SlideShare a Scribd company logo
CHAPTER 1
Introduction to Machine Maintenance
and Installation
• What is the place of Maintenance
Professionals in Industry?
Maintenance Planner
Sales Engineer
Maintenance Engineer
Technique Manager
• Which industries require the service of
maintenance professionals?
• All manufacturing industries:
 Metal industries
 Plastic factories
 Automotive industries
 Cement factories
 Lather and Lather Products
 Textile and Garment Factories
 Breweries
 Soft drink factories
 Alcohol and liquor factories
 Food processing industries
 Construction industries, etc.
• Service industries
 Hotels and Resorts
• What is Maintenance?
• Maintenance can be considered as a
combination of activities directed towards
preservation and restoration of the performance
of a facility, machine or equipment.
• Which comprises:
• service
• repair,
• replace, and
• modify components of a machine/equipment.
1. INTRODUCTION
• The main purposes of maintenance:
to eliminate system failures and hazards.
to ensure that equipment continues to work
within the design tolerances and
specifications.
to ensure the defined functions and standards
of operations of the plant are maintained, and
to ensure equipment are capable of being
performed for the required period.
1. INTRO. Cont.
Inadequate or lack of effective and efficient
maintenance system especially in a manufacturing
enterprise gives rise to several undesirable
consequences. These consequences include:
(i) Excessive machine breakdown
(ii) Frequent emergency maintenance work
(iii) Shortened life-span of the facility
(iv) Poor use of maintenance staff
(v) Loss in production output
(vi) Inability to meet delivery dates
(vii) Excessive overtime
1. INTRO. Cont.
Effect of Poor Maintenance
• The level of maintenance required at the
equipment operation stage is affected by
factors at other stages through which the
equipment passes. Theses are:
1. Design stage:
2. Installation stage:
3. Commissioning stage:
4. Operational stage:
1. INTRO. Cont.
1. Design stage:
Reliability and maintainability are the important factors
which should be considered properly in relation to
performance of equipment, capital and running costs.
2. Installation stage:
Maintainability is an important factor to be considered
during the installation, for it is here that maintenance
problems become clear.
3. Commissioning stage:
This is a stage of technical performance testing and also
a stage of where primary design faults are located and
designed out.
4. Operational stage:
The operational stage is a stage of learning where
maintenance plays an important role.
1. INTRO. Cont.
2. Basics of Machine Installation
2.1. General Procedure of Machine Installation
Installation procedure of a machine involves a
series of activities like:
a) Location and layout;
b) Positioning of machines;
c) Foundation;
d) Leveling and alignment;
e) Grouting;
f) Fitting of other parts, accessories, piping etc.;
g) Final leveling and test runs
a) Location and Layout
• The location of a machine depends on its purpose of
installation, definite types and sizes and other special
requirements, if any.
• For example, a centrifugal pump location should be as
close to the source of water as possible when suction lift is
present, or for a compressor location may be selected near
the particular shop where maximum air will be consumed
and at the same time a clear intake air will be available.
• Moreover the location plan should permit to have required
wide space all-around for continuing the erection work and
should facilitate regular inspection, repairing, etc.
• The location should also be finalized in such a fashion that
it will not disturb or obstruct the operation and
maintenance work of other nearby machines.
a) Location and Layout Cont.
• Once the location is finalized, the work of laying
out the foundation plan is to be undertaken.
• Laying out means marking of the foundation plan.
It may be done with the help of chalk on a
concrete floor and by a string with a number of
pegs.
• The general procedure is to indicate the outlines as
per specification of the machine.
• The axis lines are to be drawn both longitudinally
and crosswise to locate the center of foundation.
• Excavation of soil may be started only when the
layout is completed as per the requirement.
b) Positioning of Machines
• Positioning of the machine at the location is an important
job, which deserves care, skill an efficient teamwork.
• An equipment may have the weight of a few tons. But it is
to be loaded or unloaded, to be moved vertically or
horizontally to bring it at the site and to place it on the
foundation as well.
• Different types of lifting devices like pulley blocks, chain-
hoists, overhead cranes etc. may be used as per the
availability and requirement.
• When the load is light, rope pulley blocks are widely used
and chain pulley blocks may be useful, but for a very
heavy load, electric cranes are generally employed.
• However, the slinging should be done with much care to
avoid any impact shock, to avoid formation of any
scratches and breakages, etc.
b) Positioning of Machines Cont.
• For a machine of about 2 tones, hemp rope or
Manila rope of diameter about 4 to 5 cm may be
used instead of chains, wooden blocks and felts
should be interposed between rope and the
machine, to avoid damage to the finishing.
• Care must be taken to sling the machine upright
with weight distributed evenly. Thus, the efficient
fixing and passing of ropes or ‘chains’ through the
machine structure deserves skill and experience.
• Two typical slinging diagram (Fig. 1: a & b) are
given for a lathe and a vertical milling machine
