SlideShare a Scribd company logo
1 of 15
Download to read offline
Analysis of Continuous Prestressed Concrete
Beams
Chris Burgoyne
March 26, 2005
1 Introduction
This conference is devoted to the development of structural analysis rather than
the strength of materials, but the eļ¬€ective use of prestressed concrete relies on
an appropriate combination of structural analysis techniques with knowledge of
the material behaviour. Design of prestressed concrete structures is usually left
to specialists; the unwary will either make mistakes or spend inordinate time
trying to extract a solution from the various equations.
There are a number of fundamental diļ¬€erences between the behaviour of
prestressed concrete and that of other materials. Structures are not unstressed
when unloaded; the design space of feasible solutions is totally bounded; in
hyperstatic structures, various states of self-stress can be induced by altering
the cable proļ¬le, and all of these factors get inļ¬‚uenced by creep and thermal
eļ¬€ects. How were these problems recognised and how have they been tackled?
Ever since the development of reinforced concrete by Hennebique at the end
of the 19th century (Cusack 1984), it was recognised that steel and concrete
could be more eļ¬€ectively combined if the steel was pretensioned, putting the
concrete into compression. Cracking could be reduced, if not prevented alto-
gether, which would increase stiļ¬€ness and improve durability. Early attempts
all failed because the initial prestress soon vanished, leaving the structure to be-
have as though it was reinforced; good descriptions of these attempts are given
by Leonhardt (1964) and Abeles (1964).
It was Freyssinetā€™s observations of the sagging of the shallow arches on three
bridges that he had just completed in 1927 over the River Allier near Vichy
which led directly to prestressed concrete (Freyssinet 1956). Only the bridge at
Boutiron survived WWII (Fig 1). Hitherto, it had been assumed that concrete
had a Youngā€™s modulus which remained ļ¬xed, but he recognised that the de-
ferred strains due to creep explained why the prestress had been lost in the early
trials. Freyssinet (Fig. 2) also correctly reasoned that high tensile steel had to
be used, so that some prestress would remain after the creep had occurred, and
also that high quality concrete should be used, since this minimised the total
amount of creep. The history of Freyssinetā€™s early prestressed concrete work is
written elsewhere (Grote and Marrey 2000).
1
Figure 1: Boutiron Bridge, Vichy
Figure 2: Eugene Freyssinet
2
At about the same time work was underway on creep at the BRE laboratory
in England ((Glanville 1930) and (1933)). It is debatable which man should be
given credit for the discovery of creep but Freyssinet clearly gets the credit for
successfully using the knowledge to prestress concrete.
There are still problems associated with understanding how prestressed con-
crete works, partly because there is more than one way of thinking about it.
These diļ¬€erent philosophies are to some extent contradictory, and certainly
confusing to the young engineer. It is also reļ¬‚ected, to a certain extent, in the
various codes of practice.
Permissible stress design philosophy sees prestressed concrete as a way of
avoiding cracking by eliminating tensile stresses; the objective is for suļ¬ƒcient
compression to remain after creep losses. Untensioned reinforcement, which
attracts prestress due to creep, is anathema. This philosophy derives directly
from Freyssinetā€™s logic and is primarily a working stress concept.
Ultimate strength philosophy sees prestressing as a way of utilising high ten-
sile steel as reinforcement. High strength steels have high elastic strain capacity,
which could not be utilised when used as reinforcement; if the steel is preten-
sioned, much of that strain capacity is taken out before bonding the steel to the
concrete. Structures designed this way are normally designed to be in compres-
sion everywhere under permanent loads, but allowed to crack under high live
load. The idea derives directly from the work of Dischinger (1936) and his work
on the bridge at Aue in 1939 (SchĀØonberg and Fichter 1939), as well as that of
Finsterwalder (1939). It is primarily an ultimate load concept. The idea of par-
tial prestressing derives from these ideas since the addition of quite signiļ¬cant
amounts of untensioned reinforcement does not alter the logic (Emperger 1939).
The Load-Balancing philosophy, introduced by T.Y. Lin, uses prestressing
to counter the eļ¬€ect of the permanent loads (Lin 1963). The sag of the cables
causes an upward force on the beam, which counteracts the load on the beam.
Clearly, only one load can be balanced, but if this is taken as the total dead
weight, then under that load the beam will perceive only the net axial prestress
and will have no tendency to creep up or down.
These three philosophies all have their champions, and heated debates take
place between them as to which is the most fundamental.
2 Section design
From the outset it was recognised that prestressed concrete has to be checked
at both the working load and the ultimate load. For steel structures, and
those made from reinforced concrete, there is a fairly direct relationship between
the load capacity under an allowable stress design, and that at the ultimate
load under an ultimate strength design. Older codes were based on permissible
stresses at the working load; new codes use moment capacities at the ultimate
load. Diļ¬€erent load factors are used in the two codes, but a structure which
passes one code is likely to be acceptable under the other.
For prestressed concrete, those ideas do not hold, since the structure is highly
3
Figure 3: Load deļ¬‚ection curve
stressed, even when unloaded. A small increase of load can cause some stress
limits to be breached, while a large increase in load might be needed to cross
other limits. The designer has considerable freedom to vary both the working
load and ultimate load capacities independently; both need to be checked.
A designer normally has to check the tensile and compressive stresses, in both
the top and bottom ļ¬bre of the section, for every load case. The critical sections
are normally, but not always, the mid-span and the sections over piers but other
sections may become critical when the cable proļ¬le has to be determined.
The stresses at any position are made up of three components, one of which
normally has a diļ¬€erent sign from the other two; consistency of sign convention
is essential.
If P is the prestressing force and e its eccentricity, A and Z are the area of
the cross-section and its elastic section modulus (top or bottom ļ¬bres), while
M is the applied moment, then
ft ā‰¤
P
A
+
Pe
Z
āˆ’
M
Z
ā‰¤ fc (1)
where ft and fc are the permissible stresses in tension and compression.
Thus, for any combination of P and M, the designer already has four in-
equalities to deal with.
The prestressing force diļ¬€ers over time, due to creep losses, and a designer is
usually faced with at least three combinations of prestressing force and moment;
ā€¢ the applied moment at the time the prestress is ļ¬rst applied, before creep
losses occur,
ā€¢ the maximum applied moment after creep losses, and
ā€¢ the minimum applied moment after creep losses.
Other combinations may be needed in more complex cases. There are at
least twelve inequalities that have to be satisļ¬ed at any cross-section, but since
an I-section can be deļ¬ned by six variables, and two are needed to deļ¬ne the
4
Figure 4: Gustave Magnel
prestress, the problem is over-speciļ¬ed and it is not immediately obvious which
conditions are superļ¬‚uous. In the hands of inexperienced engineers, the design
process can be very long-winded. However, it is possible to separate out the
design of the cross-section from the design of the prestress. By considering
pairs of stress limits on the same ļ¬bre, but for diļ¬€erent load cases, the eļ¬€ects
of the prestress can be eliminated, leaving expressions of the form:-
Z ā‰„
Moment Range
Permissible stress range
(2)
These inequalities, which can be evaluated exhaustively with little diļ¬ƒculty,
allow the minimum size of the cross-section to be determined.
Once a suitable cross-section has been found, the prestress can be designed
using a construction due to Magnel (Fig. 4). The stress limits can all be
rearranged into the form:-
e ā‰„ āˆ’
Z
A
+
1
P
(fZ + M) (3)
By plotting these on a diagram of eccentricity versus the reciprocal of the
prestressing force, a series of bound lines will be formed. Provided the inequal-
ities (2) are satisļ¬ed, these bound lines will always leave a zone showing all
feasible combinations of P and e. The most economical design, using the min-
imum prestress, usually lies on the right hand side of the diagram, where the
design is limited by the permissible tensile stresses.
5
Figure 5: Magnel diagram
Plotting the eccentricity on the vertical axis allows direct comparison with
the cross-section, as shown in Fig. 5. Inequalities (3) make no reference to
the physical dimensions of the structure, but these practical cover limits can be
shown as well.
A good designer knows how changes to the design and the loadings alter
the Magnel diagram. Changing both the maximum and minimum bending
moments, but keeping the range the same, raises and lowers the feasible region.
If the moments become more sagging the feasible region gets lower in the beam.
In general, as spans increase, the dead load moments increase in proportion to
the live load. A stage will be reached where the economic point (A on Fig.
5) moves outside the physical limits of the beam; Guyon (1951a) denoted the
limiting condition as the critical span. Shorter spans will be governed by tensile
stresses in the two extreme ļ¬bres, while longer spans will be governed by the
limiting eccentricity and tensile stresses in the bottom ļ¬bre (assuming sagging
bending). However, it does not take a large increase in moment for point B to
move outside the cover limit, at which point compressive stresses will govern in
the bottom ļ¬bre under maximum moment.
Only when much longer spans are required, and the feasible region moves
as far down as possible, does the structure become governed by compressive
stresses in both ļ¬bres.
3 Continuous beams
The design of statically determinate beams is relatively straightforward; the
engineer can work on the basis of the design of individual cross-sections, as
outlined above. A number of complications arise when the structure is indeter-
minate which means that the designer has to consider, not only a critical section,
6
Figure 6: Luzancy Bridge
but also the behaviour of the beam as a whole. These are due to the interac-
tion of a number of factors, such as Parasitic Moments, Creep, Temperature
eļ¬€ects and Construction Sequence eļ¬€ects. It is the development of these ideas
which forms the core of this paper. The problems of continuity were addressed
at a conference in London (Andrew and Witt 1951). The basic principles, and
nomenclature, were already in use, but to modern eyes concentration on hand
analysis techniques was unusual, and one of the principle concerns seems to have
been the diļ¬ƒculty of estimating losses of prestressing force.
3.1 Secondary Moments
A prestressing cable in a beam causes the structure to deļ¬‚ect. Unlike the
statically determinate beam, where this motion is unrestrained, the movement
causes a redistribution of the support reactions which in turn induces additional
moments. These are often termed Secondary Moments, but they are not always
small, or Parasitic Moments, but they are not always bad. They are normally
denoted by M2.
Freyssinetā€™s bridge across the Marne at Luzancy, started in 1941 but not
completed until 1946, is often thought of as a simply supported beam, but it
was actually built as a two-hinged arch (Harris 1986), with support reactions
adjusted by means of ļ¬‚at jacks and wedges which were later grouted-in (Fig.
6). The same principles were applied in the later and larger beams built over
the same river.
Magnel built the ļ¬rst indeterminate beam bridge at Sclayn, in Belgium (Fig.
7) in 1946. The cables are virtually straight, but he adjusted the deck proļ¬le so
that the cables were close to the soļ¬ƒt near mid-span but above the centroidal
axis at the internal support (Magnel 1951). Even with straight cables the sag-
7
Figure 7: Sclayn Bridge
ging secondary moments are large; about 50% of the hogging moment at the
central support caused by dead and live load.
The nomenclature for dealing with these reactant moments was quickly es-
tablished (Guyon 1951b). The designer needed to distinguish between the actual
location of the cable proļ¬le (es), and its apparent position, known as its line of
thrust (ep). The two proļ¬les diļ¬€er by M2/P. The cable proļ¬le has to ļ¬t within
the section and is subject to cover constraints, but it is the line of thrust which
has to be used in the stress calculations.
A good designer can exploit this freedom, but it is also the cause of problems;
the secondary moments cannot be found until the proļ¬le is known but the cable
cannot be designed until the secondary moments are known. Guyon (1951b)
introduced the concept of the concordant proļ¬le, which is a proļ¬le that causes
no secondary moments; es and ep thus coincide. Any line of thrust is itself a
concordant proļ¬le.
The designer is then faced with a slightly simpler problem; a cable proļ¬le
has to be chosen which not only satisļ¬es the eccentricity limits (3) but is also
concordant. That in itself is not a trivial operation, but is helped by the fact
that the bending moment diagram that results from any load applied to a beam
will itself be a concordant proļ¬le for a cable of constant force. Such loads are
termed notional loads to distinguish them from the real loads on the structure.
Superposition can be used to progressively build-up a set of notional loads whose
bending moment diagram gives the desired concordant proļ¬le. The question of
whether such a proļ¬le can be found will be addressed later.
Inexperienced designers often stop at this stage of the design process, but
they are clearly then not making full advantage of the power of prestressing, and
their structures are often uneconomic. Guyon pointed out that it was possible to
move the cable proļ¬le by means of a linear transformation in such a way that the
line of thrust remains unchanged. Having chosen a suitable concordant proļ¬le
(which remains as the line of thrust), the designer can then alter the proļ¬le by
linear transformations until a suitable cable proļ¬le is achieved. This freedom
8
allows the engineer to choose lines of thrust which lie outside the cross-section.
Experienced designers often claim that they ā€œdo not botherā€ with concordant
proļ¬les; they simply use their judgement to choose a secondary moment that
they expect to obtain in the particular structure they are designing. They can
then use modiļ¬ed forms of the eccentricity equations (3) which allow them to
produce limits on the actual cable proļ¬le directly:-
es ā‰„ āˆ’
Z
A
+
1
P
(fZ + M + M2) (4)
A slightly diļ¬€erent problem now has to be solved; how to ļ¬nd a cable proļ¬le
that not only satisļ¬es the local eccentricity limits but also generates the required
value of M2.
The two methods are, in fact, directly equivalent, since a proļ¬le that satisļ¬es
one set of constraints will automatically satisfy the other.
3.2 Analysis to determine M2
The calculation of the secondary moments M2 or the determination of the line of
thrust ep, which are equivalent, can be done in several ways. The development of
these methods reļ¬‚ects changes elsewhere in analysis techniques, and of course
the adoption of computer techniques. At the 1951 conference, for example,
Guyon proposed the method of nodal points (a variation of the method of ļ¬xed
points) (Guyon 1951b); as with most methods at the time the objective was
to minimise the number of simultaneous equations to be solved. The most
common method in use today is to determine the forces that the cable exerts
on the concrete and then to analyse the beam under those loads. This can
be done at several levels of detail; if the structure is analysed as a beam the
resulting bending moment will be the total eļ¬€ect of the cable (= Pep) and
the reactions will be those that contribute to the secondary moments M2. If a
more detailed method, such as a ļ¬nite element analysis, is used, the distribution
of cables across the width can be determined, as can local eļ¬€ects of the cable
proļ¬le distribution, which can be particularly important with cables which have
signiļ¬cant horizontal curvature.
Alternatively, for continuous beams, use can be made of virtual work to
derive a set of equations from which the secondary moments can be determined
directly in terms of the actual cable proļ¬le (see, for example, (Burgoyne 1988)).
This is not usually much easier than the cable force method, but it does allow
analytical formulations to be developed which can be used to derive further
theories.
3.3 Existence of line of thrust?
Experienced engineers adopt their own strategies for designing complex struc-
tures. Low (1982), for example, showed that there were limits on the minimum
prestressing force that is needed in a continuous beam. One minimum limit
was derived directly from the Magnel diagram, while another considered the
9
range of eccentricities that have to be allowed for between the maximum sag-
ging region at mid-span and the maximum hogging region over the piers. If the
prestressing force is not high enough, the eccentricity range is too large and it
is impossible to ļ¬nd a secondary moment that leaves the cable proļ¬le always
inside the structure.
But Low also showed that there was a third limit on the prestressing force
which had to be satisļ¬ed before a solution could be found, which he called the
ā€œthird equationā€. It was later shown (Burgoyne 1988) that this limit related to
the existence of the line of thrust. If the prestressing force is too low, then a cable
placed anywhere between the upper or lower limits on the cable proļ¬le will give
secondary moments of the same sign. Under these conditions, no concordant
proļ¬le can exist, so the designer will never be able to ļ¬nd a satisfactory solution
without increasing the prestressing force. By satisfying Lowā€™s third limit, the
designer is assured that a valid proļ¬le exists, even if it still has to be found.
3.4 Applicability of plastic theory
Prestressed concrete beams are normally checked for ultimate moment capacity,
but that is not the same thing as saying that plastic theory can be used to design
such beams. Plastic theory can only be used if prestressed concrete structures
have suļ¬ƒcient ductility to allow redistribution of bending moments as hinges
form.
La Grange conducted a study on indeterminate beams and frames, where he
concluded that indeterminate prestressed concrete structures attained a load at
failure which was just below that predicted by full plastic theory (La Grange
1961). The small discrepancy was due to the post-peak softening that occurs in
prestressed concrete structures, so that in order to allow the full set of plastic
hinges to develop, the ļ¬rst hinges undergo some reduction in moment capacity.
However he concluded that the diļ¬€erence was, in practical terms, negligible.
Prestressing steel is much stronger than normal reinforcing steel and does not
exhibit a well-deļ¬ned yield point, so the steel has to have much higher strains
before signiļ¬cant plastic deformation occurs. Some of that strain capacity is
consumed during the act of prestressing but signiļ¬cant elastic curvatures still
have to take place before yielding can occur. This gives a lower limit on the
depth of the neutral axis at failure.
There is a further complication, because higher strength steels are typically
more brittle than reinforcing steels, with strain capacities of the order of 3%.
Thus designers should limit the strains that develop in the steel at the ultimate
load, and a limit which is frequently applied is to limit the additional strain, after
prestressing, to 1%. This limit can be criticised as too low, but it takes account
of the fact that the analysis at the ultimate load uses an average strain along
the tendon, while the strain at crack locations can be higher. This condition
provides an upper limit on the depth of the neutral axis.
The result of these two conditions is that prestressed concrete beams can
only behave plasticly if they satisfy relatively narrow limits on the position of
the neutral axis, which in turn provides narrow limits on the section geometry.
10
Codes of practice normally aim to force designs into this narrow band of accept-
ability, and they only allow redistribution if certain conditions on the neutral
axis position are satisļ¬ed.
3.5 Secondary moments at the ultimate load?
A closely related question for the designer of continuous prestressed concrete is
whether secondary moments should be taken into account when the ultimate
moment is calculated. The question is not trivial; secondary moments can be
of the same order of magnitude as the dead-load bending moments, although
distributed in a diļ¬€erent way.
The logic behind limit-state codes is to check each possible failure mecha-
nism of the structure, such as cracking, vibration or collapse. A proper check
on the ultimate limit-state would therefore require determination of the ļ¬nal
collapse mechanism of the structure. When the ļ¬nal plastic hinge forms the
structure becomes a mechanism, so when the penultimate hinge formed, the
structure must have been statically determinate; secondary moments do not ex-
ist in statically determinate beams. The moment distribution in the beam can
be found purely by equilibrium considerations which will diļ¬€er from the elastic
moments by a certain amount of redistribution.
However, in most cases, ultimate moment capacities are checked on a section-
by-section basis by applying factored values of the elastic load distribution.
Some codes make no mention of secondary moments, but others allow the in-
clusion of M2 in the ultimate load calculation (Mattock 1983). In eļ¬€ect, this
condition ensures that the ļ¬rst plastic hinge forms with a suļ¬ƒcient reserve of
strength; up to this load, the structure has been behaving elastically, so sec-
ondary moments would, indeed, have been present. In a beam with sagging
secondary moments the eļ¬€ect can be to signiļ¬cantly reduce the ultimate mo-
ment capacity that has to be provided over the piers, and to increase the moment
capacity that is required in the span regions.
There have been some laboratory studies of continuous beams where the
support reactions were measured as loads were increased until a collapse mech-
anism developed. The magnitudes of these reactions allowed the presence (or
absence) of the secondary moments to be monitored, and the results showed
that the secondary moments disappeared as the ļ¬nal hinge formed. The plastic
hinges did not form suddenly, but slowly developed through an elasto-plastic
regime (Mattock, Yamazaki, and Kattula 1971).
The existence of secondary moments is an academic question if the structure
is ductile, since the moment distribution, with or without M2, satisļ¬es the Lower
Bound Theorem if the structure is provided with adequate rotation capacity, but
codes do not always allow these eļ¬€ects to be taken into account, or limit the
amount of redistribution that can take place.
11
3.6 Temperature eļ¬€ects
Temperature variations apply to all structures but the eļ¬€ect on prestressed
concrete beams can be more pronounced than in other structures. The tem-
perature proļ¬le through the depth of a beam (Emerson 1973) can be split into
three components for the purposes of calculation (Hambly 1991). The ļ¬rst
causes a longitudinal expansion, which is normally released by the articulation
of the structure; the second causes curvature which leads to deļ¬‚ection in all
beams and reactant moments in continuous beams, while the third causes a set
of self-equilibrating set of stresses across the cross-section.
The reactant moments can be calculated and allowed-for, but it is the self-
equilibrating stresses that cause the main problems for prestressed concrete
beams. These beams normally have high thermal mass which means that daily
temperature variations do not penetrate to the core of the structure. The result
is a very non-uniform temperature distribution across the depth which in turn
leads to signiļ¬cant self-equilibrating stresses. If the core of the structure is
warm, while the surface is cool, such as at night, then quite large tensile stresses
can be developed on the top and bottom surfaces. However, they only penetrate
a very short distance into the concrete and the potential crack width is very
small. It can be very expensive to overcome the tensile stress by changing
the section or the prestress, and they are normally taken into account by the
provision of a mesh of ļ¬ne bars close to the surface.
A larger problem can arise if thermal stresses act as a trigger for more
damaging cracking, such as the release of locked-in heat of hydration eļ¬€ects
which can occur when a thick web is associated with thin slabs.
3.7 Construction sequence eļ¬€ects
Prestressed concrete tends to be used for the longer-span bridge structures,
which often means that they are built sequentially. As a result, the bending
moments at the end of construction diļ¬€er from those which would be expected
if the bridge had been built in one go (the monolithic moment). As an example,
balanced cantilever construction builds out from a central pier, so the structure
is inevitably in hogging bending throughout. When the tips of two cantilevers
meet they are joined by an in-situ stitch, or sometimes by a short suspended
span that is usually made fully continuous. The cantilever will have prestressing
cables at the top to resist hogging bending, while continuity cables will be
introduced across the joint to resist the sagging bending that will occur later.
The designer has to allow for the temporary condition, and also for the
trapped moments that are induced by the construction sequence. These trapped
moments can be large, and obey the same rules as the secondary moments,
in that they are brought about by a redistribution of the dead-load support
reactions. The designer may deliberately choose to use the continuity cables to
induce a secondary moment that reduces the trapped moment.
Further trapped moments can be induced by the use of temporary prestress-
ing cables which are introduced when the structure is in one conļ¬guration, and
12
then removed later after the support conditions have changed. For example, in
span-by-span construction, where a long viaduct is built one span at a time, it
is sometimes necessary to introduce temporary cables to resist sagging bend-
ing moments that occur during construction but which will be removed later.
Putting a cable into a two-span structure (for example), and then removing it
once the structure is more indeterminate, does not leave a zero stress state;
these eļ¬€ects should not be overlooked.
3.8 Creep eļ¬€ects
The ļ¬nal eļ¬€ect that needs to be considered is, appropriately enough, creep
(Bazant and Wittmann 1982). It was Freyssinetā€™s original observation of creep
that made prestressed concrete possible since he managed to reduce the loss of
force caused by creep. In simply supported beams creep causes some loss of
prestress and increased deļ¬‚ections, which may need to be taken into account,
but it does not alter the distribution of bending moments so the design remains
relatively straightforward.
If the structure is indeterminate there is always the possibility that the
bending moments may be altered by redistribution of the support reactions.
If the structure is built in one piece, all the concrete will be of the same age,
and its eļ¬€ective modulus will change uniformly throughout the structure. No
redistribution of forces is to be expected under these circumstances.
However, if the concrete is of diļ¬€erent ages, the amount of creep that can
occur in the various parts of the structure will vary, which allows redistribution
of moments. It is now well-established that the structure will creep towards
the monolithic state, and the designer can take the as-built condition (includ-
ing trapped moments) and the monolithic state as limiting conditions for the
behaviour of the beam. This simpliļ¬es the design process.
England has studied the eļ¬€ect of temperature variation through the depth
of the beam. Creep is temperature dependent and takes place more quickly on
the warmer side of a structure than on the colder side, which can signiļ¬cantly
alter the load distribution. This work was originally applied to nuclear reactor
containment vessels, where the temperature variation across the thickness can
be of the order of 100ā—¦
C (England, Cheng, and Andrews 1984). The work
makes use of the concept of a steady-state, when creep can continue but without
redistribution of stress. More recently, it has been shown that the much smaller
temperature variations that can be expected through the depth of a bridge deck,
which may be of the order of 5ā—¦
C, can also have a signiļ¬cant eļ¬€ect. The speed
with which creep occurs is very heavily dependent on the relative ages of the
concrete in diļ¬€erent parts of the structure (Xu and Burgoyne 2005).
4 Conclusion
The successful design of continuous prestressed concrete beams cannot be di-
vorced from the techniques used to analyse the structure, and the way these have
13
developed in the 60 years since the ļ¬rst indeterminate structures were built is
a fascinating reļ¬‚ection on the way structural analysis has developed over the
same period.
It remains the case that designers cannot blindly use analysis programs with-
out fundamental understanding of the way prestressed concrete behaves.
Acknowledgements
I am grateful to Robert Benaim for his helpful comments on an earlier draft of
this paper.
Figures 4 and 7; Prof Taerwe, University of Ghent. Figure 6; Jacques Mossot
(www.structurae.de).
References
Abeles, P. W. (1964). An introduction to prestressed concrete. London: Con-
crete Publications.
Andrew, R. P. and P. Witt (Eds.) (1951). Prestressed Concrete Statically
Indeterminate Structures. Cement and Concrete Association.
Bazant, Z. P. and F. H. Wittmann (1982). Creep and shrinkage in concrete
structures. John Wiley.
Burgoyne, C. J. (1988). Cable design for continuous prestressed concrete
bridges. Proc. Inst. Civ. Engrs 85, 161ā€“184.
Cusack, P. (1984). FranĀøcois Hennebique: the specialist organisation and the
success of ferro-concrete: 1892-1909. Trans. Newcomen Soc. 56, 71ā€“86.
Dischinger (1936). German patent no. 535,440.
Emerson, M. (1973). The calculation of the distribution of temperature
in bridges. Technical report, Transport and Road Research Laboratory.
LR561.
Emperger, X. X. (1939). Stahlbeton mit vorgespannten Zulagen aus
hĀØoherwertigem Stahl (Reinforced concrete with additional high strength
steel). Berlin: Ernst & Sohn.
England, G. L., Y. F. Cheng, and K. R. F. Andrews (1984). A temperature-
creep theory for prestressed concrete continuum beam structures. Journ.
Thermal Stresses 7, 361ā€“381.
Finsterwalder, U. (Sept 1939). EisenbetontrĀØager mit selbsttĀØatiger vorspan-
nung (reinforced concrete beams with self-acting prestressing). Der
Bauinginieur.
Freyssinet, E. (1956). Birth of prestressing. Library translation 59, Cement
and Concrete Association. Translated from French. Published by Travaux,
July-August 1954.
14
Glanville, W. H. (1930). Studies in reinforced concrete - III: The creep or
ļ¬‚ow of concrete under load. Building Research Technical Paper 12, Dept
of Scientiļ¬c and Industrial Research, London. 39 pp.
Glanville, W. H. (1933). Creep of concrete under load. The Structural Engi-
neer 11/2, 54ā€“73.
Grote, J. and B. Marrey (2000). Freyssinet, Prestressing and Europe 1930-
1945. Paris: Ā“Editions du Linteau.
Guyon, Y. (1951a). BĀ“eton PrĀ“econtraint. Paris: Editions Eyrolles. Translated
as Prestressed Concrete by Harris A.J. (et al): published London, Con-
tractors Record and Municipal Engineering, 1953.
Guyon, Y. (1951b). A theoretical treatment of continuity in prestressed con-
crete. In R. P. Andrew and P. Witt (Eds.), Prestressed Concrete Statically
Indeterminate Structures, pp. 131ā€“145. Cement and Concrete Association.
Hambly, E. C. (1991). Bridge deck behaviour (2 ed.). London: E & FN Spon.
Harris, A. J. (1986). Luzancy Bridge after 41 years. Concrete Quar-
terly 149/June, 6ā€“7.
La Grange, L. E. (1961). Moment redistribution in prestressed concrete beams
and frames. Ph. D. thesis, University of Cambridge.
Leonhardt, F. (1964). Prestressed Concrete: Design and Construction. Berlin:
Ernst & Sohn.
Lin, T. Y. (1963). Load balancing method for design and analysis of pre-
stressed concrete structures. Journ. Amer. Conc. Inst. 60/6, 719ā€“742.
Low, A. M. (1982). The preliminary design of prestressed concrete viaducts.
Proc. Inst. Civ. Engrs 73, 351ā€“364.
Magnel, G. (1951). Continuity in prestressed concrete. In R. P. Andrew and
P. Witt (Eds.), Prestressed Concrete Statically Indeterminate Structures,
pp. 77ā€“86. Cement and Concrete Association.
Mattock, A. H. (1983). Secondary moments and moment redistribution in ACI
318-77 Code. In M. Z. Cohn (Ed.), Int. Symp. Nonlinearity and Continuity
in Prestressed Concrete, Volume 3, pp. 27ā€“48. University of Waterloo,
Ontario, Canada.
Mattock, A. H., J. Yamazaki, and B. T. Kattula (1971). Comparative study
of prestressed concrete beams, with and without bond. ACI Journal 68,
116ā€“125.
SchĀØonberg, M. and F. Fichter (Feb 1939). Die Adolf-Hitler-BrĀØucke in Aue
(Sa) (The Adolf Hitler Bridge at Aue (Saxony)). Die Bautechnik.
Xu, Q. and C. Burgoyne (2005). Eļ¬€ect of temperature and construction se-
quence on creep of concrete bridges. Proc. Inst. Civ. Engrs, Bridge Engi-
neering (in Press).
15

