Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
The document summarizes a meeting with the Hayfield Citizens Association to provide updates on the Hayfield Road Pipe Conveyance Project. It discusses design changes requiring new sanitary sewer laterals for 23 properties, progress made by utility companies relocating lines, the expected construction bidding and award schedule, and plans for ongoing communication with the community during construction.
Backlick Run Gravity Sewer Abandonment Project June 2020Fairfax County
This is a 4,000 linear foot section of gravity sewer that was taken out of service. The pipe had deteriorated and was prone to collapse. The area was restored and site improvements were completed.
This document provides information about a stream restoration project on Pike Branch at Wilton Road in Fairfax County, Virginia. It outlines the project area limits, typical restoration practices that will be used such as native vegetation planting, reinforced streambeds, and instream rock structures. It also shows examples of construction efforts like access roads and channel grading. The presentation discusses the project overview, current steps being taken to get approvals, and outlines a timeline for advertising, beginning, and completing construction over the next 2-3 years.
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
The document discusses plans to replace an existing sanitary sewer line crossing Little Hunting Creek in Virginia. It describes alternatives considered, including open cut replacement, which was selected for design. Key aspects of the design include surveys, permitting requirements from various agencies, and construction plans to install the new line using a cofferdam while minimizing environmental and community impacts. Construction is scheduled to take place from July to November 2019 following design and permitting from 2017 to early 2019.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
The document summarizes a meeting with the Hayfield Citizens Association to provide updates on the Hayfield Road Pipe Conveyance Project. It discusses design changes requiring new sanitary sewer laterals for 23 properties, progress made by utility companies relocating lines, the expected construction bidding and award schedule, and plans for ongoing communication with the community during construction.
Backlick Run Gravity Sewer Abandonment Project June 2020Fairfax County
This is a 4,000 linear foot section of gravity sewer that was taken out of service. The pipe had deteriorated and was prone to collapse. The area was restored and site improvements were completed.
This document provides information about a stream restoration project on Pike Branch at Wilton Road in Fairfax County, Virginia. It outlines the project area limits, typical restoration practices that will be used such as native vegetation planting, reinforced streambeds, and instream rock structures. It also shows examples of construction efforts like access roads and channel grading. The presentation discusses the project overview, current steps being taken to get approvals, and outlines a timeline for advertising, beginning, and completing construction over the next 2-3 years.
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
The document discusses plans to replace an existing sanitary sewer line crossing Little Hunting Creek in Virginia. It describes alternatives considered, including open cut replacement, which was selected for design. Key aspects of the design include surveys, permitting requirements from various agencies, and construction plans to install the new line using a cofferdam while minimizing environmental and community impacts. Construction is scheduled to take place from July to November 2019 following design and permitting from 2017 to early 2019.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
A virtual meeting about the project will be held on August 19, 2020 at 6:00 p.m. Please see a how to sign in on slide 2. A 2019 study evaluated several alternatives for replacement. Those alternatives will be discussed with the community at the virtual meeting.
Lakevale Sewer Improvements Community MeetingFairfax County
The document summarizes sewer improvement plans for Lakevale, VA following a sewer backup event. Short term plans include installing backflow devices on homes impacted by the backup and maintenance before storms. Mid term plans involve temporary pump station modifications. Long term plans include hydraulic modeling of system alternatives, preliminary engineering and design reports, and construction which may include upsizing pipes and storage. Community input will be gathered during planning, design, and construction through public meetings and an online project website.
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations ProjectFairfax County
The work under this project included provision for the replacement of all pumping, piping, valves, generator, electrical, and mechanical equipment at each pump station. Each pump station also included structural and architectural repairs for the buildings as well as the installation of a security system. Miscellaneous site and civil modifications were also completed. This project was substantially complete on May 27, 2021.
