Integration Management
Develop
Project
Charter
Inputs
•SOW
•Business Case
•Contract
•EEF
•OPA
Tools
•Expert Judgment
Outputs
•Charter
Develop
PM Plan
Inputs
•Charter
•Outputs from
Planning
•EEF
•OPA
Tools
•Expert Judgment
Outputs
•PM Plan
Direct &
Manage
Project
Execution
Inputs
•PM Plan
•Approved Change
Requests
•EEF
•OPA
Tools
•Expert Judgment
•PMIS
Outputs
•Deliverables
•Work Perf Info
•Change Requests
•PM Plan Updates
•Doc Updates
Monitor
& Control
Project
Work
Inputs
•PM Plan
•Perf Reports
•EEF
•OPA
Tools
•Expert Judgment
Outputs
•Change Requests
•PM Plan Updates
•Doc Updates
Perform
Integrated
Change
Control
Inputs
•PM Plan
•Work Perf Info
•Change Requests
•EEF
•OPA
Tools
•Expert Judgment
•Change Control
Meetings
Outputs
•Change Request
Status Updates
•PM Plan Updates
•Doc Updates
Close
Project or
Phase
Inputs
•PM Plan
•Accepted
Deliverables
•OPA
Tools
•Expert Judgment
Outputs
•Final Product,
Service or Result
•OPA Updates
Initiating Planning Executing M&C M&C Closing
Scope Management
Collect
Requirements
Inputs
•Charter
•Stakeholder Register
Tools
•Interviews
•Focus Groups
•Facilitated Workshops
•Group Creativity
Techniques (ABIND)
•Group Decision Making
Techniques (DUMP)
•Questionnaires & Surveys
•Observation
•Prototypes
Outputs
•Requirements Doc
•Requirements Mgmt. plan
•Requirements
Traceability Matrix
Define Scope
Inputs
•Charter
•Requirements Doc
•OPA
Tools
•Expert Judgment
•Product Analysis
•Alternatives ID
•Facilitated Workshops
Outputs
•Scope Statement
•Doc Updates
Create WBS
Inputs
•Scope Statement
•Requirements Doc
•OPA
Tools
•Decomposition
Outputs
•WBS
•WBS Dictionary
•Scope Baseline
•Project Doc Updates
Verify Scope
Inputs
•PM Plan
•Requirements Doc
•Requirements Traceability
Matrix
•Validated Deliverables
Tools
•Inspection
Outputs
•Accepted Deliverables
•Change Requests
•Doc Updates
Control Scope
Inputs
•PM Plan
•Work Perf Info
•Requirements Doc
•Requirements Traceability
Matrix
•OPA
Tools
•Variance Analysis
Outputs
•Work Perf Measurements
•OPA Updates
•Change Requests
•PM Plan Updates
•Doc Updates
Planning M&C M&C
Time Management
Define
Activities
Inputs
•Scope Baseline
•EEF
•OPA
Tools
•Decomposition
•Rolling Wave Planning
•Templates
•Expert Judgment
Outputs
•Activity List
•Activity Attributes
•Milestone List
Sequence
Activities
Inputs
•Activity List
•Activity Attributes
•Milestone List
•Project Scope
Statement
•OPA
Tools
• Precedence Diagramming
Method (PDM)
• Dependency
Determination
• Leads and Lags
• Schedule Network
Templates
Outputs
•Schedule Network
Diagrams
•Doc Updates
Estimate
Activity
Resources
Inputs
•Activity List
•Activity Attributes
•Resource Calendars
•EEF
•OPA
Tools
•Expert Judgment
•Alternatives Analysis
•Published Est. Data
•Bottom-up Estimating
•PM Software
Outputs
•Activity Resource
Requirements
•Resource Breakdown
Structure
•Doc Updates
Estimate
Activity
Durations
Inputs
•Activity List
•Activity Attributes
•Act. Resource Reqts.
•Resource Calendars
•Scope Statement
•EEF
•OPA
Tools
•Expert Judgment
•Analogous Est.
•Parametric Est.
•3-Point Est. (PERT)
•Reserve Analysis
Outputs
•Activity Duration
Estimates
•Doc Updates
Develop
Schedule
Inputs
• Activity List
• Activity Attributes
• Schedule Network Diagrams
• Act. Res. Reqts.
• Resource Calendars
• Act. Dur. Est.
• Scope Statement
• EEF & OPA
Tools
• Schedule Network Analysis
• Critical Path Method
• Critical Chain Method
• Resource Leveling
• What-if Scenario Analysis
• Leads & Lags
• Schedule Compression
(Crash/Fast-track)
• Scheduling Tool
Outputs
•Project Schedule
•Schedule Baseline
•Schedule Data
•Doc Updates
Control
Schedule
Inputs
•PM Plan
•Project Schedule
•Work Perf Info
•OPA
Tools
• Perf Reviews
• Variance Analysis
• PM Software
• Resource Leveling
• What-if Scenario
• Adjusting Leads/Lags
• Schedule Compression
• Scheduling Tool
Outputs
• Work Perf Measurements
• OPA Updates
• Change Requests
• PM Plan Updates
• Doc Updates
Planning M&C
Cost Management
Estimate
Costs
Inputs
•Scope Baseline
•Project Schedule
•HR Plan
•Risk Register
•EEF
•OPA
Tools
•Expert Judgment
•Analogous Estimating
•Parametric Estimating
•Bottom-Up Estimating
•Three-Point Estimates (PERT)
Outputs
•Activity Cost Estimates
•Basis of Estimates
•Doc Updates
Determine
Budget
Inputs
•Activity Cost Estimates
•Basis of Estimates
•Scope Baseline
•Project Schedule
Tools
•Cost Aggregation
•Reserve Analysis (Mgmt vs. Contingency)
•Expert Judgment
•Historical Relationships
•Funding Limit Reconciliation
Outputs
•Cost Performance Baseline
•Project Funding Requirements
•Document Updates
Control
Costs
Inputs
•PM Plan
•Project Funding Requirements
•Work Perf Info
•OPA
Tools
• Earned Value Management
• Forecasting
• TCPI
• Perf. Reviews
• Variance Analysis
• PM Software
Outputs
• Work Perf. Measurements
• Budget Forecasts
• OPA
• Change Requests
• PM Plan Updates
• Doc Updates
Planning M&C
• Reserve Analysis
• Cost of Quality
• PM Estimating Software
• Vendor Bid Analysis
• Resource Calendars
• Contracts
• OPA
Quality Management
Plan Quality
Inputs
•Scope Baseline
•Stakeholder Register
•Cost Perf. Baseline
•Schedule Baseline
Tools
•Cost-Benefit Analysis
•Cost of Quality
•Control Charts
•Benchmarking
Outputs
•Quality Mgmt Plan
•Quality Metrics
•Quality Checklists
Perform Quality
Assurance
Inputs
•PM Plan
•Quality Metrics
•Work Perf. Info
•Quality Control Measurements
Tools
•Plan Quality and Perform Quality Control Tools
& Techniques
•Quality Audits
•Process Analysis
Outputs
•OPA Updates
•Change Requests
•PM Plan Updates
•Doc Updates
Perform Quality
Control
Inputs
•PM Plan
•Quality Metrics
•Quality Checklists
•Work Perf Measurements
Tools
• Cause and Effect Diagrams
• Control Charts
• Flowcharting
• Histogram
• Pareto Diagram
• Run Chart
Outputs
• Quality Control Measurements
• Validated Changes
• Validated Deliverables
• OPA Updates
• Change Requests
• PM Plan Updates
• Doc Updates
Planning M&CExecuting
