Mechanical Installation
Page -1-
1. INTRODUCTION AND PURPOSE
1.1. This specification covers the installation, testing and pre-
commissioning of mechanical equipment. Work is to be performed
in conjunction with the manufacturer’s instructions, standard
industrial practices, and relevant codes and standards.
1.2. The electrical/instrumentation installation work is identified in a
separate document. The mechanical work shall be coordinated
with the electrical/instrumentation work to provide a complete and
operable system.
1.3. Whenever conflicts exist between the manufacturer’s instructions,
this Specification, other specifications, the drawings, or codes, the
OWNER Construction Manager shall be notified and shall provide
the final resolution.
2. CODES AND STANDARDS
All equipment shall be installed in accordance with, but not limited to, the
latest editions and applicable provisions of the following codes, laws,
regulations, and standards.
2.1. Codes, Laws, and Regulations
2.1.1. Mine Safety and Health Administration (MSHA)
2.1.2. Standard Building Code (SBC)
2.1.3. Standard Fire Prevention Code (SFPC)
2.1.4. Standard Mechanical Code (SMC)
2.1.5. USA Environmental Protection Agency (EPA)
2.1.6. All state and local laws and ordinances.
2.1.7. All other applicable codes, laws, and regulations.
2.2. Standards
2.2.1. American Institute of Steel Construction (AISC)
2.2.2. American Iron and Steel Institute (AISI)
2.2.3. American National Standards Institute (ANSI)
2.2.4. American Society of Mechanical Engineers (ASME)
2.2.5. American Society for Testing and Materials (ASTM)
2.2.6. American Welding Society (AWS)
Mechanical Installation
Page -2-
2.2.7. National Electrical Code (NEC)
2.2.8. Steel Structures Painting Council (SSPC)
2.2.9. All other applicable standards.
3. GENERAL REQUIREMENTS
3.1. The Contractor shall provide supervision, labor, equipment,
materials, tools, and supplies unless specifically noted as being
provided by others, to perform the work described herein in
accordance with this document and the referenced specification,
drawings, and related documents. Work not specifically shown on
the drawings or enumerated herein but that is reasonably
necessary for the proper completion of the contract shall be
provided by the Contractor the same as if shown on the drawings or
enumerated herein.
3.2. The mechanical equipment shall be installed in accordance with all
applicable federal, state and local codes, standards, rules,
regulations, and laws including, but not limited to, the codes and
standards referenced in Section 2 of this Specification.
3.3. Unload OWNER furnished equipment and materials. Load and
transport equipment and materials from the storage area to the
installation location.
3.4. Install all the equipment shown on the drawings or as noted in other
contract documents.
3.5. Equipment installation shall include the supply and placement of
grout for equipment or materials and the supply and installation of
anchors and fasteners as required for a complete installation.
3.6. Motor driven equipment placement shall include alignment,
assembly of belts, sheaves, couplings, guards, etc. as required for
a complete installation.
3.7. The Contractor shall inspect the location for the equipment to be
installed prior to beginning installation to insure readiness of area
including anchor bolt locations, size, projections and placement of
support steel where applicable.
3.8. Work in an area shall be coordinated through the OWNER
Construction Manager. No installation of equipment shall be
installed without release of the area for such installation.
Mechanical Installation
Page -3-
3.9. All materials and equipment furnished by the Contractor shall be in
accordance with the specifications. Substitution of any materials
deviating from the specifications and drawings shall be approved in
writing by OWNER. A description of Contractor supplied
substituted material shall be submitted to the OWNER Construction
Manager for approval.
3.10. The Contractor is responsible to alter the drawing dimensions
affected by using different approved items where applicable. Any
such dimensional changes shall be submitted on “As-Built”
drawings.
4. INSTALLATION REQUIREMENTS
4.1. The Contractor shall read and understand the manufacturer’s
installation requirements prior to beginning the installation of the
equipment.
4.2. Equipment shall only be lifted and handled in accordance with the
manufacturer’s instructions and at points and locations designated
for such handling.
4.3. Before installation, all parts shall be thoroughly cleaned of all rust,
grit and foreign matter. Where accessible without disassembly, all
holes and grooves for lubrication shall be examined and cleaned
where necessary. Bolts and screws shall be tightened uniformly
without over-stressing the threads. Anchor bolts shall be
adequately tightened, and all other bolts shall be tightened per
manufacturer's instructions.
4.4. During installation of equipment, all small access openings shall be
covered with temporary covers made of tape, plywood or sheet
metal whenever work is not actually in progress.
4.5. Clearance around all equipment shall be checked prior to installing
the equipment. Any interference or lack of access for maintenance
that may be evident shall be reported to the OWNER Construction
Manager.
4.6. All foundation elevations and bolt locations shall be verified prior to
the start of installation of equipment. Bending of bolts to fit
equipment base plate holes beyond the limit of the bolt sleeves will
not be acceptable.
4.7. Leveling and alignment of all equipment shall be within the
tolerance specified in the manufacturer's instructions. Where
equipment is received as a shop-assembled unit, alignment shall
be checked and adjusted where necessary.
Mechanical Installation
Page -4-
4.8. Leveling plates, dowels, shims, and grout are to be furnished by the
Contractor. Grouting material shall be applied in accordance with
the printed instruction from the grouting material manufacturer.
4.9. Field alterations to equipment to facilitate installation shall not be
made without written approval from OWNER. Subassemblies shall
be dismantled only to the extent necessary to verify clearances,
equipment condition and lubrication requirements. Total
dismantling of the subassemblies, if necessary, shall be carried out
only with the written approval from OWNER.
4.10. The Contractor shall maintain alignment and lubrication records on
all mechanical equipment and submit them to OWNER for
acceptance upon completion of the installation. Such records shall
clearly indicate at least the following:
4.10.1. Equipment name and number
4.10.2. Contract number and name
4.10.3. Contractor's name
4.10.4. Contractor’s employee name, craft type and employee
number.
4.10.5. Date and other pertinent details
4.11. Shaft coupling installation and alignment shall be per
manufacturer's instructions. All allowable offsets and angular
misalignment shall be per manufacturer's tolerances.
4.12. Safety guards around rotating equipment furnished by the
equipment manufacturer, but shipped loose shall be installed by the
Contractor in accordance with equipment manufacturer’s
instructions.
4.13. Welding
4.13.1. All welding for non-ASME code vessel/equipment shall
be in accordance with the structural welding code of
American Welding Society AWS-D1.1. No welding is
allowed on ASME code vessel/equipment.
4.13.2. All welding procedures and welding procedure
qualification test records shall be submitted for review
and acceptance by OWNER.
4.13.3. Prior to performing welding on any equipment, specific
release shall be obtained from OWNER.
Mechanical Installation
Page -5-
4.13.4. Welding shall not be performed in the proximity of
bearings. Grounding for welding shall not be through the
shaft or bearing.
4.13.5. Welding shall not be carried out while the rigging is
attached to the equipment.
4.14. Cleaning, Lubricating and Hydraulics
4.14.1. All equipment shall be lubricated in accordance with the
manufacturer's instructions.
4.14.2. Rotating equipment which has been shipped dismantled
for assembly in the field, or shipped without lubricants,
shall have the bearings cleaned, inspected and
lubricated.
4.14.3. All field-assembled lubrication or hydraulic oil supply and
return piping shall be cleaned and pressure tested in
accordance with the applicable specification or alternate
procedure as approved by OWNER. Factory-assembled
lubrication and hydraulic systems do not require flushing
unless manufacturer states otherwise or if contamination
is suspected.
4.14.4. Grease or other protective coating applied for protection
of the equipment in shipping and storage shall be
removed using suitable solvents or cleaners which will
not damage the finish of the machine.
4.14.5. Contractor shall be responsible to provide all hydraulic
oils, lubricating oils and flushing oils for all mechanical
equipment in strict accordance with the manufacturer's
recommendation.
5. INSPECTION AND PRE-COMMISSIONING OF MECHANICAL
EQUIPMENT
5.1. After the basic system and equipment is installed, the following
shall be performed and recorded to assure construction
completeness:
5.1.1. Check installation for conformance with the design and
specifications using available data (design drawings,
vendor’s drawings and manuals, process and instrument
diagrams [P&IDs].)
Mechanical Installation
Page -6-
5.1.2. Confirm suitability of mechanical equipment operation by:
• Checking alignment of all couplings, belts, gears,
reducers, and sprockets (complete all records)
• Checking freedom of shaft rotation
• Checking tightness of seals, inspecting packing of
glands, and stuffing boxes
• Checking lubrication (complete all records)
5.1.3. Perform and record required tests such as visual
inspection, pressure and hydrostatic.
5.1.4. Check that all moving parts have safety guards and if not,
Contractor shall provide acceptable field guards.
5.1.5. Check cleanliness of equipment and systems.
5.1.6. The above shall include all checks and tests which can
be performed without energizing systems.
5.2. When construction completeness is confirmed, pre-operational
tests require energizing all systems. The first operation of the
equipment shall be without material, the only exception being
pumps which must be run, as applicable, with water or oil. All run-
in tests shall consist of continuous operation until all bearing
temperatures and equipment vibrations reach a steady state
condition. The following tests shall be made:
5.2.1. Check operation of hydraulic and lubrication systems. Oil
supply shall be confirmed.
5.2.2. Ensure the motor rotation has been checked before
connecting motor driven equipment.
5.3. Make sure that the equipment operates with minimum vibration
within limits established by the manufacturer.
5.3.1. Checks shall be made between all moving parts to be
sure there is no interference and that clearances are to
manufacturer’s tolerances.
5.3.2. Make sure that all instrument devices, limit switches,
timing devices, overload trips, alignment switches,
emergency stop switches and the like, are operating
properly.
5.3.3. Simulate system operation and make other adjustments
as required to ensure satisfactory run-in operation.
Mechanical Installation
Page -7-
5.3.4. It will be the Contractor’s responsibility to do touch-up
painting on all finished surfaces damaged or abraded
during installation or left unpainted for field welding.
Contractor shall prepare the surface by removing all oil,
dirt, scale, rust, and damaged paint and shall feather
edge breaks in existing paint. Contractor shall furnish
and apply the materials including primer and paint
needed to properly restore the damaged surface coating.
5.3.5. Installation Contractor is to ensure that all chutes,
material handling equipment and pipelines and ports are
free from any obstruction or contamination.
5.3.6. All piping systems and vessels are to be isolated from
contamination at all times, i.e. caps, plugs, covers, etc.
5.3.7. All systems are to be fully cleaned, tested, and inspected
prior to first filling, flushing or introduction of processed
and handled materials.
5.3.8. All manufacturer representatives required by OWNER
are to be coordinated by OWNER.
5.3.9. All installation readings must be documented and
accepted by the manufacturer representatives (where
applicable) and OWNER prior to pre-commissioning.
5.3.10. All equipment calibration if required, is to be completed
and confirmed in writing to OWNER prior to pre-
commissioning.
5.3.11. All equipment is to be certified complete and ready for
Start-Up. All parties involved in all disciplines are to sign
off on each system prior to commissioning. This
includes:
• OWNER
• Manufacturer Representative (if applicable)
• Installation Contractor
• Lower Tier Subcontractors (if applicable)
6. PAINTING
Touch-up painting of installed mechanical equipment shall be in
accordance with the following:
6.1. Chutes and other fabricated platework per fabricated platework
specification .
Mechanical Installation
Page -8-
6.2. Motor driven equipment per manufacturer’s standard paint and
color or as approved by Owner.

More Related Content

What's hot

Manufacturing processes
Manufacturing processesManufacturing processes
Manufacturing processesYPP
 
introduction to process planning murugananthan
introduction to process planning murugananthanintroduction to process planning murugananthan
introduction to process planning murugananthanMurugananthan K
 
NC CNC DNC - A K Mansuri
NC CNC DNC - A K MansuriNC CNC DNC - A K Mansuri
NC CNC DNC - A K MansuriMansuriak
 
A CASE STUDY ON PREVENTIVE MAINTENANCE
A CASE STUDY ON PREVENTIVE MAINTENANCEA CASE STUDY ON PREVENTIVE MAINTENANCE
A CASE STUDY ON PREVENTIVE MAINTENANCEZubair Ali ali
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMohanKirthik
 
Design for assembly methods
Design for assembly methodsDesign for assembly methods
Design for assembly methodsaman1312
 
Introduction to manufacturing system and cnc machines
Introduction to manufacturing system and cnc machinesIntroduction to manufacturing system and cnc machines
Introduction to manufacturing system and cnc machinesThulasikanth Vaddi
 
Uint 1 locating and clamping devices
Uint 1 locating and clamping devicesUint 1 locating and clamping devices
Uint 1 locating and clamping devicesS.DHARANI KUMAR
 
CNC Machine Maintenance
CNC Machine MaintenanceCNC Machine Maintenance
CNC Machine Maintenanceillpa
 
Theory of-metal-cutting
Theory of-metal-cuttingTheory of-metal-cutting
Theory of-metal-cuttingGaurav Gunjan
 
Basic Maintenance
Basic MaintenanceBasic Maintenance
Basic MaintenanceRAHMAT EIE
 

What's hot (20)

Manufacturing processes
Manufacturing processesManufacturing processes
Manufacturing processes
 
introduction to process planning murugananthan
introduction to process planning murugananthanintroduction to process planning murugananthan
introduction to process planning murugananthan
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
cutting speed
cutting speedcutting speed
cutting speed
 
NC CNC DNC - A K Mansuri
NC CNC DNC - A K MansuriNC CNC DNC - A K Mansuri
NC CNC DNC - A K Mansuri
 
4 tooling in cnc
4 tooling in cnc4 tooling in cnc
4 tooling in cnc
 
Lathe machine ppt
Lathe machine pptLathe machine ppt
Lathe machine ppt
 
Plant maintenance
Plant maintenancePlant maintenance
Plant maintenance
 
Capston and turrent lathe
Capston and turrent latheCapston and turrent lathe
Capston and turrent lathe
 
A CASE STUDY ON PREVENTIVE MAINTENANCE
A CASE STUDY ON PREVENTIVE MAINTENANCEA CASE STUDY ON PREVENTIVE MAINTENANCE
A CASE STUDY ON PREVENTIVE MAINTENANCE
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATION
 
Design for assembly methods
Design for assembly methodsDesign for assembly methods
Design for assembly methods
 
Introduction to manufacturing system and cnc machines
Introduction to manufacturing system and cnc machinesIntroduction to manufacturing system and cnc machines
Introduction to manufacturing system and cnc machines
 
Apt programming
Apt programmingApt programming
Apt programming
 
Maintenance
MaintenanceMaintenance
Maintenance
 
Uint 1 locating and clamping devices
Uint 1 locating and clamping devicesUint 1 locating and clamping devices
Uint 1 locating and clamping devices
 
CNC Machine Maintenance
CNC Machine MaintenanceCNC Machine Maintenance
CNC Machine Maintenance
 
Theory of-metal-cutting
Theory of-metal-cuttingTheory of-metal-cutting
Theory of-metal-cutting
 
Basic Maintenance
Basic MaintenanceBasic Maintenance
Basic Maintenance
 
Numeric control
Numeric controlNumeric control
Numeric control
 

Similar to Mechanical install

2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
Batcoda technical specification
Batcoda technical specificationBatcoda technical specification
Batcoda technical specificationDejene Tsegaye
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docxKaty A. Beitia G.
 
Awereness ISO3834 Rev 0.pptx
Awereness ISO3834 Rev 0.pptxAwereness ISO3834 Rev 0.pptx
Awereness ISO3834 Rev 0.pptxMTaufik23
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
URS - USER REQUIREMENT SPECIFICATIONS.pdf
URS - USER REQUIREMENT SPECIFICATIONS.pdfURS - USER REQUIREMENT SPECIFICATIONS.pdf
URS - USER REQUIREMENT SPECIFICATIONS.pdfDiegoMonge23
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015HaGun Gunawan
 
Residential Install Standards
Residential Install StandardsResidential Install Standards
Residential Install StandardsJim Sutton
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Iqbal Mohammad
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement weldingAanand Subi
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)MAHESH PANDIT
 
450 series rail installation instructions rev
450 series rail installation instructions rev450 series rail installation instructions rev
450 series rail installation instructions revYover Rodriguez
 
Steel building-erection-manual
Steel building-erection-manualSteel building-erection-manual
Steel building-erection-manualPradipat Bubpachat
 
ENDUROFLOOR Installation Manual
ENDUROFLOOR Installation ManualENDUROFLOOR Installation Manual
ENDUROFLOOR Installation ManualFolk James
 
Scope of work and terms and conditions fin al
Scope of work and terms and conditions fin alScope of work and terms and conditions fin al
Scope of work and terms and conditions fin alAshish Khandelwal
 

Similar to Mechanical install (20)

2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Batcoda technical specification
Batcoda technical specificationBatcoda technical specification
Batcoda technical specification
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
 
