SlideShare a Scribd company logo
1 of 13
Download to read offline
Geotechnics for Sustainable Development - Geotec Hanoi 2013, Phung (edt). Construction Publisher. ISBN 978-604-82-0013-8
1
Keywords: case history, consolidation, sand compaction pile, settlement, ground improvement
ABSTRACT: A case of using Sand Compaction Pile method to improve the foundation soil for expressway in
Vietnam is presented. The sand compaction pile (SCP) method, which forms a composite ground by driving
the pile made of compacted sands into soft ground, is one of the commonly used soil improvement techniques
in Viet Nam. The SCP method used to improve the ground through the increase of bearing capacity, which is
achieved by improving loose sandy soils or accelerating the consolidation of soft clay soils. Within the
country where the condition of sand purchase is abundant in Viet Nam, sand compaction pile were often used
for soft ground improvement to replace the Load Relief Slab and Soil-Cement Column at Hanoi-Haiphong
Expressway Project recently. The procedures used for soil improvement, the instrumentation and the field
monitoring data are described. A few observational methods based on settlement records are available to
predict future settlement and consolidation behavior, namely the hyperbolic (Tan 1971; Chin 1975) and
Asaoka (Asaoka 1978) method. The field data were from the Thai Binh Bridge approached embankment
construction at Hanoi-Haiphong Expressway Project.
1. INTRODUCTION
The sand compaction pile (SCP) method is
frequently used in construction to form compacted
sand piles by vibration, dynamic impact, or static
excitation in soft grounds. The principle of the SCP
method is based on the research papers by
Murayama and Tamimoto published in 1957 and
1960, as the hammering method developed in1957
(Ministry of construction 1957). A composite
ground consisted of rows of compacted large
diameter sand columns were driven into a soft clay
ground in coastal district of Japan, as the
foundation of a structure (Murayama 1957). The
usage of the SCP method extended to improve soft
clays since the 1960’s (Ogawa 1963, Ibaragi 1965).
The subsequent presentation of Murayama’spaper
in 1962 established the method of SCP application
to clayey soil. This method was further justified
through number of researches and construction
projects. A casing pipe with a plug of sand at its tip
was driven to the bottom of improved layer by a
vibrator method. After pouring sand or gravel
material into the casing pipe, the casing pipe was
withdrawn partly and again driven down to
compacted the sand column and enlarge its
diameter. This process is repeated as far as
compacted sand column reaches to the ground
surface. The mechanism of stabilization by the
SCP method in the case of clayey ground is
perfectly different than the sandy grounds, which is
simply to density the surrounding soil. There is
almost no effect of densification in case of clayey
soils. However, these SCPs behave as piles in soft
grounds and totally can carry more load than
without SCP. At the same time, they also work as
A case study on soft soil improvement of
Hanoi-Haiphong expressway project in
Vietnam
Hoang Tien Trung
FECON-Foundation Engng & Underground Construction, Hanoi, Vietnam. E-mail: trunght@fecon.com.vn
Jang Woo Young
GS Engineering & Construction. Seoul, Korea. E-mail: wyjang@gsconst.co.kr
2
vertical drains to accelerate consolidation of clayey
grounds. In particular, for construction on
embankments over soft soil like soft clay, peaty
soil, which has very slow shear strength, the
installation of SCPs enhances the stability of the
embankment slope, helps to increase the bearing
capacity, and accelerates the consolidation rate of
the foundation soil. The automatically controlled
SCP driving system was invented in 1981
accommodating the vibration effect on soil
properties. In the Western world, the stone column
method-gravel compaction pile (GCP) method has
been used to improve soft ground since the 1970s
(Baumann and Bauer, 1974; Hughes et al., 1975).
As countermeasures for treatment of the soft
ground was applied for this project, the Sand
Compaction Pile, Sand Drain and Prefabricated
Vertical Drain are compared each other. The
displacement behaviour of SCP during installing
on site was considered, a free moving condition, in
which relative displacements occurs has been
observed. A case study on the use of the Sand
Compaction Pie method for the soil improvement for
Hanoi-Haiphong expressway project is presented in
this paper. The site conditions, the soil improvement
procedure, and the field instrumentation are
described. The field monitoring data are presented.
The achieved degree of consolidation and the effect
of soil improvement are evaluated. Several issues
concerning the practical aspects of the sand
compaction pile method are also discussed.
2. OUTLINE OF PROJECT
Hanoi-Haiphong Expressway connects Hanoi
Capital with Haiphong Port City, a route passing 4
provinces, cities: Gia Lam suburban district of
Hanoi city, Van Giang, Yen My, An Thi suburban
districts of Hung Yen province and An Lao, Kien
Thuy suburban districts of Haiphong city. Project’s
starting point is on the Ring Road III of Hanoi city,
1025 m far from north abutment of Thanh Tri
Bridge, Gia Lam suburban district of Hanoi city.
Ending point is at Dinh Vu Dam, Kien An district,
Haiphong city. Investment shall be made in
construction of Hanoi-Haiphong Expressway in
conformity to international standards, expressway
class A, design speed of 120 km/hr, six (6) traffic
lanes, total length of 105.5 km, divided into many
bidding packages. In this study, the paper presents
guideline for design and construction the Sand
Compaction Pile at Thai Binh Abutment area of
Package EX-6 from Km63+300~Km72+000.
Fig. 1 shows alignment direction (a), plan and
profile (b) of SCP treatment area at Abutment A2
with standard section at Sta.65+400.
(a)
(b)
Figure 1.Site location
Table 2. Reviewing Results and Alternatives for D/D Stage
Items
Method for soft soil
treatment
Basic
design
Design
alternative
Consolidation
Acceleration
Embank(H)<5m
Soft soil layer
thickness(D)<20
PVD
PVD
SD
Embank(H)≥5m
Soft soil layer
thickness(D)≥20
SD
PVD
SD
Sliding prevention
LRS;
SCC*
SCP;
LRS; SCC
*
LRS: Load Relief Slab; SCC: Soil-Cement Column.
This package is planned to be completed within
32 months. And a period of less than 18 months
approximately is recommended for soft soil
treatment in consideration of the following issues:
time for preparation works, time for construction of
culverts and underpass structures, time for
construction of piles and abutments, time for
construction of pavement and completion, and
reasonable reuse of surcharge and preloading
material section by section to minimize expense for
material. There are several methods to treat the soft
ground, but it is generally classified into two
categories as sliding-prevention method and
consolidation acceleration method. Soft soil
treatment proposal of Basic Design was reviewed
and, accordingly, some alternatives were primarily
3
proposed for Detail Design. All the reviewing
results are summarized in following Table 2.
As countermeasures for treatment of the soft
ground among the consolidation acceleration
methods mentioned above, Prefabricated Vertical
Drain, Vertical Sand Drain are compared each
other. The PVD is the most appropriate for uniform
soft soil area and without sand seam, SD is
appropriate for sand seam and non-uniform soft
soil areas. The Load Relief Slab, Soil-Cement
Column and Sand Compaction Pile are proposed
for treatment of the soft ground among the sliding
prevention methods of this Package and compared
each other as show in Table 3.
Table 3. Comparison of sliding prevention methods for high
embankment
Items Load Relief Slab
Soil-Cement
Column
Sand Compaction
Pile
General
Aspects
- Support loads by
concrete piles
(35cmx35cm) and
0.3m concrete
slab on soft soil
layer
- Support
load by soil
cement
mixed
column
(D=1.3m)
- Support upper
load by forming
70cm diameter
compaction sand
pile in soft soil
layer
Advanta
ge
-Effective in
settlement
reduction by
transferring the
loads directly to
bearing layer
-Many
experiences in
Viet Nam
- Prevention
of sliding
and
reduction of
settlement by
using soil
cement
columns
- ffective on
sliding prevention
and consolidation
acceleration
-Sand is
abundant in Viet
Nam
Disadva
ntage
-Quality control is
required
- High
construction costs
- Difficult to
control pile
quality and
construction
procedure
- High
construction
costs
- Limited
experiences
in Viet Nam
-No construction
experiences in
Viet Nam
Time for
consolid
ation
0 month 0 month 10 months
Cost 3.0 2.3 1.0
Proposal
and Plan
SCP is the most appropriate for high embankment
and deep soft soil areas
From all above analysis, following criteria will
be recommended as principle in general for
primary selection of soft soil treatment method for
this package.
3. GROUND CONDITION
Fig. 2 shows ground condition in this package with
the results of standard penetration tests.
Soil investigation was carried out in detail design and
additional design by means of a rotary drilling. The borehole
locations are shown in Fig.2. It can be seen that the soft
ground is about 30~32m deep with fat clay and sandy lean
clay with SPT value around 4~6.
Figure 2. Reference borehole log for SCP Treatment at
Abutment A2 Thai Binh Bridge A2 Sta. 65+383~ Sta.
65+413
4. SOFT SOIL IMPROVEMENT
METHOD
4.1 Design Concept
At present, the design method of the SCP is usually
divided into two methods. One is to check the
stability of improved ground, in which a slip
surface is assumed to pass through the replacement
area composed of sand column and clay. Stability
analysis is carried out the circular arc method. A
replacement area ration and a stress concentration
ratio on the slip surface are needed for the stability
analysis. The other method is to check the
consolidation settlement of the composite ground
by considering the diameter, spacing and
arrangement of the sand compaction piles and the
stress concentration ratio of the composite ground.
a. Characteristics of composite ground
In the development of a theory for the SCP
method, many researchers have tried to simplify
the problem of analysis by neglecting the
interactions between the sand piles, and they have
come up with the basic concept of SCP ground as
shown in Fig. 3 (Murayama, 1962; Ichmoto and
Seumatsu, 1982). When the composite ground is
loaded, concentration of stress occurs in the sand
4
pile accompanied by the reduction in stress which
occurs in the surrounding clayey soil as shown in
Fig. 3. This can be explained by the fact that the
vertical settlement of stress concentration in the SCP
and the surrounding soil is approximately the same,
and this causes the occurrence of stress concentration
in the sand pile which is stiffer than the surrounding
soil. The distribution of vertical stress within the unit
cell can be expressed by a stress concentration ratio,
(m) is defined as follows:
m = σs/σc (1)
where, σs = stress in the column and σc = the stress
in the surrounding cohesive soil.
The average stress, σ, over the unit cell area
corresponding to a given area replacement ratio,
as = As/(As + Ac) (2)
is expressed as:
σ = σs as + σc (1 as) (3)
where, As = the area of a SCP and Ac = the area of
the clay ground surrounding the pile.
The relationships for σs and σc in composite
ground also can be expressed using a stress
increment factor, µs, in the sand pile and stress
reduction factor, µc, in the surrounding soil and
defined by the following:
Figure 3. Basic concept of SCP ground
 