respectively to explain the complicacies of
slinging.
Figure1. (a) Slinging a Center Lathe; (b) Slinging a Universal Milling Machine.
c) Foundation
• The shapes and sizes of the foundation differ according
to the type and size of the machines.
• They are also dependent on the property of the subsoil
and the dynamic loads of the machine during operation.
• If the weight of the installed machine is not too much
or if the dynamic loads are insignificant, the size of the
foundation may be finalized on the basis of design
considerations.
• But when the dynamic loads predominant, the
foundation should also serve the purpose to protect the
machine from external vibration and to lower down the
frequency of natural vibration by increasing its total
mass.
c) Foundation Cont.
Dynamic and Static Loads
•For example, for a rotary machine, the following empirical
formula may be used to find out the equivalent static load
(Pstatic):
Pstatic = G/g.e. (Πn/30)2
kdynamic
Where G = Weight of rotating masses.
g = acceleration due to gravity.
e = eccentricity of rotating masses.
n = Speed of the work-piece.
and ‘kdynamic ‘ is the dynamic co-efficient generally taken as
1.5 to 2.
•For a reciprocating machine, the general practice is to take
the equivalent static force as five or six times the value of
cutting force.
c) Foundation Cont.
• The dimensions of the foundation block may be determined, primarily
finding out the weight of the foundation (WF) with the following
empirical formula:
• WF = KF.WM
• Where, KF is a factor, commonly taken as 2.3 for the machine tools
with dynamic load and WM is the weight of the ‘machine tool’.
• The height of the foundation = Weight of the foundation (WF) / Area
of the base of foundation X Specific weight of material.
• Of course, the height, so calculated should be sufficient enough to
accommodate the foundation bolts etc.
• The width and length of the foundation can be suitably calculated
considering the foundation drawing, its height and weight.
• Normally, it is recommended that as far as possible, the foundation
should be so dimensioned that the resultant force due to the mass of
the machine and the mass of the foundation passes through the center
of gravity of the basic contact area, especially for a rotary machine.
c) Foundation Cont.
Other Design Criteria for Foundation
•Besides the dimensions, as stated above, some other
criteria are also considered for suitable foundation work.
i. Ground Condition
•The nature of soil is obviously a vital criterion. For a hard
soil or for a normal soil, the construction of a concrete bed
does not entangle too many complicacies. It is rather most
straightforward to consider the foundation plan supplied by
the manufacturer.
•But, for soft and loose soil, a large surface area with
proper depth is needed for the foundation of a machine.
• The problems encountered due to vibration may force to
construct a concrete raft (1) on piles (2), as shown in Figure
2.
c) Foundation Cont.
Figure 2: (a) Raft on Piles; (b) Bondage of Raft with Pile.
• The main structure of the machine is erected on the piles.
The piles should have a stable and rigid bond with the raft as
shown separately in the Figure 2b.
• The bond may be a reinforced concrete having a steel-rod
within it.
• For water-logged soils also, mostly the pile driven raft
construction is the means to avoid problems due to
subsidence of soil.
Vibration Consideration
•To avoid transmission of vibration to adjoining parts of buildings or
other foundations, it is necessary to provide a suitable isolation
between the equipment foundation and the joining structure.
•Usually a gap is maintained all around the foundation (like a
trench), and is filled by sand to avoid such transmission of vibration.
•Any vibration isolating material, other than sand, such as rubber,
lead sheet, felt etc. may also be used.
•As a rule, the equipment foundation shall not be allowed to serve as
support for other structures or for machineries not related to the
particular equipment.
•The impact type machines, like stamping press, drop and forging
hammer, need special care during foundation. The depth of the
foundation becomes very large to make the foundation heavy.
c) Foundation Cont.
c) Foundation Cont.
• Figure 3a shows a sand-filled trench all-around the concrete
foundation block. Such a foundation design reduces vibration
transmission.
• Figure 3b shows that the foundation block is placed on some
inserts, below which the concrete (reinforced concrete) base is
there.
• The air gap is maintained all-around and at the same time there is
an elastic support (to provide cushioning effect) in between the
foundation block and the equipment.
• Such a design avoids vibration transmission and absorbs shock as
well. The soft inserts may be cork or timber sleepers etc.
Figure 3: (a) Sand-filled
trench around
foundation; (b) Soft
insert below foundation
block.
c) Foundation Cont.
Foundation bolts
•To install the machineries, foundation bolts will be specified and
supplied by the manufacturers. Some of the foundation bolts become
rigid on pouring concrete and some may be removable and adjustable
bolts.
•A few type of foundation bolts, very commonly used, are discussed
below.
Eye foundation bolts
•They are generally made of mild steel or wrought-iron and can be
readily forged according to the size. They are very much suitable to
use for fastening the lids to tanks etc. (Fig. 4).
Figure 4: Eye Foundation Bolt.
c) Foundation Cont.
Rag bolt
•Rag bolts (Fig. 5a) are rectangular in cross-section but the width of
the rectangle increases gradually. They are having an indented or
grooved edge.
•After suspension of the bolts, the gap around them may be filled-up
with molten lead.
•Such bolts cannot be removed easily after grouting.
Lewis bolt
•Such bolts can be removed easily, as a tapered key (1) is fitted
through the side of the bolts to make it rigid.
•It may be noted that the key is fitted on the straight face of the bolt
body. (Fig. 5b)
Figure 5: (a) Rag
bolt; (b) Lewis
bolt.
c) Foundation Cont.
Cotter bolt
•To install heavy-machines, ‘cottered bolts’ are commonly used (Fig. 6a).
•A hand hold must be provided in the foundation block for the insertion of
the cotter (1).
•The bolt possesses a rectangular slot to receive the cotter. A cast-iron
washer (2) is also used as a bearing surface of the cotter.
Split end bolts
•The end of theses bolts are made splitted. The bent split facilitates a rigid
fixing of a bolt.
•Such bolts are mostly used for medium-size machine tools. (Figure 6b).
Figure 6: (a) Cotter
bolt; (b) Split end bolt.
c) Foundation Cont.
Major activities of foundation work
•The foundation involves the activities like digging-up the soil
(excavation), positioning of foundation bolts, concrete mixture
pouring and setting.
•Suppose the foundation plan of a ‘center lathe’ is supplied by the
manufacturer as shown in Figure (5.7) with proper dimensioning.
Figure 7:
Foundation plan of
a ‘center lathe’.
c) Foundation Cont.
• The erection work is undertaken mostly when the foundation
block has been set in and hardened.
• The machine tool is placed on the foundation with the help of
spacers or pads, leveling wedges, etc.
• Foundation plates are also supported similarly, for different
machines etc. At this time, a gap (minimum 50 to 70mm)
depending on the type of the machine is maintained between
the top of the foundation block and the bottom of the
machine or base plate.
• The foundation bolts are positioned before positioning the
machine and the exact location of the machine is guided by
the insertion of the projected foundation-bolt ends through
the holes, provided at the machine footings or base plate.
• The bolt-ends should remain sufficiently projected to
accommodate the washers and nuts as well.
d) Leveling and Alignment
• After having the machine on the foundation, the
important job is to level and align it with other
accessories.
• The leveling is performed with leveling wedges,
shoes etc. as stated before.
• The horizontal and slight vertical movements of the
heavy mass of machine is performed by pipes,
rollers as shown in Fig. 9a or using pinch bars (Fig.
9b).
• Straight edge, spiral level, dial indicator etc., are
generally useful instruments to level the machine.
• The leveling is to be checked in the both,
longitudinal and transverse direction.
Figure 9: (a) Rolling of Load, (b) Lifting of Load.
d) Leveling Cont.
• The parallelity, perpendicularity of different faces, axes
should be leveled and aligned, as are required.
• When leveling is completed, the foundation bolt cavity
along with the bolt may be made concreted. Pouring of
cement concrete is generally made through the gap
provided at the top of the foundation, as shown in Fig.
10.
• This concreting will provide a bondage of the
foundation bolts with the foundation block while
performing grouting, discussed later.
• Whenever, the foundation block is continuously made
for a connected accessory, (say, the alternator with the
turbine) the relative alignment should be established
before concreting the foundation bolts.
Figure 10: Pouring concrete in bolt cavity.
d) Grouting
• Grouting is a procedure of connecting the machine with the
foundation by a concrete mixture of plastic consistency or
cement mortar. It is extensively used in installing most of the
machines.
• Generally, a quick setting cement is used to perform grouting.
The top of the foundation block is made roughned, made
moistened with water and wooden partitions are placed all-
around the machine.
• The heights of such wooden boards are kept much higher than
the gap between the top or the foundation and the bottom of the
machine.
• Quick setting cement is then poured within the boundary with
care to eliminate any air gap within it.
• Once started, the pouring should be completed continuously and
the machine must be felt undisturbed for a few days after
grouting to provide it time to set.
e) Fitting of other parts
• When the machine is erected, the other
accessories may be joined accordingly.
• But, while laying out the foundation plan, the
overall requirement should be kept in mind.
• The auxiliary structures e.g. in case of a heavy-
duty diesel engine foundation, the structures for
outer bearing pedestal, water pump blocks etc.
should be planned at a time.
• This will minimize the problem of internal
fittings.
f) Final leveling and test runs
• Accurate leveling can be carried out only when
the grouting has set in after a few days.
• The machine is to be made cleaned and leveled
then. Such leveling involves minor adjustments.
• Whenever provided, the leveling screws as shown
in Fig. 7. may be operated to achieve the final
level.
• Everything should now be made ready to carry the
test run. The style of testing will differ from
machine to machine.
• For instance, for metal-cutting machine tools, they
are always sent out with a test chart.
f) Final leveling Cont.
• ‘Test chart’ may be defined as the specification
of accuracies of major typical points like
‘straightness of guide ways’ ‘Trueness of
spindles’ etc. which should exist for the desired
functioning of the respective machines.
• The accuracy shown in the chart will be re-
obtained only if the machine is correctly erected
and leveled.
End of Chapter One

