SlideShare a Scribd company logo
How to design a
Universal Incentive
Scheme
For a manufacturing company
Contents
 Incentive Theory
 Quantity vs. Quality
 Setting an Incentive Scheme: Stepping Stones
 Incentive System Types
 Incentive Approach Types
 Incentive Slabbing: Linear & Logarithmic
 Introduction to “Incentive Index”
 Divisional Index
 Multiplicative Index
 Divisional vs. Multiplicative: Head to Head
 Incentive vs. Penalty
 Penalty Plan
2
Incentive Theory
 Let’s consider an example:
 Production Capacity: 100 units
 Production Target: 80 units (i.e. 80% of Capacity)
3
0 units 80 units 100 unitsEntitlement for
Incentive
0 units 80 units 100 units
5 5 5 5
Incentive given for
these extra units
Incentive Theory4
0 units 80 units 100 units
Ascending Incentive
Rate
5 5 5 5
Quantity vs. Quality
 Incentive is given based on increased quantity.
 With increased quantity, there is a possible chance to
trade-off quality.
5
Focus on Quality
 So, while giving incentive to motivate our work-force
for increased quantity…….
 We need to keep “Quality” also in our mind
6
Setting an Incentive
Scheme: Stepping Stones
Set the
incentive
system
Set the
Approach
Set the
incentive
slabs
Set the
incentive
index
Fix the
incentive
rate
7
Set the incentive system
8
Incentive System Types:9
Name of System Method of Rate
Determination
Major
Characteristics
Straight piecework
system
Units of production
per time frame
Straight rate after
entitlement
Taylor Differential
piece rate system
Units of production
per time frame
Differential rate at
each slabs after
entitlement
Standard hour
system
Time frame per unit
production
Rate fixed if time of
production is less
than expectation
Halsey 50-50 system Time frame per unit
production
Profit shared on 50-
50 basis for saving
time in production
Set the Approach
10
Incentive Approach Types:
 Approach:
 Individual incentive approach
 Ex: Goods produced by a single individual
 Team incentive approach
 Ex: Goods produced by a group of individuals
11
Set the incentive slabs
12
Incentive Slabbing: Linear &
Logarithmic
 Equal units in each slab
 Differential rate should be introduced
 E.g. incentive entitlement is 1000 units/shift & capacity
is 1500 units/shift.
 Linear slabbing for 5 slabs will be:
13
Slabs Units
Produced
Slab 1 100
Slab 2 100
Slab 3 100
Slab 4 100
Slab 5 100
0
500
1000
1500
2000
Linear Slabbing
Linear
Slabbing
Incentive Slabbing: Linear &
Logarithmic
 Differential units in each slab
 Equal/Differential rate should be introduced
 E.g. incentive entitlement is 1000 units/shift & capacity
is 1500 units/shift.
 Linear slabbing for 5 slabs will be:
14
Slabs Units
Produced
Slab 1 193
Slab 2 114
Slab 3 80
Slab 4 62
Slab 5 51
0
500
1000
1500
2000
Logarithmic Slabbing
Logarithmic
Slabbing
Incentive Plan: Example
 Let’s consider an incentive plan for a shop floor
consisting 30 associates working in 3 shifts having 10
individuals in each shift.
 The parameters are as follows:
 Number of individuals: 10 persons
 Number of work-days in a month for a shift: 20 days
 Incentive system: Taylor differential piece rate system
 Approach: Team Approach (Single Shift)
15
Incentive Slabs: Example
 Incentive Slabs according to team approach
 Type: Linear
16
Slab No Units of good
produced per shift
Entitlement 1000
Slab 1 1100
Slab 2 1200
Slab 3 1300
Slab 4 1400
Slab 5 1500
Set the incentive index
&
Fix the incentive rate17
Introduction to…
“Incentive Index”
 “Incentive Index” is the highest monetary value a
company is willing to pay to its receptor team or
individual for a given time period (e.g. a month)
based on the performance of a given time frame.
 For team incentive plan:
 When the receptor is a team, it’s called “Divisional Index”
 When the receptor is an individual, it’s called
“Multiplicative Index”
18
Divisional Index: Example
 Lets consider that management has decided to give
highest 10,000 BDT as incentive to a specific shift for a
month based on the performance of each work-day
 Here,
 Receptor type: Team
 Time period: 1 month
 Time frame: Single Work-day
 Highest monetary value: 10,000 BDT
 As the receptor is a team, the incentive index in this case
will be “Divisional Index”
19
Divisional Index: Example
 Highest monetary value: 10,000
 Number of working days in a month: 20
 Divisional index: 10000/20
=500
 So, highest 500 BDT will given as incentive to an entire
shift for a single working day
20
Divisional Index: Incentive
Rate Fixing Example
21
0 units 80 units 100 units
Ascending Incentive
Rate
5 5 5 5
Divisional Index: Incentive
Rate Fixing Example
Divisional
Index
% of
Index
BDT Incentive
Slabs
Extra
units
produce
d
Incentive
Rate,
BDT/unit
produce
d
1000
500
10% 50 1100 100 0.5
15% 75 1200 100 0.75
20% 100 1300 100 1
25% 125 1400 100 1.25
30% 150 1500 100 1.5
22
Divisional Index: From Time
frame to Time period
Days Units Produced Extra units after
entitlement
Incentives
earned, BDT
Day 1 1155 155 91.25
Day 2 920 0 0
Day 3 1455 455 432.5
Day 4 1305 305 231.25
Day 5 1275 275 200
23
For day 1,
Extra units produced after
entitlement = 155 units
Incentive earned = 100 x 0.5 + 55 x
0.75 = 91.25 BDT
Total incentive earned in first 5
days = 955 BDT
Slab No Rate
Slab 1 0.5
Slab 2 0.75
Slab 3 1
Slab 4 1.25
Slab 5 1.5
Divisional Index: From Time
frame to Time period
 For simplification, lets consider that the next 15 days for
this shift goes just like the first 5 days
 Therefore, total incentive earned by this shift for a total
of 20 days ( a time period) will be = 955 x 4 = 3820 BDT
 From previous slides, Number of individuals in this shift =
10
 Therefore, Incentive earned by a single person of this
shift for a time period = 3820/10 = 382 BDT
24
Incentive Plan: Example
 Let’s consider an incentive plan for a shop floor
consisting 30 associates working in 3 shifts having 10
individuals in each shift.
 The parameters are as follows:
 Number of individuals: 10 persons
 Number of work-days in a month for a shift: 20 days
 Incentive system: Taylor differential piece rate system
 Approach: Team Approach (Single Shift)
25
Multiplicative Index:
Example
 Lets consider that management has decided to give
highest 1,000 BDT to each individual of a specific shift for
a month based on the performance of that shift of each
work-day
 Here,
 Receptor type: Individual
 Time period: 1 month
 Time frame: Single Work-day
 Highest monetary value: 1,000 BDT
 As the receptor is an individual, the incentive index in this
case will be “Multiplicative Index”
26
Multiplicative Index:
Example
 Highest monetary value: 1,000
 Number of working days in a month: 20
 Multiplicative index: 1000/20 = 50
 So, highest 50 BDT will given as incentive to each
individual of that shift for a single working day
27
Multiplicative Index: Incentive
Rate Fixing Example
28
0 units 80 units 100 units
Ascending Incentive
Rate
5 5 5 5
Multiplicative Index: Incentive
Rate Fixing Example
Multiplica
tive Index
% of
Index
BDT Incentive
Slabs
Extra units
produced
Incentive
Rate,
BDT/unit
produced
1000
50
10% 5 1100 100 0.05
15% 7.5 1200 100 0.075
20% 10 1300 100 0.1
25% 12.5 1400 100 0.125
30% 15 1500 100 0.15
29
Multiplicative Index: From
Time frame to Time period
Days Units Produced Extra units after
entitlement
Incentives
earned, BDT
Day 1 1155 155 9.125
Day 2 920 0 0
Day 3 1455 455 43.25
Day 4 1305 305 23.125
Day 5 1275 275 20
30
For day 1,
Extra units produced after
entitlement = 155 units
Incentive earned = 100 x 0.05 + 55 x
0.075 = 9.125 BDT
Total incentive earned in first 5 days
= 95.5 BDT
Slab No Rate
Slab 1 0.05
Slab 2 0.075
Slab 3 0.1
Slab 4 0.125
Slab 5 0.15
Multiplicative Index: From
Time frame to Time period
 For simplification, lets consider that the next 15 days for
that shift goes just like the first 5 days
 Therefore, total incentive earned by each individual of
that shift for a total of 20 days ( a time period) will be =
95.5 x 4 = 382 BDT
 For reconciliation, total amount given to that shift for a
month= 382 x 10 = 3820 BDT
31
Divisional vs. Multiplicative:
Head to Head
Divisional Index Multiplicative Index
Favorable for teams with equal
members & equal capacity within
same dept. & not prone to sudden
change in number of members
Favorable when setting a universal
incentive scheme across shifts of
different departments.
As the receptor is a team,
individual earning from incentive is
hard to control
As the receptor is an individual,
earning of every individual can be
controlled
With a change in capacity &
personnel, both slabs & index
should be changed
With a change in capacity &
personnel, only slabs need to be
changed
Different index for diff.
departments. Therefore, so many
indices. Hard to be documented
bcoz of changing.
A single index for all the
departments & shifts.
32
Incentive vs. Penalty
 In order to motivate production, incentives are
rewarded for increased quantity.
 Likewise, in order to maintain quality benchmark,
penalties are imposed on defects.
 Example:
 Lets consider entitlement is on 1000 units/shift.
 Production in a certain shift is 1155 units.
 Of these units, 20 is defective.
33
Penalty Plan
 Penalty can be imposed in two ways:
 Active Penalty:
 Incentive is given on extra 155 units after entitlement. For the
20 defectives, defective rate is determined. For that
defective rate, penalty rate is introduced.
 So, 95.5 BDT is the incentive gain per person on that day (155
units extra production)
 Defective rate: 20/1155 = 0.0173
 Defective rate slabs are introduced.
 Penalty rates are introduced.
 Penalty loss is being calculated.
 Ultimate gain = Absolute of (Incentive gain – Penalty loss)
34
Penalty Plan
 Penalty can be imposed in two ways:
 Passive Penalty:
 Incentive is given on the good units only i.e. 1155 - 20 =1135
units
 There is not direct penalty.
 Therefore, there will be either 0 or (+)ve gain in ultimate.
 Actually, there is no penalty!!!
35
Thank You.
36