    
s s
s
m
σ σ μ σ
1 (m 1)α
(4)
 
    
c c
s
1
σ σ μ σ
1 (m 1)α
(5)
Based on eq. (1) and eq. (3), eq. (4) and (5) have a
relation of:
µsas+ µc(1+as) = 1 (6)
Therefore, eq. (2) can be rewritten as:
m = µs/µc (7)
Again, reduction of settlement due to the installation of
SCP is expressed as a settlement reduction factor, β:
β = St/S (8)
where, St = the settlement of ground without treatment and S
= the settlement of composite ground reinforced by a SCP.
Equation (2), (4), (5) and (6) are usually used as basic
parameters in design and analysis of composite ground.
b. Design theory of sand compaction pile
Replacement ratio
The volume of soft clay replaced by sand is one of
the most important factors in improving week
ground using sand compaction piles. To quantify
the amount of soil replacement, define the area
replacement ratio as as the fraction of soil tributary
to the pile replaced by the sand compaction pile.
The replacement ratio is defined by the following
expression and will be calculated for square and
triangular pattern as follow:
Figure 4. Arrangement and design concept of SCP
For a square arrangement:
 
    
 
2A A π Ds sas 2A 4 dd
(9)
For a triangular arrangement:
  
 
 
 
A 2 A π D 2s sas 2A d3 2 3d
(10)
where, d = center-to-center spacing of the SCP;
D = diameter of the completed SCP (not the
diameter of the casing).
5
Design approach:
To develop a practical design method, assume the
total volume tributary to a sand compaction pile
remains constant during the site improvement
work. Also, neglect any increase in relative density
caused by vibration as the casing is driven, and
assume the loose sand is only displaced laterally
away from the sand pile during construction.
Referring to Fig. 4, let the change in volume of the
in situ sand equal the volume of sand compaction
pile per unit length, l=1m, Vscp giving:
Vscp = V0 –V1 =
 
 
 
 
o 1e e
Vv eo
(11)
Figure 5. Volume block diagram of in situ sand before
and after SCP construction
The area replacement ratio, which is defined by
equation (2) giving:
as=



scp o 1
o
V e e
A 1 e
(12)
where, eo = initial void ratio of loose sand before
improvement; e1= final void ratio of loose sand
after improvement.
The equation (12) can be changed to a more
useful form for design by considering a unit length
of SCP construction. For a unit length l=1, solving
for sand compaction pile spacing d gives for a
square arrangement:
d =
 
 
 
2
o o
o scp
o 1 o 1
1 e 1 e D
V .V .
e e e e 4

(13)
and for a triangular arrangement
d =


2
o
o 1
1 e D
.
e e 2 3

(14)
 Shear strength
Soft ground after being treated by SCP will be
considered a composite ground comprising of SCP
and surrounding soft soil. Shear strength of the
composite ground τsc is calculated as follow:
    
 
u
sc s o o c c z
2
s s s z s
C
τ (1 a )(C (P P μ .σ )U
p
a (γ .Z μ .σ )tan .(cosθ)
(15)
    
 
u
sc s o o c c z
2
m z s s s
C
(1 a )(C ( P P . )U
p
(γ .Z σ ).μ .a .tan .(cosθ)
  

(16)
where, Cu/p = ratio of strength increase; '
s = sub
water unit weight of sand; Z = depth to the failure
surface; s = friction angle of sand;  = Angle
between acting surface and horizontal surface;
z = increased stress at failure surface due to
embankment loading; '
m = Average sub water unit
weight of composite soil.
Friction angle of sand (of SCP) and ratio of
stress division depending on replacement ratio is
shown in Table 1 below:
Table 1. Friction angle and Ratio of stress division
depending on replacement ratio
Replacement
Ratio, as
Friction Angle
of sand, s
Ratio of stress
division, m
0.0 ÷ 0.4 30 3
0.4 ÷ 0.7 30 2
0.7 ÷ 1.0 30 ÷ 35 1
Cohesion and internal friction angle of the
composite soil being used for slope stability
analysis are evaluated from following equation
(13) and (14) respectively, which is derived from
equation (11).


1
tan (n.tan )s  (17)
UP.
c
μ
c
P
o
(P
p
u
C
o
)(C
s
a(C ).1  (18)
where, n = as.µs ; Po = effective overburden
pressure; Pc= pre-consolidation pressure
 Settlement
Settlement of the composite ground is less than
non-treated ground because SCP shares load acting
upon the ground and, accordingly, SCP reduces
stress acting upon soil. Following equation is used
to get settlement of the composite ground.
For normal consolidation



 
 
 
C P μ .ΔPc o cS H.log
1 e Po o
(19)
6
For over consolidation and Pc > Po+ΔP



 
 
 
C P μ .ΔPs o cS H.log
1 e Po o
(20)
For over consolidation and Pc< Po+ΔP

 
 
   
   
   
C CP P μ .ΔPs cc o cS H.log H.log
1 e 1 eP Po oo c
(21)
In the sand layer, the following formula can be
used for immediately settlement (De beer method)


 
 
 
P P ΔPo oS 0.4. .H.logi N Po
(22)
where, Po = overburden pressure; ΔP = pressure
caused by embankment; Cc = compression index;
Cs = swell index; Pc = pre-consolidation pressure;
H = soil thickness; N = standard penetration
test value.
 Coarse Sand Blanket Thickness
The thickness of CSB is estimated based on the
water head level caused by embankment loading,
which is calculated from the following equation:

2L .S
Δh
K.h
(19)
where, Δh = water head level; h = thickness of
CSB; K = permeability of CSB; L = horizontal
drain length; S = settlement velocity.
In order to ensure the drainage capacity, the
thickness of CSB shall not be less than the above
Δh value and 50cm
4.2 Design soil parameters
Detail of the soil condition and soil properties was
got in the Soil Investigation Report for Package
EX-6 prepared by Transport Engineering Design
Int. The following paragraphs will only be of
analysis of soil values for soft soil treatment. The
unit weight with depth of soil 2 is plotted in Fig.
6a, according to testing data. Initial undrain shear
strength of soft soil (Co) will be evaluated from the
following basis Field vane shear test (FVST) and
Triaxial test UU-diagram (UU Test). Moreover, for
a reliable Co value for design, the analyzing Co
value will be referred to the following basic Cone
penetration test (CPT) with Co=(qc-po)/Nk where, qc
Cone resistance value, po overburdened effective
pressure, Nk empirical cone factor, (Nk=15) and
Standard penetration test (SPT) with Co=N*100/16
(KPa). The values of Co of soil 2 are plotted in
following Fig. 6b.
(a)Unit weight (b) Co
Figure 6. Profile of unit weight & Initial undrain shear
strength Co of soft soil
Undrain shear strength of soft soil will be
increase due to consolidation with a factor called
“Factor of Increase of undrain shear strength” – m,
which is evaluated from Triaxial test, CU scheme –
CU test and, as instructed in the Standard
22TCN262-2000, m equals to tan(φcu). All m-value
from CU testing data are plotted in following Fig.
7a. Fig. 7b plots all values of pre-consolidation
pressure of the EX-6 deposit in comparison with
overburden pressure of the soil.
(a) (b) (c)
Figure 7. Profile of UU test (a), Pc with depth and in
comparing with overburden pressure (b) and Cc with
depth (c)
Fig. 7b clearly indicates that the soil is over
consolidation from about 8m upward with Pc in
order of 7t/m2
, and from this level downward the
soil is normal consolidation. The following figure
7c plotting values of compression index Cc of soil
2a versus depth also quite clearly marks this
boundary. According to Fig.7c, the following Cc
value will be recommended for design:
 Soil 2: <8m, Cc= 0.25
8-28m, Cc= 0.48
>28m, Cc= 0.36
7
Table 4. Summary of soil parameters recommen-ded for soft
soil treatment design
Soil
properties
Unit
Soil
L2-1
Soil 2
<8m 8m-28m >28m
γ t/m3
1.87 1.74 1.67 1.74
Co t/m3
0 1.8 0.07z+1.24
φo
- 24 - - -
m - - 0.3 0.25
e -
-
Fig.
4-1
Fig.
4-2
Fig.
4-3
Cv.10-3
cm2
/sec
Kv.10-7
cm/sec
Cc - - 0.25 0.48 0.36
Cs - - 0.03 0.05 0.04
Pc t/m2
- 7.00 - -
OCR - - 2.40 1 1
N - 7
Embankment material
γ(t/m3
) C(t/m2
) φo
1.85 0 30
Figure 8a. Testing curves and typical one for soil 2
above 8m in depth
Figure 8b. Testing curves and typical one for soil 2 from
8m to 28m
Figure 8c. Testing curves and typical one for soil 2
below 28m in depth.
The physical properties of the soil strata are
summarized in Table 4.
Consolidation testing data comprising of
consolidation compression curves, consolidation
coefficient and permeability and typical values of
these parameters are plotted in following Fig. 8a,
8b and 8c for soil 2.
5. MONITORING RESULTS
5.1 Monitoring systems
Monitoring system was carried out install and
control during construction work in order to
confirm whether to cause a slip failure and to
generate a settlement as calculated and predicting
by design or not. This paper presents monitoring
works for approach of Thai Binh Bridge, Abutment
A2 Sta. 65+383 ~ Sta. 65+413. As for the
monitoring equipments, settlement plate,
Alignment stakes, Observation well, Piezometer
and Inclinometer were installed at section Sta.
65+400 as shown in Fig. 6.
Figure 9. Arrangement of Monitoring Equipments
Procedure and method for installation of
monitoring equipment at the site was shown in Fig.
9. SSP shall be installed on the separation
geotextile, in such a way that the top of the base
plate rests horizontally (a). Alignment stakes
8
consists of 5 wood stakes per side, each 1.5m long,
penetrating to a depth of 1.0 m and placed at 4.0m
intervals on each side of the embankment (b).
Alignment nails shall be placed on the top surfaced
of the stakes, exactly on an alignment
perpendicular to the roadway alignment. The
depths of the inclinometers shall be installed at
least 2m into the underlying hard stratum (c).
Electric Piezometer shall be saturate 24 hours (d)
to removal of air bubble in the cell before
installation, and then taking the zero-reading. It is
measured exactly again before installation in the
field (e). Take readings directly after installation
and continue periodically as the water pressure
decreases after installation. We installed
Observation well below original ground around
0.5m and filling coarse sand around the PVC Pipe
to the designed elevation (f).
(a) (b)
(c) (d)
(e) (f)
Figure 10. Installed monitoring equipment at the site
Typical monitoring frequency was proposed at
daily basic for the first week, and then increased to
few days or weekly basic during filling operation as
shown in Table 5. Each instrument or observation
point shall be read immediately before and after
each change in loading, daily during filling
operations, then at twice weekly intervals during the
first month. Thereafter, until the end of the
settlement period, each instrument or observation
point shall be read at intervals not greater than once
a week. Monthly readings shall then be made
through the end of the construction period.
Table 5. Frequency of reading
Items
During
embankment
or structural
fill
After embankment
~1month
~until the
end of the
settlement
~Until the
end of the
contract
period
-AWS,
SSP,
Piz.,
Inc.,
OW
1 time/day
-Before and
after change
in loading
-During
filling
operations
2 times/
week
1 time/
week
1 time/
month
5.2 Measurement control method and feed-back
analysis
A graphical approach to estimate final consolidation
settlement and settlement rates from settlement data
obtained during a certain time period was proposed
by Asaoka (1978) and Hyperbolic method (1971).
For the stability analysis, Tominaga-Hashimoto
method and Matsuo-Kawamura method are used,
which may be able to manage the stability of the
landfill quantitatively.
5.3 Monitoring Results
This paper presents the geotechnical analysis of
monitoring data to evaluate current status of soft
soil treatment and to propose starting next step for
a case study Abutment A2 Thai Binh Bridge in
Viet Nam using SCP method. Table 8 below
presents detail construction processing in different
with detail design.
Fig. 11 shows the chart of time-settlement curve
during a construction period of 1st
stage (from 6
Otober 2012 to 21 June 2013) based on the
monitored data obtain from settlement plate and re-
calculated the settlement follow actual construction
time by theory in. The settlement amount reached
about 64.6 cm in compared with calculation is
127.46 cm.
9
Table 6. Settlement prediction method
Classification Hyperbolic Asaoka method
Concept
Equation  

f 0
1
s s
a t
 f 0
1
s s

 f 0
1
s s



0
f
1
s
1


Reliability
Prediction values and measured values are close.
When degree of consolidation is over 70%
prediction can be possible within 10% of error
range
Predictedsettlement is less than measured
settlement and predicted value is getting close to
measured value with time.
When degree of consolidation is over 80%,
prediction can be possible within 10% of error
range
Table 7. Stability control method
Classification Tominaga-Hashimoto Matsuo & Kawamura
Concept
Control standard
Embankment will failure if α2 ≥ 0.7 or α2 ≥α1
+0.5
Embankment will be in danger if Pi/Pf>0.8
Pi: Embankment Load
Pf: Embankment load on failure
Reliability
In case lateral movement (δ) exceeds vertical
settlement (S), it indicates unstable due to shear
deformation. So regression line is inclined toward
I-II area.
The data of S and δ/S obtained from monitoring
data are plotted in the chart. In case the plotted data
is proceeding toward the failure line, it indicates
unstable.
Table 9. Actual excess pore pressure results
dU
Max(t/m2
)
Install EL
Initial
GWL
Initial GWL
Monitoring
U0 (t/m2)
Ut
(t/m2
)
dU
(t/m2
)
U (%)
5m 11.5 -5.4
0.94 0.94
4.46 5.62 1.16 89.60
15m 9.85 -15.4 23.48 25.62 2.14 78.27
25m 8.56 -25.4 39.75 41.43 1.68 80.37
10
Table 8. Status of construction
Items
Sta. 65+383 – Sta. 65+413
Detail
Design
Actual
Condition
Method
Method
treatment
SCP
Treatment
Depth (m)
30.0
Spacing (m) 1.5
Filling time (days) 70 234
Waiting time (days) 120 24
Total (days) 190 258
Figure 11. Settlement-time Curve
Figure 12. Lateral Displacement with Depth by
Inclinometer
(a) Asaoka method
(b) Hyperbolic method
Figure 13. Estimated final settlement by Asaoka &
Hyperbolic
Inclinometers were installed at both side of
embankment. Figure 12 shows the chart of lateral
displacement with depth monitored by
inclinometer installed at 3 points as shown in
Figure 9. The maximum displacement amount
reached about 80 mm at 12m depth from top of
ground.
From consolidation settlement results, collected
in both Asaoka and Hyperbolic methods. Fig. 13
shows final estimated settlement from by analysis
result, an average final consolidation settlement
Su of 70.27 cm and degree of conssolidation
Cu =92.1% was obtained.
Three electrical piezometers were installed
under the center embankment with different depth.
The excess pore water pressure at 5m, 15m and
25mm was shown in table 9 and Figure 14.
11
(a)
(b)
Figure 14. Monitoring data of Piezometer&
Prediction of ΔP for each depth
Figure 15. Settlement & consolidation after Feedback
analysis
5.4 Feedback analysis by measurement results
The purpose of feedback analysis is adjusted
design parameter using actual observation data in
order to predicted settlement tendency in actual
condition. This estimation will help to predicted
exactly final settlement and consolidation time can
be calculated through feedback analysis. Also,
slope stability can be assessed based on this
analysis. The procedure of feedback analysis
concludes: Obtaining the settlement curve with
original design parameter and actual site
construction speed and period. Obtaining the
settlement curve with measured data and settlement
analysis based on Hyperbolic & Asaoka method.
Finally, designed parameter such as Cs and Cc
would be adjusted to obtain new designed
settlement curve the same with actual observation.
Figure 15 show the recalculated settlement is
larger than the settlement observation based on actual
construction time after ending the stage 1. The
designed parameter carried out adjusting as shown in
Table 10.
The Figure 15 shows the settlement result after
feedback analysis. The settlement St amount
reached about 64.68 cm (a) and consolidation is
96.68% (b)
Table 10. Adjusted design parameter
Items Sta. 65+400
Soil Parameter
Detail
design
Feedback
Cc
Layer 2-1 0.25 0.152
Layer 2-2 0.48 0.293
Layer 2-4 0.36 0.219
Cs
Layer 2-1
1 1Layer 2-2
Layer 2-4
Sta. 65+400: about 39.05% reduction compared to
designed value (Cc)
6. CONCLUSION
The paper summarizes successful ground impro-
vement techniques (Sand Compaction Piles) used in
Hanoi-Haiphong Expressway Project, Viet Nam.
1) The advantage of SCP method is sliding preven-
tation for higher embankment and deep soft soil
areas, beside the sand is abundant in Viet Nam.
2) The SCP method can be applied widely to
reduce the settlement & consolidation at bridge
approachment to replace the Load Relief Slab
Method and Soil-Cement Column Method at
Hanoi-Haiphong Expressway Project.
12
Table 11 Summary Table of Embankment Construction Monitoring Status
Item Description Unit
EX6-A2 Bridge B05 : Km65+383~65+413
D D EX6-A2-B05 EX6-A2-B05
Sta. 65+383 Sta. 65+400 Sta. 65+400
General
Information
Treatment method - depth SCP @ 1.5~30.0 SCP @ 1.5~30.0 SCP @ 1.5~30.0
Elevation of VDs tip EL.m - -29.00 -29.00
Number of stages 2 2 2
Finish Grade (Elevation)=FG (DD) EL.m +8.71 +8.71
Initial ground level(DD) EL.m +1.09 +1.09
Initial ground Water level (DD) EL.m
Ground level after BHC stage EL.m +0.99 +0.99
Geotextile level EL.m +1.00 +1.00
Embankment height (DD m 7.50 7.62 7.62
Estimated Settlement (DD) cm 160.4 160.4 160.4
Proposed embankment thickness
(Embankment height + settlement)
m 9.10 9.22 9.22
VD installation date date -
SSP installation date date - 6-Oct-12 6-Oct-12
Construction
Stage
Starting date of embankment date 6-Oct-12 6-Oct-12
Completion date of First Stage Filling date 28-May-13 28-May-13
Analysis date date 21-Jun-13 21-Jun-13
Emb. Elevation at end of stage filling EL.m +6.596 +6.596
Emb. Elevation at analysis date EL.m +6.514 +6.514
Emb. Thickness m 7.000 6.170 6.170
Emb. filling time day 70 234 234
Waiting time day 120 24 24
Monitored settlement (end of stage
filling)
cm 110.96cm 56.40cm 56.40cm
Monitored Settlement after waiting cm 127.46cm 64.60cm 64.60cm
Re-calculate settlement after waiting
(St)
cm
-
103.40cm 103.40cm
Feed back settlement after waiting (St) cm 64.68cm 64.68cm
Estimated settlement Re-calculate
or Feedback (Sf)
cm 66.90cm 66.90cm
Estimated Settlement Asaoka cm 67.49cm 67.49cm
Estimated Settlement Hyperbolic cm 73.04cm 73.04cm
Degree of consolidation - Asaoka % 95.71% 95.71%
Degree of consolidation - Hyperbolic % 88.44% 88.44%
Design requirements of this project satisfy satisfy
Conclusion Next stage could be started
3) The goal of this study is present a principle
theory Sand Compaction Pie method for the soil
improvement and behavior of composite ground
with a case study in Vietnam.
4) The geotechnical analysis of monitoring data
are presented to evaluated current status of soft
soil treatment and control the construction
procedure as well as to present new experiences
in monitoring work.
5) This paper will be a basic reference for soft soil
treatment engineer in Vietnam. The continous
development of this paper will attend to control
the quality of SCP after construction with many
field testing was carried out to estimate
7. REFERENCES
Adjusted Soft Soil Treatment Calculation Report
for Package EX-6, Hanoi-Haiphong Expressway
Project. Submitted by: Yooshin-KPT J.V. Detail
Design Consulting Servies (2010).
Aboshi, Hisao, Yasuo Mizuno, and Mashahiko
Kuwabara. "Present state of sand compaction pile
in Japan." Deep Foundation Improvements:
Design, Construction, and Testing, ASTM Special
Technical Publication 1089 (1991): 32-46.
Bang W.Shin; Eun C.Shin (1992). Sand Compaction
Piles: Theory and Practice for offshore
development. Proceedings of the Second
International Offshore and Polar Engineering
Conference. ISBN 1-880653-01-X, Vol 1.
Barksdale, R. D (1981). "Site improvement in
Japan using sand compaction piles."Georgia
Institute of Technology, Atlanta: 48-75.
Chow, Y. K (1996). "Settlement analysis of sand
compaction pile." Soils and foundations 36.1:
111-113.
13
Moh, Z. C., Ou, C. D., Woo, S. M., & Yu, K. (1981).
Compaction sand piles for soil improvement.
In Proc. X Int. Conf. on Soil Mechanics and
Foundation Eng., Stockholm, Vol. 3, pp. 749-752.
Sung-Min Cho; Byoung-Ill Kim; Young-Uk Kim;
Seung-Hyun Lee (2005). Effect of Soil
Compaction Piles on Settlement Reduction in
Soft Ground. International Journal of Offshore
and Polar Engineering (ISSN 1053 – 5381).
Vol. 15, No. 3, September 2005, pp. 235-240.
Juneja, A., B. Mir, and A. Parihar. "Effects of sand
compaction pile installation in model clay
beds." International Journal of Geotechnical
Engineering 5, no. 2 (2011): 199-209.
Tonimoto, K (1973). Introduction to the Sand
Compaction Pile Method as Applied to
Stabilization of Soft Foundation Grounds. No.
Tech. Rpt. 1973.
Terashi, Masaaki, Masaki Kitazume, and Shogo
Minagawa (1990). "Bearing Capacity of
Improved Ground by Sand Compaction
Piles." Deep foundation improvements: design,
construction, and testing: 47-61.
Yoon, M. J., et al (2004). "A study on the shear
strength of sand compaction pile with composite
soil and mixed soil." The KSCE Annual
Conference and Civil Expo 2004.

More Related Content

What's hot

Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Muhammad Irfan
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibrationAnjana R Menon
 
Consolidation settlement
Consolidation settlementConsolidation settlement
Consolidation settlementParth Joshi
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1R VIJAYAKUMAR
 
Static Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic IndeterminacyStatic Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic IndeterminacyDarshil Vekaria
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysisDivya Vishnoi
 
Question on pile capacity (usefulsearch.org) (useful search)
Question on pile capacity (usefulsearch.org) (useful search)Question on pile capacity (usefulsearch.org) (useful search)
Question on pile capacity (usefulsearch.org) (useful search)Make Mannan
 
Effect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionEffect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionSailish Cephas
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Make Mannan
 
Shear Strength of Soil
Shear Strength of SoilShear Strength of Soil
Shear Strength of SoilUmang Parmar
 
SOIL STABILIZATION USING LIME AND CEMENT
SOIL STABILIZATION USING LIME AND CEMENTSOIL STABILIZATION USING LIME AND CEMENT
SOIL STABILIZATION USING LIME AND CEMENTA. R. Atiq
 
Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240Wajahat Ullah
 
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Muhammad Irfan
 
coulomb's theory of earth pressure
 coulomb's theory of earth pressure coulomb's theory of earth pressure
coulomb's theory of earth pressureSANJEEV Wazir
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsNatarajaSaiCharan1
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-convertedNigitha rajan
 

What's hot (20)

Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
 
Consolidation settlement
Consolidation settlementConsolidation settlement
Consolidation settlement
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1
 
Static Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic IndeterminacyStatic Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic Indeterminacy
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
 
Question on pile capacity (usefulsearch.org) (useful search)
Question on pile capacity (usefulsearch.org) (useful search)Question on pile capacity (usefulsearch.org) (useful search)
Question on pile capacity (usefulsearch.org) (useful search)
 
Effect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionEffect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its prevention
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
 
Influence line
Influence lineInfluence line
Influence line
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Shear Strength of Soil
Shear Strength of SoilShear Strength of Soil
Shear Strength of Soil
 
Effective stress
Effective stressEffective stress
Effective stress
 
SOIL STABILIZATION USING LIME AND CEMENT
SOIL STABILIZATION USING LIME AND CEMENTSOIL STABILIZATION USING LIME AND CEMENT
SOIL STABILIZATION USING LIME AND CEMENT
 
Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240
 
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
 
coulomb's theory of earth pressure
 coulomb's theory of earth pressure coulomb's theory of earth pressure
coulomb's theory of earth pressure
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-converted
 
Soil slope stability
Soil slope stabilitySoil slope stability
Soil slope stability
 

Similar to A case study on soft soil improvement of hanoi haiphong expressway project in vietnam

Presentation 3 (1) (2).pptx
Presentation 3 (1) (2).pptxPresentation 3 (1) (2).pptx
Presentation 3 (1) (2).pptxSindhuNalamati
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxDolanGhosh4
 
Ground imrovement introduction
Ground imrovement   introductionGround imrovement   introduction
Ground imrovement introductionSanjay Thakare
 
International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)irjes
 
Bearing capacity of sand overlying clay strip footing - paxis 3 d
Bearing capacity of sand overlying clay   strip footing - paxis 3 dBearing capacity of sand overlying clay   strip footing - paxis 3 d
Bearing capacity of sand overlying clay strip footing - paxis 3 dGonzalo Nureña Zegarra
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxolaboughannam1
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxolaboughannam1
 
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of SoilIRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of SoilIRJET Journal
 
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of SoilIRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of SoilIRJET Journal
 
Effect of encasement length on geosynthetic reinforced stone columns
Effect of encasement length on geosynthetic reinforced stone columnsEffect of encasement length on geosynthetic reinforced stone columns
Effect of encasement length on geosynthetic reinforced stone columnseSAT Publishing House
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementADFIAP
 
"A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils""A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils"Remedy Geotechnics Ltd
 
Juscélia testing soil encasing materials for measuring hydraulic conductivit...
Juscélia  testing soil encasing materials for measuring hydraulic conductivit...Juscélia  testing soil encasing materials for measuring hydraulic conductivit...
Juscélia testing soil encasing materials for measuring hydraulic conductivit...Juscélia Ferreira
 
IRJET- A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...
IRJET-  	  A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...IRJET-  	  A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...
IRJET- A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...IRJET Journal
 
Soil nailing seminar report by ankush choudhury
Soil nailing seminar report by ankush choudhurySoil nailing seminar report by ankush choudhury
Soil nailing seminar report by ankush choudhuryAnkush Choudhury
 

Similar to A case study on soft soil improvement of hanoi haiphong expressway project in vietnam (20)

Presentation 3 (1) (2).pptx
Presentation 3 (1) (2).pptxPresentation 3 (1) (2).pptx
Presentation 3 (1) (2).pptx
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptx
 
Stone-column.pptx
Stone-column.pptxStone-column.pptx
Stone-column.pptx
 
Ground imrovement introduction
Ground imrovement   introductionGround imrovement   introduction
Ground imrovement introduction
 
Ijetcas14 549
Ijetcas14 549Ijetcas14 549
Ijetcas14 549
 
Soil improvement techniques
Soil improvement techniquesSoil improvement techniques
Soil improvement techniques
 
International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)
 
SSI-PerviousPile-2011
SSI-PerviousPile-2011SSI-PerviousPile-2011
SSI-PerviousPile-2011
 
Bearing capacity of sand overlying clay strip footing - paxis 3 d
Bearing capacity of sand overlying clay   strip footing - paxis 3 dBearing capacity of sand overlying clay   strip footing - paxis 3 d
Bearing capacity of sand overlying clay strip footing - paxis 3 d
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptx
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptx
 
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of SoilIRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
 
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of SoilIRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
IRJET- Effect of Stone Column and Encased Stone Column in Settlement of Soil
 
Effect of encasement length on geosynthetic reinforced stone columns
Effect of encasement length on geosynthetic reinforced stone columnsEffect of encasement length on geosynthetic reinforced stone columns
Effect of encasement length on geosynthetic reinforced stone columns
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground Improvement
 
"A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils""A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils"
 
Case study
Case studyCase study
Case study
 
Juscélia testing soil encasing materials for measuring hydraulic conductivit...
Juscélia  testing soil encasing materials for measuring hydraulic conductivit...Juscélia  testing soil encasing materials for measuring hydraulic conductivit...
Juscélia testing soil encasing materials for measuring hydraulic conductivit...
 
IRJET- A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...
IRJET-  	  A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...IRJET-  	  A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...
IRJET- A Review on the Combined Effect of Lime, Flyash and Geosynthetic R...
 
Soil nailing seminar report by ankush choudhury
Soil nailing seminar report by ankush choudhurySoil nailing seminar report by ankush choudhury
Soil nailing seminar report by ankush choudhury
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 

A case study on soft soil improvement of hanoi haiphong expressway project in vietnam

