SlideShare a Scribd company logo
LAYER OF PROTECTION
ANALYSIS (LOPA)
Layer of protection analysis (LOPA) is a semi-
quantitative tool for analyzing and assessing
risk.
History of LOPA
In a typical chemical process, various protection layers
are in place to lower the frequency of undesired
consequences:
• The process design (including inherently safer concepts);
• The basic process control system;
• Safety instrumented systems;
• Passive devices (such as dikes and blast walls);
• Active devices (such as relief valves);
• Human intervention; etc.
Decisions regarding the number of and
strength of protection layers were made
using subjective arguments, emotional
appeals, and occasionally simply by the
loudness or persistence of an individual.
KEY QUESTIONS FOR PROTECTION LAYERS
• How safe is safe enough?
• How many protection layers are needed?
• How much risk reduction should each layer
provide?
LOPA answers the key questions about the
number and strength of protection layers
by
• Providing rational, semi-quantitative, risk-
based answers,
• Reducing emotionalism,
• Providing clarity and consistency,
• Documenting the basis of the decision,
• Facilitating understanding among plant
personnel.
Use of LOPA in the Process Life Cycle
• The design stage when the process flow
diagram and the P&IDs are essentially
complete. LOPA is used to examine
scenarios, often generated by other
process hazard analysis (PHA) tools,
such as HAZOP, what-if, checklist, etc.
• Modifications to an existing process or
its control or safety systems (i.e.,
management of change).
The process life cycle showing where LOPA is
typically used
LOPA can also be used in all phases of the process life
cycle such as:
• Initial conceptual process design.
• Regular cycle of process hazard analyses (PHAs)
performed on a process.
• To determine if the risk is tolerable for a process, or If
an SIF is required.
• Reliability of equipments used in a process.
• To identify operator actions and responses that are
critical to the safety of the process.
• Also used for risk assessment of transportation
studies (road, rail, pipelines etc.) , auditing, loss
prevention, insurance issues etc.
What is LOPA?
LOPA is a simplified form of risk assessment.
LOPA typically uses order of magnitude
categories for initiating event frequency,
consequence severity, and the likelihood of
failure of independent protection layers (IPLs)
to approximate the risk of a scenario.
The primary purpose of LOPA is to determine
if there are sufficient layers of protection against
an accident scenario.
Layer of defense against a possible accident
What LOPA Does
Provides a method to reproducibly evaluate
the risk of selected accident scenarios.
A scenario is typically identified during a
qualitative hazard evaluation (HE), such as a
PHA, management of change evaluation, or
design review.
LOPA is limited to evaluating a single cause–
consequence pair as a scenario.
When to Use LOPA
• LOPA is typically applied after a qualitative
hazard evaluation (e.g., PHA) using the
scenarios identified by the qualitative
hazard review team.
• LOPA can also be used as a screening tool
prior to a more rigorous quantitative risk
assessment (CPQRA) method.
• The decision to proceed to CPQRA is
typically based on the risk level determined
by LOPA or based on the opinion of the
LOPA analyst.
Spectrum of tools for risk-based decision making
How LOPA Works
1. Identify the consequence to screen the
scenarios.
2. Select an accident scenario.
3. Identify the initiating event of the scenarios and
determine the initiating event frequency.
4. Identify the IPLs and estimate the probability of
failure on demand of each IPL.
5. Estimate the risk of the scenario by
mathematically combining the consequence,
initiating event, and IPL data.
6. Evaluate the risk to reach a decision concerning
the scenario.
How LOPA Works
How to Implement LOPA
• LOPA can be applied in a team setting, such as
during or immediately following a HAZOP- or
What-If–based review (e.g., PHA) used to
identify accident scenarios.
• LOPA can also be applied by a single analyst;
in this case, the scenarios have typically
already been identified for the analyst (such
as by a hazard evaluation team).
• Mostly companies practice LOPA with a sub-
team composed of the analyst and a process
engineer or production specialist.
Limitations of LOPA
• Risk comparisons of scenarios are valid only if the
comparisons are based on the same risk tolerance
criteria.
• The numbers generated by a LOPA calculation are not
precise values of the risk of a scenario.
• LOPA requires more time to reach a risk-based decision
than qualitative methods such as HAZOP and What-if.
• LOPA is not intended to be a hazard identification tool.
• Due to differences in risk tolerance criteria and in LOPA
implementation between organizations , the results
cannot be compared directly from one organization to
another.
Benefits of LOPA
• LOPA requires less time than quantitative
risk analysis.
• LOPA helps resolve conflicts in decision
making by providing a consistent, simplified
framework for estimating the risk.
• LOPA can improve the efficiency of hazard
evaluation meetings by providing a tool to
help reach risk judgments quicker.
• Determination of more precise cause–
consequence pairs.
• LOPA provides a means of comparing risk from
unit to unit or plant to plant.
• Provides more defensible comparative risk
judgments than qualitative methods.
• LOPA can be used to help an organization decide
if the risk is “as low as reasonably practicable”
(ALARP).
• LOPA helps identify operations and practices with
sufficient safeguards.
• LOPA helps provide the basis for a clear,
functional specification for an IPL.
• Information from LOPA helps an organization
decide which safeguards to focus on during
operation, maintenance, and related training.
Estimating the Consequence and Severity
Purpose
• Various types of consequence analysis are
used in LOPA to facilitate comparison of risk.
• The consequences are estimated to an order
of magnitude of severity.
Consequences of Interest
• Loss of containment of hazardous material
and energy by a variety of mechanisms such
as a leak from a vessel, rupture of a pipeline,
and lifting of a relief valve.
Consequence Evaluation Approaches for
LOPA
Consequence evaluation is an integral part of
any risk assessment methodology.
The different types of consequence evaluation
are:
• Release size/characterization
• Simplified injury/fatality estimates
• Simplified injury/fatality estimates with
adjustments
• Detailed injury/fatality estimates
Method 1: Category Approach without
Direct Reference to Human Harm
• This method typically uses matrices to
differentiate consequences into various
categories.
• Avoids any overt appearance that injuries
and fatalities are tolerable.
• Helps the team to make more accurate
judgments about relative risk.
Advantages:
• The method is simple and easy to
use because the size and properties
of the release are relatively easy to
assess.
• The method allows visual assessment
of where a given risk lies in relation
to the organization’s guidelines.
Method 2: Qualitative Estimates with Human
Harm
• This method uses the final impact to humans
as the consequence of interest, but arrives at
the value using purely qualitative judgment.
• The resulting risk of an injury/fatality can be
compared directly to a fatality risk tolerance
criterion for an individual event.
Advantages:
• Simplicity of understanding.
• Direct comparison with corporate guidelines.
Method 3: Qualitative Estimates with Human
Harm with Adjustments for Post-release
Probabilities
The LOPA analyst can initially estimate the
magnitude of a release “qualitatively” similar to
Method 2 and then later adjust the event
frequency by the probability that:
• The event will result in a flammable or toxic
cloud;
• For a flammable cloud, an ignition source will be
present;
• An individual will be present in the area when the
event occurs;
• The individual will experience a fatal (or injurious)
consequence.
Method 4: Quantitative Estimates with Human
Harm
• This method is similar to the qualitative
estimates with human harm method (Method
3), but uses detailed analyses in determining
the effects of a release and its effects upon
individuals and equipment.
• This method involves the use of mathematical
models to simulate the release itself, the
subsequent dispersion, and the toxic or
blast/thermal effect.
Developing Scenarios
• Scenario development is the LOPA step in
which the team or analyst constructs a
series of events, including initiating