More Related Content

What's hot

Prestressed construction
Prestressed constructionPrestressed construction
Prestressed constructionVishvendu pandey
Ā 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajat Nainwal
Ā 
Psc notes
Psc notesPsc notes
Psc notesRoy Belton
Ā 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
Ā 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
Ā 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+Est
Ā 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concreteARULPANDIAN8
Ā 
Comparison of reinforced concrete and prestressed concrete
Comparison of reinforced concrete and prestressed concreteComparison of reinforced concrete and prestressed concrete
Comparison of reinforced concrete and prestressed concreteSpice Shuvo
Ā 
Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete Abdulrahman Salah
Ā 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
Ā 
Basic concept of pre-stressing
Basic concept of pre-stressingBasic concept of pre-stressing
Basic concept of pre-stressingManjunathKB11
Ā 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemLatif Hyder Wadho
Ā 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPANfaishalniet
Ā 
Pre stressed concrete construction
Pre stressed concrete constructionPre stressed concrete construction
Pre stressed concrete constructionJenilPatel22
Ā 
Prestressed concrete circular storage tanks
Prestressed concrete circular storage tanksPrestressed concrete circular storage tanks
Prestressed concrete circular storage tanksAman Bagrecha
Ā 
Pre stress concrete
Pre stress concretePre stress concrete
Pre stress concreteSurendra Gurjar
Ā 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteUdisha15
Ā 
Prestress loss
Prestress lossPrestress loss
Prestress lossImran Islam
Ā 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12hlksd
Ā 

What's hot (20)

Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
Ā 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Ā 
Psc notes
Psc notesPsc notes
Psc notes
Ā 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Ā 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
Ā 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+
Ā 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
Ā 
Comparison of reinforced concrete and prestressed concrete
Comparison of reinforced concrete and prestressed concreteComparison of reinforced concrete and prestressed concrete
Comparison of reinforced concrete and prestressed concrete
Ā 
Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete
Ā 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
Ā 
Basic concept of pre-stressing
Basic concept of pre-stressingBasic concept of pre-stressing
Basic concept of pre-stressing
Ā 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing System
Ā 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
Ā 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
Ā 
Pre stressed concrete construction
Pre stressed concrete constructionPre stressed concrete construction
Pre stressed concrete construction
Ā 
Prestressed concrete circular storage tanks
Prestressed concrete circular storage tanksPrestressed concrete circular storage tanks
Prestressed concrete circular storage tanks
Ā 
Pre stress concrete
Pre stress concretePre stress concrete
Pre stress concrete
Ā 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Ā 
Prestress loss
Prestress lossPrestress loss
Prestress loss
Ā 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12
Ā 

Viewers also liked

Final Report (Group 5)
Final Report (Group 5)Final Report (Group 5)
Final Report (Group 5)Lokesh Kumar A M
Ā 
FINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDON
FINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDONFINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDON
FINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDONGirish Singh
Ā 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed ConcreteRavi Savani
Ā 
Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...
Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...
Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...Mid-America Transportation Center
Ā 
Failure investigation of prestressed bridge girder
Failure investigation of prestressed bridge girderFailure investigation of prestressed bridge girder
Failure investigation of prestressed bridge girderAyu Sazrina Sabari
Ā 
Stability analysis of orthotropic reinforce concrete shear wall
Stability analysis of orthotropic reinforce concrete shear wallStability analysis of orthotropic reinforce concrete shear wall
Stability analysis of orthotropic reinforce concrete shear walleSAT Journals
Ā 
Pt group presentation 2013
Pt group presentation 2013Pt group presentation 2013
Pt group presentation 2013Rabee Nassar
Ā 
Sterling PT Pvt. Ltd. (PAKISTAN)
Sterling PT Pvt. Ltd. (PAKISTAN)Sterling PT Pvt. Ltd. (PAKISTAN)
Sterling PT Pvt. Ltd. (PAKISTAN)Aamir Sharif
Ā 
presentation
presentationpresentation
presentationMahi Singh
Ā 
Project Design Report
Project Design ReportProject Design Report
Project Design ReportTaylor Wilson
Ā 
Prestress concrete
Prestress concretePrestress concrete
Prestress concreteDev Sablaniya
Ā 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningAMSYSCO Inc.
Ā 
Design ppt
Design pptDesign ppt
Design ppttishu001
Ā 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
Ā 
Prestresses concrete
Prestresses concrete Prestresses concrete
Prestresses concrete jaiveer singh
Ā 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structuresLuan Truong Van
Ā 
Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog bassamnakfour
Ā 

Viewers also liked (20)

Final Report (Group 5)
Final Report (Group 5)Final Report (Group 5)
Final Report (Group 5)
Ā 
FINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDON
FINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDONFINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDON
FINITE ELEMENT ANALYSIS OF A PRESTRESSED CONCRETE BEAM USING FRP TENDON
Ā 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
Ā 
Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...
Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...
Assessing the Damage Potential in Pretensioned Bridges Caused by Increased Tr...
Ā 
Failure investigation of prestressed bridge girder
Failure investigation of prestressed bridge girderFailure investigation of prestressed bridge girder
Failure investigation of prestressed bridge girder
Ā 
Stability analysis of orthotropic reinforce concrete shear wall
Stability analysis of orthotropic reinforce concrete shear wallStability analysis of orthotropic reinforce concrete shear wall
Stability analysis of orthotropic reinforce concrete shear wall
Ā 
Pt group presentation 2013
Pt group presentation 2013Pt group presentation 2013
Pt group presentation 2013
Ā 
FinalReport
FinalReportFinalReport
FinalReport
Ā 
Sterling PT Pvt. Ltd. (PAKISTAN)
Sterling PT Pvt. Ltd. (PAKISTAN)Sterling PT Pvt. Ltd. (PAKISTAN)
Sterling PT Pvt. Ltd. (PAKISTAN)
Ā 
presentation
presentationpresentation
presentation
Ā 
Project Design Report
Project Design ReportProject Design Report
Project Design Report
Ā 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
Ā 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post Tensioning
Ā 
Design ppt
Design pptDesign ppt
Design ppt
Ā 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
Ā 
Prestresses concrete
Prestresses concrete Prestresses concrete
Prestresses concrete
Ā 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structures
Ā 
Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog
Ā 
Ppt
PptPpt
Ppt
Ā 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Ā 

