SlideShare a Scribd company logo
Lecture (3 )
Prepared by :
Assc. Prof Nasser El-Shafey
2016- 2017
When loose, saturated sands, silts, or gravel shaken, the
material consolidates, reducing the porosity and increasing
pore water pressure. The ground settles, often unevenly,
tilting and toppling structures that were formerly supported
by the soil
Liquefaction can cause problems as soil loses it’s ability to
resist shear and flows much like quick sand. Anything
relying on the substrata for support can shift, tilt, rupture, or
collapse.
1-Liquefaction
Damage of Structure As A Result Of Soil Problems
Liquefaction-
caused building
failure in Niigata,
Japan.
Liquefaction-
caused building
failure in Niigata,
Japan
Liquefaction
Adapazari, Turkey
1999
1995 Kobe, Japan earthquake,
increase pore pressure pushed
quay wall bridge near the west
end toward the river, allowing
the soil and western-most pier
to move one meter Eastward.
2- Landslides
 When a steeply inclined mass of soil is Suddenly shaken,
a slip-plane can form, and the material slides downhill.
 During a landslide, structures sitting on the slide move
downward and structures below the slide are hit by falling
debris.
 In 1970 an earthquake off coast of Peru produced a
landslide began 80 miles away from earthquake.
The slide was large (estimated it's height at about
30 meters), killing more than 18,000 people.
Gravity retaining wall pushed
outward by landslide
One of about 75 homes
damaged as a result of the
Turnagain Heights slide.
Collapse of Tsu Wei Bridge
due to landslide during the
Ji Ji, Taiwan earthquake.
Slope instability –
Niigata, Japan 2004
IMPORTANCE OF GROUND CONDITIONS
Local soil conditions, particularly deep layers of soft soil as may
be found in river valleys or near estuaries, significantly amplify
shaking. They also modify the frequency content of seismic waves
by filtering out higher frequency excitations
DAMAGE AS A RESULT OF STRUCTURAL PROBLEMS
Engineers will occasionally design foundations to rock during
earthquakes as a way of dissipating energy and of reducing
the demand on the structure; however, when the foundation
is too small, it can become unstable and rock over
1. Foundation Failure
Large longitudinal
displacements of
bridge span causing
damage to abutment
2. Foundation Connections
Structures need to be well anchored to foundation.
The longitudinal reinforcement did not have sufficient
development length to transfer the force to the footing
Soft Story
Soft Story
Soft First Story is
a discontinuity of
strength and
stiffness for
lateral load at the
ground level.
3. Soft Story
Soft Storey at Ground Floor
Soft story (stiffening structural elements which are present
in the upper stories are missing at the ground floor)
1) Building Plan
2) Heavy mass at top should be avoided
Smaller water tank at top is preferred
NO YES
3) Large projections not allowed 4) Floating column not allowed
Short Column
Short Column
4. Torsional Moments
Curved, skewed, and eccentrically
supported structures often
experience a torsional moment
during earthquakes.
5. Shear
Most building structures use shear walls or moment-resisting
frames to resist lateral forces during earthquakes. Damage to
these systems varies from minor cracks to complete collapse.
M. McKinley-ALASKA
6. Flexural Failure
Flexural members are often designed to form plastic hinges
during large earthquakes. A plastic hinge allows a member to
yield and deform while continuing to support its load; however,
when there is insufficient confinement for reinforced concrete
members a flexural failure will occur instead.
Often, flexural damage
is accompanied by
compression or shear
damage, as the capacity
of the damaged area
has been lowered.
Flexural damage to
columns
Insufficient transverse
reinforcement to
prevent buckling of the
vertical reinforcement
7. Connection Problems
When a bridge superstructure moves off its expansion joint
or when the connections between building columns and
beams fail, the result is too often the COLLAPSE of the
structure.
Special structural systems
 1-Rigid frames
 2-Shear walls
 3-Frames and cores
 4- Coupled framed-shear wall systems
 5- Cores-coupled shear wall
6- Tubular systems
7- Perforated tubes.
8- Tube in tube.
 9- Bundle tube.
Structural system Number of floors
Frames 20
Shear walls 35
Frames & shear walls 50
Cores-coupled shear walls 55
Perforated tube 60
Tube in tube 65
Bundle tube 90
The response spectrum is a convenient method for illustrating
and quantifying how natural period of vibration and damping
of a building affects its response to earthquake shaking.
SEISMIC FORCES
Natural period of vibration of building has huge effect on maximum horizontal
acceleration, and magnitude. Buildings with T=0.2 to 0.7 seconds are amplifying
ground acc. by almost a factor of 3.0. As natural periods become longer, from 0.7
to 1.7 seconds, peak accelerations reduce towards the same intensity as the peak
ground acceleration. Beyond 1.7 seconds, maximum accelerations continue to
diminish until at T=4.0 seconds building acceleration is only 0.3 of the maximum
ground acceleration.
Earthquake effects on buildings depend on:
Mass of structure Stiffness of structure
Ductility of structures Foundation type
Soil conditions Earthquake zone
1.Symmetry: The structure is almost symmetrical in plan along
two orthogonal directions regarding the lateral stiffness and
mass distribution.
2.Recesses: shall not exceed 5% of the floor area.
3.Aspect Ratio: Lx / Ly <4.0.
4.Torsional regularity: eccentricity between C.M. & C.R.
< 15% Li for each direction (Li=Lx &Ly for x & y directions).
Plan Regularity
Quasi static analysis: Regular buildings; H <100 m & H/B <5.
Response Spectra: Regular buildings; H=100-150 m or H/B >5.
Dynamic analysis: Irregular buildings or H>150m.
Earthquake methods of Analysis
Elevation Regularity
All lateral force resisting elements such as cores,
shear walls or frames should be continuous from
foundation up to the last floor or setback or recess
level.
Stiffness and mass regularity: Difference between
two successive floors does not exceed 75% for Lateral
stiffness and 50% for mass.
Capacity Continuity: ratio between actual to
required resistance of columns in framed structures
should sustain for successive floor. The masonry
walls effect should be considered as such.
Vertical geometric regularity.
Simplified Modal Response
Spectrum Method