• Scatter Diagram
• Statistical Sampling
• Inspection
• Approved Change
Requests Review
• Design of Experiments
• Statistical Sampling
• Flowcharting
• Proprietary Quality
Mgmt Methodologies
• Approved Change Requests
• Deliverables
• OPA
• Risk Register
• EEF
• OPA
• Process Improvement
Plan
• Doc Updates
Human Resource Management
Develop HR
Plan
Inputs
•Activity Resource
Requirements
•EEF
•OPA
Tools
•Org charts and Position
Descriptions (i.e. Matrix)
•Networking
•Org Theory
Outputs
•HR Plan
Acquire
Project
Team
Inputs
•PM Plan
•EEF
•OPA
Tools
•Pre-Assignment
•Negotiation
•Acquisition
•Virtual Teams
Outputs
•Project Staff Assignments
•Resource Calendars
•PM Plan Updates
Develop
Project
Team
Inputs
•Project Staff Assignments
•PM Plan
•Resource Calendars
Tools
• Interpersonal Skills
• Training
• Team-Building Activities
• Ground Rules
• Co-Location
• Recognition & Rewards (theories of
motivation)
Outputs
•Team Perf Assessments
•EEF
Manage
Project
Team
Inputs
•Project Staff Assignments
•PM Plan
•Team Perf. Assessments
•Perf. Reports
•OPA
Tools
•Observation and Conversation
•Project Perf. Appraisals
•Conflict Management
•Issue Log
•Interpersonal Skills
Outputs
•EEF Updates
•OPA Updates
•Change Requests
•PM Plan Updates
Planning Executing
Communications Management
ID Stakeholders
Inputs
•Charter
•Procurement Docs
•EEF
•OPA
Tools
•Stakeholder Analysis
•Expert Judgment
Outputs
•Stakeholder Register
•Stakeholder Mgmt.
Strategy
Plan
Communications
Inputs
•Stakeholder Register
•Stakeholder Mgmt.
Strategy
•EEF
•OPA
Tools
•Communication
Requirements Analysis
•Communication
Technology
•Communication Models
•Communication
Methods (Push/Pull)
Outputs
•Communication Mgmt.
Plan
•Doc Updates
Distribute Info
Inputs
•PM Plan
•Perf. Reports
•OPA
Tools
•Communication Methods
•Info Distribution Tools
Outputs
•OPA Updates
Manage
Stakeholder
Expectations
Inputs
• Stakeholder Register
• Stakeholder Mgmt. Strategy
• PM Plan
• Issue Log
• Change Log
• OPA
Tools
• Communication Methods
• Interpersonal Skills
• Management Skills
Outputs
• OPA Updates
• Change Requests
• PM Plan Updates
• Project Document Updates
Report
Performance
Inputs
• PM Plan
• Work Perf Info
• Work Perf Measurements
• Budget Forecasts
• OPA
Tools
• Variance Analysis
• Forecasting Methods
• Communication Methods
• Reporting Systems
Outputs
• Performance Reports
• Organizational Process Assets
Updates
• Change Requests
Initiating ExecutingPlanning M&C
Risk Management
Plan Risk
Management
Inputs
•Project Scope
Statement
•Cost Mgmt. Plan
•Schedule Mgmt. Plan
•Communications
Mgmt. Plan
•EEF
•OPA
Tools
•Planning Meetings &
Analysis
Outputs
•Risk Mgmt. Plan
ID Risks
Inputs
• Risk Mgmt. Plan
• Activity Cost Estimates
• Activity Duration Est.
• Scope Baseline
• Stakeholder Register
• Cost Mgmt. Plan
• Schedule Mgmt. Plan
• Quality Mgmt. Plan
• Project Docs.
