SlideShare a Scribd company logo
1 of 10
Download to read offline
Libya, Benghazi
The “CONTRACT AREA 108” project
(Terra Rossa problem)
This document is dedicated to the foreign workers
in construction sites all over the world because they are
the essential stream which transfers and distributes
knowledge through countries.
A Google-earth snapshot showing the in brief the contract sites that Company XEKTE
SA , was constructing in 1980’s in Benghazi, Libya .
The Contractor Company XECTE SA (Benghazi branch) was considered to be a middle
sized contractor in Benghazi during the decade 1980-1990. At that time, the 2nd
Ring Road of
Benghazi, the “Shari Al Andalus” highway, some drainage networks around the city, and the
development of Urban Area 108A, were some of the projects that this company was constructing.
As a Contractor this Company had about one hundred workers, all foreigners, most of them
from Philippines, some from Pakistan and India, a few from Palestine, Syria, Egypt and other
countries as well. The leading personnel, Engineer Manager, Supervising Engineers, Surveyors,
Foremen, Operators of construction machines etc were all from Greece.
The Company operated a concrete pre-casting unit manufacturing cement tiles for
sidewalks, kerbs and concrete drainage pipes, one asphalt drum mix plant and a warehouse
providing maintenance for the fleet of heavy construction machines (excavators, trucks, graders etc)
that was in full operation. A mine for aggregates was occasionally operated in “El Abiar” providing
materials for the road construction.
The above mentioned projects, that were running that time, were also the main operational
concern of the Engineer Manager but as a Contractor the company was a provider of general
technical services to the Municipality of Benghazi such as repairs of public roads and substructures.
The general outline of the main projects was:
1. The 2nd
Ring Road of Benghazi project was a 5.5km road connecting Algeria street which
is close to harbor with “Assudan” Street in the area of “Northen Fwayhat”. The 2nd
Ring
Road was a two-way traffic, 12,0m / 15,0m wide with two lanes on each side. Six major
junctions, planting, drainage, traffic signs and street lighting were the complete design and
construction scheme of the contract.
2. The “Shari Al Andalus” project was the 3.4km city's section of a 9.9km highway leading
from the center of the city to the south suburbs.
3. The development of Urban Area 108A (contract 108A) concerned a complete and ready to
use network of local roads and consisted of the construction of Public Utilities such as water
supply network and house connections, sanitary sewerage (foul and gray waters) networks,
storm (surface) water drainage networks (manholes, inlets/gullies and drainage pipes), kerbs
and sidewalks, street lighting, base and sub base aggregate courses and two layers of asphalt
pavements. This contract imposed very strict specifications for road construction. Due to the
flat landscape, the design of the roads required a small gradient of no more than 0,1%
longitudinal slopes in favor of a sufficient drainage network. The accepted difference in
elevations between design and construction should have been less than 1,5 millimeters / km.
The outflows from sewers and storm water pipes were conveyed to the pumping stations.
Specifications that were applied to the works were for example AASHO T99-700, AASHO
T193-63, AASHO T 27-70 and BS 1377, BS 1881, BS 812 etc.
All the above projects were constructed under the same main articles of works as they
approved by the Municipality. However the applied specifications were causing technical or
compatibility problems having impact to the cost of works. For example the use of sulfur resisting
cement for the concrete sewers appurtenant structures and the gutters-kerbs as well, as the
specifications predicted instead of Pozzolanic cement, was a failure since this concrete was cracking
at the following the construction stages. Another example is the design of box culverts in some
locations were the circular shape was more appropriate. Further more the handling of dust on the
road’s surface during desert winds was a seasonal problem related to maintenance procedures.
