SlideShare a Scribd company logo
1 of 8
Download to read offline
Missouri University of Science and Technology
Scholars' Mine
International Conference on Case Histories in
Geotechnical Engineering
(1998) - Fourth International Conference on Case
Histories in Geotechnical Engineering
Mar 8th - Mar 15th
Design, Construction and Behavior of Bored Cast
In-situ Concrete Piles in Bangkok Sub Soil
Narong Thasnanipan
SEAFCO Co., Ltd., Bangkok, Thailand
Wanchai Teparaksa
Chulalongkorn University, Bangkok, Thailand
Aung Win Maung
SEAFCO Co., Ltd., Bangkok, Thailand
Ganeshan Baskaran
SEAFCO Co., Ltd., Bangkok, Thailand
Follow this and additional works at: http://scholarsmine.mst.edu/icchge
Part of the Geotechnical Engineering Commons
This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been accepted for inclusion in International
Conference on Case Histories in Geotechnical Engineering by an authorized administrator of Scholars' Mine. This work is protected by U. S. Copyright
Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact
scholarsmine@mst.edu.
Recommended Citation
Thasnanipan, Narong; Teparaksa, Wanchai; Maung, Aung Win; and Baskaran, Ganeshan, "Design, Construction and Behavior of
Bored Cast In-situ Concrete Piles in Bangkok Sub Soil" (1998). International Conference on Case Histories in Geotechnical Engineering.
45.
http://scholarsmine.mst.edu/icchge/4icchge/4icchge-session01/45
281
I
Proceedings: Fourth International Conference on Case Histories in Geotechnical Engineering, SL Louis, Missouri,
March 9-12, 1998.
- .
DESIGN, CONSTRUCTION AND BEHAVIOUR OF BORED CAST IN-SITU
CONCRETE PILES IN BANGKOK SUB SOIL
Narong Thasnanipan
Seafco Co.. Ltd.
Bangkok 10320
Thailand
ABSTRACT
Wanchai Teparaksa Aung Win Maung
Civil Engineering Dept. Seafco Co., Ltd.
Chulalongkorn University Bangkok 10320
Bangkok 10330 Thailand
Thailand
Ganeshan Baskaran
Seafco Co.. Ltd.
Bangkok 10320
Thailand
Paper No.1.20
This paper briefs design considerations. construction metl1ods and materials. static load test results and pile integrity test results of
the cast in-situ bored piles constructed as foundation elements for awastewater treatment plant. The treatment plant is located in
Bangkok. capital ofthe Kingdom ofThailand and is to serve about 195,000 inhabitants ofthe city. Atotal of402 piles. 296 nos. of
1500 mm diameter and 96 nos. of 1000 mm diameter, were designed to carry the whole structural load of the treatment plant.
Maximum working load on individual piles was designed to be l000 tons and 500 tons for 1500 mm and l000 mm diameter pile
respectively with asafety factor of2.5. Initially tl1e pile toe depth was designed to be 60mbelow the ground level, and embedded into
hard clay for 1500 mm diameter piles while the smaller diameter pile embedded into second sand layer at adepth of53m and base
was not decided to be grouted. Pile load test results on fully instrumental pilot piles showed tl1e failure well before reaching the
designed test load. Piles were re-designed and pile toe depth was set to be 55m, embedded into dense sand layer for both sizes and
base grouting was decided to be done for all piles. Proof load test results performed on four working piles(contract piles), two for
each size. produced well acceptable results confonning to the design and structural specifications and requirements. However,
settlements observed were higher tl1an that observed for other projects in the vicinity. Base Grouting was done using tube -a
manchette method. Amaximum volume of500 liter ofcement grout (w/c ratio,., 0.5) or maximum grouting pressure of40 bars was
usedas limiting criteria. However, maximum pressure of40 barswas hardly acltleved. From the proofload test results ultimate load
capacity was estimated and compared using different methods suggested by previous researchers. Integrity test was decided to be
perfonned on each pile and results available currently are summarized.
KEYWORDS
BoredPiles. Base Grouting, Static Pile LoadTest Integrity Tesi Pile Capacity
site, if an extra bearing capacity of 250 t/m::! could be
achieved by base grouting. the grouted piles would be capable
of carrying the designed safe working loads with adequate
safety factor.
Based on the results from a project just near by the site and
past e:xl)Criences in the vicinity it was proposed that the above
mentioned required capacity could be achieved by base
grouting the piles with tip founded at about 55 m from the
ground.
The option of extending the pile length was given up as the
clay layer is found to be at about depth of 60 m and thus
possibly higher initial settlement was expected if the piles are
embedded into the clay layer. Moreover, the end bearing
capacity would be reduced and this reduced end bearing
capacity might influence the shaft bearing capacity too. This
conclusion was reinforced by the previous pile load test
results on a pilot pile. founded at 60m and non base grouted.
This non grouted and longer pile of diameter 1500 mm,
constructed by some other piling contractor, failed at about
1750 tons. while the designed maximum test load was 2500
tons. The I000mm diameter pilot pile was. though not
plunged to failure. settlement observed was too excessive for
the structural requirements. Load settlement characteristics of
these pilot test piles have been shown in Fig. 4(a) and Fig.
4(b). Finally the previous piling contractor was disqualified
and the new contractor was called upon.
CONSTRUCTION METHODS. MATERIALS AND
PROBLEMS
Wet process
The usual wet process using the bentonite slurry was adopted.
Tempornry casing of length 15m was used to maintain the
hole stability in top soft layer. The holes were drilled using
augers and then continued using the bucket method. The
slurry was introduced upon reaching the first sand layer and
maintained all the time higher enough to support the bore.
The slurry was monitored continuously for the properties of
density. viscosity. pH and sand content.
Construction of bored piles started during the rainy season
and therefore the site needed additional requirements to
improve the working condition. As the water level was high
in the Chaophrnya river flood protection was needed. Because
of the nature of the Bangkok sub soil and the project site was
previously used as urban waste dun1ping area. the site was
very swampy during the rainy season gave a lot of
inconveniences in solving problems for drainage of water
accumulated. TI1e situation was further aggravated as the
excavated soil was not able to be removed on time. All these
reduced the productivity rate drastically. However. all the
piles were cast within the time frame set according to the
contract.
282
Slurry properties
The limiting values for the bentonite slurry according to the
contract specification were 1.04 - 1.20 for density; 30-40s for
viscosity (Marsh's cone); not less than 7 for pH and not more
than 3% for sand content.
On average 3.5 % of bentonite concentration was used.
Bentonite properties were monitored before concreting for all
piles. Arbitrary checking was done during drilling. From the
bentonite results. no significant changes were observed. On
average. the viscosity observed was 32.8s (Marsh cone); with
1naximum of 40s and a minimwn of 29s. The average values
of I.Ilg/cc. 8.9, 1.62% were noted for density, pH and sand
content respectively. The minimum values are l.02g/cc, 7,
0.1% and maximum values are 1.1 lg/cc, 9 and 1.55
respectively. Eventhough. the sand content was set to be
within 3%, at times it was difficult to achieve this. In this
cases complete recycling of the slurry was done.
Concreting and Reinforcement
Concrete cube strength of 350 ksc (35 Mpa) was used with
minimum cement content of 400 kg/m3
. Concreting was done
by usual tremie method of 250mm tremie pipe. Concreting
was requested to be done witl1 in twenty four hours after final
excavation. Since a concrete batching plant was established
within the project area. concrete supply was usually regular
and timely supplied otl1erwise it would have been a major
concern in Bangkok because of its ill fated traffic congestion.
Average concreting rate was about 25 - 30 cu.m per hour.
After pouring the concrete to the desired level, the temporary
casing was witl1drawn.
Reinforcement was provided to full length of the pile
considering the possible tensile forces during construction
period of the structure. Maximum of 0.5% of cross sectional
area was used for both sizes ofthe piles.
All the main bars used for reinforcement are of high strength
defonned bars of 4000 ksc (400 Mpa) and round bars of 2400
ksc (240 MPa) were used for spirals. Reinforcement was
provided by fabricating in the form of cages as usual and the
maximum len1:,»th of a cage was set to be 12 m. A minimum