  • 1. Geotechnics for Sustainable Development - Geotec Hanoi 2013, Phung (edt). Construction Publisher. ISBN 978-604-82-0013-8 1 Keywords: case history, consolidation, sand compaction pile, settlement, ground improvement ABSTRACT: A case of using Sand Compaction Pile method to improve the foundation soil for expressway in Vietnam is presented. The sand compaction pile (SCP) method, which forms a composite ground by driving the pile made of compacted sands into soft ground, is one of the commonly used soil improvement techniques in Viet Nam. The SCP method used to improve the ground through the increase of bearing capacity, which is achieved by improving loose sandy soils or accelerating the consolidation of soft clay soils. Within the country where the condition of sand purchase is abundant in Viet Nam, sand compaction pile were often used for soft ground improvement to replace the Load Relief Slab and Soil-Cement Column at Hanoi-Haiphong Expressway Project recently. The procedures used for soil improvement, the instrumentation and the field monitoring data are described. A few observational methods based on settlement records are available to predict future settlement and consolidation behavior, namely the hyperbolic (Tan 1971; Chin 1975) and Asaoka (Asaoka 1978) method. The field data were from the Thai Binh Bridge approached embankment construction at Hanoi-Haiphong Expressway Project. 1. INTRODUCTION The sand compaction pile (SCP) method is frequently used in construction to form compacted sand piles by vibration, dynamic impact, or static excitation in soft grounds. The principle of the SCP method is based on the research papers by Murayama and Tamimoto published in 1957 and 1960, as the hammering method developed in1957 (Ministry of construction 1957). A composite ground consisted of rows of compacted large diameter sand columns were driven into a soft clay ground in coastal district of Japan, as the foundation of a structure (Murayama 1957). The usage of the SCP method extended to improve soft clays since the 1960’s (Ogawa 1963, Ibaragi 1965). The subsequent presentation of Murayama’spaper in 1962 established the method of SCP application to clayey soil. This method was further justified through number of researches and construction projects. A casing pipe with a plug of sand at its tip was driven to the bottom of improved layer by a vibrator method. After pouring sand or gravel material into the casing pipe, the casing pipe was withdrawn partly and again driven down to compacted the sand column and enlarge its diameter. This process is repeated as far as compacted sand column reaches to the ground surface. The mechanism of stabilization by the SCP method in the case of clayey ground is perfectly different than the sandy grounds, which is simply to density the surrounding soil. There is almost no effect of densification in case of clayey soils. However, these SCPs behave as piles in soft grounds and totally can carry more load than without SCP. At the same time, they also work as A case study on soft soil improvement of Hanoi-Haiphong expressway project in Vietnam Hoang Tien Trung FECON-Foundation Engng & Underground Construction, Hanoi, Vietnam. E-mail: trunght@fecon.com.vn Jang Woo Young GS Engineering & Construction. Seoul, Korea. E-mail: wyjang@gsconst.co.kr
  • 2. 2 vertical drains to accelerate consolidation of clayey grounds. In particular, for construction on embankments over soft soil like soft clay, peaty soil, which has very slow shear strength, the installation of SCPs enhances the stability of the embankment slope, helps to increase the bearing capacity, and accelerates the consolidation rate of the foundation soil. The automatically controlled SCP driving system was invented in 1981 accommodating the vibration effect on soil properties. In the Western world, the stone column method-gravel compaction pile (GCP) method has been used to improve soft ground since the 1970s (Baumann and Bauer, 1974; Hughes et al., 1975). As countermeasures for treatment of the soft ground was applied for this project, the Sand Compaction Pile, Sand Drain and Prefabricated Vertical Drain are compared each other. The displacement behaviour of SCP during installing on site was considered, a free moving condition, in which relative displacements occurs has been observed. A case study on the use of the Sand Compaction Pie method for the soil improvement for Hanoi-Haiphong expressway project is presented in this paper. The site conditions, the soil improvement procedure, and the field instrumentation are described. The field monitoring data are presented. The achieved degree of consolidation and the effect of soil improvement are evaluated. Several issues concerning the practical aspects of the sand compaction pile method are also discussed. 2. OUTLINE OF PROJECT Hanoi-Haiphong Expressway connects Hanoi Capital with Haiphong Port City, a route passing 4 provinces, cities: Gia Lam suburban district of Hanoi city, Van Giang, Yen My, An Thi suburban districts of Hung Yen province and An Lao, Kien Thuy suburban districts of Haiphong city. Project’s starting point is on the Ring Road III of Hanoi city, 1025 m far from north abutment of Thanh Tri Bridge, Gia Lam suburban district of Hanoi city. Ending point is at Dinh Vu Dam, Kien An district, Haiphong city. Investment shall be made in construction of Hanoi-Haiphong Expressway in conformity to international standards, expressway class A, design speed of 120 km/hr, six (6) traffic lanes, total length of 105.5 km, divided into many bidding packages. In this study, the paper presents guideline for design and construction the Sand Compaction Pile at Thai Binh Abutment area of Package EX-6 from Km63+300~Km72+000. Fig. 1 shows alignment direction (a), plan and profile (b) of SCP treatment area at Abutment A2 with standard section at Sta.65+400. (a) (b) Figure 1.Site location Table 2. Reviewing Results and Alternatives for D/D Stage Items Method for soft soil treatment Basic design Design alternative Consolidation Acceleration Embank(H)<5m Soft soil layer thickness(D)<20 PVD PVD SD Embank(H)≥5m Soft soil layer thickness(D)≥20 SD PVD SD Sliding prevention LRS; SCC* SCP; LRS; SCC * LRS: Load Relief Slab; SCC: Soil-Cement Column. This package is planned to be completed within 32 months. And a period of less than 18 months approximately is recommended for soft soil treatment in consideration of the following issues: time for preparation works, time for construction of culverts and underpass structures, time for construction of piles and abutments, time for construction of pavement and completion, and reasonable reuse of surcharge and preloading material section by section to minimize expense for material. There are several methods to treat the soft ground, but it is generally classified into two categories as sliding-prevention method and consolidation acceleration method. Soft soil treatment proposal of Basic Design was reviewed and, accordingly, some alternatives were primarily
  • 3. 3 proposed for Detail Design. All the reviewing results are summarized in following Table 2. As countermeasures for treatment of the soft ground among the consolidation acceleration methods mentioned above, Prefabricated Vertical Drain, Vertical Sand Drain are compared each other. The PVD is the most appropriate for uniform soft soil area and without sand seam, SD is appropriate for sand seam and non-uniform soft soil areas. The Load Relief Slab, Soil-Cement Column and Sand Compaction Pile are proposed for treatment of the soft ground among the sliding prevention methods of this Package and compared each other as show in Table 3. Table 3. Comparison of sliding prevention methods for high embankment Items Load Relief Slab Soil-Cement Column Sand Compaction Pile General Aspects - Support loads by concrete piles (35cmx35cm) and 0.3m concrete slab on soft soil layer - Support load by soil cement mixed column (D=1.3m) - Support upper load by forming 70cm diameter compaction sand pile in soft soil layer Advanta ge -Effective in settlement reduction by transferring the loads directly to bearing layer -Many experiences in Viet Nam - Prevention of sliding and reduction of settlement by using soil cement columns - ffective on sliding prevention and consolidation acceleration -Sand is abundant in Viet Nam Disadva ntage -Quality control is required - High construction costs - Difficult to control pile quality and construction procedure - High construction costs - Limited experiences in Viet Nam -No construction experiences in Viet Nam Time for consolid ation 0 month 0 month 10 months Cost 3.0 2.3 1.0 Proposal and Plan SCP is the most appropriate for high embankment and deep soft soil areas From all above analysis, following criteria will be recommended as principle in general for primary selection of soft soil treatment method for this package. 3. GROUND CONDITION Fig. 2 shows ground condition in this package with the results of standard penetration tests. Soil investigation was carried out in detail design and additional design by means of a rotary drilling. The borehole locations are shown in Fig.2. It can be seen that the soft ground is about 30~32m deep with fat clay and sandy lean clay with SPT value around 4~6. Figure 2. Reference borehole log for SCP Treatment at Abutment A2 Thai Binh Bridge A2 Sta. 65+383~ Sta. 65+413 4. SOFT SOIL IMPROVEMENT METHOD 4.1 Design Concept At present, the design method of the SCP is usually divided into two methods. One is to check the stability of improved ground, in which a slip surface is assumed to pass through the replacement area composed of sand column and clay. Stability analysis is carried out the circular arc method. A replacement area ration and a stress concentration ratio on the slip surface are needed for the stability analysis. The other method is to check the consolidation settlement of the composite ground by considering the diameter, spacing and arrangement of the sand compaction piles and the stress concentration ratio of the composite ground. a. Characteristics of composite ground In the development of a theory for the SCP method, many researchers have tried to simplify the problem of analysis by neglecting the interactions between the sand piles, and they have come up with the basic concept of SCP ground as shown in Fig. 3 (Murayama, 1962; Ichmoto and Seumatsu, 1982). When the composite ground is loaded, concentration of stress occurs in the sand