More Related Content

What's hot

Chapter 3- training and development
Chapter  3- training and developmentChapter  3- training and development
Chapter 3- training and development
5502
 
Rewards, Benefits and Incentives of an Organization
Rewards, Benefits and Incentives of an OrganizationRewards, Benefits and Incentives of an Organization
Rewards, Benefits and Incentives of an Organization
Masum Hussain
 
Compensation strategies
Compensation strategiesCompensation strategies
Compensation strategies
anjali5491
 

What's hot (20)

Significance of training and development - Manu Melwin Joy
Significance of training and development - Manu Melwin JoySignificance of training and development - Manu Melwin Joy
Significance of training and development - Manu Melwin Joy
 
Base compensation - compensation management - Manu Melwin Joy
Base compensation  -  compensation management - Manu Melwin JoyBase compensation  -  compensation management - Manu Melwin Joy
Base compensation - compensation management - Manu Melwin Joy
 
Sales incentive plan review process
Sales incentive plan review processSales incentive plan review process
Sales incentive plan review process
 
PowerPoint presentation on Variable Pay
 PowerPoint presentation on Variable Pay  PowerPoint presentation on Variable Pay
PowerPoint presentation on Variable Pay
 
Compensation system
Compensation systemCompensation system
Compensation system
 
Incentive plans
Incentive plansIncentive plans
Incentive plans
 
Compensation dimensions
Compensation dimensionsCompensation dimensions
Compensation dimensions
 
Strategic role of compensation, strategic compensation policy, total compensa...
Strategic role of compensation, strategic compensation policy, total compensa...Strategic role of compensation, strategic compensation policy, total compensa...
Strategic role of compensation, strategic compensation policy, total compensa...
 
Bases for traditional pay system & modern pay system and establishing pay plans
Bases for traditional pay system & modern pay system and establishing pay plans Bases for traditional pay system & modern pay system and establishing pay plans
Bases for traditional pay system & modern pay system and establishing pay plans
 
Chapter 3- training and development
Chapter  3- training and developmentChapter  3- training and development
Chapter 3- training and development
 
Concept of compensation and reward, compensation dimensions, system of compen...
Concept of compensation and reward, compensation dimensions, system of compen...Concept of compensation and reward, compensation dimensions, system of compen...
Concept of compensation and reward, compensation dimensions, system of compen...
 
Individual Incentive System
Individual Incentive SystemIndividual Incentive System
Individual Incentive System
 
Reward management
Reward managementReward management
Reward management
 
Module 1 (2nd part)
Module 1 (2nd part)Module 1 (2nd part)
Module 1 (2nd part)
 
Training and Development
Training and DevelopmentTraining and Development
Training and Development
 
Compensation management
Compensation managementCompensation management
Compensation management
 
Employee benefits and compensation2
Employee benefits and compensation2Employee benefits and compensation2
Employee benefits and compensation2
 
Rewards, Benefits and Incentives of an Organization
Rewards, Benefits and Incentives of an OrganizationRewards, Benefits and Incentives of an Organization
Rewards, Benefits and Incentives of an Organization
 
Group incentive plans
Group incentive plansGroup incentive plans
Group incentive plans
 
Compensation strategies
Compensation strategiesCompensation strategies
Compensation strategies
 

Similar to How to design a universal incentive system for a manufacturing company

Topic 2 Cf And Making Investment Decisions
Topic 2 Cf And Making Investment DecisionsTopic 2 Cf And Making Investment Decisions
Topic 2 Cf And Making Investment Decisions
shengvn
 
Costs of production
Costs of productionCosts of production
Costs of production
sherrin125
 
unit 2 CVP analysis, Break-even point.pptx
unit 2 CVP analysis, Break-even point.pptxunit 2 CVP analysis, Break-even point.pptx
unit 2 CVP analysis, Break-even point.pptx
uday231983
 
Project Profitability Analysis and Evaluation
Project Profitability Analysis and EvaluationProject Profitability Analysis and Evaluation
Project Profitability Analysis and Evaluation
Arpit Amar
 

Similar to How to design a universal incentive system for a manufacturing company (20)

Topic 2 Cf And Making Investment Decisions
Topic 2 Cf And Making Investment DecisionsTopic 2 Cf And Making Investment Decisions
Topic 2 Cf And Making Investment Decisions
 
ma answers.pdf
ma answers.pdfma answers.pdf
ma answers.pdf
 
CVP analysis
CVP analysis CVP analysis
CVP analysis
 
Principle of microeconomic.pptx
Principle of microeconomic.pptxPrinciple of microeconomic.pptx
Principle of microeconomic.pptx
 
Costs of production
Costs of productionCosts of production
Costs of production
 
Costs of Production, Production Function, Law of Diminishing Returns.pptx
Costs of Production, Production Function, Law of Diminishing Returns.pptxCosts of Production, Production Function, Law of Diminishing Returns.pptx
Costs of Production, Production Function, Law of Diminishing Returns.pptx
 
Economics presentation
Economics presentationEconomics presentation
Economics presentation
 
Lesson 9--production[1]
Lesson 9--production[1]Lesson 9--production[1]
Lesson 9--production[1]
 
Income Statement Reporting Challenges with BI Tools: Helping IT and Finance t...
Income Statement Reporting Challenges with BI Tools: Helping IT and Finance t...Income Statement Reporting Challenges with BI Tools: Helping IT and Finance t...
Income Statement Reporting Challenges with BI Tools: Helping IT and Finance t...
 
leverage.pptx
leverage.pptxleverage.pptx
leverage.pptx
 
COA B2.pptx
COA B2.pptxCOA B2.pptx
COA B2.pptx
 
3. Capacity 22 HR.ppt
3. Capacity 22 HR.ppt3. Capacity 22 HR.ppt
3. Capacity 22 HR.ppt
 
Financial Decision Making for Entrepreneurs
Financial Decision Making for EntrepreneursFinancial Decision Making for Entrepreneurs
Financial Decision Making for Entrepreneurs
 
Break-Even-Analysis.pptx
Break-Even-Analysis.pptxBreak-Even-Analysis.pptx
Break-Even-Analysis.pptx
 
unit 2 CVP analysis, Break-even point.pptx
unit 2 CVP analysis, Break-even point.pptxunit 2 CVP analysis, Break-even point.pptx
unit 2 CVP analysis, Break-even point.pptx
 
