ASSIGNMENT ON POWER SYSTEM
TOPIC-
PROCEDURE TO GET ELECTRICAL
CONNECTION FOR INDUSTRY
e
CONTENTS
 PROCEDURES FOR CONNECTIONS
 GENERAL INFORMATION
 CLASSIFICATION OF SUPPLY FOR
INDUSTRY
 LOAD CHARGES
 LOAD FACTOR
 LOAD BALANCING
 MAXIMUM DEMAND
PROCEDURES FOR
CONNECTIONS
 DESIGN A LOAD
 APPLICATION PROJECT FILE SUBMIT TO JVNL
FOR HOW MUCH YOU NEED A LOAD OR
TRANSMISSION LINES LIKE 11KV OR 33KV
ETC.
 VISIT ELECTRICAL INSPECTOR FROM JVNL
 TRANSFORMER INSTALLATION WITH
INSPECTOR PERMISSION
 HIGH TENSION METER
 MAINTAIN THE LOAD
 JVNL OR ANY OTHER STATE VIDHYUT
NATIONAL LIMETED PERMISSION
 DESIGN A PANEL ROOM
 INSTALL A DG SET
 PERMISSION OF POLLUTION CONTROL
GENERAL INFORMATION
CONNECTED LOAD’ means the sum total of the installed (connected)
capacities in Kilowatts (KW) of all the energy consuming devices on the
Consumer’s premises, which can be used simultaneously. This shall be
expressed in KW or KVA. If the ratings are in KVA, the same may be
converted to KW by multiplying the KVA by 0.85
CONSUMER’ means any person who is supplied with electricity for his own
use by a licensee or the Government or by any other person engaged in the
business of supplying electricity to the public under the Act or any other law
CONTRACTED DEMAND’ means the Load in kilovolt amperes (KVA) /
KW, mutually agreed to between the Licensee and Consumer as entered in the
Agreement
Load Factor” is the ratio of the total number of units (KWh
or KVah) consumed during a given period to the total number
of units which have been consumed had the contracted load
or maximum load (in KW or KVA),
“Transmission Line” means the system consisting of all
high pressure cables and overhead lines transmitting
electricity from a generating station to another generating
station or a sub-station, together with any step-up and step-
down transformers, switch-gear and other works necessary to
and used for the control of such cables or overhead lines
LOAD SERVICE CONNECTION
CHARGES FOR INDUSTRY
 Up to 1000 KW Rs.750/- per KW
 Above 1 MW Rs.750/- per KW or actual cost whichever
is higher.
 • Test report is to be submitted while complying with
the demand notice.
 • In case of DS/NRS consumers wiring contractor's test
report is considered as authentic and no verification is
done to expedite the release of connection.
 • Connections are released on the basis of seniority of
test reports(first come first served).
CLASSIFICATION OF SUPPLY FOR
INDUSTRY
 AT 230 V., SINGLE PHASE
 AT 400 V., 3 PHASE
 H T SUPPLY, 3 PHASE, 50 C/S, 11/13.2KV
AVAILABLE IN THE LOCALITY
 H T SUPPLY, 3PHASE, 50 C/S, 33KV
 E H T SUPPLY, 3PHASE, 50 C/S, 66KV
 E H T SUPPLY, 3PHASE, 50 C/S, 110KV
 E H T SUPPLY, 3PHASE, 50 C/S, 220KV
(a) It shall be obligatory for the consumer to maintain the
desired average power factor of 0.9 for his load or any other
value that the Commission may specify in its Tariff order
during any billing period
.
(b) The Licensee may disconnect the supply temporarily if
power factor is below 0.75 unless otherwise specified in the
tariff order, during any billing period as per details given in
clause 4.36.
(c) Licensee may charge a penalty and / or give an incentive
for high /low power factor as per the tariff order of the
Commission
LOAD FACTOR
LOAD BALANCING
 a) The Licensee shall ensure that the load unbalances does not
exceed 5 % at the point of commencement of supply.
 (b)The consumer taking three-phase supply shall also balance his
load in such a way that the difference in loading between each
phase does not exceed 5% of the average loading between the
phases.
 (c)The licensee may submit to Commission the procedure and
time frame desired for levying charges on consumer/ providing
compensation to consumers, for not complying to (a) and (b)
above
MAXIMUM DEMAND
 Maximum demand register (kW or kVA). This is the
maximum power value, usually the average of 15
minutes, reached during the billing period (this
average time may vary depending on the country).
Once the value is higher than the contracted power,
the customer will pay a penalty on the electricity
bill.
 Maximum Demand is a greatest of all demands that
occur during a specific time
Industry connections

