SlideShare a Scribd company logo
1 of 4
Download to read offline
W
hen commercial properties in prime locations are left vacant due
to environmental impacts to the soil and groundwater caused by
past industrial practices, there is significant incentive to return
these Brownfield sites to usefulness. One such site is located in Port Newark,
N.J., which is one of the largest shipping ports in the New York/New Jersey
area. The site was previously operated as a wood treating facility from 1940
until operations ceased in 1991, and remained vacant until remediation
commenced under the jurisdiction of the New Jersey Department of
Environmental Protection (NJDEP).
Cement-based solidification/stabilization was used to address arsenic-
and creosote-impacted soils at the site. Prior investigations at the site found
free phase creosote in deep soils (0-12 feet), and arsenic-impacted surface
soils (0-2 feet). Remediation of the site involved the in-situ
solidification/stabilization of “deep” creosote-impacted soils, ex-situ solidi-
fication/stabilization of arsenic-impacted soils, and use of the treated soils as
sub-grade materials for construction of an asphalt surface cover system
designed for use as a container storage facility.
Approximately 25,000 cubic yards of material was treated in-situ using an
excavator-mounted mixing tool, and approximately 27,000 cubic yards of
material was excavated, treated through a pug mill, and re-used at the site as
soil-cement base for the asphaltic concrete pavement.
The use of soil-cement as an asphalt base course material reduced con-
struction costs by obviating the need to import additional fill. As a result of
the treatment, creosote and arsenic in the soil were successfully immobilized
and contained at the site and the Port Authority of New York and New Jersey
returned the property to productive use.
Background
The site consists of approximately eight acres of property, located between
the Elizabeth and Port Newark shipping channels, in Port Newark. The site
is owned by the City of Newark and is leased to the Port Authority of N.Y.
and New Jersey (Port Authority). The site was formerly operated as a wood-
treating facility (under various lessors) from 1940 until operations were
ceased in May 1991. Since razing of the former wood treating facilities in
1991, the property remained vacant.
The wood treating process utilized preservatives including creosote and
chromated copper arsenate (CCA). The creosote and CCA were stored on-
site in above-ground storage tanks, and pumped via underground pipelines
to above-ground treatment cylinders. Wood poles were moved into the
treatment cylinders via rail cars, and subsequently treated under pressure
with preservative chemicals. Following treatment, the cylinders were de-
pressurized and opened (at which point excess preservative was drained
from the cylinder and collected in sumps located beneath the door of the
cylinder), and the rail cars were wheeled out of the cylinder to an unpaved
drip track area, where excess preservative dripped from the poles to the
track. The treated poles were removed from the rail cars and transferred to
outdoor lumber storage areas. As a result of these historical wood-treating
operations, soil and groundwater at the site was impacted with constituents
Cementing
DNAPLsBy David S. Bausmith
Cementing
DNAPLs
related to the wood-treating chemicals.
Numerous on-site environmental
investigations were performed between
1984 and 1998, which identified contami-
nants related to the former wood-treating
operations in both surface and subsurface
soils on-site. Arsenic was generally present
in the top two feet of soil across the entire
site. Creosote, in the form of Dense Non-
Aqueous Phase Liquid (DNAPL), was
present over approximately two acres of
the site at depths up to approximately 12
feet beneath ground surface. The arsenic
and DNAPL represented a potential
source material for on-going groundwater
impacts. The NJDEP required these
“sources” be removed, if practicable, or
treated. A total of approximately 50,000
cubic yards (cy) of arsenic and/or
DNAPL-impacted material existed in
shallow and deep soil at the site.
Remedial action/redevelopment
requirements
A Remedial Action Work Plan (RAWP)
for the site was approved by the NJDEP
in July, 1999, which outlined the
Remedial Action Objectives (RAOs) for