lap length of forty times the diameter of tl1e bars was used at
the joints of tl1e cages.
Inclusions in pile top and concrete level below trimming level
Few cases were observed where tl1e concrete level was below
the designed cut off level and/or inclusions in pile top portion.
Mainly, this has been contributed by the high un- predicted
slumping down of concrete upon extracting the temporary
casing. As Fleming et al. (1985) pointed out concrete would
nonnally be retained by cohesive soils with shear strength in
INTRODUCTION
The city of Bangkok has been emerged as one of heavily
populated urban cities in the world. Due to its rapid economic
growth. the construction industry has been challenged to
develop the infrastructure to cope with the booming economy.
As a result. while multi storied private owned buildings
become most attractive sky scrapers in this city of Angels.
huge portion of the Government budget is swallowed by new
projects involving construction of highways and railways.
both elevated and at-grade. sub ways. large span bridges and
water and wastewater treatment facilities. Construction
industry is further challenged by tl1e city's subsoil condition
as it is plagued with a lot of constraints such as. presence of
thick soft clay as top strata, land subsidence and high risk of
flooding. These constraints compel most structures be relied
on pile foundation usually. on large diameter bored cast in-
situ piles. embedded into first or second sand layers. Though.
the first large bored pile was installed nearly two decades ago
in this city and hundreds of thousands of piles have already
been constructed. design. construction methods, perfonnances
and effectiveness of these piles are seldom studied and rarely
reported.
The project site is located at the Rama III road. with east
boundary along the Chao Phraya river which is the largest of
its kind in the kingdom. The piles are usually of 1500mm and
1000 mm diameters. The maximum design working load on
piles are 500 tons and I000 tons for l000 mm and 1500 mm
piles respectively. Pile toe was designed to be embedded into
second sand layer at depth 55m from the ground level. Fig. I
shows the general layout of the piles. All the piles are cast in
situ bored piles under wet process and base grouted.
Fig. I General lay-out ofboredpiles
SUBSOIL CONDITIONS
The gcotechinical investigation at the site indicates tl1at a
strata of 14 - I5m thick soft clay layer occurs in the project
283
area as common in Bangkok sub soil. This soft clay is
sensitive and has an-isotropic and time dependent stress
strain properties. Below is stiff to very stiff clay layer
underlain by hard clay layers. These clay layers extend down
to about 42m in depth. However, the subsoil condition below
36m from the ground level in the project area is variable - a
sand layer with a thickness of about 13m is present
sporadically. In some locations within the project site. a stiff
to hard dark gray clay is also found at the depth between 40m
and 49m. Generally a thick dense sand layer is located below
50m from the existing ground level. However, at this area
alternated layers of dense sand and hard clay of 5m thick also
was encountered. Fig. 2 shows the general bore log data
observed at the site.
----·--- - - - -
.,~...... IOC 110 0
t---j'--+-t-· - - ,
---1
-~·-·•••u.-··.. -· I
'b_, i
-· '- '
-"° !
- j
a~ ... j
u
"'.
6 a
-• 0
D •
' 00
.__L ,-
j 11:
....1..§:
.........._._...__-NCMft
Data from 3 bore holes within the project site
~ - - - ---- ..... _ - - - - - - - - - - - - ~
Fig 2 Soil profile at the project site
PILE CAPACITY AND DESIGN CONSIDERATIONS
I
The load capacity of the piles were estimated for the soil
failure using tl1e available soil data. Safety Factor of 2.5 was
used for both end bearing and shaft bearing capacities
considering the negative skin friction as well. The estimated
safe working load in tons. using individual three bore hole
data are 480, 508 and 583 for IOOO mm piles and 839, 880
and 993 for 1500 mm piles.
The estimated load capacity. with required safety factor, from
the soil bore log results is, in many cases, below the designed
safe working load. Hence, means of improving pile bearing
capacity was considered. The pile bearing capacity can be
improved either by extending the pile length further or by
grouting the pile or by enlarging the pile base. Usually,
enlarging the base for long piles is hardly practiced in
Bangkok. Piling contractors rather prefer to extend the length
of the shaft and additional required capacity is achieved by
the shaft friction. For the bored piles designed at this project
excess of 15 kN/m:: and this limit is rarely achieved by the top
soft clay of Bangkok sub soil.
Final sound concrete level has been a talking point between
the main contractor and piling contractor for both cases
where the final concrete level is above and below the designed
trim level. Usually for the first case the main contractor
suffered to trim the long pile heads but in the latter cases the
piling contractor was called upon for remedial works.
However. it should not be neglected that tl1e possibility of
failure to over flush enough concrete at the pile head to
ensure that all concrete present below the trim level is of full
strength and thus having the inclusions at the pile top.
Verticality and Position Errors
Verticality tolerance was set to be l in 100 and no piles have
been found to be out of this tolerance. However, four piles
(about 1% of the total) have been found to be out of position
deviating the specified tolerance of 7.5cm plus the allowance
for verticality. However. many of them were found to be
under the mat on which the columns were to be erected.
Hence. dealing with these erroneous locations was not
dramatic and modification of reinforcement for the mat have
been done according to the redistributed load.
GROUTING
The effectiveness of base grouted piles in Bangkok sub soil
was studied by many previous researches. Teparaksa (1994)
suggests base grouting mainly aims to increase soil stiffness
beneath the pile base which was affected by the boring
process. Also he noted that for these piles the displacement at
fully mobilized skin friction is in the order of l.59 to l.86
percent of the diameter. Test results in this project too agrees
the range suggested.
The PE pipes (OS') and tube-a manchette were in-corporated
into the reinforcement cages and lowered into the bore to
facilitate the base grouting. The grouting was done after the
concrete is set. usually the base was cracked using a high
water pressure not later than twenty four hours. and grout was
injected.
,-··- - -- . .. ----·--
I
I.
0,;.··
NAJllc:JlnTI:
r--1 NETAL Tlllt ..• •. 1/ ~·
ill
:::::.ID 1/r
n TU•t:: •• 11r
--I N<TAL TUii£ ID 1/r
11"':.:1:::-~,_....,..,,
Fig.3 Tube a manchette used.for grouting
284
The grouting process was controlled by either maximum
grout volume of 500 litters or a maximum pressure of 40 bars.
But. the pressure of 40 bars was rarely achieved and thus
usually the grout volume was the limiting factor. Usually the
grouting pressure was within the range of 20 - 30 bars.
Injection rate of grout was lO- 15 liters/ min. Experiments on
grout samples collected from three of the bored piles
(1500mm dia.) in this site was performed by Anwar (1997).
Comparison of base grouted and soft base (non base grouted)
piles were studied and summarized in Table 1. It was
recommended that low injection rate about 1-2 liters/min
would improve the effectiveness of base grouting. However,
practicality and sustainability of grout pump, especially for
large volume of grout, can hardly justify this requirement.
Though the direct comparison of effect of base grouting is not
possible as the compared piles are founded in different soil
strata other parameters in Table l are worth enough to be
noted.
Table 1 load distribution and settlement behavior of base
grouted and soft base piles.
Base Soft
Grouted Base
Diameter(mm) 1500 1500
Base Depth (m) 55 60
Design Load Qd (ton) 1000 1000
Failure Load (ton) 2725 * 1750
Load at 20mm total settlement (Qd 2290 1520
% increase in Or. 50.66
Portion ofQL carried by shaft (Qs) 1720 1450
% increase in Qs 18.6
Portion ofQL carried by base (Oi,1 570 70
% increase in 0., 714
Total settlement at (Qd) (mm) 5 8.13
Total settlement at 1.5 Qd (mm) 7.5 15.08
*-Estimated
PILE LOAD TEST AND RESULTS
Four piles. two from each size, were selected to perform the
static pile load test. All the test piles and anchor piles are
contract piles. The maintained load test was performed in two
cycles for each pile with the first cycle having maximum test
load of safe design working load. The maximum test load for
second cycle was 150 % of the design safe working load. The
