SlideShare a Scribd company logo
1 of 31
Progress Update (Nr. 1)
Week ending 25th September
Programme Update - ITS
Scheme Start on Site : 14th September
Throughout the course of the two weeks we have successfully completed the below:
- Isolated and disconnected the existing mechanical and electrical building services
- Commenced internal strip out and demolitions of the existing building fabric
- Carried out the asbestos removal within the lower ground plant room
- Demolished the existing outbuilding and garage/office areas
- Commenced scaffold to the rear of the building to enable efficient waste removal
Progress Photos – External
Site Compound and external hoardings set up
Progress Photos – External
External outbuilding and
garage/office demolished
Progress Photos – External
Tree protection area set up
around Horse Chestnut Tree
Progress Photos – Internal
Internal soft strip and
demolition works
commenced
Progress Photos – Internal
Progress Photos – Internal
Existing Plant Room now
fully stripped of asbestos
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete strip out of existing mechanical and electrical building services
- Complete internal soft strip and demolition works
- Remove scaffold & associated rubbish chute at the rear of the building
- Commence external drainage works (including forming new manholes)
- Commence excavation to proposed basement area
- Install temporary propping to basement to assist with excavations
Progress Update (Nr. 2)
Week ending 9th October
Programme Update - ITS
For Period : Mon 28th September – Friday 9th October
- Fully completed strip out of existing mechanical and electrical building services
- Fully completed internal soft strip, demolition and non-structural works
- Removed scaffold & associated rubbish chute at the rear of the building
- Fully completed cut and carve demolition of structures around rear of building
- Commenced external drainage works (including forming new manhole)
- Numerous trial pits excavated and waste samples collected for review off site; in
preparation for groundworks commencing
Progress Photos – Internal
Building now completely
stripped at all floor levels
Progress Photos – Internal
Building now completely
stripped at all floor levels
Progress Photos – Internal
All internal non-structural
walls now removed on each
floor level
Progress Photos – External
Trial pits now complete and
backfilled on site to
establish extent of existing
foundations
Progress Photos – External
All external demolition
works now complete
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Commence new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
Progress Update (Nr. 3)
Week ending 23rd October
Programme Update - ITS
For Period : Mon 10th October – Friday 23rd October
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Completed new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
Progress Photos – Internal
First fix mechanical and
electrical works
commenced within the
existing buidling
Progress Photos – Internal
Damp proof membrane
applied to walls within
basement
Progress Photos – Internal
Further internal damp-
proofing works to basement
walls commenced including
re-plaster (to 1.5m) where
required
Progress Photos – External
Reduced level dig complete
to basement area with
damp proofing and
reinforcement installation
begun.
Progress Photos – External
Below ground drainage
‘pop ups’ for sinks and
toilets etc installed prior to
concrete pours
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete excavations to new ground floor slab and perimeter retaining walls
- Complete installation of reinforcement to basement slab and concrete pour
- Excavate pad foundations to proposed ground floor and install associated holding
down bolts in preparation for steelwork
- Complete internal damp-proofing works to basement walls
- Commence internal builders work and remove remaining load bearing walls:
including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors

More Related Content

What's hot

Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)Lwj Welson
 
Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013tboyko
 
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-inRenovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-inAnthony Boyko
 
Balinese residences at adora de goa
Balinese residences at adora de goaBalinese residences at adora de goa
Balinese residences at adora de goaprovidenthousing4
 
Plots for sale in electronic city
Plots for sale in electronic cityPlots for sale in electronic city
Plots for sale in electronic cityprovidenthousing4
 
Flats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, BangaloreFlats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, Bangaloreprovidenthousing4
 
Big Water Visitor Center
Big Water Visitor CenterBig Water Visitor Center
Big Water Visitor CenterRay Rankin
 
Directors report (2)
Directors report (2)Directors report (2)
Directors report (2)Elimlodge
 
CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013tboyko
 
King Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolitionKing Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolitionallieger
 

