SlideShare a Scribd company logo
1 
3708 W. Deer Crossing Dr, Stillwater, OK 
New Construction 2010 
4 year results: Ground Source Heat Pump System 
Find online at youtube.com search igshpa
New System to install: Closed-Loop Ground 
Source Heat Pump with Desuperheater 
2 
• Foundation poured 
December 26, 2008 
• Home size: 6,000 SF 
• Layout: 2 story, 
ductwork in attic, HPs 
in attic. 
• 2.5 acres. 
• Recommended 
Tonnage: 9 Ton 
• Ground Loop: 6 Loop 
Wells 300’ deep 
• Move in date June 1, 2010 
• 5 bids to install heating cooling 
systems 
• HPs 2, 3 & 4 Ton
Final Accepted Bid for GSHP System 2009 
(complete installation ducts, units, new construction) 
• Conventional System Gas, electric would have cost: $30,000 
• GSHP System 9 Tons 3 units 2, 3, and 4 ton 
– Loop 6 bore holes 300’ deep 1” HDPE $8,100 
– Headering $4,124 
– Inside Piping $3,912 
– Unit Delivery $17,697 
– Rough in $9,084 
– Final and Start-up $2,402 
Total $45,321 
– 30% tax credit -$13,599 
– $200 per ton from Stillwater, OK electric utility -$1,800 
Total cost for the GSHP system $29,922 
• Final cost for GSHP System less than a conventional system 
and projected annual cost $959 or $80 per month. 
3
4 
GSHP Installation: Contractor Information 
• Location: Goldsby, OK 
• 85 miles from Stillwater 
• Website: comfortworks.us 
• HVAC Specialty: 
Geothermal (IGSHPA 
Certified) 
• Ownership: Chris Ellis 
• Background Information: 
Established 1975 as C&S 
Heating and Air Cond., Inc 
Sold in 2007 and became 
Comfortworks, Inc.
GSHP New Construction Equipment: 
ClimateMaster Tranquility 27 Design Features 
5
6 
6 
GSHP New Construction Equipment 
2 Ton UNIT 3 Ton UNIT 4 Ton UNIT 
5
Site Plan Drilling Locations: Preparing the Property 
•Drill sites location: 
concerns for containment of 
mud and water runoff in 
street and adj. property. 
•Design Recommendation 
3,600’ for Loop field. 
•Site needs 9 tons so six 
boreholes will be drilled to 
300’ for a total of 1800 feet 
using 1 inch HDPE pipe. 
•Recommended spacing 
between boreholes was 25’. 
7 
#2 #1 
Home 
#3 
#4 
15’ 
25’ 
#5 
#6 
•All underground 
utilities flagged prior 
to drilling and digging
Site Plan Drilling Locations: Preparing the Property 
8
9 
9 
Drilling the boreholes •Drilling rig is brought onto 
site 
•Make sure site is cleared 
and ready for drilling 
•Cuttings in the form of mud 
may come from the 
boreholes. 
•In the city, a reclaim unit 
can be used to contain the 
cuttings from going into 
sewer drain. 
•Deer Crossing site is on 2 
½ acres with adequate area 
for runoff without going into 
street or sewer drain.
10 
Heat Exchange Pipe Loop for Boreholes 
1 inch HDPE pipe loop is placed 
in each borehole to serve as a 
heat exchanger between the 
earth and heat pump 
600 feet of 1” 
HDPE Pipe in 
borehole with 
about 5 feet 
sticking out 
HDPE Pipe comes with U-Bend 
thermally fused and tested 610’ long 
HDPE Pipe is placed 
on spool, pressure 
checked with water 
and sealed by 
bending ends prior to 
inserting into 
borehole. 
The HDPE pipe is then lowered to the bottom 
of the borehole with weight of water and 
weight of a 1” x 8’ steel rod attached to end.
11 
Grouting the boreholes 
BH 20 Grout is a Black Hills 
20% solids, modified Bentonite 
Grout which requires no 
polymer additives and is a 
complete mineral based 
product. Once placed, BH 20 
Grout will set into a semi-rigid 
plug of the borehole. 
Mixing the borehole Grout 
•Grout is pumped into each borehole 
from the bottom up through a tremie 
pipe. 
•The grout serves several purposes. 
• Seal the hole to prevent aquifer 
contamination 
• Bond to the pipe 
• Serve as an exchange medium 
between the earth and the pipe 
Grout mixer
12 
Grouting the boreholes 
Inserting the tremie pipe 
Pumping Grout into boreholes 
•Tremie pipe is 1st pushed into borehole 
to the bottom of the borehole. 
•Grout is pumped into each borehole 
from the bottom and is gradually pulled 
up filling any voids. 
•Settling of grout can be expected. 
•As grout settles in each hole, it is 
refilled to top it off 
Grout pumping 
from bottom of 
borehole to the 
top. 
Grout fills 
borehole 
displacing water
13 
Connecting the boreholes Trench is dug to place header pipe 
connecting the ground loop with the 
heat pump units in the home. 
4-5 foot deep trench 
12” wide for header 
piping 
All open pipe are 
taped or plugged to 
prevent dirt from 
getting into pipe. 
All pipe fittings are socket 
fused producing a joint 
stronger then the pipe. 
Butt weld fusion joint 
is stronger than pipe
Connecting the ground loops 
with the heat pumps through 
a reverse return header. 
14 
4-5 foot deep 
trench is dug to 
reduce thermal 
losses between 
loops and heat 
pumps. Depth 
also prevents 
damage to lines 
from 
landscaping. Trench connects 
•Headers are thermally fused at each connection 
and lines are pressure tested prior to filling in 
trenches 
header circulation 
pipes to house utility 
room and then to 
Heat Pumps 
Header pipes are 
pressure tested to 
ensure no leaks 
Borehole Loops are connected to 
header circulation lines using 
Reverse Return
15 
Diagram of Header System with 
Reverse Return for Cooling 
To Heat Pumps 
27 GPM Max Flow 
2” 
2” 
2” 
2” 
2” 
2” 
1 1/4” 
1 1/4” 2” 
1” 
1” 
1” 
1” 
1” 
1” 1” 
1” 
1” 1” 
1” 1” 
Ground Loop 
6 Boreholes 300’ Deep 
1” HDPE pipe
16 
16 
Covering up the Header and Trenches 
•Trenches are filled in and yard brought 
to rough grade condition 
•Professional operators leave the area, 
as good as, or better than before. 
•Location of each borehole loop and the 
header system is located using metal 
plates and GPS. 
Trenches are filled in 
and yard brought to 
rough grade condition 
Care is taken to cover 
the trench and mix 
cuttings with soil. 
GPS is used for 
location of boreholes 
and header system
Ductwork Return and supply 
boots were installed 
in each room 
except bathrooms 
and kitchen to 
minimize pressure 
imbalances, 
improve privacy, 
and is quiet. 
17 
The first step in 
installing ductwork 
is to read the floor 
plan and locate the 
supply and return 
vents. 
Ductwork is sealed, 
insulated, wrapped 
and properly 
supported.
18 
Location of HP and Utility rooms 
3Ton 
2Ton 
4Ton 
Location of 3 Ton 
Unit 2nd floor 
South Utility room 
For 1st floor 
bedroom zone 
conditioning 
Location of 4 & 2 Ton 
Units 2nd floor North 
Utility room for 2nd 
floor conditioning 
HT 
HT 
Location of 
Purge and Flush 
Controls Garage 
Utility room
•Lines are brought into garage utility room for 
connection to heat pump units in attic. 
•Each connection/joint is thermally fused to 
ensure closed and sealed flow of water in 
pipes. 
19 
19 
Circulation Pipes in the Home 
Lines from ground 
loop are brought 
under foundation and 
up into garage utility 
room 
Thermal fusing of 
pipe connections 
Purging and flushing 
connections in garage 
utility room 
Heating HDPE pipe 
and socket tee for 
thermal fusing of pipe 
connections
20 
20 
Heat Pump Installation 
•Location in utility rooms 2nd floor attic space. 
•Three units are installed 
•2 Ton Climate Master – Tranquility 27 
•3 Ton Climate Master – Tranquility 27 with desuperheater 
•4 Ton Climate Master – Tranquility 27 with desuperheater 
Tranquility 27 2 Ton Unit 
TTV026AGC01ALKS 
for cooling/heating 2nd 
floor zone 
Tranquility 27 3 Ton Unit 
TTV038AGC01ALKS 
for cooling/heating 1st 
floor bedrm/study zone 
Tranquility 27 4 Ton Unit 
TTV049AGC01ARKS 
for cooling/heating 1st 
floor Living rm/kit zone
21 
21 
Circulation Pipes in the Home 
•Since circulation lines will run through the 
attic, antifreeze is added to prevent freezing 
of lines during winter. 
•Insulation is added to pipes in attic 
Circulation HDPE 
pipes in attic are 
insulated 
Pipes are 
connected to 
Heat Pump 
Units in attic.
22 
22 
Finalizing Pipe Loop Installation 
Inline air bleeder to 
burp off any future 
trapped air. 
Each HP unit has a High 
efficiency pump for 
circulation between heat 
pump and ground loops 
4 Ton HP has two 
circulation pumps 
Ground Loop and 
Heat Pumps are 
connected to 
flushing and purging 
cart. 
Flushing and 
purging cart is 
used to 
eliminate any air 
in the system.
23 
23 
Connecting Desuperheater to Hot Water Tank 
•Desuperheater is connected to 
supplement hot water heater with hot 
water generated from Tranquility unit’s 
heat exchanger 
•New electric hot water heater 
•Water heater could be put on timer to 
take advantage of Time of Use Rate 
(1:00 p.m. to 7:00 p.m. peak period) 
Desuperheater lines 
connected to electric hot 
water heater 
New electric hot water heater 
connected to desuperheater
24 
24 
Insulation of pipes in attic and 
Programmable Thermostat 
• All pipes in attic running from ground loop are insulated 
to prevent sweating in fall and spring. 
•New programmable thermostats installed and set for 
Time-of-Use rate 
New Downstairs 
Furnace/Air Handler 
New Programmable Thermostat 
Programmed to time of use.
1st thru 4th Year Money & Energy Savings Results 
Total Elec. for lights, cooking, GHP 
1st Year 2nd Year 3rd Year 4 th Y ear 
Total SF = 6000 6000 6000 6000 
Total kWh = 22945 21573 23054 23607 
Aver. kWh/day = 63 60 62 64 
GHP Cost $45,321 
Conv Cost $30,000 
Tax credit 30% +$200/ton 
Final cost $29,922 
Total Electric for year $ = $1,742 $1,802 $1,872 $2,019 
Average Monthly Electric Bill = $145 $150 $156 $168 
Average Monthly kWh = 1,912 1,798 1,874 1,967 
Average Cost Per Day = $4.82 $4.90 $5.13 $5.53 
Plug Load = $92 $77 $83 $88 
Geothermal Heat Pump System 
Cost Average mo. Electric for 
GHP 
*Average mo elec bill – Plug Load = $53 $73 $73 $80 
Total Elec for GHP 1st yr= $636 $876 $876 $960 
Average Cost Per Day = $1.74 $2.40 $2.40 $2.63 
Average Cost Per SF/year= $0.11 $0.15 $0.15 $0.16 
*Projected cost per month $80 GHP Actual average cost per month $66 
*Projected cost per month $80 GHP Actual average cost per month $70
4 year Comparison Total Electric Cost/Month 
26 
Winter Rates Oct-Apr 
2013-2014 
Aver. $168/mo. 
$.09376/kWh >600 kWh =$.05727/kWh 
2011-2012 
Aver. $150/mo. 
Summer Rates May –Sep 
$.10126/kWh 
2010-2011 
Aver. $145/mo. 
2012-2013 
Aver. $156/mo. 
Cost/Month
27 
3708 W. Deer Crossing Dr, Stillwater, OK 
New Construction 2010 
Ground Source Heat Pump 
More Details can be found at http://www.youtube.com 
Search for IGSHPA and videos listed as Home 1-6
Accredited Installer Workshop 
IGSHPA Stillwater, OK 
• The three day comprehensive Installation 
Workshops are designed for GHP 
developers, architects, manufacturers, 
distributors, dealers, installers, HVAC 
contractors, trenching/drilling contractors, 
and anyone who desires a working 
knowledge of this innovative technology. 
http://www.igshpa.okstate.edu/training/accredited.htm 
Call 800-626-4747
Accredited Driller Workshop 
IGSHPA, Stillwater, OK 
• This workshop will train individuals on proper 
construction and completion methods for vertical 
GeoExchange boreholes. Accreditation as an 
“Accredited Vertical Loop Installer” 
• Who should attend? Water Well Drillers, Water Well 
Contractors, Drilling Company Administrators 
• Applications of Production Drilling and Borehole 
Construction for GeoExchange Systems course 
http://www.igshpa.okstate.edu/training/drillers.htm 
Call 800-626-4747
Certified GeoExchange Designer (CGD) 
PLUS and Online Course, IGSHPA, Stillwater 
• From an introduction to the technology to a 
complete review of the design process, 
participants learn the specific information they 
need to know to be a successful GeoExchange 
Designer. 
• As an architect or engineer or designer, you have 
specific questions about GHP systems that you 
want answered. 
• CGD Certification is offered by IGSHPA and AEE 
as an industry standard. 
http://www.igshpa.okstate.edu/training/cgd.htm 
Call 800-626-4747

More Related Content

What's hot

Geothermal AIA
Geothermal AIAGeothermal AIA
Geothermal AIA
GaryBergeron
 
Steamboilers (elements of mechanical engineering)
Steamboilers (elements of mechanical engineering)Steamboilers (elements of mechanical engineering)
Steamboilers (elements of mechanical engineering)
Rohan Lakhani
 
Building technology options
Building technology optionsBuilding technology options
Building technology options
Jeevan Fernando
 
heating-cooling units
heating-cooling unitsheating-cooling units
heating-cooling units
aquaindustrialgroup
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
National Productivity Council, Hyderabad, India
 
FIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects OnlyFIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects OnlyJonathan Morales
 
Summary of changes in burner specifications
Summary of changes in burner specificationsSummary of changes in burner specifications
Summary of changes in burner specifications
Kapil Batra
 
Furnace Improvements Sales Presentation
Furnace Improvements Sales PresentationFurnace Improvements Sales Presentation
Furnace Improvements Sales Presentation
Jonathan Morales
 
Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015
miresmaeil
 
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
University of Minnesota
 
White sulphur springs geothermal well
White sulphur springs geothermal wellWhite sulphur springs geothermal well
White sulphur springs geothermal well
Darrel Dunn
 
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired BoilerOnline Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
National Productivity Council, Hyderabad, India
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
National Productivity Council, Hyderabad, India
 
Materials used in boiler & furnace
Materials used in boiler & furnaceMaterials used in boiler & furnace
Materials used in boiler & furnace
MOHAMMAD ASIF
 
Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)
dishant pagdar
 
Furnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technologyFurnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technology
Disha Mangal
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
Manohar Tatwawadi
 
Thermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boilerThermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boiler
VENUS ENERGY AUDIT SYSTEM
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
National Productivity Council, Hyderabad, India
 

What's hot (20)

Geothermal AIA
Geothermal AIAGeothermal AIA
Geothermal AIA
 
Steamboilers (elements of mechanical engineering)
Steamboilers (elements of mechanical engineering)Steamboilers (elements of mechanical engineering)
Steamboilers (elements of mechanical engineering)
 
Building technology options
Building technology optionsBuilding technology options
Building technology options
 
heating-cooling units
heating-cooling unitsheating-cooling units
heating-cooling units
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
 
FIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects OnlyFIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects Only
 
Summary of changes in burner specifications
Summary of changes in burner specificationsSummary of changes in burner specifications
Summary of changes in burner specifications
 
SP1037 TECHFEST
SP1037 TECHFESTSP1037 TECHFEST
SP1037 TECHFEST
 
Furnace Improvements Sales Presentation
Furnace Improvements Sales PresentationFurnace Improvements Sales Presentation
Furnace Improvements Sales Presentation
 
Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015
 
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
 
White sulphur springs geothermal well
White sulphur springs geothermal wellWhite sulphur springs geothermal well
White sulphur springs geothermal well
 
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired BoilerOnline Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
 
Materials used in boiler & furnace
Materials used in boiler & furnaceMaterials used in boiler & furnace
Materials used in boiler & furnace
 
Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)
 
Furnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technologyFurnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technology
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
Thermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boilerThermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boiler
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
 

Similar to GeothermalHeatPump-DeerCrossingStillwaterOK first Four years revised Jun 26-2014

Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
Vaibhav Paydelwar
 
TRIC Trenchless LA building & safety
TRIC Trenchless LA building & safetyTRIC Trenchless LA building & safety
TRIC Trenchless LA building & safetyMEL3360
 