maximum test load for these botl1 cycles were maintained for
24 hours.
The third cycle was performed as a quick test and each
incremental load was maintained for 10 minutes. The
maximwn test load on tl1is third cycle was 250 % of the safe
design working load. The results were satisfactory and
complying the design requirements (Max. allowed settlement
of l0mm under working load)
Ultimate load interpretation
Predicted ultimate loads were based on graphical methods
proposed by Mazurkiewicz (1972). Fuller and Hoy (1970) and
Butler and Hoy (1977). It may be appropriate to mention here
that ultimate capacity determined from the above mentioned
methods generally not yield a load corresponding to a
"plunging" failure. The ultimate capacity is defined by the
load at which the pile moves rapidly (plunging) without any
further load increment. Most of the existing methods for
detennining the ultimate capacity from pile load test
however. are mostly based on some arbitrary displacement
criteria and there is no consensus on the best method of
interpreting the failure load. Fellenius (1980) pointed out that
preferred method of interpretaion often depend on an
individual's e~-perience and he further recommended that
several methods be applied and that a preferred method be
chosen on the basis of the user's needs and special conditions
ofthe job.
For base grouted piles in Bangkok sub soil, the predicted
failure load based on the above methods well agrees each
other (Teparaksa. 1994). For this particular project the
variation of predicted loads by these different methods are in
the range of 2.5% to 19%. It should be noted that the tests
were not perfonned to failure of piles. As the piles were not
tested for failure it was difficult to compare the results with
actual failure load.
Tah/e :! (iltimate loadpredicted hy different method'i
Max. Ultimate Load (tons)
Test Mazurk Fuller Butler and
Pile Dia. Load -iewicz and Hoy Hoy
No. (mm) (ton) (1972) (1970) (1977)
TP-1 1000 750 1625 1585 1575
TP-2 1000 1250 1700 1480 1460
TP-3 1500 1500 3600 3200 3185
TP-4 1500 2500 3250 2775 2725
(Note: Piles were not tested to failure)
Summary ofpile load test results
Table J (a). (b) and (c ) summarize the pile load test results
and Fig. 5and Fig. 6 show the corresponding load settlement
characteristics.
285
Table 3 (a) CYCLE - I
Cycle l (Maintained Load Test)
Base Max. Head Elastic
Pile Dia. depth Load Movement Recovery
No. (mm) (m) (ton) (mm) (mm)
TP-1 1000 55 500 4.69 4.52
TP-2 1000 55 500 4.66 3.98
TP-3 1500 55.3 1000 4.55 4.47
TP-4 1500 55.5 1000 5.47 5.43
Table 3 {h) CYCLE - 2
Cycle 2 (Maintained Load Test)
Base Max. Head Elastic
Pile Dia. depth Load Movement Recovery
No. (m) (m) (ton) (mm) (mm)
TP-1 1000 55 750 8.55 7.66
TP-2 1000 55 1250 17.40 12.49
TP-3 1500 55.3 1500 7.72 6.59
TP-4 1500 55.5 2500 27.19 16.00
Table 3 (c) CYCLE - 3
Cycle 3 (Quick Test)
Base Max. Head Elastic
Pile Dia. depth Load Movement Recovery
No. (m) (m) (ton) (mm) (mm)
TP-2 1000 55 1250 17.05 12.43
TP-4 1500 55.5 2500 29.26 17.52
Load test results on soft base pilot piles
' ·- ·-- - ··- -·-- ···-- ·-- ·-- - -· ···- - -,
,,,,.nffc,,r..._., I
a ;'!l,t ~:'!C ~"loC 1:)0C'I •J~ ,~ , 1 ~·.u 7r.c):'I l.tv. ;,,~oo :, 1~ I
1· -~-·+--- -+ ------+-- 1---+- - ~ ·- - . _.,._._ !
.: L
:t•• t
... ~
•
j ~-' ~
., t'
;
; :,:t 
L ..·-- - ···- ---·····-- ··-- -·-- ---~
F'ig. 4(a) load test on pilot pile with non base groutedpile
(Diam. 1500mm, Toe embeddment at depth 60m
below ground)
- -- -- ----- .. ·- --·-·-· ·--- ----·-- -- - - - - '
Fig 4 (b) load test on pilot pile with non base grouted pile
(Diam. 1000mm, Toe embeddment at depth 53m
below ground)
Load test results on base grouted contract piles
, -· --- ·· ··-- --·· --- --· - ------ - -···· ----·i
1..0 •n (lo"'-... ) I9 7~ ,c,ov I
~ - .• "''''"".:~::~'~"'" i
":r ~ - -- •· - - ~ ~- ,1 ... , .11.. 0.,1:tont !."'<:,t.!l
~: -:: t --------=:,.
II
" 62">
,:· • 0 [
;;;
L________________ _____ - - -
;
I___,
Fig. 5 (a) (proof) Load test on contract pile ([P- I)
_______Dia. 1000mm, Toe depth 55m below Ground Levet
-- -- -··- - -
Fig. 5 (b) (proof) Load test on contract pile ([P - 2)
,-. __pia. /000"_~"'· Toe depth 55m below Ground~~/
i
LO AU (T o r.g .i :
i:.:'~ -~::,~:.::::~,~~
•~ ,,, f -------- :::----.: .!81~ ~ - -L I
I~"'-"l .. H,• '"" '' ~ I
. I1. ---·- --·- .. -·---- . . --·- ·----· ··-------·· .·--'
Fig 6 (a) (pr<><~/) Load lest on contract pile (Fl' - 3)
IJia. 1500mm, Toe depth 55.3 m below Ground Level
. ··· ·- -·-·,
:•·•O i~~....., ., I
-~-•COCII
ii ] .,J
.::t......., ~-:··,~ ·____
. .... . . . ~ - - - - - - - } -I - • ., , . ... ,o... ._ ,.
l
-~ ... -._ r·---
{ : : ~~ ~-c~
E_~O, ---- -. ------ -___ ___,_,r_" _' '_~~~·-- - -
Fig 6 {h) (pref,~ Load test on contract pile ([P- 3)
Dia. 1500mm, Toe depth 55.5 m below Ground Level
286
INTEGRITY TEST AND SIGNAL INTERPRETATIONS
It was requested to perfonn the integrity test on all the piles
cast. Commonly interpreted defects by the integrity testing
equipment developed by IBBC-TNO are shown in Table 4.
The integrity testing results showed clearly the physical
damages in many piles where the ill considered means were
practiced to cut the piles to trimming level.
Almost all the cracks were indicated on piles adjacent to the
sheet pile cofferdam which was used for deep excavation.
These piles in many cases were repaired by coring and
cement grouted. Physical damages to piles located adjacent to
the excavation boundary were a major source of trouble as the
sheet piles used for temporary retaining purpose cannot
completely retain the soil movement and local soil strains
induced could be sufficient enough to cause cracking.
Possibility of providing more main reinforcement bars for
piles adjacent to the excavation zone to prevent these worse
effects would have been worth to have considered.
Table 4 Interpretations by sonic integrity test
Diam. Diam.
1500 mm 1000mm
nos. % nos. %
Available test results 300 100 59 100
Sectional increase (small) 25 8.3 10 16.9
Sectional increase 04 1.3 02 3.4
(prominent)
Sectional Decrease (small) 04 1.3 - -
Intennittent sectional lO 3.3 04 6.8
variations<•>
Cracks (small) '21
IO 3.3 08 13.6
Cracks (prominent) <
2
> 03 l.O - -
Notes:
I. These variations were attributed lo the sub soil
conditions
2. All the cracks have been fi>und on piles adjacent to the
excavation supported by steel sheet piles
CONCLUSION
A case history of cast in-situ concrete bored piles in Bangkok
sub soil has been summarized. A total of 402 piles of
1000mm (96 nos.) and 1500mm (306 nos.) have been
constmcted as foundation elements of a wastewater treatment
plant.
Base grouting has been considered to improve the bearing
capacity and settlement behavior of bored piles. Maximum
pressure of 40 bars or 500 liter of grout volume has been used
as limiting criteria. Base grouting with ·tube -a manchette·
method has been adopted and found to be effective.
Static pile load test results on contract piles and pilot test
piles have been sum1narized. Pilot piles with base non
grouted. have shown either high degree of settlement or failed
well before the designed maximu1n test load. Ultimate load
capacit)' has been estimated by different methods and
variation of the ultimate capacity found to be within 2.5 to 19
percent.
Pile integrity test was decided to be performed on all piles and
commonly indicated signal characteristics have been
tabulated for available data.
ACKNOWLEDGEMENT
The authors are much thankful for all the staff and e1nployees
of SEAFCO CO.. LTD. especially for Mr. Kamol
Yooyucnpattana and Mr. Chetsadar Plongkrathok.
REFERENCES
Anwar M. A [ 1997]. ..Base grouting to improve the
performance of wet process bored piles in Bangkok sub soils".
AIT Master Thesis. Bangkok. Thailand.
Fleming, W. G. K .. F. Reiding and P. Middendorp. (1985)
..Faults in cast in place piles and tl1eir detection". Proc.
Second Intent. Conf. On Stn1ctural Faults and Repair.. ICE.
Westminister. London. pp. JO l - 310.
Joshi. R. C .. and H. D. Sharn1a [ I 987 J"Prediction of ultimate
pile capacity from load tests on bored and belled. expanded
base compacted and driven piles" Proc. Intern.. Symp. On
Prediction and Performance in Gcotechnical Engineering.
GaJgar)'. pp. 135 - 144.
Ng Kim Cheng [ 1983J. "'The construction problems and
perfomiance of large bored piles in second sand layer". AIT
Master Thesis. Bangkok. Thailand
Teparaksa. W. I 1994)...Newly developed toe-grouted bored
pile in soft Bangkok clay: Performance and Behaviour...
Intern. Conf. On Design and Construction of Deep
Foundations. FHWA. Florida. pp. 1337 - 1351..
Woo Siu Mun and C. H. Juang ( 1994)...Analysis of pile load
test results... Conf. On Deep Foundations and Ground
Improvement Schemes. Bangkok. Thailand.
287

More Related Content

What's hot

A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...
A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...
A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...IRJET Journal
 
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...IJERA Editor
 
Design of pavement on subgrade soil by stabilization
Design of pavement on subgrade soil by stabilizationDesign of pavement on subgrade soil by stabilization
Design of pavement on subgrade soil by stabilizationAmeer Muhammed
 
Soil stablization using coir
Soil stablization using coirSoil stablization using coir
Soil stablization using coirgsharda123
 
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...IEI GSC
 
Parametric Characterization and Model Prediction of CBR Values of Stabilized ...
Parametric Characterization and Model Prediction of CBR Values of Stabilized ...Parametric Characterization and Model Prediction of CBR Values of Stabilized ...
Parametric Characterization and Model Prediction of CBR Values of Stabilized ...IJMER
 
Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...IEI GSC
 
Study of mechanical behaviour of partially replaced cement (2)
Study of mechanical behaviour of partially replaced cement (2)Study of mechanical behaviour of partially replaced cement (2)
Study of mechanical behaviour of partially replaced cement (2)Rajarshi Patty
 
THE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASH
THE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASHTHE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASH
THE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASHEditorIJAERD
 

What's hot (19)

A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...
A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...
A Study on Strength Properties of Concrete Made with Waste Ready-Mix Concrete...
 
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
 
X01226148151
X01226148151X01226148151
X01226148151
 
Design of pavement on subgrade soil by stabilization
Design of pavement on subgrade soil by stabilizationDesign of pavement on subgrade soil by stabilization
Design of pavement on subgrade soil by stabilization
 
GGBS PPT
GGBS PPTGGBS PPT
GGBS PPT
 
Va 2008
Va 2008Va 2008
Va 2008
 
M046047076
M046047076M046047076
M046047076
 
Improving Properties of Black Cotton Soil with Quarry Dust
Improving Properties of Black Cotton Soil with Quarry DustImproving Properties of Black Cotton Soil with Quarry Dust
Improving Properties of Black Cotton Soil with Quarry Dust
 
My Extended Abstract of FYP 2 (UMP)
My Extended Abstract of FYP 2 (UMP)My Extended Abstract of FYP 2 (UMP)
My Extended Abstract of FYP 2 (UMP)
 
A013150107
A013150107A013150107
A013150107
 
Soil stablization using coir
Soil stablization using coirSoil stablization using coir
Soil stablization using coir
 
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
Laboratory Investigation on the Mechanical Behavior of Concrete Containing St...
 
Parametric Characterization and Model Prediction of CBR Values of Stabilized ...
Parametric Characterization and Model Prediction of CBR Values of Stabilized ...Parametric Characterization and Model Prediction of CBR Values of Stabilized ...
Parametric Characterization and Model Prediction of CBR Values of Stabilized ...
 
Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...Evaluation of durability properties of recycled aggregate concrete incorporat...
Evaluation of durability properties of recycled aggregate concrete incorporat...
 
I235459
I235459I235459
I235459
 
Study of mechanical behaviour of partially replaced cement (2)
Study of mechanical behaviour of partially replaced cement (2)Study of mechanical behaviour of partially replaced cement (2)
Study of mechanical behaviour of partially replaced cement (2)
 
Ijciet 06 08_001
Ijciet 06 08_001Ijciet 06 08_001
Ijciet 06 08_001
 
Construction of an ash pond with wrp,
Construction of an ash pond with wrp,Construction of an ash pond with wrp,
Construction of an ash pond with wrp,
 
THE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASH
THE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASHTHE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASH
THE ENGINEERING CHARACTERISTICS OF BLACK COTTON SOIL TREATED WITH CORN STRAW ASH
 

Similar to Design construction and behavior of bored cast in situ concrete

68254fb9-e555-4275-91bd-16e4c9550bdc.pptx
68254fb9-e555-4275-91bd-16e4c9550bdc.pptx68254fb9-e555-4275-91bd-16e4c9550bdc.pptx
68254fb9-e555-4275-91bd-16e4c9550bdc.pptxBenjaminSebastian10
 
Gabion structures ppt
Gabion  structures pptGabion  structures ppt
Gabion structures pptswetass8
 
gabionppt-151104071437-lva1-app6892.pdf
gabionppt-151104071437-lva1-app6892.pdfgabionppt-151104071437-lva1-app6892.pdf
gabionppt-151104071437-lva1-app6892.pdfCscDigitalIndia1
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifaSUNILPRASAD68
 
gwapa-si-babu.pptx
gwapa-si-babu.pptxgwapa-si-babu.pptx
gwapa-si-babu.pptxMarco529318
 
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptxHORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptxSamirsinh Parmar
 
IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...
IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...
IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...IRJET Journal
 
Uplift Capacity of Single Pile Under Vertical Loading in Black Cotton Soil
Uplift Capacity of Single Pile Under Vertical Loading in Black Cotton SoilUplift Capacity of Single Pile Under Vertical Loading in Black Cotton Soil
Uplift Capacity of Single Pile Under Vertical Loading in Black Cotton SoilIRJET Journal
 
Porous Concrete uses and occurrences and
Porous Concrete uses and occurrences  andPorous Concrete uses and occurrences  and
Porous Concrete uses and occurrences andYoungYouTuberNaduu
 
Experimental Study on High Strength Concrete using Industrial Wastes
Experimental Study on High Strength Concrete using Industrial WastesExperimental Study on High Strength Concrete using Industrial Wastes
Experimental Study on High Strength Concrete using Industrial Wastesijtsrd
 
Development of mix design for high strength Concrete with Admixtures
Development of mix design for high strength Concrete with AdmixturesDevelopment of mix design for high strength Concrete with Admixtures
Development of mix design for high strength Concrete with AdmixturesIOSR Journals
 
GI030402-deep-soil-mixing-bala.pdf
GI030402-deep-soil-mixing-bala.pdfGI030402-deep-soil-mixing-bala.pdf
GI030402-deep-soil-mixing-bala.pdfciguti
 
Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...
Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...
Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...IJSRD
 
use of blast furnace slag in road construction.ppt
use of blast furnace slag in road construction.pptuse of blast furnace slag in road construction.ppt
use of blast furnace slag in road construction.pptNagarjunJH
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 

Similar to Design construction and behavior of bored cast in situ concrete (20)

68254fb9-e555-4275-91bd-16e4c9550bdc.pptx
68254fb9-e555-4275-91bd-16e4c9550bdc.pptx68254fb9-e555-4275-91bd-16e4c9550bdc.pptx
68254fb9-e555-4275-91bd-16e4c9550bdc.pptx
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 
Gabion structures ppt
Gabion  structures pptGabion  structures ppt
Gabion structures ppt
 
gabionppt-151104071437-lva1-app6892.pdf
gabionppt-151104071437-lva1-app6892.pdfgabionppt-151104071437-lva1-app6892.pdf
gabionppt-151104071437-lva1-app6892.pdf
 
May17
May17May17
May17
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifa
 
gwapa-si-babu.pptx
gwapa-si-babu.pptxgwapa-si-babu.pptx
gwapa-si-babu.pptx
 
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptxHORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
 
IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...
IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...
IRJET- Experimental Investigation on Partial Replacement of Sand by Quarry Du...
 
Ce 6601 qb
Ce 6601 qbCe 6601 qb
Ce 6601 qb
 
Uplift Capacity of Single Pile Under Vertical Loading in Black Cotton Soil
Uplift Capacity of Single Pile Under Vertical Loading in Black Cotton SoilUplift Capacity of Single Pile Under Vertical Loading in Black Cotton Soil
Uplift Capacity of Single Pile Under Vertical Loading in Black Cotton Soil
 
Porous Concrete uses and occurrences and
Porous Concrete uses and occurrences  andPorous Concrete uses and occurrences  and
Porous Concrete uses and occurrences and
 
Soil nailing
Soil nailingSoil nailing
Soil nailing
 
Experimental Study on High Strength Concrete using Industrial Wastes
Experimental Study on High Strength Concrete using Industrial WastesExperimental Study on High Strength Concrete using Industrial Wastes
Experimental Study on High Strength Concrete using Industrial Wastes
 
Development of mix design for high strength Concrete with Admixtures
Development of mix design for high strength Concrete with AdmixturesDevelopment of mix design for high strength Concrete with Admixtures
Development of mix design for high strength Concrete with Admixtures
 
GI030402-deep-soil-mixing-bala.pdf
GI030402-deep-soil-mixing-bala.pdfGI030402-deep-soil-mixing-bala.pdf
GI030402-deep-soil-mixing-bala.pdf
 
Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...
Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...
Evolution of Properties of Pavers Blocks using Nylon Fiber Fly Ash and Rice H...
 
240790029 1030104-1
240790029 1030104-1240790029 1030104-1
240790029 1030104-1
 
use of blast furnace slag in road construction.ppt
use of blast furnace slag in road construction.pptuse of blast furnace slag in road construction.ppt
use of blast furnace slag in road construction.ppt
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 

Recently uploaded

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Design construction and behavior of bored cast in situ concrete

  • 1. Missouri University of Science and Technology Scholars' Mine International Conference on Case Histories in Geotechnical Engineering (1998) - Fourth International Conference on Case Histories in Geotechnical Engineering Mar 8th - Mar 15th Design, Construction and Behavior of Bored Cast In-situ Concrete Piles in Bangkok Sub Soil Narong Thasnanipan SEAFCO Co., Ltd., Bangkok, Thailand Wanchai Teparaksa Chulalongkorn University, Bangkok, Thailand Aung Win Maung SEAFCO Co., Ltd., Bangkok, Thailand Ganeshan Baskaran SEAFCO Co., Ltd., Bangkok, Thailand Follow this and additional works at: http://scholarsmine.mst.edu/icchge Part of the Geotechnical Engineering Commons This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been accepted for inclusion in International Conference on Case Histories in Geotechnical Engineering by an authorized administrator of Scholars' Mine. This work is protected by U. S. Copyright Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact scholarsmine@mst.edu. Recommended Citation Thasnanipan, Narong; Teparaksa, Wanchai; Maung, Aung Win; and Baskaran, Ganeshan, "Design, Construction and Behavior of Bored Cast In-situ Concrete Piles in Bangkok Sub Soil" (1998). International Conference on Case Histories in Geotechnical Engineering. 45. http://scholarsmine.mst.edu/icchge/4icchge/4icchge-session01/45
  • 2. 281 I Proceedings: Fourth International Conference on Case Histories in Geotechnical Engineering, SL Louis, Missouri, March 9-12, 1998. - . DESIGN, CONSTRUCTION AND BEHAVIOUR OF BORED CAST IN-SITU CONCRETE PILES IN BANGKOK SUB SOIL Narong Thasnanipan Seafco Co.. Ltd. Bangkok 10320 Thailand ABSTRACT Wanchai Teparaksa Aung Win Maung Civil Engineering Dept. Seafco Co., Ltd. Chulalongkorn University Bangkok 10320 Bangkok 10330 Thailand Thailand Ganeshan Baskaran Seafco Co.. Ltd. Bangkok 10320 Thailand Paper No.1.20 This paper briefs design considerations. construction metl1ods and materials. static load test results and pile integrity test results of the cast in-situ bored piles constructed as foundation elements for awastewater treatment plant. The treatment plant is located in Bangkok. capital ofthe Kingdom ofThailand and is to serve about 195,000 inhabitants ofthe city. Atotal of402 piles. 296 nos. of 1500 mm diameter and 96 nos. of 1000 mm diameter, were designed to carry the whole structural load of the treatment plant. Maximum working load on individual piles was designed to be l000 tons and 500 tons for 1500 mm and l000 mm diameter pile respectively with asafety factor of2.5. Initially tl1e pile toe depth was designed to be 60mbelow the ground level, and embedded into hard clay for 1500 mm diameter piles while the smaller diameter pile embedded into second sand layer at adepth of53m and base was not decided to be grouted. Pile load test results on fully instrumental pilot piles showed tl1e failure well before reaching the designed test load. Piles were re-designed and pile toe depth was set to be 55m, embedded into dense sand layer for both sizes and base grouting was decided to be done for all piles. Proof load test results performed on four working piles(contract piles), two for each size. produced well acceptable results confonning to the design and structural specifications and requirements. However, settlements observed were higher tl1an that observed for other projects in the vicinity. Base Grouting was done using tube -a manchette method. Amaximum volume of500 liter ofcement grout (w/c ratio,., 0.5) or maximum grouting pressure of40 bars was usedas limiting criteria. However, maximum pressure of40 barswas hardly acltleved. From the proofload test results ultimate load capacity was estimated and compared using different methods suggested by previous researchers. Integrity test was decided to be perfonned on each pile and results available currently are summarized. KEYWORDS BoredPiles. Base Grouting, Static Pile LoadTest Integrity Tesi Pile Capacity
  • 3. site, if an extra bearing capacity of 250 t/m::! could be achieved by base grouting. the grouted piles would be capable of carrying the designed safe working loads with adequate safety factor. Based on the results from a project just near by the site and past e:xl)Criences in the vicinity it was proposed that the above mentioned required capacity could be achieved by base grouting the piles with tip founded at about 55 m from the ground. The option of extending the pile length was given up as the clay layer is found to be at about depth of 60 m and thus possibly higher initial settlement was expected if the piles are embedded into the clay layer. Moreover, the end bearing capacity would be reduced and this reduced end bearing capacity might influence the shaft bearing capacity too. This conclusion was reinforced by the previous pile load test results on a pilot pile. founded at 60m and non base grouted. This non grouted and longer pile of diameter 1500 mm, constructed by some other piling contractor, failed at about 1750 tons. while the designed maximum test load was 2500 tons. The I000mm diameter pilot pile was. though not plunged to failure. settlement observed was too excessive for the structural requirements. Load settlement characteristics of these pilot test piles have been shown in Fig. 4(a) and Fig. 4(b). Finally the previous piling contractor was disqualified and the new contractor was called upon. CONSTRUCTION METHODS. MATERIALS AND PROBLEMS Wet process The usual wet process using the bentonite slurry was adopted. Tempornry casing of length 15m was used to maintain the hole stability in top soft layer. The holes were drilled using augers and then continued using the bucket method. The slurry was introduced upon reaching the first sand layer and maintained all the time higher enough to support the bore. The slurry was monitored continuously for the properties of density. viscosity. pH and sand content. Construction of bored piles started during the rainy season and therefore the site needed additional requirements to improve the working condition. As the water level was high in the Chaophrnya river flood protection was needed. Because of the nature of the Bangkok sub soil and the project site was previously used as urban waste dun1ping area. the site was very swampy during the rainy season gave a lot of inconveniences in solving problems for drainage of water accumulated. TI1e situation was further aggravated as the excavated soil was not able to be removed on time. All these reduced the productivity rate drastically. However. all the piles were cast within the time frame set according to the contract. 282 Slurry properties The limiting values for the bentonite slurry according to the contract specification were 1.04 - 1.20 for density; 30-40s for viscosity (Marsh's cone); not less than 7 for pH and not more than 3% for sand content. On average 3.5 % of bentonite concentration was used. Bentonite properties were monitored before concreting for all piles. Arbitrary checking was done during drilling. From the bentonite results. no significant changes were observed. On average. the viscosity observed was 32.8s (Marsh cone); with 1naximum of 40s and a minimwn of 29s. The average values of I.Ilg/cc. 8.9, 1.62% were noted for density, pH and sand content respectively. The minimum values are l.02g/cc, 7, 0.1% and maximum values are 1.1 lg/cc, 9 and 1.55 respectively. Eventhough. the sand content was set to be within 3%, at times it was difficult to achieve this. In this cases complete recycling of the slurry was done. Concreting and Reinforcement Concrete cube strength of 350 ksc (35 Mpa) was used with minimum cement content of 400 kg/m3 . Concreting was done by usual tremie method of 250mm tremie pipe. Concreting was requested to be done witl1 in twenty four hours after final excavation. Since a concrete batching plant was established within the project area. concrete supply was usually regular and timely supplied otl1erwise it would have been a major concern in Bangkok because of its ill fated traffic congestion. Average concreting rate was about 25 - 30 cu.m per hour. After pouring the concrete to the desired level, the temporary casing was witl1drawn. Reinforcement was provided to full length of the pile considering the possible tensile forces during construction period of the structure. Maximum of 0.5% of cross sectional area was used for both sizes ofthe piles. All the main bars used for reinforcement are of high strength defonned bars of 4000 ksc (400 Mpa) and round bars of 2400 ksc (240 MPa) were used for spirals. Reinforcement was provided by fabricating in the form of cages as usual and the maximum len1:,»th of a cage was set to be 12 m. A minimum lap length of forty times the diameter of tl1e bars was used at the joints of tl1e cages. Inclusions in pile top and concrete level below trimming level Few cases were observed where tl1e concrete level was below the designed cut off level and/or inclusions in pile top portion. Mainly, this has been contributed by the high un- predicted slumping down of concrete upon extracting the temporary casing. As Fleming et al. (1985) pointed out concrete would nonnally be retained by cohesive soils with shear strength in
