BLD 165, Fall 2016
Northern Virginia Community College
Report Number 2
Ebenezer, Offei Boadi
Reston Town Center West
Commercial Township Development
September 1, 2016
Section 1
Project: Reston Town Center West
Location: 12100 Sunset Hills Road, Reston, VA 20191
Type of Construction: Commercial Township Development
Date of Visit: Thursday, September 1, 2016
Construction Company: L. F. Jennings, Inc.
Superintendent: Josh Beltran, Gary Parsons, Tim Jones
Estimated Value of Completion: $17 – 24 Million
Percentage of Completion: 30%
Expected Date of Substantial Completion: February 2018
Project Manager: James Godino
Architect: Matt Hopkins, Director – Streetsense Architecture
Weather: Rainy, 70 – 80s
Section 2
Site Access: The site is easily accessible from Tysons Corner Center merging onto VA-267
W/Dulles Toll Rd via EXIT 45 on the left toward Reston/Herndon/Dulles Airport. Take the VA-
602/Reston Pkwy exit, EXIT 12 where you slight right Reston Pkwy/VA-602 turning right onto
Sunset Hills Rd for about 0.49 miles reaches the site on your right. There is only one wide
construction entrance where equipment and deliveries are made through unto the site where they
turn around at the open area because the storage was about 670ft from the main construction.
Demolition and Site Clearing: There was no existing building on the site which was supposed
to be demolished for the new project to take place. The was no “buried city” found when
excavation took place. Since the area was already reserved for future development.
Protection of Adjacent Property: The project is surrounded by a standard construction fence and
notification signs were put in place starting from the walk way, the entrance and the fence itself.
Security has not been a problem because the site is surrounded by commercial buildings and
other construction sites.
Utility Availability (Temporary): The project had a fuel tanks installed in place for the heavy
machines and operating equipment which this was provided by the subcontractors.
Utility Availability (Permanent): Permanent power will be provided by BKY Electric
company, INC. There is an underground transformer located on Sunset Hills Rd. Alexandria,
Virginia. The duct bank has already been installed to the street and installed on the site for the
other existing buildings but they are waiting for the work to reach some stage for Doherty
Plumbing Co, INC. to connect the permanent service. Permanent water, sewer, sanitary, and
sprinkler service will be provided by the SSWR. Since the site is too small, there is no
communication services provided because the Superintendent is able to reach the subcontractors
with ease.
Surface Topography and Drainage: A large underground storm water management system was
put in place on the site. This system was designed to capture and treat the existing site as well as
planned future development on the site. Therefore, the necessary preventive measures had been
installed and put in place.
Subsurface Conditions: When excavation began, the contractor discovered that the soil was
suitable for backfill which was recognize in accordance to the geotechnical report. The
contractor did not import any treated control fill for the project and the excavated one disposed-
off site. Base on the soil type and the topography, the contractor adopted pad foundation and
introduce damp proof course around it as well as raising a footing for the structure to rest on.
Equipment: The site utilizes standard heavy equipment for excavation and setting large
components in place. Majority of the equipment is provided by the subcontractors where the
equipment is owned by the company.
Special Equipment: There were some special equipment on the job site like cranes.
Equipment filling station Ongoing construction
Stanchion installation Sewer
Storage area Road
Gas line Vehicular parking

More Related Content

What's hot

Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Crosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Crosstown TO
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Crosstown TO
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...Crosstown TO
 

What's hot (20)

Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
WALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom CompWALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom Comp
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
 

Similar to ste p rept 2

Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County
 
Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021Fairfax County
 
Oakton Community Park Phase 2A
Oakton Community Park Phase 2AOakton Community Park Phase 2A
Oakton Community Park Phase 2AFairfax County
 
Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021Fairfax County
 
Franconia at Westchester Drive Median Refuge
Franconia at Westchester Drive Median RefugeFranconia at Westchester Drive Median Refuge
Franconia at Westchester Drive Median RefugeFairfax County
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairFairfax County
 
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Fairfax County
 
Ici final project
Ici final projectIci final project
Ici final projectkongzc
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond ImprovementFairfax County
 
Chichester Lane Sidewalk Improvements
Chichester Lane Sidewalk ImprovementsChichester Lane Sidewalk Improvements
Chichester Lane Sidewalk ImprovementsFairfax County
 
Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016Fairfax County
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Fairfax County
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Graham Park Plaza Emergency Repair
Graham Park Plaza Emergency RepairGraham Park Plaza Emergency Repair
Graham Park Plaza Emergency RepairFairfax County
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairFairfax County
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Fairfax County
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationFairfax County
 
Gallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsGallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsFairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Brown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall ImprovementBrown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall ImprovementFairfax County
 

Similar to ste p rept 2 (20)

Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020
 
Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021
 
Oakton Community Park Phase 2A
Oakton Community Park Phase 2AOakton Community Park Phase 2A
Oakton Community Park Phase 2A
 
Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021
 
Franconia at Westchester Drive Median Refuge
Franconia at Westchester Drive Median RefugeFranconia at Westchester Drive Median Refuge
Franconia at Westchester Drive Median Refuge
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
 
Ici final project
Ici final projectIci final project
Ici final project
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond Improvement
 
Chichester Lane Sidewalk Improvements
Chichester Lane Sidewalk ImprovementsChichester Lane Sidewalk Improvements
Chichester Lane Sidewalk Improvements
 
Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Graham Park Plaza Emergency Repair
Graham Park Plaza Emergency RepairGraham Park Plaza Emergency Repair
Graham Park Plaza Emergency Repair
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall Restoration
 
Gallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsGallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue Improvements
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Brown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall ImprovementBrown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall Improvement
 

ste p rept 2

  • 1. BLD 165, Fall 2016 Northern Virginia Community College Report Number 2 Ebenezer, Offei Boadi Reston Town Center West Commercial Township Development September 1, 2016
  • 2. Section 1 Project: Reston Town Center West Location: 12100 Sunset Hills Road, Reston, VA 20191 Type of Construction: Commercial Township Development Date of Visit: Thursday, September 1, 2016 Construction Company: L. F. Jennings, Inc. Superintendent: Josh Beltran, Gary Parsons, Tim Jones Estimated Value of Completion: $17 – 24 Million Percentage of Completion: 30% Expected Date of Substantial Completion: February 2018 Project Manager: James Godino Architect: Matt Hopkins, Director – Streetsense Architecture Weather: Rainy, 70 – 80s
  • 3. Section 2 Site Access: The site is easily accessible from Tysons Corner Center merging onto VA-267 W/Dulles Toll Rd via EXIT 45 on the left toward Reston/Herndon/Dulles Airport. Take the VA- 602/Reston Pkwy exit, EXIT 12 where you slight right Reston Pkwy/VA-602 turning right onto Sunset Hills Rd for about 0.49 miles reaches the site on your right. There is only one wide construction entrance where equipment and deliveries are made through unto the site where they turn around at the open area because the storage was about 670ft from the main construction. Demolition and Site Clearing: There was no existing building on the site which was supposed to be demolished for the new project to take place. The was no “buried city” found when excavation took place. Since the area was already reserved for future development. Protection of Adjacent Property: The project is surrounded by a standard construction fence and notification signs were put in place starting from the walk way, the entrance and the fence itself. Security has not been a problem because the site is surrounded by commercial buildings and other construction sites. Utility Availability (Temporary): The project had a fuel tanks installed in place for the heavy machines and operating equipment which this was provided by the subcontractors. Utility Availability (Permanent): Permanent power will be provided by BKY Electric company, INC. There is an underground transformer located on Sunset Hills Rd. Alexandria, Virginia. The duct bank has already been installed to the street and installed on the site for the other existing buildings but they are waiting for the work to reach some stage for Doherty Plumbing Co, INC. to connect the permanent service. Permanent water, sewer, sanitary, and sprinkler service will be provided by the SSWR. Since the site is too small, there is no communication services provided because the Superintendent is able to reach the subcontractors with ease. Surface Topography and Drainage: A large underground storm water management system was put in place on the site. This system was designed to capture and treat the existing site as well as planned future development on the site. Therefore, the necessary preventive measures had been installed and put in place. Subsurface Conditions: When excavation began, the contractor discovered that the soil was suitable for backfill which was recognize in accordance to the geotechnical report. The contractor did not import any treated control fill for the project and the excavated one disposed- off site. Base on the soil type and the topography, the contractor adopted pad foundation and introduce damp proof course around it as well as raising a footing for the structure to rest on.
  • 4. Equipment: The site utilizes standard heavy equipment for excavation and setting large components in place. Majority of the equipment is provided by the subcontractors where the equipment is owned by the company. Special Equipment: There were some special equipment on the job site like cranes.
  • 5. Equipment filling station Ongoing construction Stanchion installation Sewer
  • 6. Storage area Road Gas line Vehicular parking