SlideShare a Scribd company logo
1 of 24
Wastewater Engineering
TREATMENT OF SEWAGE
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
1
Classification and Application of
Wastewater Treatment Methods
The individual treatment methods are usually
classified as:
Physical unit operations
Chemical unit processes
Biological unit processes.
The different treatment methods used in
wastewater treatment plant are classified in
three different categories as:
Preliminary Treatment
Primary Treatment
Secondary Treatment
Tertiary Treatment
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
2
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
Physical Unit Operations:
◦ Most of these methods are based on physical forces
◦ Screening, mixing, sedimentation, flotation, and filtration.
Chemical Unit Processes:
◦ Addition of chemicals or by other chemical reaction
◦ Precipitation, gas transfer, adsorption, and disinfection.
Biological Unit Processes:
◦ treatment by biological activity.
◦ Removes biodegradable organic substances from the wastewater, either in colloidal or dissolved form.
◦ Trickling Filters, ASP, Oxidation Ponds, Oxidation Ditches, Aerated Lagoons
screens
Sedimentation tanks
Trickling filters
3
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
Preliminary Treatment:
◦ Separate large floating materials (e.g. Dead Animals, Tree Branches, Papers, Inorganic Materials –
sand, Oil)
◦ BOD removal – 15 – 30 %
◦ Screening, Grit Chambers or Detritus Tanks, Skimming Tanks.
Primary Treatment:
◦ Large Suspended organic solids.
◦ Sedimentation Tanks
Secondary Treatment:
◦ treatment by biological activity (aerobic/anaerobic).
◦ Trickling Filters, ASP, Oxidation Ponds, Oxidation Ditches, Aerated Lagoons
Tertiary Treatment: Chlorination, UV, Ozone
4
TYPICALFLOW SHEET OFA SEWAGE TREATMENT
PLANT
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
5
PRELIMINARY TREATMENT UNITS
Solely separating the floating materials and also the heavy settable organic and inorganic solids.
Removing the oils and grease from the sewage.
Reduces the BOD of the wastewater by about 15 to 30%.
Grit chambers or detritus tanks - remove grit and sand
Skimming tanks - remove oils and grease
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
6
DESIGN OF SCREENS
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
7
SCREENING
Trapping and removal of floating matter
Protection of pumps – by preventing choking
Placed before Grit Chamber
Types of Screens
Coarse Screens
Racks (opening 50 mm or more)
Rags, woods, paper ( burial and
incineration)
Medium Screens
Bar screens - steel bars parallel to each other
20 mm to 50 mm
Some inclined to about 30ᵒ to 60ᵒ to increase
opening area.
Cleaning Mechanical / Manual
Fine screens
06 mm to 20 mm
20% suspended solids from water
Brass or Bronze plates and wire mesh
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
8
DESIGN CONSIDERATIONS FOR
SCREENS
VELOCITY OF FLOW
Low velocity – greater amount of screening
Design velocity should permit 100% removal of solids without settlement
IS 6280 – 1971 ( SPECIFICATIONS FOR DESIGN OF SCREENS)
0.6 to 1.2 m/sec found to be satisfactory
Minimum Approach Velocity – 0.3 m/sec
Materials
Steel Bars of flat rods
Clear Spacing between bars = 15 mm – 75 mm
Minimum Cross section = 10 mm ˟ 50 mm (* Larger dimensions always parallel to the flow)
Maximum screen width = 1.5 m
Angle of inclination = 45ᵒ - 60ᵒ (Manual ); 60ᵒ -90ᵒ (Automatic)
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
9
DESIGN OF SCREENS
1. PEAK SEWAGE FLOW = VELOCITY OF FLOW THROUGH SCREEN Χ NET PROJECTED AREA
2. EFFICIENCY COEFFICENT OF BARS =
𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒
𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒+𝐓𝐇𝐈𝐂𝐊𝐍𝐄𝐒𝐒 𝐎𝐅 𝐓𝐇𝐄 𝐁𝐀𝐑𝐒
3. EFFICIENCY COEFFICENT OF BARS =
𝐍𝐄𝐓 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀
𝐆𝐑𝐎𝐒𝐒 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀
4. NO. OF OPENINGS = NO. OF BARS + 1
5. GROSS WIDTH OF THE BAR = (NO.OF BARS X WIDTH OF BAR) + (NO. OF OPENINGS X WIDTH OF OPENINGS)
6. GROSS AREA = GROSS WIDTH X GROSS DEPTH
7. HEAD LOSS = 0.0729 (V2 – v2 )
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
10
Numerical
Estimate Screen requirement for a plant treating a peak flow of 60 MLD of sewage.
1. Peak Flow = 60 Ml/day =
60,000
24 𝑋 60 𝑋 60
= 0.694 cu-m/sec
2. Assume velocity through the screen as 0.8 m/sec
3. Net Area of the screen = Q/A =
0.694
0.8
= 0.87 m2
4. Efficiency coefficent of bars =
𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒
𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒+𝐓𝐇𝐈𝐂𝐊𝐍𝐄𝐒𝐒 𝐎𝐅 𝐓𝐇𝐄 𝐁𝐀𝐑𝐒
Assume that the rectangular steel abrs have a screen width of 1 cm and are placed with a clear spacing of 5
cm
=
5
5+1
=
5
6
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
11
Numerical
5. Efficiency coefficent of bars =
𝐍𝐄𝐓 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀
𝐆𝐑𝐎𝐒𝐒 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀
5
6
=
0.87
𝐆𝐑𝐎𝐒𝐒 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀
Gross Projected Area = 1.04 m2
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
