Existing Situation at Rankala Lake
Part of the Lake is infested with Water HyacinthPart of the Lake is infested with Water Hyacinth
and polluted affecting the aquatic life as well as
creating mosquito menaceFortress
Proposed Integrated Plan for Rankala Lake.
EE
E
A
B
C
D
Proposed convergence space. 
Proposed artist village.
Proposed State‐of‐Art  Museum.
D Proposed  cultural  complex ‐ food plaza.
E Proposed  Theme gardens.
F Cleaning of the Lake  / Rejuvenation.
E
E
A
B C
D
Fortress
Proposed Cultural Center at Rankala Lake
• Performing Spacese o g Spaces
• Multi-arts complex
• Museum of Fine Arts
• A Library
Indoor and outdoor auditoria• Indoor and outdoor auditoria
Estimated Cost – 43 Cr.
Fortress
Proposed Museum of wrestling events in Kolhapur region
KASBAG
MAIDAN Proposed  location  for
Gallery of  wrestling  
history‐events.
Estimated Cost – 5 Cr.
Fortress
Outer Circle Proposal: Koteshwar Mandir & Kotitirth Development
Existing Status
O 1 5 l l i it• Over 1.5 lc annual visitors
• Garden with pathway overlooking the sacred lake
• Good Seating arrangement
• Beautiful Lake view
S i S th M di• Swami Samarth Mandir
Key Issues
• Approach roads are not well maintainedpp
• No public utility facilities
• No planned parking area
• Grossly inadequate infrastructure
Fortress
I
Proposed Holistic Plan for Kotithirth Lake
I
Issues:
• Approach roads are not well maintained
• No public utility facilities
J
F
I
• No planned parking area
• Grossly inadequate infrastructure
A
G
E
HI
C
D
Proposed Activities –
B
E
Restaurant- organic food
Meditation hall-
Open air amphitheater-
Museum
A
B
C
E
G
F
Fast food
Shops-
Laser show Musical fountain-H
Museum
I Ghat development
Mythological wall paintingsJ
C
D Yoga hall / center
Exhibition hall
Estimated Cost – 13 Cr.
Fortress
Beautification of City Entry Points & Chowks
Map showing Locations of Entry Points ofp g y
under consideration for Beautification
Estimated Cost – 7 Cr.
Fortress
Proposal for Theme Gardens
Ramkala Choupati  Nehru Garden Tembhalai Garden Town Hall Garden
Name of Garden Area Themes & attractionsName of Garden Area Themes & attractions
1.Padmavati Garden 4000 sq.mt. Play area, pathways, fantasy garden etc.
2. Rankala garden. 22000 Sq.mt. Acupressure pathways, aroma gardens, Play area etc.
3 Nehru garden 8000 sq mt Rose garden Hibiscus garden etc3. Nehru garden. 8000 sq.mt. Rose garden, Hibiscus garden etc.
4. Tembalai garden 4800 sq.mt. Play area, sculpture park, Butter fly garden etc.
5. Town hall garden. 4000 sq.mt. Rare species of plants,
Fortress
• A perennial river Panchaganga flowing
River Ghat Development – Existing Situation
adjacent to Kolhapur City periphery over
20KM stretch
• 2 Major Ghats at Shivaji Bridge (500 m) &
Datta Mandir (500 m) are poor in conditionatta a d (500 ) a e poo co d t o
• Religious & heritage structure are in
existence
• Non existence of social infrastructure
No facility for Bath or Holy Dip• No facility for Bath or Holy Dip
• Unclean & inadequately maintained ghat
precinct
• Unclean and Dirty water due to disposal of
religious waste, emersion of idols, Cloth &
Cattle washing
• Poor approach roads, Lighting to the
ghatsg
• No safety and security arrangement
Fortress
• Development of 1km stretch at two locations
River Ghat Development - Proposed
p
on Right bank focusing on rejuvenation of river
• River front development at multiple location
would enable decongestion of crowd &would enable decongestion of crowd &
promoting one of the major tourism attractions
• Facilitate & ensure clean environment around
th h tthe ghats
Ghat, Walking Path Parks & Gardens Lighting
• Restoration & Conservation of • Public & Children’s parks • Lighting for regular night timeRestoration & Conservation of
existing Structures
• Series of Ghat in step & ramps
• Wide pedestrian walkways
• Seat, benches & other Sculpture
Public & Children s parks
• Soil erosion & Slope stabilization
• Roadside & Plaza Parking
Lighting for regular night time
usage
• Lighting for special occasions
Movement Network Social Infrastructure
Seat, benches & other Sculpture
• View posts cum Lifeguard stations
• Information / facilitation centre
• PA System
• Public Toilet
• Approach Road & Signage
• Car & Bicycle parking
• Taxi / Rickshaw Stand
• Mela / Exhibition Space
• Water sports – Rowing, boating
Revenue GenerationPublic Toilet
• Drinking water
• Police post
Revenue Generation
• Commercial area – Shops
• Food Courts / Kiosks
• Parks Estimated Cost – 20 Cr.
Fortress
Leisure Tourist Destination Development – Panhala Fort
12th Century construction, at 977.2 m
altitude
Largest of all Deccan forts having 7Largest of all Deccan forts having 7
Km long fort wall with steep slop
beneath
Associated with the life of great
Maratha ruler, Chhatrapati Shivaji
Maharaj.
Panhala - Rich heritage & Tourist attractionPanhala - Rich heritage & Tourist attraction
Fortress
Leisure Tourist Destination Development – Panhala Fort
Development of Panhala as a historical & Scenic Appeal
Development ComponentDevelopment Component
• Entrance Road, Ramp & Steps
• Conservation plan for Panhala Fort
• Repairs of fort wall
• Soil conservation, Landscaping &
Pl t tiPlantation
• VIP Guest House
• History research centrey
• Tourist amenities / Facilities
Estimated Cost – 15 Cr.
Fortress
Leisure Tourist Destination Development – Pawankhind
Development Componentp p
• Entrance Road, Ramp & Steps
• Museum displaying history of brave
Marathas
• Statue of Veer Bajiprabhu Deshpande
• Viewers GalleryViewers Gallery
• Tourist amenities / facilities
Estimated Cost – 3 Cr.
Fortress
Leisure Tourist Destination Development – Palaces
Development Component
Estimated Cost – 10 Cr.
• Conservation plan for Places in Kolhapur City
• Facility upgradation
Fortress
Proposed Developments in Infrastructure
Fortress
City & Regional Infrastructure Rs Cr
Proposed Infrastructure Development Plan
City & Regional Infrastructure Rs. Cr.
City Roads 149
City Ring Road 150
Land Acquisition for City Ring Road 150Land Acquisition for City Ring Road 150
City Access Roads 85
Pedestrian / Walk Ways in the City 45
Railway Infrastructure / Amenities Improvement 20
Airport Development 102
Land Acquisition for Airport Development 165
Public Transportation Facilities ( MSRTC / KMT) 65
Parking Infrastructure 30
Water Supply 84
Water Supply Augmentation – Special Project 414
S N t k d STP 280Sewerage Network and STP 280
Solid Waste Management 15
Health Infrastructure Improvements 30
Power 82Power 82
Total 1866
Fortress
City Roads – Existing Status
• Non-user-friendly streets for pedestrians, NMVs and the
di bl ddisabled
• Non existence of Foot over bridge, Subway or RUB at
traffic Congested Squares / points
• High Pedestrian Influx especially in the time of Festivals/
Events
• Poor road geometrics and riding surfacesg g
• Elements of safety inadequately addressed
• Inappropriate cross sections
• Poor street lighting & Road Signage• Poor street lighting & Road Signage
• Unplanned parking lane / zone
• Non existence of Multifunctional zone leads to reduction
i ff ti din effective road uses
Total Roads within the City Limit : 571.00 KM (415.00 KM with BT Surface)
Connectivity and Quality of Roads requires improvements
Road development proposed under IRDP (On BOT basis) : 49.99 KM ( Rs.240 cr)
Fortress
Movement Network – Proposed
CS
T
Mahalaxmi
K ti Ti th
Bhawani
Mandap
Bindu
Chowk
Rankala
Lake
Koti Tirth
N d R d 8 K
Mahalaxmi surrounding Road– 18Km Mahalaxmi
Ring Road – 40 Km
IRDP Road – 49.99 Km
Navdurga Road – 8 Km
NH 04
City Access Roads Fortress
City Roads – Proposed
• Appropriate Road section for all users
A i t R d G t i ith idi S f
9 m wide Typical Section
• Appropriate Road Geometric with riding Surface
• Streetscape & urban forestry properly addressed
• Street Furniture, Safety barrier , signage & Street
Lighting
• Controlled traffic lanes / ways
Roads proposed under Holy City Program : 26 KM (32 Roads)
Est. Cost – Rs. 42 Cr.
Fortress
Outer Ring Road – Proposed
• 45m wide Ring Road with 4 Lane connecting NH
0404
• Bypassing the City from Radhnagari, Gargoti,
Ratnagiri Road and other districts
Schematic
Mahalax
mi
Schematic
Ring Road : 40 Km appx
Est. Cost – Rs. 300 Cr.
(Road Development – Rs. 150 Cr. & Land Acquisition – Rs. 150 Cr.)
Fortress
Existing Status
K lh Cit h lti l E t i t
City Access Roads
Existing Status
• Kolhapur City has multiple Entry points
• Shivaji Bridge (Constructed in A.D. 1877) on
Pachganga River needs immediate attention
• Narrow and poor roads without dividers & foot pathNarrow and poor roads without dividers & foot path
• Lack of street furniture
• Dilapidated sewerage system has adverse effect on
roads
Proposed
• Road development & maintenance affected due to
inadequate funds
Proposedp
• Majority of the roads will widened to 4 lanes with
appropriate section & roadside amenities
• Provide smooth Entry to cityy y
• Connect the other important religious / tourist
destination
• City Access Roads : 25 Km
Estimated Cost – Rs. 85 Cr.
• Other Link Roads : 60 Km
• Bridge at Panchganga river
Fortress
Pedestrian Infrastructure – Existing Status
• Low road capacities & pedestrian influence
• Non-user-friendly streets for pedestrians,y p ,
NMVs and the disabled
• Only 1 FOB is functional at Station Road
• Narrow road width is main constraint forNarrow road width is main constraint for
dedicated pedestrian lane
• Unsafe road crossings
• Footpath encroached by Hawker / MobileFootpath encroached by Hawker / Mobile
Vendor
• Most of road made One way / no vehicular
resulting in traffic congestion on roadsresulting in traffic congestion on roads
Pedestrian infrastructure needs immediate
improvement to meet the requirement of user
Fortress
Pedestrian Infrastructure - Proposed
• Developing a sustainable Pedestrian infrastructure in city
th t t th i t f P d t i &that meets the requirements of Pedestrian users &
Hawkers
• 4 meter wide for pedestrian movement & 7 meter wide for
pedestrian plus Hawker’s zonepedestrian plus Hawker s zone
• Covered with decorative Polycarbonate roofing sheet
• Staircase & an escalator
• Underground cabling & Lighting
Proposed Skywalk / FOB
• Adequate safety & waste disposal arrangement
Proposed Skywalk / FOB
Sky walk at Railway Station to Dabholkar Chowk to Central Bus Stand
Sky walk at Shivaji Market to KMC Office to Bhavani Mandap
Sky walk at Venus Corner to Kondaol LaxmipuriSky walk at Venus Corner to Kondaol , Laxmipuri
Skywalk at Central Bus Stand to Rajarampuri Road
Foot over Bridge at New Shahupuri
Foot Over Bridge at Ganpati Mandir Chaowk Rankala LakeFoot Over Bridge at Ganpati Mandir Chaowk, Rankala Lake
Foot Over Bridge at Shivaji Stadium
Estimated Cost – Rs. 45 Cr.
Fortress
Railway Infrastructure – Existing Status
Kolhapur is connected to Pune, Mumbai, Delhi,
Nagpur Ahmadabad & BangaloreNagpur, Ahmadabad & Bangalore
Direct trains are available to cater the routine
passenger flow
One of the important destinations for Deccan
Odyssey – The famous luxury train of India
Shri CSMT Building – A heritage structure
Two Platforms with basic facilities
Only one Foot Over BridgeOnly one Foot Over Bridge
Only one entry provided to Station from North side
Inadequate waiting hall & Passenger amenities
Upgradation & development of Railway
infrastructure require to cater the Passenger flow
Fortress
Railway Infrastructure – Proposed
• Improve the connectivity on existing routes• Improve the connectivity on existing routes
• Add new routes / trains to other cities
• Conservation & restoration of Shri Chhatrapati Shahu
Maharaj Terminus Building A heritage structureMaharaj Terminus Building – A heritage structure
• Construction of New Railway station building with all
passenger amenities Like waiting hall, Art gallery etc.
• Extension & upgradation of existing Platforms with• Extension & upgradation of existing Platforms with
passenger amenities
• Construction of additional Platform
• New Foot over Bridge & Entry to Railway station from• New Foot over Bridge & Entry to Railway station from
South
• Improvement & repairs of the Babubhai Parikh Railway
Under BridgeUnder Bridge
• Categorized Parking zones
• Beautification (Landscaping & tree plantation) of the
Railway station premises
Estimated Cost – Rs. 20 Cr.
a ay stat o p e ses
Fortress
Airport Infrastructure – Existing Status
• Daily Air service by Deccan Airways to
Mumbai & Belgaon
• Operation & Maintenance by MIDC
• Approximately 10000 Sqft. Terminal
Building with limited amenities
• 45 M wide &1 3 Km long Runway45 M wide &1.3 Km long Runway
• Increasing Air traffic due to development of
Industrial areas at & around the Kolhapur
Development of Airport require for the improvement in
Air Connectivity
Fortress
Airport Infrastructure – Proposed
Development of New Modern Airport &
Connecting Kolhapur by Air to important
cities
D l t C tDevelopment Component -
• Up gradation & expansion of runway as per
Boeing Standard
• Aprons & Taxiway
• New Navigation Facilities
• Night Landing Facilitiesg g
• Airport Peripheral Wall
• Internal Road & Parking Area
• 300 Passenger capacity Terminal Building• 300 Passenger capacity Terminal Building
• Electrification
• Airport Approach Road & other development
Estimated Cost – Rs. 267 Cr.
(Land Acquisition – Rs. 165 Cr. & Development – Rs. 102 Cr.)
Fortress
Existing Status
Transport Infrastructure - MSRTC
Existing Status
• Kolhapur City has 3 bus stand at Dabholkar
Chowk Rankalvesh & Sambhaji NagarChowk, Rankalvesh & Sambhaji Nagar
• Central Bus Stand & Depot spread over 8 Acres
of Land
• Lack of Basic passenger / tourist amenities
Proposed
• Lack of Basic passenger / tourist amenities
• Surrounded by Hawkers
Proposed
Proposed
Development of Bus Stand building with
Passenger amenities, platform & apron at
p
1. Central Bus Stand
2. Rankalavesh Bus Stand
3. Sambhaji Nagar Standj g
Estimated Cost – Rs. 35 Cr.
Improvement in the Regional level transport connectivity
Fortress
• Kolhapur Municipal Transport
Transport Infrastructure (KMT) – Existing Status
(KMC undertaking) plies 117
buses over 27 routes in the city
• 3 Nos. of Terminus at Bhavani
Mandap, Shahupuri &
Gangavesh
• 285 Nos. of bus stop
D t T i d b• Depots, Terminuses and bays
warrant upgradation
Buses are in poor condition• Buses are in poor condition
• Service level warrants
improvementimprovement
KMT Service needs immediate improvement for the reliable and regular transport facility to Citizen
Fortress
• Transformation of Public transport for public & Pilgrims
• Development of new modern bus Terminus / depot with facilities as
Transport Infrastructure (KMT) – Proposed
Development of new modern bus Terminus / depot with facilities as
• Bus bays with emergency yard
• Parking Zones for Bus, Rickshaws &
NMV
• Seating Zones
• Administrative block
• Public utilities like toilet, water,
• Small shops like food courts,
newspapers couriers & Convenience
• No. of Routes & frequency of buses will be enhanced
• Seating Zones
• Proper signage
• Cloak rooms for passengers
newspapers, couriers & Convenience
stores
• Provision 200 Nos. of Bus shelter with drinking water & informatory Map
• Dedicated daily bus service for Navdurga Darshan & Kolhapur Darshan
Site Particulars / Facilities
Bindu Chowk (Shifting of existing
Bhavani Mandap depot)
Main Central Bus Terminus (61000 Sqft)
Shahupuri Bus Terminus with Commercial (22000 Sqft)
G h B T i ith C i lGangavesh Bus Terminus with Commercial
Panchganga Ghat Bus Terminus with Commercial
Central Bus Stand Bus Terminus
Railway Station Bus TerminusRailway Station Bus Terminus
Airport / MIDC Area Bus Terminus with Commercial
Estimated Cost – Rs. 30 Cr.
Fortress
Existing Status
Parking Infrastructure
Mahalaxmi marketMahalaxmi market
Bindu ChowkBindu Chowk
Existing Status
• Unplanned & unorganized Parking on road,
Footpath leads to traffic congestion
• Unorganized parking leads to reduction in
Kapilteerth MarketKapilteerth Market
Unorganized parking leads to reduction in
effective width of road & inconvenience to citizen
/ Pilgrim
Proposed
Multistoried Parking for NMV, LMV at Mahalaxmi
Temple Surrounding to control movement
1. Mahalaxmi Market
2. Kapeelteerth Market
3 Bindu Chowk3. Bindu Chowk
Estimated Cost – Rs. 30 Cr.
Fortress
Water Supply System - Existing Status
Existing Raw Water Source
1 Bhogawati River; Balinga Works; 41 MLD Cap; 8 Km away
Water Supply Network Coverage
Length of Main Transmission Line: 57 Kms1.Bhogawati River; Balinga Works; 41 MLD Cap; 8 Km away
2.Panchganaga River via Bawada Water Works; 20 MLD
Capacity; 6 Kms Panchganga River vis Puikhadi Works; 30
MLD; 11 Kms away
Length of Main Transmission Line: 57 Kms
Length of Distribution Network: 400 Kms
Network Coverage in Main City Area; 80%
Network Coverage in Extended City Area: 20%; y
3.Kamlamba Tank; Kalmba Works; 08 MLD; 3 Km away
Total Capacity Available: 99 MLD
g y
No. of Metered Connection: 66, 625
key Issues
1. Renovation and Augmentation of Pumping Capacities
2. 100% Metering for the purpose of recovering projected Water
Revenues
3. Augumenataion of Balinga Water Works; Temblai Dam Area
Water Scheme; and Kalamba Water WorksWater Scheme; and Kalamba Water Works.
4. Arresting continuous Pollution of Panchganga River by
tapping & diverting Sewage flowing through Jayanti and
Dudhali Nallah, and diverting the sewage to proposed STP of
100 MLD Capacity with ST Facilities.
5. Developing Alternative Source of Clean Raw Water Supply
Source from Dudhganga River at Kalammawadi Dam, adding
92 MLD Capacity.92 MLD Capacity.
6. Proper Water Management for Panchganga and Bhogawati
River so as to adequately establish balance between
Agriculture Usage and City Water Supply Demand.
Fortress
Water Supply System – Proposed Priority Works
Balinga Water Works Kalamba Water Works Temblai Area W/S Scheme
H d W k WTP f 5 MLD C it O GSR f 2 MLD C itHead Works
Pumping Machineries
Rising Main; Dia 700 mm, 2 Kms
Length
WTP of 5 MLD Capacity
Gravity Main; Dia 500 mm; 4 Kms in
Length; From Kalamba Lake to
Kalamba WTP
One GSR of 2 MLD Capacity
One Feeder Main; Dia 450 mm; 2.5 Kms
in Length
Additional Distribution Network of about
Up gradation of 41 MLD WTP to
60 MLD Capacity
Rising Main; Dia 700 mm; From
Balinga WTP to Chmbukadi
Kalamba Lake De-silting and Kalamba
Dam Dam Strengthening
10 Kms in Length
Balinga WTP to Chmbukadi
Gravity Main; Dia 750 mm; 6 Kms
Length; From Chambukadi to
Bindu Chowk
ESR’s of 2 MLD Capacities, each
at Gangavesh & Mirajkar Tikati
Estimated Cost: Rs. 60 Crores Estimated Cost: Rs. 17.50 Crores Estimated Cost:: Rs. 6.35 Crores
Estimated Funds Required for Water Supply Augmentation Plan: Rs. 84 Crores
Under UIDSSMT Scheme, Out of the Total Investment Gap Identified i.e. Rs. 73.95 Crores at 2005-06 DSR Rates, only about
58.44 Crores has been sanctioned. In addition to above, Rs. 84 Crores as discussed above is required on Priority basis to
upgrade the City Water Supply System
Fortress
Water Supply Source Augmentation: Special Project
Need for Alternate Water Supply Source
Continued -
pp y
• Heavy Pollution of Panchganga River due to Sugar
Mills, Tannery Units & Untreated Sewage released
from Small Town, on the upstream side
L W t A il bilit i P h Ri St• Low Water Availability in Panchganga River Stream
for almost 3 to 5 Months, resulting into under
capacity lifting for Drinking purpose
New Source as Kalmmawadi Dam
By Tapping Dudhganga Storage Reservoir (28 TMC
Capacity) at Kalmmawadi Village, 92 MLD Raw Water
Availability can be ensured
Suggested Project Development Routes: -Suggested Project Development Routes: -
BOOT: Viability Gap Funding / SPV
Soft Loans form Foreign Development Banks
Fortress
Water Supply Source Augmentation: Special Project
Improvements & Argumentation to KOLHAPUR W.S.S Ph II (Source as Kalmawadi Dam)
S N Name of Sub-Works Cost Estimates in Cr
Continued -
S. N. Name of Sub-Works Cost Estimates in Cr.
1. Working Survey 0.60
2. Design, Pro. & Const. of Dam Out let modifications, Inlet Arrangements upto Intake, Tower (Work of Irrigation Dept. 1.15
3. Design, Pro. & Const. 7.2 m Dia Intake-cum-Distriburtion Tower upto 64 m (Work of Irrigation Dept. 2.20
4. Pro. Const. Tunnel of 63 sq.m Area 600 m, length at CH. 5.2 Kms. 1.85
5. Gravity Main (Raw Water) of Dam to Sump, M.S. Pipe 10 mm Thk., L=53.10 Kms, OD Dia 1820 mm 265.60
6. Rising Main from Sump to Puikahdi WTP M.S. Pipe 10 mm thk., 1.25 Kms 12.35
7. WTP (92 MLD) 7.82
8. Cross Section to Chambukhadi 0.60
9. Pumping Machinery (R/W) at Sump (1000 BHP, 4 Nos., 50% Standby) 8.55
10. Pump House 0.65
11. Design, Prov. & Const. Sump Cap. 47,50,000 Ltrs. 0.53
12.. Misc. Works 27.90
Total Net Cost Rs 329 80Total Net Cost, Rs. 329.80
Add. MJP Centage Charges @14% 46.17
Total Gross Amount 375.97
Add 10% Escalation on Net Cost 37.60
Gross Cost 413.57
The Alternative Source Development Project, as one time Intervention, would address the Water Supply Situation on long-term basis
Fortress
Sewerage System: Existing Status
The Interception & Diversion Works as proposed for the
4 M j O N ll h ’ d ib d b l4 Major Open Nallahs’ are as described below –
Dudhali
Nallah Basin
Jayanti
Nallah
Line Bazaar
Nallah
Bapat
Campa a as a a
Zone
a a
Zone
Ca p
Nallah
Zone
Sewage
flowing
Sewage
flowing
Sewage
flowing
Sewage
flowingg
through
Dudhali
Natural Open
Nallah is
Intercepted &
g
through
Jayanti
Natural
Open
Nallah is
g
through
Line Bazaar
Natural
Open
Nallah is
g
through
Bapat
Camp
Natural
OpenIntercepted &
diverted by
Pumping
Station 4 to
Jahyanti
Nallah is
Intercepte
d &
diverted by
Pumping
Nallah is
proposed
to be
pumped to
Receiving
Open
Nallah is
proposed
to be
pumped
Nallah Station 1
to
Receiving
Chamber
at Kasba
Chamber at
Kasba
Bavada
to
Receiving
Chamber
at Kasba
Bavadaat Kasba
Bavada
Bavada
Fortress
Sewerage System: Existing Situation Continued -
Topographically, the KolhapurMunicipal Limits is divided into 4 Drainage Zones, and details of these Zones are described below -
D dh li N ll h B i J ti N ll h Z Li B N ll h Z B t C N ll h ZDudhali Nallah Basin Jayanti Nallah Zone Line Bazaar Nallah Zone Bapat Camp Nallah Zone
Catchment Area includes Sector 4 & 5
mainly, and some parts of Sector 1
Total Catchment Area is about 1600
Ha covering 2 0 Lakhs of present
Mostly sewered Zone with
Catchment Area which includes
parts of Sector 1; 2 & 4
Total Catchment is about 2100
Totally un-sewered Zone, with
Catchment Area Covering most
of the Area of Sector 6
Total Catchment is about 500 Ha
Totally un-sewered Zone,
with Catchment Area
Covering most of the Area of
Sector 6Ha, covering 2.0 Lakhs of present
Population
Total Length of Main Sewer is 26
Kms., carrying 26 MLD of Sewage
Total Catchment is about 2100
Ha, covering 7.50 Lakhs
Population
Total Length of Main Sewer is
63 Kms, carrying 20 MLD of
Total Catchment is about 500 Ha,
covering 0.35 Lakhs of
Population
Total Length of Main Sewer is 9.0
Kms, carrying 5..2 MLD of
Sector 6
Total Catchment is about 400
Ha, covering 0.50 Lakhs of
Population
Total Length of Main Sewer is
Sewage Sewage, currently utilized for
Irrigation in Catchment, itself
23 Kms, carrying 6.8 MLD of
Sewage
Sewage flowing through Dudhali Natural
Open Nallah is Intercepted & diverted
by Pumping Station 4 to Jahyanti Nallah
Sewage flowing through Jayanti
Natural Open Nallah is
Intercepted & diverted by
Sewage flowing through Line
Bazaar Natural Open Nallah is
proposed to be pumped to
Sewage flowing through Bapat
Camp Natural Open Nallah is
proposed to be pumped toby Pumping Station 4 to Jahyanti Nallah Intercepted & diverted by
Pumping Station 1 to Receiving
Chamber at Kasba Bavada
proposed to be pumped to
Receiving Chamber at Kasba
Bavada
proposed to be pumped to
Receiving Chamber at Kasba
Bavada
26 MLD 20 MLD 5 2 MLD 6 80 MLD26 MLD 20 MLD 5.2 MLD 6.80 MLD
Existing STP (Primary Treatment only) is of 39.80 MLD Capacity while Treatment Demand is 58 MLD
Due to Usage of Natural Open Nallah for conveyance of Sewage, Storm Water flow into these along the natural Slopes during
Monsoon Season, leading to over-flow situation at Interception Site
Usage of Open Nallah are also prone to mixing of Solid Waste into the Sewage, and contributes to Air-borne and Water-borne
Diseases
Thus, there exists basic need for Rising Mains along the Natural Nallah, Interception & Diversion Works, Pumping Machineries
and Augmented Secondary Treatment Capacity, present load 58 MLD, and 100 MLD as Year 2025 Load
Fortress
Sewerage System: Priority Works & Investment Requirements
Dudhali Nallah Basin Jayanti Nallah Zone Line Bazaar Nallah Zone Bapat Camp Nallah Zone
1 Interception & Diversion Works (K T 1 Interception & Diversion Works 1 Interception & Diversion Works 1 Interception & Diversion1. Interception & Diversion Works – (K.T.
Weir) (Length – 20.00 m x Width – 4.00
m)
2. Screen Chamber / Sump Well (6.00 m X
3.70 m & 11.00 m x 11.00 m) – 2 Nos.
1. Interception & Diversion Works –
(K.T. Weir) (Length – 20.00 m x
Width – 10.00 m)
2. Screen Chamber / Sump Well
(6.00 m X 3.70 m & 11.00 m x
1. Interception & Diversion Works –
(K.T. Weir) (Length – 20.00 m x
Width – 2.00 m)
2. Screen Chamber / Sump Well
(6.00 m X 3.70 m & 7.50 m x
1. Interception & Diversion
Works – (K.T. Weir) (Length
– 20.00 m x Width – 2.00 m)
2. Screen Chamber / Sump
Well (6.00 m X 3.70 m &
3. Pumping Machinery – 150 HP – 3 Nos.;
75 HP – 2 Nos.
4. Rising Mains –
a) Dia 600 mm D.I. K-9 L – 2000 M
11.00 m) – 2 Nos.
3. Pumping Machinery – 300 HP – 2
Nos.
4. Rising Mains –
a) Dia 750 mm D I K 9 L 2300 M
3.40 m) – 2 Nos.
3. Pumping Machinery – 75 HP – 3
Nos. & 25 HP – 2 Nos.
4. Rising Mains –
a) Dia 750 mm D I K 9 L 2300 M
7.50 m x 4.00 m) – 2 Nos.
3. Pumping Machinery – 100
HP – 3 Nos. & 40 HP – 2
Nos.
4. Rising Mains –a) Dia 750 mm D.I. K-9 L – 2300 M
b) Dia 1000 mm D.I. K-9 L – 4600 m
a) Dia 750 mm D.I. K-9 L – 2300 M
b) Dia 1000 mm D.I. K-9 L – 4600 m
4. Rising Mains
a) Dia 350 mm D.I. K-9 L –
2000 M
Estimated Cost of Above Works: 280 Crores
1. Interception & Diversion Works: 10 Cr.
2. Rising Mains: 70 Cr.
3. Gravity Mains: 50 Cr.
4 P i M hi i 50 C4. Pumping Machineries: 50 Crores
5. Secondary Treatment Plant (STP) of Capacity 100 MLD: 100 Cr.
Under UIDSSMT Scheme, Out of the Total Investment Gap Identified, only about 32 Crores has been sanctioned for Sewer Lines
of Length measuring 50 kms; 80% of the Total Length in the range of Dia 250 mm to Dia 750 mm and 20% of the Total Length inof Length measuring 50 kms; 80% of the Total Length in the range of Dia 250 mm to Dia 750 mm, and 20% of the Total Length in
the range of Dia 800 mm to Dia 1000 mm
In order to control & stop the Pollution of Panchganga River, and ensure the Availability of Right Quality Raw Water for Drinking
Water Supply, the above Identified Investments are of Prime importance.
Fortress
Health Infrastructure
Existing Status
• Major Hospitals• Major Hospitals
Savitribai Phule Hospital: 120 Beds
Panchganga Hospital: 30 Beds
Isolation Hospital: 30 Beds
Other Health Centers & Facilities
OPD Centers: 14 Nos
RCH Center: 10 Nos
Blood Bank: 1 Nos
Proposed
Blood Bank: 1 Nos
• Most of these Centers have poor infrastructure including
Medical Equipments & Accessories
Proposed
• Setting-up 6 New OPD Centers as per Population Norms
• Repair Works at 3 Major Municipal Hospitals
• Repair Works at 14 Existing OPD Centersp g
• Repair Works at 10 RCH Centers
• Strengthening of Blood Bank
• Procurement of 4 Ambulances
Procurement of High End Medical Equipments for Major• Procurement of High End Medical Equipments for Major
Hospitals
Estimated Cost – Rs. 15 Cr.
Fortress
Power Infrastructure
Existing Status
• Sufficient supplySufficient supply
• Overhead distribution network
• Roadside transformers & Poles leading to reduction in effective roadways
Proposedp
• UG Cable work to provide pole free streets at Temple areas
• New Substations to assure supply
• Standby and adequate transformers for religious structures
Work Cost
220 KV Substation at Shendapark 60.00
33 KV Substation at Hohite Park near Rankala Lake 3.50
33 KV Substation at Gawatmandai 2 0033 KV Substation at Gawatmandai 2.00
33 x 11 KV Substation at Shivaji Stadium 2.00
630 KVA Transformer at Mahalaxmi Temple 0.25
2 Nos. of 200 KVA Transformer at Ghat area 0.20
2 N f 500 KVA T f t K tit th2 Nos. of 500 KVA Transformers at Kotiteerth 0.30
UG Cable work at Temple Inner Circuit for 25 KM 10.00
Shifting of Existing Transformers at Temple area 1.80
UG Cable work at Jyotiba Temple 1.20
2 Nos. 0f 100 KVA Trasformers at each site of Jyotiba ,
Narsobawadi, Khidrapur 0.24
Total Estimated Cost in Cr. 81.49
Fortress
Tourism Infrastructure Rs. Cr. City & Regional Infrastructure Rs. Cr.
Religious Tourism Infrastructure City Roads 149
Estimated Plan Outlay for Total Holy City Programme
Religious Tourism Infrastructure City Roads 149
Mahalaxmi Temple Precinct Redevelopment 21 City Ring Road 150
Land Acquisition & Resettlement 20 Land Acquisition for City Ring Road 150
Jotiba Temple Precinct Development 20 City Access Roads 85Jotiba Temple Precinct Development 20 City Access Roads 85
Khidrapur Temple Precinct Improvements 5 Pedestrian / Walk Ways in the City 45
Narsobawadi Temple Surrounding Improvements 10 Railway Infrastructure / Amenities Improvement 20
Other Destination Development 15 Airport Development 102p p p
Other Tourism Infrastructure Land Acquisition for Airport Development 165
Leisure Tourist Destination Development 25 Public Transportation Facilities ( MSRTC / KMT) 65
Heritage Conservation and Restoration 9 Parking Infrastructure 30g g
Rankala Lake Development 43 Water Supply 84
Koteetirth Lake Development 13 Water Supply Augmentation – Special Project 414
Panchganga River Front Development 20 Sewerage Network and STP 280
City Entry Points Beautification & Garden Dev. 7 Solid Waste Management 15
Administration, Establishment etc 25 Health Infrastructure Improvements 30
Power 82
Total 233 Total 1866
Total Estimated Project Outlay : Rs. 2099 Cr.
Fortress
SECTOR
Est.
Cost
2009-10 2010-11 2011-12 2012-13 2013-14
Program Implementation Plan
SECTOR Cost,
Cr. Qtr 1 Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4
Religious Tourism
Infrastructure
208 51 76 2754
City & Regional
Infrastructure
1866
Establishment &
25 5 5 5 5 5
507 669 501 135 54
Administrative Expenses
25 5 5 5 5 5
Total Fund Flow (In Cr.) 2099 563 750 560 167 59
GOI (49%) 1019 150 375 375 75 44
Proper
Sharing
Pattern
GOM (40%) 834 365 275 115 74 5
KMC (4%) 91 20 30 30 6 5
Private
Investment (7%)
155 28 70 40 12 5
• Total Program Outlay : Rs. 2099 Cr.                            • Program Implementation Period : 5 Yr.       
Fortress
Religious Tourism Infrastructure Agency City & Regional Infrastructure Agency
M h l i T l P i t R d l t D th Cit R d KMC
Project Implementing Agencies
Mahalaxmi Temple Precinct Redevelopment Devosthan City Roads KMC
Land Acquisition & Resettlement KMC City Ring Road
PWD /
MSRDC
Jotiba Temple Precinct Development Devosthan City Access Roads PWDp p y
Khidrapur Temple Precinct Improvements Devosthan Pedestrian / Walk Ways KMC
Narsobawadi Temple Surrounding
Improvements
Devosthan Railway Infrastructure / Amenities Improvement CR
/
Other Destination Development
Devostan/
MTDC
Airport Development MIDC
Leisure Tourist Destination Development PWD/MTDC Public Transportation Facilities
MSRTC /
KMT
Heritage Conservation and Restoration Various Parking Facilities KMC
Rankala Lake Development KMC Water Supply MJP / KMC
Koteetirth Lake Development KMC Water Supply Augmentation – Special Project MJP / KMC
Panchganga River Front Development IRD/KMC Sewerage KMC
City Entry Points Beautification & Garden Dev. KMC Solid Waste Management KMC
Health Services KMC
MSEDCL /
Power
MSEDCL /
MSETCLCR: Central Railway IRD: Irrigation Dept.
Project Implementation is proposed through over a dozen implementation agencies to be a co-ordinated through a
special committee to be formed at state and District level
Fortress
Thank you
Fortress

