2. Programme Update - ITS
For Period : Mon 14th March – Friday 15th April
- Completed new dormer construction within roof and associated external render
- Completed Bauder roofing to new build structure and continued works to existing
re-roof
- Completed external brickwork to new-build structure & began stripping scaffold
- Completed floor screed pour to all floors and construction of internal lift shift
- Commenced internal partitions within new and existing buildings
- Commenced ceiling works to existing building & internal/external decorations
6. Progress Photos
Roof to new-build structure
complete and re-roofing to
existing building ongoing –
installation of new ‘Velux’
roof lights also commenced
8. Next Few Weeks………..
A look ahead to works commencing within the next 4 weeks :
- Commence installation of new passenger lift
- Complete works to existing re-roof and associated areas
- Continue 2nd fix joinery including hanging the doors throughout the existing building
- Complete necessary sub-station cabling works to energise new mains panel board
- Commence the installation of lighting within the existing building
- Commence installation of curtain walling/glazing to new build structure
- Continue internal decorations and complete all external decorations