During the time that I was assigned as a Deputy Engineer to the project of Urban Area 108A
(contract 108A), a problem appeared and was initially considered relative to the false compaction of
the backfills of the sanitary sewer trenches. The deformation (settlement) of sub grade surface in
roads, where sanitary sewers existed, was a sign that the upcoming works of base and sub base
aggregate courses would be affected as well.
The Office of Resident Engineers (Ove Arup & Partners) stated that «this was a construction
of sewers error since the specification defined that backfills should be compacted to (at least) 95%
of standard Proctor Test». If the compaction rate of 95% of Proctors Test was achieved then
settlement of backfill would be zero.
On this statement, the Contractors argument was that it was a problem of the approved
backfill material. In this case «approved material» was the originally excavated material for which
initially the Contractor had claims rejecting it as unsuitable.
The following investigation lead to these conclusions: The existing material was a type of
clay known as «Terra Rossa» in the Mediterranean area, which is a stiff when dry and very reddish
soil, its color due to iron oxides originating from weathering of initial rock formations. This Terra
Rossa has a part of Montmorillonite (mineral) crystals, a rather long and flat molecule forming
cornflake-like particles, which expands when it absorbs water. So when the laboratory executed the
Standard Proctor Test under different moisture contents it was unavoidable that the volume of
compacted material would be inflated. On site this meant to be the problem. When the compacted
material dried under the extreme heat of Africa, the volume shrunk and the backfill settled.
A new statement coming from the RE's led to additional and extensive investigation. They
stated that «if the California Bearing Ratio (CBR) value of material for fill was according to
specifications (ie over 10%) then the problem would be avoided». Since this test measures the load-
bearing capacity of soils used for building roads, the Contractor (XEKTE SA) suggested that the
evaluation of the results should be contacted on site. A program of site tests was agreed with RE's so
that from the results to decide if CBR value was the necessary and efficient parameter to approve
the material. This program included
· Excavating the trenches again to a suitable depth,
· Backfilling with the excavated material in layers of 10cm,
· Compacting to 95% of Proctor Value,
· Measuring the levels on a predefined grid and
· Flooding the trenches with water and wait to dry
· When the trenches dried the surveyor should again measure the levels and
· Finally the laboratory should test the CBR value on site.
Depending on the results the RE would decide if the settlement of the backfills was a matter
of compaction or suitability of used material.
This was the procedure which finally led to the total rejection of the excavated material as
unsuitable for backfilling. After all these years of Engineering experience, today I can state that a
necessary test to determine the acceptable clay-like materials is based on the amount of Methylene
blue dye absorbed by the sample. If a soil fails this test then it should be rejected from use in
construction.
(1) Excavating the trenches
again to a suitable depth,
(2) Backfilling with the
excavated material in layers of
10cm,
(3a) Compacting to 95% of
Proctor Value (around
manholes)
(3b) Compacting to 95% of Proctor Value (over
the pipes)
I recall with admiration an employee from
Syria, hard working under the summer sun and
heat, hours and hours compacting, the backfill
material. The result was always a well
compacted layer stiff as a stone.
(3c) Compacting to 95% of Proctor Value (Field
laboratory tests)
(3d) Compacting to 95% of Proctor Value (Field laboratory tests)
(5a) Flooding the trenches with water and
wait to dry
(5b) Flooding the trenches with water and
wait to dry (monitoring the drying procedure)
(5c) Flooding the trenches with water and wait to dry
(monitoring the drying procedure)
Paving asphalt wearing course on the “Shari Al Andalus” highway
Libya & TERRA ROSSA
Libya & TERRA ROSSA

More Related Content

What's hot

use of municipal wastewater
use of municipal wastewateruse of municipal wastewater
use of municipal wastewaterCol Islam Ul Haq
 
IRJET- Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...
IRJET-  	  Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...IRJET-  	  Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...
IRJET- Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...IRJET Journal
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Rice husk ash based geopolymer concrete
Rice husk ash based geopolymer concreteRice husk ash based geopolymer concrete
Rice husk ash based geopolymer concreteShaswat K. Das
 
IRJET - Design of Improved Drainage System using Pervious Concrete
IRJET  -  	  Design of Improved Drainage System using Pervious ConcreteIRJET  -  	  Design of Improved Drainage System using Pervious Concrete
IRJET - Design of Improved Drainage System using Pervious ConcreteIRJET Journal
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeJill Reeves
 
Presentation on pervios concrete
Presentation on pervios concretePresentation on pervios concrete
Presentation on pervios concretepratik vanam
 
Yazdanbakhsh et al ETH LCA of RCA in NYC 2016
Yazdanbakhsh et al ETH LCA of RCA in NYC 2016Yazdanbakhsh et al ETH LCA of RCA in NYC 2016
Yazdanbakhsh et al ETH LCA of RCA in NYC 2016Thomas Baez
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaInfocengrs63
 
Commercialisation of geopolymer concrete as part of FP7 SUS-CON project
Commercialisation of geopolymer concrete as part of FP7 SUS-CON projectCommercialisation of geopolymer concrete as part of FP7 SUS-CON project
Commercialisation of geopolymer concrete as part of FP7 SUS-CON projectQUBGeopolymer
 
In-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield RedevelopmentIn-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield RedevelopmentDavid Bausmith
 
Project ppt guide shri a.n.dabhade sir 1
Project ppt guide  shri a.n.dabhade sir 1Project ppt guide  shri a.n.dabhade sir 1
Project ppt guide shri a.n.dabhade sir 1Awanish Shukla
 
Design of an Export Pipeline
Design of an Export Pipeline Design of an Export Pipeline
Design of an Export Pipeline Sarah Busef
 
Thrasher Commercial Group
Thrasher Commercial GroupThrasher Commercial Group
Thrasher Commercial GroupJill Reeves
 
A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...HoangTienTrung1
 

What's hot (20)

use of municipal wastewater
use of municipal wastewateruse of municipal wastewater
use of municipal wastewater
 
IRJET- Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...
IRJET-  	  Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...IRJET-  	  Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...
IRJET- Utilization of Reclaimed Asphalt Pavement and Ceramic Waste in Pav...
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Rice husk ash based geopolymer concrete
Rice husk ash based geopolymer concreteRice husk ash based geopolymer concrete
Rice husk ash based geopolymer concrete
 
Porous Pavement in Cold Climates Part 2
Porous Pavement in Cold Climates Part 2Porous Pavement in Cold Climates Part 2
Porous Pavement in Cold Climates Part 2
 
IRJET - Design of Improved Drainage System using Pervious Concrete
IRJET  -  	  Design of Improved Drainage System using Pervious ConcreteIRJET  -  	  Design of Improved Drainage System using Pervious Concrete
IRJET - Design of Improved Drainage System using Pervious Concrete
 
Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel Bridge
 
Presentation on pervios concrete
Presentation on pervios concretePresentation on pervios concrete
Presentation on pervios concrete
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
 
Yazdanbakhsh et al ETH LCA of RCA in NYC 2016
Yazdanbakhsh et al ETH LCA of RCA in NYC 2016Yazdanbakhsh et al ETH LCA of RCA in NYC 2016
Yazdanbakhsh et al ETH LCA of RCA in NYC 2016
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari delta
 
Ref#8.pdf
Ref#8.pdfRef#8.pdf
Ref#8.pdf
 
Commercialisation of geopolymer concrete as part of FP7 SUS-CON project
Commercialisation of geopolymer concrete as part of FP7 SUS-CON projectCommercialisation of geopolymer concrete as part of FP7 SUS-CON project
Commercialisation of geopolymer concrete as part of FP7 SUS-CON project
 
In-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield RedevelopmentIn-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield Redevelopment
 
Evocrete Booklet
Evocrete BookletEvocrete Booklet
Evocrete Booklet
 
Project ppt guide shri a.n.dabhade sir 1
Project ppt guide  shri a.n.dabhade sir 1Project ppt guide  shri a.n.dabhade sir 1
Project ppt guide shri a.n.dabhade sir 1
 
Design of an Export Pipeline
Design of an Export Pipeline Design of an Export Pipeline
Design of an Export Pipeline
 
Thrasher Commercial Group
Thrasher Commercial GroupThrasher Commercial Group
Thrasher Commercial Group
 
A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...
 

Viewers also liked

Joint Mobilization Review
Joint Mobilization ReviewJoint Mobilization Review
Joint Mobilization Reviewcaseychristyatc
 
Glenohumeral Joint
Glenohumeral JointGlenohumeral Joint
Glenohumeral Jointlibbyrowan
 
Kaltenborn manual mobilization srs
Kaltenborn manual mobilization srsKaltenborn manual mobilization srs
Kaltenborn manual mobilization srsSreeraj S R
 
Supraspinatus tendinitis 30may2013
Supraspinatus tendinitis 30may2013Supraspinatus tendinitis 30may2013
Supraspinatus tendinitis 30may2013Rahila Najihah
 
Supraspinatus Tendinitis Case Presentation of Musculoskeletal Module
Supraspinatus Tendinitis Case Presentation of Musculoskeletal ModuleSupraspinatus Tendinitis Case Presentation of Musculoskeletal Module
Supraspinatus Tendinitis Case Presentation of Musculoskeletal ModuleAyaz Iqbal
 
Manual Therapy, Joint Mobilisation
Manual Therapy, Joint Mobilisation Manual Therapy, Joint Mobilisation
Manual Therapy, Joint Mobilisation ARUN Balasubramniam
 

Viewers also liked (8)

Joint Mobilization Review
Joint Mobilization ReviewJoint Mobilization Review
Joint Mobilization Review
 
Glenohumeral Joint
Glenohumeral JointGlenohumeral Joint
Glenohumeral Joint
 
Kaltenborn manual mobilization srs
Kaltenborn manual mobilization srsKaltenborn manual mobilization srs
Kaltenborn manual mobilization srs
 
Supraspinatus tendinitis 30may2013
Supraspinatus tendinitis 30may2013Supraspinatus tendinitis 30may2013
Supraspinatus tendinitis 30may2013
 
Shoulder Lecture
Shoulder LectureShoulder Lecture
Shoulder Lecture
 
Supraspinatus Tendinitis Case Presentation of Musculoskeletal Module
Supraspinatus Tendinitis Case Presentation of Musculoskeletal ModuleSupraspinatus Tendinitis Case Presentation of Musculoskeletal Module
Supraspinatus Tendinitis Case Presentation of Musculoskeletal Module
 
Manual Therapy, Joint Mobilisation
Manual Therapy, Joint Mobilisation Manual Therapy, Joint Mobilisation
Manual Therapy, Joint Mobilisation
 
Principles Of Technique
Principles Of TechniquePrinciples Of Technique
Principles Of Technique
 

Similar to Libya & TERRA ROSSA

Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
Introduction to civil Engg.pptx
Introduction to civil Engg.pptxIntroduction to civil Engg.pptx
Introduction to civil Engg.pptxpriyanka415514
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Abner Silva
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfKARTHIKGOUD64
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...Christian Olele
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation supportJim McMullan
 
Interlocking concrete pavement for the port
Interlocking concrete pavement for the portInterlocking concrete pavement for the port
Interlocking concrete pavement for the portNECB
 
Design construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteDesign construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteLữ Phát
 
wagdy garas CV 1
wagdy garas CV 1wagdy garas CV 1
wagdy garas CV 1Wagdy Garas
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concreteSahil Khan
 
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdfASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdfHaddushGebremedhin
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologyAlexASquare1
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologyAlexASquare1
 
Porous road construction _ Asphalt as a healing material
Porous road construction _ Asphalt as a healing materialPorous road construction _ Asphalt as a healing material
Porous road construction _ Asphalt as a healing materialMuhammad Faysal Sheikh
 

Similar to Libya & TERRA ROSSA (20)

Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
Introduction to civil Engg.pptx
Introduction to civil Engg.pptxIntroduction to civil Engg.pptx
Introduction to civil Engg.pptx
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 
Highway network system
Highway network system Highway network system
Highway network system
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
Interlocking concrete pavement for the port
Interlocking concrete pavement for the portInterlocking concrete pavement for the port
Interlocking concrete pavement for the port
 
Amr7231044
Amr7231044Amr7231044
Amr7231044
 
Design construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteDesign construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concrete
 
wagdy garas CV 1
wagdy garas CV 1wagdy garas CV 1
wagdy garas CV 1
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdfASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
basic civil unit 1.pptx
basic civil  unit 1.pptxbasic civil  unit 1.pptx
basic civil unit 1.pptx
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Porous road construction _ Asphalt as a healing material
Porous road construction _ Asphalt as a healing materialPorous road construction _ Asphalt as a healing material
Porous road construction _ Asphalt as a healing material
 

Libya & TERRA ROSSA

  • 1. Libya, Benghazi The “CONTRACT AREA 108” project (Terra Rossa problem) This document is dedicated to the foreign workers in construction sites all over the world because they are the essential stream which transfers and distributes knowledge through countries.
  • 2. A Google-earth snapshot showing the in brief the contract sites that Company XEKTE SA , was constructing in 1980’s in Benghazi, Libya .
  • 3. The Contractor Company XECTE SA (Benghazi branch) was considered to be a middle sized contractor in Benghazi during the decade 1980-1990. At that time, the 2nd Ring Road of Benghazi, the “Shari Al Andalus” highway, some drainage networks around the city, and the development of Urban Area 108A, were some of the projects that this company was constructing. As a Contractor this Company had about one hundred workers, all foreigners, most of them from Philippines, some from Pakistan and India, a few from Palestine, Syria, Egypt and other countries as well. The leading personnel, Engineer Manager, Supervising Engineers, Surveyors, Foremen, Operators of construction machines etc were all from Greece. The Company operated a concrete pre-casting unit manufacturing cement tiles for sidewalks, kerbs and concrete drainage pipes, one asphalt drum mix plant and a warehouse providing maintenance for the fleet of heavy construction machines (excavators, trucks, graders etc) that was in full operation. A mine for aggregates was occasionally operated in “El Abiar” providing materials for the road construction. The above mentioned projects, that were running that time, were also the main operational concern of the Engineer Manager but as a Contractor the company was a provider of general technical services to the Municipality of Benghazi such as repairs of public roads and substructures. The general outline of the main projects was: 1. The 2nd Ring Road of Benghazi project was a 5.5km road connecting Algeria street which is close to harbor with “Assudan” Street in the area of “Northen Fwayhat”. The 2nd Ring Road was a two-way traffic, 12,0m / 15,0m wide with two lanes on each side. Six major junctions, planting, drainage, traffic signs and street lighting were the complete design and construction scheme of the contract. 2. The “Shari Al Andalus” project was the 3.4km city's section of a 9.9km highway leading from the center of the city to the south suburbs. 3. The development of Urban Area 108A (contract 108A) concerned a complete and ready to use network of local roads and consisted of the construction of Public Utilities such as water supply network and house connections, sanitary sewerage (foul and gray waters) networks, storm (surface) water drainage networks (manholes, inlets/gullies and drainage pipes), kerbs and sidewalks, street lighting, base and sub base aggregate courses and two layers of asphalt pavements. This contract imposed very strict specifications for road construction. Due to the flat landscape, the design of the roads required a small gradient of no more than 0,1% longitudinal slopes in favor of a sufficient drainage network. The accepted difference in elevations between design and construction should have been less than 1,5 millimeters / km. The outflows from sewers and storm water pipes were conveyed to the pumping stations. Specifications that were applied to the works were for example AASHO T99-700, AASHO T193-63, AASHO T 27-70 and BS 1377, BS 1881, BS 812 etc. All the above projects were constructed under the same main articles of works as they approved by the Municipality. However the applied specifications were causing technical or compatibility problems having impact to the cost of works. For example the use of sulfur resisting cement for the concrete sewers appurtenant structures and the gutters-kerbs as well, as the specifications predicted instead of Pozzolanic cement, was a failure since this concrete was cracking at the following the construction stages. Another example is the design of box culverts in some locations were the circular shape was more appropriate. Further more the handling of dust on the road’s surface during desert winds was a seasonal problem related to maintenance procedures.
  • 4. During the time that I was assigned as a Deputy Engineer to the project of Urban Area 108A (contract 108A), a problem appeared and was initially considered relative to the false compaction of the backfills of the sanitary sewer trenches. The deformation (settlement) of sub grade surface in roads, where sanitary sewers existed, was a sign that the upcoming works of base and sub base aggregate courses would be affected as well. The Office of Resident Engineers (Ove Arup & Partners) stated that «this was a construction of sewers error since the specification defined that backfills should be compacted to (at least) 95% of standard Proctor Test». If the compaction rate of 95% of Proctors Test was achieved then settlement of backfill would be zero. On this statement, the Contractors argument was that it was a problem of the approved backfill material. In this case «approved material» was the originally excavated material for which initially the Contractor had claims rejecting it as unsuitable. The following investigation lead to these conclusions: The existing material was a type of clay known as «Terra Rossa» in the Mediterranean area, which is a stiff when dry and very reddish soil, its color due to iron oxides originating from weathering of initial rock formations. This Terra Rossa has a part of Montmorillonite (mineral) crystals, a rather long and flat molecule forming cornflake-like particles, which expands when it absorbs water. So when the laboratory executed the Standard Proctor Test under different moisture contents it was unavoidable that the volume of compacted material would be inflated. On site this meant to be the problem. When the compacted material dried under the extreme heat of Africa, the volume shrunk and the backfill settled. A new statement coming from the RE's led to additional and extensive investigation. They stated that «if the California Bearing Ratio (CBR) value of material for fill was according to specifications (ie over 10%) then the problem would be avoided». Since this test measures the load- bearing capacity of soils used for building roads, the Contractor (XEKTE SA) suggested that the evaluation of the results should be contacted on site. A program of site tests was agreed with RE's so that from the results to decide if CBR value was the necessary and efficient parameter to approve the material. This program included · Excavating the trenches again to a suitable depth, · Backfilling with the excavated material in layers of 10cm, · Compacting to 95% of Proctor Value, · Measuring the levels on a predefined grid and · Flooding the trenches with water and wait to dry · When the trenches dried the surveyor should again measure the levels and · Finally the laboratory should test the CBR value on site. Depending on the results the RE would decide if the settlement of the backfills was a matter of compaction or suitability of used material. This was the procedure which finally led to the total rejection of the excavated material as unsuitable for backfilling. After all these years of Engineering experience, today I can state that a necessary test to determine the acceptable clay-like materials is based on the amount of Methylene blue dye absorbed by the sample. If a soil fails this test then it should be rejected from use in construction.
  • 5. (1) Excavating the trenches again to a suitable depth, (2) Backfilling with the excavated material in layers of 10cm, (3a) Compacting to 95% of Proctor Value (around manholes)
  • 6. (3b) Compacting to 95% of Proctor Value (over the pipes) I recall with admiration an employee from Syria, hard working under the summer sun and heat, hours and hours compacting, the backfill material. The result was always a well compacted layer stiff as a stone. (3c) Compacting to 95% of Proctor Value (Field laboratory tests) (3d) Compacting to 95% of Proctor Value (Field laboratory tests)
  • 7. (5a) Flooding the trenches with water and wait to dry (5b) Flooding the trenches with water and wait to dry (monitoring the drying procedure) (5c) Flooding the trenches with water and wait to dry (monitoring the drying procedure)
  • 8. Paving asphalt wearing course on the “Shari Al Andalus” highway