12
DESIGN OF GRIT CHAMBERS
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
13
DESIGN OF GRIT CHAMBERS
Detritus tanks
 Screens → GRIT → Sedimentation
Removes Inorganic materials – Sand, Silt , Clay e.t.c
Prevents damage of Pumps – due to abrasion
Removes particle size - 0.2 mm
Modifications – Aeration
Types
Horizontal Grit Chambers
Aerated Grit Chambers
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
14
DESIGN OF GRIT CHAMBERS
PEAK SEWAGE FLOW = HORIZONTAL VELOCITY Χ CROSS SECTION AREA
DETENTION PERIOD =
𝐃𝐄𝐏𝐓𝐇 𝐎𝐅 𝐖𝐀𝐓𝐄𝐑 𝐈𝐍 𝐁𝐀𝐒𝐈𝐍
𝐒𝐄𝐓𝐓𝐋𝐈𝐍𝐆 𝐕𝐄𝐋𝐎𝐂𝐈𝐓𝐘
◦ ASSUME SETTLING VELOCITY FOR GRIT CHAMBERS = 0.016 to 0.022 m/sec
◦ DETENTION PERIOD = 1-2 mins.
◦ ASSUME WATER DEPTH = 1 m
*For design purpose 2 units of Grit chambers have to be provided in a Sewage treatment plant.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
15
AERATED GRIT CHAMBERS
Spiral flow aeration tanks
Detention period = 3 mins
Hopper bottom (0.9 m) with steep slopes
Helical or Spiral flow
Air feed rate = 0.15 – 0.45 m3 /min –m ( 0.3
m3 /min –m)
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
16
DETRITUS TANKS
Rectangular chambers ( lesser flow velocity – 0.09 m/sec)
Longer Detention periods – 3 to 4 minutes
Separate fine as well as large Grit materials
Baffle walls and Aeration Systems
Grit is removed by scraper mechanism.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
17
DESIGN OF SEDIMENTATION TANKS
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
18
Sedimentation Tanks
After removal of larger floating and suspended
materials (through screening) and heavier grit
materials (in grit chamber)
Directed to Primary Clarifier (Sedimentation)
for the removal of suspended organics as well as
finer inorganic solids.
Sedimentation is essentially a phase separation
operation for separating liquid and solids.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
19
Types of Settling
TYPE I ‐ Discrete (or Free) settling: The particles settle without interaction
and occurs under low solids concentration. A typical occurrence of this
type of settling is the removal of sand particles.
o TYPE II ‐ Flocculent settling: This is defined as a condition where
particles initially settle independently, but flocculate in the depth of the
clarification unit. The velocity of settling particles are usually increasing as
the particles aggregates. The mechanisms of flocculent settling are not well
understood.
o TYPE III ‐ Hindered (or Zone) settling: Inter‐particle forces are sufficient
to hinder the settling of neighboring particles. The particles tend to remain
in a fixed positions with respect to each others. This type of settling is
typical in the settler for the activated sludge process (secondary clarifier).
o TYPE IV ‐ Compression settling: This occurs when the particle
concentration is so high that so that particles at one level are mechanically
influenced by particles on lower levels. The settling velocity then
drastically reduces.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
20
Sedimentation Basin Zones
Inlet zone:
The inlet or influent zone should provide a smooth transition of water and should distribute the
flow uniformly across the inlet to the tank.
The normal design includes baffles that gently spread the flow across the total inlet of the tank and
prevent short circuiting in the tank.
The baffle could include a wall across the inlet, perforated with holes across the width of the tank.
Settling Zone
The settling zone is the largest portion of the sedimentation basin.
This zone provides the calm area necessary for the suspended particles to settle.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
21
Sedimentation Basin Zones
Sludge zone:
Located at the bottom of the tank, provides a storage area for the sludge before it is removed for additional
treatment or disposal.
High flow velocities near the sludge zone should be minimized.
Sludge is removed for further treatment from the sludge zone by scraper or vacuum devices which move
along the bottom.
Outlet Zone
The basin outlet zone or launder should provide a smooth transition from the sedimentation zone to the
outlet from the tank.
This area of the tank also controls the depth of water in the basin.
Weirs are set at the end of the tank to control the overflow rate and prevent the solids from leaving the
tank before they settle out.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
22
Sedimentation Basin Types
Intermittent and Continuous Types:
o The intermittent tanks, also called quiescent type tanks, are those which store water for a certain
period and keep it in complete rest.
o In a continuous flow type tank, the flow velocity is only reduced and the water is not brought to
complete rest as is done in an intermittent type.
Rectangular or Circular Types:
o Settling basins may be either long rectangular or circular in plan.
o Long narrow rectangular tanks with horizontal flow are generally preferred to the circular tanks
with radial or spiral flow.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
23
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
24

More Related Content

What's hot

L9 -Filtration of Water.pptx
L9 -Filtration of Water.pptxL9 -Filtration of Water.pptx
L9 -Filtration of Water.pptxPRACHI DESSAI
 
L14- Fluoridation & Defluoridation.pptx
L14- Fluoridation & Defluoridation.pptxL14- Fluoridation & Defluoridation.pptx
L14- Fluoridation & Defluoridation.pptxPRACHI DESSAI
 
L7- Sedimentation.pptx
L7- Sedimentation.pptxL7- Sedimentation.pptx
L7- Sedimentation.pptxPRACHI DESSAI
 
L9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptxL9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptxPRACHI DESSAI
 
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptxL11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptxPRACHI DESSAI
 
L5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptxL5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptxPRACHI DESSAI
 
L3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptxL3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptxPRACHI DESSAI
 
L7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptxL7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptxPRACHI DESSAI
 
L6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptxL6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptxPRACHI DESSAI
 
L3 -Intake Structures.ppt
L3 -Intake Structures.pptL3 -Intake Structures.ppt
L3 -Intake Structures.pptPRACHI DESSAI
 
L4- TYPES OF SEWERS.pptx
L4-  TYPES OF SEWERS.pptxL4-  TYPES OF SEWERS.pptx
L4- TYPES OF SEWERS.pptxPRACHI DESSAI
 
L1- INTRODUCTION TO WASTE WATER ENGINEERING.pptx
L1- INTRODUCTION TO WASTE WATER ENGINEERING.pptxL1- INTRODUCTION TO WASTE WATER ENGINEERING.pptx
L1- INTRODUCTION TO WASTE WATER ENGINEERING.pptxPRACHI DESSAI
 
L5 - OSH and Laws.pptx
L5 - OSH and Laws.pptxL5 - OSH and Laws.pptx
L5 - OSH and Laws.pptxPRACHI DESSAI
 