the site and methods for achieving those
objectives. The RAO included: 1) reduc-
ing the potential for direct contact expo-
sure to constituents in surface soils; 2)
restricting future on-site groundwater
use, and mitigating potential migration
of constituents to potential off-site
receptors and deeper groundwater; and,
3) reducing the potential mobility of
DNAPLs and minimizing future dissolu-
tion of DNAPL constituents and arsenic
to the groundwater. During development
of the RAWP, numerous remedial alter-
natives were considered which would sat-
isfy these RAOs (i.e., potential source
material removal, slurry wall contain-
ment, pumping and treatment of
groundwater, etc.). However, many alter-
natives were either not practicable or
extremely costly. Additionally, because
the Port Authority ultimately desired to
return the site to productive use as a
marine cargo storage facility, the remedi-
al actions selected for the site had to be
consistent with the proposed end use.
Improvements to the site’s infrastruc-
ture were also required to render the
property functional as a marine cargo
storage facility. Specifically, the site
required construction of new storm
water drainage, electrical supply, and
potable water supply systems, as well as
an asphaltic concrete pavement cover.
Although required for redevelopment,
the asphaltic concrete pavement would
also satisfy the remedial requirement to
prevent direct contact exposure to con-
stituents in the surface soil. In order for
the storm water drainage system to func-
tion properly, the entire surface of the
site had to be raised by approximately
two feet above existing grades. The final
site surface also had to be constructed in
accordance with strict grade tolerances
and strength requirements stipulated by
the Port Authority. For example, the final
surface could not exhibit grade transi-
tions exceeding 0.5 percent over a dis-
tance of 20 feet to minimize the potential
for stacked cargo containers to tip. The
final surface also had to withstand 100
repetitious H-20 rated loadings per day,
which represented the anticipated traffic
conditions for the site.
Cement-based
solidification/stabilization
In order to achieve the RAOs for the site
and simultaneously provide a site that met
the Port Authority’s requirements for stor-
age of marine cargo, cement-based solidi-
fication/stabilization (S/S) was selected as
the primary remedial action. The NJDEP
approved this approach, based on the
results of treatability studies which showed
that contaminants in the soil would be
effectively immobilized after being blend-
ed with eight percent Type I Portland
cement by wet weight of soil.As part of the
remedial design phase, minimum strength
requirements were established for the shal-
low and deep stabilized soils. Deep stabi-
lized soils were required to provide a min-
imum 28-day unconfined compressive
strength (UCS) of 25 pounds per square
inch (psi), and shallow stabilized soils were
required to provide a minimum seven-day
UCS of 250 psi.
Cement-based S/S of target site soils
was accomplished using a combination of
in-situ and ex-situ technologies.
Treatment of deeper soils impacted with
DNAPL was completed in-situ to elimi-
nate need to remove, handle and treat
materials above-grade. In addition, in-situ
treatment minimized the release of
volatile constituents during treatment
that could otherwise require costly
vapor/odor control equipment if DNAPL-
impacted soils were removed and treated
above-grade.
Shallow soils were treated ex-situ in a
pug mill. Soils treated in the pug mill not
only provided a material that could be
graded to achieve final design topography
for the site, but also provided a high-
strength base for the asphaltic concrete
pavement which would withstand the
anticipated traffic loads for the site.
In-situ S/S of the deeper soils was
accomplished using proprietary equip-
ment provided by the Lang Tool
Company, consisting of a hydraulically-
powered mixing head mounted on an
excavator. A mobile on-site slurry plant
was used to prepare cement-water slurry,
which was pumped directly to the in-situ
mixer via flexible hoses. Flow metering
equipment was used to control the quan-
tity of cement blended with the soil, and
to ensure that a minimum of eight percent
cement by wet weight of soil was added.
Approximately 25,000 cy of deep soil