The four pump stations (PS) included, Lakevale PS (10209 Kenbrooke Ct, Vienna), High Ridge PS (3890 Fairfax Ridge Rd, Fairfax), Weid PS (8418A Holly Leaf Drive, McLean), and Langley Oaks PS (6526 Heather Brook Ct, McLean)
Restore ~4,000 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Langley School Pump Station Community Meeting October 22, 2020Fairfax County
This document summarizes a community meeting about a wastewater infrastructure project in Fairfax County, VA. The project involves replacing an aging pump station and force main from 1966, as well as repairing or replacing sections of gravity sewer. The preliminary plan is to rebuild the pump station on the same site, relocate the force main to the road right-of-way, and replace gravity sewer sections in the same locations. Community input will be solicited on options for abandoning the old force main. The project is estimated to cost $3.4 million and is scheduled to begin construction phases in 2021, with completion targeted for 2022.
Great Passage Storm Sewer Improvement ProjectFairfax County
This project improved drainage and reduced flood potential in a Fairfax County community. It installed a headwall, yard inlet, and pedestrian bridge with handrails to increase water flow into the storm sewer system. The project cleared land, excavated, installed structures, widened a swale, added landscaping and restored the site with native plants. It was completed in May 2014 by a project team from the county's Maintenance and Stormwater Management and Utilities Design and Construction divisions.
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
This project included removal and replacement of fuel storage tanks for stand by generators at the Long Branch Sanitary Sewer Pump Station and New Alexandria Stormwater Pump Station. Existing underground storage tanks were replaced with new above ground fuel tanks. The project included installation of piping, valves, fuel polishing systems, day tanks, and appurtenances, as well as associated site work. This project was substantially complete on October 29, 2021.
Powerpoint - Langley School Pump Station and Force Main ProjectFairfax County
The Purpose
Inform the community about the upcoming project,
Phase 1 of the project is eminent
Gravity Sewer on Langley Lane
Force main from Langley High School to Georgetown Pike
Hayfield Road Pipe Conveyance System January 2021Fairfax County
The purpose of this project was to alleviate an ongoing stormwater surcharge issue in the Hayfield Road community by providing additional capacity to the stormwater sewer system through the installation of a new stormwater sewer line and outlet into the woods.
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
The Springfield Forest Schupps Add. 1115DP Summerton Way Pond project retrofitted an existing dry pond in Fairfax County, VA to improve stormwater quality and detention. The retrofit removed the existing concrete trickle ditch, regraded the facility to lengthen the flow path and maximize pond volume, excavated three micro-pools, installed an endwall, concrete apron, and trash rack at the riser, constructed an access road, and restored the site with seed and plantings. The project aims to remove phosphorus, nitrogen, and suspended solids from stormwater runoff.
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Fairfax County
Restore up to 7,500 feet of stream channel and tributaries
Reduce erosion and sediment transport
Install new sanitary sewers serving over 500 single family homes
Improve watershed conditions and reduce downstream impacts
Improve and protect public infrastructure
Prevent costly emergency repairs
Reduce risk to public health and the environment
Maintain close coordination with stakeholders and community
Build partnerships with local organizations
This document summarizes a stormwater management project in Fairfax Station, Virginia. The project retrofitted an existing stormwater pond to provide improved water quality and additional storage. Work included regrading the pond, excavating micropools, extending riprap, installing a rock weir, replacing a trail, and restoring plantings. Upon completion, the project is estimated to remove over 10 pounds of phosphorus, 2 pounds of nitrogen, and 470 pounds of suspended solids from stormwater each year.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
Fairfax County walkway construction of 1,600 linear feet of concrete sidewalk, curb ramps, curb and gutter, retaining wall, pavement markings and signage, drainage improvements and utility adjustments.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland
Harry Holland has over 40 years of experience in water infrastructure projects. He was previously the Director of Planning, Development & Professional Services at Brisbane Water, where he was responsible for strategic planning and engineering for water and sewerage infrastructure projects. Currently, through his company Harry Holland & Associates Pty Ltd, he provides engineering consulting services including design, project management, and quality verification for major pipeline and water infrastructure projects in Australia. Recent projects include providing these services for Anglo American and BMA's pipeline relocation projects in the Bowen Basin.