L2 - Sources of water.ppt
L2 - Sources of water.pptL2 - Sources of water.ppt
L2 - Sources of water.pptPRACHI DESSAI
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxPRACHI DESSAI
 
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptxL12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptxPRACHI DESSAI
 
L4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptxL4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptxPRACHI DESSAI
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxPRACHI DESSAI
 
Collection and Distribution of Water: Intakes
Collection and Distribution of Water: IntakesCollection and Distribution of Water: Intakes
Collection and Distribution of Water: IntakesDivine Abaloyan
 
L9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.pptL9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.pptPRACHI DESSAI
 

What's hot (20)

L9 -Filtration of Water.pptx
L9 -Filtration of Water.pptxL9 -Filtration of Water.pptx
L9 -Filtration of Water.pptx
 
L14- Fluoridation & Defluoridation.pptx
L14- Fluoridation & Defluoridation.pptxL14- Fluoridation & Defluoridation.pptx
L14- Fluoridation & Defluoridation.pptx
 
L7- Sedimentation.pptx
L7- Sedimentation.pptxL7- Sedimentation.pptx
L7- Sedimentation.pptx
 
L9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptxL9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptx
 
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptxL11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
 
L5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptxL5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptx
 
L3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptxL3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptx
 
L7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptxL7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptx
 
L6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptxL6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptx
 
L3 -Intake Structures.ppt
L3 -Intake Structures.pptL3 -Intake Structures.ppt
L3 -Intake Structures.ppt
 
L4- TYPES OF SEWERS.pptx
L4-  TYPES OF SEWERS.pptxL4-  TYPES OF SEWERS.pptx
L4- TYPES OF SEWERS.pptx
 
L1- INTRODUCTION TO WASTE WATER ENGINEERING.pptx
L1- INTRODUCTION TO WASTE WATER ENGINEERING.pptxL1- INTRODUCTION TO WASTE WATER ENGINEERING.pptx
L1- INTRODUCTION TO WASTE WATER ENGINEERING.pptx
 
L5 - OSH and Laws.pptx
L5 - OSH and Laws.pptxL5 - OSH and Laws.pptx
L5 - OSH and Laws.pptx
 
L2 - Sources of water.ppt
L2 - Sources of water.pptL2 - Sources of water.ppt
L2 - Sources of water.ppt
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptx
 
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptxL12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
 
L4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptxL4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptx
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptx
 
Collection and Distribution of Water: Intakes
Collection and Distribution of Water: IntakesCollection and Distribution of Water: Intakes
Collection and Distribution of Water: Intakes
 
L9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.pptL9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.ppt
 

Similar to L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx

Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02muhammed ajeeb
 
Wastewater -physical removal methods.pptx
Wastewater -physical removal methods.pptxWastewater -physical removal methods.pptx
Wastewater -physical removal methods.pptxAyisha586983
 
Treatment of water
Treatment of waterTreatment of water
Treatment of waterdhavalsshah
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.pptmadhukarjadhav10
 
SEDIMENTATION
SEDIMENTATIONSEDIMENTATION
SEDIMENTATIONErika Joy
 
WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)
WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)
WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)SHUBHAM PATIDAR FISHERIES ADDAA
 
Land fills and leachate treatment
Land fills and leachate treatmentLand fills and leachate treatment
Land fills and leachate treatmentDeepak Siddavaram
 
UNIT-II-IWM.pptx
UNIT-II-IWM.pptxUNIT-II-IWM.pptx
UNIT-II-IWM.pptxKawinKit
 
L&t waste water-treatment by Ohm-Srinivas
L&t waste water-treatment by Ohm-SrinivasL&t waste water-treatment by Ohm-Srinivas
L&t waste water-treatment by Ohm-SrinivasSrinivas Kalasapati
 
ABC Waters Design Features Handout
ABC Waters Design Features Handout ABC Waters Design Features Handout
ABC Waters Design Features Handout Zhao Chin Tok
 
Breaking down the best practices for the planning and operation of legacy sit...
Breaking down the best practices for the planning and operation of legacy sit...Breaking down the best practices for the planning and operation of legacy sit...
Breaking down the best practices for the planning and operation of legacy sit...Daniel Eyde
 