events and the failure of IPLs
(independent protection layers), that
lead to an undesired consequence.
• A scenario is an unplanned event or
sequence of events that results in an
undesirable consequence.
Each scenario consists of at least two elements:
• An initiating event that starts the chain of
events and
• A consequence (the potential for over
pressuring the system, release of toxic or
flammable material to the atmosphere,
fatality, etc.) that results if the chain of events
continues without interruption.
Minimum Requirements for a scenario
• Each scenario must have a unique initiating
event/consequence pair.
• If the same initiating event can result in
different consequences, additional scenarios
should be developed.
A scenario may also include:
• Enabling events or conditions that have to
occur or be present before the initiating event
can result in a consequence.
• The failure of safeguards (which may be IPLs)
Coincident Initiating and Enabling Event
Coincident Initiating and Enabling Condition
Effect of IPL Failing to operate as intended
Identifying Candidate Scenarios
The most common source of
information for identifying scenarios
are hazard evaluations (HE)
developed and documented for
existing processes and performed
during the design of new and
modified processes
Other sources for identifying candidate
scenarios for LOPA are:
• Issues related to plant operation.
• incidents in the process, or from other
processes.
• the requirement to change the process.
• Interlock reviews to assess whether the
safety instrumented function (SIF)—
interlock—is required.
Scenario Development
Once a scenario has been identified,
it must be developed and
documented to the level where a
basic understanding of the events
and safeguards is achieved.
Identifying Initiating Event Frequency
• For LOPA, each scenario has a single
initiating event
• The frequency of the initiating event is
normally expressed in events per year.
Types of Initiating Events
• Initiating events are grouped into three
general types: external events,
equipment failures, and human failures.
Types of Initiating Events
Root Cause
Defined as an underlying system-related (the
most basic) reason why an incident occurred”
• Initiating events can be the result of various
underlying root causes such as external
events, equipment failures, or human
failures.
• Root causes are not the same as initiating
events
• Root causes can, however, contribute to
determining the frequency of occurrence of
the initiating event.
Enabling Events/Conditions
• In some scenarios, the initiating event
may not be obvious.
• In complex scenarios (where initiating or
triggering event is not clear), there may
be other factors that are neither failures
nor protection layers.
• These factors are called enabling events
or conditions.
Frequency Estimation
Failure Rate Data
• Guidelines for Chemical Process Quantitative Risk
Analysis (CCPS)
• Guidelines for Process Equipment Reliability Data
(CCPS)
• IEEE
• EuReData
• OREDA
• Company experience (including hazard analysis team
experience)
• Vendor data
Selection of Failure Rates
• Failure rates should be consistent with
the basic design of the facility.
• All the failure rates used should be from
the same location in the data range.
• The failure rate data selected should be
representative of the industry or
operation under consideration.
Expression of Failure Rates
• Decimal systems,
• Scientific notation- or exponent-based systems.
• Integer systems.
Independent Protection Layers
An IPL is a device, system, or action
that is capable of preventing a scenario
from proceeding to its undesired
consequence, independent of the
initiating event or the action of any other
layer of protection associated with the
scenario.
Event tree showing effect of IPL success or failure when demanded
All IPLs are safeguards, but not all
safeguards are IPLs.
• A safeguard is any device, system, or
action that would likely interrupt the chain
of events following an initiating event.
Safeguards can be classified as:
• Active or passive,
• Preventive (prerelease) or mitigating (post
release)
Protection Layers in LOPA
• Process Design
• Basic Process Control Systems
• Critical Alarms and Human Interventions
• Safety Instrumented Function (SIF)
• Physical Protection (Relief Valves, Rupture
Discs, etc.)
• Post-release Protection (Dikes, Blast Walls,
etc.)
• Plant Emergency Response
• Community Emergency Response
Process Design
• Inherently safer design of the process
equipment
• Scenarios are eliminated by the inherently
safer design
• Some inherently safer process design
features are considered to have a non-zero
PFD. They do have possible failure modes
that have been observed in industry. These
companies consider such inherently safer
process design features as IPLs.
• Whether process design should be
credited as an IPL, or considered as a
method of eliminating a scenario,
depends upon the method employed
within a particular organization
Basic Process Control Systems
• The basic process control system (BPCS),
including normal manual controls, is the first
level of protection during normal operation
• The normal operation of a BPCS control loop
can be credited as an IPL
• Failure of the BPCS can be an initiating event
• When using the BPCS as an IPL, the analyst
must evaluate the effectiveness of the access
control and security systems as human error
can degrade the performance of the BPCS
Critical Alarms and Human Intervention
• These systems are the second level of
protection during normal operation and
should be activated by the BPCS
• Operator action, initiated by alarms or
observation, can be credited as an IPL
• Company procedures and training may
improve the performance of humans in
the system, but procedures themselves
are not an IPL
Safety Instrumented Function (SIF)
• A SIF is a combination of sensors, logic
solver, and final elements with a specified
safety integrity level that detects an out-of-
limit (abnormal) condition and brings the
process to a functionally safe state.
• SIF is normally considered to be an IPL
• The design of the system, the level of
redundancy, and the amount and type of
testing will determine the PFD the SIF
receives in LOPA
Physical Protection (Relief Valves, Rupture
Discs, etc.)
• These devices, when appropriately sized,
designed and maintained, are IPLs which can
provide a high degree of protection
Post-release Protection (Dikes, Blast Walls, etc.)
• These IPLs are passive devices which provide a
high level of protection if designed and
maintained correctly.
• Failure rates are low, but should be included in
the scenarios
Plant Emergency Response
• These features (fire brigade, manual
deluge systems, facility evacuation, etc.)
are not normally considered as IPLs since
they are activated after the initial release
• There are too many variables (e.g., time
delays) affecting their overall
effectiveness in mitigating a scenario.
Community Emergency Response
• These measures, which include
community evacuation and shelter-in-
place, are not normally considered as IPLs
since they are activated after the initial
release
• There are too many variables affecting
their effectiveness in mitigating a
scenario.
• They provide no protection for plant
personnel
IPL Rules
In order to be considered an IPL, a device,
system, or action must be:
• Effective in preventing the consequence
when it functions as designed,
• Independent of the initiating event and the
components of any other IPL
• Auditable; the assumed effectiveness in
terms of consequence prevention and PFD
must be capable of validation in some
manner.
Effectiveness
• A device, system or action must be effective in
preventing the undesired consequence
associated with the scenario.
Independence
• To assure that the effects of the initiating event,
or of other IPLs, do not interact with a specific IPL
Independence requires that an IPL’s effectiveness
is independent of:
• the occurrence, or consequences, of the initiating
event;
• the failure of any component of an IPL already
credited for the same scenario.
Auditability
• A component, system or action must be
auditable to demonstrate that it meets
the risk mitigation requirements of a
LOPA IPL.
• The audit should also confirm that the
IPL design, installation, functional
testing, and maintenance systems are in
place to achieve the specified PFD for the
IPL.
PFD Value for an IPL
The PFD for an IPL is the probability that,
when demanded, it will not perform the
required task. Failure to perform could be
caused by
• A component of an IPL being in a failed or
unsafe state when the initiating event occurs
• A component failing during the performance
of its task
• Human intervention failing to be effective, etc.
Examples of IPLs
• Passive IPLs
• Active IPLs
• Instrumented Systems
• Basic Process Control System (BPCS)
• Safety Instrumented Systems (SIS)
• Vendor Installed Safeguards
• Deluges, Sprays, Foam Systems, and other
Firefighting Mitigation Systems
• Pressure Relief Devices
• Human IPLs
Passive IPLs
• A passive IPL is not required to take an action
in order for it to achieve its function in
reducing risk.
• These achieve the intended function if their
process or mechanical design is correct and if
constructed, installed, and maintained
correctly.
• Examples are tank dikes, blast walls or
bunkers, fireproofing, flame or detonation
arrestors, etc.
Active IPLs
Active IPLs are required to move from one state
to another in response to a change in a
measurable process property (e.g., temperature
or pressure), or a signal from another source
(such as a push-button or a switch).
Example:-
• a sensor of some type (instrument, mechanical,
or human),
• a decision-making process (logic solver, relay,
spring, human, etc.),
• an action (automatic, mechanical, or human).
Basic components of active IPL.
Instrumented Systems
These systems are a combination of sensors, logic
solvers, process controllers, and final elements that
work together, either to automatically regulate plant
operation, or to prevent the occurrence of a specific
event within a chemical manufacturing process.
Types of instrumented systems:-
• Continuous controller (e.g., the process
controller that regulates flow, temperature, or
pressure)
• State controller (the logic solver which takes
process measurements and executes on–off
changes to alarm indicators and to process
valves)
Basic Process Control System (BPCS)
It is the control system that continuously
monitors and controls the process in day-to-
day plant operation.
The BPCS may provide three different types of
safety functions that can be IPLs:
• continuous control action.
• state controllers providing information to
operators.
• state controllers providing automatic actions.
Safety Instrumented System (SIS)
A safety instrumented system (SIS) is a combination
of sensors, logic solvers and final elements that
performs one or more safety instrumented functions
(SIFs)
SIFs are state control functions, sometimes called
safety interlocks and safety critical alarms.
Each of the SIFs will have its own PFD value based
on
• the number and type of sensors, logic solvers, and
final control elements; and
• the time interval between periodic functional tests
of system components.
International standards have grouped SIFs for
application in the chemical process industry into
categories called Safety Integrity Levels (SILs).
SIL 1: PFD ≥ 1 × 10–2 to <1 × 10–1 (implemented
with a single sensor)
SIL 2: PFD ≥ 1 × 10–3 to <1 × 10–2 (fully
redundant from the sensor through the SIS
logic solver)
SIL 3: PFD ≥ 1×10–4 to <1 × 10–3
SIL 4 PFD ≥ 1×10–5 to <1 × 10–4 (These SIFs are
included in the IEC 61508 and 61511
standards)
Vendor Installed Safeguards
• Fired Equipment (burner management
systems including fire-eyes, purging
cycles, etc.)
• Rotating Equipment (vibration switches,
high-temperature detection, over-speed
protection, anti-surge protection, etc.)
Deluges, Sprays, Foam Systems, and Other
Firefighting Mitigation Systems
• Deluges, water sprays, foam systems may
be considered as IPLs for preventing the
ultimate release (e.g., a BLEVE, or
exothermic runaway reaction initiated by
external heat input)
• If the possibility of damage from the fire or
explosion could render them ineffective
then they should usually be considered
safeguards rather than IPLs
Pressure Relief Devices
• Pressure relief valves open when the
pressure under the valve exceeds the
pressure exerted by the spring holding
the valve closed
Human IPLs
• Human IPLs involve the reliance on
operators, or other staff, to take action to
prevent an undesired consequence, in
response to alarms or following a routine
check of the system
• (Guidelines for Preventing Human Error
in Process Safety; CCPS 1994b, and Swain
1983)
PREVENTIVE IPLs Versus MITIGATION IPLs
• Some IPLs are intended to prevent the scenario
from occurring and may be termed preventive
IPLs.
• IPLs intended to reduce the severity of the
consequence of the initiating event is termed as
mitigation IPLs.
• Examples of preventive IPLs are SIFs (e.g., steam
valve closure, emergency cooling water flow,
inhibitor addition.)
• Examples of mitigation IPLs is Pressure Relief
Devices.
Determining the Frequency of Scenarios
Quantitative Calculation of Risk and Frequency
Frequency of scenario = Initiating event
frequency multiplied by product of IPL PFDs.
Calculating the Frequency of Additional
Outcomes
• Flammable effects such as fire or
explosion.
• Toxic effects where applicable.
• Exposure to flammable or toxic effects.
• Injury or fatality.
To calculate the frequency of additional
outcomes, Equation is modified by multiplying
the frequency of the release scenario by the
appropriate probabilities for the outcome of
interest.
These include:
• The probability of ignition (Pignition)—for
flammable releases,
• The probability that personnel are in the affected
area (Pperson present )—a precursor parameter for
calculating exposures and injuries, and
• The probability that injury occurs (Pinjury)— for
injury or fatality.
• Frequency of a fire for a single scenario for a
single system.
• Frequency of a person exposed to a fire
• Frequency of a person injured in a fire
• Toxic effects by omitting the probability
of ignition
Calculation of Risk
RC
k = risk index of incident outcome of interest
k, expressed as a magnitude of consequences
per unit time.
fC
k = is the frequency of the incident outcome
of interest k, in year-1
Ck = factor related to the magnitude of the
consequences of incident outcome of interest
k. Ck might be expressed as a category
Using LOPA to make Risk Decision
• Decision making takes place after the
scenarios have been fully developed and
the existing risk has been calculated,
whether qualitative or quantitative
• The decisions regarding risk normally fall
into one of three general categories:
1. Manage the residual risk—continue the
management systems that maintain the
risk at its current (presumably tolerable)
level.
2. Modify (mitigate) the risk to make it
tolerable.
3. Abandon the risk (businesses, process,
etc.) because it is too high.
{Decisions to abandon operations are normally made as a
result of other studies such as quantitative risk assessment
(CPQRA)}
Three basic types of risk judgment are
used in conjunction with LOPA:
1. Compare the calculated risk with a
predetermined risk tolerance criteria.
2. Expert judgment by a qualified risk
analyst, (is not recommended by the
authors but is included for completeness.)
3. Relative comparison among competing
alternatives for risk reduction, using either
of the methods described above.
Comparing Calculated Risk to
Scenario Risk Tolerance Criteria
a) Matrix Methods
Method of visually showing the
frequency tolerable for a scenario based on
the consequence severity and the scenario
frequency
b) Numerical Criteria Method (Maximum
Tolerable Risk per Scenario)
• Risk criteria based on a maximum
tolerable risk per scenario
• For example, an organization can establish
as its criteria a maximum frequency (per
year or per 1000 hours) of a single fatality.
• Frequency of releases of hazardous
materials, fires, or property damage dollar
loss.
c) Number of IPL Credits
• Specify the number of IPL credits for
scenarios of certain consequence levels
and frequency
• Tabular values are provided for the
number of IPL credits for ranges of
initiating event frequency
• Tolerable criteria are not shown explicitly
• An IPL Credit is defined as a reduction in
event frequency of 1 × 10–2.
Expert Judgment
• When specific risk tolerance criteria are not
available
• The expert would compare the IPLs and other
features of the scenario to industry practice,
similar processes, or other points of reference
in his or her experience.
• Should not be a “Lone Ranger” approach
• Decisions should result from group
consultations, not from one or two people
operating in isolation.
Cost–Benefit for Relative Comparison
• Compares the cost of the avoided
consequence at its frequency versus the
cost of the IPL improvements to reduce
the risk
• Cost–benefit analysis is generally the
method used to select the IPLs for risk
reduction from among the candidate IPLs

More Related Content

What's hot

Process Safety
Process SafetyProcess Safety
Process Safety
Consultivo
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
Shirazeh arghami
 
Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management System
ACM Facility Safety
 
HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY
damomech92
 
Hazop ppt
Hazop pptHazop ppt
Hazop ppt
Sangeeta Phadke
 
Hazop method
Hazop methodHazop method
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
Doruk Kimyasal Yönetim Sistemeri
 
HZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by TonyHZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by TonyAnthony Izegaegbe
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
Triumvirate Environmental
 
Presentation hazop introduction
Presentation hazop introductionPresentation hazop introduction
Presentation hazop introduction
Sundararajan Thangavelu
 
Event tree analysis and risk assessment
Event tree analysis and risk assessmentEvent tree analysis and risk assessment
Event tree analysis and risk assessment
Salah Mansour
 
Process Hazard Analysis
Process Hazard AnalysisProcess Hazard Analysis
Process Hazard Analysis
NGE
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
aashir14
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
idell bryan
 
Bow Tie Risk Analysis
Bow Tie Risk AnalysisBow Tie Risk Analysis
Bow Tie Risk Analysis
John Kingsley
 
Hazop Study
Hazop StudyHazop Study
Hazop Study
Ihsan Wassan
 
Relief systems
Relief systemsRelief systems
Relief systems
A Ramesh Babu
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
TheSafetyGuru
 

What's hot (20)

Process Safety
Process SafetyProcess Safety
Process Safety
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
 
Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management System
 
HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY
 
Hazop ppt
Hazop pptHazop ppt
Hazop ppt
 
Hazop method
Hazop methodHazop method
Hazop method
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
HZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by TonyHZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by Tony
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
 
Presentation hazop introduction
Presentation hazop introductionPresentation hazop introduction
Presentation hazop introduction
 
Event tree analysis and risk assessment
Event tree analysis and risk assessmentEvent tree analysis and risk assessment
Event tree analysis and risk assessment
 
Process Hazard Analysis
Process Hazard AnalysisProcess Hazard Analysis
Process Hazard Analysis
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
 
Bow Tie Risk Analysis
Bow Tie Risk AnalysisBow Tie Risk Analysis
Bow Tie Risk Analysis
 
Hazop Study
Hazop StudyHazop Study
Hazop Study
 
Relief systems
Relief systemsRelief systems
Relief systems
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
 
management of change
management of changemanagement of change
management of change
 
HAZOP.PPT
HAZOP.PPTHAZOP.PPT
HAZOP.PPT
 

Similar to LOPA | Layer Of Protection Analysis | Gaurav Singh Rajput

Critical systems specification
Critical systems specificationCritical systems specification
Critical systems specificationAryan Ajmer
 
Hazard analysis
Hazard analysisHazard analysis
Hazard analysis
Reena Titoria
 
Risk assessment and management
Risk assessment and managementRisk assessment and management
Risk assessment and management
TaekHyeun Kim
 
Risk Assessment and Management.ppt
Risk Assessment and Management.pptRisk Assessment and Management.ppt
Risk Assessment and Management.ppt
BasauKhator1
 
HAZOP Process Hazard Analysis (PHA) PPT.pdf
HAZOP Process Hazard Analysis (PHA) PPT.pdfHAZOP Process Hazard Analysis (PHA) PPT.pdf
HAZOP Process Hazard Analysis (PHA) PPT.pdf
NadEem681471
 
Preliminary Hazard Analysis
Preliminary Hazard AnalysisPreliminary Hazard Analysis
Preliminary Hazard Analysis
MANIKANDAN V
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
Hayat khan
 
topic5 (2).ppt
topic5 (2).ppttopic5 (2).ppt
topic5 (2).ppt
Kameswara Rao Poranki
 
topic5.ppt
topic5.ppttopic5.ppt
topic5.ppt
ghgc1
 
topic5 (1).ppt
topic5 (1).ppttopic5 (1).ppt
topic5 (1).ppt
Hedi Ben Mohamed
 
Risk assessment
Risk assessmentRisk assessment
Risk assessment
AhmedAbdelHalimAhmed
 
Unit V - Hazard Indentification Techniques.pptx
Unit V - Hazard Indentification Techniques.pptxUnit V - Hazard Indentification Techniques.pptx
Unit V - Hazard Indentification Techniques.pptx
Narmatha D
 
mod 4.pdf ppt about the safety at industries
mod 4.pdf ppt about the safety at industriesmod 4.pdf ppt about the safety at industries
mod 4.pdf ppt about the safety at industries
Midhundas31
 
Application of FMEA to a Sterility Testing Isolator: A Case Study
Application of FMEA to a Sterility Testing Isolator: A Case StudyApplication of FMEA to a Sterility Testing Isolator: A Case Study
Application of FMEA to a Sterility Testing Isolator: A Case Study
Tim Sandle, Ph.D.
 