This document provides information about an upcoming stream restoration project along Dead Run in Fairfax County, Virginia. The project will restore 2,800 linear feet of Dead Run and its tributaries through McLean Central Park and Dead Run Stream Valley Park from February 2018 to early 2020. It will involve natural channel design, repairing a tributary headcut, replacing a pedestrian bridge, invasive plant removal, and replanting the riparian corridor. The work will be conducted in three phases by Meadville Land Services to minimize disturbances. Residents are asked to stay outside construction limits for their safety.
The Huntsman Lake Dredging project in Fairfax County, VA involved removing over 43,000 cubic yards of sediment from Huntsman Lake to increase its sediment storage capacity to over 100 years. It also included restoring the shoreline, improving aquatic habitat, and upgrading access and maintenance of the lake. The project enhances sediment and nutrient removal to improve water quality downstream.
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding the realignment of Old Courthouse Road at Besley Road. The meeting covered project progress updates, revised roadway and bridge designs, hydrologic and hydraulic analysis of the new bridge structure, maintenance of traffic plans during construction, projected costs and schedule, and a question and answer session. Traffic on Besley Road will be detoured for approximately 6 months onto nearby roads. The adjacent communities will be notified of traffic changes through various means with advanced notice.
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
A virtual meeting about the project will be held on August 19, 2020 at 6:00 p.m. Please see a how to sign in on slide 2. A 2019 study evaluated several alternatives for replacement. Those alternatives will be discussed with the community at the virtual meeting.
Lakevale Sewer Improvements Community MeetingFairfax County
The document summarizes sewer improvement plans for Lakevale, VA following a sewer backup event. Short term plans include installing backflow devices on homes impacted by the backup and maintenance before storms. Mid term plans involve temporary pump station modifications. Long term plans include hydraulic modeling of system alternatives, preliminary engineering and design reports, and construction which may include upsizing pipes and storage. Community input will be gathered during planning, design, and construction through public meetings and an online project website.
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations ProjectFairfax County
The work under this project included provision for the replacement of all pumping, piping, valves, generator, electrical, and mechanical equipment at each pump station. Each pump station also included structural and architectural repairs for the buildings as well as the installation of a security system. Miscellaneous site and civil modifications were also completed. This project was substantially complete on May 27, 2021.
The four pump stations (PS) included, Lakevale PS (10209 Kenbrooke Ct, Vienna), High Ridge PS (3890 Fairfax Ridge Rd, Fairfax), Weid PS (8418A Holly Leaf Drive, McLean), and Langley Oaks PS (6526 Heather Brook Ct, McLean)
Restore ~4,000 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Langley School Pump Station Community Meeting October 22, 2020Fairfax County
This document summarizes a community meeting about a wastewater infrastructure project in Fairfax County, VA. The project involves replacing an aging pump station and force main from 1966, as well as repairing or replacing sections of gravity sewer. The preliminary plan is to rebuild the pump station on the same site, relocate the force main to the road right-of-way, and replace gravity sewer sections in the same locations. Community input will be solicited on options for abandoning the old force main. The project is estimated to cost $3.4 million and is scheduled to begin construction phases in 2021, with completion targeted for 2022.
Great Passage Storm Sewer Improvement ProjectFairfax County
This project improved drainage and reduced flood potential in a Fairfax County community. It installed a headwall, yard inlet, and pedestrian bridge with handrails to increase water flow into the storm sewer system. The project cleared land, excavated, installed structures, widened a swale, added landscaping and restored the site with native plants. It was completed in May 2014 by a project team from the county's Maintenance and Stormwater Management and Utilities Design and Construction divisions.
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
This project included removal and replacement of fuel storage tanks for stand by generators at the Long Branch Sanitary Sewer Pump Station and New Alexandria Stormwater Pump Station. Existing underground storage tanks were replaced with new above ground fuel tanks. The project included installation of piping, valves, fuel polishing systems, day tanks, and appurtenances, as well as associated site work. This project was substantially complete on October 29, 2021.
Powerpoint - Langley School Pump Station and Force Main ProjectFairfax County
The Purpose
Inform the community about the upcoming project,
Phase 1 of the project is eminent
Gravity Sewer on Langley Lane
Force main from Langley High School to Georgetown Pike
Hayfield Road Pipe Conveyance System January 2021Fairfax County
The purpose of this project was to alleviate an ongoing stormwater surcharge issue in the Hayfield Road community by providing additional capacity to the stormwater sewer system through the installation of a new stormwater sewer line and outlet into the woods.
