2. Programme Update - ITS
For Period : Mon 7th December – Friday 18th December
- Completed external steelwork installation
- Completed installation of ground floor slab
- Commenced installation of external system scaffold around new steelwork structure
- Completed overboarding of existing ceilings to all floors within existing building
- Continued internal builders work within existing building
- Commenced internal plastering works to walls within existing building
10. Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete installation of external system scaffold around new steelwork structure
- Commence below ground brickwork
- Complete intumescent sprayed coating to external steel frame
- Complete new wall linings to basement
- Complete internal builders work within existing building
- Continue plastering works to walls and ceilings within existing building