were treated in-situ for the project, at an
average rate of 450 cy per day. The average
volumetric increase of the deep soils fol-
lowing treatment and curing was 23 per-
cent. This bulking effect reduced the
quantity of imported fill required to
achieve final design grades by approxi-
mately 5,800 cy. Laboratory testing of
samples of the treated deep soil indicated
that the cured material consistently
achieved the minimum 28-day uncon-
fined compressive strength requirement of
25 psi. Adequate strength was generally
achieved within seven-days, with the
seven-day UCS averaging 95 psi.
Confirmatory test pits completed in the
treated deep soils verified that S/S activi-
ties homogeneously mixed the soil and
cement, and effectively immobilized
DNAPL in the deeper soils.
Ex-situ S/S of shallow soils was accom-
plished by systematically stripping the top
two feet of soil from the site, screening the
soil to remove debris larger than three
inches in diameter, crushing the oversized material down to a maximum
dimension of 1.5 inches, mixing the screened soil and re-sized material with
eight percent cement by wet weight of soil and placing and compacting the
stabilized material on-site. The pug mill was equipped with spray bars to add
water (as needed) to the soil and cement during mixing to maintain the
moisture content of the soil-cement at, or slightly above, the material’s opti-
mum moisture content for compaction. The treated shallow soils were spread
in lifts between six and eight inches in thickness, and compacted to a mini-
mum of 95 percent of Modified Proctor maximum dry density.
A total of approximately 27,000 cy of shallow soil were treated during the
project, and treatment rates ranged from 200 to 700 cy per day. The seven-
day UCS of the soil-cement samples tested during construction consistently
exceeded the minimum requirement of 250 psi, and averaged a value of 600
psi. Because the soil-cement served as the base course for the asphaltic con-
crete pavement system, the unexpectedly high UCS of the soil-cement sug-
gests that the loading capacity and/or service-life of the pavement will be
greater than anticipated as part of the design.
Cement-based S/S activities at the site were completed between
December, 2000 and April, 2001. The storm water drainage, water supply
and electrical lighting systems were constructed concurrently with the S/S
activities. Construction of the asphaltic concrete pavement cover was com-
pleted in November, 2001, and the Port Authority returned the site to active
use in March, 2002.
Summary
Cement-based S/S was effectively implemented for the remediation and
redevelopment of a former wood-treating site in Port Newark, N.J.
Approximately 52,000 cy of soil impacted with wood treating chemicals
were treated via in-situ and ex-situ S/S technologies with eight percent Type
I Portland cement by wet weight of soil. The S/S treatment effectively immo-
bilized the soil and the related contaminants on-site, precluding the need to
remove and dispose of soils off-site. The volumetric increase of site soils
resulting from the S/S activities also reduced construction costs by offsetting
imported fill requirements. Further cost savings related to potential import-
ed fill requirements were realized through the effective use of soil-cement as
sub base material for the asphalt pavement. Treatment of the soils via
cement-based S/S also resulted in dramatic improvements in the bearing
strength of the site, which has rendered the property suitable for use as a
marine cargo storage facility.
The post-remediation monitoring requirements include quarterly
groundwater flow monitoring and sampling/analysis. This will continue for
a minimum of eight quarters (started the first quarter of 2002). In its early
stages, the post remediation groundwater monitoring indicates site-related
contaminants are being contained. More significantly, test pits and visual
inspections performed after implementing the stabilization remedy con-
firmed that the source material was immobilized. PE
For more information contact, David S. Bausmith, P.E., Key Environmental
Inc., 456 Route 22 West, Suite D, Whitehouse Station, N.J., 08889.
Approximately 25,000 cy of deep soil were
treated in-situ for the project, at an average
rate of 450 cy per day.
Reprinted from Pollution Engineering, Copyright November 2002.