• EEF
• OPA
Tools
• Documentation Reviews
• Info Gathering Techniques (F-
BIRD)
• Checklist Analysis
• Assumptions Analysis
• Diagramming Techniques (CSI)
• SWOT Analysis
• Expert Judgment
Outputs
•Risk Register
Qualitative
Analysis
Inputs
•Risk Register
•Risk Mgmt. Plan
•Project Scope
Statement
•OPA
Tools
• Risk P x I Assessment
• P x I Matrix
• Risk Data Quality
Assessment
• Risk Categorization
• Risk Urgency Assessment
• Expert Judgment
Outputs
•Risk Register Updates
Quantitative
Analysis
Inputs
•Risk Register
•Risk Mgmt. Plan
•Cost Mgmt. Plan
•Schedule Mgmt. Plan
•OPA
Tools
•Data Gathering and
Representation
Techniques
•Quantitative Risk
Analysis & Modeling
Techniques (MEDS)
•Expert Judgment
Outputs
•Risk Register Updates
Plan Risk
Responses
Inputs
•Risk Register
•Risk Management Plan
Tools
• Strategies for Negative
Risks/Threats
• Strategies for Positive
Risks/Opportunities
• Contingent Response
Strategies
• Expert Judgment
Outputs
• Risk Register Updates
• Risk-Related Contract
Decisions
• PM Plan Updates
• Doc Updates
Monitor &
Control Risks
Inputs
• Risk Register
• PM Plan
• WPI
• Performance Reports
Tools
• Risk Reassessment
• Risk Audit
• Variance & Trend Analysis
• Technical Performance
Measurement
• Reserve Analysis
• Status Meetings
Outputs
• Risk Register Updates
• OPA Updates
• Change Requests
• PM Plan Updates
• Doc Updates
Planning M&C
Procurement Management
Plan
Procurement
Inputs
• Scope Baseline
• Requirements Doc
• Teaming Agreements
• Risk Register
• Risk-Related Contract Decisions
• Activity Resource Reqmts.
• Project Schedule
Tools
•Make-or-Buy Analysis
•Expert Judgment
•Contract Types
Outputs
•Procurement Mgmt Plan
•Procurement SOW
•Make-or-Buy Decisions
•Procurement Docs (IFB, RFP)
•Source Selection Criteria
•Change Requests
Conduct
Procurements
Inputs
•PM Plan
•Procurement Docs
•Source Selection Criteria
•Qualified Seller List
•Seller Proposals
Tools
•Bidder Conferences
•Proposal Eval. Techs.
•Independent Est.
•Expert Judgment
•Advertising
Outputs
• Selected sellers
• Procurement contract award
• Resource Calendars
• Change Requests
• PM Plan Updates
• Doc. Updates
Administer
Procurements
Inputs
• Procurement Docs
• PM Plan
• Contract
• Performance Reports
• Approved Change Requests
• WPI
Tools
• Contract change control system
• Procurement Performance Reviews
• Inspections and Audits
• Performance Reporting
• Payment Systems
• Claims Administration
• Records Mgmt. System
Outputs
•Procurement Documentation
•OPA Updates
•Change Requests
•PM Plan Updates
Close
Procurements
Inputs
•PM Plan
•Procurement
Documentation
Tools
•Procurement Audits
•Negotiated Settlements
•Records Mgmt. System
Outputs
•Closed Procurements
•OPA Updates
Planning Executing M&C Closing
• Activity Cost Est.
• Cost Perf. Baseline
• EEF
• OPA
•Project Docs.
•Make-or-Buy
Decisions
•Teaming
Agreements
•OPA
• Internet Search
• Procurement
Negotiations

PMBOK 4th Ed ITTO

  • 1.
    Integration Management Develop Project Charter Inputs •SOW •Business Case •Contract •EEF •OPA Tools •ExpertJudgment Outputs •Charter Develop PM Plan Inputs •Charter •Outputs from Planning •EEF •OPA Tools •Expert Judgment Outputs •PM Plan Direct & Manage Project Execution Inputs •PM Plan •Approved Change Requests •EEF •OPA Tools •Expert Judgment •PMIS Outputs •Deliverables •Work Perf Info •Change Requests •PM Plan Updates •Doc Updates Monitor & Control Project Work Inputs •PM Plan •Perf Reports •EEF •OPA Tools •Expert Judgment Outputs •Change Requests •PM Plan Updates •Doc Updates Perform Integrated Change Control Inputs •PM Plan •Work Perf Info •Change Requests •EEF •OPA Tools •Expert Judgment •Change Control Meetings Outputs •Change Request Status Updates •PM Plan Updates •Doc Updates Close Project or Phase Inputs •PM Plan •Accepted Deliverables •OPA Tools •Expert Judgment Outputs •Final Product, Service or Result •OPA Updates Initiating Planning Executing M&C M&C Closing
  • 2.
