SlideShare a Scribd company logo
Furnace Improvements Services
        Low Cost Value Added Solutions for Fired Heaters


                      Project Case Studies




   Increased Capacity                     Higher Efficiency
   Longer Run Lengths                     Lower NOx Emissions

Furnace Improvements Services Inc.      A.G. Furnace Improvements Pvt. Ltd.
    1600 Highway 6, Suite 480                       K-33, Kalkaji
      Sugar Land, TX 77478                      New Delhi – 110019
        Tel: (281)980-0325                     Tel 1: 91-11-405 8 8696
       Fax: (832) 886-1665                     Tel 2: 91-11-262-8 6775

                         Email: info@heatflux.com
                          Web: www.heatflux.com
                                Case Study 183
Furnace Improvements
Low Cost Solutions for Fired Heaters



            No. 4 Platformer Heater Capacity
                      Improvement
In October 2000, FIS carried out a Platformer Heater Revamp Project for a refinery in Corpus
Christi, TX.

The four-cell Reformer Heater was originally designed for a heat duty of 181.32 MMBtu/hr, in
1970. The heater was operating at 67% thermal efficiency. Client wanted to increase the capacity
and improve the efficiency of this heater but didn’t want an air preheater system and neither
generates steam.

The refinery approached the original designer of the heater. They proposed a conventional
scheme to preheat the feed in the convection section. The scheme had four major drawbacks:
   • Increased of fluid pressure drop
   • Required grade mounted stack
   • Required large diameter piping
   • Cost was very high

FIS was contacted by the refinery to
develop an economical scheme for
improving efficiency. FIS redesigned
the heater with our patented “Split
Flow Technology” scheme. In this
scheme the feed is heated parallel in
the convection and radiant sections.
This design works very well to
increase capacity and minimizing the
pressure drop during the process.

FIS scheme was able to increase capacity,    FIS Split Flow* Technology applied to Platform Heater
and improve efficiency with the following
advantages:
   • Fluid pressure drop decreases
   • Existing stacks were reused.
   • Additional piping was only half the size of conventional scheme.
   • Scheme was nearly half the cost of conventional revamp.

                           Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


FIS carried out the entire
scope of activities from                 Reformer Heater Data Comparison
conceptualization         to                            Before Revamp
                               Item           Units                          After Revamp
commissioning     of    this                            (Operating)
heater revamp. The heater Capacity            BPD       18,000               26,000
was             successfully
commissioned in October Heat Release          MM Btu/hr 234                  225
2002. After revamp, the Stack Temp.           °F        1,092                478
capacity of this heater was
improved from 18,000 BPD Fuel                 MSCFH     244                  242.8
                               Consumption
to 26,000 BPD. The client is
                                                        5.8 Million *
very pleased with the heater Fuel Savings     $/annum
                                                        * Based on $6.0 / MMBtu
performance. The heater has
been running successfully since 2002.




                         Reformer Heater Before and After Revamp


                                                    *Split Flow Patented Technology – US 7204 966B2
Client              CITGO
Client Contact      Mr. Ed De La Cruz
Telephone           (361) 844-5741
Location            Corpus Christi, TX
                          Revamping - Training – Troubleshooting

                                      www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                           •••




                        Revamping - Training – Troubleshooting

                                    www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                         Case Study 185

          CFHT Efficiency Improvement and
              NOx Reduction Project
A northern refinery had a Catalytic Feed Hydrotreater Heater (CFHT) in their Fluid Catalytic
Cracking (FCC) unit. It is a natural draft vertical cylindrical furnace, with a horizontal overhead
convection section and three up fired low NOx natural draft burners. Client was having tube
failures in this heater and decided to contact Furnace Improvements (FIS). They also wanted to
replace the burners.


Furnace Improvements carried out a thorough analysis of the heater. The existing convection
section was designed with very tight design parameters. It also had a very high heat flux leading
to high skin temperatures and subsequent tube failures. The burners had a very high heat release
rate, and were leading to long flames and flame impingement.