06 Treatment of water -Filtration and Water Softening
06 Treatment of water -Filtration and Water Softening06 Treatment of water -Filtration and Water Softening
06 Treatment of water -Filtration and Water Softeningakashpadole
 
CE3303 UNIT 2 WATER TREATMENT PPT.pptx
CE3303 UNIT 2 WATER TREATMENT PPT.pptxCE3303 UNIT 2 WATER TREATMENT PPT.pptx
CE3303 UNIT 2 WATER TREATMENT PPT.pptxshiva463860
 

Similar to L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx (20)

Sewage treatment
Sewage treatmentSewage treatment
Sewage treatment
 
Wastewater
WastewaterWastewater
Wastewater
 
Water treatment process
Water treatment processWater treatment process
Water treatment process
 
Unit 4
Unit  4Unit  4
Unit 4
 
Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02
 
Wastewater -physical removal methods.pptx
Wastewater -physical removal methods.pptxWastewater -physical removal methods.pptx
Wastewater -physical removal methods.pptx
 
Etp intro
Etp introEtp intro
Etp intro
 
Treatment of water
Treatment of waterTreatment of water
Treatment of water
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.ppt
 
anu
anuanu
anu
 
SEDIMENTATION
SEDIMENTATIONSEDIMENTATION
SEDIMENTATION
 
WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)
WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)
WASTE WATER AND THEIR TREATMENT (PRIMARY, SECONDARY AND TERTIARY)
 
Land fills and leachate treatment
Land fills and leachate treatmentLand fills and leachate treatment
Land fills and leachate treatment
 
UNIT-II-IWM.pptx
UNIT-II-IWM.pptxUNIT-II-IWM.pptx
UNIT-II-IWM.pptx
 
L&t waste water-treatment by Ohm-Srinivas
L&t waste water-treatment by Ohm-SrinivasL&t waste water-treatment by Ohm-Srinivas
L&t waste water-treatment by Ohm-Srinivas
 
ABC Waters Design Features Handout
ABC Waters Design Features Handout ABC Waters Design Features Handout
ABC Waters Design Features Handout
 
Breaking down the best practices for the planning and operation of legacy sit...
Breaking down the best practices for the planning and operation of legacy sit...Breaking down the best practices for the planning and operation of legacy sit...
Breaking down the best practices for the planning and operation of legacy sit...
 
NUKE PPT.pdf
NUKE PPT.pdfNUKE PPT.pdf
NUKE PPT.pdf
 
06 Treatment of water -Filtration and Water Softening
06 Treatment of water -Filtration and Water Softening06 Treatment of water -Filtration and Water Softening
06 Treatment of water -Filtration and Water Softening
 
CE3303 UNIT 2 WATER TREATMENT PPT.pptx
CE3303 UNIT 2 WATER TREATMENT PPT.pptxCE3303 UNIT 2 WATER TREATMENT PPT.pptx
CE3303 UNIT 2 WATER TREATMENT PPT.pptx
 

More from PRACHI DESSAI

L3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptxL3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptxPRACHI DESSAI
 
L2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptxL2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptxPRACHI DESSAI
 
L1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptxL1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptxPRACHI DESSAI
 
L3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptxL3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptxPRACHI DESSAI
 
2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptx2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptxPRACHI DESSAI
 
1. Introduction to EIA.pptx
1. Introduction to EIA.pptx1. Introduction to EIA.pptx
1. Introduction to EIA.pptxPRACHI DESSAI
 
L10-Chlorination.pptx
L10-Chlorination.pptxL10-Chlorination.pptx
L10-Chlorination.pptxPRACHI DESSAI
 
L8 - Construction Safety.pptx
L8 - Construction Safety.pptxL8 - Construction Safety.pptx
L8 - Construction Safety.pptxPRACHI DESSAI
 
L7 - Emergency Response.ppt
L7 - Emergency Response.pptL7 - Emergency Response.ppt
L7 - Emergency Response.pptPRACHI DESSAI
 
L2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptxL2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptxPRACHI DESSAI
 