More Related Content

What's hot

C:\fakepath\Impact of tsunami on soil properties
C:\fakepath\Impact of tsunami on soil propertiesC:\fakepath\Impact of tsunami on soil properties
C:\fakepath\Impact of tsunami on soil propertiessekaran
 
Moffett/Ellis/Whisman Presentation to the Moffett RAB
Moffett/Ellis/Whisman Presentation to the Moffett RABMoffett/Ellis/Whisman Presentation to the Moffett RAB
Moffett/Ellis/Whisman Presentation to the Moffett RABSteve Williams
 
RECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTX
RECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTXRECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTX
RECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTXGOKULKRISHNAG4
 
Influence of compactive efforts on compacted foundry sand treated with cement...
Influence of compactive efforts on compacted foundry sand treated with cement...Influence of compactive efforts on compacted foundry sand treated with cement...
Influence of compactive efforts on compacted foundry sand treated with cement...Alexander Decker
 
IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...IRJET Journal
 
Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationUniversity of Wisconsin-Madison
 
Combining Solar Technology with Sustained and Controlled Release Reactants - ...
Combining Solar Technology with Sustained and Controlled Release Reactants - ...Combining Solar Technology with Sustained and Controlled Release Reactants - ...
Combining Solar Technology with Sustained and Controlled Release Reactants - ...Lindsay Swearingen
 
Extractive Energetic - Thesis by Jessica Wolff
Extractive Energetic - Thesis by Jessica WolffExtractive Energetic - Thesis by Jessica Wolff
Extractive Energetic - Thesis by Jessica WolffMichael Hewitt, GISP
 
Hangar One Update to the Moffett RAB
Hangar One Update to the Moffett RABHangar One Update to the Moffett RAB
Hangar One Update to the Moffett RABSteve Williams
 
GREEN RECYCLED AGGREGATE CONCRETE (GRAC)
GREEN RECYCLED AGGREGATE CONCRETE (GRAC)GREEN RECYCLED AGGREGATE CONCRETE (GRAC)
GREEN RECYCLED AGGREGATE CONCRETE (GRAC)Dayal Kurian
 
Groundwater remediation project
Groundwater remediation projectGroundwater remediation project
Groundwater remediation projectTurlough Guerin
 

What's hot (18)

C:\fakepath\Impact of tsunami on soil properties
C:\fakepath\Impact of tsunami on soil propertiesC:\fakepath\Impact of tsunami on soil properties
C:\fakepath\Impact of tsunami on soil properties
 
Moffett/Ellis/Whisman Presentation to the Moffett RAB
Moffett/Ellis/Whisman Presentation to the Moffett RABMoffett/Ellis/Whisman Presentation to the Moffett RAB
Moffett/Ellis/Whisman Presentation to the Moffett RAB
 
Report
ReportReport
Report
 
MSC-Project
MSC-ProjectMSC-Project
MSC-Project
 
RECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTX
RECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTXRECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTX
RECYCLED AGGREGATE CONCRETE / SLIDE SHARE / PPTX
 
Influence of compactive efforts on compacted foundry sand treated with cement...
Influence of compactive efforts on compacted foundry sand treated with cement...Influence of compactive efforts on compacted foundry sand treated with cement...
Influence of compactive efforts on compacted foundry sand treated with cement...
 
Libya & TERRA ROSSA
Libya & TERRA ROSSALibya & TERRA ROSSA
Libya & TERRA ROSSA
 
IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...IRJET-  	  Improving the Geotechnical Property of Expansive Soil through Marb...
IRJET- Improving the Geotechnical Property of Expansive Soil through Marb...
 
Comolli suolo
Comolli suoloComolli suolo
Comolli suolo
 
Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research Station
 
Ijetcas14 549
Ijetcas14 549Ijetcas14 549
Ijetcas14 549
 
Combining Solar Technology with Sustained and Controlled Release Reactants - ...
Combining Solar Technology with Sustained and Controlled Release Reactants - ...Combining Solar Technology with Sustained and Controlled Release Reactants - ...
Combining Solar Technology with Sustained and Controlled Release Reactants - ...
 
Newsletter 12 04
Newsletter 12 04Newsletter 12 04
Newsletter 12 04
 
Extractive Energetic - Thesis by Jessica Wolff
Extractive Energetic - Thesis by Jessica WolffExtractive Energetic - Thesis by Jessica Wolff
Extractive Energetic - Thesis by Jessica Wolff
 
Hangar One Update to the Moffett RAB
Hangar One Update to the Moffett RABHangar One Update to the Moffett RAB
Hangar One Update to the Moffett RAB
 
GREEN RECYCLED AGGREGATE CONCRETE (GRAC)
GREEN RECYCLED AGGREGATE CONCRETE (GRAC)GREEN RECYCLED AGGREGATE CONCRETE (GRAC)
GREEN RECYCLED AGGREGATE CONCRETE (GRAC)
 
