3. High-level budget plan
High level Milestones Labour hours Total Costs *
Project charter 16 hrs € 1000.0
Frame work document 4hrs € 250.0
IBMAN office meeting 4 hrs € 250.0
Status presentation 11 hrs € 687.5
Producing the deliverable 198 hrs € 12375.0
Communication to IBMAN students 1 hr € 62.5
Final presentation 22 hrs € 1375.0
Total 243 Hrs €16000.0
*at a rate of € 62.5 per working hour
4. Project progress status
04.05.2011 Project charter
07.05.2011 Define research area
18.05.2011 Layout and content
31.05.2011 Meeting IBMAN office
01.06.2011 Status presentation
16.06.2011 Discussing the analyzed input
23.06.2011 Uploading the final guide
26.06.2011 Communication to IBMAN students
29.06.2011 Closure report
12.07.2011 Final presentation