What's hot (12)

Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)
 
Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013
 
ste p rept 2
ste p rept 2ste p rept 2
ste p rept 2
 
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-inRenovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
 
Balinese residences at adora de goa
Balinese residences at adora de goaBalinese residences at adora de goa
Balinese residences at adora de goa
 
Plots for sale in electronic city
Plots for sale in electronic cityPlots for sale in electronic city
Plots for sale in electronic city
 
Ici final project
Ici final projectIci final project
Ici final project
 
Flats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, BangaloreFlats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, Bangalore
 
Big Water Visitor Center
Big Water Visitor CenterBig Water Visitor Center
Big Water Visitor Center
 
Directors report (2)
Directors report (2)Directors report (2)
Directors report (2)
 
CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013
 
King Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolitionKing Street Staion: 3rd floor walls demolition
King Street Staion: 3rd floor walls demolition
 

Viewers also liked

Project timeline slides v2
Project timeline slides v2Project timeline slides v2
Project timeline slides v2Eileen Feng
 
Mind Map- Interdepartmental Communication for Rehabbing Affordable Housing
Mind Map- Interdepartmental Communication for Rehabbing Affordable HousingMind Map- Interdepartmental Communication for Rehabbing Affordable Housing
Mind Map- Interdepartmental Communication for Rehabbing Affordable HousingRobert Baca
 
Project timeline v0.1
Project timeline v0.1Project timeline v0.1
Project timeline v0.1Fred Fish
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
The project schedule and budget
The project schedule and budgetThe project schedule and budget
The project schedule and budgettumetr1
 
January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update parkmercedvision
 
Template for building project schedule
Template for building project schedule Template for building project schedule
Template for building project schedule Snehan
 
Project Timeline Template - Deliverable Based Consulting
Project Timeline Template - Deliverable Based ConsultingProject Timeline Template - Deliverable Based Consulting
Project Timeline Template - Deliverable Based ConsultingDeliverable Based Consulting
 
Project Planning Timeline Editable ppt
Project Planning Timeline Editable pptProject Planning Timeline Editable ppt
Project Planning Timeline Editable ppt24point0
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Business plan presentation
Business plan presentationBusiness plan presentation
Business plan presentation2AM
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by meAnkit Walia
 

Viewers also liked (13)

Project timeline slides v2
Project timeline slides v2Project timeline slides v2
Project timeline slides v2
 
Mind Map- Interdepartmental Communication for Rehabbing Affordable Housing
Mind Map- Interdepartmental Communication for Rehabbing Affordable HousingMind Map- Interdepartmental Communication for Rehabbing Affordable Housing
Mind Map- Interdepartmental Communication for Rehabbing Affordable Housing
 
Project timeline v0.1
Project timeline v0.1Project timeline v0.1
Project timeline v0.1
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
The project schedule and budget
The project schedule and budgetThe project schedule and budget
The project schedule and budget
 
January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update January 23rd ,2017 Parkmerced Vision Update
January 23rd ,2017 Parkmerced Vision Update
 
Template for building project schedule
Template for building project schedule Template for building project schedule
Template for building project schedule
 
Planning And Managing The Project
Planning And Managing The ProjectPlanning And Managing The Project
Planning And Managing The Project
 
Project Timeline Template - Deliverable Based Consulting
Project Timeline Template - Deliverable Based ConsultingProject Timeline Template - Deliverable Based Consulting
Project Timeline Template - Deliverable Based Consulting
 
Project Planning Timeline Editable ppt
Project Planning Timeline Editable pptProject Planning Timeline Editable ppt
Project Planning Timeline Editable ppt
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Business plan presentation
Business plan presentationBusiness plan presentation
Business plan presentation
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by me
 

Similar to Progress Update: Works Completed and Next Steps

SCTE Solar Story
SCTE Solar StorySCTE Solar Story
SCTE Solar StorySCTE
 
Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !wesleyvillhard
 
advanced constructiion technologies
advanced constructiion technologiesadvanced constructiion technologies
advanced constructiion technologiesMOHANAHARIHARAN R
 
Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation vsproul
 
superstructure ppt.ppt
superstructure ppt.pptsuperstructure ppt.ppt
superstructure ppt.pptYanyanYamson1
 
PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14Jim Benge
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline KH
 
Stadium_Construction_Progress_Report_Number_16_02.24.11.pdf
Stadium_Construction_Progress_Report_Number_16_02.24.11.pdfStadium_Construction_Progress_Report_Number_16_02.24.11.pdf
Stadium_Construction_Progress_Report_Number_16_02.24.11.pdfBrian Phillip
 

Similar to Progress Update: Works Completed and Next Steps (15)

ITS Building Project - progress update 6
ITS Building Project - progress update 6ITS Building Project - progress update 6
ITS Building Project - progress update 6
 
ITS Building Project - progress update 4
ITS Building Project - progress update 4ITS Building Project - progress update 4
ITS Building Project - progress update 4
 
ITS Building Project - progress update 7
ITS Building Project - progress update 7ITS Building Project - progress update 7
ITS Building Project - progress update 7
 
ITS Bulding Project - progress update April 2016
ITS Bulding Project  - progress update April 2016 ITS Bulding Project  - progress update April 2016
ITS Bulding Project - progress update April 2016
 
SCTE Solar Story
SCTE Solar StorySCTE Solar Story
SCTE Solar Story
 
Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !
 
advanced constructiion technologies
advanced constructiion technologiesadvanced constructiion technologies
advanced constructiion technologies
 
Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation
 
superstructure ppt.ppt
superstructure ppt.pptsuperstructure ppt.ppt
superstructure ppt.ppt
 
PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
 
Stadium_Construction_Progress_Report_Number_16_02.24.11.pdf
Stadium_Construction_Progress_Report_Number_16_02.24.11.pdfStadium_Construction_Progress_Report_Number_16_02.24.11.pdf
Stadium_Construction_Progress_Report_Number_16_02.24.11.pdf
 
Projects alrawan
Projects alrawanProjects alrawan
Projects alrawan
 
Making of burj khalifa
Making of burj khalifaMaking of burj khalifa
Making of burj khalifa
 

More from Institute for Transport Studies (ITS)

Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Institute for Transport Studies (ITS)
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challengesInstitute for Transport Studies (ITS)
 
A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...Institute for Transport Studies (ITS)
 
Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourInstitute for Transport Studies (ITS)
 
Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Institute for Transport Studies (ITS)
 

More from Institute for Transport Studies (ITS) (20)

Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
 
BA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of LeedsBA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of Leeds
 
Highways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating ImpactHighways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating Impact
 
Using telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollutionUsing telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollution
 
Masters Dissertation Posters 2017
Masters Dissertation Posters 2017Masters Dissertation Posters 2017
Masters Dissertation Posters 2017
 
Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challenges
 
Secretary of State Visit
Secretary of State VisitSecretary of State Visit
Secretary of State Visit
 
Business model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futuresBusiness model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futures
 
A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...
 
Cars cars everywhere
Cars cars everywhereCars cars everywhere
Cars cars everywhere
 
Annual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leedsAnnual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leeds
 
Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviour
 
Rail freight in Japan - track access
Rail freight in Japan - track accessRail freight in Japan - track access
Rail freight in Japan - track access
 
Real time traffic management - challenges and solutions
Real time traffic management - challenges and solutionsReal time traffic management - challenges and solutions
Real time traffic management - challenges and solutions
 
Proportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networksProportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networks
 
Capacity maximising traffic signal control policies
Capacity maximising traffic signal control policiesCapacity maximising traffic signal control policies
Capacity maximising traffic signal control policies
 
Bayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehiclesBayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehicles
 
Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...
 