  • 4. 4 pile accompanied by the reduction in stress which occurs in the surrounding clayey soil as shown in Fig. 3. This can be explained by the fact that the vertical settlement of stress concentration in the SCP and the surrounding soil is approximately the same, and this causes the occurrence of stress concentration in the sand pile which is stiffer than the surrounding soil. The distribution of vertical stress within the unit cell can be expressed by a stress concentration ratio, (m) is defined as follows: m = σs/σc (1) where, σs = stress in the column and σc = the stress in the surrounding cohesive soil. The average stress, σ, over the unit cell area corresponding to a given area replacement ratio, as = As/(As + Ac) (2) is expressed as: σ = σs as + σc (1 as) (3) where, As = the area of a SCP and Ac = the area of the clay ground surrounding the pile. The relationships for σs and σc in composite ground also can be expressed using a stress increment factor, µs, in the sand pile and stress reduction factor, µc, in the surrounding soil and defined by the following: Figure 3. Basic concept of SCP ground        s s s m σ σ μ σ 1 (m 1)α (4)        c c s 1 σ σ μ σ 1 (m 1)α (5) Based on eq. (1) and eq. (3), eq. (4) and (5) have a relation of: µsas+ µc(1+as) = 1 (6) Therefore, eq. (2) can be rewritten as: m = µs/µc (7) Again, reduction of settlement due to the installation of SCP is expressed as a settlement reduction factor, β: β = St/S (8) where, St = the settlement of ground without treatment and S = the settlement of composite ground reinforced by a SCP. Equation (2), (4), (5) and (6) are usually used as basic parameters in design and analysis of composite ground. b. Design theory of sand compaction pile Replacement ratio The volume of soft clay replaced by sand is one of the most important factors in improving week ground using sand compaction piles. To quantify the amount of soil replacement, define the area replacement ratio as as the fraction of soil tributary to the pile replaced by the sand compaction pile. The replacement ratio is defined by the following expression and will be calculated for square and triangular pattern as follow: Figure 4. Arrangement and design concept of SCP For a square arrangement:          2A A π Ds sas 2A 4 dd (9) For a triangular arrangement:          A 2 A π D 2s sas 2A d3 2 3d (10) where, d = center-to-center spacing of the SCP; D = diameter of the completed SCP (not the diameter of the casing).
  • 5. 5 Design approach: To develop a practical design method, assume the total volume tributary to a sand compaction pile remains constant during the site improvement work. Also, neglect any increase in relative density caused by vibration as the casing is driven, and assume the loose sand is only displaced laterally away from the sand pile during construction. Referring to Fig. 4, let the change in volume of the in situ sand equal the volume of sand compaction pile per unit length, l=1m, Vscp giving: Vscp = V0 –V1 =         o 1e e Vv eo (11) Figure 5. Volume block diagram of in situ sand before and after SCP construction The area replacement ratio, which is defined by equation (2) giving: as=    scp o 1 o V e e A 1 e (12) where, eo = initial void ratio of loose sand before improvement; e1= final void ratio of loose sand after improvement. The equation (12) can be changed to a more useful form for design by considering a unit length of SCP construction. For a unit length l=1, solving for sand compaction pile spacing d gives for a square arrangement: d =       2 o o o scp o 1 o 1 1 e 1 e D V .V . e e e e 4  (13) and for a triangular arrangement d =   2 o o 1 1 e D . e e 2 3  (14)  Shear strength Soft ground after being treated by SCP will be considered a composite ground comprising of SCP and surrounding soft soil. Shear strength of the composite ground τsc is calculated as follow:        u sc s o o c c z 2 s s s z s C τ (1 a )(C (P P μ .σ )U p a (γ .Z μ .σ )tan .(cosθ) (15)        u sc s o o c c z 2 m z s s s C (1 a )(C ( P P . )U p (γ .Z σ ).μ .a .tan .(cosθ)     (16) where, Cu/p = ratio of strength increase; ' s = sub water unit weight of sand; Z = depth to the failure surface; s = friction angle of sand;  = Angle between acting surface and horizontal surface; z = increased stress at failure surface due to embankment loading; ' m = Average sub water unit weight of composite soil. Friction angle of sand (of SCP) and ratio of stress division depending on replacement ratio is shown in Table 1 below: Table 1. Friction angle and Ratio of stress division depending on replacement ratio Replacement Ratio, as Friction Angle of sand, s Ratio of stress division, m 0.0 ÷ 0.4 30 3 0.4 ÷ 0.7 30 2 0.7 ÷ 1.0 30 ÷ 35 1 Cohesion and internal friction angle of the composite soil being used for slope stability analysis are evaluated from following equation (13) and (14) respectively, which is derived from equation (11).   1 tan (n.tan )s  (17) UP. c μ c P o (P p u C o )(C s a(C ).1  (18) where, n = as.µs ; Po = effective overburden pressure; Pc= pre-consolidation pressure  Settlement Settlement of the composite ground is less than non-treated ground because SCP shares load acting upon the ground and, accordingly, SCP reduces stress acting upon soil. Following equation is used to get settlement of the composite ground. For normal consolidation          C P μ .ΔPc o cS H.log 1 e Po o (19)
  • 6. 6 For over consolidation and Pc > Po+ΔP          C P μ .ΔPs o cS H.log 1 e Po o (20) For over consolidation and Pc< Po+ΔP                  C CP P μ .ΔPs cc o cS H.log H.log 1 e 1 eP Po oo c (21) In the sand layer, the following formula can be used for immediately settlement (De beer method)         P P ΔPo oS 0.4. .H.logi N Po (22) where, Po = overburden pressure; ΔP = pressure caused by embankment; Cc = compression index; Cs = swell index; Pc = pre-consolidation pressure; H = soil thickness; N = standard penetration test value.  Coarse Sand Blanket Thickness The thickness of CSB is estimated based on the water head level caused by embankment loading, which is calculated from the following equation:  2L .S Δh K.h (19) where, Δh = water head level; h = thickness of CSB; K = permeability of CSB; L = horizontal drain length; S = settlement velocity. In order to ensure the drainage capacity, the thickness of CSB shall not be less than the above Δh value and 50cm 4.2 Design soil parameters Detail of the soil condition and soil properties was got in the Soil Investigation Report for Package EX-6 prepared by Transport Engineering Design Int. The following paragraphs will only be of analysis of soil values for soft soil treatment. The unit weight with depth of soil 2 is plotted in Fig. 6a, according to testing data. Initial undrain shear strength of soft soil (Co) will be evaluated from the following basis Field vane shear test (FVST) and Triaxial test UU-diagram (UU Test). Moreover, for a reliable Co value for design, the analyzing Co value will be referred to the following basic Cone penetration test (CPT) with Co=(qc-po)/Nk where, qc Cone resistance value, po overburdened effective pressure, Nk empirical cone factor, (Nk=15) and Standard penetration test (SPT) with Co=N*100/16 (KPa). The values of Co of soil 2 are plotted in following Fig. 6b. (a)Unit weight (b) Co Figure 6. Profile of unit weight & Initial undrain shear strength Co of soft soil Undrain shear strength of soft soil will be increase due to consolidation with a factor called “Factor of Increase of undrain shear strength” – m, which is evaluated from Triaxial test, CU scheme – CU test and, as instructed in the Standard 22TCN262-2000, m equals to tan(φcu). All m-value from CU testing data are plotted in following Fig. 7a. Fig. 7b plots all values of pre-consolidation pressure of the EX-6 deposit in comparison with overburden pressure of the soil. (a) (b) (c) Figure 7. Profile of UU test (a), Pc with depth and in comparing with overburden pressure (b) and Cc with depth (c) Fig. 7b clearly indicates that the soil is over consolidation from about 8m upward with Pc in order of 7t/m2 , and from this level downward the soil is normal consolidation. The following figure 7c plotting values of compression index Cc of soil 2a versus depth also quite clearly marks this boundary. According to Fig.7c, the following Cc value will be recommended for design:  Soil 2: <8m, Cc= 0.25 8-28m, Cc= 0.48 >28m, Cc= 0.36
  • 7. 7 Table 4. Summary of soil parameters recommen-ded for soft soil treatment design Soil properties Unit Soil L2-1 Soil 2 <8m 8m-28m >28m γ t/m3 1.87 1.74 1.67 1.74 Co t/m3 0 1.8 0.07z+1.24 φo - 24 - - - m - - 0.3 0.25 e - - Fig. 4-1 Fig. 4-2 Fig. 4-3 Cv.10-3 cm2 /sec Kv.10-7 cm/sec Cc - - 0.25 0.48 0.36 Cs - - 0.03 0.05 0.04 Pc t/m2 - 7.00 - - OCR - - 2.40 1 1 N - 7 Embankment material γ(t/m3 ) C(t/m2 ) φo 1.85 0 30 Figure 8a. Testing curves and typical one for soil 2 above 8m in depth Figure 8b. Testing curves and typical one for soil 2 from 8m to 28m Figure 8c. Testing curves and typical one for soil 2 below 28m in depth. The physical properties of the soil strata are summarized in Table 4. Consolidation testing data comprising of consolidation compression curves, consolidation coefficient and permeability and typical values of these parameters are plotted in following Fig. 8a, 8b and 8c for soil 2. 5. MONITORING RESULTS 5.1 Monitoring systems Monitoring system was carried out install and control during construction work in order to confirm whether to cause a slip failure and to generate a settlement as calculated and predicting by design or not. This paper presents monitoring works for approach of Thai Binh Bridge, Abutment A2 Sta. 65+383 ~ Sta. 65+413. As for the monitoring equipments, settlement plate, Alignment stakes, Observation well, Piezometer and Inclinometer were installed at section Sta. 65+400 as shown in Fig. 6. Figure 9. Arrangement of Monitoring Equipments Procedure and method for installation of monitoring equipment at the site was shown in Fig. 9. SSP shall be installed on the separation geotextile, in such a way that the top of the base plate rests horizontally (a). Alignment stakes