Similar to Analysis of continuous prestressed concrete

Effect of creep on composite steel concrete section
Effect of creep on composite steel concrete sectionEffect of creep on composite steel concrete section
Effect of creep on composite steel concrete sectionKamel Farid
Ā 
Modelling of Reinforced Concrete Beam-column Joint for Cyclic Earthquake Loa...
Modelling of Reinforced Concrete Beam-column Joint  for Cyclic Earthquake Loa...Modelling of Reinforced Concrete Beam-column Joint  for Cyclic Earthquake Loa...
Modelling of Reinforced Concrete Beam-column Joint for Cyclic Earthquake Loa...Khalid Abdel Naser Abdel Rahim
Ā 
CIVL372-Lecture1.ppt
CIVL372-Lecture1.pptCIVL372-Lecture1.ppt
CIVL372-Lecture1.pptaptccivil
Ā 
okkkkk.ppt
okkkkk.pptokkkkk.ppt
okkkkk.pptBhanuB11
Ā 
CIVL372-Lecture1.ppt
CIVL372-Lecture1.pptCIVL372-Lecture1.ppt
CIVL372-Lecture1.pptashvinparmessur
Ā 
CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...
CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...
CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...IAEME Publication
Ā 
Advanced Plain concrete lecture 1.ppt
Advanced Plain concrete lecture 1.pptAdvanced Plain concrete lecture 1.ppt
Advanced Plain concrete lecture 1.pptAbdulqadeerZardari
Ā 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgeseSAT Journals
Ā 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgeseSAT Journals
Ā 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsFawad Najam
Ā 
CE4410 Final Design Report
CE4410 Final Design ReportCE4410 Final Design Report
CE4410 Final Design ReportChase Bowman
Ā 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfvijayvijay327286
Ā 
A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...
A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...
A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...nhandoan10
Ā 
Pullout test as nondestructive test method in structural engineering
Pullout test as nondestructive test method in structural engineeringPullout test as nondestructive test method in structural engineering
Pullout test as nondestructive test method in structural engineeringMohammed Layth
Ā 
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design NoteAuber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design NoteHoa Nguyen
Ā 
Stress ribbon bridges stiffened by arches or cables
Stress ribbon bridges stiffened by arches or cablesStress ribbon bridges stiffened by arches or cables
Stress ribbon bridges stiffened by arches or cablesMasum Majid
Ā 
prestress Register (1).pdf
prestress Register (1).pdfprestress Register (1).pdf
prestress Register (1).pdfHamzaHussain553342
Ā 
Module 2_spring 2020.pdf
Module 2_spring 2020.pdfModule 2_spring 2020.pdf
Module 2_spring 2020.pdfMohammad Javed
Ā 

Similar to Analysis of continuous prestressed concrete (20)

Effect of creep on composite steel concrete section
Effect of creep on composite steel concrete sectionEffect of creep on composite steel concrete section
Effect of creep on composite steel concrete section
Ā 
Modelling of Reinforced Concrete Beam-column Joint for Cyclic Earthquake Loa...
Modelling of Reinforced Concrete Beam-column Joint  for Cyclic Earthquake Loa...Modelling of Reinforced Concrete Beam-column Joint  for Cyclic Earthquake Loa...
Modelling of Reinforced Concrete Beam-column Joint for Cyclic Earthquake Loa...
Ā 
CIVL372-Lecture1.ppt
CIVL372-Lecture1.pptCIVL372-Lecture1.ppt
CIVL372-Lecture1.ppt
Ā 
okkkkk.ppt
okkkkk.pptokkkkk.ppt
okkkkk.ppt
Ā 
rrc
rrc rrc
rrc
Ā 
CIVL372-Lecture1.ppt
CIVL372-Lecture1.pptCIVL372-Lecture1.ppt
CIVL372-Lecture1.ppt
Ā 
CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...
CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...
CROSS-CORRELATION OF STRESSES IN THE TRAN REINFORCEMENT UNDER SHEAR LOAD AND ...
Ā 
Advanced Plain concrete lecture 1.ppt
Advanced Plain concrete lecture 1.pptAdvanced Plain concrete lecture 1.ppt
Advanced Plain concrete lecture 1.ppt
Ā 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridges
Ā 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridges
Ā 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
Ā 
CE4410 Final Design Report
CE4410 Final Design ReportCE4410 Final Design Report
CE4410 Final Design Report
Ā 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Ā 
A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...
A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...
A THEORETICAL STUDY ON COLLAPSE MECHANISM AND STRUCTURAL BEHAVIOR OF MULTI-ST...
Ā 
Pullout test as nondestructive test method in structural engineering
Pullout test as nondestructive test method in structural engineeringPullout test as nondestructive test method in structural engineering
Pullout test as nondestructive test method in structural engineering
Ā 
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design NoteAuber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Ā 
Stress ribbon bridges stiffened by arches or cables
Stress ribbon bridges stiffened by arches or cablesStress ribbon bridges stiffened by arches or cables
Stress ribbon bridges stiffened by arches or cables
Ā 
2014 cac crs
2014 cac crs2014 cac crs
2014 cac crs
Ā 
prestress Register (1).pdf
prestress Register (1).pdfprestress Register (1).pdf
prestress Register (1).pdf
Ā 
Module 2_spring 2020.pdf
Module 2_spring 2020.pdfModule 2_spring 2020.pdf
Module 2_spring 2020.pdf
Ā 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
Ā 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”soniya singh
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĆ£o Esperancinha
Ā 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
Ā 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
Ā 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
Ā 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Ā 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
Ā 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
Ā 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
Ā 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
Ā 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
Ā 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
Ā 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
Ā 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
Ā 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Ā 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Ā 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
Ā 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
Ā 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
Ā 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Ā 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Ā 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
Ā 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
Ā 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
Ā 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
Ā 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
Ā 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
Ā 