Awereness ISO3834 Rev 0.pptx
Awereness ISO3834 Rev 0.pptxAwereness ISO3834 Rev 0.pptx
Awereness ISO3834 Rev 0.pptx
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
URS - USER REQUIREMENT SPECIFICATIONS.pdf
URS - USER REQUIREMENT SPECIFICATIONS.pdfURS - USER REQUIREMENT SPECIFICATIONS.pdf
URS - USER REQUIREMENT SPECIFICATIONS.pdf
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
 
Residential Install Standards
Residential Install StandardsResidential Install Standards
Residential Install Standards
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
 
Spe
SpeSpe
Spe
 
API-936 exam preperation.pdf
API-936 exam preperation.pdfAPI-936 exam preperation.pdf
API-936 exam preperation.pdf
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement welding
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
 
20 01 00
20 01 0020 01 00
20 01 00
 
450 series rail installation instructions rev
450 series rail installation instructions rev450 series rail installation instructions rev
450 series rail installation instructions rev
 
Steel building-erection-manual
Steel building-erection-manualSteel building-erection-manual
Steel building-erection-manual
 
Nes 362
Nes 362Nes 362
Nes 362
 
ENDUROFLOOR Installation Manual
ENDUROFLOOR Installation ManualENDUROFLOOR Installation Manual
ENDUROFLOOR Installation Manual
 
Scope of work and terms and conditions fin al
Scope of work and terms and conditions fin alScope of work and terms and conditions fin al
Scope of work and terms and conditions fin al
 

Recently uploaded

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 

Recently uploaded (20)