More Related Content

What's hot

Study of lateral load resisting systems of variable heights in all soil types...
Study of lateral load resisting systems of variable heights in all soil types...Study of lateral load resisting systems of variable heights in all soil types...
Study of lateral load resisting systems of variable heights in all soil types...
eSAT Publishing House
 
Science Project
Science ProjectScience Project
Science Project
TabelTop
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
Shivananda Roy
 
Load analysis and structural consideration
Load analysis and structural considerationLoad analysis and structural consideration
Load analysis and structural consideration
Hajee Mohammad Danesh Science & Technology University, Dinajpur
 
Structural System Overview
Structural System OverviewStructural System Overview
Structural System OverviewAmjed Bin-Ali
 
Analysis of continuous prestressed concrete
Analysis of continuous prestressed concreteAnalysis of continuous prestressed concrete
Analysis of continuous prestressed concrete
SRAVANTHI mehar
 
Footing design
Footing designFooting design
Footing designYasin J
 
PPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESPPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACES
srinivas cnu
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Hossam Shafiq II
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
mbrsalman
 
ANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACING
ANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACINGANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACING
ANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACING
ijiert bestjournal
 
An Overview On Box Girder Bridges
An Overview On Box Girder BridgesAn Overview On Box Girder Bridges
An Overview On Box Girder Bridges
IRJET Journal
 
Shear wall and its design guidelines
Shear wall and its design guidelinesShear wall and its design guidelines
Shear wall and its design guidelines
Muhammad Zain Ul abdin
 
seismic behaviour of beam column joint
seismic behaviour of beam column jointseismic behaviour of beam column joint
seismic behaviour of beam column joint
saurabh gehlod
 
Virtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsVirtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsAndrew J Horton
 
Introduction on Theory of Structures
Introduction on Theory of StructuresIntroduction on Theory of Structures
Introduction on Theory of Structuresandyoreta
 
Design and analysis of cantilever beam
Design and analysis of cantilever beamDesign and analysis of cantilever beam
Design and analysis of cantilever beam
College
 
Civil Engineering basics
Civil Engineering basicsCivil Engineering basics
Civil Engineering basics
Yasir Hashmi
 
Stress ribbon bridge
Stress ribbon bridgeStress ribbon bridge
Stress ribbon bridge
Bishnu prasad
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)
Shekh Muhsen Uddin Ahmed
 

What's hot (20)

Study of lateral load resisting systems of variable heights in all soil types...
Study of lateral load resisting systems of variable heights in all soil types...Study of lateral load resisting systems of variable heights in all soil types...
Study of lateral load resisting systems of variable heights in all soil types...
 
