Good Neighbourly Relations Committee
Meeting
City of Brossard : May 17 2017
New Champlain Bridge Corridor Project
Centre communautaire Nathalie Croteau
Please note that the English version is used
only for refernce purposes. In case of
disrepancy between the English and French
versions, the French version shall prevail.
Projet de corridor du nouveau pont Champlain 2
Committee Members
Residents
Luis Oscar Corrales
Ginette Dufresne
Marc Gagné
Nabil Halouani
Jacques Picard
Goreti Fernandes
Marc Turcotte – Representative from a community
organization
Éric Jutras – Member of the business community
Partners
Dan Genest – The Signature on the Saint-Laurent team
Benoît Fillion – City of Brossard
Vincent Jarry – Infrastructure Canada
Projet de corridor du nouveau pont Champlain
1. Provide information about the work that has been
completed, is underway and planned between now and fall
2017
2. Answer questions, find potential solutions and discuss the
issues
Objectives of the Meeting
3
Projet de corridor du nouveau pont Champlain
Agenda
4
Série Item Durée Heure
1. Opening 10 min. 19h00 à 19h10
2. Work completed, underway and to come
• Eastern approach area
• Hwy-10 area
• Cable-stayed bridge area
40 min. 19h10
à 19h50
3. Question period 20 min. 19h50 à 20h10
4. Varia 15 min. 20h10 à 20h25
5. Adjournment: next meeting and topic 5 min. 20h25 à 20h30
Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
• Winter season: good work progress in general on
the East Approach
 End of the earthworks of the east abutment
 More than 75% of the piers segments were installed
(70 out of 90)
 Beginning of the pre-assembly of girders
 Two complaints since January 25
• First partial closure of the 132 highway and the
Blvd. Marie-Victorin
Projet de corridor du nouveau pont Champlain
Main Priorities for the Upcoming Months-
South Shore
Projet de corridor du nouveau pont Champlain 8
South Shore: Overview
Works mainly completed at the opening of the
New Champlain Bridge in late 2018
Adjustment of ramps for
access and exit to the New
Champlain Bridge
New Champlain Bridge
Construction
Construction of a new bike access to
the New Champlain Bridge
Projet de corridor du nouveau pont Champlain
Location of Work Areas
City of Brossard
Cable-stayed
bridge
Projet de corridor du nouveau pont Champlain
Highway 10
• Soil management
• Preparatory works for the configuration of the highway 10
East Approch
• Installation of prefabricated segments of piers and pier caps
• Construction of the east abutment, including the building housing the electric
systems
• Preparations for the construction of the span above Route 132
Cable-stayed bridge
• Construction of main pylon, rear and principal spans
South Shore
Priorities : May to September 2017
10
Projet de corridor du nouveau pont Champlain
Description of Activity
Approximate Duration of Works
Planned Work Period
Legend: Work and Impacts
• Traffic and Public Transportation:
• Proximity of Residential Areas:
• Boating:
• Bike Paths:
Minor impact
Medium impact
Major impact
Indication by level colour code
11
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come -
East Approach
Design and planning underway so modifications are possible
Projet de corridor du nouveau pont Champlain
Objective: Construction of East Approach of the new Champlain Bridge
Travaux en cours et à venir :
• Placement of prefabricated segments of piers and pier caps
• Continue the construction of the abutment, including the building housing the
electric systems
• Preparatory works for the construction of the span above Highway 132
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels)
are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic are
too significant
East Approach Area
13
Projet de corridor du nouveau pont Champlain
Nov
2015
May Nov
2016
May Nov.
2017
Nov
2018
May
East Approach: Timetable
14
Feb
2016
Aug Feb
2017
Aug. Feb.
2018
Aug.
Construction of
footings and pier
bases
Installation of piers and pier
caps
Assembly of superstructure and
deck
Finishing work
Projet de corridor du nouveau pont Champlain 15
Placement of prefabricated segments
of piers and pier caps
Duration: 15 months
Projected period: October 2016 to January 2018
Works and Impacts: East Approach
Projet de corridor du nouveau pont Champlain 16
Construction of East Abutment’s building
Duration: three months
Projected period: May to July 2017
Works and Impacts: East Approach
Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
Preparatory works for the construction of the span
above Highway 132
Duration : four months
Projected period: Fall 2017
17
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Highway 10
Conception et planification en développement
donc des modifications sont possibles
Projet de corridor du nouveau pont Champlain
Highway 10 Area
19
Objective: Area reserved for soil management for the work site and preparatory
work for the reconfiguration of highway links
Work underway:
• Soil storage
• Creation of a retaining basin for permanent drainage
• Earthworks at the eastern abutment
Upcoming Works
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Night-time trucking from the West Approach to the East Approach
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Soil management and creation of a retaining basin
Duration: throughout the project
Projected period: 2016 to 2019
20
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Installation of permanent anti-noise walls
Duration : three months
Projected period: fall 2017
21
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Cable-stayed Bridge
Design and planning underway so modifications are possible
Projet de corridor du nouveau pont Champlain
Cable-stayed Bridge: Timetable
23
2. Pylon foundations
October 2015 to April 20161. Jetty
August to October 2015
7. Main span
March 2017 to
September 2018
3. Rear span
November 2015 to July 2017
6. Upper pylon
February to December
2017
4. Lower pylon
May to October 2016
5. Lower crossbeam
October to February 2017
Projet de corridor du nouveau pont Champlain
Key activities since winter 2017
24Construction of the rear span
Projet de corridor du nouveau pont Champlain
Key activities since winter 2017
Construction of the main pylon and the principal span
Projet de corridor du nouveau pont Champlain
Works and impacts : Bike path of the
seaway dike
26
Ponctual closing of variable duration and variable frequency
--from a few hours up to a few days--
Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
Projet de corridor du nouveau pont Champlain
Anticipated Impacts
Projet de corridor du nouveau pont Champlain
Anticipated impacts
• Road traffic
• Noise
• Air quality
• Navigation
28
Projet de corridor du nouveau pont Champlain
Traffic
• PJCCI’s Major Work Blitz
 May 20 / 21 : Complete closure of the Hwy-15 South heading to South Shore
 May 27 / 28 : Complete closure of the Hwy-15 North heading to Montreal
• Disruptions to come
• Upcoming major disruptions for the Fall 2017 : installation of
superstructure and deck above Highway 132 traffic lanes
29
Configuration – Disruptions Schedule Duration
Installation of foundations and temporary
scaffolding
Summer 2017 3 weeks
Passage of pier caps pieces
Summer / Fall
2017
8 nights
Route Deviation from route 132 & boul.
Marie-Victorin
Fall 2017 18 months
Projet de corridor du nouveau pont Champlain
Example of temporary scaffolding
30
Projet de corridor du nouveau pont Champlain
Passage of Pier Caps Pieces
31
Projet de corridor du nouveau pont Champlain
Steel Pier Caps
32
Projet de corridor du nouveau pont Champlain 33
B1: Turenne area
B2: Voltaire area
B3: Tisserand area
Noise Management
Preparatory works Highway
132
Area
Activity
Period
D/E/N
Exposed
sensitive
area
Ambient
noise dBA
Criterion
dBA
Estimated
noise dBA
Required
measures
EastApproach
Placement of prefabricated segments of
piers and pier caps
D B1 / B2 60 / 62 75 62 / 63 Not required
Construction
of building (east abutment)
D B2 62 75 71 Not required
Preparatory works Highway 132 D / E –N B2 62 75 / 67 To come
Hgw
10
Installation of permanent anti-noise
walls
D B2 62 75 75
Monitoring
required
Cable-
Stayed
Miscellaneous work D B1 / B2 60 / 62 75 62 / 63 Not required
Projet de corridor du nouveau pont Champlain
Air Quality Management
• Migitation measures : increased environmental monitoring + Frequent
water spaying and cleaning
• Regulatory framework : Contractual environmental obligations and
Clean Air Regulation (CAR)
Applicable MDDELCC standards
MDDELCC CAR
PMt PM2.5
120 ug/m3 30 ug/m3
34
Projet de corridor du nouveau pont Champlain
Water traffic
35
Background
• Work site in water as well as a transport
corridor for heavy parts between the Port of
Montreal and the cable-stayed bridge area
• Navigational vigilance in the St. Lawrence
and in the Lesser La Prairie Basin
Main mitigation measures
• Communication
• Waterway signs and marking
• Patrolling and nautical surveillance
• Equipment lighting
• Information session with the users of the river
Projet de corridor du nouveau pont Champlain
Follow-uo
Projet de corridor du nouveau pont Champlain
Follow-up on Interventions
37
SSL
• Date for the installations of anti-noise walls
• Landscaping and building of the east abutment
INFC
• LED lighting tracking : return of MTMDET and Toronto case study
Ville de Brossard
• Follow-up on plantation planned in the Champlain park
Projet de corridor du nouveau pont Champlain
• Site visit
 Elected : April 28
 Good Neighbourly Relations Committee and municipal administrators : May
5
 Media : May 19
• Newsletter: sign up online
• Notice sent by post to citizen, if required, and local newspaper notices
• Sign up / contact us:
 Website: www.newchamplain.ca
 Email: info@sslc.ca
 Phone us at: (514) 876-1020
 Twitter: @NOUV_CHAMPLAIN
Communications
38
Projet de corridor du nouveau pont Champlain
Next meetings
Projet de corridor du nouveau pont Champlain
Good Neighbourly Relations Committee :
 September 27 (To be confirmed)
 Topic : Landscaping
Next meetings
40

More Related Content

What's hot

Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Crosstown TO
 

What's hot (20)

Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
 
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
Meeting of the verdun  sud ouest good neighbourly relations committee - febru...Meeting of the verdun  sud ouest good neighbourly relations committee - febru...
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
 
Details of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlainDetails of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlain
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016
 
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
 
Presentation anti noise walls good neighbourly relations committee City of Br...
Presentation anti noise walls good neighbourly relations committee City of Br...Presentation anti noise walls good neighbourly relations committee City of Br...
Presentation anti noise walls good neighbourly relations committee City of Br...
 
Minute meetings june 21 2107 - verdun sud-ouest good neighbourly relations ...
Minute meetings   june 21 2107 - verdun sud-ouest good neighbourly relations ...Minute meetings   june 21 2107 - verdun sud-ouest good neighbourly relations ...
Minute meetings june 21 2107 - verdun sud-ouest good neighbourly relations ...
 
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
Noise management: Meeting of the Verdun/Sud-Ouest Good Neighbourly Relations ...
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
 
Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
Gaétan Laberge sector mobility scenario - Meeting of the Verdun / Sud-Ouest G...
 
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 

Similar to Brossard Good Neighbourly Relations Committee - May 17, 2017

Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
Crosstown TO
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
Robert Lee - CEng, MICE, PMP
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Crosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
Crosstown TO
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO
 

Similar to Brossard Good Neighbourly Relations Committee - May 17, 2017 (20)

2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Review of work in 2016
Review of work in 2016Review of work in 2016
Review of work in 2016
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Plan for major repairs and maintenance work on JCCBI structures
Plan for major repairs and maintenance work on JCCBI structuresPlan for major repairs and maintenance work on JCCBI structures
Plan for major repairs and maintenance work on JCCBI structures
 
JCCBI 2015 Project Report
JCCBI 2015 Project ReportJCCBI 2015 Project Report
JCCBI 2015 Project Report
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
2018 Planning
2018 Planning2018 Planning
2018 Planning
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016
 
Queen street station tunnel or throat development rodger querns
Queen street station tunnel or throat development  rodger quernsQueen street station tunnel or throat development  rodger querns
Queen street station tunnel or throat development rodger querns
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
 

More from Pont Samuel-De Champlain Bridge

More from Pont Samuel-De Champlain Bridge (20)

Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
 
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
 
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
 
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
 
Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019
 
Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019
 
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
 
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
 
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
 
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
 
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
 
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
 
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
 
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
 
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
 
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
 
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
 
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
 
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
 
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
 

Recently uploaded

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 

Brossard Good Neighbourly Relations Committee - May 17, 2017

  • 1. Good Neighbourly Relations Committee Meeting City of Brossard : May 17 2017 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau Please note that the English version is used only for refernce purposes. In case of disrepancy between the English and French versions, the French version shall prevail.
  • 2. Projet de corridor du nouveau pont Champlain 2 Committee Members Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Goreti Fernandes Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada
  • 3. Projet de corridor du nouveau pont Champlain 1. Provide information about the work that has been completed, is underway and planned between now and fall 2017 2. Answer questions, find potential solutions and discuss the issues Objectives of the Meeting 3
  • 4. Projet de corridor du nouveau pont Champlain Agenda 4 Série Item Durée Heure 1. Opening 10 min. 19h00 à 19h10 2. Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area 40 min. 19h10 à 19h50 3. Question period 20 min. 19h50 à 20h10 4. Varia 15 min. 20h10 à 20h25 5. Adjournment: next meeting and topic 5 min. 20h25 à 20h30
  • 5. Projet de corridor du nouveau pont Champlain Work Completed over the Past Few Months
  • 6. Projet de corridor du nouveau pont Champlain Work Completed over the Past Few Months • Winter season: good work progress in general on the East Approach  End of the earthworks of the east abutment  More than 75% of the piers segments were installed (70 out of 90)  Beginning of the pre-assembly of girders  Two complaints since January 25 • First partial closure of the 132 highway and the Blvd. Marie-Victorin
  • 7. Projet de corridor du nouveau pont Champlain Main Priorities for the Upcoming Months- South Shore
  • 8. Projet de corridor du nouveau pont Champlain 8 South Shore: Overview Works mainly completed at the opening of the New Champlain Bridge in late 2018 Adjustment of ramps for access and exit to the New Champlain Bridge New Champlain Bridge Construction Construction of a new bike access to the New Champlain Bridge
  • 9. Projet de corridor du nouveau pont Champlain Location of Work Areas City of Brossard Cable-stayed bridge
  • 10. Projet de corridor du nouveau pont Champlain Highway 10 • Soil management • Preparatory works for the configuration of the highway 10 East Approch • Installation of prefabricated segments of piers and pier caps • Construction of the east abutment, including the building housing the electric systems • Preparations for the construction of the span above Route 132 Cable-stayed bridge • Construction of main pylon, rear and principal spans South Shore Priorities : May to September 2017 10
  • 11. Projet de corridor du nouveau pont Champlain Description of Activity Approximate Duration of Works Planned Work Period Legend: Work and Impacts • Traffic and Public Transportation: • Proximity of Residential Areas: • Boating: • Bike Paths: Minor impact Medium impact Major impact Indication by level colour code 11
  • 12. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come - East Approach Design and planning underway so modifications are possible
  • 13. Projet de corridor du nouveau pont Champlain Objective: Construction of East Approach of the new Champlain Bridge Travaux en cours et à venir : • Placement of prefabricated segments of piers and pier caps • Continue the construction of the abutment, including the building housing the electric systems • Preparatory works for the construction of the span above Highway 132 Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant East Approach Area 13
  • 14. Projet de corridor du nouveau pont Champlain Nov 2015 May Nov 2016 May Nov. 2017 Nov 2018 May East Approach: Timetable 14 Feb 2016 Aug Feb 2017 Aug. Feb. 2018 Aug. Construction of footings and pier bases Installation of piers and pier caps Assembly of superstructure and deck Finishing work
  • 15. Projet de corridor du nouveau pont Champlain 15 Placement of prefabricated segments of piers and pier caps Duration: 15 months Projected period: October 2016 to January 2018 Works and Impacts: East Approach
  • 16. Projet de corridor du nouveau pont Champlain 16 Construction of East Abutment’s building Duration: three months Projected period: May to July 2017 Works and Impacts: East Approach
  • 17. Projet de corridor du nouveau pont Champlain Works and Impacts: East Approach Preparatory works for the construction of the span above Highway 132 Duration : four months Projected period: Fall 2017 17