More Related Content

What's hot

Design for assembly methods
Design for assembly methodsDesign for assembly methods
Design for assembly methods
aman1312
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
TAMILMECHKIT
 
Manufacturing Technology -II Unit 2
Manufacturing Technology -II Unit 2Manufacturing Technology -II Unit 2
Manufacturing Technology -II Unit 2
Ravi Sankar
 
Mechanical install
Mechanical installMechanical install
Mechanical install
shyamadhikary123
 
Milling Fixture
Milling FixtureMilling Fixture
Milling Fixture
Amruta Rane
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centers
RAHUL THAKER
 
Cnc axis and motion nomenclature
Cnc axis and motion nomenclatureCnc axis and motion nomenclature
Cnc axis and motion nomenclature
meet shah
 
Drill bushes
Drill bushesDrill bushes
Drill bushes
Amruta Rane
 
3.cutting tools nomenclature
3.cutting tools nomenclature3.cutting tools nomenclature
3.cutting tools nomenclature
Prashant Mulge 8095548003
 
Engineering Drawing basics.ppt
Engineering Drawing basics.pptEngineering Drawing basics.ppt
Engineering Drawing basics.ppt
DIEMS Aurangabad
 
Limit Gauges
Limit GaugesLimit Gauges
Limit Gauges
taruian
 
Cad cam input output devices
Cad cam input output devicesCad cam input output devices
Cad cam input output devices
Jagilam Kumar
 
Jigs and Fixture
Jigs and FixtureJigs and Fixture
Jigs and Fixture
Kondayya Devarakonda
 
COMPUTER AIDED MACHINE DRAWING LAB MANUAL
COMPUTER AIDED MACHINE DRAWING LAB MANUALCOMPUTER AIDED MACHINE DRAWING LAB MANUAL
COMPUTER AIDED MACHINE DRAWING LAB MANUAL
ASHOK KUMAR RAJENDRAN
 
Capston and turrent lathe
Capston and turrent latheCapston and turrent lathe
Capston and turrent lathe
Yuga Aravind Kumar
 
Milling & Gear Cutting
Milling & Gear CuttingMilling & Gear Cutting
Milling & Gear Cutting
Konal Singh
 
Mechanical CNC machine
Mechanical CNC machineMechanical CNC machine
Mechanical CNC machine
Digitech Rathod
 
Machine elements
Machine elementsMachine elements
Machine elements
AISSMS IOIT,PUNE
 
Uint 1 locating and clamping devices
Uint 1 locating and clamping devicesUint 1 locating and clamping devices
Uint 1 locating and clamping devices
S.DHARANI KUMAR
 
Fluid power introduction
Fluid power introductionFluid power introduction
Fluid power introduction
sukusobhaa
 

What's hot (20)

Design for assembly methods
Design for assembly methodsDesign for assembly methods
Design for assembly methods
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 
Manufacturing Technology -II Unit 2
Manufacturing Technology -II Unit 2Manufacturing Technology -II Unit 2
Manufacturing Technology -II Unit 2
 
Mechanical install
Mechanical installMechanical install
Mechanical install
 
Milling Fixture
Milling FixtureMilling Fixture
Milling Fixture
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centers
 
Cnc axis and motion nomenclature
Cnc axis and motion nomenclatureCnc axis and motion nomenclature
Cnc axis and motion nomenclature
 
Drill bushes
Drill bushesDrill bushes
Drill bushes
 
3.cutting tools nomenclature
3.cutting tools nomenclature3.cutting tools nomenclature
3.cutting tools nomenclature
 
Engineering Drawing basics.ppt
Engineering Drawing basics.pptEngineering Drawing basics.ppt
Engineering Drawing basics.ppt
 