L10 - Employee Training.ppt
L10 - Employee Training.pptL10 - Employee Training.ppt
L10 - Employee Training.pptPRACHI DESSAI
 
L4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.pptL4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.pptPRACHI DESSAI
 
L3- Accident investigation.ppt
L3- Accident investigation.pptL3- Accident investigation.ppt
L3- Accident investigation.pptPRACHI DESSAI
 

More from PRACHI DESSAI (13)

L3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptxL3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptx
 
L2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptxL2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptx
 
L1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptxL1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptx
 
L3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptxL3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptx
 
2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptx2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptx
 
1. Introduction to EIA.pptx
1. Introduction to EIA.pptx1. Introduction to EIA.pptx
1. Introduction to EIA.pptx
 
L10-Chlorination.pptx
L10-Chlorination.pptxL10-Chlorination.pptx
L10-Chlorination.pptx
 
L8 - Construction Safety.pptx
L8 - Construction Safety.pptxL8 - Construction Safety.pptx
L8 - Construction Safety.pptx
 
L7 - Emergency Response.ppt
L7 - Emergency Response.pptL7 - Emergency Response.ppt
L7 - Emergency Response.ppt
 
L2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptxL2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptx
 
L10 - Employee Training.ppt
L10 - Employee Training.pptL10 - Employee Training.ppt
L10 - Employee Training.ppt
 
L4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.pptL4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.ppt
 
L3- Accident investigation.ppt
L3- Accident investigation.pptL3- Accident investigation.ppt
L3- Accident investigation.ppt
 

Recently uploaded

Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessorAshwiniTodkar4
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsmeharikiros2
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...ssuserdfc773
 

Recently uploaded (20)

Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 

L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx

  • 1. Wastewater Engineering TREATMENT OF SEWAGE REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 1
  • 2. Classification and Application of Wastewater Treatment Methods The individual treatment methods are usually classified as: Physical unit operations Chemical unit processes Biological unit processes. The different treatment methods used in wastewater treatment plant are classified in three different categories as: Preliminary Treatment Primary Treatment Secondary Treatment Tertiary Treatment REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 2
  • 3. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI Physical Unit Operations: ◦ Most of these methods are based on physical forces ◦ Screening, mixing, sedimentation, flotation, and filtration. Chemical Unit Processes: ◦ Addition of chemicals or by other chemical reaction ◦ Precipitation, gas transfer, adsorption, and disinfection. Biological Unit Processes: ◦ treatment by biological activity. ◦ Removes biodegradable organic substances from the wastewater, either in colloidal or dissolved form. ◦ Trickling Filters, ASP, Oxidation Ponds, Oxidation Ditches, Aerated Lagoons screens Sedimentation tanks Trickling filters 3
  • 4. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI Preliminary Treatment: ◦ Separate large floating materials (e.g. Dead Animals, Tree Branches, Papers, Inorganic Materials – sand, Oil) ◦ BOD removal – 15 – 30 % ◦ Screening, Grit Chambers or Detritus Tanks, Skimming Tanks. Primary Treatment: ◦ Large Suspended organic solids. ◦ Sedimentation Tanks Secondary Treatment: ◦ treatment by biological activity (aerobic/anaerobic). ◦ Trickling Filters, ASP, Oxidation Ponds, Oxidation Ditches, Aerated Lagoons Tertiary Treatment: Chlorination, UV, Ozone 4
  • 5. TYPICALFLOW SHEET OFA SEWAGE TREATMENT PLANT REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 5
  • 6. PRELIMINARY TREATMENT UNITS Solely separating the floating materials and also the heavy settable organic and inorganic solids. Removing the oils and grease from the sewage. Reduces the BOD of the wastewater by about 15 to 30%. Grit chambers or detritus tanks - remove grit and sand Skimming tanks - remove oils and grease REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 6
  • 7. DESIGN OF SCREENS REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 7
  • 8. SCREENING Trapping and removal of floating matter Protection of pumps – by preventing choking Placed before Grit Chamber Types of Screens Coarse Screens Racks (opening 50 mm or more) Rags, woods, paper ( burial and incineration) Medium Screens Bar screens - steel bars parallel to each other 20 mm to 50 mm Some inclined to about 30ᵒ to 60ᵒ to increase opening area. Cleaning Mechanical / Manual Fine screens 06 mm to 20 mm 20% suspended solids from water Brass or Bronze plates and wire mesh REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 8
  • 9. DESIGN CONSIDERATIONS FOR SCREENS VELOCITY OF FLOW Low velocity – greater amount of screening Design velocity should permit 100% removal of solids without settlement IS 6280 – 1971 ( SPECIFICATIONS FOR DESIGN OF SCREENS) 0.6 to 1.2 m/sec found to be satisfactory Minimum Approach Velocity – 0.3 m/sec Materials Steel Bars of flat rods Clear Spacing between bars = 15 mm – 75 mm Minimum Cross section = 10 mm ˟ 50 mm (* Larger dimensions always parallel to the flow) Maximum screen width = 1.5 m Angle of inclination = 45ᵒ - 60ᵒ (Manual ); 60ᵒ -90ᵒ (Automatic) REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 9
  • 10. DESIGN OF SCREENS 1. PEAK SEWAGE FLOW = VELOCITY OF FLOW THROUGH SCREEN Χ NET PROJECTED AREA 2. EFFICIENCY COEFFICENT OF BARS = 𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒 𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒+𝐓𝐇𝐈𝐂𝐊𝐍𝐄𝐒𝐒 𝐎𝐅 𝐓𝐇𝐄 𝐁𝐀𝐑𝐒 3. EFFICIENCY COEFFICENT OF BARS = 𝐍𝐄𝐓 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀 𝐆𝐑𝐎𝐒𝐒 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀 4. NO. OF OPENINGS = NO. OF BARS + 1 5. GROSS WIDTH OF THE BAR = (NO.OF BARS X WIDTH OF BAR) + (NO. OF OPENINGS X WIDTH OF OPENINGS) 6. GROSS AREA = GROSS WIDTH X GROSS DEPTH 7. HEAD LOSS = 0.0729 (V2 – v2 ) REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 10
  • 11. Numerical Estimate Screen requirement for a plant treating a peak flow of 60 MLD of sewage. 1. Peak Flow = 60 Ml/day = 60,000 24 𝑋 60 𝑋 60 = 0.694 cu-m/sec 2. Assume velocity through the screen as 0.8 m/sec 3. Net Area of the screen = Q/A = 0.694 0.8 = 0.87 m2 4. Efficiency coefficent of bars = 𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒 𝐂𝐋𝐄𝐀𝐑 𝐒𝐏𝐀𝐂𝐈𝐍𝐆 𝐁𝐄𝐓𝐖𝐄𝐄𝐍 𝐁𝐀𝐑𝐒+𝐓𝐇𝐈𝐂𝐊𝐍𝐄𝐒𝐒 𝐎𝐅 𝐓𝐇𝐄 𝐁𝐀𝐑𝐒 Assume that the rectangular steel abrs have a screen width of 1 cm and are placed with a clear spacing of 5 cm = 5 5+1 = 5 6 REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 11
  • 12. Numerical 5. Efficiency coefficent of bars = 𝐍𝐄𝐓 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀 𝐆𝐑𝐎𝐒𝐒 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀 5 6 = 0.87 𝐆𝐑𝐎𝐒𝐒 𝐏𝐑𝐎𝐉𝐄𝐂𝐓𝐄𝐃 𝐀𝐑𝐄𝐀 Gross Projected Area = 1.04 m2 REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 12