Project Profitability Analysis and Evaluation
Project Profitability Analysis and EvaluationProject Profitability Analysis and Evaluation
Project Profitability Analysis and Evaluation
 
Advanced Computer Programming..pptx
Advanced Computer Programming..pptxAdvanced Computer Programming..pptx
Advanced Computer Programming..pptx
 
Notes on Cost volume profit analysis
Notes on Cost volume profit analysisNotes on Cost volume profit analysis
Notes on Cost volume profit analysis
 
Unit 3 review_session
Unit 3 review_sessionUnit 3 review_session
Unit 3 review_session
 
Incentives
IncentivesIncentives
Incentives
 

Recently uploaded

Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
Khaled Al Awadi
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 

Recently uploaded (20)

Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
USA classified ads posting – best classified sites in usa.pdf
USA classified ads posting – best classified sites in usa.pdfUSA classified ads posting – best classified sites in usa.pdf
USA classified ads posting – best classified sites in usa.pdf
 
sales plan presentation by mckinsey alum
sales plan presentation by mckinsey alumsales plan presentation by mckinsey alum
sales plan presentation by mckinsey alum
 
Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
The Inspiring Personality To Watch In 2024.pdf
The Inspiring Personality To Watch In 2024.pdfThe Inspiring Personality To Watch In 2024.pdf
The Inspiring Personality To Watch In 2024.pdf
 
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
 
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
 
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | ShajaraLuxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
LinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxLinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptx
 
Evolution and Growth of Supply chain.pdf
Evolution and Growth of Supply chain.pdfEvolution and Growth of Supply chain.pdf
Evolution and Growth of Supply chain.pdf
 
HR and Employment law update: May 2024.
HR and Employment law update:  May 2024.HR and Employment law update:  May 2024.
HR and Employment law update: May 2024.
 
Understanding UAE Labour Law: Key Points for Employers and Employees
Understanding UAE Labour Law: Key Points for Employers and EmployeesUnderstanding UAE Labour Law: Key Points for Employers and Employees
Understanding UAE Labour Law: Key Points for Employers and Employees
 