  • 4. INTRODUCTION The city of Bangkok has been emerged as one of heavily populated urban cities in the world. Due to its rapid economic growth. the construction industry has been challenged to develop the infrastructure to cope with the booming economy. As a result. while multi storied private owned buildings become most attractive sky scrapers in this city of Angels. huge portion of the Government budget is swallowed by new projects involving construction of highways and railways. both elevated and at-grade. sub ways. large span bridges and water and wastewater treatment facilities. Construction industry is further challenged by tl1e city's subsoil condition as it is plagued with a lot of constraints such as. presence of thick soft clay as top strata, land subsidence and high risk of flooding. These constraints compel most structures be relied on pile foundation usually. on large diameter bored cast in- situ piles. embedded into first or second sand layers. Though. the first large bored pile was installed nearly two decades ago in this city and hundreds of thousands of piles have already been constructed. design. construction methods, perfonnances and effectiveness of these piles are seldom studied and rarely reported. The project site is located at the Rama III road. with east boundary along the Chao Phraya river which is the largest of its kind in the kingdom. The piles are usually of 1500mm and 1000 mm diameters. The maximum design working load on piles are 500 tons and I000 tons for l000 mm and 1500 mm piles respectively. Pile toe was designed to be embedded into second sand layer at depth 55m from the ground level. Fig. I shows the general layout of the piles. All the piles are cast in situ bored piles under wet process and base grouted. Fig. I General lay-out ofboredpiles SUBSOIL CONDITIONS The gcotechinical investigation at the site indicates tl1at a strata of 14 - I5m thick soft clay layer occurs in the project 283 area as common in Bangkok sub soil. This soft clay is sensitive and has an-isotropic and time dependent stress strain properties. Below is stiff to very stiff clay layer underlain by hard clay layers. These clay layers extend down to about 42m in depth. However, the subsoil condition below 36m from the ground level in the project area is variable - a sand layer with a thickness of about 13m is present sporadically. In some locations within the project site. a stiff to hard dark gray clay is also found at the depth between 40m and 49m. Generally a thick dense sand layer is located below 50m from the existing ground level. However, at this area alternated layers of dense sand and hard clay of 5m thick also was encountered. Fig. 2 shows the general bore log data observed at the site. ----·--- - - - - .,~...... IOC 110 0 t---j'--+-t-· - - , ---1 -~·-·•••u.-··.. -· I 'b_, i -· '- ' -"° ! - j a~ ... j u "'. 6 a -• 0 D • ' 00 .__L ,- j 11: ....1..§: .........._._...__-NCMft Data from 3 bore holes within the project site ~ - - - ---- ..... _ - - - - - - - - - - - - ~ Fig 2 Soil profile at the project site PILE CAPACITY AND DESIGN CONSIDERATIONS I The load capacity of the piles were estimated for the soil failure using tl1e available soil data. Safety Factor of 2.5 was used for both end bearing and shaft bearing capacities considering the negative skin friction as well. The estimated safe working load in tons. using individual three bore hole data are 480, 508 and 583 for IOOO mm piles and 839, 880 and 993 for 1500 mm piles. The estimated load capacity. with required safety factor, from the soil bore log results is, in many cases, below the designed safe working load. Hence, means of improving pile bearing capacity was considered. The pile bearing capacity can be improved either by extending the pile length further or by grouting the pile or by enlarging the pile base. Usually, enlarging the base for long piles is hardly practiced in Bangkok. Piling contractors rather prefer to extend the length of the shaft and additional required capacity is achieved by the shaft friction. For the bored piles designed at this project
  • 5. excess of 15 kN/m:: and this limit is rarely achieved by the top soft clay of Bangkok sub soil. Final sound concrete level has been a talking point between the main contractor and piling contractor for both cases where the final concrete level is above and below the designed trim level. Usually for the first case the main contractor suffered to trim the long pile heads but in the latter cases the piling contractor was called upon for remedial works. However. it should not be neglected that tl1e possibility of failure to over flush enough concrete at the pile head to ensure that all concrete present below the trim level is of full strength and thus having the inclusions at the pile top. Verticality and Position Errors Verticality tolerance was set to be l in 100 and no piles have been found to be out of this tolerance. However, four piles (about 1% of the total) have been found to be out of position deviating the specified tolerance of 7.5cm plus the allowance for verticality. However. many of them were found to be under the mat on which the columns were to be erected. Hence. dealing with these erroneous locations was not dramatic and modification of reinforcement for the mat have been done according to the redistributed load. GROUTING The effectiveness of base grouted piles in Bangkok sub soil was studied by many previous researches. Teparaksa (1994) suggests base grouting mainly aims to increase soil stiffness beneath the pile base which was affected by the boring process. Also he noted that for these piles the displacement at fully mobilized skin friction is in the order of l.59 to l.86 percent of the diameter. Test results in this project too agrees the range suggested. The PE pipes (OS') and tube-a manchette were in-corporated into the reinforcement cages and lowered into the bore to facilitate the base grouting. The grouting was done after the concrete is set. usually the base was cracked using a high water pressure not later than twenty four hours. and grout was injected. ,-··- - -- . .. ----·-- I I. 0,;.·· NAJllc:JlnTI: r--1 NETAL Tlllt ..• •. 1/ ~· ill :::::.ID 1/r n TU•t:: •• 11r --I N<TAL TUii£ ID 1/r 11"':.:1:::-~,_....,..,, Fig.3 Tube a manchette used.for grouting 284 The grouting process was controlled by either maximum grout volume of 500 litters or a maximum pressure of 40 bars. But. the pressure of 40 bars was rarely achieved and thus usually the grout volume was the limiting factor. Usually the grouting pressure was within the range of 20 - 30 bars. Injection rate of grout was lO- 15 liters/ min. Experiments on grout samples collected from three of the bored piles (1500mm dia.) in this site was performed by Anwar (1997). Comparison of base grouted and soft base (non base grouted) piles were studied and summarized in Table 1. It was recommended that low injection rate about 1-2 liters/min would improve the effectiveness of base grouting. However, practicality and sustainability of grout pump, especially for large volume of grout, can hardly justify this requirement. Though the direct comparison of effect of base grouting is not possible as the compared piles are founded in different soil strata other parameters in Table l are worth enough to be noted. Table 1 load distribution and settlement behavior of base grouted and soft base piles. Base Soft Grouted Base Diameter(mm) 1500 1500 Base Depth (m) 55 60 Design Load Qd (ton) 1000 1000 Failure Load (ton) 2725 * 1750 Load at 20mm total settlement (Qd 2290 1520 % increase in Or. 50.66 Portion ofQL carried by shaft (Qs) 1720 1450 % increase in Qs 18.6 Portion ofQL carried by base (Oi,1 570 70 % increase in 0., 714 Total settlement at (Qd) (mm) 5 8.13 Total settlement at 1.5 Qd (mm) 7.5 15.08 *-Estimated PILE LOAD TEST AND RESULTS Four piles. two from each size, were selected to perform the static pile load test. All the test piles and anchor piles are contract piles. The maintained load test was performed in two cycles for each pile with the first cycle having maximum test load of safe design working load. The maximum test load for second cycle was 150 % of the design safe working load. The maximum test load for these botl1 cycles were maintained for 24 hours. The third cycle was performed as a quick test and each incremental load was maintained for 10 minutes. The maximwn test load on tl1is third cycle was 250 % of the safe design working load. The results were satisfactory and