Science Project
Science ProjectScience Project
Science Project
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 
Load analysis and structural consideration
Load analysis and structural considerationLoad analysis and structural consideration
Load analysis and structural consideration
 
Structural System Overview
Structural System OverviewStructural System Overview
Structural System Overview
 
Analysis of continuous prestressed concrete
Analysis of continuous prestressed concreteAnalysis of continuous prestressed concrete
Analysis of continuous prestressed concrete
 
Footing design
Footing designFooting design
Footing design
 
PPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESPPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACES
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
 
ANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACING
ANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACINGANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACING
ANALYSIS OF MOMENT RESISTING FRAME BY KNEE BRACING
 
An Overview On Box Girder Bridges
An Overview On Box Girder BridgesAn Overview On Box Girder Bridges
An Overview On Box Girder Bridges
 
Shear wall and its design guidelines
Shear wall and its design guidelinesShear wall and its design guidelines
Shear wall and its design guidelines
 
seismic behaviour of beam column joint
seismic behaviour of beam column jointseismic behaviour of beam column joint
seismic behaviour of beam column joint
 
Virtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsVirtual Outriggers in Tall Buildings
Virtual Outriggers in Tall Buildings
 
Introduction on Theory of Structures
Introduction on Theory of StructuresIntroduction on Theory of Structures
Introduction on Theory of Structures
 
Design and analysis of cantilever beam
Design and analysis of cantilever beamDesign and analysis of cantilever beam
Design and analysis of cantilever beam
 
Civil Engineering basics
Civil Engineering basicsCivil Engineering basics
Civil Engineering basics
 
Stress ribbon bridge
Stress ribbon bridgeStress ribbon bridge
Stress ribbon bridge
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)
 

Similar to Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engineering هندسة الزلازل & Assc.Prof Nasser El-Shafey)

Tackle earthquake in engineering buildings
Tackle earthquake in engineering buildingsTackle earthquake in engineering buildings
Tackle earthquake in engineering buildings
Aditya Raj Pradhan
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildings
Rithika Ravishankar
 
Earthquake resistant construction
Earthquake resistant constructionEarthquake resistant construction
Earthquake resistant construction
Harsh Jain
 
Earthquake
EarthquakeEarthquake
Earthquake
preeti patil
 
LOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUESLOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUES
SachinKotian10
 
Earthquake engineering : Causes, Analysis and Mitigation.
Earthquake engineering : Causes, Analysis and Mitigation.Earthquake engineering : Causes, Analysis and Mitigation.
Earthquake engineering : Causes, Analysis and Mitigation.
Aman Saxena
 
Earthquake Resistant Design Techniques
Earthquake Resistant Design TechniquesEarthquake Resistant Design Techniques
Earthquake Resistant Design Techniques
Sahil Kaundal
 
Types of foundations.
Types of foundations.Types of foundations.
Types of foundations.
Akhil Bhardwaj
 
Power point presentation on Soil Liquefaction
Power point presentation on Soil LiquefactionPower point presentation on Soil Liquefaction
Power point presentation on Soil Liquefaction
LectureNotesAdmin
 
Low cost earthquake resistant housing
Low cost earthquake resistant housingLow cost earthquake resistant housing
Low cost earthquake resistant housing
B1 Architect
 
scribfree.com_on-earthquake-resistant-structures.pptx
scribfree.com_on-earthquake-resistant-structures.pptxscribfree.com_on-earthquake-resistant-structures.pptx
scribfree.com_on-earthquake-resistant-structures.pptx
aps ratnuchak
 
Building components
Building componentsBuilding components
Building components
PAAVAI ENGINEERING COLLEGE
 
Earthquake and effect in building types precaution
Earthquake and effect in building types precaution Earthquake and effect in building types precaution
Earthquake and effect in building types precaution
Aditya Sanyal
 
Msb4pp a4design07
Msb4pp a4design07Msb4pp a4design07
Msb4pp a4design07
José Fernando Miranda
 
Earthquake-resistant-buildings-Bayan.pptx
Earthquake-resistant-buildings-Bayan.pptxEarthquake-resistant-buildings-Bayan.pptx
Earthquake-resistant-buildings-Bayan.pptx
Maroofimad
 
Soil properties and its importance in construction
Soil properties and its importance in constructionSoil properties and its importance in construction
Soil properties and its importance in construction
Venkatesh Yadav
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakambaJohn Chakamba
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
Andhra University
 

Similar to Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engineering هندسة الزلازل & Assc.Prof Nasser El-Shafey) (20)

Tackle earthquake in engineering buildings
Tackle earthquake in engineering buildingsTackle earthquake in engineering buildings
Tackle earthquake in engineering buildings
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildings
 
Earthquake resistant construction
Earthquake resistant constructionEarthquake resistant construction
Earthquake resistant construction
 
Earthquake
EarthquakeEarthquake
Earthquake
 
LOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUESLOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUES
 
Earthquake engineering : Causes, Analysis and Mitigation.
Earthquake engineering : Causes, Analysis and Mitigation.Earthquake engineering : Causes, Analysis and Mitigation.
Earthquake engineering : Causes, Analysis and Mitigation.
 