How to design a universal incentive system for a manufacturing company

  • 1. How to design a Universal Incentive Scheme For a manufacturing company
  • 2. Contents  Incentive Theory  Quantity vs. Quality  Setting an Incentive Scheme: Stepping Stones  Incentive System Types  Incentive Approach Types  Incentive Slabbing: Linear & Logarithmic  Introduction to “Incentive Index”  Divisional Index  Multiplicative Index  Divisional vs. Multiplicative: Head to Head  Incentive vs. Penalty  Penalty Plan 2
  • 3. Incentive Theory  Let’s consider an example:  Production Capacity: 100 units  Production Target: 80 units (i.e. 80% of Capacity) 3 0 units 80 units 100 unitsEntitlement for Incentive 0 units 80 units 100 units 5 5 5 5 Incentive given for these extra units
  • 4. Incentive Theory4 0 units 80 units 100 units Ascending Incentive Rate 5 5 5 5
  • 5. Quantity vs. Quality  Incentive is given based on increased quantity.  With increased quantity, there is a possible chance to trade-off quality. 5
  • 6. Focus on Quality  So, while giving incentive to motivate our work-force for increased quantity…….  We need to keep “Quality” also in our mind 6
  • 7. Setting an Incentive Scheme: Stepping Stones Set the incentive system Set the Approach Set the incentive slabs Set the incentive index Fix the incentive rate 7
  • 8. Set the incentive system 8
  • 9. Incentive System Types:9 Name of System Method of Rate Determination Major Characteristics Straight piecework system Units of production per time frame Straight rate after entitlement Taylor Differential piece rate system Units of production per time frame Differential rate at each slabs after entitlement Standard hour system Time frame per unit production Rate fixed if time of production is less than expectation Halsey 50-50 system Time frame per unit production Profit shared on 50- 50 basis for saving time in production
  • 11. Incentive Approach Types:  Approach:  Individual incentive approach  Ex: Goods produced by a single individual  Team incentive approach  Ex: Goods produced by a group of individuals 11
  • 12. Set the incentive slabs 12
  • 13. Incentive Slabbing: Linear & Logarithmic  Equal units in each slab  Differential rate should be introduced  E.g. incentive entitlement is 1000 units/shift & capacity is 1500 units/shift.  Linear slabbing for 5 slabs will be: 13 Slabs Units Produced Slab 1 100 Slab 2 100 Slab 3 100 Slab 4 100 Slab 5 100 0 500 1000 1500 2000 Linear Slabbing Linear Slabbing
  • 14. Incentive Slabbing: Linear & Logarithmic  Differential units in each slab  Equal/Differential rate should be introduced  E.g. incentive entitlement is 1000 units/shift & capacity is 1500 units/shift.  Linear slabbing for 5 slabs will be: 14 Slabs Units Produced Slab 1 193 Slab 2 114 Slab 3 80 Slab 4 62 Slab 5 51 0 500 1000 1500 2000 Logarithmic Slabbing Logarithmic Slabbing
  • 15. Incentive Plan: Example  Let’s consider an incentive plan for a shop floor consisting 30 associates working in 3 shifts having 10 individuals in each shift.  The parameters are as follows:  Number of individuals: 10 persons  Number of work-days in a month for a shift: 20 days  Incentive system: Taylor differential piece rate system  Approach: Team Approach (Single Shift) 15
  • 16. Incentive Slabs: Example  Incentive Slabs according to team approach  Type: Linear 16 Slab No Units of good produced per shift Entitlement 1000 Slab 1 1100 Slab 2 1200 Slab 3 1300 Slab 4 1400 Slab 5 1500
  • 17. Set the incentive index & Fix the incentive rate17
  • 18. Introduction to… “Incentive Index”  “Incentive Index” is the highest monetary value a company is willing to pay to its receptor team or individual for a given time period (e.g. a month) based on the performance of a given time frame.  For team incentive plan:  When the receptor is a team, it’s called “Divisional Index”  When the receptor is an individual, it’s called “Multiplicative Index” 18
  • 19. Divisional Index: Example  Lets consider that management has decided to give highest 10,000 BDT as incentive to a specific shift for a month based on the performance of each work-day  Here,  Receptor type: Team  Time period: 1 month  Time frame: Single Work-day  Highest monetary value: 10,000 BDT  As the receptor is a team, the incentive index in this case will be “Divisional Index” 19
  • 20. Divisional Index: Example  Highest monetary value: 10,000  Number of working days in a month: 20  Divisional index: 10000/20 =500  So, highest 500 BDT will given as incentive to an entire shift for a single working day 20
  • 21. Divisional Index: Incentive Rate Fixing Example 21 0 units 80 units 100 units Ascending Incentive Rate 5 5 5 5
  • 22. Divisional Index: Incentive Rate Fixing Example Divisional Index % of Index BDT Incentive Slabs Extra units produce d Incentive Rate, BDT/unit produce d 1000 500 10% 50 1100 100 0.5 15% 75 1200 100 0.75 20% 100 1300 100 1 25% 125 1400 100 1.25 30% 150 1500 100 1.5 22