More Related Content

What's hot

Varanasi -town planning pdf
Varanasi -town planning  pdfVaranasi -town planning  pdf
Varanasi -town planning pdf
AayushiMalviya4
 
Bhubaneswar- Urban Planning
Bhubaneswar- Urban PlanningBhubaneswar- Urban Planning
Bhubaneswar- Urban Planning
Kharunya Chitravelu
 
LAP - Rajkot Case Study
LAP - Rajkot Case StudyLAP - Rajkot Case Study
LAP - Rajkot Case Study
CEPT University
 
Synopsis Of cultural complex
Synopsis Of cultural complexSynopsis Of cultural complex
Synopsis Of cultural complex
Shourya Puri
 
Gandhinagar town planning and master plan study
Gandhinagar town planning and master plan studyGandhinagar town planning and master plan study
Gandhinagar town planning and master plan study
Anoushka Tyagi
 
Sabarmati riverfront development
Sabarmati riverfront developmentSabarmati riverfront development
Sabarmati riverfront development
Shailja km
 
Ud ppt
Ud pptUd ppt
Ud ppt
vermaharsha
 
Virasat - E - Khalsa memorial and heritage complex.
Virasat - E - Khalsa memorial and heritage complex.Virasat - E - Khalsa memorial and heritage complex.
Virasat - E - Khalsa memorial and heritage complex.
KARTIK PARIHAR
 
Case studies on heritage conservation
Case studies on heritage conservationCase studies on heritage conservation
Case studies on heritage conservation
Akshada Muley
 
Urban square
Urban squareUrban square
Urban square
krishna chand ch
 
Case study of URBAN HAAT, CBD BELAPUR
Case study of URBAN HAAT, CBD BELAPURCase study of URBAN HAAT, CBD BELAPUR
Case study of URBAN HAAT, CBD BELAPUR
Omkar Nandavadekar
 
Aranya low cost housing-BV Doshi
Aranya low cost housing-BV DoshiAranya low cost housing-BV Doshi
Aranya low cost housing-BV Doshi
kusha Ahmed
 
Site analysis - Transit hub
Site analysis - Transit hubSite analysis - Transit hub
Site analysis - Transit hub
nainadesh
 
Kondan Retreat Resort Pune case study
Kondan Retreat Resort Pune case study Kondan Retreat Resort Pune case study
Kondan Retreat Resort Pune case study
ABHISHEKMOHALKAR
 
Riverfront development
Riverfront developmentRiverfront development
Riverfront development
misschand
 
Garden of five senses
Garden of five sensesGarden of five senses
Garden of five senses
Dhir Dhwaj
 
Hierarchy Of Open Spaces
Hierarchy Of Open SpacesHierarchy Of Open Spaces
Hierarchy Of Open Spaces
Ravtej Singh
 
Virasat e-khaalsa museum
Virasat e-khaalsa museumVirasat e-khaalsa museum
Virasat e-khaalsa museum
meenalgajbhiye
 
urban design Amritsar the heritage street
urban design Amritsar the heritage streeturban design Amritsar the heritage street
urban design Amritsar the heritage street
Priyanka Sagar
 

What's hot (20)

Varanasi -town planning pdf
Varanasi -town planning  pdfVaranasi -town planning  pdf
Varanasi -town planning pdf
 
Bhubaneswar- Urban Planning
Bhubaneswar- Urban PlanningBhubaneswar- Urban Planning
Bhubaneswar- Urban Planning
 
LAP - Rajkot Case Study
LAP - Rajkot Case StudyLAP - Rajkot Case Study
LAP - Rajkot Case Study
 
Synopsis Of cultural complex
Synopsis Of cultural complexSynopsis Of cultural complex
Synopsis Of cultural complex
 
Planning principles of hindu citites jaipur
Planning principles of hindu citites jaipurPlanning principles of hindu citites jaipur
Planning principles of hindu citites jaipur
 
Gandhinagar town planning and master plan study
Gandhinagar town planning and master plan studyGandhinagar town planning and master plan study
Gandhinagar town planning and master plan study
 
Sabarmati riverfront development
Sabarmati riverfront developmentSabarmati riverfront development
Sabarmati riverfront development
 
Ud ppt
Ud pptUd ppt
Ud ppt
 
Virasat - E - Khalsa memorial and heritage complex.
Virasat - E - Khalsa memorial and heritage complex.Virasat - E - Khalsa memorial and heritage complex.
Virasat - E - Khalsa memorial and heritage complex.
 
Case studies on heritage conservation
Case studies on heritage conservationCase studies on heritage conservation
Case studies on heritage conservation
 
Urban square
Urban squareUrban square
Urban square
 
Case study of URBAN HAAT, CBD BELAPUR
Case study of URBAN HAAT, CBD BELAPURCase study of URBAN HAAT, CBD BELAPUR
Case study of URBAN HAAT, CBD BELAPUR
 
Aranya low cost housing-BV Doshi
Aranya low cost housing-BV DoshiAranya low cost housing-BV Doshi
Aranya low cost housing-BV Doshi
 
Site analysis - Transit hub
Site analysis - Transit hubSite analysis - Transit hub
Site analysis - Transit hub
 
Kondan Retreat Resort Pune case study
Kondan Retreat Resort Pune case study Kondan Retreat Resort Pune case study
Kondan Retreat Resort Pune case study
 
Riverfront development
Riverfront developmentRiverfront development
Riverfront development
 
Garden of five senses
Garden of five sensesGarden of five senses
Garden of five senses
 
Hierarchy Of Open Spaces
Hierarchy Of Open SpacesHierarchy Of Open Spaces
Hierarchy Of Open Spaces
 
Virasat e-khaalsa museum
Virasat e-khaalsa museumVirasat e-khaalsa museum
Virasat e-khaalsa museum
 
urban design Amritsar the heritage street
urban design Amritsar the heritage streeturban design Amritsar the heritage street
urban design Amritsar the heritage street
 

Viewers also liked

Our Kolhapur
Our KolhapurOur Kolhapur
Our Kolhapur
Prakash Tanksale
 
Jyotiba
JyotibaJyotiba
Change of name in kolhapur, maharashtra
Change of name in kolhapur, maharashtra Change of name in kolhapur, maharashtra
Change of name in kolhapur, maharashtra Change of Name Ads
 
Kolhapur,Gurhal07
Kolhapur,Gurhal07Kolhapur,Gurhal07
Kolhapur,Gurhal07
Prakash Tanksale
 
Kolhapur bijapur e
Kolhapur bijapur eKolhapur bijapur e
Kolhapur bijapur e
Suneel Sule
 
Mahalaxmi temple kolhapur, maharastra
Mahalaxmi temple kolhapur, maharastraMahalaxmi temple kolhapur, maharastra
Mahalaxmi temple kolhapur, maharastra
Srinivasreddy Patil
 
Chennai City
Chennai CityChennai City
Mahaveer Marketing & Jain Pulses
Mahaveer Marketing & Jain PulsesMahaveer Marketing & Jain Pulses
Mahaveer Marketing & Jain PulsesAvnish Jain
 
GWEI Center for Learning - Kolhapur
GWEI  Center for Learning - KolhapurGWEI  Center for Learning - Kolhapur
GWEI Center for Learning - Kolhapur
Gandhi Legacy Tour
 
Pench National Park
Pench National ParkPench National Park
Pench National Park
Sonali Dudhane
 
Ar. Sourabh - Portfolio
Ar. Sourabh - PortfolioAr. Sourabh - Portfolio
Ar. Sourabh - PortfolioSourabh Somani
 
Mahabaleshwar tourist spot
Mahabaleshwar tourist spotMahabaleshwar tourist spot
Mahabaleshwar tourist spotAmol Gondane
 
Kolkata-the city of joy
Kolkata-the city of joyKolkata-the city of joy
Kolkata-the city of joysunnik
 
Jaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian CityJaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian CityLakshya Pandit
 
Bhavnagar - District Profile
Bhavnagar - District ProfileBhavnagar - District Profile
Bhavnagar - District Profile
Our Vibrant Gujarat
 
Surat ~ the city of sun
Surat ~ the city of sunSurat ~ the city of sun
Surat ~ the city of sun
MAYUR BEHERA
 

Viewers also liked (20)

Kolhapur
KolhapurKolhapur
Kolhapur
 
Our Kolhapur
Our KolhapurOur Kolhapur
Our Kolhapur
 
Jyotiba
JyotibaJyotiba
Jyotiba
 
Change of name in kolhapur, maharashtra
Change of name in kolhapur, maharashtra Change of name in kolhapur, maharashtra
Change of name in kolhapur, maharashtra
 
Kolhapur,Gurhal07
Kolhapur,Gurhal07Kolhapur,Gurhal07
Kolhapur,Gurhal07
 
Kolhapur bijapur e
Kolhapur bijapur eKolhapur bijapur e
Kolhapur bijapur e
 
Mahalaxmi temple kolhapur, maharastra
Mahalaxmi temple kolhapur, maharastraMahalaxmi temple kolhapur, maharastra
Mahalaxmi temple kolhapur, maharastra
 
Chennai City
Chennai CityChennai City
Chennai City
 
Mahaveer Marketing & Jain Pulses
Mahaveer Marketing & Jain PulsesMahaveer Marketing & Jain Pulses
Mahaveer Marketing & Jain Pulses
 
GWEI Center for Learning - Kolhapur
GWEI  Center for Learning - KolhapurGWEI  Center for Learning - Kolhapur
GWEI Center for Learning - Kolhapur
 
Pench National Park
Pench National ParkPench National Park
Pench National Park
 
Panhala
PanhalaPanhala
Panhala
 
Ar. Sourabh - Portfolio
Ar. Sourabh - PortfolioAr. Sourabh - Portfolio
Ar. Sourabh - Portfolio
 
Mahabaleshwar tourist spot
Mahabaleshwar tourist spotMahabaleshwar tourist spot
Mahabaleshwar tourist spot
 
final pptbot
final pptbotfinal pptbot
final pptbot
 
Kolkata-the city of joy
Kolkata-the city of joyKolkata-the city of joy
Kolkata-the city of joy
 
Jaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian CityJaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian City
 
Bhavnagar - District Profile
Bhavnagar - District ProfileBhavnagar - District Profile
Bhavnagar - District Profile
 
Surat ~ the city of sun
Surat ~ the city of sunSurat ~ the city of sun
Surat ~ the city of sun
 
Symbian os presentation
Symbian os presentationSymbian os presentation
Symbian os presentation
 

Similar to Holy city kolhapur

Bicycle way
Bicycle wayBicycle way
Bicycle way
Cut Rani R
 
FINAL PPT.pptx
FINAL PPT.pptxFINAL PPT.pptx
FINAL PPT.pptx
NeethuSusan3
 
ANALYSIS & PROPOSALS - TRANSPORTATION.pdf
ANALYSIS & PROPOSALS - TRANSPORTATION.pdfANALYSIS & PROPOSALS - TRANSPORTATION.pdf
ANALYSIS & PROPOSALS - TRANSPORTATION.pdf
ChhabiYadav2
 
Local Area Plan : Vancouver
Local Area Plan : VancouverLocal Area Plan : Vancouver
Local Area Plan : Vancouver
Hrishikesh Satpute
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14
West Central Association
 
Parramatta city river strategy
Parramatta city river strategyParramatta city river strategy
Parramatta city river strategy
Kaustubh Umekar
 
Unseen heroes - SMART CITY MEASURES
Unseen heroes - SMART CITY MEASURESUnseen heroes - SMART CITY MEASURES
Unseen heroes - SMART CITY MEASURES
ASHWIN KUMAR
 
Orange County Great Park & Neighborhoods - Sustainable Features and Design El...
Orange County Great Park & Neighborhoods - Sustainable Features and Design El...Orange County Great Park & Neighborhoods - Sustainable Features and Design El...
Orange County Great Park & Neighborhoods - Sustainable Features and Design El...
American Society of Civil Engineers, Orange County Branch
 
Brigham City, UT SDAT Presentation
Brigham City, UT SDAT PresentationBrigham City, UT SDAT Presentation
Brigham City, UT SDAT Presentation
CommunitiesbyDesign
 
Fulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopFulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 Workshop
West Central Association
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014
West Central Association
 
State of the Trails 2015
State of the Trails 2015State of the Trails 2015
State of the Trails 2015
Paul Schumann
 
Jordan River State Park Proposal
Jordan River State Park ProposalJordan River State Park Proposal
Jordan River State Park Proposal
State of Utah, Salt Lake City
 
Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...Edge Hill University
 
Unravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategyUnravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategy
Ka Long Bryan Wong
 
waer-161202150627.pdf
waer-161202150627.pdfwaer-161202150627.pdf
waer-161202150627.pdf
J+DESIGN
 
presentation for Urban renewal project .
presentation for Urban renewal project .presentation for Urban renewal project .
presentation for Urban renewal project .
GAURAVREDDY25
 
GA400 trail presentation - 30% design
GA400 trail presentation - 30% designGA400 trail presentation - 30% design
GA400 trail presentation - 30% design
Livable Buckhead / BATMA
 
Birmingham Cycle Revolution, Paul Simkins- Cycle City Event
Birmingham Cycle Revolution, Paul Simkins- Cycle City EventBirmingham Cycle Revolution, Paul Simkins- Cycle City Event
Birmingham Cycle Revolution, Paul Simkins- Cycle City Event
Design South East
 
Glen Millar Presentation
Glen Millar PresentationGlen Millar Presentation
Glen Millar Presentation
Gerry Darby
 

Similar to Holy city kolhapur (20)

Bicycle way
Bicycle wayBicycle way
Bicycle way
 
FINAL PPT.pptx
FINAL PPT.pptxFINAL PPT.pptx
FINAL PPT.pptx
 
ANALYSIS & PROPOSALS - TRANSPORTATION.pdf
ANALYSIS & PROPOSALS - TRANSPORTATION.pdfANALYSIS & PROPOSALS - TRANSPORTATION.pdf
ANALYSIS & PROPOSALS - TRANSPORTATION.pdf
 
Local Area Plan : Vancouver
Local Area Plan : VancouverLocal Area Plan : Vancouver
Local Area Plan : Vancouver
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14
 
Parramatta city river strategy
Parramatta city river strategyParramatta city river strategy
Parramatta city river strategy
 
Unseen heroes - SMART CITY MEASURES
Unseen heroes - SMART CITY MEASURESUnseen heroes - SMART CITY MEASURES
Unseen heroes - SMART CITY MEASURES
 
Orange County Great Park & Neighborhoods - Sustainable Features and Design El...
Orange County Great Park & Neighborhoods - Sustainable Features and Design El...Orange County Great Park & Neighborhoods - Sustainable Features and Design El...
Orange County Great Park & Neighborhoods - Sustainable Features and Design El...
 
Brigham City, UT SDAT Presentation
Brigham City, UT SDAT PresentationBrigham City, UT SDAT Presentation
Brigham City, UT SDAT Presentation
 
Fulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopFulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 Workshop
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014
 
State of the Trails 2015
State of the Trails 2015State of the Trails 2015
State of the Trails 2015
 
Jordan River State Park Proposal
Jordan River State Park ProposalJordan River State Park Proposal
Jordan River State Park Proposal
 
Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...
 
Unravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategyUnravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategy
 
waer-161202150627.pdf
waer-161202150627.pdfwaer-161202150627.pdf
waer-161202150627.pdf
 
presentation for Urban renewal project .
presentation for Urban renewal project .presentation for Urban renewal project .
presentation for Urban renewal project .
 
GA400 trail presentation - 30% design
GA400 trail presentation - 30% designGA400 trail presentation - 30% design
GA400 trail presentation - 30% design
 
Birmingham Cycle Revolution, Paul Simkins- Cycle City Event
Birmingham Cycle Revolution, Paul Simkins- Cycle City EventBirmingham Cycle Revolution, Paul Simkins- Cycle City Event
Birmingham Cycle Revolution, Paul Simkins- Cycle City Event
 
Glen Millar Presentation
Glen Millar PresentationGlen Millar Presentation
Glen Millar Presentation
 

Recently uploaded

How To Change Name On Volaris Ticket.pdf
How To Change Name On Volaris Ticket.pdfHow To Change Name On Volaris Ticket.pdf
How To Change Name On Volaris Ticket.pdf
namechange763
 
Paddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WA
Paddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WAPaddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WA
Paddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WA
River Recreation - Washington Whitewater Rafting
 
Exploring Heritage The Ultimate Cultural Tour in Palmer, Puerto Rico
Exploring Heritage The Ultimate Cultural Tour in Palmer, Puerto RicoExploring Heritage The Ultimate Cultural Tour in Palmer, Puerto Rico
Exploring Heritage The Ultimate Cultural Tour in Palmer, Puerto Rico
Caribbean Breeze Adventures
 
Uk Visa Complete Guide and application process
Uk Visa Complete Guide and application processUk Visa Complete Guide and application process
Uk Visa Complete Guide and application process
pandeypratikwgblindi
 
LUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdf
LUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdfLUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdf
LUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdf
Diper Tour
 
TOP 10 Historic Places To See in Kuruskhetra.
TOP 10 Historic Places To See in Kuruskhetra.TOP 10 Historic Places To See in Kuruskhetra.
TOP 10 Historic Places To See in Kuruskhetra.
ujjwalsethi113
 
Understanding the Running Costs of Electric Scooters.pptx
Understanding the Running Costs of Electric Scooters.pptxUnderstanding the Running Costs of Electric Scooters.pptx
Understanding the Running Costs of Electric Scooters.pptx
Zivah ElectriVa Private Limited
 
Winter Festivities in Italy
Winter Festivities in ItalyWinter Festivities in Italy
Winter Festivities in Italy
Time for Sicily
 
Jose RIZAL History and his travel Paris to berlin
Jose RIZAL History and his travel Paris to berlinJose RIZAL History and his travel Paris to berlin
Jose RIZAL History and his travel Paris to berlin
MaryGraceArdalesLope
 
The Power of a Glamping Go-To-Market Accelerator Plan.pptx
The Power of a Glamping Go-To-Market Accelerator Plan.pptxThe Power of a Glamping Go-To-Market Accelerator Plan.pptx
The Power of a Glamping Go-To-Market Accelerator Plan.pptx
RezStream
 
Agence Régionale du Tourisme Grand Est - brochure MICE 2024.pdf
Agence Régionale du Tourisme Grand Est - brochure MICE 2024.pdfAgence Régionale du Tourisme Grand Est - brochure MICE 2024.pdf
Agence Régionale du Tourisme Grand Est - brochure MICE 2024.pdf
MICEboard
 
欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】
欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】
欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】
bljeremy734
 
Exploring Montreal's Artistic Heritage Top Art Galleries and Museums to Visit
Exploring Montreal's Artistic Heritage Top Art Galleries and Museums to VisitExploring Montreal's Artistic Heritage Top Art Galleries and Museums to Visit
Exploring Montreal's Artistic Heritage Top Art Galleries and Museums to Visit
Spade & Palacio Tours
 
How To Talk To a Live Person at American Airlines
How To Talk To a Live Person at American AirlinesHow To Talk To a Live Person at American Airlines
How To Talk To a Live Person at American Airlines
flyn goo
 
Antarctica- Icy wilderness of extremes and wonder
Antarctica- Icy wilderness of extremes and wonderAntarctica- Icy wilderness of extremes and wonder
Antarctica- Icy wilderness of extremes and wonder
tahreemzahra82
 
Get tailored experience with Stonehenge tours from London
Get tailored experience with Stonehenge tours from LondonGet tailored experience with Stonehenge tours from London
Get tailored experience with Stonehenge tours from London
London Country Tours
 
4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA
4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA
4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA
Bush Troop Safari
 
Ooty Honeymoon Package from Chennai.docx
Ooty Honeymoon Package from Chennai.docxOoty Honeymoon Package from Chennai.docx
Ooty Honeymoon Package from Chennai.docx
Ooty Heritage Tours and Travels
 

Recently uploaded (18)

How To Change Name On Volaris Ticket.pdf
How To Change Name On Volaris Ticket.pdfHow To Change Name On Volaris Ticket.pdf
How To Change Name On Volaris Ticket.pdf
 
Paddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WA
Paddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WAPaddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WA
Paddle, Float, and Explore The Ultimate River Tour Experience in Monitor, WA
 
Exploring Heritage The Ultimate Cultural Tour in Palmer, Puerto Rico
Exploring Heritage The Ultimate Cultural Tour in Palmer, Puerto RicoExploring Heritage The Ultimate Cultural Tour in Palmer, Puerto Rico
Exploring Heritage The Ultimate Cultural Tour in Palmer, Puerto Rico
 
Uk Visa Complete Guide and application process
Uk Visa Complete Guide and application processUk Visa Complete Guide and application process
Uk Visa Complete Guide and application process
 
LUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdf
LUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdfLUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdf
LUXURY TRAVEL THE ULTIMATE TOKYO EXPERIENCE FROM SINGAPORE.pdf
 
TOP 10 Historic Places To See in Kuruskhetra.
TOP 10 Historic Places To See in Kuruskhetra.TOP 10 Historic Places To See in Kuruskhetra.
TOP 10 Historic Places To See in Kuruskhetra.
 
Understanding the Running Costs of Electric Scooters.pptx
Understanding the Running Costs of Electric Scooters.pptxUnderstanding the Running Costs of Electric Scooters.pptx
Understanding the Running Costs of Electric Scooters.pptx
 
Winter Festivities in Italy
Winter Festivities in ItalyWinter Festivities in Italy
Winter Festivities in Italy
 
Jose RIZAL History and his travel Paris to berlin
Jose RIZAL History and his travel Paris to berlinJose RIZAL History and his travel Paris to berlin
Jose RIZAL History and his travel Paris to berlin
 
The Power of a Glamping Go-To-Market Accelerator Plan.pptx
The Power of a Glamping Go-To-Market Accelerator Plan.pptxThe Power of a Glamping Go-To-Market Accelerator Plan.pptx
The Power of a Glamping Go-To-Market Accelerator Plan.pptx
 
Agence Régionale du Tourisme Grand Est - brochure MICE 2024.pdf
Agence Régionale du Tourisme Grand Est - brochure MICE 2024.pdfAgence Régionale du Tourisme Grand Est - brochure MICE 2024.pdf
Agence Régionale du Tourisme Grand Est - brochure MICE 2024.pdf
 
欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】
欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】
欧洲杯开户-信誉的欧洲杯开户-正规欧洲杯开户|【​网址​🎉ac123.net🎉​】
 
Exploring Montreal's Artistic Heritage Top Art Galleries and Museums to Visit
Exploring Montreal's Artistic Heritage Top Art Galleries and Museums to VisitExploring Montreal's Artistic Heritage Top Art Galleries and Museums to Visit
Exploring Montreal's Artistic Heritage Top Art Galleries and Museums to Visit
 
How To Talk To a Live Person at American Airlines
How To Talk To a Live Person at American AirlinesHow To Talk To a Live Person at American Airlines
How To Talk To a Live Person at American Airlines
 
Antarctica- Icy wilderness of extremes and wonder
Antarctica- Icy wilderness of extremes and wonderAntarctica- Icy wilderness of extremes and wonder
Antarctica- Icy wilderness of extremes and wonder
 
Get tailored experience with Stonehenge tours from London
Get tailored experience with Stonehenge tours from LondonGet tailored experience with Stonehenge tours from London
Get tailored experience with Stonehenge tours from London
 
4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA
4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA
4 DAYS MASAI MARA WILDEBEEST MIGRATION SAFARI TOUR PACKAGE KENYA
 
Ooty Honeymoon Package from Chennai.docx
Ooty Honeymoon Package from Chennai.docxOoty Honeymoon Package from Chennai.docx
Ooty Honeymoon Package from Chennai.docx
 

Holy city kolhapur

  • 1. Existing Situation at Rankala Lake Part of the Lake is infested with Water HyacinthPart of the Lake is infested with Water Hyacinth and polluted affecting the aquatic life as well as creating mosquito menaceFortress
  • 2. Proposed Integrated Plan for Rankala Lake. EE E A B C D Proposed convergence space.  Proposed artist village. Proposed State‐of‐Art  Museum. D Proposed  cultural  complex ‐ food plaza. E Proposed  Theme gardens. F Cleaning of the Lake  / Rejuvenation. E E A B C D Fortress
  • 3. Proposed Cultural Center at Rankala Lake • Performing Spacese o g Spaces • Multi-arts complex • Museum of Fine Arts • A Library Indoor and outdoor auditoria• Indoor and outdoor auditoria Estimated Cost – 43 Cr. Fortress
  • 4. Proposed Museum of wrestling events in Kolhapur region KASBAG MAIDAN Proposed  location  for Gallery of  wrestling   history‐events. Estimated Cost – 5 Cr. Fortress
  • 5. Outer Circle Proposal: Koteshwar Mandir & Kotitirth Development Existing Status O 1 5 l l i it• Over 1.5 lc annual visitors • Garden with pathway overlooking the sacred lake • Good Seating arrangement • Beautiful Lake view S i S th M di• Swami Samarth Mandir Key Issues • Approach roads are not well maintainedpp • No public utility facilities • No planned parking area • Grossly inadequate infrastructure Fortress
  • 6. I Proposed Holistic Plan for Kotithirth Lake I Issues: • Approach roads are not well maintained • No public utility facilities J F I • No planned parking area • Grossly inadequate infrastructure A G E HI C D Proposed Activities – B E Restaurant- organic food Meditation hall- Open air amphitheater- Museum A B C E G F Fast food Shops- Laser show Musical fountain-H Museum I Ghat development Mythological wall paintingsJ C D Yoga hall / center Exhibition hall Estimated Cost – 13 Cr. Fortress
  • 7. Beautification of City Entry Points & Chowks Map showing Locations of Entry Points ofp g y under consideration for Beautification Estimated Cost – 7 Cr. Fortress
  • 8. Proposal for Theme Gardens Ramkala Choupati  Nehru Garden Tembhalai Garden Town Hall Garden Name of Garden Area Themes & attractionsName of Garden Area Themes & attractions 1.Padmavati Garden 4000 sq.mt. Play area, pathways, fantasy garden etc. 2. Rankala garden. 22000 Sq.mt. Acupressure pathways, aroma gardens, Play area etc. 3 Nehru garden 8000 sq mt Rose garden Hibiscus garden etc3. Nehru garden. 8000 sq.mt. Rose garden, Hibiscus garden etc. 4. Tembalai garden 4800 sq.mt. Play area, sculpture park, Butter fly garden etc. 5. Town hall garden. 4000 sq.mt. Rare species of plants, Fortress
  • 9. • A perennial river Panchaganga flowing River Ghat Development – Existing Situation adjacent to Kolhapur City periphery over 20KM stretch • 2 Major Ghats at Shivaji Bridge (500 m) & Datta Mandir (500 m) are poor in conditionatta a d (500 ) a e poo co d t o • Religious & heritage structure are in existence • Non existence of social infrastructure No facility for Bath or Holy Dip• No facility for Bath or Holy Dip • Unclean & inadequately maintained ghat precinct • Unclean and Dirty water due to disposal of religious waste, emersion of idols, Cloth & Cattle washing • Poor approach roads, Lighting to the ghatsg • No safety and security arrangement Fortress
  • 10. • Development of 1km stretch at two locations River Ghat Development - Proposed p on Right bank focusing on rejuvenation of river • River front development at multiple location would enable decongestion of crowd &would enable decongestion of crowd & promoting one of the major tourism attractions • Facilitate & ensure clean environment around th h tthe ghats Ghat, Walking Path Parks & Gardens Lighting • Restoration & Conservation of • Public & Children’s parks • Lighting for regular night timeRestoration & Conservation of existing Structures • Series of Ghat in step & ramps • Wide pedestrian walkways • Seat, benches & other Sculpture Public & Children s parks • Soil erosion & Slope stabilization • Roadside & Plaza Parking Lighting for regular night time usage • Lighting for special occasions Movement Network Social Infrastructure Seat, benches & other Sculpture • View posts cum Lifeguard stations • Information / facilitation centre • PA System • Public Toilet • Approach Road & Signage • Car & Bicycle parking • Taxi / Rickshaw Stand • Mela / Exhibition Space • Water sports – Rowing, boating Revenue GenerationPublic Toilet • Drinking water • Police post Revenue Generation • Commercial area – Shops • Food Courts / Kiosks • Parks Estimated Cost – 20 Cr. Fortress
  • 11. Leisure Tourist Destination Development – Panhala Fort 12th Century construction, at 977.2 m altitude Largest of all Deccan forts having 7Largest of all Deccan forts having 7 Km long fort wall with steep slop beneath Associated with the life of great Maratha ruler, Chhatrapati Shivaji Maharaj. Panhala - Rich heritage & Tourist attractionPanhala - Rich heritage & Tourist attraction Fortress
  • 12. Leisure Tourist Destination Development – Panhala Fort Development of Panhala as a historical & Scenic Appeal Development ComponentDevelopment Component • Entrance Road, Ramp & Steps • Conservation plan for Panhala Fort • Repairs of fort wall • Soil conservation, Landscaping & Pl t tiPlantation • VIP Guest House • History research centrey • Tourist amenities / Facilities Estimated Cost – 15 Cr. Fortress
  • 13. Leisure Tourist Destination Development – Pawankhind Development Componentp p • Entrance Road, Ramp & Steps • Museum displaying history of brave Marathas • Statue of Veer Bajiprabhu Deshpande • Viewers GalleryViewers Gallery • Tourist amenities / facilities Estimated Cost – 3 Cr. Fortress
  • 14. Leisure Tourist Destination Development – Palaces Development Component Estimated Cost – 10 Cr. • Conservation plan for Places in Kolhapur City • Facility upgradation Fortress
  • 15. Proposed Developments in Infrastructure Fortress
  • 16. City & Regional Infrastructure Rs Cr Proposed Infrastructure Development Plan City & Regional Infrastructure Rs. Cr. City Roads 149 City Ring Road 150 Land Acquisition for City Ring Road 150Land Acquisition for City Ring Road 150 City Access Roads 85 Pedestrian / Walk Ways in the City 45 Railway Infrastructure / Amenities Improvement 20 Airport Development 102 Land Acquisition for Airport Development 165 Public Transportation Facilities ( MSRTC / KMT) 65 Parking Infrastructure 30 Water Supply 84 Water Supply Augmentation – Special Project 414 S N t k d STP 280Sewerage Network and STP 280 Solid Waste Management 15 Health Infrastructure Improvements 30 Power 82Power 82 Total 1866 Fortress
  • 17. City Roads – Existing Status • Non-user-friendly streets for pedestrians, NMVs and the di bl ddisabled • Non existence of Foot over bridge, Subway or RUB at traffic Congested Squares / points • High Pedestrian Influx especially in the time of Festivals/ Events • Poor road geometrics and riding surfacesg g • Elements of safety inadequately addressed • Inappropriate cross sections • Poor street lighting & Road Signage• Poor street lighting & Road Signage • Unplanned parking lane / zone • Non existence of Multifunctional zone leads to reduction i ff ti din effective road uses Total Roads within the City Limit : 571.00 KM (415.00 KM with BT Surface) Connectivity and Quality of Roads requires improvements Road development proposed under IRDP (On BOT basis) : 49.99 KM ( Rs.240 cr) Fortress
  • 18. Movement Network – Proposed CS T Mahalaxmi K ti Ti th Bhawani Mandap Bindu Chowk Rankala Lake Koti Tirth N d R d 8 K Mahalaxmi surrounding Road– 18Km Mahalaxmi Ring Road – 40 Km IRDP Road – 49.99 Km Navdurga Road – 8 Km NH 04 City Access Roads Fortress
  • 19. City Roads – Proposed • Appropriate Road section for all users A i t R d G t i ith idi S f 9 m wide Typical Section • Appropriate Road Geometric with riding Surface • Streetscape & urban forestry properly addressed • Street Furniture, Safety barrier , signage & Street Lighting • Controlled traffic lanes / ways Roads proposed under Holy City Program : 26 KM (32 Roads) Est. Cost – Rs. 42 Cr. Fortress
  • 20. Outer Ring Road – Proposed • 45m wide Ring Road with 4 Lane connecting NH 0404 • Bypassing the City from Radhnagari, Gargoti, Ratnagiri Road and other districts Schematic Mahalax mi Schematic Ring Road : 40 Km appx Est. Cost – Rs. 300 Cr. (Road Development – Rs. 150 Cr. & Land Acquisition – Rs. 150 Cr.) Fortress
  • 21. Existing Status K lh Cit h lti l E t i t City Access Roads Existing Status • Kolhapur City has multiple Entry points • Shivaji Bridge (Constructed in A.D. 1877) on Pachganga River needs immediate attention • Narrow and poor roads without dividers & foot pathNarrow and poor roads without dividers & foot path • Lack of street furniture • Dilapidated sewerage system has adverse effect on roads Proposed • Road development & maintenance affected due to inadequate funds Proposedp • Majority of the roads will widened to 4 lanes with appropriate section & roadside amenities • Provide smooth Entry to cityy y • Connect the other important religious / tourist destination • City Access Roads : 25 Km Estimated Cost – Rs. 85 Cr. • Other Link Roads : 60 Km • Bridge at Panchganga river Fortress
  • 22. Pedestrian Infrastructure – Existing Status • Low road capacities & pedestrian influence • Non-user-friendly streets for pedestrians,y p , NMVs and the disabled • Only 1 FOB is functional at Station Road • Narrow road width is main constraint forNarrow road width is main constraint for dedicated pedestrian lane • Unsafe road crossings • Footpath encroached by Hawker / MobileFootpath encroached by Hawker / Mobile Vendor • Most of road made One way / no vehicular resulting in traffic congestion on roadsresulting in traffic congestion on roads Pedestrian infrastructure needs immediate improvement to meet the requirement of user Fortress
  • 23. Pedestrian Infrastructure - Proposed • Developing a sustainable Pedestrian infrastructure in city th t t th i t f P d t i &that meets the requirements of Pedestrian users & Hawkers • 4 meter wide for pedestrian movement & 7 meter wide for pedestrian plus Hawker’s zonepedestrian plus Hawker s zone • Covered with decorative Polycarbonate roofing sheet • Staircase & an escalator • Underground cabling & Lighting Proposed Skywalk / FOB • Adequate safety & waste disposal arrangement Proposed Skywalk / FOB Sky walk at Railway Station to Dabholkar Chowk to Central Bus Stand Sky walk at Shivaji Market to KMC Office to Bhavani Mandap Sky walk at Venus Corner to Kondaol LaxmipuriSky walk at Venus Corner to Kondaol , Laxmipuri Skywalk at Central Bus Stand to Rajarampuri Road Foot over Bridge at New Shahupuri Foot Over Bridge at Ganpati Mandir Chaowk Rankala LakeFoot Over Bridge at Ganpati Mandir Chaowk, Rankala Lake Foot Over Bridge at Shivaji Stadium Estimated Cost – Rs. 45 Cr. Fortress
  • 24. Railway Infrastructure – Existing Status Kolhapur is connected to Pune, Mumbai, Delhi, Nagpur Ahmadabad & BangaloreNagpur, Ahmadabad & Bangalore Direct trains are available to cater the routine passenger flow One of the important destinations for Deccan Odyssey – The famous luxury train of India Shri CSMT Building – A heritage structure Two Platforms with basic facilities Only one Foot Over BridgeOnly one Foot Over Bridge Only one entry provided to Station from North side Inadequate waiting hall & Passenger amenities Upgradation & development of Railway infrastructure require to cater the Passenger flow Fortress
  • 25. Railway Infrastructure – Proposed • Improve the connectivity on existing routes• Improve the connectivity on existing routes • Add new routes / trains to other cities • Conservation & restoration of Shri Chhatrapati Shahu Maharaj Terminus Building A heritage structureMaharaj Terminus Building – A heritage structure • Construction of New Railway station building with all passenger amenities Like waiting hall, Art gallery etc. • Extension & upgradation of existing Platforms with• Extension & upgradation of existing Platforms with passenger amenities • Construction of additional Platform • New Foot over Bridge & Entry to Railway station from• New Foot over Bridge & Entry to Railway station from South • Improvement & repairs of the Babubhai Parikh Railway Under BridgeUnder Bridge • Categorized Parking zones • Beautification (Landscaping & tree plantation) of the Railway station premises Estimated Cost – Rs. 20 Cr. a ay stat o p e ses Fortress
  • 26. Airport Infrastructure – Existing Status • Daily Air service by Deccan Airways to Mumbai & Belgaon • Operation & Maintenance by MIDC • Approximately 10000 Sqft. Terminal Building with limited amenities • 45 M wide &1 3 Km long Runway45 M wide &1.3 Km long Runway • Increasing Air traffic due to development of Industrial areas at & around the Kolhapur Development of Airport require for the improvement in Air Connectivity Fortress
  • 27. Airport Infrastructure – Proposed Development of New Modern Airport & Connecting Kolhapur by Air to important cities D l t C tDevelopment Component - • Up gradation & expansion of runway as per Boeing Standard • Aprons & Taxiway • New Navigation Facilities • Night Landing Facilitiesg g • Airport Peripheral Wall • Internal Road & Parking Area • 300 Passenger capacity Terminal Building• 300 Passenger capacity Terminal Building • Electrification • Airport Approach Road & other development Estimated Cost – Rs. 267 Cr. (Land Acquisition – Rs. 165 Cr. & Development – Rs. 102 Cr.) Fortress
  • 28. Existing Status Transport Infrastructure - MSRTC Existing Status • Kolhapur City has 3 bus stand at Dabholkar Chowk Rankalvesh & Sambhaji NagarChowk, Rankalvesh & Sambhaji Nagar • Central Bus Stand & Depot spread over 8 Acres of Land • Lack of Basic passenger / tourist amenities Proposed • Lack of Basic passenger / tourist amenities • Surrounded by Hawkers Proposed Proposed Development of Bus Stand building with Passenger amenities, platform & apron at p 1. Central Bus Stand 2. Rankalavesh Bus Stand 3. Sambhaji Nagar Standj g Estimated Cost – Rs. 35 Cr. Improvement in the Regional level transport connectivity Fortress
  • 29. • Kolhapur Municipal Transport Transport Infrastructure (KMT) – Existing Status (KMC undertaking) plies 117 buses over 27 routes in the city • 3 Nos. of Terminus at Bhavani Mandap, Shahupuri & Gangavesh • 285 Nos. of bus stop D t T i d b• Depots, Terminuses and bays warrant upgradation Buses are in poor condition• Buses are in poor condition • Service level warrants improvementimprovement KMT Service needs immediate improvement for the reliable and regular transport facility to Citizen Fortress
  • 30. • Transformation of Public transport for public & Pilgrims • Development of new modern bus Terminus / depot with facilities as Transport Infrastructure (KMT) – Proposed Development of new modern bus Terminus / depot with facilities as • Bus bays with emergency yard • Parking Zones for Bus, Rickshaws & NMV • Seating Zones • Administrative block • Public utilities like toilet, water, • Small shops like food courts, newspapers couriers & Convenience • No. of Routes & frequency of buses will be enhanced • Seating Zones • Proper signage • Cloak rooms for passengers newspapers, couriers & Convenience stores • Provision 200 Nos. of Bus shelter with drinking water & informatory Map • Dedicated daily bus service for Navdurga Darshan & Kolhapur Darshan Site Particulars / Facilities Bindu Chowk (Shifting of existing Bhavani Mandap depot) Main Central Bus Terminus (61000 Sqft) Shahupuri Bus Terminus with Commercial (22000 Sqft) G h B T i ith C i lGangavesh Bus Terminus with Commercial Panchganga Ghat Bus Terminus with Commercial Central Bus Stand Bus Terminus Railway Station Bus TerminusRailway Station Bus Terminus Airport / MIDC Area Bus Terminus with Commercial Estimated Cost – Rs. 30 Cr. Fortress
  • 31. Existing Status Parking Infrastructure Mahalaxmi marketMahalaxmi market Bindu ChowkBindu Chowk Existing Status • Unplanned & unorganized Parking on road, Footpath leads to traffic congestion • Unorganized parking leads to reduction in Kapilteerth MarketKapilteerth Market Unorganized parking leads to reduction in effective width of road & inconvenience to citizen / Pilgrim Proposed Multistoried Parking for NMV, LMV at Mahalaxmi Temple Surrounding to control movement 1. Mahalaxmi Market 2. Kapeelteerth Market 3 Bindu Chowk3. Bindu Chowk Estimated Cost – Rs. 30 Cr. Fortress
  • 32. Water Supply System - Existing Status Existing Raw Water Source 1 Bhogawati River; Balinga Works; 41 MLD Cap; 8 Km away Water Supply Network Coverage Length of Main Transmission Line: 57 Kms1.Bhogawati River; Balinga Works; 41 MLD Cap; 8 Km away 2.Panchganaga River via Bawada Water Works; 20 MLD Capacity; 6 Kms Panchganga River vis Puikhadi Works; 30 MLD; 11 Kms away Length of Main Transmission Line: 57 Kms Length of Distribution Network: 400 Kms Network Coverage in Main City Area; 80% Network Coverage in Extended City Area: 20%; y 3.Kamlamba Tank; Kalmba Works; 08 MLD; 3 Km away Total Capacity Available: 99 MLD g y No. of Metered Connection: 66, 625 key Issues 1. Renovation and Augmentation of Pumping Capacities 2. 100% Metering for the purpose of recovering projected Water Revenues 3. Augumenataion of Balinga Water Works; Temblai Dam Area Water Scheme; and Kalamba Water WorksWater Scheme; and Kalamba Water Works. 4. Arresting continuous Pollution of Panchganga River by tapping & diverting Sewage flowing through Jayanti and Dudhali Nallah, and diverting the sewage to proposed STP of 100 MLD Capacity with ST Facilities. 5. Developing Alternative Source of Clean Raw Water Supply Source from Dudhganga River at Kalammawadi Dam, adding 92 MLD Capacity.92 MLD Capacity. 6. Proper Water Management for Panchganga and Bhogawati River so as to adequately establish balance between Agriculture Usage and City Water Supply Demand. Fortress
  • 33. Water Supply System – Proposed Priority Works Balinga Water Works Kalamba Water Works Temblai Area W/S Scheme H d W k WTP f 5 MLD C it O GSR f 2 MLD C itHead Works Pumping Machineries Rising Main; Dia 700 mm, 2 Kms Length WTP of 5 MLD Capacity Gravity Main; Dia 500 mm; 4 Kms in Length; From Kalamba Lake to Kalamba WTP One GSR of 2 MLD Capacity One Feeder Main; Dia 450 mm; 2.5 Kms in Length Additional Distribution Network of about Up gradation of 41 MLD WTP to 60 MLD Capacity Rising Main; Dia 700 mm; From Balinga WTP to Chmbukadi Kalamba Lake De-silting and Kalamba Dam Dam Strengthening 10 Kms in Length Balinga WTP to Chmbukadi Gravity Main; Dia 750 mm; 6 Kms Length; From Chambukadi to Bindu Chowk ESR’s of 2 MLD Capacities, each at Gangavesh & Mirajkar Tikati Estimated Cost: Rs. 60 Crores Estimated Cost: Rs. 17.50 Crores Estimated Cost:: Rs. 6.35 Crores Estimated Funds Required for Water Supply Augmentation Plan: Rs. 84 Crores Under UIDSSMT Scheme, Out of the Total Investment Gap Identified i.e. Rs. 73.95 Crores at 2005-06 DSR Rates, only about 58.44 Crores has been sanctioned. In addition to above, Rs. 84 Crores as discussed above is required on Priority basis to upgrade the City Water Supply System Fortress
  • 34. Water Supply Source Augmentation: Special Project Need for Alternate Water Supply Source Continued - pp y • Heavy Pollution of Panchganga River due to Sugar Mills, Tannery Units & Untreated Sewage released from Small Town, on the upstream side L W t A il bilit i P h Ri St• Low Water Availability in Panchganga River Stream for almost 3 to 5 Months, resulting into under capacity lifting for Drinking purpose New Source as Kalmmawadi Dam By Tapping Dudhganga Storage Reservoir (28 TMC Capacity) at Kalmmawadi Village, 92 MLD Raw Water Availability can be ensured Suggested Project Development Routes: -Suggested Project Development Routes: - BOOT: Viability Gap Funding / SPV Soft Loans form Foreign Development Banks Fortress
  • 35. Water Supply Source Augmentation: Special Project Improvements & Argumentation to KOLHAPUR W.S.S Ph II (Source as Kalmawadi Dam) S N Name of Sub-Works Cost Estimates in Cr Continued - S. N. Name of Sub-Works Cost Estimates in Cr. 1. Working Survey 0.60 2. Design, Pro. & Const. of Dam Out let modifications, Inlet Arrangements upto Intake, Tower (Work of Irrigation Dept. 1.15 3. Design, Pro. & Const. 7.2 m Dia Intake-cum-Distriburtion Tower upto 64 m (Work of Irrigation Dept. 2.20 4. Pro. Const. Tunnel of 63 sq.m Area 600 m, length at CH. 5.2 Kms. 1.85 5. Gravity Main (Raw Water) of Dam to Sump, M.S. Pipe 10 mm Thk., L=53.10 Kms, OD Dia 1820 mm 265.60 6. Rising Main from Sump to Puikahdi WTP M.S. Pipe 10 mm thk., 1.25 Kms 12.35 7. WTP (92 MLD) 7.82 8. Cross Section to Chambukhadi 0.60 9. Pumping Machinery (R/W) at Sump (1000 BHP, 4 Nos., 50% Standby) 8.55 10. Pump House 0.65 11. Design, Prov. & Const. Sump Cap. 47,50,000 Ltrs. 0.53 12.. Misc. Works 27.90 Total Net Cost Rs 329 80Total Net Cost, Rs. 329.80 Add. MJP Centage Charges @14% 46.17 Total Gross Amount 375.97 Add 10% Escalation on Net Cost 37.60 Gross Cost 413.57 The Alternative Source Development Project, as one time Intervention, would address the Water Supply Situation on long-term basis Fortress