Earthquake Resistant Design Techniques
Earthquake Resistant Design TechniquesEarthquake Resistant Design Techniques
Earthquake Resistant Design Techniques
 
Types of foundations.
Types of foundations.Types of foundations.
Types of foundations.
 
pile wall
pile wallpile wall
pile wall
 
Power point presentation on Soil Liquefaction
Power point presentation on Soil LiquefactionPower point presentation on Soil Liquefaction
Power point presentation on Soil Liquefaction
 
Low cost earthquake resistant housing
Low cost earthquake resistant housingLow cost earthquake resistant housing
Low cost earthquake resistant housing
 
scribfree.com_on-earthquake-resistant-structures.pptx
scribfree.com_on-earthquake-resistant-structures.pptxscribfree.com_on-earthquake-resistant-structures.pptx
scribfree.com_on-earthquake-resistant-structures.pptx
 
Tall buildings
Tall buildingsTall buildings
Tall buildings
 
Building components
Building componentsBuilding components
Building components
 
Earthquake and effect in building types precaution
Earthquake and effect in building types precaution Earthquake and effect in building types precaution
Earthquake and effect in building types precaution
 
Msb4pp a4design07
Msb4pp a4design07Msb4pp a4design07
Msb4pp a4design07
 
Earthquake-resistant-buildings-Bayan.pptx
Earthquake-resistant-buildings-Bayan.pptxEarthquake-resistant-buildings-Bayan.pptx
Earthquake-resistant-buildings-Bayan.pptx
 
Soil properties and its importance in construction
Soil properties and its importance in constructionSoil properties and its importance in construction
Soil properties and its importance in construction
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 

More from Hossam Shafiq II

Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaBasics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Hossam Shafiq II
 
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Hossam Shafiq II
 
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Hossam Shafiq II
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Hossam Shafiq II
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Hossam Shafiq II
 
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Hossam Shafiq II
 
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Hossam Shafiq II
 
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Hossam Shafiq II
 
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Hossam Shafiq II
 
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Hossam Shafiq II
 
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Hossam Shafiq II
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Hossam Shafiq II
 
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Hossam Shafiq II
 
Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...
Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...
Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...
Hossam Shafiq II
 
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Hossam Shafiq II
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Hossam Shafiq II
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Hossam Shafiq II
 
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Hossam Shafiq II
 
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Hossam Shafiq II
 
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Hossam Shafiq II
 

More from Hossam Shafiq II (20)

Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaBasics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
 
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
 
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
 
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
 
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
 
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
 
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
 
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
 
Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...
Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...
Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdel...
 
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
 
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
 
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
 
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
 

Recently uploaded

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 

Recently uploaded (20)

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 

Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engineering هندسة الزلازل & Assc.Prof Nasser El-Shafey)