CISSP Chapter 1 Risk Management
CISSP Chapter 1  Risk ManagementCISSP Chapter 1  Risk Management
CISSP Chapter 1 Risk Management
Karthikeyan Dhayalan
 
crisc_wk_3.pptx
crisc_wk_3.pptxcrisc_wk_3.pptx
crisc_wk_3.pptx
dotco
 
HAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdfHAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdf
Farahbennour
 
Introduction to quality management system • Product quality review (PQR) • Qu...
Introduction to quality management system• Product quality review (PQR) • Qu...Introduction to quality management system• Product quality review (PQR) • Qu...
Introduction to quality management system • Product quality review (PQR) • Qu...
samahhamed3
 
HAZOP Module.pptx
HAZOP Module.pptxHAZOP Module.pptx
HAZOP Module.pptx
akaash13
 
What is HAZOP?
What is HAZOP?What is HAZOP?
What is HAZOP?
John Kingsley
 

Similar to LOPA | Layer Of Protection Analysis | Gaurav Singh Rajput (20)

Critical systems specification
Critical systems specificationCritical systems specification
Critical systems specification
 
Hazard analysis
Hazard analysisHazard analysis
Hazard analysis
 
Risk assessment and management
Risk assessment and managementRisk assessment and management
Risk assessment and management
 
Risk Assessment and Management.ppt
Risk Assessment and Management.pptRisk Assessment and Management.ppt
Risk Assessment and Management.ppt
 
HAZOP Process Hazard Analysis (PHA) PPT.pdf
HAZOP Process Hazard Analysis (PHA) PPT.pdfHAZOP Process Hazard Analysis (PHA) PPT.pdf
HAZOP Process Hazard Analysis (PHA) PPT.pdf
 
Preliminary Hazard Analysis
Preliminary Hazard AnalysisPreliminary Hazard Analysis
Preliminary Hazard Analysis
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
 
topic5 (2).ppt
topic5 (2).ppttopic5 (2).ppt
topic5 (2).ppt
 
topic5.ppt
topic5.ppttopic5.ppt
topic5.ppt
 
topic5 (1).ppt
topic5 (1).ppttopic5 (1).ppt
topic5 (1).ppt
 
Risk assessment
Risk assessmentRisk assessment
Risk assessment
 
Unit V - Hazard Indentification Techniques.pptx
Unit V - Hazard Indentification Techniques.pptxUnit V - Hazard Indentification Techniques.pptx
Unit V - Hazard Indentification Techniques.pptx
 
mod 4.pdf ppt about the safety at industries
mod 4.pdf ppt about the safety at industriesmod 4.pdf ppt about the safety at industries
mod 4.pdf ppt about the safety at industries
 
Application of FMEA to a Sterility Testing Isolator: A Case Study
Application of FMEA to a Sterility Testing Isolator: A Case StudyApplication of FMEA to a Sterility Testing Isolator: A Case Study
Application of FMEA to a Sterility Testing Isolator: A Case Study
 
CISSP Chapter 1 Risk Management
CISSP Chapter 1  Risk ManagementCISSP Chapter 1  Risk Management
CISSP Chapter 1 Risk Management
 
crisc_wk_3.pptx
crisc_wk_3.pptxcrisc_wk_3.pptx
crisc_wk_3.pptx
 
HAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdfHAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdf
 
Introduction to quality management system • Product quality review (PQR) • Qu...
Introduction to quality management system• Product quality review (PQR) • Qu...Introduction to quality management system• Product quality review (PQR) • Qu...
Introduction to quality management system • Product quality review (PQR) • Qu...
 
HAZOP Module.pptx
HAZOP Module.pptxHAZOP Module.pptx
HAZOP Module.pptx
 
What is HAZOP?
What is HAZOP?What is HAZOP?
What is HAZOP?
 

More from Gaurav Singh Rajput

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Gaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
Gaurav Singh Rajput
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Gaurav Singh Rajput
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
Gaurav Singh Rajput
 

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 

Recently uploaded

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 

Recently uploaded (20)