  • 18. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come Highway 10 Conception et planification en développement donc des modifications sont possibles
  • 19. Projet de corridor du nouveau pont Champlain Highway 10 Area 19 Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links Work underway: • Soil storage • Creation of a retaining basin for permanent drainage • Earthworks at the eastern abutment Upcoming Works • Installation of permanent anti-noise walls Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Night-time trucking from the West Approach to the East Approach
  • 20. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Soil management and creation of a retaining basin Duration: throughout the project Projected period: 2016 to 2019 20
  • 21. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Installation of permanent anti-noise walls Duration : three months Projected period: fall 2017 21
  • 22. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come Cable-stayed Bridge Design and planning underway so modifications are possible
  • 23. Projet de corridor du nouveau pont Champlain Cable-stayed Bridge: Timetable 23 2. Pylon foundations October 2015 to April 20161. Jetty August to October 2015 7. Main span March 2017 to September 2018 3. Rear span November 2015 to July 2017 6. Upper pylon February to December 2017 4. Lower pylon May to October 2016 5. Lower crossbeam October to February 2017
  • 24. Projet de corridor du nouveau pont Champlain Key activities since winter 2017 24Construction of the rear span
  • 25. Projet de corridor du nouveau pont Champlain Key activities since winter 2017 Construction of the main pylon and the principal span
  • 26. Projet de corridor du nouveau pont Champlain Works and impacts : Bike path of the seaway dike 26 Ponctual closing of variable duration and variable frequency --from a few hours up to a few days-- Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
  • 27. Projet de corridor du nouveau pont Champlain Anticipated Impacts
  • 28. Projet de corridor du nouveau pont Champlain Anticipated impacts • Road traffic • Noise • Air quality • Navigation 28
  • 29. Projet de corridor du nouveau pont Champlain Traffic • PJCCI’s Major Work Blitz  May 20 / 21 : Complete closure of the Hwy-15 South heading to South Shore  May 27 / 28 : Complete closure of the Hwy-15 North heading to Montreal • Disruptions to come • Upcoming major disruptions for the Fall 2017 : installation of superstructure and deck above Highway 132 traffic lanes 29 Configuration – Disruptions Schedule Duration Installation of foundations and temporary scaffolding Summer 2017 3 weeks Passage of pier caps pieces Summer / Fall 2017 8 nights Route Deviation from route 132 & boul. Marie-Victorin Fall 2017 18 months
  • 30. Projet de corridor du nouveau pont Champlain Example of temporary scaffolding 30
  • 31. Projet de corridor du nouveau pont Champlain Passage of Pier Caps Pieces 31
  • 32. Projet de corridor du nouveau pont Champlain Steel Pier Caps 32
  • 33. Projet de corridor du nouveau pont Champlain 33 B1: Turenne area B2: Voltaire area B3: Tisserand area Noise Management Preparatory works Highway 132 Area Activity Period D/E/N Exposed sensitive area Ambient noise dBA Criterion dBA Estimated noise dBA Required measures EastApproach Placement of prefabricated segments of piers and pier caps D B1 / B2 60 / 62 75 62 / 63 Not required Construction of building (east abutment) D B2 62 75 71 Not required Preparatory works Highway 132 D / E –N B2 62 75 / 67 To come Hgw 10 Installation of permanent anti-noise walls D B2 62 75 75 Monitoring required Cable- Stayed Miscellaneous work D B1 / B2 60 / 62 75 62 / 63 Not required
  • 34. Projet de corridor du nouveau pont Champlain Air Quality Management • Migitation measures : increased environmental monitoring + Frequent water spaying and cleaning • Regulatory framework : Contractual environmental obligations and Clean Air Regulation (CAR) Applicable MDDELCC standards MDDELCC CAR PMt PM2.5 120 ug/m3 30 ug/m3 34
  • 35. Projet de corridor du nouveau pont Champlain Water traffic 35 Background • Work site in water as well as a transport corridor for heavy parts between the Port of Montreal and the cable-stayed bridge area • Navigational vigilance in the St. Lawrence and in the Lesser La Prairie Basin Main mitigation measures • Communication • Waterway signs and marking • Patrolling and nautical surveillance • Equipment lighting • Information session with the users of the river
  • 36. Projet de corridor du nouveau pont Champlain Follow-uo
  • 37. Projet de corridor du nouveau pont Champlain Follow-up on Interventions 37 SSL • Date for the installations of anti-noise walls • Landscaping and building of the east abutment INFC • LED lighting tracking : return of MTMDET and Toronto case study Ville de Brossard • Follow-up on plantation planned in the Champlain park
  • 38. Projet de corridor du nouveau pont Champlain • Site visit  Elected : April 28  Good Neighbourly Relations Committee and municipal administrators : May 5  Media : May 19 • Newsletter: sign up online • Notice sent by post to citizen, if required, and local newspaper notices • Sign up / contact us:  Website: www.newchamplain.ca  Email: info@sslc.ca  Phone us at: (514) 876-1020  Twitter: @NOUV_CHAMPLAIN Communications 38
  • 39. Projet de corridor du nouveau pont Champlain Next meetings
  • 40. Projet de corridor du nouveau pont Champlain Good Neighbourly Relations Committee :  September 27 (To be confirmed)  Topic : Landscaping Next meetings 40