FIS redesigned the convection section within one week with a better design overcoming the
drawbacks in the existing design. FIS also replaced the existing burners with six new low NOx
burners and re-rate the heater. FIS developed the detail engineering and fabrication drawings for
the convection section and burners replacement. FIS also developed material and burner
specifications, evaluated the vendor quotations, and witnessed the burner test.

                                 CFHT Heater Parameters

                                                       Before           After
                 Parameter             Units
                                                      Revamp           Revamp
                  Heat Duty          MMBtu/hr           16.70            16.70

                 Heat Release        MMBtu/hr           21.64            19.45

                  Skin Temp.             °F              740              675

                  Efficiency             %              79.57            85.87

                 Stack Temp.             °F              764              537


                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




After the revamp job, the performance of the heater improved as expected. The some of the
results were:
    • Radiant section skin temperature was reduced from 740°F to 675°F.
    • Thermal efficiency was improved from 79.5% to 86%.
    • Stack flue gas temperature was reduced from 764°F to 537°F.


The heater was successfully commissioned in October 2003.


Client               ConocoPhillips
Client Contact       Mr. Hiren Yagnik
Telephone            (618) 255-2534
Location             Roxana, IL

                                             •••




                          Revamping - Training – Troubleshooting

                                      www.heatflux.com
Furnace Improvements
  Low Cost Solutions for Fired Heaters



                                           Case Study 187

               Reboiler Trim Heaters Efficiency
                    Improvement Project
  There were two trim heaters, stripper and stabilizer reboiler, in             STABILIZER REBOILER HEATER
  a reforming plant.                                                                  Convection Section
                                                                                                                     #1           #2

  The heaters were originally designed for a heat duty of 12 and
  13.8 MM Btu/hr respectively. The convection sections in these
  heaters were in poor condition. They were operating at very                             #1            #2


  low efficiency. Client contacted Furnace Improvements (FIS)                                                                               12'- 5"

  looking to improve the performance of these trim heaters.
                                                                       9'- 8"



  FIS studied the design and operating conditions of the heaters.
  FIS solution was to replace the existing convection sections                       #1            #2                     #1           #2

  and provide new stacks to increase the capacity of the heaters                           5'- 3 1/4"
                                                                                    Convection Section
                                                                                                                          5'- 3 1/4"
                                                                                                                    Convection Section
                                                                                    Before and After Revamp
                                                                                     (Before Revamp)
                                                                                                   (After Revamp)
  by 10% and improve their thermal efficiency by 7-8%.


                               Trim Heaters Parameters (Stripper / Stabilizer)
                          Before        After                                                            Before                 After
Parameter      Units                                  Parameter         Units
                          Revamp       Revamp                                                           Revamp                 Revamp
             MMBtu/                                                    MMBtu/
Heat Duty                   13.78       15.14         Heat Duty                                              12.0                13.20
               hr                                                        hr
  Heat       MMBtu/                                      Heat          MMBtu/
                            18.06       18.29                                                            16.13                   16.10
 Release       hr                                       Release          hr
Efficiency       %          76.4         83.2         Efficiency                %                            74.4                  82.0
 Stack                                                  Stack
                 °F          813         572                                °F                               832                   575
 Temp.                                                  Temp.

  FIS carried out process design, detailed engineering, fabrication drawings, engineering
  specifications, material requisitions, and supervised field activities. The heaters are running with
  the enhanced capacity and efficiency since October 2002.
  Client                 CITGO
  Client Contact         Mr. Ed De La Cruz
  Telephone              (361) 844-5741
  Location               Corpus Christi, TX                                             •••

                              Revamping - Training – Troubleshooting

                                           www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                          Case Study 204

Crude Furnace NOx Reduction and Capacity
            Increase Project
An Ohio refinery has a Crude Heater in their Crude
Unit. The Crude Heater is a balanced draft, box type,
horizontal tube radiant heater, having a common
convection section on top. The heater was originally
built in 1968 for 423.2 MMBtu/hr heat duty. The
convection section is designed to preheat oil feed
and also super heat steam from 371°F to 450°F.
This furnace had 84 up-fired burners having a total
heat release of about 500 MMBtu/hr.