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 

LOPA | Layer Of Protection Analysis | Gaurav Singh Rajput

  • 2. Layer of protection analysis (LOPA) is a semi- quantitative tool for analyzing and assessing risk. History of LOPA In a typical chemical process, various protection layers are in place to lower the frequency of undesired consequences: • The process design (including inherently safer concepts); • The basic process control system; • Safety instrumented systems; • Passive devices (such as dikes and blast walls); • Active devices (such as relief valves); • Human intervention; etc.
  • 3. Decisions regarding the number of and strength of protection layers were made using subjective arguments, emotional appeals, and occasionally simply by the loudness or persistence of an individual. KEY QUESTIONS FOR PROTECTION LAYERS • How safe is safe enough? • How many protection layers are needed? • How much risk reduction should each layer provide?
  • 4. LOPA answers the key questions about the number and strength of protection layers by • Providing rational, semi-quantitative, risk- based answers, • Reducing emotionalism, • Providing clarity and consistency, • Documenting the basis of the decision, • Facilitating understanding among plant personnel.
  • 5. Use of LOPA in the Process Life Cycle • The design stage when the process flow diagram and the P&IDs are essentially complete. LOPA is used to examine scenarios, often generated by other process hazard analysis (PHA) tools, such as HAZOP, what-if, checklist, etc. • Modifications to an existing process or its control or safety systems (i.e., management of change).
  • 6. The process life cycle showing where LOPA is typically used
  • 7. LOPA can also be used in all phases of the process life cycle such as: • Initial conceptual process design. • Regular cycle of process hazard analyses (PHAs) performed on a process. • To determine if the risk is tolerable for a process, or If an SIF is required. • Reliability of equipments used in a process. • To identify operator actions and responses that are critical to the safety of the process. • Also used for risk assessment of transportation studies (road, rail, pipelines etc.) , auditing, loss prevention, insurance issues etc.
  • 8. What is LOPA? LOPA is a simplified form of risk assessment. LOPA typically uses order of magnitude categories for initiating event frequency, consequence severity, and the likelihood of failure of independent protection layers (IPLs) to approximate the risk of a scenario. The primary purpose of LOPA is to determine if there are sufficient layers of protection against an accident scenario.
  • 9. Layer of defense against a possible accident
  • 10. What LOPA Does Provides a method to reproducibly evaluate the risk of selected accident scenarios. A scenario is typically identified during a qualitative hazard evaluation (HE), such as a PHA, management of change evaluation, or design review. LOPA is limited to evaluating a single cause– consequence pair as a scenario.
  • 11.
  • 12. When to Use LOPA • LOPA is typically applied after a qualitative hazard evaluation (e.g., PHA) using the scenarios identified by the qualitative hazard review team. • LOPA can also be used as a screening tool prior to a more rigorous quantitative risk assessment (CPQRA) method. • The decision to proceed to CPQRA is typically based on the risk level determined by LOPA or based on the opinion of the LOPA analyst.
  • 13. Spectrum of tools for risk-based decision making
  • 14. How LOPA Works 1. Identify the consequence to screen the scenarios. 2. Select an accident scenario. 3. Identify the initiating event of the scenarios and determine the initiating event frequency. 4. Identify the IPLs and estimate the probability of failure on demand of each IPL. 5. Estimate the risk of the scenario by mathematically combining the consequence, initiating event, and IPL data. 6. Evaluate the risk to reach a decision concerning the scenario.
  • 16. How to Implement LOPA • LOPA can be applied in a team setting, such as during or immediately following a HAZOP- or What-If–based review (e.g., PHA) used to identify accident scenarios. • LOPA can also be applied by a single analyst; in this case, the scenarios have typically already been identified for the analyst (such as by a hazard evaluation team). • Mostly companies practice LOPA with a sub- team composed of the analyst and a process engineer or production specialist.
  • 17. Limitations of LOPA • Risk comparisons of scenarios are valid only if the comparisons are based on the same risk tolerance criteria. • The numbers generated by a LOPA calculation are not precise values of the risk of a scenario. • LOPA requires more time to reach a risk-based decision than qualitative methods such as HAZOP and What-if. • LOPA is not intended to be a hazard identification tool. • Due to differences in risk tolerance criteria and in LOPA implementation between organizations , the results cannot be compared directly from one organization to another.
  • 18. Benefits of LOPA • LOPA requires less time than quantitative risk analysis. • LOPA helps resolve conflicts in decision making by providing a consistent, simplified framework for estimating the risk. • LOPA can improve the efficiency of hazard evaluation meetings by providing a tool to help reach risk judgments quicker. • Determination of more precise cause– consequence pairs.
  • 19. • LOPA provides a means of comparing risk from unit to unit or plant to plant. • Provides more defensible comparative risk judgments than qualitative methods. • LOPA can be used to help an organization decide if the risk is “as low as reasonably practicable” (ALARP). • LOPA helps identify operations and practices with sufficient safeguards. • LOPA helps provide the basis for a clear, functional specification for an IPL. • Information from LOPA helps an organization decide which safeguards to focus on during operation, maintenance, and related training.
  • 20. Estimating the Consequence and Severity Purpose • Various types of consequence analysis are used in LOPA to facilitate comparison of risk. • The consequences are estimated to an order of magnitude of severity. Consequences of Interest • Loss of containment of hazardous material and energy by a variety of mechanisms such as a leak from a vessel, rupture of a pipeline, and lifting of a relief valve.
  • 21. Consequence Evaluation Approaches for LOPA Consequence evaluation is an integral part of any risk assessment methodology. The different types of consequence evaluation are: • Release size/characterization • Simplified injury/fatality estimates • Simplified injury/fatality estimates with adjustments • Detailed injury/fatality estimates
  • 22. Method 1: Category Approach without Direct Reference to Human Harm • This method typically uses matrices to differentiate consequences into various categories. • Avoids any overt appearance that injuries and fatalities are tolerable. • Helps the team to make more accurate judgments about relative risk.
  • 23. Advantages: • The method is simple and easy to use because the size and properties of the release are relatively easy to assess. • The method allows visual assessment of where a given risk lies in relation to the organization’s guidelines.
  • 24.
  • 25.
  • 26. Method 2: Qualitative Estimates with Human Harm • This method uses the final impact to humans as the consequence of interest, but arrives at the value using purely qualitative judgment. • The resulting risk of an injury/fatality can be compared directly to a fatality risk tolerance criterion for an individual event. Advantages: • Simplicity of understanding. • Direct comparison with corporate guidelines.
  • 27.
  • 28.
  • 29. Method 3: Qualitative Estimates with Human Harm with Adjustments for Post-release Probabilities The LOPA analyst can initially estimate the magnitude of a release “qualitatively” similar to Method 2 and then later adjust the event frequency by the probability that: • The event will result in a flammable or toxic cloud; • For a flammable cloud, an ignition source will be present; • An individual will be present in the area when the event occurs; • The individual will experience a fatal (or injurious) consequence.
  • 30. Method 4: Quantitative Estimates with Human Harm • This method is similar to the qualitative estimates with human harm method (Method 3), but uses detailed analyses in determining the effects of a release and its effects upon individuals and equipment. • This method involves the use of mathematical models to simulate the release itself, the subsequent dispersion, and the toxic or blast/thermal effect.