    Scope Management Collect Requirements Inputs •Charter •Stakeholder Register Tools •Interviews •FocusGroups •Facilitated Workshops •Group Creativity Techniques (ABIND) •Group Decision Making Techniques (DUMP) •Questionnaires & Surveys •Observation •Prototypes Outputs •Requirements Doc •Requirements Mgmt. plan •Requirements Traceability Matrix Define Scope Inputs •Charter •Requirements Doc •OPA Tools •Expert Judgment •Product Analysis •Alternatives ID •Facilitated Workshops Outputs •Scope Statement •Doc Updates Create WBS Inputs •Scope Statement •Requirements Doc •OPA Tools •Decomposition Outputs •WBS •WBS Dictionary •Scope Baseline •Project Doc Updates Verify Scope Inputs •PM Plan •Requirements Doc •Requirements Traceability Matrix •Validated Deliverables Tools •Inspection Outputs •Accepted Deliverables •Change Requests •Doc Updates Control Scope Inputs •PM Plan •Work Perf Info •Requirements Doc •Requirements Traceability Matrix •OPA Tools •Variance Analysis Outputs •Work Perf Measurements •OPA Updates •Change Requests •PM Plan Updates •Doc Updates Planning M&C M&C
  • 3.
    Time Management Define Activities Inputs •Scope Baseline •EEF •OPA Tools •Decomposition •RollingWave Planning •Templates •Expert Judgment Outputs •Activity List •Activity Attributes •Milestone List Sequence Activities Inputs •Activity List •Activity Attributes •Milestone List •Project Scope Statement •OPA Tools • Precedence Diagramming Method (PDM) • Dependency Determination • Leads and Lags • Schedule Network Templates Outputs •Schedule Network Diagrams •Doc Updates Estimate Activity Resources Inputs •Activity List •Activity Attributes •Resource Calendars •EEF •OPA Tools •Expert Judgment •Alternatives Analysis •Published Est. Data •Bottom-up Estimating •PM Software Outputs •Activity Resource Requirements •Resource Breakdown Structure •Doc Updates Estimate Activity Durations Inputs •Activity List •Activity Attributes •Act. Resource Reqts. •Resource Calendars •Scope Statement •EEF •OPA Tools •Expert Judgment •Analogous Est. •Parametric Est. •3-Point Est. (PERT) •Reserve Analysis Outputs •Activity Duration Estimates •Doc Updates Develop Schedule Inputs • Activity List • Activity Attributes • Schedule Network Diagrams • Act. Res. Reqts. • Resource Calendars • Act. Dur. Est. • Scope Statement • EEF & OPA Tools • Schedule Network Analysis • Critical Path Method • Critical Chain Method • Resource Leveling • What-if Scenario Analysis • Leads & Lags • Schedule Compression (Crash/Fast-track) • Scheduling Tool Outputs •Project Schedule •Schedule Baseline •Schedule Data •Doc Updates Control Schedule Inputs •PM Plan •Project Schedule •Work Perf Info •OPA Tools • Perf Reviews • Variance Analysis • PM Software • Resource Leveling • What-if Scenario • Adjusting Leads/Lags • Schedule Compression • Scheduling Tool Outputs • Work Perf Measurements • OPA Updates • Change Requests • PM Plan Updates • Doc Updates Planning M&C
  • 4.
    Cost Management Estimate Costs Inputs •Scope Baseline •ProjectSchedule •HR Plan •Risk Register •EEF •OPA Tools •Expert Judgment •Analogous Estimating •Parametric Estimating •Bottom-Up Estimating •Three-Point Estimates (PERT) Outputs •Activity Cost Estimates •Basis of Estimates •Doc Updates Determine Budget Inputs •Activity Cost Estimates •Basis of Estimates •Scope Baseline •Project Schedule Tools •Cost Aggregation •Reserve Analysis (Mgmt vs. Contingency) •Expert Judgment •Historical Relationships •Funding Limit Reconciliation Outputs •Cost Performance Baseline •Project Funding Requirements •Document Updates Control Costs Inputs •PM Plan •Project Funding Requirements •Work Perf Info •OPA Tools • Earned Value Management • Forecasting • TCPI • Perf. Reviews • Variance Analysis • PM Software Outputs • Work Perf. Measurements • Budget Forecasts • OPA • Change Requests • PM Plan Updates • Doc Updates Planning M&C • Reserve Analysis • Cost of Quality • PM Estimating Software • Vendor Bid Analysis • Resource Calendars • Contracts • OPA
  • 5.