Limit Gauges
Limit GaugesLimit Gauges
Limit Gauges
 
Cad cam input output devices
Cad cam input output devicesCad cam input output devices
Cad cam input output devices
 
Jigs and Fixture
Jigs and FixtureJigs and Fixture
Jigs and Fixture
 
COMPUTER AIDED MACHINE DRAWING LAB MANUAL
COMPUTER AIDED MACHINE DRAWING LAB MANUALCOMPUTER AIDED MACHINE DRAWING LAB MANUAL
COMPUTER AIDED MACHINE DRAWING LAB MANUAL
 
Capston and turrent lathe
Capston and turrent latheCapston and turrent lathe
Capston and turrent lathe
 
Milling & Gear Cutting
Milling & Gear CuttingMilling & Gear Cutting
Milling & Gear Cutting
 
Mechanical CNC machine
Mechanical CNC machineMechanical CNC machine
Mechanical CNC machine
 
Machine elements
Machine elementsMachine elements
Machine elements
 
Uint 1 locating and clamping devices
Uint 1 locating and clamping devicesUint 1 locating and clamping devices
Uint 1 locating and clamping devices
 
Fluid power introduction
Fluid power introductionFluid power introduction
Fluid power introduction
 

Similar to Introduction to machine maintinance and installation

Precast elements
Precast elementsPrecast elements
Precast elements
Shrividhyah
 
Precast elements
Precast elementsPrecast elements
Precast elements
Shrividhyah
 
Unit-2 [Dynamic Equipment Foundation].pdf
Unit-2 [Dynamic Equipment Foundation].pdfUnit-2 [Dynamic Equipment Foundation].pdf
Unit-2 [Dynamic Equipment Foundation].pdf
Sanjivani College of Engineering, Kopargaon
 
Chapter 9 Machine Installation in maintenance.ppt
Chapter 9 Machine Installation in maintenance.pptChapter 9 Machine Installation in maintenance.ppt
Chapter 9 Machine Installation in maintenance.ppt
AbeyuAssefa
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
usamazahoor159
 
Site report
Site reportSite report
Site report
Tee Joanne
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
ManviVarshney2
 
Construction Equipment and other details .pptx
Construction Equipment and other details .pptxConstruction Equipment and other details .pptx
Construction Equipment and other details .pptx
M Ariful Islam
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
Anees Khan
 
Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptx
charantinku6799
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
AJAY SHAHU
 
Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)
Construction Tech. and Mgmt., VNIT Nagpur
 
Design Principles
Design PrinciplesDesign Principles
Design Principles
Nishma2
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
SAGAR RAUT
 
Mechanised construction
Mechanised constructionMechanised construction
Mechanised construction
MANUJ sinh
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
ssuseref23d3
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
GourhariBiswas1
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Muhammad Umar
 
Construction Equipments.ppt
Construction Equipments.pptConstruction Equipments.ppt
Construction Equipments.ppt
VinayakNaik80
 

Similar to Introduction to machine maintinance and installation (20)

Precast elements
Precast elementsPrecast elements
Precast elements
 
Precast elements
Precast elementsPrecast elements
Precast elements
 
Unit-2 [Dynamic Equipment Foundation].pdf
Unit-2 [Dynamic Equipment Foundation].pdfUnit-2 [Dynamic Equipment Foundation].pdf
Unit-2 [Dynamic Equipment Foundation].pdf
 
Chapter 9 Machine Installation in maintenance.ppt
Chapter 9 Machine Installation in maintenance.pptChapter 9 Machine Installation in maintenance.ppt
Chapter 9 Machine Installation in maintenance.ppt
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
 
Site report
Site reportSite report
Site report
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Construction Equipment and other details .pptx
Construction Equipment and other details .pptxConstruction Equipment and other details .pptx
Construction Equipment and other details .pptx
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptx
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)
 
Design Principles
Design PrinciplesDesign Principles
Design Principles
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Mechanised construction
Mechanised constructionMechanised construction
Mechanised construction
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
 
Construction Equipments.ppt
Construction Equipments.pptConstruction Equipments.ppt
Construction Equipments.ppt
 

Recently uploaded

Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 

Recently uploaded (20)

Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 

Introduction to machine maintinance and installation

  • 1. CHAPTER 1 Introduction to Machine Maintenance and Installation
  • 2. • What is the place of Maintenance Professionals in Industry? Maintenance Planner Sales Engineer Maintenance Engineer Technique Manager
  • 3. • Which industries require the service of maintenance professionals? • All manufacturing industries:  Metal industries  Plastic factories  Automotive industries  Cement factories  Lather and Lather Products  Textile and Garment Factories  Breweries  Soft drink factories  Alcohol and liquor factories  Food processing industries  Construction industries, etc. • Service industries  Hotels and Resorts
  • 4. • What is Maintenance? • Maintenance can be considered as a combination of activities directed towards preservation and restoration of the performance of a facility, machine or equipment. • Which comprises: • service • repair, • replace, and • modify components of a machine/equipment. 1. INTRODUCTION
  • 5. • The main purposes of maintenance: to eliminate system failures and hazards. to ensure that equipment continues to work within the design tolerances and specifications. to ensure the defined functions and standards of operations of the plant are maintained, and to ensure equipment are capable of being performed for the required period. 1. INTRO. Cont.
  • 6. Inadequate or lack of effective and efficient maintenance system especially in a manufacturing enterprise gives rise to several undesirable consequences. These consequences include: (i) Excessive machine breakdown (ii) Frequent emergency maintenance work (iii) Shortened life-span of the facility (iv) Poor use of maintenance staff (v) Loss in production output (vi) Inability to meet delivery dates (vii) Excessive overtime 1. INTRO. Cont. Effect of Poor Maintenance
  • 7. • The level of maintenance required at the equipment operation stage is affected by factors at other stages through which the equipment passes. Theses are: 1. Design stage: 2. Installation stage: 3. Commissioning stage: 4. Operational stage: 1. INTRO. Cont.
  • 8. 1. Design stage: Reliability and maintainability are the important factors which should be considered properly in relation to performance of equipment, capital and running costs. 2. Installation stage: Maintainability is an important factor to be considered during the installation, for it is here that maintenance problems become clear. 3. Commissioning stage: This is a stage of technical performance testing and also a stage of where primary design faults are located and designed out. 4. Operational stage: The operational stage is a stage of learning where maintenance plays an important role. 1. INTRO. Cont.
  • 9. 2. Basics of Machine Installation 2.1. General Procedure of Machine Installation Installation procedure of a machine involves a series of activities like: a) Location and layout; b) Positioning of machines; c) Foundation; d) Leveling and alignment; e) Grouting; f) Fitting of other parts, accessories, piping etc.; g) Final leveling and test runs
  • 10. a) Location and Layout • The location of a machine depends on its purpose of installation, definite types and sizes and other special requirements, if any. • For example, a centrifugal pump location should be as close to the source of water as possible when suction lift is present, or for a compressor location may be selected near the particular shop where maximum air will be consumed and at the same time a clear intake air will be available. • Moreover the location plan should permit to have required wide space all-around for continuing the erection work and should facilitate regular inspection, repairing, etc. • The location should also be finalized in such a fashion that it will not disturb or obstruct the operation and maintenance work of other nearby machines.
  • 11. a) Location and Layout Cont. • Once the location is finalized, the work of laying out the foundation plan is to be undertaken. • Laying out means marking of the foundation plan. It may be done with the help of chalk on a concrete floor and by a string with a number of pegs. • The general procedure is to indicate the outlines as per specification of the machine. • The axis lines are to be drawn both longitudinally and crosswise to locate the center of foundation. • Excavation of soil may be started only when the layout is completed as per the requirement.
  • 12. b) Positioning of Machines • Positioning of the machine at the location is an important job, which deserves care, skill an efficient teamwork. • An equipment may have the weight of a few tons. But it is to be loaded or unloaded, to be moved vertically or horizontally to bring it at the site and to place it on the foundation as well. • Different types of lifting devices like pulley blocks, chain- hoists, overhead cranes etc. may be used as per the availability and requirement. • When the load is light, rope pulley blocks are widely used and chain pulley blocks may be useful, but for a very heavy load, electric cranes are generally employed. • However, the slinging should be done with much care to avoid any impact shock, to avoid formation of any scratches and breakages, etc.
  • 13. b) Positioning of Machines Cont. • For a machine of about 2 tones, hemp rope or Manila rope of diameter about 4 to 5 cm may be used instead of chains, wooden blocks and felts should be interposed between rope and the machine, to avoid damage to the finishing. • Care must be taken to sling the machine upright with weight distributed evenly. Thus, the efficient fixing and passing of ropes or ‘chains’ through the machine structure deserves skill and experience. • Two typical slinging diagram (Fig. 1: a & b) are given for a lathe and a vertical milling machine respectively to explain the complicacies of slinging.