Analysis of continuous prestressed concrete

  • 1. Analysis of Continuous Prestressed Concrete Beams Chris Burgoyne March 26, 2005 1 Introduction This conference is devoted to the development of structural analysis rather than the strength of materials, but the eļ¬€ective use of prestressed concrete relies on an appropriate combination of structural analysis techniques with knowledge of the material behaviour. Design of prestressed concrete structures is usually left to specialists; the unwary will either make mistakes or spend inordinate time trying to extract a solution from the various equations. There are a number of fundamental diļ¬€erences between the behaviour of prestressed concrete and that of other materials. Structures are not unstressed when unloaded; the design space of feasible solutions is totally bounded; in hyperstatic structures, various states of self-stress can be induced by altering the cable proļ¬le, and all of these factors get inļ¬‚uenced by creep and thermal eļ¬€ects. How were these problems recognised and how have they been tackled? Ever since the development of reinforced concrete by Hennebique at the end of the 19th century (Cusack 1984), it was recognised that steel and concrete could be more eļ¬€ectively combined if the steel was pretensioned, putting the concrete into compression. Cracking could be reduced, if not prevented alto- gether, which would increase stiļ¬€ness and improve durability. Early attempts all failed because the initial prestress soon vanished, leaving the structure to be- have as though it was reinforced; good descriptions of these attempts are given by Leonhardt (1964) and Abeles (1964). It was Freyssinetā€™s observations of the sagging of the shallow arches on three bridges that he had just completed in 1927 over the River Allier near Vichy which led directly to prestressed concrete (Freyssinet 1956). Only the bridge at Boutiron survived WWII (Fig 1). Hitherto, it had been assumed that concrete had a Youngā€™s modulus which remained ļ¬xed, but he recognised that the de- ferred strains due to creep explained why the prestress had been lost in the early trials. Freyssinet (Fig. 2) also correctly reasoned that high tensile steel had to be used, so that some prestress would remain after the creep had occurred, and also that high quality concrete should be used, since this minimised the total amount of creep. The history of Freyssinetā€™s early prestressed concrete work is written elsewhere (Grote and Marrey 2000). 1
  • 2. Figure 1: Boutiron Bridge, Vichy Figure 2: Eugene Freyssinet 2
  • 3. At about the same time work was underway on creep at the BRE laboratory in England ((Glanville 1930) and (1933)). It is debatable which man should be given credit for the discovery of creep but Freyssinet clearly gets the credit for successfully using the knowledge to prestress concrete. There are still problems associated with understanding how prestressed con- crete works, partly because there is more than one way of thinking about it. These diļ¬€erent philosophies are to some extent contradictory, and certainly confusing to the young engineer. It is also reļ¬‚ected, to a certain extent, in the various codes of practice. Permissible stress design philosophy sees prestressed concrete as a way of avoiding cracking by eliminating tensile stresses; the objective is for suļ¬ƒcient compression to remain after creep losses. Untensioned reinforcement, which attracts prestress due to creep, is anathema. This philosophy derives directly from Freyssinetā€™s logic and is primarily a working stress concept. Ultimate strength philosophy sees prestressing as a way of utilising high ten- sile steel as reinforcement. High strength steels have high elastic strain capacity, which could not be utilised when used as reinforcement; if the steel is preten- sioned, much of that strain capacity is taken out before bonding the steel to the concrete. Structures designed this way are normally designed to be in compres- sion everywhere under permanent loads, but allowed to crack under high live load. The idea derives directly from the work of Dischinger (1936) and his work on the bridge at Aue in 1939 (SchĀØonberg and Fichter 1939), as well as that of Finsterwalder (1939). It is primarily an ultimate load concept. The idea of par- tial prestressing derives from these ideas since the addition of quite signiļ¬cant amounts of untensioned reinforcement does not alter the logic (Emperger 1939). The Load-Balancing philosophy, introduced by T.Y. Lin, uses prestressing to counter the eļ¬€ect of the permanent loads (Lin 1963). The sag of the cables causes an upward force on the beam, which counteracts the load on the beam. Clearly, only one load can be balanced, but if this is taken as the total dead weight, then under that load the beam will perceive only the net axial prestress and will have no tendency to creep up or down. These three philosophies all have their champions, and heated debates take place between them as to which is the most fundamental. 2 Section design From the outset it was recognised that prestressed concrete has to be checked at both the working load and the ultimate load. For steel structures, and those made from reinforced concrete, there is a fairly direct relationship between the load capacity under an allowable stress design, and that at the ultimate load under an ultimate strength design. Older codes were based on permissible stresses at the working load; new codes use moment capacities at the ultimate load. Diļ¬€erent load factors are used in the two codes, but a structure which passes one code is likely to be acceptable under the other. For prestressed concrete, those ideas do not hold, since the structure is highly 3
  • 4. Figure 3: Load deļ¬‚ection curve stressed, even when unloaded. A small increase of load can cause some stress limits to be breached, while a large increase in load might be needed to cross other limits. The designer has considerable freedom to vary both the working load and ultimate load capacities independently; both need to be checked. A designer normally has to check the tensile and compressive stresses, in both the top and bottom ļ¬bre of the section, for every load case. The critical sections are normally, but not always, the mid-span and the sections over piers but other sections may become critical when the cable proļ¬le has to be determined. The stresses at any position are made up of three components, one of which normally has a diļ¬€erent sign from the other two; consistency of sign convention is essential. If P is the prestressing force and e its eccentricity, A and Z are the area of the cross-section and its elastic section modulus (top or bottom ļ¬bres), while M is the applied moment, then ft ā‰¤ P A + Pe Z āˆ’ M Z ā‰¤ fc (1) where ft and fc are the permissible stresses in tension and compression. Thus, for any combination of P and M, the designer already has four in- equalities to deal with. The prestressing force diļ¬€ers over time, due to creep losses, and a designer is usually faced with at least three combinations of prestressing force and moment; ā€¢ the applied moment at the time the prestress is ļ¬rst applied, before creep losses occur, ā€¢ the maximum applied moment after creep losses, and ā€¢ the minimum applied moment after creep losses. Other combinations may be needed in more complex cases. There are at least twelve inequalities that have to be satisļ¬ed at any cross-section, but since an I-section can be deļ¬ned by six variables, and two are needed to deļ¬ne the 4
  • 5. Figure 4: Gustave Magnel prestress, the problem is over-speciļ¬ed and it is not immediately obvious which conditions are superļ¬‚uous. In the hands of inexperienced engineers, the design process can be very long-winded. However, it is possible to separate out the design of the cross-section from the design of the prestress. By considering pairs of stress limits on the same ļ¬bre, but for diļ¬€erent load cases, the eļ¬€ects of the prestress can be eliminated, leaving expressions of the form:- Z ā‰„ Moment Range Permissible stress range (2) These inequalities, which can be evaluated exhaustively with little diļ¬ƒculty, allow the minimum size of the cross-section to be determined. Once a suitable cross-section has been found, the prestress can be designed using a construction due to Magnel (Fig. 4). The stress limits can all be rearranged into the form:- e ā‰„ āˆ’ Z A + 1 P (fZ + M) (3) By plotting these on a diagram of eccentricity versus the reciprocal of the prestressing force, a series of bound lines will be formed. Provided the inequal- ities (2) are satisļ¬ed, these bound lines will always leave a zone showing all feasible combinations of P and e. The most economical design, using the min- imum prestress, usually lies on the right hand side of the diagram, where the design is limited by the permissible tensile stresses. 5
  • 6. Figure 5: Magnel diagram Plotting the eccentricity on the vertical axis allows direct comparison with the cross-section, as shown in Fig. 5. Inequalities (3) make no reference to the physical dimensions of the structure, but these practical cover limits can be shown as well. A good designer knows how changes to the design and the loadings alter the Magnel diagram. Changing both the maximum and minimum bending moments, but keeping the range the same, raises and lowers the feasible region. If the moments become more sagging the feasible region gets lower in the beam. In general, as spans increase, the dead load moments increase in proportion to the live load. A stage will be reached where the economic point (A on Fig. 5) moves outside the physical limits of the beam; Guyon (1951a) denoted the limiting condition as the critical span. Shorter spans will be governed by tensile stresses in the two extreme ļ¬bres, while longer spans will be governed by the limiting eccentricity and tensile stresses in the bottom ļ¬bre (assuming sagging bending). However, it does not take a large increase in moment for point B to move outside the cover limit, at which point compressive stresses will govern in the bottom ļ¬bre under maximum moment. Only when much longer spans are required, and the feasible region moves as far down as possible, does the structure become governed by compressive stresses in both ļ¬bres. 3 Continuous beams The design of statically determinate beams is relatively straightforward; the engineer can work on the basis of the design of individual cross-sections, as outlined above. A number of complications arise when the structure is indeter- minate which means that the designer has to consider, not only a critical section, 6