    Quality Management Plan Quality Inputs •ScopeBaseline •Stakeholder Register •Cost Perf. Baseline •Schedule Baseline Tools •Cost-Benefit Analysis •Cost of Quality •Control Charts •Benchmarking Outputs •Quality Mgmt Plan •Quality Metrics •Quality Checklists Perform Quality Assurance Inputs •PM Plan •Quality Metrics •Work Perf. Info •Quality Control Measurements Tools •Plan Quality and Perform Quality Control Tools & Techniques •Quality Audits •Process Analysis Outputs •OPA Updates •Change Requests •PM Plan Updates •Doc Updates Perform Quality Control Inputs •PM Plan •Quality Metrics •Quality Checklists •Work Perf Measurements Tools • Cause and Effect Diagrams • Control Charts • Flowcharting • Histogram • Pareto Diagram • Run Chart Outputs • Quality Control Measurements • Validated Changes • Validated Deliverables • OPA Updates • Change Requests • PM Plan Updates • Doc Updates Planning M&CExecuting • Scatter Diagram • Statistical Sampling • Inspection • Approved Change Requests Review • Design of Experiments • Statistical Sampling • Flowcharting • Proprietary Quality Mgmt Methodologies • Approved Change Requests • Deliverables • OPA • Risk Register • EEF • OPA • Process Improvement Plan • Doc Updates
  • 6.
    Human Resource Management DevelopHR Plan Inputs •Activity Resource Requirements •EEF •OPA Tools •Org charts and Position Descriptions (i.e. Matrix) •Networking •Org Theory Outputs •HR Plan Acquire Project Team Inputs •PM Plan •EEF •OPA Tools •Pre-Assignment •Negotiation •Acquisition •Virtual Teams Outputs •Project Staff Assignments •Resource Calendars •PM Plan Updates Develop Project Team Inputs •Project Staff Assignments •PM Plan •Resource Calendars Tools • Interpersonal Skills • Training • Team-Building Activities • Ground Rules • Co-Location • Recognition & Rewards (theories of motivation) Outputs •Team Perf Assessments •EEF Manage Project Team Inputs •Project Staff Assignments •PM Plan •Team Perf. Assessments •Perf. Reports •OPA Tools •Observation and Conversation •Project Perf. Appraisals •Conflict Management •Issue Log •Interpersonal Skills Outputs •EEF Updates •OPA Updates •Change Requests •PM Plan Updates Planning Executing
  • 7.
    Communications Management ID Stakeholders Inputs •Charter •ProcurementDocs •EEF •OPA Tools •Stakeholder Analysis •Expert Judgment Outputs •Stakeholder Register •Stakeholder Mgmt. Strategy Plan Communications Inputs •Stakeholder Register •Stakeholder Mgmt. Strategy •EEF •OPA Tools •Communication Requirements Analysis •Communication Technology •Communication Models •Communication Methods (Push/Pull) Outputs •Communication Mgmt. Plan •Doc Updates Distribute Info Inputs •PM Plan •Perf. Reports •OPA Tools •Communication Methods •Info Distribution Tools Outputs •OPA Updates Manage Stakeholder Expectations Inputs • Stakeholder Register • Stakeholder Mgmt. Strategy • PM Plan • Issue Log • Change Log • OPA Tools • Communication Methods • Interpersonal Skills • Management Skills Outputs • OPA Updates • Change Requests • PM Plan Updates • Project Document Updates Report Performance Inputs • PM Plan • Work Perf Info • Work Perf Measurements • Budget Forecasts • OPA Tools • Variance Analysis • Forecasting Methods • Communication Methods • Reporting Systems Outputs • Performance Reports • Organizational Process Assets Updates • Change Requests Initiating ExecutingPlanning M&C
  • 8.