  • 14. Figure1. (a) Slinging a Center Lathe; (b) Slinging a Universal Milling Machine.
  • 15. c) Foundation • The shapes and sizes of the foundation differ according to the type and size of the machines. • They are also dependent on the property of the subsoil and the dynamic loads of the machine during operation. • If the weight of the installed machine is not too much or if the dynamic loads are insignificant, the size of the foundation may be finalized on the basis of design considerations. • But when the dynamic loads predominant, the foundation should also serve the purpose to protect the machine from external vibration and to lower down the frequency of natural vibration by increasing its total mass.
  • 16. c) Foundation Cont. Dynamic and Static Loads •For example, for a rotary machine, the following empirical formula may be used to find out the equivalent static load (Pstatic): Pstatic = G/g.e. (Πn/30)2 kdynamic Where G = Weight of rotating masses. g = acceleration due to gravity. e = eccentricity of rotating masses. n = Speed of the work-piece. and ‘kdynamic ‘ is the dynamic co-efficient generally taken as 1.5 to 2. •For a reciprocating machine, the general practice is to take the equivalent static force as five or six times the value of cutting force.
  • 17. c) Foundation Cont. • The dimensions of the foundation block may be determined, primarily finding out the weight of the foundation (WF) with the following empirical formula: • WF = KF.WM • Where, KF is a factor, commonly taken as 2.3 for the machine tools with dynamic load and WM is the weight of the ‘machine tool’. • The height of the foundation = Weight of the foundation (WF) / Area of the base of foundation X Specific weight of material. • Of course, the height, so calculated should be sufficient enough to accommodate the foundation bolts etc. • The width and length of the foundation can be suitably calculated considering the foundation drawing, its height and weight. • Normally, it is recommended that as far as possible, the foundation should be so dimensioned that the resultant force due to the mass of the machine and the mass of the foundation passes through the center of gravity of the basic contact area, especially for a rotary machine.
  • 18. c) Foundation Cont. Other Design Criteria for Foundation •Besides the dimensions, as stated above, some other criteria are also considered for suitable foundation work. i. Ground Condition •The nature of soil is obviously a vital criterion. For a hard soil or for a normal soil, the construction of a concrete bed does not entangle too many complicacies. It is rather most straightforward to consider the foundation plan supplied by the manufacturer. •But, for soft and loose soil, a large surface area with proper depth is needed for the foundation of a machine.
  • 19. • The problems encountered due to vibration may force to construct a concrete raft (1) on piles (2), as shown in Figure 2. c) Foundation Cont. Figure 2: (a) Raft on Piles; (b) Bondage of Raft with Pile. • The main structure of the machine is erected on the piles. The piles should have a stable and rigid bond with the raft as shown separately in the Figure 2b. • The bond may be a reinforced concrete having a steel-rod within it. • For water-logged soils also, mostly the pile driven raft construction is the means to avoid problems due to subsidence of soil.
  • 20. Vibration Consideration •To avoid transmission of vibration to adjoining parts of buildings or other foundations, it is necessary to provide a suitable isolation between the equipment foundation and the joining structure. •Usually a gap is maintained all around the foundation (like a trench), and is filled by sand to avoid such transmission of vibration. •Any vibration isolating material, other than sand, such as rubber, lead sheet, felt etc. may also be used. •As a rule, the equipment foundation shall not be allowed to serve as support for other structures or for machineries not related to the particular equipment. •The impact type machines, like stamping press, drop and forging hammer, need special care during foundation. The depth of the foundation becomes very large to make the foundation heavy. c) Foundation Cont.
  • 21. c) Foundation Cont. • Figure 3a shows a sand-filled trench all-around the concrete foundation block. Such a foundation design reduces vibration transmission. • Figure 3b shows that the foundation block is placed on some inserts, below which the concrete (reinforced concrete) base is there. • The air gap is maintained all-around and at the same time there is an elastic support (to provide cushioning effect) in between the foundation block and the equipment. • Such a design avoids vibration transmission and absorbs shock as well. The soft inserts may be cork or timber sleepers etc. Figure 3: (a) Sand-filled trench around foundation; (b) Soft insert below foundation block.
  • 22. c) Foundation Cont. Foundation bolts •To install the machineries, foundation bolts will be specified and supplied by the manufacturers. Some of the foundation bolts become rigid on pouring concrete and some may be removable and adjustable bolts. •A few type of foundation bolts, very commonly used, are discussed below. Eye foundation bolts •They are generally made of mild steel or wrought-iron and can be readily forged according to the size. They are very much suitable to use for fastening the lids to tanks etc. (Fig. 4). Figure 4: Eye Foundation Bolt.