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
The Springfield Forest Schupps Add. 1115DP Summerton Way Pond project retrofitted an existing dry pond in Fairfax County, VA to improve stormwater quality and detention. The retrofit removed the existing concrete trickle ditch, regraded the facility to lengthen the flow path and maximize pond volume, excavated three micro-pools, installed an endwall, concrete apron, and trash rack at the riser, constructed an access road, and restored the site with seed and plantings. The project aims to remove phosphorus, nitrogen, and suspended solids from stormwater runoff.
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Fairfax County
Restore up to 7,500 feet of stream channel and tributaries
Reduce erosion and sediment transport
Install new sanitary sewers serving over 500 single family homes
Improve watershed conditions and reduce downstream impacts
Improve and protect public infrastructure
Prevent costly emergency repairs
Reduce risk to public health and the environment
Maintain close coordination with stakeholders and community
Build partnerships with local organizations
This document summarizes a stormwater management project in Fairfax Station, Virginia. The project retrofitted an existing stormwater pond to provide improved water quality and additional storage. Work included regrading the pond, excavating micropools, extending riprap, installing a rock weir, replacing a trail, and restoring plantings. Upon completion, the project is estimated to remove over 10 pounds of phosphorus, 2 pounds of nitrogen, and 470 pounds of suspended solids from stormwater each year.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
Fairfax County walkway construction of 1,600 linear feet of concrete sidewalk, curb ramps, curb and gutter, retaining wall, pavement markings and signage, drainage improvements and utility adjustments.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland
Harry Holland has over 40 years of experience in water infrastructure projects. He was previously the Director of Planning, Development & Professional Services at Brisbane Water, where he was responsible for strategic planning and engineering for water and sewerage infrastructure projects. Currently, through his company Harry Holland & Associates Pty Ltd, he provides engineering consulting services including design, project management, and quality verification for major pipeline and water infrastructure projects in Australia. Recent projects include providing these services for Anglo American and BMA's pipeline relocation projects in the Bowen Basin.
This document provides information about an upcoming stream restoration project along Dead Run in Fairfax County, Virginia. The project will restore 2,800 linear feet of Dead Run and its tributaries through McLean Central Park and Dead Run Stream Valley Park from February 2018 to early 2020. It will involve natural channel design, repairing a tributary headcut, replacing a pedestrian bridge, invasive plant removal, and replanting the riparian corridor. The work will be conducted in three phases by Meadville Land Services to minimize disturbances. Residents are asked to stay outside construction limits for their safety.
The Huntsman Lake Dredging project in Fairfax County, VA involved removing over 43,000 cubic yards of sediment from Huntsman Lake to increase its sediment storage capacity to over 100 years. It also included restoring the shoreline, improving aquatic habitat, and upgrading access and maintenance of the lake. The project enhances sediment and nutrient removal to improve water quality downstream.
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding the realignment of Old Courthouse Road at Besley Road. The meeting covered project progress updates, revised roadway and bridge designs, hydrologic and hydraulic analysis of the new bridge structure, maintenance of traffic plans during construction, projected costs and schedule, and a question and answer session. Traffic on Besley Road will be detoured for approximately 6 months onto nearby roads. The adjacent communities will be notified of traffic changes through various means with advanced notice.
Columbia Road/Randolph Court Stream Restoration July 2015Fairfax County
This document summarizes a proposed stream restoration project in Fairfax County, VA. It describes the existing failing gabion walls and eroding stream banks. The proposed project would replace the gabion walls with more natural stream restoration structures like cross vanes, root wads, and boulder toes to stabilize the banks. It would also add planted buffer zones and benches along the stream. The project requires designing temporary construction access given the steep slopes, and coordinating with other planned restoration work. It outlines the conceptual design, approval, and construction schedule.
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding a project to realign Old Courthouse Road near Besley Road and Wolftrap Elementary School. The project goals are to eliminate flooding, improve safety, and meet current road design standards. Concerns from the community such as speeding, pedestrian access, and environmental impacts were addressed. The presentation provided project details including timelines, designs, and responses to community questions and comments.
The Bradley Acres Pond Retrofit project in Fairfax County, VA converted an existing dry pond into a constructed wetland pond. The project removed the existing trickle ditch, excavated three shallow marshes, constructed a step pool conveyance channel and plunge pool, and installed two stone weir structures. Native plants were seeded and trees/plugs were replanted. The project provides improved downstream water quality by removing nutrients and suspended solids from stormwater runoff.
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)City of Midland
The purpose of this hearing was to present the planned improvements to Fairgrounds Road from State Loop (SL) 250 to Pecan Avenue in the City of Midland, Midland County, Texas, and to receive public comment. Displays will be available for viewing at 6:00 p.m. with the formal hearing commencing at 7:00 p.m.
The existing facility consists of one 12-foot travel lane in each direction with no shoulders. The existing right-of-way (ROW) width varies from approximately 62 feet south of Wadley Avenue to 77 feet historically used for the roadway north of Wadley Avenue.
The proposed project would widen Fairgrounds Road from two lanes to five lanes. South of Wadley Avenue, Fairgrounds Road would consist of one 11-foot lane and one 14-foot shared use lane in each direction and an 11-foot continuous center left-turn lane. There would be five-foot wide sidewalks on each side of the roadway. North of Wadley Avenue, Fairgrounds Road would consist of two 12-foot lanes in each direction with a 12-foot continuous center left-turn lane. An eight-foot bike/pedestrian trail would be constructed on the west side of the roadway. The length of the proposed project is approximately 1.5 miles. The proposed typical ROW width would vary from approximately 80 feet south of Wadley Avenue to approximately 129.5 feet north of Wadley Avenue. The proposed improvements would require approximately 11.4 acres of additional ROW, of which, 10.9 acres are already owned by the City of Midland. The proposed project would not result in any residential relocations or commercial displacements. Information about the tentative schedule for ROW acquisition and construction may be obtained from the City of Midland.
As part of this project, the City of Midland is considering a Section 4(f) de minimis impact determination for impacts to F.T. Hogan Park (Hogan Park). An approximate 10.9 acre strip of land generally located east of Hogan Park Golf Course from Wadley Avenue to Loop 250 would be required for permanent incorporation into the proposed transportation facility. A Section 4(f) de minimis finding means that the proposed project would not adversely affect the activities, features, or attributes that qualify Hogan Park for protection under Section 4(f). The City of Midland and TxDOT will consider comments received during this Public Hearing before making a final Section 4(f) de minimis determination.
Director of Infrastructure and Development Services Lisa Pyles and Parks and Recreation Director Slade Strickland provided City Council with a quarterly update on Addison's Capital Improvement Program and other Town projects on February 10, 2015.
Berkshire Gas Company installed approximately 2,250 feet of 12-inch gas main beneath the Connecticut River between Hadley and Hatfield, MA using horizontal directional drilling. The project involved drilling a pilot hole, reaming it to size, and pulling the gas pipe through in a single pull. It provided additional gas capacity for Amherst College and improved system reliability in the Hadley/Amherst area. The project was completed on schedule in November 2013 through careful planning, permitting, and execution of the directional drilling.
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
This document provides information about a stream stabilization project along Pike Branch in Fairfax County, VA. The project aims to stabilize approximately 1,300 feet of stream between Telegraph Road and Wilton Road to improve watershed conditions, reduce flooding and erosion, create wildlife habitat, and enhance water quality. The document discusses regulatory drivers for stormwater management, details the project objectives and timeline, describes existing conditions along the stream, and outlines proposed stabilization structures and retaining wall repairs. Next steps outlined include completing design plans and scheduling construction.
The document discusses plans to consolidate the County's stormwater, wastewater, and maintenance divisions onto a single 23.7 acre site. It provides an overview of the study process, existing conditions, concept options, and impact analyses. Three concept options were developed from staff and stakeholder input. Traffic, noise, wetlands and environmental analyses found minimal impacts. Next steps include refining the concepts and obtaining required approvals before beginning construction.
