SlideShare a Scribd company logo
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Page
The factory
7
Supplier park:
• centre of train manufacturing excellence
• 78ha site
• R1 billion investment
• maximum capacity end 2019:
• two cars per day
• 1 500 workers employed on site
Training centre:
• 4 000m2
• to train 19 500 people
Testing centre:
• static test buildings
• 1.2 km test track
Manufacturing buildings
• 31 500m2
2 June 2016Moving forward with Trencon and Black Jill JV
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Page
Key construction milestones
9
May
Building construction
starts
October
Training Centre
buildings ready to be
equipped
March
First manufacturing
building completed
September
Construction ends
Second Quarter
Train production
starts
2016 2017
2 June 2016Moving forward with Trencon and Black Jill JV
Page
Construction milestones
Overall construction programme will last approximately 18 months
2 June 2016Moving forward with Trencon and Black Jill JV 10
Note: Main construction Milestones for P0+1+2: black dot =complete, orange dot = planned.
Work package 2016 2017
Dec
2015
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Jan
2018
Plant rescue, clearance, earthworks, infrastructure
RS site buildings
Rail infrastructure
Electrical reticulation and equipment
Electrical reticulation and equipment (traction)
Mechanical (HVAC, gas, air, water)
Cranes
Transborder and turn table
Non-statutory signage (Gibela visual identity)
Bulk electrical supply
Bulk roads and rails
Bulk potable water, sewerage pipelines
Bulk stormwater
Start of construction
Plant removal complete
Start of building package
CBS Portion 1 Beneficial occupation
M07 Beneficial occupation
Permanent power supply
Progress: 67%
•
•
•
•
•
•
Page
Special thanks
2 June 2016Moving forward with Trencon and Black Jill JV 14
To the Executive Mayor of Ekurhuleni
and the EMM Executive Committee
and officials for their ongoing
support of the project
“This project means that Ekurhuleni is no longer
the historic leader in manufacturing – it affirms us
as the future leader and puts us at the cutting
edge of technology.”
Gibela Trencon Presentation - 02june2016

More Related Content

What's hot

Project Management Presentation Slides
Project Management Presentation SlidesProject Management Presentation Slides
Project Management Presentation SlidesArissa Loh
 
Project status
Project statusProject status
Project statusAlexlytto
 
Topic of architectural_design-december-2015
Topic of architectural_design-december-2015Topic of architectural_design-december-2015
Topic of architectural_design-december-2015saradhi333
 
Rlsにおけるプロダクト プロジェクトマネジメント
Rlsにおけるプロダクト プロジェクトマネジメントRlsにおけるプロダクト プロジェクトマネジメント
Rlsにおけるプロダクト プロジェクトマネジメントRecruit Lifestyle Co., Ltd.
 
50t_Horizontal_Lay_System
50t_Horizontal_Lay_System50t_Horizontal_Lay_System
50t_Horizontal_Lay_SystemMarzena Haddow
 
International Construction Quality Inspector
International Construction Quality InspectorInternational Construction Quality Inspector
International Construction Quality InspectorJOSE CASAS BUEY
 
Figaf pi auto migration 20191024 webinar
Figaf pi auto migration 20191024 webinarFigaf pi auto migration 20191024 webinar
Figaf pi auto migration 20191024 webinarDaniel Graversen
 
Halil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil EngineeringHalil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil EngineeringHalil Özkan
 

What's hot (16)

Project Management Presentation Slides
Project Management Presentation SlidesProject Management Presentation Slides
Project Management Presentation Slides
 
Project status
Project statusProject status
Project status
 
Topic of architectural_design-december-2015
Topic of architectural_design-december-2015Topic of architectural_design-december-2015
Topic of architectural_design-december-2015
 
Resume
ResumeResume
Resume
 
Rlsにおけるプロダクト プロジェクトマネジメント
Rlsにおけるプロダクト プロジェクトマネジメントRlsにおけるプロダクト プロジェクトマネジメント
Rlsにおけるプロダクト プロジェクトマネジメント
 
wadhwa Briefing & Achievement
wadhwa Briefing & Achievementwadhwa Briefing & Achievement
wadhwa Briefing & Achievement
 
50t_Horizontal_Lay_System
50t_Horizontal_Lay_System50t_Horizontal_Lay_System
50t_Horizontal_Lay_System
 
Scrum transfer
Scrum transferScrum transfer
Scrum transfer
 
civil designer
civil designercivil designer
civil designer
 
Slide9 mp psht6of6
Slide9 mp psht6of6Slide9 mp psht6of6
Slide9 mp psht6of6
 
International Construction Quality Inspector
International Construction Quality InspectorInternational Construction Quality Inspector
International Construction Quality Inspector
 
Figaf pi auto migration 20191024 webinar
Figaf pi auto migration 20191024 webinarFigaf pi auto migration 20191024 webinar
Figaf pi auto migration 20191024 webinar
 
Halil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil EngineeringHalil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil Engineering
 
Case Study SADC
Case Study SADCCase Study SADC
Case Study SADC
 
6056996 003
6056996 0036056996 003
6056996 003
 
J0017870
J0017870J0017870
J0017870
 

Similar to Gibela Trencon Presentation - 02june2016

Birmingham New Street Station - What does the client need from the architect?...
Birmingham New Street Station - What does the client need from the architect?...Birmingham New Street Station - What does the client need from the architect?...
Birmingham New Street Station - What does the client need from the architect?...SIG Design and Technology
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.vragabata
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
VW Project Presentation
VW Project PresentationVW Project Presentation
VW Project PresentationShreyas Gupta
 
Concrete Towers - a business case for sustained investment_Rev 5
Concrete Towers - a business case for sustained investment_Rev 5Concrete Towers - a business case for sustained investment_Rev 5
Concrete Towers - a business case for sustained investment_Rev 5Santie Gouws
 
mohamed_mahmoud_atia - Planning & Cost Control Engineer
mohamed_mahmoud_atia - Planning & Cost Control Engineermohamed_mahmoud_atia - Planning & Cost Control Engineer
mohamed_mahmoud_atia - Planning & Cost Control Engineermohamed atia
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and faAl-Amin Ahmed Nabin
 
AEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 FinalistsAEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 FinalistsAutodesk AEC
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
 
CNG station construction project report.
CNG station construction project report.CNG station construction project report.
CNG station construction project report.Hagi Sahib
 
HH-- Leader onshore, explorer offshore
HH-- Leader onshore, explorer offshoreHH-- Leader onshore, explorer offshore
HH-- Leader onshore, explorer offshoreWang Steven
 
Where Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterWhere Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterNSW Environment and Planning
 
GRUG 3 October 2010 opening presentation 20101003
GRUG 3 October 2010 opening presentation 20101003GRUG 3 October 2010 opening presentation 20101003
GRUG 3 October 2010 opening presentation 20101003Glasgow Revit User Group
 
Company Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressed
Company Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressedCompany Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressed
Company Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressedEdy PT.Alexis Cipta Furnitama
 
EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...
EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...
EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...Behzad Katirachi
 
Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16waqar ahmed
 
EPCC: at the heart of data-driven innovation for business
EPCC: at the heart of data-driven innovation for businessEPCC: at the heart of data-driven innovation for business
EPCC: at the heart of data-driven innovation for businessEPCC, University of Edinburgh
 

Similar to Gibela Trencon Presentation - 02june2016 (20)

Birmingham New Street Station - What does the client need from the architect?...
Birmingham New Street Station - What does the client need from the architect?...Birmingham New Street Station - What does the client need from the architect?...
Birmingham New Street Station - What does the client need from the architect?...
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
VW Project Presentation
VW Project PresentationVW Project Presentation
VW Project Presentation
 
Concrete Towers - a business case for sustained investment_Rev 5
Concrete Towers - a business case for sustained investment_Rev 5Concrete Towers - a business case for sustained investment_Rev 5
Concrete Towers - a business case for sustained investment_Rev 5
 
Kevin Allmond CV
Kevin Allmond CVKevin Allmond CV
Kevin Allmond CV
 
jahangir
jahangirjahangir
jahangir
 
mohamed_mahmoud_atia - Planning & Cost Control Engineer
mohamed_mahmoud_atia - Planning & Cost Control Engineermohamed_mahmoud_atia - Planning & Cost Control Engineer
mohamed_mahmoud_atia - Planning & Cost Control Engineer
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and fa
 
AEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 FinalistsAEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 Finalists
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
CNG station construction project report.
CNG station construction project report.CNG station construction project report.
CNG station construction project report.
 
HH-- Leader onshore, explorer offshore
HH-- Leader onshore, explorer offshoreHH-- Leader onshore, explorer offshore
HH-- Leader onshore, explorer offshore
 
project management report
project management reportproject management report
project management report
 
Where Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterWhere Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark Winchester
 
GRUG 3 October 2010 opening presentation 20101003
GRUG 3 October 2010 opening presentation 20101003GRUG 3 October 2010 opening presentation 20101003
GRUG 3 October 2010 opening presentation 20101003
 
Company Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressed
Company Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressedCompany Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressed
Company Profile PT. ALEXIS CIPTA FURNITAMA UPDATE.compressed
 
EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...
EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...
EXPERIENCE DURING ' AS-BUILT ' SERVICES IN INDUSTRIAL PROJECT USING LASER 3D ...
 
Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16
 
EPCC: at the heart of data-driven innovation for business
EPCC: at the heart of data-driven innovation for businessEPCC: at the heart of data-driven innovation for business
EPCC: at the heart of data-driven innovation for business
 

Recently uploaded

Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageRCC Institute of Information Technology
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234AafreenAbuthahir2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisDr. Radhey Shyam
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdfKamal Acharya
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionjeevanprasad8
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
 

Recently uploaded (20)

Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 

Gibela Trencon Presentation - 02june2016

  • 1.
  • 7. Page The factory 7 Supplier park: • centre of train manufacturing excellence • 78ha site • R1 billion investment • maximum capacity end 2019: • two cars per day • 1 500 workers employed on site Training centre: • 4 000m2 • to train 19 500 people Testing centre: • static test buildings • 1.2 km test track Manufacturing buildings • 31 500m2 2 June 2016Moving forward with Trencon and Black Jill JV
  • 9. Page Key construction milestones 9 May Building construction starts October Training Centre buildings ready to be equipped March First manufacturing building completed September Construction ends Second Quarter Train production starts 2016 2017 2 June 2016Moving forward with Trencon and Black Jill JV
  • 10. Page Construction milestones Overall construction programme will last approximately 18 months 2 June 2016Moving forward with Trencon and Black Jill JV 10 Note: Main construction Milestones for P0+1+2: black dot =complete, orange dot = planned. Work package 2016 2017 Dec 2015 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2018 Plant rescue, clearance, earthworks, infrastructure RS site buildings Rail infrastructure Electrical reticulation and equipment Electrical reticulation and equipment (traction) Mechanical (HVAC, gas, air, water) Cranes Transborder and turn table Non-statutory signage (Gibela visual identity) Bulk electrical supply Bulk roads and rails Bulk potable water, sewerage pipelines Bulk stormwater Start of construction Plant removal complete Start of building package CBS Portion 1 Beneficial occupation M07 Beneficial occupation Permanent power supply Progress: 67%
  • 11.
  • 13.
  • 14. Page Special thanks 2 June 2016Moving forward with Trencon and Black Jill JV 14 To the Executive Mayor of Ekurhuleni and the EMM Executive Committee and officials for their ongoing support of the project “This project means that Ekurhuleni is no longer the historic leader in manufacturing – it affirms us as the future leader and puts us at the cutting edge of technology.”