Client contacted Furnace Improvements (FIS) to
perform an engineering study for NOx reduction on
this furnace and modeled the furnace with Ultra
Low NOx Burners.

During the study it was found that the radiant tubes
in this heater had been suffering from high tube
metal temperature and flame impingement. The
convection section was inefficient; the air preheater
operating temperature was reaching their
metallurgical limits and the flue gas temperature
leaving the convection section was 300°F higher than
design.

Furnace Improvements modified the convection section and reduced relative coking rates. The
relative coking rates in the existing convection section and the proposed retubed convection
section are shown in the graph below. The Client accepted our recommendations and
immediately assigned FIS the NOx reduction and performance improvement project.

FIS Revamp consists of:
   • Modifying the radiant section
   • Retubing the convection section
   • Burners replacement with Ultra Low NOx burners
                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                                 Relative Coking Rates in Convection Section

                                       0.3


                                      0.25
               Relative Coking Rate




                                       0.2

                                                                                                           Existing
                                      0.15
                                                                                                           Proposed
                                       0.1


                                      0.05


                                        0
                                             1    2    3   4   5   6    7   8   9 10 11 12 13 14 15 16
                                                                        Tube No.




FIS developed the detailed engineering and fabrication drawings for this revamp. We also
developed the detailed specifications for tubes, finning, tube supports, burners, burner supports,
fabrication and erection. We floated enquires, evaluated vendor proposals, and made
recommendations for placing a direct purchase order to the vendors. We carried out testing on
the burners and checked the parameters while the heater was running with full capacity.


         Parameters                                                    Units           Pre Revamp        Post Revamp

         Capacity                                                           BPD             155,900          160,000

         Heater Duty (Process + Steam)                                  MMBtu/hr             443.1            450.46

         Maximum TMT (rad. /conv.)                                              °F         996 / 1,130      801 / 746




The client is able to process more throughput than expected. The tube skin temperatures are very
low. The NOx emissions were reduced to ≈ 0.05 lb/MMBtu. The heater was commissioned in
                                                      Revamping - Training – Troubleshooting

                                                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


April 2004 and has been running successfully ever since.

Client                Premcor
Client Contact        Mr. Jim Prorok
Telephone             (419) 226 2610
Location              Lima, OH
                                                  •••

                                       Case Study 210

       No.2 Reformer Heater NOx Reduction
                     Project
A Reformer Heater was designed as a multi-cell heater consisting of five radiant cells, a common
convection section and five stacks. The heater was originally designed for 12,000 BPD charge
rate. It was revamped several times. The existing heater is rated to process 24,000 BPD of feed
(Naphtha) at an absorbed heat duty of 160.6 MM Btu/hr, an efficiency of 86.9% with a total of 62
burners.

Furnace      Improvements     (FIS) was
approached to do the study and develop
options to reduce NOx emissions.

FIS reviewed the design and operating data
and recommended replacing the existing
burners with Next Generation Ultra Low
NOx Burners.

Two of the cells have staged fuel burners and
other three-cells have premix burners. The
four cells (A, B, C, & D) have 14 burners
each and the last cell (E) has only 6 burners.
FIS installed 15 burners in cells A, B, C, &
D. The burners were installed on a staggered pattern to allow maximum flue gas recirculation.
Cell E, have the same number of burners as existing.

FIS carried out the entire scope of activities from conceptualization to commissioning of this
heater revamp. The heater was successfully commissioned in October 2004. The NOx emissions

                           Revamping - Training – Troubleshooting

                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


were reduced to less than 0.03 lbs Btu.

Client                ConocoPhillips
Client Contact        Mr. Brent Colle
Telephone             (580) 767 2499
Location              Ponca City, OK
                                                   •••



                                          Case Study 242

        NHT and Platformer Heater Capacity
                 Increase Project
The Platformer Heater (H-20/21/22) was originally
designed for 12,000 BPD operation and rated for 119.6
MMBtu/hr process heat duty. The design thermal
efficiency of the heater was ~ 88% but it was operating
only at 80 – 81%.