  • 1. Lecture (3 ) Prepared by : Assc. Prof Nasser El-Shafey 2016- 2017
  • 2. When loose, saturated sands, silts, or gravel shaken, the material consolidates, reducing the porosity and increasing pore water pressure. The ground settles, often unevenly, tilting and toppling structures that were formerly supported by the soil Liquefaction can cause problems as soil loses it’s ability to resist shear and flows much like quick sand. Anything relying on the substrata for support can shift, tilt, rupture, or collapse. 1-Liquefaction Damage of Structure As A Result Of Soil Problems
  • 3. Liquefaction- caused building failure in Niigata, Japan. Liquefaction- caused building failure in Niigata, Japan
  • 4. Liquefaction Adapazari, Turkey 1999 1995 Kobe, Japan earthquake, increase pore pressure pushed quay wall bridge near the west end toward the river, allowing the soil and western-most pier to move one meter Eastward.
  • 5. 2- Landslides  When a steeply inclined mass of soil is Suddenly shaken, a slip-plane can form, and the material slides downhill.  During a landslide, structures sitting on the slide move downward and structures below the slide are hit by falling debris.
  • 6.  In 1970 an earthquake off coast of Peru produced a landslide began 80 miles away from earthquake. The slide was large (estimated it's height at about 30 meters), killing more than 18,000 people. Gravity retaining wall pushed outward by landslide One of about 75 homes damaged as a result of the Turnagain Heights slide.
  • 7. Collapse of Tsu Wei Bridge due to landslide during the Ji Ji, Taiwan earthquake. Slope instability – Niigata, Japan 2004
  • 8. IMPORTANCE OF GROUND CONDITIONS Local soil conditions, particularly deep layers of soft soil as may be found in river valleys or near estuaries, significantly amplify shaking. They also modify the frequency content of seismic waves by filtering out higher frequency excitations
  • 9. DAMAGE AS A RESULT OF STRUCTURAL PROBLEMS Engineers will occasionally design foundations to rock during earthquakes as a way of dissipating energy and of reducing the demand on the structure; however, when the foundation is too small, it can become unstable and rock over 1. Foundation Failure Large longitudinal displacements of bridge span causing damage to abutment
  • 10. 2. Foundation Connections Structures need to be well anchored to foundation. The longitudinal reinforcement did not have sufficient development length to transfer the force to the footing
  • 11. Soft Story Soft Story Soft First Story is a discontinuity of strength and stiffness for lateral load at the ground level. 3. Soft Story Soft Storey at Ground Floor
  • 12. Soft story (stiffening structural elements which are present in the upper stories are missing at the ground floor)
  • 13. 1) Building Plan 2) Heavy mass at top should be avoided Smaller water tank at top is preferred NO YES
  • 14. 3) Large projections not allowed 4) Floating column not allowed
  • 17. 4. Torsional Moments Curved, skewed, and eccentrically supported structures often experience a torsional moment during earthquakes.
  • 18. 5. Shear Most building structures use shear walls or moment-resisting frames to resist lateral forces during earthquakes. Damage to these systems varies from minor cracks to complete collapse. M. McKinley-ALASKA
  • 19. 6. Flexural Failure Flexural members are often designed to form plastic hinges during large earthquakes. A plastic hinge allows a member to yield and deform while continuing to support its load; however, when there is insufficient confinement for reinforced concrete members a flexural failure will occur instead. Often, flexural damage is accompanied by compression or shear damage, as the capacity of the damaged area has been lowered.
  • 20. Flexural damage to columns Insufficient transverse reinforcement to prevent buckling of the vertical reinforcement
  • 21. 7. Connection Problems When a bridge superstructure moves off its expansion joint or when the connections between building columns and beams fail, the result is too often the COLLAPSE of the structure.
  • 22. Special structural systems  1-Rigid frames  2-Shear walls  3-Frames and cores  4- Coupled framed-shear wall systems  5- Cores-coupled shear wall 6- Tubular systems 7- Perforated tubes. 8- Tube in tube.  9- Bundle tube. Structural system Number of floors Frames 20 Shear walls 35 Frames & shear walls 50 Cores-coupled shear walls 55 Perforated tube 60 Tube in tube 65 Bundle tube 90
  • 23. The response spectrum is a convenient method for illustrating and quantifying how natural period of vibration and damping of a building affects its response to earthquake shaking. SEISMIC FORCES
  • 24. Natural period of vibration of building has huge effect on maximum horizontal acceleration, and magnitude. Buildings with T=0.2 to 0.7 seconds are amplifying ground acc. by almost a factor of 3.0. As natural periods become longer, from 0.7 to 1.7 seconds, peak accelerations reduce towards the same intensity as the peak ground acceleration. Beyond 1.7 seconds, maximum accelerations continue to diminish until at T=4.0 seconds building acceleration is only 0.3 of the maximum ground acceleration. Earthquake effects on buildings depend on: Mass of structure Stiffness of structure Ductility of structures Foundation type Soil conditions Earthquake zone
  • 25. 1.Symmetry: The structure is almost symmetrical in plan along two orthogonal directions regarding the lateral stiffness and mass distribution. 2.Recesses: shall not exceed 5% of the floor area. 3.Aspect Ratio: Lx / Ly <4.0. 4.Torsional regularity: eccentricity between C.M. & C.R. < 15% Li for each direction (Li=Lx &Ly for x & y directions). Plan Regularity Quasi static analysis: Regular buildings; H <100 m & H/B <5. Response Spectra: Regular buildings; H=100-150 m or H/B >5. Dynamic analysis: Irregular buildings or H>150m. Earthquake methods of Analysis
  • 26. Elevation Regularity All lateral force resisting elements such as cores, shear walls or frames should be continuous from foundation up to the last floor or setback or recess level. Stiffness and mass regularity: Difference between two successive floors does not exceed 75% for Lateral stiffness and 50% for mass. Capacity Continuity: ratio between actual to required resistance of columns in framed structures should sustain for successive floor. The masonry walls effect should be considered as such. Vertical geometric regularity.
  • 27.