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Fairfax County
The Golden Woods Pond Retrofit project in Fairfax County, Virginia involved upgrading an existing stormwater management pond to reduce pollution and improve water quality. The project included removing a concrete ditch, constructing stone pools and a bioswale, upgrading the pond and control structure, replacing a culvert, and restoring the surrounding area. The project was completed on time and on budget in August 2016. It is estimated to reduce nitrogen, phosphorus and suspended solids pollution in the nearby Pond Branch Watershed by over 129 pounds, 10 pounds, and 7,500 pounds respectively each year.
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Fairfax County
Fairfax County plans to begin construction on a stream restoration project in Bull Neck Run in August 2018. Approximately 1,900 linear feet of Bull Neck Run will be restored. The stream runs through Fairfax County Park Authority property and Spring Hill Farm HOA property.
Overview of the Fairhill/MLK green infrastructure ambassador project taking shape in Cleveland. Includes details on project history, improvements, Project Clean Lake, traffic patterns and impacts during construction, and more.
Enbridge has expanded its major projects portfolio from $20 billion to $27 billion, announcing $11 billion in new projects. It has a proven track record of successfully delivering major pipeline projects on time and under budget through technical expertise and effective regulatory navigation. Current projects include expanding several pipelines to increase capacity and build new pipelines to access new markets.
Merrywood Force Main Rehabilitation ProjectFairfax County
The Merrywood Force Main Rehabilitation project included rehabilitation of 1,080 linear feet of 6-inch force main, its discharge manhole, and the installation of a future bypass system in front of the pump station.
PPT Item # 5 - Water Main Installation HDDahcitycouncil
The Director of Public Works is seeking approval to contract with Miller Brothers for a water main installation project via horizontal directional drilling in the Wildrose, Cloverleaf, and Rosemary areas. Miller Brothers was selected through a competitive bidding process. The project will improve infrastructure and comply with regulations by relocating water mains from rear easements to the streets. Approval is requested to amend the FY 2023 budget by $520,052 to fully fund the $970,052 project.
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use innovative & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
This document provides an overview and update on the Purple Line Extension project. It discusses the project schedule and sections, introduces the construction relations team, and focuses on upcoming work at the Wilshire/La Cienega station. Key details include that advanced utility relocation is beginning in July 2013, station box construction will start with soldier pile installation and decking, and Metro is seeking exemptions to work restrictions to complete the project faster and minimize impacts. The document aims to inform stakeholders on project progress and receive their feedback.
Similar to Hayfield Road Project Citizens Association Meeting Oct. 18, 2017 (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
This document summarizes a pedestrian access improvement project along Clarks Crossing Road in Fairfax County, Virginia. The project improved pedestrian and bicycle access by constructing a missing link of sidewalk between Brookside Lane and an existing sidewalk further along Clarks Crossing Road. Work included installing sidewalk, curb ramps, drainage improvements, and milling and overlaying asphalt. The project was substantially completed in March 2022 and provides approximately 200 feet of new pedestrian access along Clarks Crossing Road.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Sully Community Center Construction ProgressFairfax County
This document provides construction progress photos of the Sully Community Center in Fairfax County, Virginia. The photos show the ongoing construction of the building's exterior, interior spaces like the lobby, corridors, multi-purpose rooms, game room, gym, exercise room, and healthcare suite. The document was published by the Fairfax County Department of Public Works and Environmental Services to share updates on the construction of the new community center, which is scheduled to open in summer 2022.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This document summarizes a meeting about a proposed arts center in Reston, Virginia that would result from a proffer from Boston Properties for development of an area known as Block J. The meeting covered the background and objectives of community outreach efforts to understand needs for the arts venue. Feedback was shared from previous focus group meetings on performing arts, visual arts, and other topics. Key spaces discussed included a 500-seat theater, art studios, galleries, and support spaces. Next steps include further programming, cost estimating, and community input before potential design and construction.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
This document summarizes a focus group meeting to discuss needs and ideas for a proposed new arts center in Reston, Virginia. The meeting covered background on the proposed project, which would result from a development proffer. Attendees provided input through polls and discussion on desired visual arts programming, spaces, and amenities. Key priorities identified included studio space, galleries, classrooms, digital media facilities, and ensuring the center is diverse, equitable and accessible. The project team will take this community feedback into account as they continue planning.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
A Comprehensive Guide on Cable Location Services Detections Method, Tools, an...Aussie Hydro-Vac Services
Explore Aussie Hydrovac's comprehensive cable location services, employing advanced tools like ground-penetrating radar and robotic CCTV crawlers for precise detection. Also offering aerial surveying solutions. Contact for reliable service in Australia.
