Berkshire Gas Company installed approximately 2,250 feet of 12-inch gas main beneath the Connecticut River between Hadley and Hatfield, MA using horizontal directional drilling. The project involved drilling a pilot hole, reaming it to size, and pulling the gas pipe through in a single pull. It provided additional gas capacity for Amherst College and improved system reliability in the Hadley/Amherst area. The project was completed on schedule in November 2013 through careful planning, permitting, and execution of the directional drilling.
Merrywood Force Main Rehabilitation ProjectFairfax County
The Merrywood Force Main Rehabilitation project included rehabilitation of 1,080 linear feet of 6-inch force main, its discharge manhole, and the installation of a future bypass system in front of the pump station.
A monthly status and progress report for the Cove Point LNG export facility reporting the facility is 38% built. Dominion also reports the engineering is about done (99.8% complete) and equipment purchases are also done (99% complete).
A webinar slide presentation from Williams detailing their Northeast Supply Enhancement pipeline project--a Transco pipeline project that will increase capacity and flows heading into northeastern markets. In particular, Transco wants to provide more natural gas to utility giant National Grid beginning with the 2019-2020 heating season.
Merrywood Force Main Rehabilitation ProjectFairfax County
The Merrywood Force Main Rehabilitation project included rehabilitation of 1,080 linear feet of 6-inch force main, its discharge manhole, and the installation of a future bypass system in front of the pump station.
A monthly status and progress report for the Cove Point LNG export facility reporting the facility is 38% built. Dominion also reports the engineering is about done (99.8% complete) and equipment purchases are also done (99% complete).
A webinar slide presentation from Williams detailing their Northeast Supply Enhancement pipeline project--a Transco pipeline project that will increase capacity and flows heading into northeastern markets. In particular, Transco wants to provide more natural gas to utility giant National Grid beginning with the 2019-2020 heating season.
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
KAUST engaged Maritime Survey Australia to act as a project manager to oversee a major refit of the vessel, RV Thuwal which involved wiring upgrades, installation of new navigational equipment, a new galley, a scientific survey room and a vessel upgrade of the hydraulics, heating, ventilation and cooling systems.
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
KAUST engaged Maritime Survey Australia to act as a project manager to oversee a major refit of the vessel, RV Thuwal which involved wiring upgrades, installation of new navigational equipment, a new galley, a scientific survey room and a vessel upgrade of the hydraulics, heating, ventilation and cooling systems.
Avant la création d'un questionnaire, d'un sondage, d'une enquête ou d'une étude de marché, il est nécessaire de préparer celle-ci au préalable. Drag'n Survey est un logiciel en ligne gratuit pour la création, la diffusion et l'analyse de questionnaire en ligne. Les équipes de Drag'n Survey mettent à disposition des utilisateurs des aides pour les accompagner dans leurs créations.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Marcellus Drilling News
Empire Pipeline, a subsidiary of National Fuel Gas Company (which also owns driller Seneca Resources) is asking the Federal Energy Regulatory Commission (FERC) for approval on a new 17-mile pipeline in Steuben County, NY. The project is called the Tuscorara Lateral Project and will cost a projected $43 million. The pipeline will connect a gas storage field and compressor station in Tuscarora, NY (also owned by National Fuel Gas) with the existing Empire Pipeline network--a network that stretches from Buffalo to Syracuse and down to Corning. This "little" piece of pipeline will open up much needed extra volumes of natural gas for Upstate New Yorkers.
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Fairfax County
Fairfax County plans to begin construction on a stream restoration project in Bull Neck Run in August 2018. Approximately 1,900 linear feet of Bull Neck Run will be restored. The stream runs through Fairfax County Park Authority property and Spring Hill Farm HOA property.
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Comprehensive program for Agricultural Finance, the Automotive Sector, and Empowerment . We will define the full scope and provide a detailed two-week plan for identifying strategic partners in each area within Limpopo, including target areas.:
1. Agricultural : Supporting Primary and Secondary Agriculture
• Scope: Provide support solutions to enhance agricultural productivity and sustainability.
• Target Areas: Polokwane, Tzaneen, Thohoyandou, Makhado, and Giyani.
2. Automotive Sector: Partnerships with Mechanics and Panel Beater Shops
• Scope: Develop collaborations with automotive service providers to improve service quality and business operations.
• Target Areas: Polokwane, Lephalale, Mokopane, Phalaborwa, and Bela-Bela.
3. Empowerment : Focusing on Women Empowerment
• Scope: Provide business support support and training to women-owned businesses, promoting economic inclusion.
• Target Areas: Polokwane, Thohoyandou, Musina, Burgersfort, and Louis Trichardt.
We will also prioritize Industrial Economic Zone areas and their priorities.
Sign up on https://profilesmes.online/welcome/
To be eligible:
1. You must have a registered business and operate in Limpopo
2. Generate revenue
3. Sectors : Agriculture ( primary and secondary) and Automative
Women and Youth are encouraged to apply even if you don't fall in those sectors.