  • 8. 8 consists of 5 wood stakes per side, each 1.5m long, penetrating to a depth of 1.0 m and placed at 4.0m intervals on each side of the embankment (b). Alignment nails shall be placed on the top surfaced of the stakes, exactly on an alignment perpendicular to the roadway alignment. The depths of the inclinometers shall be installed at least 2m into the underlying hard stratum (c). Electric Piezometer shall be saturate 24 hours (d) to removal of air bubble in the cell before installation, and then taking the zero-reading. It is measured exactly again before installation in the field (e). Take readings directly after installation and continue periodically as the water pressure decreases after installation. We installed Observation well below original ground around 0.5m and filling coarse sand around the PVC Pipe to the designed elevation (f). (a) (b) (c) (d) (e) (f) Figure 10. Installed monitoring equipment at the site Typical monitoring frequency was proposed at daily basic for the first week, and then increased to few days or weekly basic during filling operation as shown in Table 5. Each instrument or observation point shall be read immediately before and after each change in loading, daily during filling operations, then at twice weekly intervals during the first month. Thereafter, until the end of the settlement period, each instrument or observation point shall be read at intervals not greater than once a week. Monthly readings shall then be made through the end of the construction period. Table 5. Frequency of reading Items During embankment or structural fill After embankment ~1month ~until the end of the settlement ~Until the end of the contract period -AWS, SSP, Piz., Inc., OW 1 time/day -Before and after change in loading -During filling operations 2 times/ week 1 time/ week 1 time/ month 5.2 Measurement control method and feed-back analysis A graphical approach to estimate final consolidation settlement and settlement rates from settlement data obtained during a certain time period was proposed by Asaoka (1978) and Hyperbolic method (1971). For the stability analysis, Tominaga-Hashimoto method and Matsuo-Kawamura method are used, which may be able to manage the stability of the landfill quantitatively. 5.3 Monitoring Results This paper presents the geotechnical analysis of monitoring data to evaluate current status of soft soil treatment and to propose starting next step for a case study Abutment A2 Thai Binh Bridge in Viet Nam using SCP method. Table 8 below presents detail construction processing in different with detail design. Fig. 11 shows the chart of time-settlement curve during a construction period of 1st stage (from 6 Otober 2012 to 21 June 2013) based on the monitored data obtain from settlement plate and re- calculated the settlement follow actual construction time by theory in. The settlement amount reached about 64.6 cm in compared with calculation is 127.46 cm.
  • 9. 9 Table 6. Settlement prediction method Classification Hyperbolic Asaoka method Concept Equation    f 0 1 s s a t  f 0 1 s s   f 0 1 s s    0 f 1 s 1   Reliability Prediction values and measured values are close. When degree of consolidation is over 70% prediction can be possible within 10% of error range Predictedsettlement is less than measured settlement and predicted value is getting close to measured value with time. When degree of consolidation is over 80%, prediction can be possible within 10% of error range Table 7. Stability control method Classification Tominaga-Hashimoto Matsuo & Kawamura Concept Control standard Embankment will failure if α2 ≥ 0.7 or α2 ≥α1 +0.5 Embankment will be in danger if Pi/Pf>0.8 Pi: Embankment Load Pf: Embankment load on failure Reliability In case lateral movement (δ) exceeds vertical settlement (S), it indicates unstable due to shear deformation. So regression line is inclined toward I-II area. The data of S and δ/S obtained from monitoring data are plotted in the chart. In case the plotted data is proceeding toward the failure line, it indicates unstable. Table 9. Actual excess pore pressure results dU Max(t/m2 ) Install EL Initial GWL Initial GWL Monitoring U0 (t/m2) Ut (t/m2 ) dU (t/m2 ) U (%) 5m 11.5 -5.4 0.94 0.94 4.46 5.62 1.16 89.60 15m 9.85 -15.4 23.48 25.62 2.14 78.27 25m 8.56 -25.4 39.75 41.43 1.68 80.37
  • 10. 10 Table 8. Status of construction Items Sta. 65+383 – Sta. 65+413 Detail Design Actual Condition Method Method treatment SCP Treatment Depth (m) 30.0 Spacing (m) 1.5 Filling time (days) 70 234 Waiting time (days) 120 24 Total (days) 190 258 Figure 11. Settlement-time Curve Figure 12. Lateral Displacement with Depth by Inclinometer (a) Asaoka method (b) Hyperbolic method Figure 13. Estimated final settlement by Asaoka & Hyperbolic Inclinometers were installed at both side of embankment. Figure 12 shows the chart of lateral displacement with depth monitored by inclinometer installed at 3 points as shown in Figure 9. The maximum displacement amount reached about 80 mm at 12m depth from top of ground. From consolidation settlement results, collected in both Asaoka and Hyperbolic methods. Fig. 13 shows final estimated settlement from by analysis result, an average final consolidation settlement Su of 70.27 cm and degree of conssolidation Cu =92.1% was obtained. Three electrical piezometers were installed under the center embankment with different depth. The excess pore water pressure at 5m, 15m and 25mm was shown in table 9 and Figure 14.
  • 11. 11 (a) (b) Figure 14. Monitoring data of Piezometer& Prediction of ΔP for each depth Figure 15. Settlement & consolidation after Feedback analysis 5.4 Feedback analysis by measurement results The purpose of feedback analysis is adjusted design parameter using actual observation data in order to predicted settlement tendency in actual condition. This estimation will help to predicted exactly final settlement and consolidation time can be calculated through feedback analysis. Also, slope stability can be assessed based on this analysis. The procedure of feedback analysis concludes: Obtaining the settlement curve with original design parameter and actual site construction speed and period. Obtaining the settlement curve with measured data and settlement analysis based on Hyperbolic & Asaoka method. Finally, designed parameter such as Cs and Cc would be adjusted to obtain new designed settlement curve the same with actual observation. Figure 15 show the recalculated settlement is larger than the settlement observation based on actual construction time after ending the stage 1. The designed parameter carried out adjusting as shown in Table 10. The Figure 15 shows the settlement result after feedback analysis. The settlement St amount reached about 64.68 cm (a) and consolidation is 96.68% (b) Table 10. Adjusted design parameter Items Sta. 65+400 Soil Parameter Detail design Feedback Cc Layer 2-1 0.25 0.152 Layer 2-2 0.48 0.293 Layer 2-4 0.36 0.219 Cs Layer 2-1 1 1Layer 2-2 Layer 2-4 Sta. 65+400: about 39.05% reduction compared to designed value (Cc) 6. CONCLUSION The paper summarizes successful ground impro- vement techniques (Sand Compaction Piles) used in Hanoi-Haiphong Expressway Project, Viet Nam. 1) The advantage of SCP method is sliding preven- tation for higher embankment and deep soft soil areas, beside the sand is abundant in Viet Nam. 2) The SCP method can be applied widely to reduce the settlement & consolidation at bridge approachment to replace the Load Relief Slab Method and Soil-Cement Column Method at Hanoi-Haiphong Expressway Project.
  • 12. 12 Table 11 Summary Table of Embankment Construction Monitoring Status Item Description Unit EX6-A2 Bridge B05 : Km65+383~65+413 D D EX6-A2-B05 EX6-A2-B05 Sta. 65+383 Sta. 65+400 Sta. 65+400 General Information Treatment method - depth SCP @ 1.5~30.0 SCP @ 1.5~30.0 SCP @ 1.5~30.0 Elevation of VDs tip EL.m - -29.00 -29.00 Number of stages 2 2 2 Finish Grade (Elevation)=FG (DD) EL.m +8.71 +8.71 Initial ground level(DD) EL.m +1.09 +1.09 Initial ground Water level (DD) EL.m Ground level after BHC stage EL.m +0.99 +0.99 Geotextile level EL.m +1.00 +1.00 Embankment height (DD m 7.50 7.62 7.62 Estimated Settlement (DD) cm 160.4 160.4 160.4 Proposed embankment thickness (Embankment height + settlement) m 9.10 9.22 9.22 VD installation date date - SSP installation date date - 6-Oct-12 6-Oct-12 Construction Stage Starting date of embankment date 6-Oct-12 6-Oct-12 Completion date of First Stage Filling date 28-May-13 28-May-13 Analysis date date 21-Jun-13 21-Jun-13 Emb. Elevation at end of stage filling EL.m +6.596 +6.596 Emb. Elevation at analysis date EL.m +6.514 +6.514 Emb. Thickness m 7.000 6.170 6.170 Emb. filling time day 70 234 234 Waiting time day 120 24 24 Monitored settlement (end of stage filling) cm 110.96cm 56.40cm 56.40cm Monitored Settlement after waiting cm 127.46cm 64.60cm 64.60cm Re-calculate settlement after waiting (St) cm - 103.40cm 103.40cm Feed back settlement after waiting (St) cm 64.68cm 64.68cm Estimated settlement Re-calculate or Feedback (Sf) cm 66.90cm 66.90cm Estimated Settlement Asaoka cm 67.49cm 67.49cm Estimated Settlement Hyperbolic cm 73.04cm 73.04cm Degree of consolidation - Asaoka % 95.71% 95.71% Degree of consolidation - Hyperbolic % 88.44% 88.44% Design requirements of this project satisfy satisfy Conclusion Next stage could be started 3) The goal of this study is present a principle theory Sand Compaction Pie method for the soil improvement and behavior of composite ground with a case study in Vietnam. 4) The geotechnical analysis of monitoring data are presented to evaluated current status of soft soil treatment and control the construction procedure as well as to present new experiences in monitoring work. 5) This paper will be a basic reference for soft soil treatment engineer in Vietnam. The continous development of this paper will attend to control the quality of SCP after construction with many field testing was carried out to estimate 7. REFERENCES Adjusted Soft Soil Treatment Calculation Report for Package EX-6, Hanoi-Haiphong Expressway Project. Submitted by: Yooshin-KPT J.V. Detail Design Consulting Servies (2010). Aboshi, Hisao, Yasuo Mizuno, and Mashahiko Kuwabara. "Present state of sand compaction pile in Japan." Deep Foundation Improvements: Design, Construction, and Testing, ASTM Special Technical Publication 1089 (1991): 32-46. Bang W.Shin; Eun C.Shin (1992). Sand Compaction Piles: Theory and Practice for offshore development. Proceedings of the Second International Offshore and Polar Engineering Conference. ISBN 1-880653-01-X, Vol 1. Barksdale, R. D (1981). "Site improvement in Japan using sand compaction piles."Georgia Institute of Technology, Atlanta: 48-75. Chow, Y. K (1996). "Settlement analysis of sand compaction pile." Soils and foundations 36.1: 111-113.
  • 13. 13 Moh, Z. C., Ou, C. D., Woo, S. M., & Yu, K. (1981). Compaction sand piles for soil improvement. In Proc. X Int. Conf. on Soil Mechanics and Foundation Eng., Stockholm, Vol. 3, pp. 749-752. Sung-Min Cho; Byoung-Ill Kim; Young-Uk Kim; Seung-Hyun Lee (2005). Effect of Soil Compaction Piles on Settlement Reduction in Soft Ground. International Journal of Offshore and Polar Engineering (ISSN 1053 – 5381). Vol. 15, No. 3, September 2005, pp. 235-240. Juneja, A., B. Mir, and A. Parihar. "Effects of sand compaction pile installation in model clay beds." International Journal of Geotechnical Engineering 5, no. 2 (2011): 199-209. Tonimoto, K (1973). Introduction to the Sand Compaction Pile Method as Applied to Stabilization of Soft Foundation Grounds. No. Tech. Rpt. 1973. Terashi, Masaaki, Masaki Kitazume, and Shogo Minagawa (1990). "Bearing Capacity of Improved Ground by Sand Compaction Piles." Deep foundation improvements: design, construction, and testing: 47-61. Yoon, M. J., et al (2004). "A study on the shear strength of sand compaction pile with composite soil and mixed soil." The KSCE Annual Conference and Civil Expo 2004.