There are three vertical Cylindrical Heaters along with
the Platformer Heaters, which share a common
convection section and a stack. They are the
Hydrotreater Charge Heater (H-18), Hydrotreater
Stripper Reboiler (H-19) and Depropaniser Reboiler
(H-23).

The heaters were running at 13,000 to 15,000 BPD charge rate. Client wished to revamp the
heaters to 18,000 BPD capacity. Furnace Improvements (FIS) was employed to develop the best
capacity improvement scheme for a #2 Platformer Heater and NHT Heaters.

The conventional revamp option was to extend the existing radiant cells. The other option was to
install a new heater for extra duty required. Both options require a big amount of space and high
cost.
                                                Heater       Existing Heat   Revamped   Extra
                                                             Duty            Duty       Duty
FIS’ recommendation was to increase the
                                                H-18         11.97           13.50      1.53
capacity of the heater based on FIS patented
                                                H-19         18.45           23.50      5.05
“Split Flow Technology”. The heaters were
                                                H-20         27.29           42.50      15.21
                            Revamping - TrainingH-21
                                                 – Troubleshooting
                                                            25.10            30.90      5.30
                                                H-22
                                          www.heatflux.com   21.70           23.10      1.40
                                                H-23         15.15           17.40      2.25
                                                Total        119.7           150.90     30.74
Furnace Improvements
Low Cost Solutions for Fired Heaters


revamped for 18,000 BPD capacity and a design heat duty of 150.4 MMBtu/hr. The revamp cost
was one fourth of the alternate design. The heater firing was limited to the design firing rate. The
thermal efficiency of the heaters was increased from 80% to 89%.




FIS Revamp consists of:
   • Replacement of Coils
   • New Burners and Radiant Floor
   • New Convection Section
   • Replacement of Stack Damper

The heater was revamped not only for increased capacity but also for improved thermal
efficiency and improved reliability. In addition to this, the Platformer Heater’s burners were
replaced with new Ultra Low NOx flat flame burners and the calculated fuel consumption
savings are $876,700 per year.




             Before Revamp                                   After Revamp

 FIS carried out the entire scope of activities from conceptualization to commissioning of this
heater revamp. The heater was successfully commissioned in November 2005 and has been
                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


running ever since.

Client                Valero
Client Contact        Mr. Steven Guillory
Telephone             (409) 948-7463
Location              Texas City, TX
                                              •••




                           Revamping - Training – Troubleshooting

                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                          Case Study 247

                        Combined Feed Heater

The first new heater job by Furnace Improvements (FIS) was
for a Corpus Christi refinery. The new vertical cylindrical
heater is a combined feed heater with a natural draft. It is used
to heat a mixture of hydrocarbon and hydrogen.

The heater was designed for:
   • Absorbed heat duty - 40MMBtu/hr
   • Feed Flow Rate – 450,995 lb/hr
   • 6 Ultra Low NOx Burners
   • Efficiency - 82%

FIS’ scope of services for this heater included design,
engineering, fabrication, procurement, supply and project
services.

The heater was successfully commissioned in August 2005.




Client                 CITGO
Client Contact         Mr. Ed De La Cruz
Telephone              (361) 844-5741
Location               Corpus Christi, TX




                                                •••

                             Revamping - Training – Troubleshooting

                                          www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                        Case Study 248

   Platformer Heater Capacity Improvement
                   Project
Furnace Improvements (FIS) was employed by a
refinery in California to perform a capacity
improvement on a Platformer Heater (H-70-01/02/03).

The heater was originally built in 1979. It was designed
for 12 MBPD and rated for 135.58 MMBtu/hr of heat
duty and 84.03 MMBtu/hr of process heat duty. The
heater was running at 13,000 to 15,000 BPD charge
rate.

Client was seeking to revamp the heater for 18,000
BPD and process heat duty of 113.01 MMBtu/hr and
total heat duty of 160.86 MMBtu/hr.

The design thermal efficiency of the heater was ~ 88%
and was operating at 80- 81%. The stack temperature
was higher by almost 300°F than design.

The conventional revamp option was to extend the existing radiant cells. Extending the radiant
cells has the following disadvantages:
    • Space limitation
    • Higher firing rates
    • Very high cost ( requires radiant tubes and new manifolds)

FIS’ recommended increasing the capacity of the heater using our patented “Split Flow
Technology”. Advantages of revamped design based on split flow are as follows:
   • Lower heat flux
   • Lower firing rates
   • No radiant section modification
   • No civil works


                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                   Design          Revamp        Extra Duty      Re-Rated        Convection
     Heater
                  Heat Duty       Heat Duty       Required      Radiant Duty       Duty
     Section
                                                   MMBtu/hr
   70-H-1            27.68           37.47            9.79            29.01          8.46
   70-H-2            33.42           44.66            11.24           34.45         10.21
   70-H-3            22.93           30.88            7.95            24.35          6.53
   Steam
                     51.58           47.85              -               -           47.85
   Generation
   Total
   Process           84.03          113.01            28.08           87.81          25.2
   Duty

The overall heater efficiency was improved 9%. There was an increased heat duty by 28.08
MMBtu/hr, about 33% more than the original design values. The firing rate was well within the
original firing rate.

FIS carried out the entire scope of activities from conceptualization to commissioning of this
heater revamp. The heater was successfully commissioned in February 2008.


Client                Valero
Client Contact        Mr. Pat Leyel
Telephone             (562) - 491-7256
Location              Wilmington, CA

                                                •••




                             Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                         Case Study 254

       Crude Heater NOx Reduction Project
A refinery has a Crude Heater (191-H-1) in its Atmospheric Vacuum Unit AVU-191. The heater
was built in 1969 and designed for 160,000 BPD at a total heat duty of 490.7 MMBtu/hr. The
heater was later revamped to process 178,500 BPD of crude and 31,500 BPD of slip stream at
total heat duty of 612.4 MMBtu/hr.

    Furnace Improvements (FIS) was
approached to modify the existing Crude
Heater (191-H-1) to enable it to be retrofitted
with a selective Catalytic Reduction Unit
(SCR) to reduce NOx emissions to less than
0.010 lb/MMBtu. A new SCR and Waste
Heat Recovery (WHR) are installed to
accomplish these changes. FIS also
performed the CFD analysis to ensure there is
proper mixing of Ammonia with flue gases in
the SCR unit and there is uniform distribution                                                of
flue gases over the catalyst bed.

In the proposed option FIS designed the
heater for 260,000 BPD at a firing rate of 727
MMBtu/hr (LHV). Crude feed to 191-H-1 is split into two streams: A hot stream (main crude
charge) at 215,000 BPD, 456° F and a cold stream (slip crude stream) at 45,000 BPD, 240° F.
The total absorbed heat duty of the Crude Heater is 672.2 MMBtu/hr. The WHR section is
designed to reduce the flue gas temperature to 300° F as opposed to the current 350° F to 385° F.

FIS’ scope included providing engineering services, designing equipment and supplying
materials needed to modify the existing Crude Heater and auxiliary equipments. FIS’ scope
included the supply of a new waste heat recovery unit, modify the existing heater convection,
and upgrade of the FD and ID Fans. The new waste heat recovery is installed and connected to
the new SCR and existing Crude Heater.

Crude Heater Revamp
The existing slip crude stream in the convection section has 24 rows. Fourteen rows are removed
from service to achieve the required temperature window for SCR operation. The convection
                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


section is divided into two sections: lower and upper, by installing a new horizontal baffle plate.
The plate acts as a barrier and forces the flue gases to exit from the lower section to the SCR,
WHR and return to the upper section. The blanking plate is a new concept and it’s being done for
the 1st time. This design saved our client between $5- $6 Million.

Waste Heat Recovery Unit
The Crude Heater (191-H-1) is supplemented with an outboard WHR unit. The unit is located
downstream of the SCR unit. The heat transfer area was removed from the heater convection
section to achieve the required temperature window. This was done to avoid condensation
recovered in the WHR. The design slip crude flow rate through the WHR will be 45,000 BPD
(560,000 lb/hr). The outboard WHR unit will heat slip crude stream from 240° F to 470° F. The
calculated pressure drop across the WHR is 46.9 psig. The flue gas enters the WHR at a
temperature of 700° F and leaves at 300° F.

Soot Blowers
Twenty-eight electric-motor driven soot blowers are provided in the WHR unit. The soot blowers
are installed in the WHR to clean the surfaces for any ammonium bisulphate deposits resulting
from the reaction of excess NH3 and SO3.

FD & ID Fans
The FD fans are upgraded to increase capacity and reduce the noise across the combustion
systems. The fans are retrofitted with a new impeller, shaft, inlet vanes, inlet cones to match new
rotor, inlet damper and silencer and intake hood. The motor is also being upgraded from a 400
HP to 500 HP motor. Similarly the four ID fans and motors are upgraded.

Dampers
There are a total of 16 dampers being provided in the Crude Heater. All the 16 dampers are
replaced because they were not in working condition. The new dampers are installed at the
existing damper locations.

Finger Ducts & Expansion Joints
New duct work is installed to the north side of the Crude Heater. The hot flue gas ducting is
designed to optimally fit from the heater to the new SCR and also from SCR to WHR. The hot
flue gas enters the duct, passes through the Ammonia Injection Grid (AIG) and enters the SCR.
Expansion joints were also provided on each duct. Cold flue gas ducting was designed to fully
integrate with the WHR system with the existing convection box (below the existing ID fans).
The six cold flue gas ducts tie into heater above the blanking plate.


                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




Ammonia Injection Grid
The new AIG was installed in the hot flue gas finger ducts. The AIG is located 10 ft from the
heater casing. Ammonia is injected from the bottom through these pipes in the direction of the
flue gas flow. NOx in the flue gases reacts with Ammonia over a catalyst to form Nitrogen and
water vapor.

 Description                            Before Revamp               After Revamp
 Total Heat Duty, MMbtu/Hr              612.4                       672.2
 Heater Efficiency (LHV), %             91                          92.4
 Stack Temperature, °F                  350 – 385                   300
 NOx, lb/MMbtu                                                      < 0.01 lb/MMBtu


The total cost of the project for design, engineering, fabrication and supply was $7 Million.
Erection has been completed and the heater was commissioned in February 2009.


Client               ConocoPhillips
Client Contact       Mr. David Burkholder
Telephone            504-656-3427
Location             Belle Chasse, LA


                                                  •••




                           Revamping - Training – Troubleshooting

                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                          Case Study 255

     Reactor Charge Heater (B-301) Capacity
                Increase Project
A Port Arthur Refinery has a reactor charge heater in the GFU Unit. The charge heater is a
vertical cylindrical heater built in 1981 with an air preheating system. It was designed for a total
heat duty of 60 MM Btu/hr.

Furnace Improvements (FIS) was employed in March 2005 to rerate the heater. The rerating was
to be done with new process conditions to minimize the pressure drop.

FIS rerated the heater for new process conditions
using our patented “Split Flow Technology”. FIS
also utilized the convectional series flow technology
to minimize the pressure drop and hardware changes,
therefore, overall minimizing project cost.

FIS recommended rearrangement of the number of
passes or the replacement of the radiant and
convection sections.

FIS carried out the entire scope of activities from
conceptualization to commissioning of this heater
revamp. The heater was successfully revamped in
December 2006 and restarted operation in January
2007. The client is very pleased with the heater
performance.