  • 31. Developing Scenarios • Scenario development is the LOPA step in which the team or analyst constructs a series of events, including initiating events and the failure of IPLs (independent protection layers), that lead to an undesired consequence. • A scenario is an unplanned event or sequence of events that results in an undesirable consequence.
  • 32. Each scenario consists of at least two elements: • An initiating event that starts the chain of events and • A consequence (the potential for over pressuring the system, release of toxic or flammable material to the atmosphere, fatality, etc.) that results if the chain of events continues without interruption. Minimum Requirements for a scenario
  • 33. • Each scenario must have a unique initiating event/consequence pair. • If the same initiating event can result in different consequences, additional scenarios should be developed. A scenario may also include: • Enabling events or conditions that have to occur or be present before the initiating event can result in a consequence. • The failure of safeguards (which may be IPLs)
  • 34. Coincident Initiating and Enabling Event Coincident Initiating and Enabling Condition
  • 35. Effect of IPL Failing to operate as intended
  • 36. Identifying Candidate Scenarios The most common source of information for identifying scenarios are hazard evaluations (HE) developed and documented for existing processes and performed during the design of new and modified processes
  • 37. Other sources for identifying candidate scenarios for LOPA are: • Issues related to plant operation. • incidents in the process, or from other processes. • the requirement to change the process. • Interlock reviews to assess whether the safety instrumented function (SIF)— interlock—is required.
  • 38. Scenario Development Once a scenario has been identified, it must be developed and documented to the level where a basic understanding of the events and safeguards is achieved.
  • 39.
  • 40.
  • 41. Identifying Initiating Event Frequency • For LOPA, each scenario has a single initiating event • The frequency of the initiating event is normally expressed in events per year. Types of Initiating Events • Initiating events are grouped into three general types: external events, equipment failures, and human failures.
  • 43. Root Cause Defined as an underlying system-related (the most basic) reason why an incident occurred” • Initiating events can be the result of various underlying root causes such as external events, equipment failures, or human failures. • Root causes are not the same as initiating events • Root causes can, however, contribute to determining the frequency of occurrence of the initiating event.
  • 44. Enabling Events/Conditions • In some scenarios, the initiating event may not be obvious. • In complex scenarios (where initiating or triggering event is not clear), there may be other factors that are neither failures nor protection layers. • These factors are called enabling events or conditions.
  • 45. Frequency Estimation Failure Rate Data • Guidelines for Chemical Process Quantitative Risk Analysis (CCPS) • Guidelines for Process Equipment Reliability Data (CCPS) • IEEE • EuReData • OREDA • Company experience (including hazard analysis team experience) • Vendor data
  • 46. Selection of Failure Rates • Failure rates should be consistent with the basic design of the facility. • All the failure rates used should be from the same location in the data range. • The failure rate data selected should be representative of the industry or operation under consideration.
  • 47.
  • 48. Expression of Failure Rates • Decimal systems, • Scientific notation- or exponent-based systems. • Integer systems.
  • 49. Independent Protection Layers An IPL is a device, system, or action that is capable of preventing a scenario from proceeding to its undesired consequence, independent of the initiating event or the action of any other layer of protection associated with the scenario.
  • 50. Event tree showing effect of IPL success or failure when demanded
  • 51. All IPLs are safeguards, but not all safeguards are IPLs. • A safeguard is any device, system, or action that would likely interrupt the chain of events following an initiating event. Safeguards can be classified as: • Active or passive, • Preventive (prerelease) or mitigating (post release)
  • 52. Protection Layers in LOPA • Process Design • Basic Process Control Systems • Critical Alarms and Human Interventions • Safety Instrumented Function (SIF) • Physical Protection (Relief Valves, Rupture Discs, etc.) • Post-release Protection (Dikes, Blast Walls, etc.) • Plant Emergency Response • Community Emergency Response
  • 53. Process Design • Inherently safer design of the process equipment • Scenarios are eliminated by the inherently safer design • Some inherently safer process design features are considered to have a non-zero PFD. They do have possible failure modes that have been observed in industry. These companies consider such inherently safer process design features as IPLs.
  • 54. • Whether process design should be credited as an IPL, or considered as a method of eliminating a scenario, depends upon the method employed within a particular organization
  • 55. Basic Process Control Systems • The basic process control system (BPCS), including normal manual controls, is the first level of protection during normal operation • The normal operation of a BPCS control loop can be credited as an IPL • Failure of the BPCS can be an initiating event • When using the BPCS as an IPL, the analyst must evaluate the effectiveness of the access control and security systems as human error can degrade the performance of the BPCS
  • 56. Critical Alarms and Human Intervention • These systems are the second level of protection during normal operation and should be activated by the BPCS • Operator action, initiated by alarms or observation, can be credited as an IPL • Company procedures and training may improve the performance of humans in the system, but procedures themselves are not an IPL
  • 57. Safety Instrumented Function (SIF) • A SIF is a combination of sensors, logic solver, and final elements with a specified safety integrity level that detects an out-of- limit (abnormal) condition and brings the process to a functionally safe state. • SIF is normally considered to be an IPL • The design of the system, the level of redundancy, and the amount and type of testing will determine the PFD the SIF receives in LOPA
  • 58. Physical Protection (Relief Valves, Rupture Discs, etc.) • These devices, when appropriately sized, designed and maintained, are IPLs which can provide a high degree of protection Post-release Protection (Dikes, Blast Walls, etc.) • These IPLs are passive devices which provide a high level of protection if designed and maintained correctly. • Failure rates are low, but should be included in the scenarios
  • 59. Plant Emergency Response • These features (fire brigade, manual deluge systems, facility evacuation, etc.) are not normally considered as IPLs since they are activated after the initial release • There are too many variables (e.g., time delays) affecting their overall effectiveness in mitigating a scenario.
  • 60. Community Emergency Response • These measures, which include community evacuation and shelter-in- place, are not normally considered as IPLs since they are activated after the initial release • There are too many variables affecting their effectiveness in mitigating a scenario. • They provide no protection for plant personnel
  • 61.
  • 62. IPL Rules In order to be considered an IPL, a device, system, or action must be: • Effective in preventing the consequence when it functions as designed, • Independent of the initiating event and the components of any other IPL • Auditable; the assumed effectiveness in terms of consequence prevention and PFD must be capable of validation in some manner.
  • 63. Effectiveness • A device, system or action must be effective in preventing the undesired consequence associated with the scenario. Independence • To assure that the effects of the initiating event, or of other IPLs, do not interact with a specific IPL Independence requires that an IPL’s effectiveness is independent of: • the occurrence, or consequences, of the initiating event; • the failure of any component of an IPL already credited for the same scenario.
  • 64. Auditability • A component, system or action must be auditable to demonstrate that it meets the risk mitigation requirements of a LOPA IPL. • The audit should also confirm that the IPL design, installation, functional testing, and maintenance systems are in place to achieve the specified PFD for the IPL.
  • 65. PFD Value for an IPL The PFD for an IPL is the probability that, when demanded, it will not perform the required task. Failure to perform could be caused by • A component of an IPL being in a failed or unsafe state when the initiating event occurs • A component failing during the performance of its task • Human intervention failing to be effective, etc.