Core technology of Hyundai Motor Group's EV platform 'E-GMP'Hyundai Motor Group
What’s the force behind Hyundai Motor Group's EV performance and quality?
Maximized driving performance and quick charging time through high-density battery pack and fast charging technology and applicable to various vehicle types!
Discover more about Hyundai Motor Group’s EV platform ‘E-GMP’!
Fleet management these days is next to impossible without connected vehicle solutions. Why? Well, fleet trackers and accompanying connected vehicle management solutions tend to offer quite a few hard-to-ignore benefits to fleet managers and businesses alike. Let’s check them out!
Ever been troubled by the blinking sign and didn’t know what to do?
Here’s a handy guide to dashboard symbols so that you’ll never be confused again!
Save them for later and save the trouble!
Symptoms like intermittent starting and key recognition errors signal potential problems with your Mercedes’ EIS. Use diagnostic steps like error code checks and spare key tests. Professional diagnosis and solutions like EIS replacement ensure safe driving. Consult a qualified technician for accurate diagnosis and repair.
What Does the PARKTRONIC Inoperative, See Owner's Manual Message Mean for You...Autohaus Service and Sales
Learn what "PARKTRONIC Inoperative, See Owner's Manual" means for your Mercedes-Benz. This message indicates a malfunction in the parking assistance system, potentially due to sensor issues or electrical faults. Prompt attention is crucial to ensure safety and functionality. Follow steps outlined for diagnosis and repair in the owner's manual.
"Trans Failsafe Prog" on your BMW X5 indicates potential transmission issues requiring immediate action. This safety feature activates in response to abnormalities like low fluid levels, leaks, faulty sensors, electrical or mechanical failures, and overheating.
5 Warning Signs Your BMW's Intelligent Battery Sensor Needs AttentionBertini's German Motors
IBS monitors and manages your BMW’s battery performance. If it malfunctions, you will have to deal with an array of electrical issues in your vehicle. Recognize warning signs like dimming headlights, frequent battery replacements, and electrical malfunctions to address potential IBS issues promptly.
𝘼𝙣𝙩𝙞𝙦𝙪𝙚 𝙋𝙡𝙖𝙨𝙩𝙞𝙘 𝙏𝙧𝙖𝙙𝙚𝙧𝙨 𝙞𝙨 𝙫𝙚𝙧𝙮 𝙛𝙖𝙢𝙤𝙪𝙨 𝙛𝙤𝙧 𝙢𝙖𝙣𝙪𝙛𝙖𝙘𝙩𝙪𝙧𝙞𝙣𝙜 𝙩𝙝𝙚𝙞𝙧 𝙥𝙧𝙤𝙙𝙪𝙘𝙩𝙨. 𝙒𝙚 𝙝𝙖𝙫𝙚 𝙖𝙡𝙡 𝙩𝙝𝙚 𝙥𝙡𝙖𝙨𝙩𝙞𝙘 𝙜𝙧𝙖𝙣𝙪𝙡𝙚𝙨 𝙪𝙨𝙚𝙙 𝙞𝙣 𝙖𝙪𝙩𝙤𝙢𝙤𝙩𝙞𝙫𝙚 𝙖𝙣𝙙 𝙖𝙪𝙩𝙤 𝙥𝙖𝙧𝙩𝙨 𝙖𝙣𝙙 𝙖𝙡𝙡 𝙩𝙝𝙚 𝙛𝙖𝙢𝙤𝙪𝙨 𝙘𝙤𝙢𝙥𝙖𝙣𝙞𝙚𝙨 𝙗𝙪𝙮 𝙩𝙝𝙚 𝙜𝙧𝙖𝙣𝙪𝙡𝙚𝙨 𝙛𝙧𝙤𝙢 𝙪𝙨.
Over the 10 years, we have gained a strong foothold in the market due to our range's high quality, competitive prices, and time-lined delivery schedules.
In this presentation, we have discussed a very important feature of BMW X5 cars… the Comfort Access. Things that can significantly limit its functionality. And things that you can try to restore the functionality of such a convenient feature of your vehicle.
What Exactly Is The Common Rail Direct Injection System & How Does It WorkMotor Cars International
Learn about Common Rail Direct Injection (CRDi) - the revolutionary technology that has made diesel engines more efficient. Explore its workings, advantages like enhanced fuel efficiency and increased power output, along with drawbacks such as complexity and higher initial cost. Compare CRDi with traditional diesel engines and discover why it's the preferred choice for modern engines.
Why Is Your BMW X3 Hood Not Responding To Release CommandsDart Auto
Experiencing difficulty opening your BMW X3's hood? This guide explores potential issues like mechanical obstruction, hood release mechanism failure, electrical problems, and emergency release malfunctions. Troubleshooting tips include basic checks, clearing obstructions, applying pressure, and using the emergency release.
1. Connecticut River Crossing 2013
Hadley/Hatfield, MA
David M. Grande
Director – Gas Engineering & System Operations
Berkshire Gas Company
115 Cheshire Road
Pittsfield, MA 01202-1388
Phone 413-445-0265
dgrande@berkshiregas.com
Paul Scarpa
Senior Engineer
Berkshire Gas Company
115 Cheshire Road
Pittsfield, MA 01202-1388
Phone 413-445-0383
pscarpa@berkshiregas.com
Confidential – Not for internal distribution or public release.
1
2. Berkshire Gas Company – Located in Western Massachusetts
Connecticut River
12/19/13
22
3. Company Information
• 38,000 Customers
• 1,500 Miles – Mains & Services
• 1 Satellite LNG Plant
• 3 Propane Air Plants
• 120 Employees
• 160 Years Old
• 6 City Gate Stations
12/19/13
33
4. Project Context – Connecticut River Crossing
•
Installation of approximately 2,250 linear feet of 12-inch coated steel gas
main. The project commences on Bridge Lane in Hatfield, MA and continues
beneath the Connecticut River, terminating on Huntington Rd. in Hadley, MA.
Approximately 1,600 linear feet of the proposed gas main shall be installed
beneath the Connecticut River via directional drilling. The remaining 650
linear shall be installed within an open trench.
•
Project is being done to provide additional firm volumes to Amherst College
and provide additional system reliability for the Hadley/Amherst area.
•
New main will run in parallel with existing 6-inch coated steel main which was
installed in 1959 when the Company brought Natural Gas service to the
Hadley/Amherst area.
12/19/13
44
5. UMASS & Amherst College – Amherst MA
UMASS – Central Heating Plant
Amherst College – Central Heating Plant
12/19/13
55
7. Project Mile Stones
•
Engineering for Project began in November 2012
• The following was performed:
•
•
•
•
•
•
Survey – current easement (Hadley) town ROW (Hatfield)
Test Borings – both sides of the river
Preliminary Design Plans- used to submit wetland filings
Wetland Delineation
Notice of Intent
• Wetland Notice of Intent submission to the Hadley and Hatfield Conservation
Commissions and Mass DEP
• Filing Notice of Intent with the Natural Heritage and Endanger Species Program
(NHESP)
Army Corps of Engineers (ACOE) Category 2 Permit filing
•
Frac Out Plan
Final Design Plans and Details
• Final Permit Approval Received in September 2013
•
12/19/13
77
8. Project Milestones
•
Request for Proposal (RFP) was issued on 8/19/2013
•
•
•
12/19/13
Bidders
• Hemlock Directional Boring Inc.
• C.B. Utility Co., Inc.
• JS Rae Construction
• Directional Technologies, Inc.
• Mears Group Inc.
RFP’s were due on 9/3/2013
Project Awarded to JS Rae on 9/9/2013
88
12. Current Conditions – Hatfield Side
Milestone Schedule
Hatfield – Westside – River Approx. 900 ft. wide
12/19/13
12
12
13. Current Conditions – Hadley Side
Milestone Schedule
Hadley – Eastside
12/19/13
13
13
14. Connecticut River Crossing
Milestone Schedule
– Hadley Side
Existing 6” Coated Steel Main
Company has existing 25ft. Permanent and working easement
12/19/13
14
14
20. Connecticut River Crossing – Corrosion Control
Milestone Schedule
Warrior 100 Pipe Coating & Rubber Pipe Rollers
12/19/13
20
20
21. Connecticut River Crossing – Corrosion Control
Milestone Schedule
Powercrete R-95 Epoxy Based Coating Used for Welds – Designed for HDD
12/19/13
21
21
22. Connecticut River Crossing – Initial Pressure Test
Milestone Schedule
Final Pressure Test – 300 Psig – 4 Hours - Deadweight
12/19/13
22
22
23. Connecticut River Crossing - Drilling
Milestone Schedule
During the pilot hole drilling, a directional guidance system is used to
navigate the pilot hole along its pre-designed profile.
Down Hole System – Wire Line
12/19/13
23
23
27. Construction - Drilling Pilot Hole
Milestone Schedule – 120ft. 30” & 130ft. 12”
Conductor barrel were used
•
•
Used to minimize the potential of a drilling frac out and/or ground collapse near the entry location.
The conductor barrel created a clear pathway through the soft soil conditions so that drilling could begin in more preferable geology
12/19/13
27
27
29. Construction – Drilling Pilot Hole
Milestone Schedule
Final Pilot Hole Maximum Depth was 60 ft. Below Existing River Bed,
12/19/13
29
29
30. Construction - Reaming
Milestone Schedule
22” ream & 18” ream were used.
The 22” ream was used to go through the bedrock
12/19/13
30
30
31. Construction - Reaming
Milestone Schedule
Reaming consisted of pushing from the drill rig in Hadley and pulling with excavator in Hatfield.
12/19/13
31
31
41. Questions
David M. Grande
Director – Gas Engineering & System Operations
Berkshire Gas Company
115 Cheshire Road
Pittsfield, MA 01202-1388
Phone 413-445-0265
dgrande@berkshiregas.com
12/19/13
41
41