The modification of an existing product or the formulation of a new product to fill a newly identified market niche or customer need are both examples of product development. This study generally developed and conducted the formulation of aramang baked products enriched with malunggay conducted by the researchers. Specifically, it answered the acceptability level in terms of taste, texture, flavor, odor, and color also the overall acceptability of enriched aramang baked products. The study used the frequency distribution for evaluators to determine the acceptability of enriched aramang baked products enriched with malunggay. As per sensory evaluation conducted by the researchers, it was proven that aramang baked products enriched with malunggay was acceptable in terms of Odor, Taste, Flavor, Color, and Texture. Based on the results of sensory evaluation of enriched aramang baked products proven that three (3) treatments were all highly acceptable in terms of variable Odor, Taste, Flavor, Color and Textures conducted by the researchers.
Exploring low emissions development opportunities in food systemsCIFOR-ICRAF
Presented by Christopher Martius (CIFOR-ICRAF) at "Side event 60th sessions of the UNFCCC Subsidiary Bodies - Sustainable Bites: Innovating Low Emission Food Systems One Country at a Time" on 13 June 2024
Download the Latest OSHA 10 Answers PDF : oyetrade.comNarendra Jayas
Latest OSHA 10 Test Question and Answers PDF for Construction and General Industry Exam.
Download the full set of 390 MCQ type question and answers - https://www.oyetrade.com/OSHA-10-Answers-2021.php
To Help OSHA 10 trainees to pass their pre-test and post-test we have prepared set of 390 question and answers called OSHA 10 Answers in downloadable PDF format. The OSHA 10 Answers question bank is prepared by our in-house highly experienced safety professionals and trainers. The OSHA 10 Answers document consists of 390 MCQ type question and answers updated for year 2024 exams.
Monitor indicators of genetic diversity from space using Earth Observation dataSpatial Genetics
Genetic diversity within and among populations is essential for species persistence. While targets and indicators for genetic diversity are captured in the Kunming-Montreal Global Biodiversity Framework, assessing genetic diversity across many species at national and regional scales remains challenging. Parties to the Convention on Biological Diversity (CBD) need accessible tools for reliable and efficient monitoring at relevant scales. Here, we describe how Earth Observation satellites (EO) make essential contributions to enable, accelerate, and improve genetic diversity monitoring and preservation. Specifically, we introduce a workflow integrating EO into existing genetic diversity monitoring strategies and present a set of examples where EO data is or can be integrated to improve assessment, monitoring, and conservation. We describe how available EO data can be integrated in innovative ways to support calculation of the genetic diversity indicators of the GBF monitoring framework and to inform management and monitoring decisions, especially in areas with limited research infrastructure or access. We also describe novel, integrative approaches to improve the indicators that can be implemented with the coming generation of EO data, and new capabilities that will provide unprecedented detail to characterize the changes to Earth’s surface and their implications for biodiversity, on a global scale.