  • 36. Sewerage System: Existing Status The Interception & Diversion Works as proposed for the 4 M j O N ll h ’ d ib d b l4 Major Open Nallahs’ are as described below – Dudhali Nallah Basin Jayanti Nallah Line Bazaar Nallah Bapat Campa a as a a Zone a a Zone Ca p Nallah Zone Sewage flowing Sewage flowing Sewage flowing Sewage flowingg through Dudhali Natural Open Nallah is Intercepted & g through Jayanti Natural Open Nallah is g through Line Bazaar Natural Open Nallah is g through Bapat Camp Natural OpenIntercepted & diverted by Pumping Station 4 to Jahyanti Nallah is Intercepte d & diverted by Pumping Nallah is proposed to be pumped to Receiving Open Nallah is proposed to be pumped Nallah Station 1 to Receiving Chamber at Kasba Chamber at Kasba Bavada to Receiving Chamber at Kasba Bavadaat Kasba Bavada Bavada Fortress
  • 37. Sewerage System: Existing Situation Continued - Topographically, the KolhapurMunicipal Limits is divided into 4 Drainage Zones, and details of these Zones are described below - D dh li N ll h B i J ti N ll h Z Li B N ll h Z B t C N ll h ZDudhali Nallah Basin Jayanti Nallah Zone Line Bazaar Nallah Zone Bapat Camp Nallah Zone Catchment Area includes Sector 4 & 5 mainly, and some parts of Sector 1 Total Catchment Area is about 1600 Ha covering 2 0 Lakhs of present Mostly sewered Zone with Catchment Area which includes parts of Sector 1; 2 & 4 Total Catchment is about 2100 Totally un-sewered Zone, with Catchment Area Covering most of the Area of Sector 6 Total Catchment is about 500 Ha Totally un-sewered Zone, with Catchment Area Covering most of the Area of Sector 6Ha, covering 2.0 Lakhs of present Population Total Length of Main Sewer is 26 Kms., carrying 26 MLD of Sewage Total Catchment is about 2100 Ha, covering 7.50 Lakhs Population Total Length of Main Sewer is 63 Kms, carrying 20 MLD of Total Catchment is about 500 Ha, covering 0.35 Lakhs of Population Total Length of Main Sewer is 9.0 Kms, carrying 5..2 MLD of Sector 6 Total Catchment is about 400 Ha, covering 0.50 Lakhs of Population Total Length of Main Sewer is Sewage Sewage, currently utilized for Irrigation in Catchment, itself 23 Kms, carrying 6.8 MLD of Sewage Sewage flowing through Dudhali Natural Open Nallah is Intercepted & diverted by Pumping Station 4 to Jahyanti Nallah Sewage flowing through Jayanti Natural Open Nallah is Intercepted & diverted by Sewage flowing through Line Bazaar Natural Open Nallah is proposed to be pumped to Sewage flowing through Bapat Camp Natural Open Nallah is proposed to be pumped toby Pumping Station 4 to Jahyanti Nallah Intercepted & diverted by Pumping Station 1 to Receiving Chamber at Kasba Bavada proposed to be pumped to Receiving Chamber at Kasba Bavada proposed to be pumped to Receiving Chamber at Kasba Bavada 26 MLD 20 MLD 5 2 MLD 6 80 MLD26 MLD 20 MLD 5.2 MLD 6.80 MLD Existing STP (Primary Treatment only) is of 39.80 MLD Capacity while Treatment Demand is 58 MLD Due to Usage of Natural Open Nallah for conveyance of Sewage, Storm Water flow into these along the natural Slopes during Monsoon Season, leading to over-flow situation at Interception Site Usage of Open Nallah are also prone to mixing of Solid Waste into the Sewage, and contributes to Air-borne and Water-borne Diseases Thus, there exists basic need for Rising Mains along the Natural Nallah, Interception & Diversion Works, Pumping Machineries and Augmented Secondary Treatment Capacity, present load 58 MLD, and 100 MLD as Year 2025 Load Fortress
  • 38. Sewerage System: Priority Works & Investment Requirements Dudhali Nallah Basin Jayanti Nallah Zone Line Bazaar Nallah Zone Bapat Camp Nallah Zone 1 Interception & Diversion Works (K T 1 Interception & Diversion Works 1 Interception & Diversion Works 1 Interception & Diversion1. Interception & Diversion Works – (K.T. Weir) (Length – 20.00 m x Width – 4.00 m) 2. Screen Chamber / Sump Well (6.00 m X 3.70 m & 11.00 m x 11.00 m) – 2 Nos. 1. Interception & Diversion Works – (K.T. Weir) (Length – 20.00 m x Width – 10.00 m) 2. Screen Chamber / Sump Well (6.00 m X 3.70 m & 11.00 m x 1. Interception & Diversion Works – (K.T. Weir) (Length – 20.00 m x Width – 2.00 m) 2. Screen Chamber / Sump Well (6.00 m X 3.70 m & 7.50 m x 1. Interception & Diversion Works – (K.T. Weir) (Length – 20.00 m x Width – 2.00 m) 2. Screen Chamber / Sump Well (6.00 m X 3.70 m & 3. Pumping Machinery – 150 HP – 3 Nos.; 75 HP – 2 Nos. 4. Rising Mains – a) Dia 600 mm D.I. K-9 L – 2000 M 11.00 m) – 2 Nos. 3. Pumping Machinery – 300 HP – 2 Nos. 4. Rising Mains – a) Dia 750 mm D I K 9 L 2300 M 3.40 m) – 2 Nos. 3. Pumping Machinery – 75 HP – 3 Nos. & 25 HP – 2 Nos. 4. Rising Mains – a) Dia 750 mm D I K 9 L 2300 M 7.50 m x 4.00 m) – 2 Nos. 3. Pumping Machinery – 100 HP – 3 Nos. & 40 HP – 2 Nos. 4. Rising Mains –a) Dia 750 mm D.I. K-9 L – 2300 M b) Dia 1000 mm D.I. K-9 L – 4600 m a) Dia 750 mm D.I. K-9 L – 2300 M b) Dia 1000 mm D.I. K-9 L – 4600 m 4. Rising Mains a) Dia 350 mm D.I. K-9 L – 2000 M Estimated Cost of Above Works: 280 Crores 1. Interception & Diversion Works: 10 Cr. 2. Rising Mains: 70 Cr. 3. Gravity Mains: 50 Cr. 4 P i M hi i 50 C4. Pumping Machineries: 50 Crores 5. Secondary Treatment Plant (STP) of Capacity 100 MLD: 100 Cr. Under UIDSSMT Scheme, Out of the Total Investment Gap Identified, only about 32 Crores has been sanctioned for Sewer Lines of Length measuring 50 kms; 80% of the Total Length in the range of Dia 250 mm to Dia 750 mm and 20% of the Total Length inof Length measuring 50 kms; 80% of the Total Length in the range of Dia 250 mm to Dia 750 mm, and 20% of the Total Length in the range of Dia 800 mm to Dia 1000 mm In order to control & stop the Pollution of Panchganga River, and ensure the Availability of Right Quality Raw Water for Drinking Water Supply, the above Identified Investments are of Prime importance. Fortress
  • 39. Health Infrastructure Existing Status • Major Hospitals• Major Hospitals Savitribai Phule Hospital: 120 Beds Panchganga Hospital: 30 Beds Isolation Hospital: 30 Beds Other Health Centers & Facilities OPD Centers: 14 Nos RCH Center: 10 Nos Blood Bank: 1 Nos Proposed Blood Bank: 1 Nos • Most of these Centers have poor infrastructure including Medical Equipments & Accessories Proposed • Setting-up 6 New OPD Centers as per Population Norms • Repair Works at 3 Major Municipal Hospitals • Repair Works at 14 Existing OPD Centersp g • Repair Works at 10 RCH Centers • Strengthening of Blood Bank • Procurement of 4 Ambulances Procurement of High End Medical Equipments for Major• Procurement of High End Medical Equipments for Major Hospitals Estimated Cost – Rs. 15 Cr. Fortress
  • 40. Power Infrastructure Existing Status • Sufficient supplySufficient supply • Overhead distribution network • Roadside transformers & Poles leading to reduction in effective roadways Proposedp • UG Cable work to provide pole free streets at Temple areas • New Substations to assure supply • Standby and adequate transformers for religious structures Work Cost 220 KV Substation at Shendapark 60.00 33 KV Substation at Hohite Park near Rankala Lake 3.50 33 KV Substation at Gawatmandai 2 0033 KV Substation at Gawatmandai 2.00 33 x 11 KV Substation at Shivaji Stadium 2.00 630 KVA Transformer at Mahalaxmi Temple 0.25 2 Nos. of 200 KVA Transformer at Ghat area 0.20 2 N f 500 KVA T f t K tit th2 Nos. of 500 KVA Transformers at Kotiteerth 0.30 UG Cable work at Temple Inner Circuit for 25 KM 10.00 Shifting of Existing Transformers at Temple area 1.80 UG Cable work at Jyotiba Temple 1.20 2 Nos. 0f 100 KVA Trasformers at each site of Jyotiba , Narsobawadi, Khidrapur 0.24 Total Estimated Cost in Cr. 81.49 Fortress
  • 41. Tourism Infrastructure Rs. Cr. City & Regional Infrastructure Rs. Cr. Religious Tourism Infrastructure City Roads 149 Estimated Plan Outlay for Total Holy City Programme Religious Tourism Infrastructure City Roads 149 Mahalaxmi Temple Precinct Redevelopment 21 City Ring Road 150 Land Acquisition & Resettlement 20 Land Acquisition for City Ring Road 150 Jotiba Temple Precinct Development 20 City Access Roads 85Jotiba Temple Precinct Development 20 City Access Roads 85 Khidrapur Temple Precinct Improvements 5 Pedestrian / Walk Ways in the City 45 Narsobawadi Temple Surrounding Improvements 10 Railway Infrastructure / Amenities Improvement 20 Other Destination Development 15 Airport Development 102p p p Other Tourism Infrastructure Land Acquisition for Airport Development 165 Leisure Tourist Destination Development 25 Public Transportation Facilities ( MSRTC / KMT) 65 Heritage Conservation and Restoration 9 Parking Infrastructure 30g g Rankala Lake Development 43 Water Supply 84 Koteetirth Lake Development 13 Water Supply Augmentation – Special Project 414 Panchganga River Front Development 20 Sewerage Network and STP 280 City Entry Points Beautification & Garden Dev. 7 Solid Waste Management 15 Administration, Establishment etc 25 Health Infrastructure Improvements 30 Power 82 Total 233 Total 1866 Total Estimated Project Outlay : Rs. 2099 Cr. Fortress
  • 42. SECTOR Est. Cost 2009-10 2010-11 2011-12 2012-13 2013-14 Program Implementation Plan SECTOR Cost, Cr. Qtr 1 Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4 Religious Tourism Infrastructure 208 51 76 2754 City & Regional Infrastructure 1866 Establishment & 25 5 5 5 5 5 507 669 501 135 54 Administrative Expenses 25 5 5 5 5 5 Total Fund Flow (In Cr.) 2099 563 750 560 167 59 GOI (49%) 1019 150 375 375 75 44 Proper Sharing Pattern GOM (40%) 834 365 275 115 74 5 KMC (4%) 91 20 30 30 6 5 Private Investment (7%) 155 28 70 40 12 5 • Total Program Outlay : Rs. 2099 Cr.                            • Program Implementation Period : 5 Yr.        Fortress
  • 43. Religious Tourism Infrastructure Agency City & Regional Infrastructure Agency M h l i T l P i t R d l t D th Cit R d KMC Project Implementing Agencies Mahalaxmi Temple Precinct Redevelopment Devosthan City Roads KMC Land Acquisition & Resettlement KMC City Ring Road PWD / MSRDC Jotiba Temple Precinct Development Devosthan City Access Roads PWDp p y Khidrapur Temple Precinct Improvements Devosthan Pedestrian / Walk Ways KMC Narsobawadi Temple Surrounding Improvements Devosthan Railway Infrastructure / Amenities Improvement CR / Other Destination Development Devostan/ MTDC Airport Development MIDC Leisure Tourist Destination Development PWD/MTDC Public Transportation Facilities MSRTC / KMT Heritage Conservation and Restoration Various Parking Facilities KMC Rankala Lake Development KMC Water Supply MJP / KMC Koteetirth Lake Development KMC Water Supply Augmentation – Special Project MJP / KMC Panchganga River Front Development IRD/KMC Sewerage KMC City Entry Points Beautification & Garden Dev. KMC Solid Waste Management KMC Health Services KMC MSEDCL / Power MSEDCL / MSETCLCR: Central Railway IRD: Irrigation Dept. Project Implementation is proposed through over a dozen implementation agencies to be a co-ordinated through a special committee to be formed at state and District level Fortress