  • 66. Examples of IPLs • Passive IPLs • Active IPLs • Instrumented Systems • Basic Process Control System (BPCS) • Safety Instrumented Systems (SIS) • Vendor Installed Safeguards • Deluges, Sprays, Foam Systems, and other Firefighting Mitigation Systems • Pressure Relief Devices • Human IPLs
  • 67. Passive IPLs • A passive IPL is not required to take an action in order for it to achieve its function in reducing risk. • These achieve the intended function if their process or mechanical design is correct and if constructed, installed, and maintained correctly. • Examples are tank dikes, blast walls or bunkers, fireproofing, flame or detonation arrestors, etc.
  • 68.
  • 69. Active IPLs Active IPLs are required to move from one state to another in response to a change in a measurable process property (e.g., temperature or pressure), or a signal from another source (such as a push-button or a switch). Example:- • a sensor of some type (instrument, mechanical, or human), • a decision-making process (logic solver, relay, spring, human, etc.), • an action (automatic, mechanical, or human).
  • 70. Basic components of active IPL.
  • 71. Instrumented Systems These systems are a combination of sensors, logic solvers, process controllers, and final elements that work together, either to automatically regulate plant operation, or to prevent the occurrence of a specific event within a chemical manufacturing process. Types of instrumented systems:- • Continuous controller (e.g., the process controller that regulates flow, temperature, or pressure) • State controller (the logic solver which takes process measurements and executes on–off changes to alarm indicators and to process valves)
  • 72. Basic Process Control System (BPCS) It is the control system that continuously monitors and controls the process in day-to- day plant operation. The BPCS may provide three different types of safety functions that can be IPLs: • continuous control action. • state controllers providing information to operators. • state controllers providing automatic actions.
  • 73. Safety Instrumented System (SIS) A safety instrumented system (SIS) is a combination of sensors, logic solvers and final elements that performs one or more safety instrumented functions (SIFs) SIFs are state control functions, sometimes called safety interlocks and safety critical alarms. Each of the SIFs will have its own PFD value based on • the number and type of sensors, logic solvers, and final control elements; and • the time interval between periodic functional tests of system components.
  • 74. International standards have grouped SIFs for application in the chemical process industry into categories called Safety Integrity Levels (SILs). SIL 1: PFD ≥ 1 × 10–2 to <1 × 10–1 (implemented with a single sensor) SIL 2: PFD ≥ 1 × 10–3 to <1 × 10–2 (fully redundant from the sensor through the SIS logic solver) SIL 3: PFD ≥ 1×10–4 to <1 × 10–3 SIL 4 PFD ≥ 1×10–5 to <1 × 10–4 (These SIFs are included in the IEC 61508 and 61511 standards)
  • 75. Vendor Installed Safeguards • Fired Equipment (burner management systems including fire-eyes, purging cycles, etc.) • Rotating Equipment (vibration switches, high-temperature detection, over-speed protection, anti-surge protection, etc.)
  • 76. Deluges, Sprays, Foam Systems, and Other Firefighting Mitigation Systems • Deluges, water sprays, foam systems may be considered as IPLs for preventing the ultimate release (e.g., a BLEVE, or exothermic runaway reaction initiated by external heat input) • If the possibility of damage from the fire or explosion could render them ineffective then they should usually be considered safeguards rather than IPLs
  • 77. Pressure Relief Devices • Pressure relief valves open when the pressure under the valve exceeds the pressure exerted by the spring holding the valve closed
  • 78. Human IPLs • Human IPLs involve the reliance on operators, or other staff, to take action to prevent an undesired consequence, in response to alarms or following a routine check of the system • (Guidelines for Preventing Human Error in Process Safety; CCPS 1994b, and Swain 1983)
  • 79.
  • 80. PREVENTIVE IPLs Versus MITIGATION IPLs • Some IPLs are intended to prevent the scenario from occurring and may be termed preventive IPLs. • IPLs intended to reduce the severity of the consequence of the initiating event is termed as mitigation IPLs. • Examples of preventive IPLs are SIFs (e.g., steam valve closure, emergency cooling water flow, inhibitor addition.) • Examples of mitigation IPLs is Pressure Relief Devices.
  • 81. Determining the Frequency of Scenarios Quantitative Calculation of Risk and Frequency Frequency of scenario = Initiating event frequency multiplied by product of IPL PFDs.
  • 82. Calculating the Frequency of Additional Outcomes • Flammable effects such as fire or explosion. • Toxic effects where applicable. • Exposure to flammable or toxic effects. • Injury or fatality.
  • 83. To calculate the frequency of additional outcomes, Equation is modified by multiplying the frequency of the release scenario by the appropriate probabilities for the outcome of interest. These include: • The probability of ignition (Pignition)—for flammable releases, • The probability that personnel are in the affected area (Pperson present )—a precursor parameter for calculating exposures and injuries, and • The probability that injury occurs (Pinjury)— for injury or fatality.
  • 84. • Frequency of a fire for a single scenario for a single system. • Frequency of a person exposed to a fire
  • 85. • Frequency of a person injured in a fire • Toxic effects by omitting the probability of ignition
  • 86. Calculation of Risk RC k = risk index of incident outcome of interest k, expressed as a magnitude of consequences per unit time. fC k = is the frequency of the incident outcome of interest k, in year-1 Ck = factor related to the magnitude of the consequences of incident outcome of interest k. Ck might be expressed as a category
  • 87. Using LOPA to make Risk Decision • Decision making takes place after the scenarios have been fully developed and the existing risk has been calculated, whether qualitative or quantitative • The decisions regarding risk normally fall into one of three general categories:
  • 88. 1. Manage the residual risk—continue the management systems that maintain the risk at its current (presumably tolerable) level. 2. Modify (mitigate) the risk to make it tolerable. 3. Abandon the risk (businesses, process, etc.) because it is too high. {Decisions to abandon operations are normally made as a result of other studies such as quantitative risk assessment (CPQRA)}
  • 89. Three basic types of risk judgment are used in conjunction with LOPA: 1. Compare the calculated risk with a predetermined risk tolerance criteria. 2. Expert judgment by a qualified risk analyst, (is not recommended by the authors but is included for completeness.) 3. Relative comparison among competing alternatives for risk reduction, using either of the methods described above.
  • 90. Comparing Calculated Risk to Scenario Risk Tolerance Criteria a) Matrix Methods Method of visually showing the frequency tolerable for a scenario based on the consequence severity and the scenario frequency
  • 91.
  • 92. b) Numerical Criteria Method (Maximum Tolerable Risk per Scenario) • Risk criteria based on a maximum tolerable risk per scenario • For example, an organization can establish as its criteria a maximum frequency (per year or per 1000 hours) of a single fatality. • Frequency of releases of hazardous materials, fires, or property damage dollar loss.
  • 93. c) Number of IPL Credits • Specify the number of IPL credits for scenarios of certain consequence levels and frequency • Tabular values are provided for the number of IPL credits for ranges of initiating event frequency • Tolerable criteria are not shown explicitly • An IPL Credit is defined as a reduction in event frequency of 1 × 10–2.
  • 94.
  • 95. Expert Judgment • When specific risk tolerance criteria are not available • The expert would compare the IPLs and other features of the scenario to industry practice, similar processes, or other points of reference in his or her experience. • Should not be a “Lone Ranger” approach • Decisions should result from group consultations, not from one or two people operating in isolation.
  • 96. Cost–Benefit for Relative Comparison • Compares the cost of the avoided consequence at its frequency versus the cost of the IPL improvements to reduce the risk • Cost–benefit analysis is generally the method used to select the IPLs for risk reduction from among the candidate IPLs