  • 23. c) Foundation Cont. Rag bolt •Rag bolts (Fig. 5a) are rectangular in cross-section but the width of the rectangle increases gradually. They are having an indented or grooved edge. •After suspension of the bolts, the gap around them may be filled-up with molten lead. •Such bolts cannot be removed easily after grouting. Lewis bolt •Such bolts can be removed easily, as a tapered key (1) is fitted through the side of the bolts to make it rigid. •It may be noted that the key is fitted on the straight face of the bolt body. (Fig. 5b) Figure 5: (a) Rag bolt; (b) Lewis bolt.
  • 24. c) Foundation Cont. Cotter bolt •To install heavy-machines, ‘cottered bolts’ are commonly used (Fig. 6a). •A hand hold must be provided in the foundation block for the insertion of the cotter (1). •The bolt possesses a rectangular slot to receive the cotter. A cast-iron washer (2) is also used as a bearing surface of the cotter. Split end bolts •The end of theses bolts are made splitted. The bent split facilitates a rigid fixing of a bolt. •Such bolts are mostly used for medium-size machine tools. (Figure 6b). Figure 6: (a) Cotter bolt; (b) Split end bolt.
  • 25. c) Foundation Cont. Major activities of foundation work •The foundation involves the activities like digging-up the soil (excavation), positioning of foundation bolts, concrete mixture pouring and setting. •Suppose the foundation plan of a ‘center lathe’ is supplied by the manufacturer as shown in Figure (5.7) with proper dimensioning. Figure 7: Foundation plan of a ‘center lathe’.
  • 26. c) Foundation Cont. • The erection work is undertaken mostly when the foundation block has been set in and hardened. • The machine tool is placed on the foundation with the help of spacers or pads, leveling wedges, etc. • Foundation plates are also supported similarly, for different machines etc. At this time, a gap (minimum 50 to 70mm) depending on the type of the machine is maintained between the top of the foundation block and the bottom of the machine or base plate. • The foundation bolts are positioned before positioning the machine and the exact location of the machine is guided by the insertion of the projected foundation-bolt ends through the holes, provided at the machine footings or base plate. • The bolt-ends should remain sufficiently projected to accommodate the washers and nuts as well.
  • 27. d) Leveling and Alignment • After having the machine on the foundation, the important job is to level and align it with other accessories. • The leveling is performed with leveling wedges, shoes etc. as stated before. • The horizontal and slight vertical movements of the heavy mass of machine is performed by pipes, rollers as shown in Fig. 9a or using pinch bars (Fig. 9b). • Straight edge, spiral level, dial indicator etc., are generally useful instruments to level the machine. • The leveling is to be checked in the both, longitudinal and transverse direction.
  • 28. Figure 9: (a) Rolling of Load, (b) Lifting of Load.
  • 29. d) Leveling Cont. • The parallelity, perpendicularity of different faces, axes should be leveled and aligned, as are required. • When leveling is completed, the foundation bolt cavity along with the bolt may be made concreted. Pouring of cement concrete is generally made through the gap provided at the top of the foundation, as shown in Fig. 10. • This concreting will provide a bondage of the foundation bolts with the foundation block while performing grouting, discussed later. • Whenever, the foundation block is continuously made for a connected accessory, (say, the alternator with the turbine) the relative alignment should be established before concreting the foundation bolts.
  • 30. Figure 10: Pouring concrete in bolt cavity.
  • 31. d) Grouting • Grouting is a procedure of connecting the machine with the foundation by a concrete mixture of plastic consistency or cement mortar. It is extensively used in installing most of the machines. • Generally, a quick setting cement is used to perform grouting. The top of the foundation block is made roughned, made moistened with water and wooden partitions are placed all- around the machine. • The heights of such wooden boards are kept much higher than the gap between the top or the foundation and the bottom of the machine. • Quick setting cement is then poured within the boundary with care to eliminate any air gap within it. • Once started, the pouring should be completed continuously and the machine must be felt undisturbed for a few days after grouting to provide it time to set.
  • 32. e) Fitting of other parts • When the machine is erected, the other accessories may be joined accordingly. • But, while laying out the foundation plan, the overall requirement should be kept in mind. • The auxiliary structures e.g. in case of a heavy- duty diesel engine foundation, the structures for outer bearing pedestal, water pump blocks etc. should be planned at a time. • This will minimize the problem of internal fittings.
  • 33. f) Final leveling and test runs • Accurate leveling can be carried out only when the grouting has set in after a few days. • The machine is to be made cleaned and leveled then. Such leveling involves minor adjustments. • Whenever provided, the leveling screws as shown in Fig. 7. may be operated to achieve the final level. • Everything should now be made ready to carry the test run. The style of testing will differ from machine to machine. • For instance, for metal-cutting machine tools, they are always sent out with a test chart.
  • 34. f) Final leveling Cont. • ‘Test chart’ may be defined as the specification of accuracies of major typical points like ‘straightness of guide ways’ ‘Trueness of spindles’ etc. which should exist for the desired functioning of the respective machines. • The accuracy shown in the chart will be re- obtained only if the machine is correctly erected and leveled.