau pont Champlain
Cable-stayed Bridge: Timetable
23
2. Pylon foundations
October 2015 to April 20161. Jetty
August to October 2015
7. Main span
March 2017 to
September 2018
3. Rear span
November 2015 to July 2017
6. Upper pylon
February to December
2017
4. Lower pylon
May to October 2016
5. Lower crossbeam
October to February 2017
24. Projet de corridor du nouveau pont Champlain
Key activities since winter 2017
24Construction of the rear span
25. Projet de corridor du nouveau pont Champlain
Key activities since winter 2017
Construction of the main pylon and the principal span
26. Projet de corridor du nouveau pont Champlain
Works and impacts : Bike path of the
seaway dike
26
Ponctual closing of variable duration and variable frequency
--from a few hours up to a few days--
Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
28. Projet de corridor du nouveau pont Champlain
Anticipated impacts
• Road traffic
• Noise
• Air quality
• Navigation
28
29. Projet de corridor du nouveau pont Champlain
Traffic
• PJCCI’s Major Work Blitz
May 20 / 21 : Complete closure of the Hwy-15 South heading to South Shore
May 27 / 28 : Complete closure of the Hwy-15 North heading to Montreal
• Disruptions to come
• Upcoming major disruptions for the Fall 2017 : installation of
superstructure and deck above Highway 132 traffic lanes
29
Configuration – Disruptions Schedule Duration
Installation of foundations and temporary
scaffolding
Summer 2017 3 weeks
Passage of pier caps pieces
Summer / Fall
2017
8 nights
Route Deviation from route 132 & boul.
Marie-Victorin
Fall 2017 18 months
30. Projet de corridor du nouveau pont Champlain
Example of temporary scaffolding
30
31. Projet de corridor du nouveau pont Champlain
Passage of Pier Caps Pieces
31
33. Projet de corridor du nouveau pont Champlain 33
B1: Turenne area
B2: Voltaire area
B3: Tisserand area
Noise Management
Preparatory works Highway
132
Area
Activity
Period
D/E/N
Exposed
sensitive
area
Ambient
noise dBA
Criterion
dBA
Estimated
noise dBA
Required
measures
EastApproach
Placement of prefabricated segments of
piers and pier caps
D B1 / B2 60 / 62 75 62 / 63 Not required
Construction
of building (east abutment)
D B2 62 75 71 Not required
Preparatory works Highway 132 D / E –N B2 62 75 / 67 To come
Hgw
10
Installation of permanent anti-noise
walls
D B2 62 75 75
Monitoring
required
Cable-
Stayed
Miscellaneous work D B1 / B2 60 / 62 75 62 / 63 Not required
34. Projet de corridor du nouveau pont Champlain
Air Quality Management
• Migitation measures : increased environmental monitoring + Frequent
water spaying and cleaning
• Regulatory framework : Contractual environmental obligations and
Clean Air Regulation (CAR)
Applicable MDDELCC standards
MDDELCC CAR
PMt PM2.5
120 ug/m3 30 ug/m3
34
35. Projet de corridor du nouveau pont Champlain
Water traffic
35
Background
• Work site in water as well as a transport
corridor for heavy parts between the Port of
Montreal and the cable-stayed bridge area
• Navigational vigilance in the St. Lawrence
and in the Lesser La Prairie Basin
Main mitigation measures
• Communication
• Waterway signs and marking
• Patrolling and nautical surveillance
• Equipment lighting
• Information session with the users of the river
37. Projet de corridor du nouveau pont Champlain
Follow-up on Interventions
37
SSL
• Date for the installations of anti-noise walls
• Landscaping and building of the east abutment
INFC
• LED lighting tracking : return of MTMDET and Toronto case study
Ville de Brossard
• Follow-up on plantation planned in the Champlain park
38. Projet de corridor du nouveau pont Champlain
• Site visit
Elected : April 28
Good Neighbourly Relations Committee and municipal administrators : May
5
Media : May 19
• Newsletter: sign up online
• Notice sent by post to citizen, if required, and local newspaper notices
• Sign up / contact us:
Website: www.newchamplain.ca
Email: info@sslc.ca
Phone us at: (514) 876-1020
Twitter: @NOUV_CHAMPLAIN
Communications
38
40. Projet de corridor du nouveau pont Champlain
Good Neighbourly Relations Committee :
September 27 (To be confirmed)
Topic : Landscaping
Next meetings
40