  • 7. Figure 6: Luzancy Bridge but also the behaviour of the beam as a whole. These are due to the interac- tion of a number of factors, such as Parasitic Moments, Creep, Temperature eļ¬€ects and Construction Sequence eļ¬€ects. It is the development of these ideas which forms the core of this paper. The problems of continuity were addressed at a conference in London (Andrew and Witt 1951). The basic principles, and nomenclature, were already in use, but to modern eyes concentration on hand analysis techniques was unusual, and one of the principle concerns seems to have been the diļ¬ƒculty of estimating losses of prestressing force. 3.1 Secondary Moments A prestressing cable in a beam causes the structure to deļ¬‚ect. Unlike the statically determinate beam, where this motion is unrestrained, the movement causes a redistribution of the support reactions which in turn induces additional moments. These are often termed Secondary Moments, but they are not always small, or Parasitic Moments, but they are not always bad. They are normally denoted by M2. Freyssinetā€™s bridge across the Marne at Luzancy, started in 1941 but not completed until 1946, is often thought of as a simply supported beam, but it was actually built as a two-hinged arch (Harris 1986), with support reactions adjusted by means of ļ¬‚at jacks and wedges which were later grouted-in (Fig. 6). The same principles were applied in the later and larger beams built over the same river. Magnel built the ļ¬rst indeterminate beam bridge at Sclayn, in Belgium (Fig. 7) in 1946. The cables are virtually straight, but he adjusted the deck proļ¬le so that the cables were close to the soļ¬ƒt near mid-span but above the centroidal axis at the internal support (Magnel 1951). Even with straight cables the sag- 7
  • 8. Figure 7: Sclayn Bridge ging secondary moments are large; about 50% of the hogging moment at the central support caused by dead and live load. The nomenclature for dealing with these reactant moments was quickly es- tablished (Guyon 1951b). The designer needed to distinguish between the actual location of the cable proļ¬le (es), and its apparent position, known as its line of thrust (ep). The two proļ¬les diļ¬€er by M2/P. The cable proļ¬le has to ļ¬t within the section and is subject to cover constraints, but it is the line of thrust which has to be used in the stress calculations. A good designer can exploit this freedom, but it is also the cause of problems; the secondary moments cannot be found until the proļ¬le is known but the cable cannot be designed until the secondary moments are known. Guyon (1951b) introduced the concept of the concordant proļ¬le, which is a proļ¬le that causes no secondary moments; es and ep thus coincide. Any line of thrust is itself a concordant proļ¬le. The designer is then faced with a slightly simpler problem; a cable proļ¬le has to be chosen which not only satisļ¬es the eccentricity limits (3) but is also concordant. That in itself is not a trivial operation, but is helped by the fact that the bending moment diagram that results from any load applied to a beam will itself be a concordant proļ¬le for a cable of constant force. Such loads are termed notional loads to distinguish them from the real loads on the structure. Superposition can be used to progressively build-up a set of notional loads whose bending moment diagram gives the desired concordant proļ¬le. The question of whether such a proļ¬le can be found will be addressed later. Inexperienced designers often stop at this stage of the design process, but they are clearly then not making full advantage of the power of prestressing, and their structures are often uneconomic. Guyon pointed out that it was possible to move the cable proļ¬le by means of a linear transformation in such a way that the line of thrust remains unchanged. Having chosen a suitable concordant proļ¬le (which remains as the line of thrust), the designer can then alter the proļ¬le by linear transformations until a suitable cable proļ¬le is achieved. This freedom 8
  • 9. allows the engineer to choose lines of thrust which lie outside the cross-section. Experienced designers often claim that they ā€œdo not botherā€ with concordant proļ¬les; they simply use their judgement to choose a secondary moment that they expect to obtain in the particular structure they are designing. They can then use modiļ¬ed forms of the eccentricity equations (3) which allow them to produce limits on the actual cable proļ¬le directly:- es ā‰„ āˆ’ Z A + 1 P (fZ + M + M2) (4) A slightly diļ¬€erent problem now has to be solved; how to ļ¬nd a cable proļ¬le that not only satisļ¬es the local eccentricity limits but also generates the required value of M2. The two methods are, in fact, directly equivalent, since a proļ¬le that satisļ¬es one set of constraints will automatically satisfy the other. 3.2 Analysis to determine M2 The calculation of the secondary moments M2 or the determination of the line of thrust ep, which are equivalent, can be done in several ways. The development of these methods reļ¬‚ects changes elsewhere in analysis techniques, and of course the adoption of computer techniques. At the 1951 conference, for example, Guyon proposed the method of nodal points (a variation of the method of ļ¬xed points) (Guyon 1951b); as with most methods at the time the objective was to minimise the number of simultaneous equations to be solved. The most common method in use today is to determine the forces that the cable exerts on the concrete and then to analyse the beam under those loads. This can be done at several levels of detail; if the structure is analysed as a beam the resulting bending moment will be the total eļ¬€ect of the cable (= Pep) and the reactions will be those that contribute to the secondary moments M2. If a more detailed method, such as a ļ¬nite element analysis, is used, the distribution of cables across the width can be determined, as can local eļ¬€ects of the cable proļ¬le distribution, which can be particularly important with cables which have signiļ¬cant horizontal curvature. Alternatively, for continuous beams, use can be made of virtual work to derive a set of equations from which the secondary moments can be determined directly in terms of the actual cable proļ¬le (see, for example, (Burgoyne 1988)). This is not usually much easier than the cable force method, but it does allow analytical formulations to be developed which can be used to derive further theories. 3.3 Existence of line of thrust? Experienced engineers adopt their own strategies for designing complex struc- tures. Low (1982), for example, showed that there were limits on the minimum prestressing force that is needed in a continuous beam. One minimum limit was derived directly from the Magnel diagram, while another considered the 9
  • 10. range of eccentricities that have to be allowed for between the maximum sag- ging region at mid-span and the maximum hogging region over the piers. If the prestressing force is not high enough, the eccentricity range is too large and it is impossible to ļ¬nd a secondary moment that leaves the cable proļ¬le always inside the structure. But Low also showed that there was a third limit on the prestressing force which had to be satisļ¬ed before a solution could be found, which he called the ā€œthird equationā€. It was later shown (Burgoyne 1988) that this limit related to the existence of the line of thrust. If the prestressing force is too low, then a cable placed anywhere between the upper or lower limits on the cable proļ¬le will give secondary moments of the same sign. Under these conditions, no concordant proļ¬le can exist, so the designer will never be able to ļ¬nd a satisfactory solution without increasing the prestressing force. By satisfying Lowā€™s third limit, the designer is assured that a valid proļ¬le exists, even if it still has to be found. 3.4 Applicability of plastic theory Prestressed concrete beams are normally checked for ultimate moment capacity, but that is not the same thing as saying that plastic theory can be used to design such beams. Plastic theory can only be used if prestressed concrete structures have suļ¬ƒcient ductility to allow redistribution of bending moments as hinges form. La Grange conducted a study on indeterminate beams and frames, where he concluded that indeterminate prestressed concrete structures attained a load at failure which was just below that predicted by full plastic theory (La Grange 1961). The small discrepancy was due to the post-peak softening that occurs in prestressed concrete structures, so that in order to allow the full set of plastic hinges to develop, the ļ¬rst hinges undergo some reduction in moment capacity. However he concluded that the diļ¬€erence was, in practical terms, negligible. Prestressing steel is much stronger than normal reinforcing steel and does not exhibit a well-deļ¬ned yield point, so the steel has to have much higher strains before signiļ¬cant plastic deformation occurs. Some of that strain capacity is consumed during the act of prestressing but signiļ¬cant elastic curvatures still have to take place before yielding can occur. This gives a lower limit on the depth of the neutral axis at failure. There is a further complication, because higher strength steels are typically more brittle than reinforcing steels, with strain capacities of the order of 3%. Thus designers should limit the strains that develop in the steel at the ultimate load, and a limit which is frequently applied is to limit the additional strain, after prestressing, to 1%. This limit can be criticised as too low, but it takes account of the fact that the analysis at the ultimate load uses an average strain along the tendon, while the strain at crack locations can be higher. This condition provides an upper limit on the depth of the neutral axis. The result of these two conditions is that prestressed concrete beams can only behave plasticly if they satisfy relatively narrow limits on the position of the neutral axis, which in turn provides narrow limits on the section geometry. 10
  • 11. Codes of practice normally aim to force designs into this narrow band of accept- ability, and they only allow redistribution if certain conditions on the neutral axis position are satisļ¬ed. 3.5 Secondary moments at the ultimate load? A closely related question for the designer of continuous prestressed concrete is whether secondary moments should be taken into account when the ultimate moment is calculated. The question is not trivial; secondary moments can be of the same order of magnitude as the dead-load bending moments, although distributed in a diļ¬€erent way. The logic behind limit-state codes is to check each possible failure mecha- nism of the structure, such as cracking, vibration or collapse. A proper check on the ultimate limit-state would therefore require determination of the ļ¬nal collapse mechanism of the structure. When the ļ¬nal plastic hinge forms the structure becomes a mechanism, so when the penultimate hinge formed, the structure must have been statically determinate; secondary moments do not ex- ist in statically determinate beams. The moment distribution in the beam can be found purely by equilibrium considerations which will diļ¬€er from the elastic moments by a certain amount of redistribution. However, in most cases, ultimate moment capacities are checked on a section- by-section basis by applying factored values of the elastic load distribution. Some codes make no mention of secondary moments, but others allow the in- clusion of M2 in the ultimate load calculation (Mattock 1983). In eļ¬€ect, this condition ensures that the ļ¬rst plastic hinge forms with a suļ¬ƒcient reserve of strength; up to this load, the structure has been behaving elastically, so sec- ondary moments would, indeed, have been present. In a beam with sagging secondary moments the eļ¬€ect can be to signiļ¬cantly reduce the ultimate mo- ment capacity that has to be provided over the piers, and to increase the moment capacity that is required in the span regions. There have been some laboratory studies of continuous beams where the support reactions were measured as loads were increased until a collapse mech- anism developed. The magnitudes of these reactions allowed the presence (or absence) of the secondary moments to be monitored, and the results showed that the secondary moments disappeared as the ļ¬nal hinge formed. The plastic hinges did not form suddenly, but slowly developed through an elasto-plastic regime (Mattock, Yamazaki, and Kattula 1971). The existence of secondary moments is an academic question if the structure is ductile, since the moment distribution, with or without M2, satisļ¬es the Lower Bound Theorem if the structure is provided with adequate rotation capacity, but codes do not always allow these eļ¬€ects to be taken into account, or limit the amount of redistribution that can take place. 11
  • 12. 3.6 Temperature eļ¬€ects Temperature variations apply to all structures but the eļ¬€ect on prestressed concrete beams can be more pronounced than in other structures. The tem- perature proļ¬le through the depth of a beam (Emerson 1973) can be split into three components for the purposes of calculation (Hambly 1991). The ļ¬rst causes a longitudinal expansion, which is normally released by the articulation of the structure; the second causes curvature which leads to deļ¬‚ection in all beams and reactant moments in continuous beams, while the third causes a set of self-equilibrating set of stresses across the cross-section. The reactant moments can be calculated and allowed-for, but it is the self- equilibrating stresses that cause the main problems for prestressed concrete beams. These beams normally have high thermal mass which means that daily temperature variations do not penetrate to the core of the structure. The result is a very non-uniform temperature distribution across the depth which in turn leads to signiļ¬cant self-equilibrating stresses. If the core of the structure is warm, while the surface is cool, such as at night, then quite large tensile stresses can be developed on the top and bottom surfaces. However, they only penetrate a very short distance into the concrete and the potential crack width is very small. It can be very expensive to overcome the tensile stress by changing the section or the prestress, and they are normally taken into account by the provision of a mesh of ļ¬ne bars close to the surface. A larger problem can arise if thermal stresses act as a trigger for more damaging cracking, such as the release of locked-in heat of hydration eļ¬€ects which can occur when a thick web is associated with thin slabs. 3.7 Construction sequence eļ¬€ects Prestressed concrete tends to be used for the longer-span bridge structures, which often means that they are built sequentially. As a result, the bending moments at the end of construction diļ¬€er from those which would be expected if the bridge had been built in one go (the monolithic moment). As an example, balanced cantilever construction builds out from a central pier, so the structure is inevitably in hogging bending throughout. When the tips of two cantilevers meet they are joined by an in-situ stitch, or sometimes by a short suspended span that is usually made fully continuous. The cantilever will have prestressing cables at the top to resist hogging bending, while continuity cables will be introduced across the joint to resist the sagging bending that will occur later. The designer has to allow for the temporary condition, and also for the trapped moments that are induced by the construction sequence. These trapped moments can be large, and obey the same rules as the secondary moments, in that they are brought about by a redistribution of the dead-load support reactions. The designer may deliberately choose to use the continuity cables to induce a secondary moment that reduces the trapped moment. Further trapped moments can be induced by the use of temporary prestress- ing cables which are introduced when the structure is in one conļ¬guration, and 12
  • 13. then removed later after the support conditions have changed. For example, in span-by-span construction, where a long viaduct is built one span at a time, it is sometimes necessary to introduce temporary cables to resist sagging bend- ing moments that occur during construction but which will be removed later. Putting a cable into a two-span structure (for example), and then removing it once the structure is more indeterminate, does not leave a zero stress state; these eļ¬€ects should not be overlooked. 3.8 Creep eļ¬€ects The ļ¬nal eļ¬€ect that needs to be considered is, appropriately enough, creep (Bazant and Wittmann 1982). It was Freyssinetā€™s original observation of creep that made prestressed concrete possible since he managed to reduce the loss of force caused by creep. In simply supported beams creep causes some loss of prestress and increased deļ¬‚ections, which may need to be taken into account, but it does not alter the distribution of bending moments so the design remains relatively straightforward. If the structure is indeterminate there is always the possibility that the bending moments may be altered by redistribution of the support reactions. If the structure is built in one piece, all the concrete will be of the same age, and its eļ¬€ective modulus will change uniformly throughout the structure. No redistribution of forces is to be expected under these circumstances. However, if the concrete is of diļ¬€erent ages, the amount of creep that can occur in the various parts of the structure will vary, which allows redistribution of moments. It is now well-established that the structure will creep towards the monolithic state, and the designer can take the as-built condition (includ- ing trapped moments) and the monolithic state as limiting conditions for the behaviour of the beam. This simpliļ¬es the design process. England has studied the eļ¬€ect of temperature variation through the depth of the beam. Creep is temperature dependent and takes place more quickly on the warmer side of a structure than on the colder side, which can signiļ¬cantly alter the load distribution. This work was originally applied to nuclear reactor containment vessels, where the temperature variation across the thickness can be of the order of 100ā—¦ C (England, Cheng, and Andrews 1984). The work makes use of the concept of a steady-state, when creep can continue but without redistribution of stress. More recently, it has been shown that the much smaller temperature variations that can be expected through the depth of a bridge deck, which may be of the order of 5ā—¦ C, can also have a signiļ¬cant eļ¬€ect. The speed with which creep occurs is very heavily dependent on the relative ages of the concrete in diļ¬€erent parts of the structure (Xu and Burgoyne 2005). 4 Conclusion The successful design of continuous prestressed concrete beams cannot be di- vorced from the techniques used to analyse the structure, and the way these have 13
  • 14. developed in the 60 years since the ļ¬rst indeterminate structures were built is a fascinating reļ¬‚ection on the way structural analysis has developed over the same period. It remains the case that designers cannot blindly use analysis programs with- out fundamental understanding of the way prestressed concrete behaves. Acknowledgements I am grateful to Robert Benaim for his helpful comments on an earlier draft of this paper. Figures 4 and 7; Prof Taerwe, University of Ghent. Figure 6; Jacques Mossot (www.structurae.de). References Abeles, P. W. (1964). An introduction to prestressed concrete. London: Con- crete Publications. Andrew, R. P. and P. Witt (Eds.) (1951). Prestressed Concrete Statically Indeterminate Structures. Cement and Concrete Association. Bazant, Z. P. and F. H. Wittmann (1982). Creep and shrinkage in concrete structures. John Wiley. Burgoyne, C. J. (1988). Cable design for continuous prestressed concrete bridges. Proc. Inst. Civ. Engrs 85, 161ā€“184. Cusack, P. (1984). FranĀøcois Hennebique: the specialist organisation and the success of ferro-concrete: 1892-1909. Trans. Newcomen Soc. 56, 71ā€“86. Dischinger (1936). German patent no. 535,440. Emerson, M. (1973). The calculation of the distribution of temperature in bridges. Technical report, Transport and Road Research Laboratory. LR561. Emperger, X. X. (1939). Stahlbeton mit vorgespannten Zulagen aus hĀØoherwertigem Stahl (Reinforced concrete with additional high strength steel). Berlin: Ernst & Sohn. England, G. L., Y. F. Cheng, and K. R. F. Andrews (1984). A temperature- creep theory for prestressed concrete continuum beam structures. Journ. Thermal Stresses 7, 361ā€“381. Finsterwalder, U. (Sept 1939). EisenbetontrĀØager mit selbsttĀØatiger vorspan- nung (reinforced concrete beams with self-acting prestressing). Der Bauinginieur. Freyssinet, E. (1956). Birth of prestressing. Library translation 59, Cement and Concrete Association. Translated from French. Published by Travaux, July-August 1954. 14
  • 15. Glanville, W. H. (1930). Studies in reinforced concrete - III: The creep or ļ¬‚ow of concrete under load. Building Research Technical Paper 12, Dept of Scientiļ¬c and Industrial Research, London. 39 pp. Glanville, W. H. (1933). Creep of concrete under load. The Structural Engi- neer 11/2, 54ā€“73. Grote, J. and B. Marrey (2000). Freyssinet, Prestressing and Europe 1930- 1945. Paris: Ā“Editions du Linteau. Guyon, Y. (1951a). BĀ“eton PrĀ“econtraint. Paris: Editions Eyrolles. Translated as Prestressed Concrete by Harris A.J. (et al): published London, Con- tractors Record and Municipal Engineering, 1953. Guyon, Y. (1951b). A theoretical treatment of continuity in prestressed con- crete. In R. P. Andrew and P. Witt (Eds.), Prestressed Concrete Statically Indeterminate Structures, pp. 131ā€“145. Cement and Concrete Association. Hambly, E. C. (1991). Bridge deck behaviour (2 ed.). London: E & FN Spon. Harris, A. J. (1986). Luzancy Bridge after 41 years. Concrete Quar- terly 149/June, 6ā€“7. La Grange, L. E. (1961). Moment redistribution in prestressed concrete beams and frames. Ph. D. thesis, University of Cambridge. Leonhardt, F. (1964). Prestressed Concrete: Design and Construction. Berlin: Ernst & Sohn. Lin, T. Y. (1963). Load balancing method for design and analysis of pre- stressed concrete structures. Journ. Amer. Conc. Inst. 60/6, 719ā€“742. Low, A. M. (1982). The preliminary design of prestressed concrete viaducts. Proc. Inst. Civ. Engrs 73, 351ā€“364. Magnel, G. (1951). Continuity in prestressed concrete. In R. P. Andrew and P. Witt (Eds.), Prestressed Concrete Statically Indeterminate Structures, pp. 77ā€“86. Cement and Concrete Association. Mattock, A. H. (1983). Secondary moments and moment redistribution in ACI 318-77 Code. In M. Z. Cohn (Ed.), Int. Symp. Nonlinearity and Continuity in Prestressed Concrete, Volume 3, pp. 27ā€“48. University of Waterloo, Ontario, Canada. Mattock, A. H., J. Yamazaki, and B. T. Kattula (1971). Comparative study of prestressed concrete beams, with and without bond. ACI Journal 68, 116ā€“125. SchĀØonberg, M. and F. Fichter (Feb 1939). Die Adolf-Hitler-BrĀØucke in Aue (Sa) (The Adolf Hitler Bridge at Aue (Saxony)). Die Bautechnik. Xu, Q. and C. Burgoyne (2005). Eļ¬€ect of temperature and construction se- quence on creep of concrete bridges. Proc. Inst. Civ. Engrs, Bridge Engi- neering (in Press). 15