Concrete recycling
Concrete recyclingConcrete recycling
Concrete recycling
 
Groundwater remediation project
Groundwater remediation projectGroundwater remediation project
Groundwater remediation project
 

Viewers also liked

In loving remembrance finished 4
In loving remembrance finished 4In loving remembrance finished 4
In loving remembrance finished 4Kenneth Robinson
 
Consumer realtionship management
Consumer realtionship managementConsumer realtionship management
Consumer realtionship managementManjot Kaur Dhillon
 
kabihasnang mesopotamia
kabihasnang mesopotamiakabihasnang mesopotamia
kabihasnang mesopotamiaahljunrallos
 
Mu seminor2014 06
Mu seminor2014 06Mu seminor2014 06
Mu seminor2014 06sejs-ej
 
Mu seminor2014 00
Mu seminor2014 00Mu seminor2014 00
Mu seminor2014 00sejs-ej
 
Environmental Stabilization & Brownfield Redevelopment
Environmental Stabilization & Brownfield RedevelopmentEnvironmental Stabilization & Brownfield Redevelopment
Environmental Stabilization & Brownfield RedevelopmentDavid Bausmith
 
Human brain based circuit systems
Human brain based circuit systemsHuman brain based circuit systems
Human brain based circuit systemsHariharasudhan Mani
 
Unit II Developmental Theories & other Relevant Theorie's
Unit II Developmental Theories & other Relevant Theorie'sUnit II Developmental Theories & other Relevant Theorie's
Unit II Developmental Theories & other Relevant Theorie'sMeryrose Tanangonan
 

Viewers also liked (14)

In loving remembrance finished 4
In loving remembrance finished 4In loving remembrance finished 4
In loving remembrance finished 4
 
Consumer realtionship management
Consumer realtionship managementConsumer realtionship management
Consumer realtionship management
 
kabihasnang mesopotamia
kabihasnang mesopotamiakabihasnang mesopotamia
kabihasnang mesopotamia
 
Mu seminor2014 06
Mu seminor2014 06Mu seminor2014 06
Mu seminor2014 06
 
Options and futures
Options and futures Options and futures
Options and futures
 
Training
TrainingTraining
Training
 
SOURAV GANGULY
SOURAV GANGULYSOURAV GANGULY
SOURAV GANGULY
 
Environmental
EnvironmentalEnvironmental
Environmental
 
Mu seminor2014 00
Mu seminor2014 00Mu seminor2014 00
Mu seminor2014 00
 
Environmental Stabilization & Brownfield Redevelopment
Environmental Stabilization & Brownfield RedevelopmentEnvironmental Stabilization & Brownfield Redevelopment
Environmental Stabilization & Brownfield Redevelopment
 
Human brain based circuit systems
Human brain based circuit systemsHuman brain based circuit systems
Human brain based circuit systems
 
Mam dacayo
Mam dacayoMam dacayo
Mam dacayo
 
Unit II Developmental Theories & other Relevant Theorie's
Unit II Developmental Theories & other Relevant Theorie'sUnit II Developmental Theories & other Relevant Theorie's
Unit II Developmental Theories & other Relevant Theorie's
 
Deforestation
DeforestationDeforestation
Deforestation
 

Similar to In-Situ Contaminant Stabilization and Brownfield Redevelopment

Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Michael Hewitt, GISP
 
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...mbehan
 
Design construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteDesign construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteLữ Phát
 
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...Sam Stribling
 
Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...
Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...
Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...Kehsun Lin
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation supportJim McMullan
 
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...TRC Companies, Inc.
 
IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...
IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...
IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...IRJET Journal
 
Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Hsuain
 
Interlocking concrete pavement for the port
Interlocking concrete pavement for the portInterlocking concrete pavement for the port
Interlocking concrete pavement for the portNECB
 
IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...
IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...
IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...IRJET Journal
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Cost effective cleaning up of contaminated groundwater
Cost effective cleaning up of contaminated groundwaterCost effective cleaning up of contaminated groundwater
Cost effective cleaning up of contaminated groundwaterTurlough Guerin GAICD FGIA
 

Similar to In-Situ Contaminant Stabilization and Brownfield Redevelopment (20)

Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
 
Missouri
MissouriMissouri
Missouri
 
Missouri
MissouriMissouri
Missouri
 
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
 
Design construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteDesign construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concrete
 
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
 
Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...
Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...
Subsurface 1D Transport of Dioxin Beneath An Uncontrolled Dump Site - A Case ...
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
 
Pennsylvania
PennsylvaniaPennsylvania
Pennsylvania
 
IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...
IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...
IRJET- Effect of Fly Ash and Nano Calcium Silicates in Clayey Soil Used as Cl...
 
Landfilling
Landfilling Landfilling
Landfilling
 
Pennsylvania
PennsylvaniaPennsylvania
Pennsylvania
 
Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...
 
Interlocking concrete pavement for the port
Interlocking concrete pavement for the portInterlocking concrete pavement for the port
Interlocking concrete pavement for the port
 
IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...
IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...
IRJET=-Effect of Municipal Solid Waste Leachate on the Strength of Compacted ...
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
West virginia
West virginiaWest virginia
West virginia
 
Cost effective cleaning up of contaminated groundwater
Cost effective cleaning up of contaminated groundwaterCost effective cleaning up of contaminated groundwater
Cost effective cleaning up of contaminated groundwater
 
B1303070716
B1303070716B1303070716
B1303070716
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