More Related Content

What's hot

“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
Dr. Babasaheb Ambedkar Technological University
 
Srldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power MeetSrldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power Meet
PRIYANK JAIN
 
Reactive power compensation using statcom
Reactive power compensation using statcomReactive power compensation using statcom
Reactive power compensation using statcom
Amit Meena
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIAArun Muraleedharan
 
Congestion management using facts devices in deregulated power system
Congestion management using facts devices in deregulated power systemCongestion management using facts devices in deregulated power system
Congestion management using facts devices in deregulated power system
eSAT Journals
 
K.Sravanthi.
K.Sravanthi.K.Sravanthi.
K.Sravanthi.
SRAVANTHI KUPPA
 
Load flow analysis with upfc under unsymmetrical fault condition
Load flow analysis with upfc under unsymmetrical fault conditionLoad flow analysis with upfc under unsymmetrical fault condition
Load flow analysis with upfc under unsymmetrical fault condition
Alexander Decker
 
Control of Active And reactive power flow in transmission line and power Osci...
Control of Active And reactive power flow in transmission line and power Osci...Control of Active And reactive power flow in transmission line and power Osci...
Control of Active And reactive power flow in transmission line and power Osci...
AM Publications
 
Steady state analysis on HVLF-AC transmission for offshore wind power by mode...
Steady state analysis on HVLF-AC transmission for offshore wind power by mode...Steady state analysis on HVLF-AC transmission for offshore wind power by mode...
Steady state analysis on HVLF-AC transmission for offshore wind power by mode...
AM Publications
 
Distributed power flow controller (naresh)
Distributed power flow controller (naresh)Distributed power flow controller (naresh)
Distributed power flow controller (naresh)
Naresh Raye
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
Ameen San
 
IRJET- An Improvement of the Power Quality of Power Distribution System using...
IRJET- An Improvement of the Power Quality of Power Distribution System using...IRJET- An Improvement of the Power Quality of Power Distribution System using...
IRJET- An Improvement of the Power Quality of Power Distribution System using...
IRJET Journal
 
Instantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its ApplicationsInstantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its Applications
arunj89
 
129 venezuelan static var compensator
129 venezuelan static var compensator129 venezuelan static var compensator
129 venezuelan static var compensatorwmelis
 
Congestion issues and its related management
Congestion issues and its related managementCongestion issues and its related management
Congestion issues and its related managementalpna1808
 
[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi
[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi
[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi
IJET - International Journal of Engineering and Techniques
 
Contingency analysis
Contingency analysisContingency analysis
Contingency analysis
Sajan Sahu
 
Minimizing losses in power distribution system
Minimizing losses in power distribution systemMinimizing losses in power distribution system
Minimizing losses in power distribution system
harshal567
 
Power systems İntroduction
Power systems İntroductionPower systems İntroduction
Power systems İntroduction
Caner Göksel Sonuzun
 
Gy3512171221
Gy3512171221Gy3512171221
Gy3512171221
IJERA Editor
 

What's hot (20)

“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
 
Srldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power MeetSrldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power Meet
 
Reactive power compensation using statcom
Reactive power compensation using statcomReactive power compensation using statcom
Reactive power compensation using statcom
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIA
 
Congestion management using facts devices in deregulated power system
Congestion management using facts devices in deregulated power systemCongestion management using facts devices in deregulated power system
Congestion management using facts devices in deregulated power system
 
K.Sravanthi.
K.Sravanthi.K.Sravanthi.
K.Sravanthi.
 
Load flow analysis with upfc under unsymmetrical fault condition
Load flow analysis with upfc under unsymmetrical fault conditionLoad flow analysis with upfc under unsymmetrical fault condition
Load flow analysis with upfc under unsymmetrical fault condition
 
Control of Active And reactive power flow in transmission line and power Osci...
Control of Active And reactive power flow in transmission line and power Osci...Control of Active And reactive power flow in transmission line and power Osci...
Control of Active And reactive power flow in transmission line and power Osci...
 
Steady state analysis on HVLF-AC transmission for offshore wind power by mode...
Steady state analysis on HVLF-AC transmission for offshore wind power by mode...Steady state analysis on HVLF-AC transmission for offshore wind power by mode...
Steady state analysis on HVLF-AC transmission for offshore wind power by mode...
 
Distributed power flow controller (naresh)
Distributed power flow controller (naresh)Distributed power flow controller (naresh)
Distributed power flow controller (naresh)
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 
IRJET- An Improvement of the Power Quality of Power Distribution System using...
IRJET- An Improvement of the Power Quality of Power Distribution System using...IRJET- An Improvement of the Power Quality of Power Distribution System using...
IRJET- An Improvement of the Power Quality of Power Distribution System using...
 
Instantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its ApplicationsInstantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its Applications
 
129 venezuelan static var compensator
129 venezuelan static var compensator129 venezuelan static var compensator
129 venezuelan static var compensator
 
Congestion issues and its related management
Congestion issues and its related managementCongestion issues and its related management
Congestion issues and its related management
 
[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi
[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi
[IJET V2I5P4] Authors: Rachana Chavan, Rakesh Singh Lodhi
 
Contingency analysis
Contingency analysisContingency analysis
Contingency analysis
 
Minimizing losses in power distribution system
Minimizing losses in power distribution systemMinimizing losses in power distribution system
Minimizing losses in power distribution system
 
Power systems İntroduction
Power systems İntroductionPower systems İntroduction
Power systems İntroduction
 
Gy3512171221
Gy3512171221Gy3512171221
Gy3512171221
 

Viewers also liked

El primer empleo
El primer empleoEl primer empleo
El primer empleo
Hviano
 
Европа-парк
Европа-паркЕвропа-парк
Европа-парк
Elena Yanchenko
 
Pronodix : classement général provisoire
Pronodix : classement général provisoirePronodix : classement général provisoire
Pronodix : classement général provisoire
benjaave
 
Reportaje Artiles | Grazia Spain
Reportaje Artiles | Grazia Spain Reportaje Artiles | Grazia Spain
Reportaje Artiles | Grazia Spain Armando Pinedo
 
Classementweb22 23octobre semaine9
Classementweb22 23octobre semaine9Classementweb22 23octobre semaine9
Classementweb22 23octobre semaine9
benjaave
 
Grupo N° 4 Tema:Teoría sobre los ciclos economicos
Grupo N° 4  Tema:Teoría sobre los ciclos economicos Grupo N° 4  Tema:Teoría sobre los ciclos economicos
Grupo N° 4 Tema:Teoría sobre los ciclos economicos Anahy Brucela
 
Cesar augustopulidopulgarin actividad1_2mapac.pdf
Cesar augustopulidopulgarin actividad1_2mapac.pdfCesar augustopulidopulgarin actividad1_2mapac.pdf
Cesar augustopulidopulgarin actividad1_2mapac.pdf
cesar pulido pulgarin
 
Formulacion de proyectos
Formulacion de proyectosFormulacion de proyectos
Formulacion de proyectosAngeLik MorEno
 

Viewers also liked (11)

El primer empleo
El primer empleoEl primer empleo
El primer empleo
 
Европа-парк
Европа-паркЕвропа-парк
Европа-парк
 
Assem Zahan CV
Assem Zahan CVAssem Zahan CV
Assem Zahan CV
 
barath resume new
barath resume newbarath resume new
barath resume new
 
Pronodix : classement général provisoire
Pronodix : classement général provisoirePronodix : classement général provisoire
Pronodix : classement général provisoire
 
Reportaje Artiles | Grazia Spain
Reportaje Artiles | Grazia Spain Reportaje Artiles | Grazia Spain
Reportaje Artiles | Grazia Spain
 
Classementweb22 23octobre semaine9
Classementweb22 23octobre semaine9Classementweb22 23octobre semaine9
Classementweb22 23octobre semaine9
 
Cannes 2013 | Grazia
Cannes 2013 | Grazia Cannes 2013 | Grazia
Cannes 2013 | Grazia
 
Grupo N° 4 Tema:Teoría sobre los ciclos economicos
Grupo N° 4  Tema:Teoría sobre los ciclos economicos Grupo N° 4  Tema:Teoría sobre los ciclos economicos
Grupo N° 4 Tema:Teoría sobre los ciclos economicos
 
Cesar augustopulidopulgarin actividad1_2mapac.pdf
Cesar augustopulidopulgarin actividad1_2mapac.pdfCesar augustopulidopulgarin actividad1_2mapac.pdf
Cesar augustopulidopulgarin actividad1_2mapac.pdf
 
Formulacion de proyectos
Formulacion de proyectosFormulacion de proyectos
Formulacion de proyectos
 

Similar to Industry connections

Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
PoojaAnupGarg
 
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATEPERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
ijiert bestjournal
 
Briefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power DeliveryBriefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power Delivery
Black & Veatch
 
Iirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving stationIirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving station
Iaetsd Iaetsd
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
GPERI
 
F1075157
F1075157F1075157
F1075157
IJERD Editor
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
ssuserd0df33
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
IRJET Journal
 
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMTHD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
ijiert bestjournal
 
DVARVVO_WPb_0117
DVARVVO_WPb_0117DVARVVO_WPb_0117
DVARVVO_WPb_0117Paul Chang
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Design
phase3-120A
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
Power System Operation
 
FACTS Flexible AC Transmission System.ppt
FACTS Flexible AC Transmission System.pptFACTS Flexible AC Transmission System.ppt
FACTS Flexible AC Transmission System.ppt
rajeshplacherikunnel
 
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IRJET Journal
 
Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...
Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...
Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...
IJMTST Journal
 
Unit 3 FACTS Technology
Unit 3 FACTS TechnologyUnit 3 FACTS Technology
Unit 3 FACTS Technology
SANTOSH GADEKAR
 
IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...
IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...
IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...
IRJET Journal
 

Similar to Industry connections (20)

Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATEPERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
 
Briefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power DeliveryBriefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power Delivery
 
White paper
White paperWhite paper
White paper
 
Iirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving stationIirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving station
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
 
F1075157
F1075157F1075157
F1075157
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
 
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMTHD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
 
Dps 02 rev02
Dps 02 rev02Dps 02 rev02
Dps 02 rev02
 
DVARVVO_WPb_0117
DVARVVO_WPb_0117DVARVVO_WPb_0117
DVARVVO_WPb_0117
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Design
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
 
FACTS Flexible AC Transmission System.ppt
FACTS Flexible AC Transmission System.pptFACTS Flexible AC Transmission System.ppt
FACTS Flexible AC Transmission System.ppt
 
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
 
Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...
Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...
Modeling Optimization Voltage Index Unified Power Flow Controller Equivalent ...
 
Unit 3 FACTS Technology
Unit 3 FACTS TechnologyUnit 3 FACTS Technology
Unit 3 FACTS Technology
 
IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...
IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...
IRJET- Voltage Stability Improvement and Reactive Power Compensation using ST...
 

Recently uploaded

一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
itech2017
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 

Recently uploaded (20)

一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 

Industry connections

  • 1. CAREER POINT UNIVERSITY ASSIGNMENT ON POWER SYSTEM TOPIC- PROCEDURE TO GET ELECTRICAL CONNECTION FOR INDUSTRY e
  • 2. CONTENTS  PROCEDURES FOR CONNECTIONS  GENERAL INFORMATION  CLASSIFICATION OF SUPPLY FOR INDUSTRY  LOAD CHARGES  LOAD FACTOR  LOAD BALANCING  MAXIMUM DEMAND
  • 3. PROCEDURES FOR CONNECTIONS  DESIGN A LOAD  APPLICATION PROJECT FILE SUBMIT TO JVNL FOR HOW MUCH YOU NEED A LOAD OR TRANSMISSION LINES LIKE 11KV OR 33KV ETC.  VISIT ELECTRICAL INSPECTOR FROM JVNL  TRANSFORMER INSTALLATION WITH INSPECTOR PERMISSION  HIGH TENSION METER  MAINTAIN THE LOAD  JVNL OR ANY OTHER STATE VIDHYUT NATIONAL LIMETED PERMISSION
  • 4.  DESIGN A PANEL ROOM  INSTALL A DG SET  PERMISSION OF POLLUTION CONTROL
  • 5. GENERAL INFORMATION CONNECTED LOAD’ means the sum total of the installed (connected) capacities in Kilowatts (KW) of all the energy consuming devices on the Consumer’s premises, which can be used simultaneously. This shall be expressed in KW or KVA. If the ratings are in KVA, the same may be converted to KW by multiplying the KVA by 0.85 CONSUMER’ means any person who is supplied with electricity for his own use by a licensee or the Government or by any other person engaged in the business of supplying electricity to the public under the Act or any other law CONTRACTED DEMAND’ means the Load in kilovolt amperes (KVA) / KW, mutually agreed to between the Licensee and Consumer as entered in the Agreement
  • 6. Load Factor” is the ratio of the total number of units (KWh or KVah) consumed during a given period to the total number of units which have been consumed had the contracted load or maximum load (in KW or KVA), “Transmission Line” means the system consisting of all high pressure cables and overhead lines transmitting electricity from a generating station to another generating station or a sub-station, together with any step-up and step- down transformers, switch-gear and other works necessary to and used for the control of such cables or overhead lines
  • 7. LOAD SERVICE CONNECTION CHARGES FOR INDUSTRY  Up to 1000 KW Rs.750/- per KW  Above 1 MW Rs.750/- per KW or actual cost whichever is higher.  • Test report is to be submitted while complying with the demand notice.  • In case of DS/NRS consumers wiring contractor's test report is considered as authentic and no verification is done to expedite the release of connection.  • Connections are released on the basis of seniority of test reports(first come first served).
  • 8. CLASSIFICATION OF SUPPLY FOR INDUSTRY  AT 230 V., SINGLE PHASE  AT 400 V., 3 PHASE  H T SUPPLY, 3 PHASE, 50 C/S, 11/13.2KV AVAILABLE IN THE LOCALITY  H T SUPPLY, 3PHASE, 50 C/S, 33KV  E H T SUPPLY, 3PHASE, 50 C/S, 66KV  E H T SUPPLY, 3PHASE, 50 C/S, 110KV  E H T SUPPLY, 3PHASE, 50 C/S, 220KV
  • 9. (a) It shall be obligatory for the consumer to maintain the desired average power factor of 0.9 for his load or any other value that the Commission may specify in its Tariff order during any billing period . (b) The Licensee may disconnect the supply temporarily if power factor is below 0.75 unless otherwise specified in the tariff order, during any billing period as per details given in clause 4.36. (c) Licensee may charge a penalty and / or give an incentive for high /low power factor as per the tariff order of the Commission LOAD FACTOR
  • 10. LOAD BALANCING  a) The Licensee shall ensure that the load unbalances does not exceed 5 % at the point of commencement of supply.  (b)The consumer taking three-phase supply shall also balance his load in such a way that the difference in loading between each phase does not exceed 5% of the average loading between the phases.  (c)The licensee may submit to Commission the procedure and time frame desired for levying charges on consumer/ providing compensation to consumers, for not complying to (a) and (b) above
  • 11. MAXIMUM DEMAND  Maximum demand register (kW or kVA). This is the maximum power value, usually the average of 15 minutes, reached during the billing period (this average time may vary depending on the country). Once the value is higher than the contracted power, the customer will pay a penalty on the electricity bill.  Maximum Demand is a greatest of all demands that occur during a specific time