  • 13. DESIGN OF GRIT CHAMBERS REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 13
  • 14. DESIGN OF GRIT CHAMBERS Detritus tanks  Screens → GRIT → Sedimentation Removes Inorganic materials – Sand, Silt , Clay e.t.c Prevents damage of Pumps – due to abrasion Removes particle size - 0.2 mm Modifications – Aeration Types Horizontal Grit Chambers Aerated Grit Chambers REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 14
  • 15. DESIGN OF GRIT CHAMBERS PEAK SEWAGE FLOW = HORIZONTAL VELOCITY Χ CROSS SECTION AREA DETENTION PERIOD = 𝐃𝐄𝐏𝐓𝐇 𝐎𝐅 𝐖𝐀𝐓𝐄𝐑 𝐈𝐍 𝐁𝐀𝐒𝐈𝐍 𝐒𝐄𝐓𝐓𝐋𝐈𝐍𝐆 𝐕𝐄𝐋𝐎𝐂𝐈𝐓𝐘 ◦ ASSUME SETTLING VELOCITY FOR GRIT CHAMBERS = 0.016 to 0.022 m/sec ◦ DETENTION PERIOD = 1-2 mins. ◦ ASSUME WATER DEPTH = 1 m *For design purpose 2 units of Grit chambers have to be provided in a Sewage treatment plant. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 15
  • 16. AERATED GRIT CHAMBERS Spiral flow aeration tanks Detention period = 3 mins Hopper bottom (0.9 m) with steep slopes Helical or Spiral flow Air feed rate = 0.15 – 0.45 m3 /min –m ( 0.3 m3 /min –m) REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 16
  • 17. DETRITUS TANKS Rectangular chambers ( lesser flow velocity – 0.09 m/sec) Longer Detention periods – 3 to 4 minutes Separate fine as well as large Grit materials Baffle walls and Aeration Systems Grit is removed by scraper mechanism. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 17
  • 18. DESIGN OF SEDIMENTATION TANKS REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 18
  • 19. Sedimentation Tanks After removal of larger floating and suspended materials (through screening) and heavier grit materials (in grit chamber) Directed to Primary Clarifier (Sedimentation) for the removal of suspended organics as well as finer inorganic solids. Sedimentation is essentially a phase separation operation for separating liquid and solids. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 19
  • 20. Types of Settling TYPE I ‐ Discrete (or Free) settling: The particles settle without interaction and occurs under low solids concentration. A typical occurrence of this type of settling is the removal of sand particles. o TYPE II ‐ Flocculent settling: This is defined as a condition where particles initially settle independently, but flocculate in the depth of the clarification unit. The velocity of settling particles are usually increasing as the particles aggregates. The mechanisms of flocculent settling are not well understood. o TYPE III ‐ Hindered (or Zone) settling: Inter‐particle forces are sufficient to hinder the settling of neighboring particles. The particles tend to remain in a fixed positions with respect to each others. This type of settling is typical in the settler for the activated sludge process (secondary clarifier). o TYPE IV ‐ Compression settling: This occurs when the particle concentration is so high that so that particles at one level are mechanically influenced by particles on lower levels. The settling velocity then drastically reduces. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 20
  • 21. Sedimentation Basin Zones Inlet zone: The inlet or influent zone should provide a smooth transition of water and should distribute the flow uniformly across the inlet to the tank. The normal design includes baffles that gently spread the flow across the total inlet of the tank and prevent short circuiting in the tank. The baffle could include a wall across the inlet, perforated with holes across the width of the tank. Settling Zone The settling zone is the largest portion of the sedimentation basin. This zone provides the calm area necessary for the suspended particles to settle. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 21
  • 22. Sedimentation Basin Zones Sludge zone: Located at the bottom of the tank, provides a storage area for the sludge before it is removed for additional treatment or disposal. High flow velocities near the sludge zone should be minimized. Sludge is removed for further treatment from the sludge zone by scraper or vacuum devices which move along the bottom. Outlet Zone The basin outlet zone or launder should provide a smooth transition from the sedimentation zone to the outlet from the tank. This area of the tank also controls the depth of water in the basin. Weirs are set at the end of the tank to control the overflow rate and prevent the solids from leaving the tank before they settle out. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 22
  • 23. Sedimentation Basin Types Intermittent and Continuous Types: o The intermittent tanks, also called quiescent type tanks, are those which store water for a certain period and keep it in complete rest. o In a continuous flow type tank, the flow velocity is only reduced and the water is not brought to complete rest as is done in an intermittent type. Rectangular or Circular Types: o Settling basins may be either long rectangular or circular in plan. o Long narrow rectangular tanks with horizontal flow are generally preferred to the circular tanks with radial or spiral flow. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 23
  • 24. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 24