In-Situ Contaminant Stabilization and Brownfield Redevelopment

  • 1. W hen commercial properties in prime locations are left vacant due to environmental impacts to the soil and groundwater caused by past industrial practices, there is significant incentive to return these Brownfield sites to usefulness. One such site is located in Port Newark, N.J., which is one of the largest shipping ports in the New York/New Jersey area. The site was previously operated as a wood treating facility from 1940 until operations ceased in 1991, and remained vacant until remediation commenced under the jurisdiction of the New Jersey Department of Environmental Protection (NJDEP). Cement-based solidification/stabilization was used to address arsenic- and creosote-impacted soils at the site. Prior investigations at the site found free phase creosote in deep soils (0-12 feet), and arsenic-impacted surface soils (0-2 feet). Remediation of the site involved the in-situ solidification/stabilization of “deep” creosote-impacted soils, ex-situ solidi- fication/stabilization of arsenic-impacted soils, and use of the treated soils as sub-grade materials for construction of an asphalt surface cover system designed for use as a container storage facility. Approximately 25,000 cubic yards of material was treated in-situ using an excavator-mounted mixing tool, and approximately 27,000 cubic yards of material was excavated, treated through a pug mill, and re-used at the site as soil-cement base for the asphaltic concrete pavement. The use of soil-cement as an asphalt base course material reduced con- struction costs by obviating the need to import additional fill. As a result of the treatment, creosote and arsenic in the soil were successfully immobilized and contained at the site and the Port Authority of New York and New Jersey returned the property to productive use. Background The site consists of approximately eight acres of property, located between the Elizabeth and Port Newark shipping channels, in Port Newark. The site is owned by the City of Newark and is leased to the Port Authority of N.Y. and New Jersey (Port Authority). The site was formerly operated as a wood- treating facility (under various lessors) from 1940 until operations were ceased in May 1991. Since razing of the former wood treating facilities in 1991, the property remained vacant. The wood treating process utilized preservatives including creosote and chromated copper arsenate (CCA). The creosote and CCA were stored on- site in above-ground storage tanks, and pumped via underground pipelines to above-ground treatment cylinders. Wood poles were moved into the treatment cylinders via rail cars, and subsequently treated under pressure with preservative chemicals. Following treatment, the cylinders were de- pressurized and opened (at which point excess preservative was drained from the cylinder and collected in sumps located beneath the door of the cylinder), and the rail cars were wheeled out of the cylinder to an unpaved drip track area, where excess preservative dripped from the poles to the track. The treated poles were removed from the rail cars and transferred to outdoor lumber storage areas. As a result of these historical wood-treating operations, soil and groundwater at the site was impacted with constituents Cementing DNAPLsBy David S. Bausmith
  • 2. Cementing DNAPLs related to the wood-treating chemicals. Numerous on-site environmental investigations were performed between 1984 and 1998, which identified contami- nants related to the former wood-treating operations in both surface and subsurface soils on-site. Arsenic was generally present in the top two feet of soil across the entire site. Creosote, in the form of Dense Non- Aqueous Phase Liquid (DNAPL), was present over approximately two acres of the site at depths up to approximately 12 feet beneath ground surface. The arsenic and DNAPL represented a potential source material for on-going groundwater impacts. The NJDEP required these “sources” be removed, if practicable, or treated. A total of approximately 50,000 cubic yards (cy) of arsenic and/or DNAPL-impacted material existed in shallow and deep soil at the site. Remedial action/redevelopment requirements A Remedial Action Work Plan (RAWP) for the site was approved by the NJDEP in July, 1999, which outlined the Remedial Action Objectives (RAOs) for the site and methods for achieving those objectives. The RAO included: 1) reduc- ing the potential for direct contact expo- sure to constituents in surface soils; 2) restricting future on-site groundwater use, and mitigating potential migration of constituents to potential off-site receptors and deeper groundwater; and, 3) reducing the potential mobility of DNAPLs and minimizing future dissolu- tion of DNAPL constituents and arsenic to the groundwater. During development of the RAWP, numerous remedial alter- natives were considered which would sat- isfy these RAOs (i.e., potential source material removal, slurry wall contain- ment, pumping and treatment of groundwater, etc.). However, many alter- natives were either not practicable or extremely costly. Additionally, because the Port Authority ultimately desired to return the site to productive use as a marine cargo storage facility, the remedi- al actions selected for the site had to be consistent with the proposed end use. Improvements to the site’s infrastruc- ture were also required to render the property functional as a marine cargo storage facility. Specifically, the site required construction of new storm water drainage, electrical supply, and potable water supply systems, as well as an asphaltic concrete pavement cover. Although required for redevelopment, the asphaltic concrete pavement would also satisfy the remedial requirement to prevent direct contact exposure to con- stituents in the surface soil. In order for the storm water drainage system to func- tion properly, the entire surface of the site had to be raised by approximately two feet above existing grades. The final site surface also had to be constructed in accordance with strict grade tolerances and strength requirements stipulated by the Port Authority. For example, the final surface could not exhibit grade transi- tions exceeding 0.5 percent over a dis- tance of 20 feet to minimize the potential for stacked cargo containers to tip. The final surface also had to withstand 100 repetitious H-20 rated loadings per day, which represented the anticipated traffic conditions for the site. Cement-based solidification/stabilization In