  • 6. complying the design requirements (Max. allowed settlement of l0mm under working load) Ultimate load interpretation Predicted ultimate loads were based on graphical methods proposed by Mazurkiewicz (1972). Fuller and Hoy (1970) and Butler and Hoy (1977). It may be appropriate to mention here that ultimate capacity determined from the above mentioned methods generally not yield a load corresponding to a "plunging" failure. The ultimate capacity is defined by the load at which the pile moves rapidly (plunging) without any further load increment. Most of the existing methods for detennining the ultimate capacity from pile load test however. are mostly based on some arbitrary displacement criteria and there is no consensus on the best method of interpreting the failure load. Fellenius (1980) pointed out that preferred method of interpretaion often depend on an individual's e~-perience and he further recommended that several methods be applied and that a preferred method be chosen on the basis of the user's needs and special conditions ofthe job. For base grouted piles in Bangkok sub soil, the predicted failure load based on the above methods well agrees each other (Teparaksa. 1994). For this particular project the variation of predicted loads by these different methods are in the range of 2.5% to 19%. It should be noted that the tests were not perfonned to failure of piles. As the piles were not tested for failure it was difficult to compare the results with actual failure load. Tah/e :! (iltimate loadpredicted hy different method'i Max. Ultimate Load (tons) Test Mazurk Fuller Butler and Pile Dia. Load -iewicz and Hoy Hoy No. (mm) (ton) (1972) (1970) (1977) TP-1 1000 750 1625 1585 1575 TP-2 1000 1250 1700 1480 1460 TP-3 1500 1500 3600 3200 3185 TP-4 1500 2500 3250 2775 2725 (Note: Piles were not tested to failure) Summary ofpile load test results Table J (a). (b) and (c ) summarize the pile load test results and Fig. 5and Fig. 6 show the corresponding load settlement characteristics. 285 Table 3 (a) CYCLE - I Cycle l (Maintained Load Test) Base Max. Head Elastic Pile Dia. depth Load Movement Recovery No. (mm) (m) (ton) (mm) (mm) TP-1 1000 55 500 4.69 4.52 TP-2 1000 55 500 4.66 3.98 TP-3 1500 55.3 1000 4.55 4.47 TP-4 1500 55.5 1000 5.47 5.43 Table 3 {h) CYCLE - 2 Cycle 2 (Maintained Load Test) Base Max. Head Elastic Pile Dia. depth Load Movement Recovery No. (m) (m) (ton) (mm) (mm) TP-1 1000 55 750 8.55 7.66 TP-2 1000 55 1250 17.40 12.49 TP-3 1500 55.3 1500 7.72 6.59 TP-4 1500 55.5 2500 27.19 16.00 Table 3 (c) CYCLE - 3 Cycle 3 (Quick Test) Base Max. Head Elastic Pile Dia. depth Load Movement Recovery No. (m) (m) (ton) (mm) (mm) TP-2 1000 55 1250 17.05 12.43 TP-4 1500 55.5 2500 29.26 17.52 Load test results on soft base pilot piles ' ·- ·-- - ··- -·-- ···-- ·-- ·-- - -· ···- - -, ,,,,.nffc,,r..._., I a ;'!l,t ~:'!C ~"loC 1:)0C'I •J~ ,~ , 1 ~·.u 7r.c):'I l.tv. ;,,~oo :, 1~ I 1· -~-·+--- -+ ------+-- 1---+- - ~ ·- - . _.,._._ ! .: L :t•• t ... ~ • j ~-' ~ ., t' ; ; :,:t L ..·-- - ···- ---·····-- ··-- -·-- ---~ F'ig. 4(a) load test on pilot pile with non base groutedpile (Diam. 1500mm, Toe embeddment at depth 60m below ground)
  • 7. - -- -- ----- .. ·- --·-·-· ·--- ----·-- -- - - - - ' Fig 4 (b) load test on pilot pile with non base grouted pile (Diam. 1000mm, Toe embeddment at depth 53m below ground) Load test results on base grouted contract piles , -· --- ·· ··-- --·· --- --· - ------ - -···· ----·i 1..0 •n (lo"'-... ) I9 7~ ,c,ov I ~ - .• "''''"".:~::~'~"'" i ":r ~ - -- •· - - ~ ~- ,1 ... , .11.. 0.,1:tont !."'<:,t.!l ~: -:: t --------=:,. II " 62"> ,:· • 0 [ ;;; L________________ _____ - - - ; I___, Fig. 5 (a) (proof) Load test on contract pile ([P- I) _______Dia. 1000mm, Toe depth 55m below Ground Levet -- -- -··- - - Fig. 5 (b) (proof) Load test on contract pile ([P - 2) ,-. __pia. /000"_~"'· Toe depth 55m below Ground~~/ i LO AU (T o r.g .i : i:.:'~ -~::,~:.::::~,~~ •~ ,,, f -------- :::----.: .!81~ ~ - -L I I~"'-"l .. H,• '"" '' ~ I . I1. ---·- --·- .. -·---- . . --·- ·----· ··-------·· .·--' Fig 6 (a) (pr<><~/) Load lest on contract pile (Fl' - 3) IJia. 1500mm, Toe depth 55.3 m below Ground Level . ··· ·- -·-·, :•·•O i~~....., ., I -~-•COCII ii ] .,J .::t......., ~-:··,~ ·____ . .... . . . ~ - - - - - - - } -I - • ., , . ... ,o... ._ ,. l -~ ... -._ r·--- { : : ~~ ~-c~ E_~O, ---- -. ------ -___ ___,_,r_" _' '_~~~·-- - - Fig 6 {h) (pref,~ Load test on contract pile ([P- 3) Dia. 1500mm, Toe depth 55.5 m below Ground Level 286 INTEGRITY TEST AND SIGNAL INTERPRETATIONS It was requested to perfonn the integrity test on all the piles cast. Commonly interpreted defects by the integrity testing equipment developed by IBBC-TNO are shown in Table 4. The integrity testing results showed clearly the physical damages in many piles where the ill considered means were practiced to cut the piles to trimming level. Almost all the cracks were indicated on piles adjacent to the sheet pile cofferdam which was used for deep excavation. These piles in many cases were repaired by coring and cement grouted. Physical damages to piles located adjacent to the excavation boundary were a major source of trouble as the sheet piles used for temporary retaining purpose cannot completely retain the soil movement and local soil strains induced could be sufficient enough to cause cracking. Possibility of providing more main reinforcement bars for piles adjacent to the excavation zone to prevent these worse effects would have been worth to have considered. Table 4 Interpretations by sonic integrity test Diam. Diam. 1500 mm 1000mm nos. % nos. % Available test results 300 100 59 100 Sectional increase (small) 25 8.3 10 16.9 Sectional increase 04 1.3 02 3.4 (prominent) Sectional Decrease (small) 04 1.3 - - Intennittent sectional lO 3.3 04 6.8 variations<•> Cracks (small) '21 IO 3.3 08 13.6 Cracks (prominent) < 2 > 03 l.O - - Notes: I. These variations were attributed lo the sub soil conditions 2. All the cracks have been fi>und on piles adjacent to the excavation supported by steel sheet piles CONCLUSION A case history of cast in-situ concrete bored piles in Bangkok sub soil has been summarized. A total of 402 piles of 1000mm (96 nos.) and 1500mm (306 nos.) have been constmcted as foundation elements of a wastewater treatment plant. Base grouting has been considered to improve the bearing capacity and settlement behavior of bored piles. Maximum pressure of 40 bars or 500 liter of grout volume has been used
  • 8. as limiting criteria. Base grouting with ·tube -a manchette· method has been adopted and found to be effective. Static pile load test results on contract piles and pilot test piles have been sum1narized. Pilot piles with base non grouted. have shown either high degree of settlement or failed well before the designed maximu1n test load. Ultimate load capacit)' has been estimated by different methods and variation of the ultimate capacity found to be within 2.5 to 19 percent. Pile integrity test was decided to be performed on all piles and commonly indicated signal characteristics have been tabulated for available data. ACKNOWLEDGEMENT The authors are much thankful for all the staff and e1nployees of SEAFCO CO.. LTD. especially for Mr. Kamol Yooyucnpattana and Mr. Chetsadar Plongkrathok. REFERENCES Anwar M. A [ 1997]. ..Base grouting to improve the performance of wet process bored piles in Bangkok sub soils". AIT Master Thesis. Bangkok. Thailand. Fleming, W. G. K .. F. Reiding and P. Middendorp. (1985) ..Faults in cast in place piles and tl1eir detection". Proc. Second Intent. Conf. On Stn1ctural Faults and Repair.. ICE. Westminister. London. pp. JO l - 310. Joshi. R. C .. and H. D. Sharn1a [ I 987 J"Prediction of ultimate pile capacity from load tests on bored and belled. expanded base compacted and driven piles" Proc. Intern.. Symp. On Prediction and Performance in Gcotechnical Engineering. GaJgar)'. pp. 135 - 144. Ng Kim Cheng [ 1983J. "'The construction problems and perfomiance of large bored piles in second sand layer". AIT Master Thesis. Bangkok. Thailand Teparaksa. W. I 1994)...Newly developed toe-grouted bored pile in soft Bangkok clay: Performance and Behaviour... Intern. Conf. On Design and Construction of Deep Foundations. FHWA. Florida. pp. 1337 - 1351.. Woo Siu Mun and C. H. Juang ( 1994)...Analysis of pile load test results... Conf. On Deep Foundations and Ground Improvement Schemes. Bangkok. Thailand. 287