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
October 18, 2017
Hayfield Road
Pipe
Conveyance
Project
Hayfield Citizens Association Meeting –
October 18, 2017
3. Design Changes – Sanitary Sewer Main & Laterals
3WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Hayfield Road Pipe Conveyance Project
Existing sanitary main under the median strip & property service lateral
connections pose elevation conflicts with storm conduit elevation
• Known early on
• Original design included only 10 homes
• Shared in prior HFCA meeting presentations
Approaching the 95% plan review, it became apparent that design did not
allow sufficient cover (i.e., distance or separation) between the necessary
pipe installation work & the remaining sanitary laterals
• Laterals are owned & maintained by individual property owners
• New sanitary laterals will be installed to just behind the side walk -
on the residence side of the side walk
4. 4
CCTV inspection of the existing main & all the laterals (23 properties) on the west side of
Hayfield Road
• Complete on September 29
• Final report due to the County in November
• Condition report will be shared with each of the 23 property owners
New laterals must be installed according to the VUSBC (Va. Uniform Statewide Building Code)
• Contractor will secure necessary Plumbing permit to complete the work
• Inspection & approval is required before the contractor can backfill the work &
continue
• Each property owner will be provided a copy of the permit & evidence of
inspection approval
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Hayfield Road Pipe Conveyance Project
Design Changes – Sanitary Sewer Main & Laterals
5. 5
Hayfield Road Pipe Conveyance Project
Design Changes – Sanitary Sewer Main & Laterals
Contractor will be required to provide a minimum 48-hours advance
notice prior to making the cross-over to the new lateral
Extending the new/parallel sanitary main drives the new storm pipe &
box culvert toward the median strip
• Additional impacts on the median curb & gutter
• As always VDOT & design requirements have driven impacts to the
median
• We continue to seek ways to minimize landscape impacts
o During Bowman’s design efforts
o Even to the point of making field decisions during construction,
if possible
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
6. 6
Started relocation work on September 6, 2017
Work scheduled to be complete in January 2018
WGL reports:
o Main is a little more than 50% complete
o Challenge – only 3 individual service
connections completed of approximately
60 needed
WGL has been very responsive to the
County’s requests. Not having heard
any news, presumably they have been
good neighbors in the community.
Hayfield Road Pipe Conveyance Project
Utility Relocation Status – Washington Gas
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
7. 7
Broadmoor Street to end at pool property
Scheduled to begin their relocation work in January 2018
• Field crews are detailed to Florida restoration
• Not known yet whether Puerto Rico will impact
Dominion crew availability
Estimate 90 days to complete relocation/raising lines
• So, complete in April
• Conditioned on the weather
Cox Communications & Verizon will follow by raising their lines
Finally, Dominion will return to remove abandoned poles
Utility Relocation Status – Dominion Energy
Hayfield Road Pipe Conveyance Project
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
9. 9WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Hayfield Road Pipe Conveyance Project
Utility Relocation Status – Dominion Energy
All the same
utilities at
Telegraph Road
intersection –
just more of
them.
Plus, VDOT’s
traffic lights.
Dominion
working on this
relocation plan
now. Will
schedule the
work as soon as
possible.
O/H lines @
Telegraph Road
11. 11
Hayfield Road Pipe Conveyance Project
Progress Overview
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Wrap up final VDOT permit submission requirements
Secure additional utility company relocation schedule commitments – underground services
• Dominion, Cox, & Verizon have underground locations approximately mid-way down
Hayfield Road (Dominion has another near Luton Place & at Telegraph Road intersection)
• Cox has one additional underground location near Broadmoor Street
• Duct bank relocation of approximately 12 – 14 conduits @ Telegraph Road
Construction contract bid
• Bid ad open 30 days – announce apparent low bidder
• 60 - 70 days to finalize contract requirements & award contract
• Issue NTP as soon as possible after notice to Board of Supervisors
• Contractor structure fabrication submissions to VDOT review – 30 day turnaround –
manhole vaults, box culvert sections, outfall design & wing walls
With contract awarded/NTP issued, will schedule site walk with Police, Fire & Rescue, FCPS,
contractor, & County staff
12. 12
Hayfield Road Pipe Conveyance Project
Continuing Communication
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Other thoughts:
Offer suggestions on how best to communicate with
the community at-large
When is next HCA meeting date?
As soon as construction contract awarded, we will return to:
• Share their construction schedule
• Identify key contractor personnel
• Discuss continuing/on-going progress meetings with HCA
What did I miss?
Anything else?
13. Contact Information
For additional information, please contact
13WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Dave Anglin, Section Chief
dave.anglin@fairfaxcounty.gov
703-324-5500
www.fairfaxcounty.gov/dpwes
Hayfield Road Pipe Conveyance Project