  • 23. Divisional Index: From Time frame to Time period Days Units Produced Extra units after entitlement Incentives earned, BDT Day 1 1155 155 91.25 Day 2 920 0 0 Day 3 1455 455 432.5 Day 4 1305 305 231.25 Day 5 1275 275 200 23 For day 1, Extra units produced after entitlement = 155 units Incentive earned = 100 x 0.5 + 55 x 0.75 = 91.25 BDT Total incentive earned in first 5 days = 955 BDT Slab No Rate Slab 1 0.5 Slab 2 0.75 Slab 3 1 Slab 4 1.25 Slab 5 1.5
  • 24. Divisional Index: From Time frame to Time period  For simplification, lets consider that the next 15 days for this shift goes just like the first 5 days  Therefore, total incentive earned by this shift for a total of 20 days ( a time period) will be = 955 x 4 = 3820 BDT  From previous slides, Number of individuals in this shift = 10  Therefore, Incentive earned by a single person of this shift for a time period = 3820/10 = 382 BDT 24
  • 25. Incentive Plan: Example  Let’s consider an incentive plan for a shop floor consisting 30 associates working in 3 shifts having 10 individuals in each shift.  The parameters are as follows:  Number of individuals: 10 persons  Number of work-days in a month for a shift: 20 days  Incentive system: Taylor differential piece rate system  Approach: Team Approach (Single Shift) 25
  • 26. Multiplicative Index: Example  Lets consider that management has decided to give highest 1,000 BDT to each individual of a specific shift for a month based on the performance of that shift of each work-day  Here,  Receptor type: Individual  Time period: 1 month  Time frame: Single Work-day  Highest monetary value: 1,000 BDT  As the receptor is an individual, the incentive index in this case will be “Multiplicative Index” 26
  • 27. Multiplicative Index: Example  Highest monetary value: 1,000  Number of working days in a month: 20  Multiplicative index: 1000/20 = 50  So, highest 50 BDT will given as incentive to each individual of that shift for a single working day 27
  • 28. Multiplicative Index: Incentive Rate Fixing Example 28 0 units 80 units 100 units Ascending Incentive Rate 5 5 5 5
  • 29. Multiplicative Index: Incentive Rate Fixing Example Multiplica tive Index % of Index BDT Incentive Slabs Extra units produced Incentive Rate, BDT/unit produced 1000 50 10% 5 1100 100 0.05 15% 7.5 1200 100 0.075 20% 10 1300 100 0.1 25% 12.5 1400 100 0.125 30% 15 1500 100 0.15 29
  • 30. Multiplicative Index: From Time frame to Time period Days Units Produced Extra units after entitlement Incentives earned, BDT Day 1 1155 155 9.125 Day 2 920 0 0 Day 3 1455 455 43.25 Day 4 1305 305 23.125 Day 5 1275 275 20 30 For day 1, Extra units produced after entitlement = 155 units Incentive earned = 100 x 0.05 + 55 x 0.075 = 9.125 BDT Total incentive earned in first 5 days = 95.5 BDT Slab No Rate Slab 1 0.05 Slab 2 0.075 Slab 3 0.1 Slab 4 0.125 Slab 5 0.15
  • 31. Multiplicative Index: From Time frame to Time period  For simplification, lets consider that the next 15 days for that shift goes just like the first 5 days  Therefore, total incentive earned by each individual of that shift for a total of 20 days ( a time period) will be = 95.5 x 4 = 382 BDT  For reconciliation, total amount given to that shift for a month= 382 x 10 = 3820 BDT 31
  • 32. Divisional vs. Multiplicative: Head to Head Divisional Index Multiplicative Index Favorable for teams with equal members & equal capacity within same dept. & not prone to sudden change in number of members Favorable when setting a universal incentive scheme across shifts of different departments. As the receptor is a team, individual earning from incentive is hard to control As the receptor is an individual, earning of every individual can be controlled With a change in capacity & personnel, both slabs & index should be changed With a change in capacity & personnel, only slabs need to be changed Different index for diff. departments. Therefore, so many indices. Hard to be documented bcoz of changing. A single index for all the departments & shifts. 32
  • 33. Incentive vs. Penalty  In order to motivate production, incentives are rewarded for increased quantity.  Likewise, in order to maintain quality benchmark, penalties are imposed on defects.  Example:  Lets consider entitlement is on 1000 units/shift.  Production in a certain shift is 1155 units.  Of these units, 20 is defective. 33
  • 34. Penalty Plan  Penalty can be imposed in two ways:  Active Penalty:  Incentive is given on extra 155 units after entitlement. For the 20 defectives, defective rate is determined. For that defective rate, penalty rate is introduced.  So, 95.5 BDT is the incentive gain per person on that day (155 units extra production)  Defective rate: 20/1155 = 0.0173  Defective rate slabs are introduced.  Penalty rates are introduced.  Penalty loss is being calculated.  Ultimate gain = Absolute of (Incentive gain – Penalty loss) 34
  • 35. Penalty Plan  Penalty can be imposed in two ways:  Passive Penalty:  Incentive is given on the good units only i.e. 1155 - 20 =1135 units  There is not direct penalty.  Therefore, there will be either 0 or (+)ve gain in ultimate.  Actually, there is no penalty!!! 35

Editor's Notes

  1. Nothing is here actually