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 

Mechanical install

  • 1. Mechanical Installation Page -1- 1. INTRODUCTION AND PURPOSE 1.1. This specification covers the installation, testing and pre- commissioning of mechanical equipment. Work is to be performed in conjunction with the manufacturer’s instructions, standard industrial practices, and relevant codes and standards. 1.2. The electrical/instrumentation installation work is identified in a separate document. The mechanical work shall be coordinated with the electrical/instrumentation work to provide a complete and operable system. 1.3. Whenever conflicts exist between the manufacturer’s instructions, this Specification, other specifications, the drawings, or codes, the OWNER Construction Manager shall be notified and shall provide the final resolution. 2. CODES AND STANDARDS All equipment shall be installed in accordance with, but not limited to, the latest editions and applicable provisions of the following codes, laws, regulations, and standards. 2.1. Codes, Laws, and Regulations 2.1.1. Mine Safety and Health Administration (MSHA) 2.1.2. Standard Building Code (SBC) 2.1.3. Standard Fire Prevention Code (SFPC) 2.1.4. Standard Mechanical Code (SMC) 2.1.5. USA Environmental Protection Agency (EPA) 2.1.6. All state and local laws and ordinances. 2.1.7. All other applicable codes, laws, and regulations. 2.2. Standards 2.2.1. American Institute of Steel Construction (AISC) 2.2.2. American Iron and Steel Institute (AISI) 2.2.3. American National Standards Institute (ANSI) 2.2.4. American Society of Mechanical Engineers (ASME) 2.2.5. American Society for Testing and Materials (ASTM) 2.2.6. American Welding Society (AWS)
  • 2. Mechanical Installation Page -2- 2.2.7. National Electrical Code (NEC) 2.2.8. Steel Structures Painting Council (SSPC) 2.2.9. All other applicable standards. 3. GENERAL REQUIREMENTS 3.1. The Contractor shall provide supervision, labor, equipment, materials, tools, and supplies unless specifically noted as being provided by others, to perform the work described herein in accordance with this document and the referenced specification, drawings, and related documents. Work not specifically shown on the drawings or enumerated herein but that is reasonably necessary for the proper completion of the contract shall be provided by the Contractor the same as if shown on the drawings or enumerated herein. 3.2. The mechanical equipment shall be installed in accordance with all applicable federal, state and local codes, standards, rules, regulations, and laws including, but not limited to, the codes and standards referenced in Section 2 of this Specification. 3.3. Unload OWNER furnished equipment and materials. Load and transport equipment and materials from the storage area to the installation location. 3.4. Install all the equipment shown on the drawings or as noted in other contract documents. 3.5. Equipment installation shall include the supply and placement of grout for equipment or materials and the supply and installation of anchors and fasteners as required for a complete installation. 3.6. Motor driven equipment placement shall include alignment, assembly of belts, sheaves, couplings, guards, etc. as required for a complete installation. 3.7. The Contractor shall inspect the location for the equipment to be installed prior to beginning installation to insure readiness of area including anchor bolt locations, size, projections and placement of support steel where applicable. 3.8. Work in an area shall be coordinated through the OWNER Construction Manager. No installation of equipment shall be installed without release of the area for such installation.
  • 3. Mechanical Installation Page -3- 3.9. All materials and equipment furnished by the Contractor shall be in accordance with the specifications. Substitution of any materials deviating from the specifications and drawings shall be approved in writing by OWNER. A description of Contractor supplied substituted material shall be submitted to the OWNER Construction Manager for approval. 3.10. The Contractor is responsible to alter the drawing dimensions affected by using different approved items where applicable. Any such dimensional changes shall be submitted on “As-Built” drawings. 4. INSTALLATION REQUIREMENTS 4.1. The Contractor shall read and understand the manufacturer’s installation requirements prior to beginning the installation of the equipment. 4.2. Equipment shall only be lifted and handled in accordance with the manufacturer’s instructions and at points and locations designated for such handling. 4.3. Before installation, all parts shall be thoroughly cleaned of all rust, grit and foreign matter. Where accessible without disassembly, all holes and grooves for lubrication shall be examined and cleaned where necessary. Bolts and screws shall be tightened uniformly without over-stressing the threads. Anchor bolts shall be adequately tightened, and all other bolts shall be tightened per manufacturer's instructions. 4.4. During installation of equipment, all small access openings shall be covered with temporary covers made of tape, plywood or sheet metal whenever work is not actually in progress. 4.5. Clearance around all equipment shall be checked prior to installing the equipment. Any interference or lack of access for maintenance that may be evident shall be reported to the OWNER Construction Manager. 4.6. All foundation elevations and bolt locations shall be verified prior to the start of installation of equipment. Bending of bolts to fit equipment base plate holes beyond the limit of the bolt sleeves will not be acceptable. 4.7. Leveling and alignment of all equipment shall be within the tolerance specified in the manufacturer's instructions. Where equipment is received as a shop-assembled unit, alignment shall be checked and adjusted where necessary.
  • 4. Mechanical Installation Page -4- 4.8. Leveling plates, dowels, shims, and grout are to be furnished by the Contractor. Grouting material shall be applied in accordance with the printed instruction from the grouting material manufacturer. 4.9. Field alterations to equipment to facilitate installation shall not be made without written approval from OWNER. Subassemblies shall be dismantled only to the extent necessary to verify clearances, equipment condition and lubrication requirements. Total dismantling of the subassemblies, if necessary, shall be carried out only with the written approval from OWNER. 4.10. The Contractor shall maintain alignment and lubrication records on all mechanical equipment and submit them to OWNER for acceptance upon completion of the installation. Such records shall clearly indicate at least the following: 4.10.1. Equipment name and number 4.10.2. Contract number and name 4.10.3. Contractor's name 4.10.4. Contractor’s employee name, craft type and employee number. 4.10.5. Date and other pertinent details 4.11. Shaft coupling installation and alignment shall be per manufacturer's instructions. All allowable offsets and angular misalignment shall be per manufacturer's tolerances. 4.12. Safety guards around rotating equipment furnished by the equipment manufacturer, but shipped loose shall be installed by the Contractor in accordance with equipment manufacturer’s instructions. 4.13. Welding 4.13.1. All welding for non-ASME code vessel/equipment shall be in accordance with the structural welding code of American Welding Society AWS-D1.1. No welding is allowed on ASME code vessel/equipment. 4.13.2. All welding procedures and welding procedure qualification test records shall be submitted for review and acceptance by OWNER. 4.13.3. Prior to performing welding on any equipment, specific release shall be obtained from OWNER.
  • 5. Mechanical Installation Page -5- 4.13.4. Welding shall not be performed in the proximity of bearings. Grounding for welding shall not be through the shaft or bearing. 4.13.5. Welding shall not be carried out while the rigging is attached to the equipment. 4.14. Cleaning, Lubricating and Hydraulics 4.14.1. All equipment shall be lubricated in accordance with the manufacturer's instructions. 4.14.2. Rotating equipment which has been shipped dismantled for assembly in the field, or shipped without lubricants, shall have the bearings cleaned, inspected and lubricated. 4.14.3. All field-assembled lubrication or hydraulic oil supply and return piping shall be cleaned and pressure tested in accordance with the applicable specification or alternate procedure as approved by OWNER. Factory-assembled lubrication and hydraulic systems do not require flushing unless manufacturer states otherwise or if contamination is suspected. 4.14.4. Grease or other protective coating applied for protection of the equipment in shipping and storage shall be removed using suitable solvents or cleaners which will not damage the finish of the machine. 4.14.5. Contractor shall be responsible to provide all hydraulic oils, lubricating oils and flushing oils for all mechanical equipment in strict accordance with the manufacturer's recommendation. 5. INSPECTION AND PRE-COMMISSIONING OF MECHANICAL EQUIPMENT 5.1. After the basic system and equipment is installed, the following shall be performed and recorded to assure construction completeness: 5.1.1. Check installation for conformance with the design and specifications using available data (design drawings, vendor’s drawings and manuals, process and instrument diagrams [P&IDs].)
  • 6. Mechanical Installation Page -6- 5.1.2. Confirm suitability of mechanical equipment operation by: • Checking alignment of all couplings, belts, gears, reducers, and sprockets (complete all records) • Checking freedom of shaft rotation • Checking tightness of seals, inspecting packing of glands, and stuffing boxes • Checking lubrication (complete all records) 5.1.3. Perform and record required tests such as visual inspection, pressure and hydrostatic. 5.1.4. Check that all moving parts have safety guards and if not, Contractor shall provide acceptable field guards. 5.1.5. Check cleanliness of equipment and systems. 5.1.6. The above shall include all checks and tests which can be performed without energizing systems. 5.2. When construction completeness is confirmed, pre-operational tests require energizing all systems. The first operation of the equipment shall be without material, the only exception being pumps which must be run, as applicable, with water or oil. All run- in tests shall consist of continuous operation until all bearing temperatures and equipment vibrations reach a steady state condition. The following tests shall be made: 5.2.1. Check operation of hydraulic and lubrication systems. Oil supply shall be confirmed. 5.2.2. Ensure the motor rotation has been checked before connecting motor driven equipment. 5.3. Make sure that the equipment operates with minimum vibration within limits established by the manufacturer. 5.3.1. Checks shall be made between all moving parts to be sure there is no interference and that clearances are to manufacturer’s tolerances. 5.3.2. Make sure that all instrument devices, limit switches, timing devices, overload trips, alignment switches, emergency stop switches and the like, are operating properly. 5.3.3. Simulate system operation and make other adjustments as required to ensure satisfactory run-in operation.
  • 7. Mechanical Installation Page -7- 5.3.4. It will be the Contractor’s responsibility to do touch-up painting on all finished surfaces damaged or abraded during installation or left unpainted for field welding. Contractor shall prepare the surface by removing all oil, dirt, scale, rust, and damaged paint and shall feather edge breaks in existing paint. Contractor shall furnish and apply the materials including primer and paint needed to properly restore the damaged surface coating. 5.3.5. Installation Contractor is to ensure that all chutes, material handling equipment and pipelines and ports are free from any obstruction or contamination. 5.3.6. All piping systems and vessels are to be isolated from contamination at all times, i.e. caps, plugs, covers, etc. 5.3.7. All systems are to be fully cleaned, tested, and inspected prior to first filling, flushing or introduction of processed and handled materials. 5.3.8. All manufacturer representatives required by OWNER are to be coordinated by OWNER. 5.3.9. All installation readings must be documented and accepted by the manufacturer representatives (where applicable) and OWNER prior to pre-commissioning. 5.3.10. All equipment calibration if required, is to be completed and confirmed in writing to OWNER prior to pre- commissioning. 5.3.11. All equipment is to be certified complete and ready for Start-Up. All parties involved in all disciplines are to sign off on each system prior to commissioning. This includes: • OWNER • Manufacturer Representative (if applicable) • Installation Contractor • Lower Tier Subcontractors (if applicable) 6. PAINTING Touch-up painting of installed mechanical equipment shall be in accordance with the following: 6.1. Chutes and other fabricated platework per fabricated platework specification .
  • 8. Mechanical Installation Page -8- 6.2. Motor driven equipment per manufacturer’s standard paint and color or as approved by Owner.