order to achieve the RAOs for the site and simultaneously provide a site that met the Port Authority’s requirements for stor- age of marine cargo, cement-based solidi- fication/stabilization (S/S) was selected as the primary remedial action. The NJDEP approved this approach, based on the results of treatability studies which showed that contaminants in the soil would be effectively immobilized after being blend- ed with eight percent Type I Portland cement by wet weight of soil.As part of the remedial design phase, minimum strength requirements were established for the shal- low and deep stabilized soils. Deep stabi- lized soils were required to provide a min- imum 28-day unconfined compressive strength (UCS) of 25 pounds per square inch (psi), and shallow stabilized soils were required to provide a minimum seven-day UCS of 250 psi. Cement-based S/S of target site soils was accomplished using a combination of in-situ and ex-situ technologies. Treatment of deeper soils impacted with DNAPL was completed in-situ to elimi- nate need to remove, handle and treat materials above-grade. In addition, in-situ treatment minimized the release of volatile constituents during treatment that could otherwise require costly vapor/odor control equipment if DNAPL- impacted soils were removed and treated above-grade. Shallow soils were treated ex-situ in a pug mill. Soils treated in the pug mill not only provided a material that could be graded to achieve final design topography for the site, but also provided a high- strength base for the asphaltic concrete pavement which would withstand the anticipated traffic loads for the site. In-situ S/S of the deeper soils was accomplished using proprietary equip- ment provided by the Lang Tool Company, consisting of a hydraulically- powered mixing head mounted on an excavator. A mobile on-site slurry plant was used to prepare cement-water slurry, which was pumped directly to the in-situ mixer via flexible hoses. Flow metering equipment was used to control the quan- tity of cement blended with the soil, and to ensure that a minimum of eight percent cement by wet weight of soil was added. Approximately 25,000 cy of deep soil were treated in-situ for the project, at an average rate of 450 cy per day. The average volumetric increase of the deep soils fol- lowing treatment and curing was 23 per- cent. This bulking effect reduced the quantity of imported fill required to achieve final design grades by approxi- mately 5,800 cy. Laboratory testing of samples of the treated deep soil indicated that the cured material consistently achieved the minimum 28-day uncon- fined compressive strength requirement of 25 psi. Adequate strength was generally achieved within seven-days, with the seven-day UCS averaging 95 psi. Confirmatory test pits completed in the treated deep soils verified that S/S activi- ties homogeneously mixed the soil and cement, and effectively immobilized DNAPL in the deeper soils. Ex-situ S/S of shallow soils was accom- plished by systematically stripping the top two feet of soil from the site, screening the soil to remove debris larger than three
  • 3. inches in diameter, crushing the oversized material down to a maximum dimension of 1.5 inches, mixing the screened soil and re-sized material with eight percent cement by wet weight of soil and placing and compacting the stabilized material on-site. The pug mill was equipped with spray bars to add water (as needed) to the soil and cement during mixing to maintain the moisture content of the soil-cement at, or slightly above, the material’s opti- mum moisture content for compaction. The treated shallow soils were spread in lifts between six and eight inches in thickness, and compacted to a mini- mum of 95 percent of Modified Proctor maximum dry density. A total of approximately 27,000 cy of shallow soil were treated during the project, and treatment rates ranged from 200 to 700 cy per day. The seven- day UCS of the soil-cement samples tested during construction consistently exceeded the minimum requirement of 250 psi, and averaged a value of 600 psi. Because the soil-cement served as the base course for the asphaltic con- crete pavement system, the unexpectedly high UCS of the soil-cement sug- gests that the loading capacity and/or service-life of the pavement will be greater than anticipated as part of the design. Cement-based S/S activities at the site were completed between December, 2000 and April, 2001. The storm water drainage, water supply and electrical lighting systems were constructed concurrently with the S/S activities. Construction of the asphaltic concrete pavement cover was com- pleted in November, 2001, and the Port Authority returned the site to active use in March, 2002. Summary Cement-based S/S was effectively implemented for the remediation and redevelopment of a former wood-treating site in Port Newark, N.J. Approximately 52,000 cy of soil impacted with wood treating chemicals were treated via in-situ and ex-situ S/S technologies with eight percent Type I Portland cement by wet weight of soil. The S/S treatment effectively immo- bilized the soil and the related contaminants on-site, precluding the need to remove and dispose of soils off-site. The volumetric increase of site soils resulting from the S/S activities also reduced construction costs by offsetting imported fill requirements. Further cost savings related to potential import- ed fill requirements were realized through the effective use of soil-cement as sub base material for the asphalt pavement. Treatment of the soils via cement-based S/S also resulted in dramatic improvements in the bearing strength of the site, which has rendered the property suitable for use as a marine cargo storage facility. The post-remediation monitoring requirements include quarterly groundwater flow monitoring and sampling/analysis. This will continue for a minimum of eight quarters (started the first quarter of 2002). In its early stages, the post remediation groundwater monitoring indicates site-related contaminants are being contained. More significantly, test pits and visual inspections performed after implementing the stabilization remedy con- firmed that the source material was immobilized. PE For more information contact, David S. Bausmith, P.E., Key Environmental Inc., 456 Route 22 West, Suite D, Whitehouse Station, N.J., 08889. Approximately 25,000 cy of deep soil were treated in-situ for the project, at an average rate of 450 cy per day.
  • 4. Reprinted from Pollution Engineering, Copyright November 2002.