Olson thc case_study
Olson thc case_studyOlson thc case_study
Olson thc case_study
SmarterHomeGuide
 
Geo thermal system
 Geo thermal system Geo thermal system
Geo thermal system
Dheeraj patidar
 
Will frey-geothermal-powerpoint
Will frey-geothermal-powerpointWill frey-geothermal-powerpoint
Will frey-geothermal-powerpointWilliam Frey iii
 
Ground source heat pumps[1]sk
Ground source heat pumps[1]skGround source heat pumps[1]sk
Ground source heat pumps[1]sk
CKMCforstudents
 
CPD - PHE's Principles _ Applications(1) - High Res.pdf
CPD - PHE's Principles _ Applications(1) - High Res.pdfCPD - PHE's Principles _ Applications(1) - High Res.pdf
CPD - PHE's Principles _ Applications(1) - High Res.pdf
Tickle Community
 
Presentation.pdf
Presentation.pdfPresentation.pdf
Presentation.pdf
JigneshGohil17
 
Heat pump systems
Heat pump systemsHeat pump systems
Heat pump systems
catherinelindsay
 
Earth Air Tube Heat Exchanger
Earth Air Tube Heat ExchangerEarth Air Tube Heat Exchanger
Earth Air Tube Heat Exchanger
Sushant Siddhey
 
Paryavaran bhawan
Paryavaran bhawanParyavaran bhawan
Paryavaran bhawan
MOHIT PANCHAL
 
ground cooling or passive earth cooling techniques.
ground cooling or passive earth cooling techniques.ground cooling or passive earth cooling techniques.
ground cooling or passive earth cooling techniques.
Kalyani Sandeep
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
National Productivity Council, Hyderabad, India
 
02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
HirajanSandragesan
 
GMB geothermal case-study
GMB geothermal case-studyGMB geothermal case-study
GMB geothermal case-study
Paula Woolley
 
WSPE Geothermal Presentation
WSPE Geothermal PresentationWSPE Geothermal Presentation
WSPE Geothermal PresentationDan Rehbein
 
Optimizing ground heat exchanger length with GeoperformX pipe
Optimizing ground heat exchanger length with  GeoperformX pipeOptimizing ground heat exchanger length with  GeoperformX pipe
Optimizing ground heat exchanger length with GeoperformX pipe
Jasmin Raymond
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
sneh patel
 
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1Sanju Jacob
 

Similar to GeothermalHeatPump-DeerCrossingStillwaterOK first Four years revised Jun 26-2014 (20)

Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
TRIC Trenchless LA building & safety
TRIC Trenchless LA building & safetyTRIC Trenchless LA building & safety
TRIC Trenchless LA building & safety
 
Olson thc case_study
Olson thc case_studyOlson thc case_study
Olson thc case_study
 
Geo thermal system
 Geo thermal system Geo thermal system
Geo thermal system
 
Will frey-geothermal-powerpoint
Will frey-geothermal-powerpointWill frey-geothermal-powerpoint
Will frey-geothermal-powerpoint
 
Ground source heat pumps[1]sk
Ground source heat pumps[1]skGround source heat pumps[1]sk
Ground source heat pumps[1]sk
 
CPD - PHE's Principles _ Applications(1) - High Res.pdf
CPD - PHE's Principles _ Applications(1) - High Res.pdfCPD - PHE's Principles _ Applications(1) - High Res.pdf
CPD - PHE's Principles _ Applications(1) - High Res.pdf
 
Presentation.pdf
Presentation.pdfPresentation.pdf
Presentation.pdf
 
Heat pump systems
Heat pump systemsHeat pump systems
Heat pump systems
 
Earth Air Tube Heat Exchanger
Earth Air Tube Heat ExchangerEarth Air Tube Heat Exchanger
Earth Air Tube Heat Exchanger
 
Paryavaran bhawan
Paryavaran bhawanParyavaran bhawan
Paryavaran bhawan
 
ground cooling or passive earth cooling techniques.
ground cooling or passive earth cooling techniques.ground cooling or passive earth cooling techniques.
ground cooling or passive earth cooling techniques.
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
 
02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
 
GMB geothermal case-study
GMB geothermal case-studyGMB geothermal case-study
GMB geothermal case-study
 
WSPE Geothermal Presentation
WSPE Geothermal PresentationWSPE Geothermal Presentation
WSPE Geothermal Presentation
 
Optimizing ground heat exchanger length with GeoperformX pipe
Optimizing ground heat exchanger length with  GeoperformX pipeOptimizing ground heat exchanger length with  GeoperformX pipe
Optimizing ground heat exchanger length with GeoperformX pipe
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
 
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
 
Sanitary Pump Station Rehabilitation
Sanitary Pump Station RehabilitationSanitary Pump Station Rehabilitation
Sanitary Pump Station Rehabilitation
 

GeothermalHeatPump-DeerCrossingStillwaterOK first Four years revised Jun 26-2014

  • 1. 1 3708 W. Deer Crossing Dr, Stillwater, OK New Construction 2010 4 year results: Ground Source Heat Pump System Find online at youtube.com search igshpa
  • 2. New System to install: Closed-Loop Ground Source Heat Pump with Desuperheater 2 • Foundation poured December 26, 2008 • Home size: 6,000 SF • Layout: 2 story, ductwork in attic, HPs in attic. • 2.5 acres. • Recommended Tonnage: 9 Ton • Ground Loop: 6 Loop Wells 300’ deep • Move in date June 1, 2010 • 5 bids to install heating cooling systems • HPs 2, 3 & 4 Ton
  • 3. Final Accepted Bid for GSHP System 2009 (complete installation ducts, units, new construction) • Conventional System Gas, electric would have cost: $30,000 • GSHP System 9 Tons 3 units 2, 3, and 4 ton – Loop 6 bore holes 300’ deep 1” HDPE $8,100 – Headering $4,124 – Inside Piping $3,912 – Unit Delivery $17,697 – Rough in $9,084 – Final and Start-up $2,402 Total $45,321 – 30% tax credit -$13,599 – $200 per ton from Stillwater, OK electric utility -$1,800 Total cost for the GSHP system $29,922 • Final cost for GSHP System less than a conventional system and projected annual cost $959 or $80 per month. 3
  • 4. 4 GSHP Installation: Contractor Information • Location: Goldsby, OK • 85 miles from Stillwater • Website: comfortworks.us • HVAC Specialty: Geothermal (IGSHPA Certified) • Ownership: Chris Ellis • Background Information: Established 1975 as C&S Heating and Air Cond., Inc Sold in 2007 and became Comfortworks, Inc.
  • 5. GSHP New Construction Equipment: ClimateMaster Tranquility 27 Design Features 5
  • 6. 6 6 GSHP New Construction Equipment 2 Ton UNIT 3 Ton UNIT 4 Ton UNIT 5
  • 7. Site Plan Drilling Locations: Preparing the Property •Drill sites location: concerns for containment of mud and water runoff in street and adj. property. •Design Recommendation 3,600’ for Loop field. •Site needs 9 tons so six boreholes will be drilled to 300’ for a total of 1800 feet using 1 inch HDPE pipe. •Recommended spacing between boreholes was 25’. 7 #2 #1 Home #3 #4 15’ 25’ #5 #6 •All underground utilities flagged prior to drilling and digging
  • 8. Site Plan Drilling Locations: Preparing the Property 8
  • 9. 9 9 Drilling the boreholes •Drilling rig is brought onto site •Make sure site is cleared and ready for drilling •Cuttings in the form of mud may come from the boreholes. •In the city, a reclaim unit can be used to contain the cuttings from going into sewer drain. •Deer Crossing site is on 2 ½ acres with adequate area for runoff without going into street or sewer drain.
  • 10. 10 Heat Exchange Pipe Loop for Boreholes 1 inch HDPE pipe loop is placed in each borehole to serve as a heat exchanger between the earth and heat pump 600 feet of 1” HDPE Pipe in borehole with about 5 feet sticking out HDPE Pipe comes with U-Bend thermally fused and tested 610’ long HDPE Pipe is placed on spool, pressure checked with water and sealed by bending ends prior to inserting into borehole. The HDPE pipe is then lowered to the bottom of the borehole with weight of water and weight of a 1” x 8’ steel rod attached to end.
  • 11. 11 Grouting the boreholes BH 20 Grout is a Black Hills 20% solids, modified Bentonite Grout which requires no polymer additives and is a complete mineral based product. Once placed, BH 20 Grout will set into a semi-rigid plug of the borehole. Mixing the borehole Grout •Grout is pumped into each borehole from the bottom up through a tremie pipe. •The grout serves several purposes. • Seal the hole to prevent aquifer contamination • Bond to the pipe • Serve as an exchange medium between the earth and the pipe Grout mixer
  • 12. 12 Grouting the boreholes Inserting the tremie pipe Pumping Grout into boreholes •Tremie pipe is 1st pushed into borehole to the bottom of the borehole. •Grout is pumped into each borehole from the bottom and is gradually pulled up filling any voids. •Settling of grout can be expected. •As grout settles in each hole, it is refilled to top it off Grout pumping from bottom of borehole to the top. Grout fills borehole displacing water
  • 13. 13 Connecting the boreholes Trench is dug to place header pipe connecting the ground loop with the heat pump units in the home. 4-5 foot deep trench 12” wide for header piping All open pipe are taped or plugged to prevent dirt from getting into pipe. All pipe fittings are socket fused producing a joint stronger then the pipe. Butt weld fusion joint is stronger than pipe
  • 14. Connecting the ground loops with the heat pumps through a reverse return header. 14 4-5 foot deep trench is dug to reduce thermal losses between loops and heat pumps. Depth also prevents damage to lines from landscaping. Trench connects •Headers are thermally fused at each connection and lines are pressure tested prior to filling in trenches header circulation pipes to house utility room and then to Heat Pumps Header pipes are pressure tested to ensure no leaks Borehole Loops are connected to header circulation lines using Reverse Return
  • 15. 15 Diagram of Header System with Reverse Return for Cooling To Heat Pumps 27 GPM Max Flow 2” 2” 2” 2” 2” 2” 1 1/4” 1 1/4” 2” 1” 1” 1” 1” 1” 1” 1” 1” 1” 1” 1” 1” Ground Loop 6 Boreholes 300’ Deep 1” HDPE pipe
  • 16. 16 16 Covering up the Header and Trenches •Trenches are filled in and yard brought to rough grade condition •Professional operators leave the area, as good as, or better than before. •Location of each borehole loop and the header system is located using metal plates and GPS. Trenches are filled in and yard brought to rough grade condition Care is taken to cover the trench and mix cuttings with soil. GPS is used for location of boreholes and header system
  • 17. Ductwork Return and supply boots were installed in each room except bathrooms and kitchen to minimize pressure imbalances, improve privacy, and is quiet. 17 The first step in installing ductwork is to read the floor plan and locate the supply and return vents. Ductwork is sealed, insulated, wrapped and properly supported.
  • 18. 18 Location of HP and Utility rooms 3Ton 2Ton 4Ton Location of 3 Ton Unit 2nd floor South Utility room For 1st floor bedroom zone conditioning Location of 4 & 2 Ton Units 2nd floor North Utility room for 2nd floor conditioning HT HT Location of Purge and Flush Controls Garage Utility room
  • 19. •Lines are brought into garage utility room for connection to heat pump units in attic. •Each connection/joint is thermally fused to ensure closed and sealed flow of water in pipes. 19 19 Circulation Pipes in the Home Lines from ground loop are brought under foundation and up into garage utility room Thermal fusing of pipe connections Purging and flushing connections in garage utility room Heating HDPE pipe and socket tee for thermal fusing of pipe connections
  • 20. 20 20 Heat Pump Installation •Location in utility rooms 2nd floor attic space. •Three units are installed •2 Ton Climate Master – Tranquility 27 •3 Ton Climate Master – Tranquility 27 with desuperheater •4 Ton Climate Master – Tranquility 27 with desuperheater Tranquility 27 2 Ton Unit TTV026AGC01ALKS for cooling/heating 2nd floor zone Tranquility 27 3 Ton Unit TTV038AGC01ALKS for cooling/heating 1st floor bedrm/study zone Tranquility 27 4 Ton Unit TTV049AGC01ARKS for cooling/heating 1st floor Living rm/kit zone
  • 21. 21 21 Circulation Pipes in the Home •Since circulation lines will run through the attic, antifreeze is added to prevent freezing of lines during winter. •Insulation is added to pipes in attic Circulation HDPE pipes in attic are insulated Pipes are connected to Heat Pump Units in attic.
  • 22. 22 22 Finalizing Pipe Loop Installation Inline air bleeder to burp off any future trapped air. Each HP unit has a High efficiency pump for circulation between heat pump and ground loops 4 Ton HP has two circulation pumps Ground Loop and Heat Pumps are connected to flushing and purging cart. Flushing and purging cart is used to eliminate any air in the system.
  • 23. 23 23 Connecting Desuperheater to Hot Water Tank •Desuperheater is connected to supplement hot water heater with hot water generated from Tranquility unit’s heat exchanger •New electric hot water heater •Water heater could be put on timer to take advantage of Time of Use Rate (1:00 p.m. to 7:00 p.m. peak period) Desuperheater lines connected to electric hot water heater New electric hot water heater connected to desuperheater
  • 24. 24 24 Insulation of pipes in attic and Programmable Thermostat • All pipes in attic running from ground loop are insulated to prevent sweating in fall and spring. •New programmable thermostats installed and set for Time-of-Use rate New Downstairs Furnace/Air Handler New Programmable Thermostat Programmed to time of use.
  • 25. 1st thru 4th Year Money & Energy Savings Results Total Elec. for lights, cooking, GHP 1st Year 2nd Year 3rd Year 4 th Y ear Total SF = 6000 6000 6000 6000 Total kWh = 22945 21573 23054 23607 Aver. kWh/day = 63 60 62 64 GHP Cost $45,321 Conv Cost $30,000 Tax credit 30% +$200/ton Final cost $29,922 Total Electric for year $ = $1,742 $1,802 $1,872 $2,019 Average Monthly Electric Bill = $145 $150 $156 $168 Average Monthly kWh = 1,912 1,798 1,874 1,967 Average Cost Per Day = $4.82 $4.90 $5.13 $5.53 Plug Load = $92 $77 $83 $88 Geothermal Heat Pump System Cost Average mo. Electric for GHP *Average mo elec bill – Plug Load = $53 $73 $73 $80 Total Elec for GHP 1st yr= $636 $876 $876 $960 Average Cost Per Day = $1.74 $2.40 $2.40 $2.63 Average Cost Per SF/year= $0.11 $0.15 $0.15 $0.16 *Projected cost per month $80 GHP Actual average cost per month $66 *Projected cost per month $80 GHP Actual average cost per month $70
  • 26. 4 year Comparison Total Electric Cost/Month 26 Winter Rates Oct-Apr 2013-2014 Aver. $168/mo. $.09376/kWh >600 kWh =$.05727/kWh 2011-2012 Aver. $150/mo. Summer Rates May –Sep $.10126/kWh 2010-2011 Aver. $145/mo. 2012-2013 Aver. $156/mo. Cost/Month
  • 27. 27 3708 W. Deer Crossing Dr, Stillwater, OK New Construction 2010 Ground Source Heat Pump More Details can be found at http://www.youtube.com Search for IGSHPA and videos listed as Home 1-6
  • 28. Accredited Installer Workshop IGSHPA Stillwater, OK • The three day comprehensive Installation Workshops are designed for GHP developers, architects, manufacturers, distributors, dealers, installers, HVAC contractors, trenching/drilling contractors, and anyone who desires a working knowledge of this innovative technology. http://www.igshpa.okstate.edu/training/accredited.htm Call 800-626-4747
  • 29. Accredited Driller Workshop IGSHPA, Stillwater, OK • This workshop will train individuals on proper construction and completion methods for vertical GeoExchange boreholes. Accreditation as an “Accredited Vertical Loop Installer” • Who should attend? Water Well Drillers, Water Well Contractors, Drilling Company Administrators • Applications of Production Drilling and Borehole Construction for GeoExchange Systems course http://www.igshpa.okstate.edu/training/drillers.htm Call 800-626-4747
  • 30. Certified GeoExchange Designer (CGD) PLUS and Online Course, IGSHPA, Stillwater • From an introduction to the technology to a complete review of the design process, participants learn the specific information they need to know to be a successful GeoExchange Designer. • As an architect or engineer or designer, you have specific questions about GHP systems that you want answered. • CGD Certification is offered by IGSHPA and AEE as an industry standard. http://www.igshpa.okstate.edu/training/cgd.htm Call 800-626-4747