This progress update provides information on construction works completed over the past 3 weeks on an ITS project. Key accomplishments include stripping out mechanical and electrical systems, demolishing outbuildings, completing asbestos removal, excavating for the new basement, and beginning first fix M&E works. Over the next 2 weeks, excavation will continue and the basement slab will be poured with concrete after installing reinforcement. Internal damp proofing of the basement will also be finished.
8. Programme Update - ITS
Scheme Start on Site : 14th September
Throughout the course of the two weeks we have successfully completed the below:
- Isolated and disconnected the existing mechanical and electrical building services
- Commenced internal strip out and demolitions of the existing building fabric
- Carried out the asbestos removal within the lower ground plant room
- Demolished the existing outbuilding and garage/office areas
- Commenced scaffold to the rear of the building to enable efficient waste removal
9. Progress Photos – External
Site Compound and external hoardings set up
10. Progress Photos – External
External outbuilding and
garage/office demolished
11. Progress Photos – External
Tree protection area set up
around Horse Chestnut Tree
12. Progress Photos – Internal
Internal soft strip and
demolition works
commenced
14. Progress Photos – Internal
Existing Plant Room now
fully stripped of asbestos
15. Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete strip out of existing mechanical and electrical building services
- Complete internal soft strip and demolition works
- Remove scaffold & associated rubbish chute at the rear of the building
- Commence external drainage works (including forming new manholes)
- Commence excavation to proposed basement area
- Install temporary propping to basement to assist with excavations
17. Programme Update - ITS
For Period : Mon 28th September – Friday 9th October
- Fully completed strip out of existing mechanical and electrical building services
- Fully completed internal soft strip, demolition and non-structural works
- Removed scaffold & associated rubbish chute at the rear of the building
- Fully completed cut and carve demolition of structures around rear of building
- Commenced external drainage works (including forming new manhole)
- Numerous trial pits excavated and waste samples collected for review off site; in
preparation for groundworks commencing
18. Progress Photos – Internal
Building now completely
stripped at all floor levels
19. Progress Photos – Internal
Building now completely
stripped at all floor levels
20. Progress Photos – Internal
All internal non-structural
walls now removed on each
floor level
21. Progress Photos – External
Trial pits now complete and
backfilled on site to
establish extent of existing
foundations
22. Progress Photos – External
All external demolition
works now complete
23. Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Commence new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
25. Programme Update - ITS
For Period : Mon 10th October – Friday 23rd October
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Completed new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
26. Progress Photos – Internal
First fix mechanical and
electrical works
commenced within the
existing buidling
27. Progress Photos – Internal
Damp proof membrane
applied to walls within
basement
28. Progress Photos – Internal
Further internal damp-
proofing works to basement
walls commenced including
re-plaster (to 1.5m) where
required
29. Progress Photos – External
Reduced level dig complete
to basement area with
damp proofing and
reinforcement installation
begun.
30. Progress Photos – External
Below ground drainage
‘pop ups’ for sinks and
toilets etc installed prior to
concrete pours
31. Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete excavations to new ground floor slab and perimeter retaining walls
- Complete installation of reinforcement to basement slab and concrete pour
- Excavate pad foundations to proposed ground floor and install associated holding
down bolts in preparation for steelwork
- Complete internal damp-proofing works to basement walls
- Commence internal builders work and remove remaining load bearing walls:
including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors