SlideShare a Scribd company logo
1 of 24
Download to read offline
WEUEF
Hydraulics / Advanced
Hydraulics Course
Model Answer for Assignments
Prepared by Associate Prof. Sameh KANTOUSH
Assignment # 2
A mercury manometer (sp. gr. = 13.6)
is used to measure the pressure
difference in vessels A and B, as
shown in the Figure. Determine the
pressure difference in pascals (N/m2).
Solution for Assignment # 2
The sketch of the manometer system (step 1) is shown
in Figure. Points 3 and 4 (P3, P4) are on a surface of
equal pressure (step 2) and so are the vessel A and points
1 and 2 (P1, P2):
The pressures at points 3 and 4 are, respectively (step 3),
and noting that ฮณM = ฮณ (sp. gr.)
Assignment 3
A piezometer and a Pitot tube are tapped into a horizontal water pipe, as shown in
Figure , to measure static and stagnation (static + dynamic) pressures. For the
indicated water column heights, determine the velocity at the center of the pipe.
datum
V2=0
z1=z2=0
Solution
Bernoulli equation for section 1 and 2; datum
as shown in the Figure
[ ]
2 2
1 1 2 2
1 2
2
1 1 2
1 2 3 1 2
2 1
1
p V p V
z z
2g 2g
p V p
2g
2g (h h h ) (h h )
2g(p p )
V
+ + = + +
ฮณ ฮณ
+ =
ฮณ ฮณ
ฮณ + + โˆ’ ฮณ +
โˆ’
= =
ฮณ ฮณ
1 3
V 2gh 2 9.81 0.12 1.53(m / s)
= = ร— ร— =
p2
p1
In Class Exercise
The bed width of a rectangular channel is 12.0 m, bed slope is 8 cm/km
and the discharge is 25 m3/sec. Considering the following two cases, draw
the T.E.L. & H.G.L. between two sections 5 km apart:
A. The flow is uniform and the water depth is 3.0 m,
Assignment # 4 (Excel)
Solution
Assignment # 4 (Excel)
Assignment # 5
Determine the normal water depth for each of the following open channels
if the discharge Q = 25 m3 /sec, n = 0.025, and the longitudinal bed slope
S = 10 cm/km:
A. Rectangular channel, b = 10 meters
B. Trapezoidal channel, b = 10 meters and m = 1.0, m=1.5 and m=2.
C. Draw relationship between Y & m and write your comments.
Assignment # 6
A rectangular canal has a bed slope of 8 cm/km, and a bed width of 100 m.
If at a depth of 6 m the canal carries a discharge of 860 m3/sec at uniform
flow. Find the roughness n, Chezy's coefficient C, and the coefficient of
friction f. Also find the average shear stress on the bed.
Assignment # 7
A new lined canal shall be constructed in African river basin. The maximum design
rate of flow is 100 m3/sec, the side slope is 2:1, and longitudinal bed slope is 10
cm/km. The channel is lined with concrete, for which the design Manning roughness
coefficient is 0.0182. The cost of excavation of the channel is 8 USD/m3 and the total
cost of lining is 100 USD/m2.
Determine the cost of constructing one kilometer of the channel in million USD
considering the following two cases:
(i) The bed width is four times the water depth (b=4y), and
(ii) The channel section is best hydraulic section.
Which section would you recommend? Why?
SOLUTION :
For a Trapezoidal channel
Given:
Qmax =100m3/s
Side Slope = 2:1 m=2
So= 10 cm/km = 0.0001
n = 0.0182
Cost of channel excavation = 8.0 USD/m3
Total cost of lining = 100.0 USD/ m2
Required: Construction cost of constructing one kilometer of the channel in million USD considering the following two cases:
(i) b=4y
(ii) Best hydraulic section.
Which section would you recommend? Why?
To determine:
Cost of constructing 1.0 km of the channel in million USD considering:
Case 1: The bed width, b = 4y
Flow Area of the Trapezoidal section, A= (b + my) y = (4y + 2y) y = 6y2
Wetted Perimeter of the Trapezoidal section, P = b+2y (๐‘š๐‘š2 + 1) = 4y +2y 22 + 1 =4y+2๐’š๐’š ๐Ÿ“๐Ÿ“ = 8.47y
Hydraulic Radius, Rh =
6y2
8.47y
= 0.7083y
From Manningโ€™s equation: ๐‘ธ๐‘ธ =
๐Ÿ๐Ÿ
๐’๐’
๐‘จ๐‘จ๐‘จ๐‘จ๐’‰๐’‰
๐Ÿ๐Ÿ
๐Ÿ‘๐Ÿ‘ ๐‘บ๐‘บ๐’๐’
๐Ÿ๐Ÿ
๐Ÿ๐Ÿ
100 =
1
0.0182
โˆ— 6๐‘ฆ๐‘ฆ2
โˆ— (0.7083๐‘ฆ๐‘ฆ)
2
3 โˆ— 0.0001
1
2
100= 0.54945* 6๐‘ฆ๐‘ฆ2
* 0.7946y2/3
100 = 2.6196y8/3;
38.1738 = y8/3 (38.1738)3/8 = y y = 3.92m
b=4y = 4 (3.92m) = 15.70 m (Take b = 16.0m for construction fesibility)
Q =100cms (> 85cms), thus free board= 0.9m
yex = y + free board
= 3.92m +0.9m = 4.82m
Design Flow Area, Aex = yex (b + myex) = 4.82 (16+ 2*4.82) = 123.58 m2
Design Wetted Perimeter, Pex = b+2yex โˆš (m2 +1) =16+2*4.82โˆš5 = 16 + 21.55 = 37.55m
Cost of Channel excavation = Excavation Volume * Unit cost
= (Aex * 1000m * 8) USD = (123.58m2 *1000m* 8) USD = 988640 USD
Cost of Channel Lining = Lining Area*100 USD/m2
= Pex *L*100 = 37.55m*1000m*100 = 3,755,569 USD
Total Cost = 988640 USD + 3,755,569 USD
= 4,744,209 USD โ‰ˆ 5.0 Million USD
Case 2: The best hydraulic section
This is the cross-section that conveys maximum discharge for a constant cross-section area, slope and friction coefficient
Best Hydraulic section:
Qmax. โ†’ Pmin when A, n, S are constant
A= y (b + my); b=
๐ด๐ด
๐‘ฆ๐‘ฆ
โ€“ my
๐‘ƒ๐‘ƒ = ๐‘๐‘ + 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2
Pminโ†’
๐‘‘๐‘‘๐‘‘๐‘‘
๐‘‘๐‘‘๐‘‘๐‘‘
= 0
๐‘‘๐‘‘๐‘‘๐‘‘
๐‘‘๐‘‘๐‘ฆ๐‘ฆ
= 0 = -
๐ด๐ด
๐‘ฆ๐‘ฆ2 โ€“ my + 2โˆš (m2 + 1
๐ด๐ด
๐‘ฆ๐‘ฆ2 + m = 2 1 + ๐‘š๐‘š2
๐‘ฆ๐‘ฆ(๐‘๐‘ + ๐‘š๐‘š๐‘ฆ๐‘ฆ)
๐‘ฆ๐‘ฆ2
+ ๐‘š๐‘š = 2 1 + ๐‘š๐‘š2 (๐‘๐‘ + ๐‘š๐‘š๐‘ฆ๐‘ฆ) + ๐‘š๐‘š๐‘ฆ๐‘ฆ = 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2
๐‘๐‘ + 2๐‘š๐‘š๐‘ฆ๐‘ฆ + ๐‘๐‘ = 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2 + ๐‘๐‘ 2(๐‘๐‘ + ๐‘š๐‘š๐‘ฆ๐‘ฆ) = ๐‘๐‘ + 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2
2๐ด๐ด
๐‘ฆ๐‘ฆ
= ๐‘ƒ๐‘ƒ
It shows that the best hydraulic trapezoidal
section has a hydraulic radius equal to one-half
of the water depth.
Rh =
๐’€๐’€
๐Ÿ๐Ÿ
Thus, when Rh =
๐’€๐’€
๐Ÿ๐Ÿ
Rh =
๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ
๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ ๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท
=
(b + my) y
b + 2yโˆš (m2
+ 1)
=
๐’š๐’š
๐Ÿ๐Ÿ
b= 0.472y
Manningโ€™s equation ๐‘ธ๐‘ธ =
๐Ÿ๐Ÿ
๐’๐’
๐‘จ๐‘จ๐‘จ๐‘จ๐’‰๐’‰
๐Ÿ๐Ÿ
๐Ÿ‘๐Ÿ‘ ๐‘บ๐‘บ๐’๐’
๐Ÿ๐Ÿ
๐Ÿ๐Ÿ ๐‘ธ๐‘ธ =
๐Ÿ๐Ÿ
๐’๐’
๐‘จ๐‘จ(
๐’š๐’š
๐Ÿ๐Ÿ
)
๐Ÿ๐Ÿ
๐Ÿ‘๐Ÿ‘ ๐‘บ๐‘บ๐’๐’
๐Ÿ๐Ÿ
๐Ÿ๐Ÿ
๐‘ธ๐‘ธ =
๐Ÿ๐Ÿ
๐’๐’
( (b + 2y) y )(
๐’š๐’š
๐Ÿ๐Ÿ
) ^(
๐Ÿ๐Ÿ
๐Ÿ‘๐Ÿ‘
)
(0.0001)
1
2 100 =
๐Ÿ๐Ÿ
๐ŸŽ๐ŸŽ.๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ
( (b + 2y) y )(
๐’š๐’š
๐Ÿ๐Ÿ
) (
๐Ÿ๐Ÿ
๐Ÿ‘๐Ÿ‘
)
(0.0001)
1
2
100 = 0.5494 ((0.472y + 2y)*y) * (
๐’š๐’š
๐Ÿ๐Ÿ
) (
๐Ÿ๐Ÿ
๐Ÿ‘๐Ÿ‘
)
182.017 = 2.472y2 * (
๐’š๐’š
๐Ÿ๐Ÿ
) (
๐Ÿ๐Ÿ
๐Ÿ‘๐Ÿ‘
)
y = 5.96m b=0.472y = 0.472*(5.96) = 2.814m ( Take b = 3.0m)
yex= 5.96 m+ 0.9m= 6.86m
Design Flow Area, Aex = yex (b + myex) = 6.86 (3+ 2*6.86) = 114.699 m2
Design Wetted Perimeter, Pex = b+2yex โˆš (m2 +1) = 3+2*6.86โˆš5 = 3 +30.8577 = 33.678m
Cost of Channel excavation = Excavation Volume * Unit cost
= (Aex * 1000m * 8) USD = (114.699 m2 *1000m* 8) USD = 917592 USD
Cost of Channel Lining = Lining Area*100 USD/m2
= Pex *L*100 = 33.678m *1000m*100 = 3,367,800 USD
Total Cost = 917592 + 3,367,800 = 4,285,392 USD = 4.00 Million USD
The calculations show that he best
hydraulic trapezoidal section has less
cost comparing to the other method with
higher hydraulic performance.
Assignment #8
Water is flowing in a trapezoidal channel of bed width = 8.0 m,
longitudinal bed slope = 12 cm/km, side slopes are 1:1,
Manning roughness coefficient = 0.025. If the Froude number
= 0.12, find the critical slope and specific energy.
Solution
Given:
Cross section: Trapezoidal Channel
B = 8.0m
So= 12 cm/km = 0.00012
Side Slopes m=1
Manningโ€™s roughness coefficient, n = 0.025
Froude Number, Fr = 0.12 (<1) i.e. Sub-Critical Flow (Mild Slope where yn > yc)
A= (b + my) y = (8+y) y =8*y +y2
P = b+2yโˆš (mยฒ +1) = 8+2*y*โˆš2
T = b+2y = 8+2*y
๐‘†๐‘†๐‘๐‘ =
๐‘›๐‘›๐‘›๐‘›
๐ด๐ด๐‘๐‘๐‘…๐‘…โ„Ž๐‘๐‘
2/3
2
๐‘„๐‘„2 =
0.1413 ร— 8๐‘ฆ๐‘ฆ+๐‘ฆ๐‘ฆ2 3
8+2๐‘ฆ๐‘ฆ
(1)
๐น๐น๐‘Ÿ๐‘Ÿ
2
=
๐‘„๐‘„2
๐‘”๐‘”๐ด๐ด3
๐‘‡๐‘‡
From Manningโ€™s equation; to determine
the relationship between Q and Yn
๐‘„๐‘„2 =
0.192 ร— 8๐‘ฆ๐‘ฆ+๐‘ฆ๐‘ฆ2
10
3
(8+2๐‘ฆ๐‘ฆโˆš2)
4
3
(2)
From equations (1) and (2)
0.7359 =
8๐‘ฆ๐‘ฆ+๐‘ฆ๐‘ฆ2
1
3 ร— (8+2๐‘ฆ๐‘ฆ)
(8+2.828๐‘ฆ๐‘ฆ)
4
3
By trail and errors yn
= 0.51 m and Q = 1.132 m3/s
๐‘„๐‘„2
๐‘”๐‘”๐ด๐ด๐‘๐‘
3 ๐‘‡๐‘‡๐‘๐‘ = 1 ๐‘œ๐‘œ๐‘œ๐‘œ
๐‘„๐‘„2
๐‘”๐‘”
=
๐ด๐ด๐‘๐‘
3
๐‘‡๐‘‡๐‘๐‘
0.130 =
(8โˆ—๐‘ฆ๐‘ฆ๐‘๐‘+๐‘ฆ๐‘ฆ๐‘๐‘
2 )3
8+2๐‘ฆ๐‘ฆ๐‘๐‘
By trail and errors yc
= 0.125 m
๐‘†๐‘†๐‘๐‘ =
0.025 โˆ— 1.132
1.024 โˆ— 0.1222/3
2
๐‘†๐‘†๐‘๐‘ = 0.0125
๐ธ๐ธ = ๐‘ฆ๐‘ฆ +
๐‘„๐‘„2
2๐‘”๐‘”๐ด๐ด2
๐ธ๐ธ = 0.51 +
1.281
369.572
= 0. ๐Ÿ“๐Ÿ“๐Ÿ“๐Ÿ“๐Ÿ“๐Ÿ“ m
At yn
= 0.51 and Q = 1.132 m3/s
A = 8๐‘ฆ๐‘ฆ + ๐‘ฆ๐‘ฆ2 = ((8*0.51) + 0.512) = 4.08 + 0.2601 = 4.34 m2
ู‹โ€ซุงโ€ฌโ€ซ๏บท๏ป›ุฑโ€ฌ
Vielen Dank
Thank you for your attention
ใ‚ใ‚ŠใŒใจใ†ใ”ใ–ใ„ใพใ™

More Related Content

Similar to hydraulics and advanced hydraulics solved tutorials

pipe lines lec 2.pptx
pipe lines lec 2.pptxpipe lines lec 2.pptx
pipe lines lec 2.pptxamirashraf61
ย 
pipe line calculation
pipe line calculationpipe line calculation
pipe line calculationjatinar123
ย 
51495
5149551495
51495jatinar123
ย 
Lecture 2 manning
Lecture     2  manning   Lecture     2  manning
Lecture 2 manning LuayHameed
ย 
Fluid mechanic white (cap2.1)
Fluid mechanic   white (cap2.1)Fluid mechanic   white (cap2.1)
Fluid mechanic white (cap2.1)Raul Garcia
ย 
Design of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptxDesign of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptxAathiraS10
ย 
pipe lines lec 2.pptx
pipe lines lec 2.pptxpipe lines lec 2.pptx
pipe lines lec 2.pptxamirashraf61
ย 
2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdf
2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdf2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdf
2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdfBhargรฃv Pรขtel
ย 
Computation exam
Computation examComputation exam
Computation examHenk Massink
ย 
Pipeline Design Project
Pipeline Design ProjectPipeline Design Project
Pipeline Design ProjectDaniel Kerkhoff
ย 
Answers assignment 3 integral methods-fluid mechanics
Answers assignment 3 integral methods-fluid mechanicsAnswers assignment 3 integral methods-fluid mechanics
Answers assignment 3 integral methods-fluid mechanicsasghar123456
ย 
Faculty of Engineering (2011. 2012) - Solver.doc
Faculty of Engineering (2011. 2012) - Solver.docFaculty of Engineering (2011. 2012) - Solver.doc
Faculty of Engineering (2011. 2012) - Solver.docDr. Ezzat Elsayed Gomaa
ย 
ฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑ
ฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑ
ฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑฮ’ฮฑฯ„ฮฌฯ„ฮถฮทฯ‚ .
ย 
Ch.1 fluid dynamic
Ch.1 fluid dynamicCh.1 fluid dynamic
Ch.1 fluid dynamicMalika khalil
ย 
economic channel section
economic channel sectioneconomic channel section
economic channel sectionVaibhav Pathak
ย 
Gate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanationsGate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanationskulkarni Academy
ย 
Gate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanationsGate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanationskulkarni Academy
ย 
Ch2.ppt
Ch2.pptCh2.ppt
Ch2.pptAliGlal
ย 

Similar to hydraulics and advanced hydraulics solved tutorials (20)

pipe lines lec 2.pptx
pipe lines lec 2.pptxpipe lines lec 2.pptx
pipe lines lec 2.pptx
ย 
pipe line calculation
pipe line calculationpipe line calculation
pipe line calculation
ย 
51495
5149551495
51495
ย 
Lecture 2 manning
Lecture     2  manning   Lecture     2  manning
Lecture 2 manning
ย 
Laminar flow
Laminar flowLaminar flow
Laminar flow
ย 
Fluid mechanic white (cap2.1)
Fluid mechanic   white (cap2.1)Fluid mechanic   white (cap2.1)
Fluid mechanic white (cap2.1)
ย 
Design of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptxDesign of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptx
ย 
pipe lines lec 2.pptx
pipe lines lec 2.pptxpipe lines lec 2.pptx
pipe lines lec 2.pptx
ย 
2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdf
2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdf2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdf
2A- Hydraulics, Water Distribution and WW Collection_AC_W2022 (1).pdf
ย 
Computation exam
Computation examComputation exam
Computation exam
ย 
Pipeline Design Project
Pipeline Design ProjectPipeline Design Project
Pipeline Design Project
ย 
Answers assignment 3 integral methods-fluid mechanics
Answers assignment 3 integral methods-fluid mechanicsAnswers assignment 3 integral methods-fluid mechanics
Answers assignment 3 integral methods-fluid mechanics
ย 
Faculty of Engineering (2011. 2012) - Solver.doc
Faculty of Engineering (2011. 2012) - Solver.docFaculty of Engineering (2011. 2012) - Solver.doc
Faculty of Engineering (2011. 2012) - Solver.doc
ย 
ฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑ
ฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑ
ฮกฮตฯ…ฯƒฯ„ฮฌ ฯƒฮต ฮšฮฏฮฝฮทฯƒฮท ฮ“ฮ„ ฮ›ฯ…ฮบฮตฮฏฮฟฯ… - ฮ ฯฮฟฮฒฮปฮฎฮผฮฑฯ„ฮฑ
ย 
Lab 2 Final group d
Lab 2 Final group dLab 2 Final group d
Lab 2 Final group d
ย 
Ch.1 fluid dynamic
Ch.1 fluid dynamicCh.1 fluid dynamic
Ch.1 fluid dynamic
ย 
economic channel section
economic channel sectioneconomic channel section
economic channel section
ย 
Gate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanationsGate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanations
ย 
Gate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanationsGate 2017 me 1 solutions with explanations
Gate 2017 me 1 solutions with explanations
ย 
Ch2.ppt
Ch2.pptCh2.ppt
Ch2.ppt
ย 

Recently uploaded

pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
ย 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
ย 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
ย 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
ย 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
ย 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
ย 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
ย 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
ย 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
ย 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
ย 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
ย 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
ย 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
ย 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
ย 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
ย 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
ย 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
ย 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
ย 

Recently uploaded (20)

pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
ย 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
ย 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
ย 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
ย 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
ย 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
ย 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
ย 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
ย 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
ย 
young call girls in Rajiv Chowk๐Ÿ” 9953056974 ๐Ÿ” Delhi escort Service
young call girls in Rajiv Chowk๐Ÿ” 9953056974 ๐Ÿ” Delhi escort Serviceyoung call girls in Rajiv Chowk๐Ÿ” 9953056974 ๐Ÿ” Delhi escort Service
young call girls in Rajiv Chowk๐Ÿ” 9953056974 ๐Ÿ” Delhi escort Service
ย 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
ย 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
ย 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
ย 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
ย 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
ย 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
ย 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
ย 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
ย 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
ย 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
ย 

hydraulics and advanced hydraulics solved tutorials

  • 1. WEUEF Hydraulics / Advanced Hydraulics Course Model Answer for Assignments Prepared by Associate Prof. Sameh KANTOUSH
  • 2. Assignment # 2 A mercury manometer (sp. gr. = 13.6) is used to measure the pressure difference in vessels A and B, as shown in the Figure. Determine the pressure difference in pascals (N/m2).
  • 3. Solution for Assignment # 2 The sketch of the manometer system (step 1) is shown in Figure. Points 3 and 4 (P3, P4) are on a surface of equal pressure (step 2) and so are the vessel A and points 1 and 2 (P1, P2): The pressures at points 3 and 4 are, respectively (step 3), and noting that ฮณM = ฮณ (sp. gr.)
  • 4. Assignment 3 A piezometer and a Pitot tube are tapped into a horizontal water pipe, as shown in Figure , to measure static and stagnation (static + dynamic) pressures. For the indicated water column heights, determine the velocity at the center of the pipe. datum V2=0 z1=z2=0 Solution Bernoulli equation for section 1 and 2; datum as shown in the Figure [ ] 2 2 1 1 2 2 1 2 2 1 1 2 1 2 3 1 2 2 1 1 p V p V z z 2g 2g p V p 2g 2g (h h h ) (h h ) 2g(p p ) V + + = + + ฮณ ฮณ + = ฮณ ฮณ ฮณ + + โˆ’ ฮณ + โˆ’ = = ฮณ ฮณ 1 3 V 2gh 2 9.81 0.12 1.53(m / s) = = ร— ร— = p2 p1
  • 5. In Class Exercise The bed width of a rectangular channel is 12.0 m, bed slope is 8 cm/km and the discharge is 25 m3/sec. Considering the following two cases, draw the T.E.L. & H.G.L. between two sections 5 km apart: A. The flow is uniform and the water depth is 3.0 m,
  • 6. Assignment # 4 (Excel) Solution
  • 7. Assignment # 4 (Excel)
  • 8. Assignment # 5 Determine the normal water depth for each of the following open channels if the discharge Q = 25 m3 /sec, n = 0.025, and the longitudinal bed slope S = 10 cm/km: A. Rectangular channel, b = 10 meters B. Trapezoidal channel, b = 10 meters and m = 1.0, m=1.5 and m=2. C. Draw relationship between Y & m and write your comments.
  • 9.
  • 10.
  • 11. Assignment # 6 A rectangular canal has a bed slope of 8 cm/km, and a bed width of 100 m. If at a depth of 6 m the canal carries a discharge of 860 m3/sec at uniform flow. Find the roughness n, Chezy's coefficient C, and the coefficient of friction f. Also find the average shear stress on the bed.
  • 12.
  • 13. Assignment # 7 A new lined canal shall be constructed in African river basin. The maximum design rate of flow is 100 m3/sec, the side slope is 2:1, and longitudinal bed slope is 10 cm/km. The channel is lined with concrete, for which the design Manning roughness coefficient is 0.0182. The cost of excavation of the channel is 8 USD/m3 and the total cost of lining is 100 USD/m2. Determine the cost of constructing one kilometer of the channel in million USD considering the following two cases: (i) The bed width is four times the water depth (b=4y), and (ii) The channel section is best hydraulic section. Which section would you recommend? Why?
  • 14. SOLUTION : For a Trapezoidal channel Given: Qmax =100m3/s Side Slope = 2:1 m=2 So= 10 cm/km = 0.0001 n = 0.0182 Cost of channel excavation = 8.0 USD/m3 Total cost of lining = 100.0 USD/ m2 Required: Construction cost of constructing one kilometer of the channel in million USD considering the following two cases: (i) b=4y (ii) Best hydraulic section. Which section would you recommend? Why?
  • 15. To determine: Cost of constructing 1.0 km of the channel in million USD considering: Case 1: The bed width, b = 4y Flow Area of the Trapezoidal section, A= (b + my) y = (4y + 2y) y = 6y2 Wetted Perimeter of the Trapezoidal section, P = b+2y (๐‘š๐‘š2 + 1) = 4y +2y 22 + 1 =4y+2๐’š๐’š ๐Ÿ“๐Ÿ“ = 8.47y Hydraulic Radius, Rh = 6y2 8.47y = 0.7083y From Manningโ€™s equation: ๐‘ธ๐‘ธ = ๐Ÿ๐Ÿ ๐’๐’ ๐‘จ๐‘จ๐‘จ๐‘จ๐’‰๐’‰ ๐Ÿ๐Ÿ ๐Ÿ‘๐Ÿ‘ ๐‘บ๐‘บ๐’๐’ ๐Ÿ๐Ÿ ๐Ÿ๐Ÿ 100 = 1 0.0182 โˆ— 6๐‘ฆ๐‘ฆ2 โˆ— (0.7083๐‘ฆ๐‘ฆ) 2 3 โˆ— 0.0001 1 2 100= 0.54945* 6๐‘ฆ๐‘ฆ2 * 0.7946y2/3 100 = 2.6196y8/3; 38.1738 = y8/3 (38.1738)3/8 = y y = 3.92m b=4y = 4 (3.92m) = 15.70 m (Take b = 16.0m for construction fesibility)
  • 16. Q =100cms (> 85cms), thus free board= 0.9m yex = y + free board = 3.92m +0.9m = 4.82m Design Flow Area, Aex = yex (b + myex) = 4.82 (16+ 2*4.82) = 123.58 m2 Design Wetted Perimeter, Pex = b+2yex โˆš (m2 +1) =16+2*4.82โˆš5 = 16 + 21.55 = 37.55m Cost of Channel excavation = Excavation Volume * Unit cost = (Aex * 1000m * 8) USD = (123.58m2 *1000m* 8) USD = 988640 USD Cost of Channel Lining = Lining Area*100 USD/m2 = Pex *L*100 = 37.55m*1000m*100 = 3,755,569 USD Total Cost = 988640 USD + 3,755,569 USD = 4,744,209 USD โ‰ˆ 5.0 Million USD
  • 17. Case 2: The best hydraulic section This is the cross-section that conveys maximum discharge for a constant cross-section area, slope and friction coefficient Best Hydraulic section: Qmax. โ†’ Pmin when A, n, S are constant A= y (b + my); b= ๐ด๐ด ๐‘ฆ๐‘ฆ โ€“ my ๐‘ƒ๐‘ƒ = ๐‘๐‘ + 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2 Pminโ†’ ๐‘‘๐‘‘๐‘‘๐‘‘ ๐‘‘๐‘‘๐‘‘๐‘‘ = 0 ๐‘‘๐‘‘๐‘‘๐‘‘ ๐‘‘๐‘‘๐‘ฆ๐‘ฆ = 0 = - ๐ด๐ด ๐‘ฆ๐‘ฆ2 โ€“ my + 2โˆš (m2 + 1 ๐ด๐ด ๐‘ฆ๐‘ฆ2 + m = 2 1 + ๐‘š๐‘š2 ๐‘ฆ๐‘ฆ(๐‘๐‘ + ๐‘š๐‘š๐‘ฆ๐‘ฆ) ๐‘ฆ๐‘ฆ2 + ๐‘š๐‘š = 2 1 + ๐‘š๐‘š2 (๐‘๐‘ + ๐‘š๐‘š๐‘ฆ๐‘ฆ) + ๐‘š๐‘š๐‘ฆ๐‘ฆ = 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2 ๐‘๐‘ + 2๐‘š๐‘š๐‘ฆ๐‘ฆ + ๐‘๐‘ = 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2 + ๐‘๐‘ 2(๐‘๐‘ + ๐‘š๐‘š๐‘ฆ๐‘ฆ) = ๐‘๐‘ + 2๐‘ฆ๐‘ฆ 1 + ๐‘š๐‘š2 2๐ด๐ด ๐‘ฆ๐‘ฆ = ๐‘ƒ๐‘ƒ It shows that the best hydraulic trapezoidal section has a hydraulic radius equal to one-half of the water depth.
  • 18. Rh = ๐’€๐’€ ๐Ÿ๐Ÿ Thus, when Rh = ๐’€๐’€ ๐Ÿ๐Ÿ Rh = ๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ๐‘ญ ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ๐‘จ ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ๐‘พ ๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท๐‘ท = (b + my) y b + 2yโˆš (m2 + 1) = ๐’š๐’š ๐Ÿ๐Ÿ b= 0.472y Manningโ€™s equation ๐‘ธ๐‘ธ = ๐Ÿ๐Ÿ ๐’๐’ ๐‘จ๐‘จ๐‘จ๐‘จ๐’‰๐’‰ ๐Ÿ๐Ÿ ๐Ÿ‘๐Ÿ‘ ๐‘บ๐‘บ๐’๐’ ๐Ÿ๐Ÿ ๐Ÿ๐Ÿ ๐‘ธ๐‘ธ = ๐Ÿ๐Ÿ ๐’๐’ ๐‘จ๐‘จ( ๐’š๐’š ๐Ÿ๐Ÿ ) ๐Ÿ๐Ÿ ๐Ÿ‘๐Ÿ‘ ๐‘บ๐‘บ๐’๐’ ๐Ÿ๐Ÿ ๐Ÿ๐Ÿ ๐‘ธ๐‘ธ = ๐Ÿ๐Ÿ ๐’๐’ ( (b + 2y) y )( ๐’š๐’š ๐Ÿ๐Ÿ ) ^( ๐Ÿ๐Ÿ ๐Ÿ‘๐Ÿ‘ ) (0.0001) 1 2 100 = ๐Ÿ๐Ÿ ๐ŸŽ๐ŸŽ.๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ๐ŸŽ ( (b + 2y) y )( ๐’š๐’š ๐Ÿ๐Ÿ ) ( ๐Ÿ๐Ÿ ๐Ÿ‘๐Ÿ‘ ) (0.0001) 1 2 100 = 0.5494 ((0.472y + 2y)*y) * ( ๐’š๐’š ๐Ÿ๐Ÿ ) ( ๐Ÿ๐Ÿ ๐Ÿ‘๐Ÿ‘ ) 182.017 = 2.472y2 * ( ๐’š๐’š ๐Ÿ๐Ÿ ) ( ๐Ÿ๐Ÿ ๐Ÿ‘๐Ÿ‘ ) y = 5.96m b=0.472y = 0.472*(5.96) = 2.814m ( Take b = 3.0m) yex= 5.96 m+ 0.9m= 6.86m Design Flow Area, Aex = yex (b + myex) = 6.86 (3+ 2*6.86) = 114.699 m2 Design Wetted Perimeter, Pex = b+2yex โˆš (m2 +1) = 3+2*6.86โˆš5 = 3 +30.8577 = 33.678m Cost of Channel excavation = Excavation Volume * Unit cost = (Aex * 1000m * 8) USD = (114.699 m2 *1000m* 8) USD = 917592 USD Cost of Channel Lining = Lining Area*100 USD/m2 = Pex *L*100 = 33.678m *1000m*100 = 3,367,800 USD Total Cost = 917592 + 3,367,800 = 4,285,392 USD = 4.00 Million USD The calculations show that he best hydraulic trapezoidal section has less cost comparing to the other method with higher hydraulic performance.
  • 19. Assignment #8 Water is flowing in a trapezoidal channel of bed width = 8.0 m, longitudinal bed slope = 12 cm/km, side slopes are 1:1, Manning roughness coefficient = 0.025. If the Froude number = 0.12, find the critical slope and specific energy. Solution Given: Cross section: Trapezoidal Channel B = 8.0m So= 12 cm/km = 0.00012 Side Slopes m=1 Manningโ€™s roughness coefficient, n = 0.025 Froude Number, Fr = 0.12 (<1) i.e. Sub-Critical Flow (Mild Slope where yn > yc) A= (b + my) y = (8+y) y =8*y +y2 P = b+2yโˆš (mยฒ +1) = 8+2*y*โˆš2 T = b+2y = 8+2*y
  • 20. ๐‘†๐‘†๐‘๐‘ = ๐‘›๐‘›๐‘›๐‘› ๐ด๐ด๐‘๐‘๐‘…๐‘…โ„Ž๐‘๐‘ 2/3 2 ๐‘„๐‘„2 = 0.1413 ร— 8๐‘ฆ๐‘ฆ+๐‘ฆ๐‘ฆ2 3 8+2๐‘ฆ๐‘ฆ (1) ๐น๐น๐‘Ÿ๐‘Ÿ 2 = ๐‘„๐‘„2 ๐‘”๐‘”๐ด๐ด3 ๐‘‡๐‘‡ From Manningโ€™s equation; to determine the relationship between Q and Yn ๐‘„๐‘„2 = 0.192 ร— 8๐‘ฆ๐‘ฆ+๐‘ฆ๐‘ฆ2 10 3 (8+2๐‘ฆ๐‘ฆโˆš2) 4 3 (2) From equations (1) and (2) 0.7359 = 8๐‘ฆ๐‘ฆ+๐‘ฆ๐‘ฆ2 1 3 ร— (8+2๐‘ฆ๐‘ฆ) (8+2.828๐‘ฆ๐‘ฆ) 4 3 By trail and errors yn = 0.51 m and Q = 1.132 m3/s ๐‘„๐‘„2 ๐‘”๐‘”๐ด๐ด๐‘๐‘ 3 ๐‘‡๐‘‡๐‘๐‘ = 1 ๐‘œ๐‘œ๐‘œ๐‘œ ๐‘„๐‘„2 ๐‘”๐‘” = ๐ด๐ด๐‘๐‘ 3 ๐‘‡๐‘‡๐‘๐‘ 0.130 = (8โˆ—๐‘ฆ๐‘ฆ๐‘๐‘+๐‘ฆ๐‘ฆ๐‘๐‘ 2 )3 8+2๐‘ฆ๐‘ฆ๐‘๐‘ By trail and errors yc = 0.125 m ๐‘†๐‘†๐‘๐‘ = 0.025 โˆ— 1.132 1.024 โˆ— 0.1222/3 2 ๐‘†๐‘†๐‘๐‘ = 0.0125
  • 21. ๐ธ๐ธ = ๐‘ฆ๐‘ฆ + ๐‘„๐‘„2 2๐‘”๐‘”๐ด๐ด2 ๐ธ๐ธ = 0.51 + 1.281 369.572 = 0. ๐Ÿ“๐Ÿ“๐Ÿ“๐Ÿ“๐Ÿ“๐Ÿ“ m At yn = 0.51 and Q = 1.132 m3/s A = 8๐‘ฆ๐‘ฆ + ๐‘ฆ๐‘ฆ2 = ((8*0.51) + 0.512) = 4.08 + 0.2601 = 4.34 m2
  • 22.
  • 23.
  • 24. ู‹โ€ซุงโ€ฌโ€ซ๏บท๏ป›ุฑโ€ฌ Vielen Dank Thank you for your attention ใ‚ใ‚ŠใŒใจใ†ใ”ใ–ใ„ใพใ™