    Risk Management Plan Risk Management Inputs •ProjectScope Statement •Cost Mgmt. Plan •Schedule Mgmt. Plan •Communications Mgmt. Plan •EEF •OPA Tools •Planning Meetings & Analysis Outputs •Risk Mgmt. Plan ID Risks Inputs • Risk Mgmt. Plan • Activity Cost Estimates • Activity Duration Est. • Scope Baseline • Stakeholder Register • Cost Mgmt. Plan • Schedule Mgmt. Plan • Quality Mgmt. Plan • Project Docs. • EEF • OPA Tools • Documentation Reviews • Info Gathering Techniques (F- BIRD) • Checklist Analysis • Assumptions Analysis • Diagramming Techniques (CSI) • SWOT Analysis • Expert Judgment Outputs •Risk Register Qualitative Analysis Inputs •Risk Register •Risk Mgmt. Plan •Project Scope Statement •OPA Tools • Risk P x I Assessment • P x I Matrix • Risk Data Quality Assessment • Risk Categorization • Risk Urgency Assessment • Expert Judgment Outputs •Risk Register Updates Quantitative Analysis Inputs •Risk Register •Risk Mgmt. Plan •Cost Mgmt. Plan •Schedule Mgmt. Plan •OPA Tools •Data Gathering and Representation Techniques •Quantitative Risk Analysis & Modeling Techniques (MEDS) •Expert Judgment Outputs •Risk Register Updates Plan Risk Responses Inputs •Risk Register •Risk Management Plan Tools • Strategies for Negative Risks/Threats • Strategies for Positive Risks/Opportunities • Contingent Response Strategies • Expert Judgment Outputs • Risk Register Updates • Risk-Related Contract Decisions • PM Plan Updates • Doc Updates Monitor & Control Risks Inputs • Risk Register • PM Plan • WPI • Performance Reports Tools • Risk Reassessment • Risk Audit • Variance & Trend Analysis • Technical Performance Measurement • Reserve Analysis • Status Meetings Outputs • Risk Register Updates • OPA Updates • Change Requests • PM Plan Updates • Doc Updates Planning M&C
  • 9.
    Procurement Management Plan Procurement Inputs • ScopeBaseline • Requirements Doc • Teaming Agreements • Risk Register • Risk-Related Contract Decisions • Activity Resource Reqmts. • Project Schedule Tools •Make-or-Buy Analysis •Expert Judgment •Contract Types Outputs •Procurement Mgmt Plan •Procurement SOW •Make-or-Buy Decisions •Procurement Docs (IFB, RFP) •Source Selection Criteria •Change Requests Conduct Procurements Inputs •PM Plan •Procurement Docs •Source Selection Criteria •Qualified Seller List •Seller Proposals Tools •Bidder Conferences •Proposal Eval. Techs. •Independent Est. •Expert Judgment •Advertising Outputs • Selected sellers • Procurement contract award • Resource Calendars • Change Requests • PM Plan Updates • Doc. Updates Administer Procurements Inputs • Procurement Docs • PM Plan • Contract • Performance Reports • Approved Change Requests • WPI Tools • Contract change control system • Procurement Performance Reviews • Inspections and Audits • Performance Reporting • Payment Systems • Claims Administration • Records Mgmt. System Outputs •Procurement Documentation •OPA Updates •Change Requests •PM Plan Updates Close Procurements Inputs •PM Plan •Procurement Documentation Tools •Procurement Audits •Negotiated Settlements •Records Mgmt. System Outputs •Closed Procurements •OPA Updates Planning Executing M&C Closing • Activity Cost Est. • Cost Perf. Baseline • EEF • OPA •Project Docs. •Make-or-Buy Decisions •Teaming Agreements •OPA • Internet Search • Procurement Negotiations