A new theory of lane selection on highways
A new theory of lane selection on highwaysA new theory of lane selection on highways
A new theory of lane selection on highways
 

Recently uploaded

CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 

Recently uploaded (20)

CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 

Progress Update: Works Completed and Next Steps

  • 1.
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.
  • 7. Progress Update (Nr. 1) Week ending 25th September
  • 8. Programme Update - ITS Scheme Start on Site : 14th September Throughout the course of the two weeks we have successfully completed the below: - Isolated and disconnected the existing mechanical and electrical building services - Commenced internal strip out and demolitions of the existing building fabric - Carried out the asbestos removal within the lower ground plant room - Demolished the existing outbuilding and garage/office areas - Commenced scaffold to the rear of the building to enable efficient waste removal
  • 9. Progress Photos – External Site Compound and external hoardings set up
  • 10. Progress Photos – External External outbuilding and garage/office demolished
  • 11. Progress Photos – External Tree protection area set up around Horse Chestnut Tree
  • 12. Progress Photos – Internal Internal soft strip and demolition works commenced
  • 14. Progress Photos – Internal Existing Plant Room now fully stripped of asbestos
  • 15. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete strip out of existing mechanical and electrical building services - Complete internal soft strip and demolition works - Remove scaffold & associated rubbish chute at the rear of the building - Commence external drainage works (including forming new manholes) - Commence excavation to proposed basement area - Install temporary propping to basement to assist with excavations
  • 16. Progress Update (Nr. 2) Week ending 9th October
  • 17. Programme Update - ITS For Period : Mon 28th September – Friday 9th October - Fully completed strip out of existing mechanical and electrical building services - Fully completed internal soft strip, demolition and non-structural works - Removed scaffold & associated rubbish chute at the rear of the building - Fully completed cut and carve demolition of structures around rear of building - Commenced external drainage works (including forming new manhole) - Numerous trial pits excavated and waste samples collected for review off site; in preparation for groundworks commencing
  • 18. Progress Photos – Internal Building now completely stripped at all floor levels
  • 19. Progress Photos – Internal Building now completely stripped at all floor levels
  • 20. Progress Photos – Internal All internal non-structural walls now removed on each floor level
  • 21. Progress Photos – External Trial pits now complete and backfilled on site to establish extent of existing foundations
  • 22. Progress Photos – External All external demolition works now complete
  • 23. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Commence excavations to the new basement area of the extension and muck away - Begin excavations of new perimeter retaining walls - Fully set out new building footprint and excavate necessary pad foundations - Installation of associated insulation, reinforcement and temporary formwork in preparation for concrete pours - Commence new internal flooring infills where redundant staircases removed - Commence first fix mechanical and electrical works within existing building
  • 24. Progress Update (Nr. 3) Week ending 23rd October
  • 25. Programme Update - ITS For Period : Mon 10th October – Friday 23rd October - Commence excavations to the new basement area of the extension and muck away - Begin excavations of new perimeter retaining walls - Fully set out new building footprint and excavate necessary pad foundations - Installation of associated insulation, reinforcement and temporary formwork in preparation for concrete pours - Completed new internal flooring infills where redundant staircases removed - Commence first fix mechanical and electrical works within existing building
  • 26. Progress Photos – Internal First fix mechanical and electrical works commenced within the existing buidling
  • 27. Progress Photos – Internal Damp proof membrane applied to walls within basement
  • 28. Progress Photos – Internal Further internal damp- proofing works to basement walls commenced including re-plaster (to 1.5m) where required
  • 29. Progress Photos – External Reduced level dig complete to basement area with damp proofing and reinforcement installation begun.
  • 30. Progress Photos – External Below ground drainage ‘pop ups’ for sinks and toilets etc installed prior to concrete pours
  • 31. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete excavations to new ground floor slab and perimeter retaining walls - Complete installation of reinforcement to basement slab and concrete pour - Excavate pad foundations to proposed ground floor and install associated holding down bolts in preparation for steelwork - Complete internal damp-proofing works to basement walls - Commence internal builders work and remove remaining load bearing walls: including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors