SlideShare a Scribd company logo
DESIGN AND ANALYSIS OF MULTI-
TOWER STRUCTURE USING ETABS
BY
KHALED AL SHAMI
INTRODUCTION
 BASEMENT.
 3 PARKING FLOORS.
 2 FLOOR HEALTH CLUB.
 13 FLOOR HOTEL TOWER (LEFT).
 33 FLOOR OFFICE TOWER (RIGHT).
LOCATION
 AT THE HEART OF AMMAN IN MECCA STREET.
 SURROUNDING AREA IS MOSTLY OFFICE TOWERS.
 POSITIONED NEAR AN INTERCHANGE.
 VERY HIGH ACCESSIBILITY.
WHY ETABS AND SAFE ?
 DEVELOPED BY CSI (CONSTRUCTION SPECIFICATION INSTITUTE).
 THEY WORK COMPATIBLY.
 2D/3D MODELLING.
 LINEAR/NON-LINEAR ANALYSIS.
 SIMULATION OF EARTHQUAKE AND WIND LOAD ON STRUCTURE.
 FRIENDLY INTERFACE, EVEN FOR DESIGN OF COMPLICATED STRUCTURES.
DEAD LOAD CALCULATION
LOAD NAME VALUE UNIT SOURCE
PARTITION 2 kN/m2 UBC 97 code
TILING (MARBLE) 0.4 kN/m2 2cm * 20 kN/m3
MORTAR (LIGHTWEIGHT
CONCRETE)
0.16 kN/m2 2cm * 8 kN/m3
MECHANICAL AND ELECTRICAL
EQUIPMENT
0.2 kN/m2 UBC 97 code, table
16-B
FALSE CEILING 0.1 kN/m2 UBC 97 code, table
16-B
FIRE SPRINKLERS 1.11 kN/m2 UBC 97 code, table
16-B
TOTAL 3.97 Take as 4
OTHER LOADS
FAÇADE LOAD
 APPLIED ON THE PERIMETER OF THE STRUCTURE
 HAS VALUE OF 1KN/M2. (ASCE7-5 CODE, SECTION 9.8).
SNOW LOAD
 MINIMUM SNOW LOADS (0.240 KN/M2) ARE APPLIED.
LIVE LOAD REDUCTION
 ACCORDING TO UBC 97 PROVISIONS.
 TRIBUTARY AREA METHOD.
 MINIMUM FACTOR FOR MULTIPLE STORIES IS 0.4.
LIVE LOAD (ACCORDING TO IBC 2009)
AREA LOAD UNIT SOURCE
GROUND FLOOR 4 kN/m2 IBC 2009
Code
PARKING FLOORS (1-3) 4 kN/m2 IBC 2009
Code
HEALTH CLUB (1-2) 4 kN/m2 IBC 2009
Code
LEFT TOWER (13 FLOORS HOTEL) 3.2 kN/m2 IBC 2009
Code
RIGHT TOWER (33 FLOORS
OFFICE AREA)
3.6 kN/m2 IBC 2009
Code.
WIND LOAD (UBC 97)
WIND LOAD (ASCE 7-05)
TYPE ANNOTATION VALUE UNIT SOURCE
WIND SPEED - 78 MpH Amman
municipality
DIRECTIONALITY
FACTOR
Kd 0.85 - ASCE 7-05 -
C6.5.4.4
IMPORTANCE
FACTOR
I 1 - ASCE 7-05 -
C6.5.5
EXPOSURE TYPE - B - ASCE 7-05 -
C6.5.6
TOPOGRAPHICAL
FACTOR
Kzt 1 - ASCE 7-05 -
C6.5.7
GUST FACTOR G 0.85 - ASCE 7-05 -
C6.5.8
WIND EXPOSURE PARAMETERS (ASCE 7-05)
EARTHQUAKE LOADS (UBC 97)
 TWO LOAD CASES (Qx, Qy).
TYPE ANNOTATION VALUE SOURCE
IMPORTANCE
FACTOR
I 1 TABLE 16-K UBC CODE
OVER-
STRENGTH
FACTOR
R 4.5 TABLE 16-N UBC CODE
TIME PERIOD CT 0.02 PROGRAM CALCULATED
SOIL PROFILE - SC TABLE 16-J UBC CODE
SEISMIC ZONE
FACTOR
Z 0.20 TABLE 16-I UBC CODE
LOAD COMBINATION
 TWO MANUALLY GENERATED COMBINATIONS.
 SHEAR WALL COMBINATIONS AND CONCRETE FRAME COMBINATION ARE
AUTOMATICALLY GENERATED.
Name Load Scale Factor Load Scale Factor Type
Service Load Dead 1.0 Live 1.0 Linear
Ultimate Load Dead 1.4 Live 1.6 Linear
MODELLING
 1. DEFINE
1. MATERIALS (CONCRETE, STEEL).
2. FRAME SECTIONS (COLUMNS, BEAMS)
3. SHELLS (SLABS, WALLS)
4. OPENINGS IF ANY EXISTS.
5. DEFINE SECTION MODIFIRES.
 2. DRAW
1. COLUMNS
2. BEAMS
3. ROOFS
4. WALLS
5. OPENINGS
MODELLING
 3. DEFINE
1. EARTHQUAKE LOAD (EQX, EQY).
2. WIND LOAD (WX, WY).
3. RESPONSE SPECTRUM FUNCTION (SPEC-UBC).
4. RESPONSE SPECTRUM LOAD CASES (SPEC-X, SPEC-Y).
5. MASS SOURCE.
6. P-DELTA CASE.
7. MODAL CASE (EIGEN).
 4. ASSIGN
1. AREA LOADS (ON SLABS).
2. LINE LOADS (ON BEAMS).
3. DIAPHRAGM
4. SUPPORTS (FIXED/PINNED).
5. MOMENT RELEASES FOR BEAMS.
6. MESHING (FOR WALLS AND SLABS).
7. PIER AND SPANDREL LABELS.
8. LIVE LOAD REDUCTION FACTOR.
9. SPECIAL SESIMIC EFFECTS.
 RUN
ANALYSIS
STRUCTURE'S DEFORMED SHAPE
CORE MOMENT
 ELEVATORE CORE MOMENT
CHECKING BEAMS
FOR ANY LOAD CASE OR COMBO.
 VIEW MOMENT.
 VIEW SHEAR.
 VIEW DEFLECTION.
CHECKING SLABS
CHECKING OVER-ALL DEFLECTION
 FOR UNFACTORED WIND:
H
500
=
13127
500
= 26.26 𝑐𝑚
 FACTORED SEISMIC LOAD: 0.02H = 0.02 * 13127 = 262.54 CM (ACCORDING TO UBC 97 CODE).
OR: 0.005H = 0.0065 * 13127 = 85.32 CM (ACCORDING TO JAPANESE CODE).
Load Case Translation (cm) Translation (cm) Comparison (cm)
X-Dir Y-Dir X-Dir Y-Dir
Qx 2.66 0.01 40.04 -0.86 40.04 < 262.54 safe
Qy -0.46 3.37 -2.78 68.16 68.16 < 262.54 safe
Translation (mm) Translation (mm) Comparison (mm)
Wx 1.1 11.2 8.3 108.3 108.3 < 262.6 safe
Wy 4.6 14.9 37.1 144.8 144.8 < 262.6 safe
INTER-STORY DRIFT CHECK
 Drift is the difference in horizontal deflection between the top and bottom
of any storey.
 The story drift shall not exceed 2.5% of the story height for structures with
fundamental period less than 0.7 second, for it to be considered safe.
 Allowable story drift = 2.5% * 3300mm = 82.5mm .
Load Case Maximum Drift
(mm)
Comparison Safety
Qx 4.185 4.185 < 82.5 Safe
Qy 6.538 6.538 < 82.5 Safe
MODAL RESPONSE SPECTRA (STORY RESPONSE)
 STORY SHAERS
 LOAD CASE : RESPONSE SPECTRUM
MODAL RESPONSE SPECTRA (STORY RESPONSE)
 MAXIMUM STORY DISPLACEMENT
 MODE 1.
MODAL RESPONSE SPECTRA (STORY RESPONSE)
 MAXIMUM STORY DISPLACEMENT
 MODE 25.
WIND VELOCITY PROFILE
 CALCULATED WIND VELOCITY PROFILE.
STRUCTURAL DESIGN
SHEAR WALL DESIGN
 Longitudinal reinforcement.
 Shear reinforcement.
SHAER WALL LONGITUDINAL REINFORCEMENT
 USED CODE ACI318-08.
 REINFORCEMENT CALCULATED BY ETABS.
 DEMAND/CAPACITY RATIO = 1 (USING 95% OF THE SECTION AREA)
THUS (5% FOR SAFETY).
Story Pier ID Location Required
Reinf %
As
(Cm2)
Reinforcement
32ND P1 Top 0.62 173.6 ⌀ 22 @ 20 C/C
32ND P1 Bottom 0.58 162.4 ⌀ 22 @ 20 C/C
31ST P1 Top 0.58 162.4 ⌀ 22 @ 20 C/C
31ST P1 Bottom 0.48 134.4 ⌀ 20 @ 20 C/C
30TH P1 Top 0.49 137.2 ⌀ 20 @ 20 C/C
30TH P1 Bottom 0.45 126 ⌀ 20 @ 20 C/C
SHEAR WALL HORIZONTAL REINFORCEMENT
 SPECIFY NUMBER OF BARS
IN ONE METER.
Shear reinforcement (cm2/m) Calculation Selected Reinforcement
17.5
17.5/7 = 2.5 take ⌀18 ⌀18 @ 15cm c/c
31.45
31.45/7 = 4.49 take ⌀25 ⌀25 @ 15cm c/c
SHEAR WALL RENDERING & DETAILING
SHAERWALL DETAILING
SHEAR WALL DETAILING.
 REINFORCEMENT.
 SPACING.
BEAM REINFORCEMENT
 LONGITUDINAL REINFORCEMENT.
BEAM DESIGN (LONGITUDINAL REINFORCEMENT)
ASSUME A BEAM SECTION WITH
 4 BARS AT TOP.
 4 BARS AT BOTTOM.
AS (CM2) BAR SIZE UNIT REINFORCEMENT
10
10
4
= 2.5
CM2 4 ⌀ 18
5
5
4
= 1.25
CM2 4 ⌀ 14
12 12
4
= 3.00
CM2 4 ⌀ 20
7
7
4
= 1.75
CM2 4 ⌀ 16
4
4
4
= 1.00
CM2 4 ⌀ 12
8
8
4
= 2.00
CM2
4 ⌀ 16
BEAM LONGITUDINAL REINFORCEMENT
 FINAL RESULT
BEAM SHEAR REINFORCEMENT
BEAM SHEAR REINFORCEMENT
 ASSUME DIAMETER OF STIRRUPS TO BE 10MM.
 𝑆 =
𝐴𝑠∗𝑁𝑜. 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝 𝑙𝑒𝑔𝑠
𝑣𝑎𝑙𝑢𝑒 𝑔𝑖𝑣𝑒𝑛 𝑖𝑛 𝐸𝑇𝐴𝐵𝑆
 𝑆 =
79∗2
7.82
= 20.20 𝑇𝐴𝐾𝐸 𝐴𝑆 20𝐶𝑀
 𝑆 =
79∗2
4.72
= 33.47 𝑇𝐴𝐾𝐸 𝐴𝑆 30𝐶𝑀
DIAPHRAGMS
 EACH SLAB HAS ITS OWN DIAPHRAGM.
 DIAPHRAGMS ARE ALL RIGID.
 RIGID DIAPHRAGMS HAVE INFINITE IN-PLANE STIFFNESS PROPERTIES.
 THEY DON’T EXHIBIT THE ACTUAL IN-PLANE STIFFNESS PROPERTIES AND BEHAVIOUR.
 THE ADVANTAGE OF THIS METHOD IS DECREASING THE COMPUTATIONAL TIME.
SLAB MODELLING
3DIAPHRAGMS, WHY ?
 FOR COLLAPSE MECHANISM.
 FOR EARTHQUAKE JOINT.
MODELLING POST TENSION SLABS
WHY POST TENSION SLAB ?
 TO HELP REDUCING SLAB THICKNESS
 SAVE ON REBAR STEEL.
 LESS TIME CONSUMING.
 NO NEED FOR DROP BEAMS.
POST TENSION SLAB MODELLING
 SLAB MODEL ON SAFE 2014.
POST TENSION SLAB DESIGN
 TENDON LAYOUT.
POST TENSION SLAB DESIGN
SLAB DESIGN OUTPUT
 TENDON PROFILES.
 AMOUNT OF PULLING FORCE FOR EACH TENDON.
 NEEDED ELONGATION VALUES FOR EACH TENDON.
 DEAD ENDS AND LIVE ENDS.
 BILL OF QUANTITY (BOQ) FOR SLAB.
POST TENSION SLAB DESIGN
 BILL OF QUANTITY BY SAFE 2014.
POST TENSION SLAB DESIGN
 REQUIRED REINFORCMENT.
 TOP REBAR PLAN.
CONSTRUCTION MANAGEMENT
COMMUNICATION BETWEEN PROJECT PARTICIPANTS
 MANY CONSULTANTS.
 A LOT OF WORKERS.
 DIFFERENT COMPANIES.
??? HOW TO ARRANGE COMMUNICATION ???
 PROLOG IS A WEB BASED SCHEDULER
HELPS IN MANAGING COMMUNICATION
AMONG PROJECT PARTICIPANTS.
CONSTRUCTION TENDERING
SELECTION OF CONRTRACTOR
THIS ISN’T THE FINAL DECISION TO SELECT A SPECIFIC BIDDER, BUT IT HELPS TO
SORT OUT AND FOCUS ON BEST POTENTIAL BIDDERS.
EXCLUSIONS:
 CRIMINAL RECORDS, IF THE BIDDER HAS ANY. THEN THEY WOULD BE
EXCLUDED FROM THE SELECTION.
 BUSINESS FAULTS, A BIDDER WHO HAS THESE CAN CAUSE A RISK FOR THE
PROJECT. THUS, WOULD BE EXCLUDED.
CONSTRUCTION TENDERING
SELECTION OF CONRTRACTOR
REQUIREMENTS
 TECHNICAL AND PROFESSIONAL QUALIFICATIONS, EXPERIENCE AND
CAPABILITY IS THE MOST IMPORTANT WHEN IT COMES TO LARGE SIZE
PROJECTS.
 FINANCIAL AND ECONOMICAL CAPACITY, THIS CAN GUARANTEE THE
PROJECT FEASIBILITY.
CONSTRUCTION TENDERING
SELECTION OF CONRTRACTOR
AWARDING CRITERIA
AFTER SELECTING THE BEST AND LIMITING THE BIDDER NUMBERS, IT’S TIME FOR SELECTING THE
BEST OF BEST BY HAVING A DEEPER LOOK ON THE REMAINING BIDDERS, REGARDING THE
CRITERIA’S.
1. PRICE
2. HEALTH AND SAFETY
3. SUSTAINABILITY
4. RESPONSIBLE BUSINESS PRACTICE
5. COMMITMENT TO DELIVERY DATE
PROJECT RISK ASSESSMENT
No Risk consequence Likelihood
Brief
Execution
16 Price inflation of construction
materials
High Moderate
17 Late delivery of materials High Moderate
18 Insufficient or late funding High Moderate
19 Late Design changes High Moderate
20 Tight project schedule Very High High
21 Lack of coordination between
project participants
High Moderate
22 Low management and supervision of
construction
Very High Low
23 Machinery or equipment breakdown High Low
24 Insufficient amount of skilled labours High Moderate
 RISKS AT EXECUTION STAGE.
 .
PROJECT RISK ASSESSMENT
 QUALITATIVE RISK ASSESSMENT.
 SCALED FACTOR MAY BE USED.
 MODERATE OVERALL RISK.
MEASURES AGAINST DIFFERENT RISKS
no Phase Solution
16 Price inflation of construction
materials
Run a net present value estimation of the project, considering
inflation rates.
17 Late delivery of materials Include penalty clauses in contracts with the subcontractors.
18 Insufficient or late funding Set the project budget apart from and provide at early
stages of the project.
19 Late Design changes Notify the client about the changes in cost and time before
doing and change. Also, account sometime in the scheduling
to encounter any sudden change.
20 Tight project schedule Adopt an efficient project tracking program to maintain
schedule.
21 Lack of coordination between
project participants
Adopt proper software and methods for communication
between project participants.
22 Low management and supervision of
construction
Make a checklist for things that need to be checked up
regularly. Put clear standards and task for project’s
supervision.
23 Machinery or equipment breakdown Have contact with backup machine operators and owners.
And an on-call maintenance team.
24 Insufficient amount of skilled labours Having contact with backup workers in case of having
workers missing. And providing workers training program.
 RISK MITIGATION PLAN
CONSTRUCTION SAFETY MANAGEMENT
 HIGH RISE STRUCTURE BUILDING HAS HIGHER POTENTIAL SAFETY RISKS.
 SAFETY OF CONSTRUCTION SITE
1. IMPROVES PRODUCTIVITY
2. KEEPS PROJECT ON SCHEDULE.
 WEAK SAFETY PLAN
1. ACCIDENTS CAN CAUSE DELAYING AND FINANCIAL ISSUES
2. THAT CAN LEAD THE PROJECT TO CRISES AND FAILURE.
CONSTRUCTION SAFETY MANAGEMENT PROCEDURE
HAZARD ASSESSMENT ASSESS RISKS
DECIDE
PRECAUTIONS
CONSTRUCTION SAFETY RISK ASSESSMENT
 QUALITATIVE RISK ASSESSMENT.
 RISKS ARE PLACED ACCORDING TO
1. THEIR LIKELIHOOD.
2. IMPACT.
CONSTRUCTION SAFETY RISK ASSESSMENT
 NUMERIC SCALED QUALITATIVE ASSESSMENT.
 VALUES ABOVE 10 ARE PROMOTED TO RED.
 VALUES BELOW 10 ARE PROMOTED TO GREEN.
 RED RISKS = UNACCPTABLE.
 GREEN RISKS = ACCEPTABLE.
 ACCEPTING RISKS DOESN’T MEAN IGNORING
.THEM
COMPULSORY MEASURES TO BE TAKEN
AGAINST SAFETY RISKS.
 USING GUARD RAILS ON EDGES OF BUILDING AND FLOOR OPENINGS.
 USING SAFETY NETS TO PREVENT FROM FALLING FROM HEIGHTS.
 USE SCAFFOLDING WITH COVERING NETS TO AVOID FALL OF OBJECTS.
 PROVIDING ADEQUATE TRAINING AND SUPERVISION FOR WORKERS, TO PREVENT ANY MISTAKES THAT MAY RESULT FROM IGNORANT
OR IRRESPONSIBLE ACTS.
 ESTABLISHING EMERGENCY PLANNING PROCEDURES, INCLUDING FIRST AID.
 KEEP CONTROL OF SITE ACCESSIBILITY, BY MAKING SPECIFIC GUARDED AND CONTROLLED ENTRANCES AND EXITS, SO ONLY
AUTHORIZED STAFF CAN GET THROUGH THE GATES.
 PROVIDING PPE, CLOTHING AND SIGNS, BUT THEY SHALL BE USED AS LAST RESORT AFTER USING EXPLORING ALL THE HAZARD
ELIMINATION METHODS.
CONSTRUCTION SAFETY MANAGEMENT
 CONSTRUCTION SITE SAFETY PROCEDURE SIGN
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).

More Related Content

What's hot

Optimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabsOptimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabs
Md. Shahadat Hossain
 
Matching base shear in Etabs 2016
Matching base shear in Etabs 2016Matching base shear in Etabs 2016
Matching base shear in Etabs 2016
Vamsi krishna reddy
 
Analysis and design of commercial building
Analysis and design of commercial buildingAnalysis and design of commercial building
Analysis and design of commercial building
Satrudhan11240
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ila vamsi krishna
 
Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...
Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...
Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...
IJSRD
 
Beam design
Beam designBeam design
Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000
Vikas Mehta
 
Etabs multistory-steel
Etabs multistory-steelEtabs multistory-steel
Etabs multistory-steel
Md. Shahadat Hossain
 
Lecture 1 design loads
Lecture 1   design loadsLecture 1   design loads
Lecture 1 design loads
Morsaleen Chowdhury
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
Krishnagnr
 
Design of simple beam using staad pro
Design of simple beam using staad proDesign of simple beam using staad pro
Design of simple beam using staad pro
SHAMJITH KM
 
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 SoftwareANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 Software
Abhinav Verma
 
Two way slab
Two way slabTwo way slab
Two way slab
Priodeep Chowdhury
 
Etabs example-rc building seismic load response-
Etabs example-rc building seismic load  response-Etabs example-rc building seismic load  response-
Etabs example-rc building seismic load response-
Bhaskar Alapati
 
Etabs concrete-design
Etabs concrete-designEtabs concrete-design
Etabs concrete-designmamilli
 
Project
ProjectProject
Project
tp jayamohan
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
=> No nEEd FoH WoRk , Um gOod cOnsUMer oF PArentx MOnEy
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT
jolynnTJL
 
Design and Analysis of Building using Etabs
Design and Analysis of Building using EtabsDesign and Analysis of Building using Etabs
Design and Analysis of Building using Etabs
vishal shinde
 

What's hot (20)

Optimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabsOptimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabs
 
Matching base shear in Etabs 2016
Matching base shear in Etabs 2016Matching base shear in Etabs 2016
Matching base shear in Etabs 2016
 
Analysis and design of commercial building
Analysis and design of commercial buildingAnalysis and design of commercial building
Analysis and design of commercial building
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
 
Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...
Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...
Study on Effect of Wind Load and Earthquake Load on Multi-storey RC Framed Bu...
 
Beam design
Beam designBeam design
Beam design
 
Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000
 
Etabs multistory-steel
Etabs multistory-steelEtabs multistory-steel
Etabs multistory-steel
 
Lecture 1 design loads
Lecture 1   design loadsLecture 1   design loads
Lecture 1 design loads
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
 
Design of simple beam using staad pro
Design of simple beam using staad proDesign of simple beam using staad pro
Design of simple beam using staad pro
 
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 SoftwareANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 Software
 
6. safe users-guide
6.  safe users-guide6.  safe users-guide
6. safe users-guide
 
Two way slab
Two way slabTwo way slab
Two way slab
 
Etabs example-rc building seismic load response-
Etabs example-rc building seismic load  response-Etabs example-rc building seismic load  response-
Etabs example-rc building seismic load response-
 
Etabs concrete-design
Etabs concrete-designEtabs concrete-design
Etabs concrete-design
 
Project
ProjectProject
Project
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT
 
Design and Analysis of Building using Etabs
Design and Analysis of Building using EtabsDesign and Analysis of Building using Etabs
Design and Analysis of Building using Etabs
 

Viewers also liked

ETABS Modelling
ETABS ModellingETABS Modelling
Book for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABSBook for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABS
Yousuf Dinar
 
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul LeslieModelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Rahul Leslie
 
CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2
CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2
CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2
Eur Ing Valentinos Neophytou BEng (Hons), MSc, CEng MICE
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
gopichand's
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
Ali Meer
 
Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)
Md. Shahadat Hossain
 
Rc bldg. modeling & analysis
Rc bldg. modeling & analysisRc bldg. modeling & analysis
Rc bldg. modeling & analysis
Ramil Artates
 
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8 ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
Eur Ing Valentinos Neophytou BEng (Hons), MSc, CEng MICE
 
Membrane - Plate - Shell
Membrane - Plate - ShellMembrane - Plate - Shell
Membrane - Plate - Shellneikrof
 
Multi storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial buildingMulti storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial building
Razes Dhakal
 
Analysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concreteAnalysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concrete
Surat Construction PVT LTD
 
Analysis and design of 15 storey office and
Analysis and design of 15 storey office andAnalysis and design of 15 storey office and
Analysis and design of 15 storey office and
Masroor Alam
 
Desain dinding geser beton bertulang menggunakan software ETABS
Desain dinding geser beton bertulang menggunakan software ETABSDesain dinding geser beton bertulang menggunakan software ETABS
Desain dinding geser beton bertulang menggunakan software ETABS
Afret Nobel
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
Rahul
 
Building Technology Project (Improving thermal, lighting, and acoustic aspect...
Building Technology Project (Improving thermal, lighting, and acoustic aspect...Building Technology Project (Improving thermal, lighting, and acoustic aspect...
Building Technology Project (Improving thermal, lighting, and acoustic aspect...
khaledalshami93
 
Etabs
EtabsEtabs
Etabs
hossain470
 
Etabs modeling - Design of slab according to EC2
Etabs modeling  - Design of slab according to EC2Etabs modeling  - Design of slab according to EC2
Etabs modeling - Design of slab according to EC2
Eur Ing Valentinos Neophytou BEng (Hons), MSc, CEng MICE
 
The Pushover Analysis from basics - Rahul Leslie
The Pushover Analysis from basics - Rahul LeslieThe Pushover Analysis from basics - Rahul Leslie
The Pushover Analysis from basics - Rahul Leslie
Rahul Leslie
 

Viewers also liked (20)

ETABS Modelling
ETABS ModellingETABS Modelling
ETABS Modelling
 
Book for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABSBook for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABS
 
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul LeslieModelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
Modelling Building Frame with STAAD.Pro & ETABS - Rahul Leslie
 
CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2
CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2
CSI ETABS & SAFE MANUAL: Slab Analysis and Design to EC2
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
 
Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)
 
Rc bldg. modeling & analysis
Rc bldg. modeling & analysisRc bldg. modeling & analysis
Rc bldg. modeling & analysis
 
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8 ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
 
Membrane - Plate - Shell
Membrane - Plate - ShellMembrane - Plate - Shell
Membrane - Plate - Shell
 
Multi storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial buildingMulti storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial building
 
Analysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concreteAnalysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concrete
 
Analysis and design of 15 storey office and
Analysis and design of 15 storey office andAnalysis and design of 15 storey office and
Analysis and design of 15 storey office and
 
Desain dinding geser beton bertulang menggunakan software ETABS
Desain dinding geser beton bertulang menggunakan software ETABSDesain dinding geser beton bertulang menggunakan software ETABS
Desain dinding geser beton bertulang menggunakan software ETABS
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
 
Building Technology Project (Improving thermal, lighting, and acoustic aspect...
Building Technology Project (Improving thermal, lighting, and acoustic aspect...Building Technology Project (Improving thermal, lighting, and acoustic aspect...
Building Technology Project (Improving thermal, lighting, and acoustic aspect...
 
Etabs
EtabsEtabs
Etabs
 
DETAILED CV - Aug 16 v3
DETAILED CV - Aug 16 v3DETAILED CV - Aug 16 v3
DETAILED CV - Aug 16 v3
 
Etabs modeling - Design of slab according to EC2
Etabs modeling  - Design of slab according to EC2Etabs modeling  - Design of slab according to EC2
Etabs modeling - Design of slab according to EC2
 
The Pushover Analysis from basics - Rahul Leslie
The Pushover Analysis from basics - Rahul LeslieThe Pushover Analysis from basics - Rahul Leslie
The Pushover Analysis from basics - Rahul Leslie
 

Similar to Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).

Connecting Bridge
Connecting BridgeConnecting Bridge
Connecting Bridge
MahfuzurRahman939513
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadgopichand's
 
DESIGN OF NACA SERIES 2412
DESIGN OF NACA SERIES 2412DESIGN OF NACA SERIES 2412
DESIGN OF NACA SERIES 2412
RUCHITMALIK1
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESarnath R
 
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProComputer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
IRJET Journal
 
finalprojectreportg2-141218075116-conversion-gate01 (1).pdf
finalprojectreportg2-141218075116-conversion-gate01 (1).pdffinalprojectreportg2-141218075116-conversion-gate01 (1).pdf
finalprojectreportg2-141218075116-conversion-gate01 (1).pdf
AbdurRazzak187410
 
FYP Structure.pdf
FYP Structure.pdfFYP Structure.pdf
FYP Structure.pdf
Sushrut Gautam
 
Fianl Year Project.pptx
Fianl Year Project.pptxFianl Year Project.pptx
Fianl Year Project.pptx
AashishMaharjan11
 
IRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump House
IRJET Journal
 
strip-foundation-design-calcualtion.docx
strip-foundation-design-calcualtion.docxstrip-foundation-design-calcualtion.docx
strip-foundation-design-calcualtion.docx
VICTOR A. KIPLAGAT
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
Hemant Srivastava
 
MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)sufiyan shaikh
 
Passive Cooling Design Feature for Energy Efficient in PERI Auditorium
Passive Cooling Design Feature for Energy Efficient in PERI AuditoriumPassive Cooling Design Feature for Energy Efficient in PERI Auditorium
Passive Cooling Design Feature for Energy Efficient in PERI Auditorium
IRJET Journal
 
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODECOMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
IRJET Journal
 
Finite Element Analysis of Skirt to Dished junction in a Pressure Vessel
Finite Element Analysis of Skirt to Dished junction in a Pressure VesselFinite Element Analysis of Skirt to Dished junction in a Pressure Vessel
Finite Element Analysis of Skirt to Dished junction in a Pressure Vessel
IJMER
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
IRJET Journal
 
Session 5 design of rcc structural elements PROF YADUNANDAN
Session 5 design of rcc structural elements  PROF YADUNANDANSession 5 design of rcc structural elements  PROF YADUNANDAN
Session 5 design of rcc structural elements PROF YADUNANDAN
Ajit Sabnis
 
DESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDAN
DESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDANDESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDAN
DESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDAN
Ajit Sabnis
 
CFD Analysis of Symmetrical Tangential Inlet Cyclone Separator
CFD Analysis of Symmetrical Tangential Inlet Cyclone SeparatorCFD Analysis of Symmetrical Tangential Inlet Cyclone Separator
CFD Analysis of Symmetrical Tangential Inlet Cyclone Separator
IRJET Journal
 
Design of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) StructureDesign of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) Structure
IRJET Journal
 

Similar to Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS). (20)

Connecting Bridge
Connecting BridgeConnecting Bridge
Connecting Bridge
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
DESIGN OF NACA SERIES 2412
DESIGN OF NACA SERIES 2412DESIGN OF NACA SERIES 2412
DESIGN OF NACA SERIES 2412
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAE
 
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProComputer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
 
finalprojectreportg2-141218075116-conversion-gate01 (1).pdf
finalprojectreportg2-141218075116-conversion-gate01 (1).pdffinalprojectreportg2-141218075116-conversion-gate01 (1).pdf
finalprojectreportg2-141218075116-conversion-gate01 (1).pdf
 
FYP Structure.pdf
FYP Structure.pdfFYP Structure.pdf
FYP Structure.pdf
 
Fianl Year Project.pptx
Fianl Year Project.pptxFianl Year Project.pptx
Fianl Year Project.pptx
 
IRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump House
 
strip-foundation-design-calcualtion.docx
strip-foundation-design-calcualtion.docxstrip-foundation-design-calcualtion.docx
strip-foundation-design-calcualtion.docx
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
 
MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)
 
Passive Cooling Design Feature for Energy Efficient in PERI Auditorium
Passive Cooling Design Feature for Energy Efficient in PERI AuditoriumPassive Cooling Design Feature for Energy Efficient in PERI Auditorium
Passive Cooling Design Feature for Energy Efficient in PERI Auditorium
 
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODECOMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
 
Finite Element Analysis of Skirt to Dished junction in a Pressure Vessel
Finite Element Analysis of Skirt to Dished junction in a Pressure VesselFinite Element Analysis of Skirt to Dished junction in a Pressure Vessel
Finite Element Analysis of Skirt to Dished junction in a Pressure Vessel
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
 
Session 5 design of rcc structural elements PROF YADUNANDAN
Session 5 design of rcc structural elements  PROF YADUNANDANSession 5 design of rcc structural elements  PROF YADUNANDAN
Session 5 design of rcc structural elements PROF YADUNANDAN
 
DESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDAN
DESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDANDESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDAN
DESIGN OF RCC ELEMENTS SESSION 5 PROF. YADUNANDAN
 
CFD Analysis of Symmetrical Tangential Inlet Cyclone Separator
CFD Analysis of Symmetrical Tangential Inlet Cyclone SeparatorCFD Analysis of Symmetrical Tangential Inlet Cyclone Separator
CFD Analysis of Symmetrical Tangential Inlet Cyclone Separator
 
Design of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) StructureDesign of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) Structure
 

Recently uploaded

H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).

  • 1. DESIGN AND ANALYSIS OF MULTI- TOWER STRUCTURE USING ETABS BY KHALED AL SHAMI
  • 2. INTRODUCTION  BASEMENT.  3 PARKING FLOORS.  2 FLOOR HEALTH CLUB.  13 FLOOR HOTEL TOWER (LEFT).  33 FLOOR OFFICE TOWER (RIGHT).
  • 3. LOCATION  AT THE HEART OF AMMAN IN MECCA STREET.  SURROUNDING AREA IS MOSTLY OFFICE TOWERS.  POSITIONED NEAR AN INTERCHANGE.  VERY HIGH ACCESSIBILITY.
  • 4.
  • 5. WHY ETABS AND SAFE ?  DEVELOPED BY CSI (CONSTRUCTION SPECIFICATION INSTITUTE).  THEY WORK COMPATIBLY.  2D/3D MODELLING.  LINEAR/NON-LINEAR ANALYSIS.  SIMULATION OF EARTHQUAKE AND WIND LOAD ON STRUCTURE.  FRIENDLY INTERFACE, EVEN FOR DESIGN OF COMPLICATED STRUCTURES.
  • 6. DEAD LOAD CALCULATION LOAD NAME VALUE UNIT SOURCE PARTITION 2 kN/m2 UBC 97 code TILING (MARBLE) 0.4 kN/m2 2cm * 20 kN/m3 MORTAR (LIGHTWEIGHT CONCRETE) 0.16 kN/m2 2cm * 8 kN/m3 MECHANICAL AND ELECTRICAL EQUIPMENT 0.2 kN/m2 UBC 97 code, table 16-B FALSE CEILING 0.1 kN/m2 UBC 97 code, table 16-B FIRE SPRINKLERS 1.11 kN/m2 UBC 97 code, table 16-B TOTAL 3.97 Take as 4
  • 7. OTHER LOADS FAÇADE LOAD  APPLIED ON THE PERIMETER OF THE STRUCTURE  HAS VALUE OF 1KN/M2. (ASCE7-5 CODE, SECTION 9.8). SNOW LOAD  MINIMUM SNOW LOADS (0.240 KN/M2) ARE APPLIED.
  • 8. LIVE LOAD REDUCTION  ACCORDING TO UBC 97 PROVISIONS.  TRIBUTARY AREA METHOD.  MINIMUM FACTOR FOR MULTIPLE STORIES IS 0.4.
  • 9. LIVE LOAD (ACCORDING TO IBC 2009) AREA LOAD UNIT SOURCE GROUND FLOOR 4 kN/m2 IBC 2009 Code PARKING FLOORS (1-3) 4 kN/m2 IBC 2009 Code HEALTH CLUB (1-2) 4 kN/m2 IBC 2009 Code LEFT TOWER (13 FLOORS HOTEL) 3.2 kN/m2 IBC 2009 Code RIGHT TOWER (33 FLOORS OFFICE AREA) 3.6 kN/m2 IBC 2009 Code.
  • 11. WIND LOAD (ASCE 7-05) TYPE ANNOTATION VALUE UNIT SOURCE WIND SPEED - 78 MpH Amman municipality DIRECTIONALITY FACTOR Kd 0.85 - ASCE 7-05 - C6.5.4.4 IMPORTANCE FACTOR I 1 - ASCE 7-05 - C6.5.5 EXPOSURE TYPE - B - ASCE 7-05 - C6.5.6 TOPOGRAPHICAL FACTOR Kzt 1 - ASCE 7-05 - C6.5.7 GUST FACTOR G 0.85 - ASCE 7-05 - C6.5.8
  • 13. EARTHQUAKE LOADS (UBC 97)  TWO LOAD CASES (Qx, Qy). TYPE ANNOTATION VALUE SOURCE IMPORTANCE FACTOR I 1 TABLE 16-K UBC CODE OVER- STRENGTH FACTOR R 4.5 TABLE 16-N UBC CODE TIME PERIOD CT 0.02 PROGRAM CALCULATED SOIL PROFILE - SC TABLE 16-J UBC CODE SEISMIC ZONE FACTOR Z 0.20 TABLE 16-I UBC CODE
  • 14. LOAD COMBINATION  TWO MANUALLY GENERATED COMBINATIONS.  SHEAR WALL COMBINATIONS AND CONCRETE FRAME COMBINATION ARE AUTOMATICALLY GENERATED. Name Load Scale Factor Load Scale Factor Type Service Load Dead 1.0 Live 1.0 Linear Ultimate Load Dead 1.4 Live 1.6 Linear
  • 15. MODELLING  1. DEFINE 1. MATERIALS (CONCRETE, STEEL). 2. FRAME SECTIONS (COLUMNS, BEAMS) 3. SHELLS (SLABS, WALLS) 4. OPENINGS IF ANY EXISTS. 5. DEFINE SECTION MODIFIRES.  2. DRAW 1. COLUMNS 2. BEAMS 3. ROOFS 4. WALLS 5. OPENINGS
  • 16. MODELLING  3. DEFINE 1. EARTHQUAKE LOAD (EQX, EQY). 2. WIND LOAD (WX, WY). 3. RESPONSE SPECTRUM FUNCTION (SPEC-UBC). 4. RESPONSE SPECTRUM LOAD CASES (SPEC-X, SPEC-Y). 5. MASS SOURCE. 6. P-DELTA CASE. 7. MODAL CASE (EIGEN).  4. ASSIGN 1. AREA LOADS (ON SLABS). 2. LINE LOADS (ON BEAMS). 3. DIAPHRAGM 4. SUPPORTS (FIXED/PINNED). 5. MOMENT RELEASES FOR BEAMS. 6. MESHING (FOR WALLS AND SLABS). 7. PIER AND SPANDREL LABELS. 8. LIVE LOAD REDUCTION FACTOR. 9. SPECIAL SESIMIC EFFECTS.  RUN
  • 20. CHECKING BEAMS FOR ANY LOAD CASE OR COMBO.  VIEW MOMENT.  VIEW SHEAR.  VIEW DEFLECTION.
  • 22. CHECKING OVER-ALL DEFLECTION  FOR UNFACTORED WIND: H 500 = 13127 500 = 26.26 𝑐𝑚  FACTORED SEISMIC LOAD: 0.02H = 0.02 * 13127 = 262.54 CM (ACCORDING TO UBC 97 CODE). OR: 0.005H = 0.0065 * 13127 = 85.32 CM (ACCORDING TO JAPANESE CODE). Load Case Translation (cm) Translation (cm) Comparison (cm) X-Dir Y-Dir X-Dir Y-Dir Qx 2.66 0.01 40.04 -0.86 40.04 < 262.54 safe Qy -0.46 3.37 -2.78 68.16 68.16 < 262.54 safe Translation (mm) Translation (mm) Comparison (mm) Wx 1.1 11.2 8.3 108.3 108.3 < 262.6 safe Wy 4.6 14.9 37.1 144.8 144.8 < 262.6 safe
  • 23. INTER-STORY DRIFT CHECK  Drift is the difference in horizontal deflection between the top and bottom of any storey.  The story drift shall not exceed 2.5% of the story height for structures with fundamental period less than 0.7 second, for it to be considered safe.  Allowable story drift = 2.5% * 3300mm = 82.5mm . Load Case Maximum Drift (mm) Comparison Safety Qx 4.185 4.185 < 82.5 Safe Qy 6.538 6.538 < 82.5 Safe
  • 24. MODAL RESPONSE SPECTRA (STORY RESPONSE)  STORY SHAERS  LOAD CASE : RESPONSE SPECTRUM
  • 25. MODAL RESPONSE SPECTRA (STORY RESPONSE)  MAXIMUM STORY DISPLACEMENT  MODE 1.
  • 26. MODAL RESPONSE SPECTRA (STORY RESPONSE)  MAXIMUM STORY DISPLACEMENT  MODE 25.
  • 27. WIND VELOCITY PROFILE  CALCULATED WIND VELOCITY PROFILE.
  • 29. SHEAR WALL DESIGN  Longitudinal reinforcement.  Shear reinforcement.
  • 30. SHAER WALL LONGITUDINAL REINFORCEMENT  USED CODE ACI318-08.  REINFORCEMENT CALCULATED BY ETABS.  DEMAND/CAPACITY RATIO = 1 (USING 95% OF THE SECTION AREA) THUS (5% FOR SAFETY). Story Pier ID Location Required Reinf % As (Cm2) Reinforcement 32ND P1 Top 0.62 173.6 ⌀ 22 @ 20 C/C 32ND P1 Bottom 0.58 162.4 ⌀ 22 @ 20 C/C 31ST P1 Top 0.58 162.4 ⌀ 22 @ 20 C/C 31ST P1 Bottom 0.48 134.4 ⌀ 20 @ 20 C/C 30TH P1 Top 0.49 137.2 ⌀ 20 @ 20 C/C 30TH P1 Bottom 0.45 126 ⌀ 20 @ 20 C/C
  • 31. SHEAR WALL HORIZONTAL REINFORCEMENT  SPECIFY NUMBER OF BARS IN ONE METER. Shear reinforcement (cm2/m) Calculation Selected Reinforcement 17.5 17.5/7 = 2.5 take ⌀18 ⌀18 @ 15cm c/c 31.45 31.45/7 = 4.49 take ⌀25 ⌀25 @ 15cm c/c
  • 32. SHEAR WALL RENDERING & DETAILING
  • 33. SHAERWALL DETAILING SHEAR WALL DETAILING.  REINFORCEMENT.  SPACING.
  • 35. BEAM DESIGN (LONGITUDINAL REINFORCEMENT) ASSUME A BEAM SECTION WITH  4 BARS AT TOP.  4 BARS AT BOTTOM. AS (CM2) BAR SIZE UNIT REINFORCEMENT 10 10 4 = 2.5 CM2 4 ⌀ 18 5 5 4 = 1.25 CM2 4 ⌀ 14 12 12 4 = 3.00 CM2 4 ⌀ 20 7 7 4 = 1.75 CM2 4 ⌀ 16 4 4 4 = 1.00 CM2 4 ⌀ 12 8 8 4 = 2.00 CM2 4 ⌀ 16
  • 38. BEAM SHEAR REINFORCEMENT  ASSUME DIAMETER OF STIRRUPS TO BE 10MM.  𝑆 = 𝐴𝑠∗𝑁𝑜. 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝 𝑙𝑒𝑔𝑠 𝑣𝑎𝑙𝑢𝑒 𝑔𝑖𝑣𝑒𝑛 𝑖𝑛 𝐸𝑇𝐴𝐵𝑆  𝑆 = 79∗2 7.82 = 20.20 𝑇𝐴𝐾𝐸 𝐴𝑆 20𝐶𝑀  𝑆 = 79∗2 4.72 = 33.47 𝑇𝐴𝐾𝐸 𝐴𝑆 30𝐶𝑀
  • 39. DIAPHRAGMS  EACH SLAB HAS ITS OWN DIAPHRAGM.  DIAPHRAGMS ARE ALL RIGID.  RIGID DIAPHRAGMS HAVE INFINITE IN-PLANE STIFFNESS PROPERTIES.  THEY DON’T EXHIBIT THE ACTUAL IN-PLANE STIFFNESS PROPERTIES AND BEHAVIOUR.  THE ADVANTAGE OF THIS METHOD IS DECREASING THE COMPUTATIONAL TIME.
  • 40. SLAB MODELLING 3DIAPHRAGMS, WHY ?  FOR COLLAPSE MECHANISM.  FOR EARTHQUAKE JOINT.
  • 42. WHY POST TENSION SLAB ?  TO HELP REDUCING SLAB THICKNESS  SAVE ON REBAR STEEL.  LESS TIME CONSUMING.  NO NEED FOR DROP BEAMS.
  • 43. POST TENSION SLAB MODELLING  SLAB MODEL ON SAFE 2014.
  • 44. POST TENSION SLAB DESIGN  TENDON LAYOUT.
  • 45. POST TENSION SLAB DESIGN SLAB DESIGN OUTPUT  TENDON PROFILES.  AMOUNT OF PULLING FORCE FOR EACH TENDON.  NEEDED ELONGATION VALUES FOR EACH TENDON.  DEAD ENDS AND LIVE ENDS.  BILL OF QUANTITY (BOQ) FOR SLAB.
  • 46. POST TENSION SLAB DESIGN  BILL OF QUANTITY BY SAFE 2014.
  • 47. POST TENSION SLAB DESIGN  REQUIRED REINFORCMENT.  TOP REBAR PLAN.
  • 49. COMMUNICATION BETWEEN PROJECT PARTICIPANTS  MANY CONSULTANTS.  A LOT OF WORKERS.  DIFFERENT COMPANIES. ??? HOW TO ARRANGE COMMUNICATION ???  PROLOG IS A WEB BASED SCHEDULER HELPS IN MANAGING COMMUNICATION AMONG PROJECT PARTICIPANTS.
  • 50. CONSTRUCTION TENDERING SELECTION OF CONRTRACTOR THIS ISN’T THE FINAL DECISION TO SELECT A SPECIFIC BIDDER, BUT IT HELPS TO SORT OUT AND FOCUS ON BEST POTENTIAL BIDDERS. EXCLUSIONS:  CRIMINAL RECORDS, IF THE BIDDER HAS ANY. THEN THEY WOULD BE EXCLUDED FROM THE SELECTION.  BUSINESS FAULTS, A BIDDER WHO HAS THESE CAN CAUSE A RISK FOR THE PROJECT. THUS, WOULD BE EXCLUDED.
  • 51. CONSTRUCTION TENDERING SELECTION OF CONRTRACTOR REQUIREMENTS  TECHNICAL AND PROFESSIONAL QUALIFICATIONS, EXPERIENCE AND CAPABILITY IS THE MOST IMPORTANT WHEN IT COMES TO LARGE SIZE PROJECTS.  FINANCIAL AND ECONOMICAL CAPACITY, THIS CAN GUARANTEE THE PROJECT FEASIBILITY.
  • 52. CONSTRUCTION TENDERING SELECTION OF CONRTRACTOR AWARDING CRITERIA AFTER SELECTING THE BEST AND LIMITING THE BIDDER NUMBERS, IT’S TIME FOR SELECTING THE BEST OF BEST BY HAVING A DEEPER LOOK ON THE REMAINING BIDDERS, REGARDING THE CRITERIA’S. 1. PRICE 2. HEALTH AND SAFETY 3. SUSTAINABILITY 4. RESPONSIBLE BUSINESS PRACTICE 5. COMMITMENT TO DELIVERY DATE
  • 53. PROJECT RISK ASSESSMENT No Risk consequence Likelihood Brief Execution 16 Price inflation of construction materials High Moderate 17 Late delivery of materials High Moderate 18 Insufficient or late funding High Moderate 19 Late Design changes High Moderate 20 Tight project schedule Very High High 21 Lack of coordination between project participants High Moderate 22 Low management and supervision of construction Very High Low 23 Machinery or equipment breakdown High Low 24 Insufficient amount of skilled labours High Moderate  RISKS AT EXECUTION STAGE.
  • 54.  . PROJECT RISK ASSESSMENT  QUALITATIVE RISK ASSESSMENT.  SCALED FACTOR MAY BE USED.  MODERATE OVERALL RISK.
  • 55. MEASURES AGAINST DIFFERENT RISKS no Phase Solution 16 Price inflation of construction materials Run a net present value estimation of the project, considering inflation rates. 17 Late delivery of materials Include penalty clauses in contracts with the subcontractors. 18 Insufficient or late funding Set the project budget apart from and provide at early stages of the project. 19 Late Design changes Notify the client about the changes in cost and time before doing and change. Also, account sometime in the scheduling to encounter any sudden change. 20 Tight project schedule Adopt an efficient project tracking program to maintain schedule. 21 Lack of coordination between project participants Adopt proper software and methods for communication between project participants. 22 Low management and supervision of construction Make a checklist for things that need to be checked up regularly. Put clear standards and task for project’s supervision. 23 Machinery or equipment breakdown Have contact with backup machine operators and owners. And an on-call maintenance team. 24 Insufficient amount of skilled labours Having contact with backup workers in case of having workers missing. And providing workers training program.  RISK MITIGATION PLAN
  • 56. CONSTRUCTION SAFETY MANAGEMENT  HIGH RISE STRUCTURE BUILDING HAS HIGHER POTENTIAL SAFETY RISKS.  SAFETY OF CONSTRUCTION SITE 1. IMPROVES PRODUCTIVITY 2. KEEPS PROJECT ON SCHEDULE.  WEAK SAFETY PLAN 1. ACCIDENTS CAN CAUSE DELAYING AND FINANCIAL ISSUES 2. THAT CAN LEAD THE PROJECT TO CRISES AND FAILURE.
  • 57. CONSTRUCTION SAFETY MANAGEMENT PROCEDURE HAZARD ASSESSMENT ASSESS RISKS DECIDE PRECAUTIONS
  • 58. CONSTRUCTION SAFETY RISK ASSESSMENT  QUALITATIVE RISK ASSESSMENT.  RISKS ARE PLACED ACCORDING TO 1. THEIR LIKELIHOOD. 2. IMPACT.
  • 59. CONSTRUCTION SAFETY RISK ASSESSMENT  NUMERIC SCALED QUALITATIVE ASSESSMENT.  VALUES ABOVE 10 ARE PROMOTED TO RED.  VALUES BELOW 10 ARE PROMOTED TO GREEN.  RED RISKS = UNACCPTABLE.  GREEN RISKS = ACCEPTABLE.  ACCEPTING RISKS DOESN’T MEAN IGNORING .THEM
  • 60. COMPULSORY MEASURES TO BE TAKEN AGAINST SAFETY RISKS.  USING GUARD RAILS ON EDGES OF BUILDING AND FLOOR OPENINGS.  USING SAFETY NETS TO PREVENT FROM FALLING FROM HEIGHTS.  USE SCAFFOLDING WITH COVERING NETS TO AVOID FALL OF OBJECTS.  PROVIDING ADEQUATE TRAINING AND SUPERVISION FOR WORKERS, TO PREVENT ANY MISTAKES THAT MAY RESULT FROM IGNORANT OR IRRESPONSIBLE ACTS.  ESTABLISHING EMERGENCY PLANNING PROCEDURES, INCLUDING FIRST AID.  KEEP CONTROL OF SITE ACCESSIBILITY, BY MAKING SPECIFIC GUARDED AND CONTROLLED ENTRANCES AND EXITS, SO ONLY AUTHORIZED STAFF CAN GET THROUGH THE GATES.  PROVIDING PPE, CLOTHING AND SIGNS, BUT THEY SHALL BE USED AS LAST RESORT AFTER USING EXPLORING ALL THE HAZARD ELIMINATION METHODS.
  • 61. CONSTRUCTION SAFETY MANAGEMENT  CONSTRUCTION SITE SAFETY PROCEDURE SIGN