                                                             Before Revamp


Client                 Valero
Client Contact         Mr. Steve Henderson
Telephone              (409) 985-1135
Location               Port Arthur, TX
                             Revamping - Training – Troubleshooting

                                          www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                                    •••
                                         Case Study 260

  Capacity Improvement for Reactor Charge
             Heater (080-H-001)
Furnace Improvements (FIS) was employed to carry out a capacity improvement of the Reactor
Charge Heater (080-H-001). The client wanted to increase the process heat duty from 29.95
MMBtu/hr to 37 MMBtu/hr. The maximum firing rate limitation was 54 MMBtu/hr.

This heater was originally built in 1965 as a
natural draft all radiant heater. It was modified
in 1980 to increase its thermal efficiency from
55% to 89% by adding a convection section for
steam generation. The heater was operating at
85% efficiency.

The revamp options to increase the capacity of
the heater were:
• Replace existing radiant coil and put in a
    new convection to preheat the process feed.
• Revamp using FIS Split Flow Technology.
    In this option, the process feed is split and
    heated parallel in radiant and convections
    sections. The two parallel streams are then
    combined at the outlet.

FIS revamped the heater, for increasing the processing capacity, using “Split Flow Technology.”




                             Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


           Parameter                       Units           Design   Operating   Revamp
           Total Absorbed Duty          MMBtu/hr       47.63        55.48       42.4
           Process Duty (Total)         MMBtu/hr       29.99        37.68       37.01
           Process Radiant Duty         MMBtu/hr       29.99        37.68       25.01
           Process Convection Duty      MMBtu/hr       -            -           12
           Total Fuel Firing Rate       MMBtu/hr       53.47        64.83       49.87
           Firebox Temperature          °F             1540         1630        1511
           Radiant Average Heat
                                        Btu/hr/ft2     11,820       14,850      11,480
           Flux




Advantages of the revamped design based on Split Flow are as follows:
         a) No radiant section modification – Existing tubes and supports can be used
         b) Steam generation system can be reused with minimum modifications
         c) Lowest cost
         d) Shortest turn-around time

The heater is operating successfully after revamp. FIS carried out the entire scope of activities
from conceptualization to commissioning of this heater revamp.


Client                 Alon USA
Client Contact         Mr. Steve Mattingley / Mr. Jeff Broman
Telephone              (432) 263-9333/ (432) 263-9237
Location               Big Spring, TX

                                                     •••




                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                        Case Study 263B

   N 744 Boiler NOx
   Reduction Project
Furnace Improvements (FIS) was approached
to convert a CO boiler in Unit 40 to be a
standalone refinery fuel gas fired boiler, and
reduce NOx emissions. The existing boiler
was revamped into a fuel gas fired boiler with
a maximum capacity of 400,000 lb/hr of
steam @ 625 psig, 750 °F and reduced the
NOx emissions down to 0.02 lb/MMBTU (16
ppm).

FIS developed a heat transfer model of the boiler. Analyzed the performance of the boiler with
NOx reduction and provided the client with various options for NOx reduction. They selected the
option of ultra low NOx burners with external flue gas recirculation and steam injection into the
burners. FIS scope of services included the following:

   •   NOx Reduction System - Ultra Low NOx Burners and FGR Fan:
       The burners required about 16-17% FGR and 20,000 Lbs/Hr steam injection to reduce the
       NOx emissions to 0.02 Lb/MMBtu. FIS procured the FGR fan. FIS performed the CFD
       modeling of the ducting and combustion air – FGR mixbox to ensure that FGR and
       combustion air are thoroughly mixed before it enters the burners. FIS also performed the
       CFD modeling of the existing and new ultra low NOx burners to predict the overall
       combustion scenario, flame patterns, flame lengths etc.

   •   New Economizer:
       The existing economizer was heavily fouled and the stack temperatures were running
       about 460 °F. FIS installed a new economizer which increased the efficiency of the boiler
       by 3%. The additional fuel savings due to increased efficiency will pay out the new
       economizer in about one year and six months. The lower stack temperature (310 °F) with
       the new economizer also reduced the size of the FGR fan.

   •   Steam Super Heater Modifications:

                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


       FIS performed the heat transfer modeling of the steam super heater and found that the
       existing heat transfer surface was inadequate and steam temperature will drop to about
       680 °F after the revamp. FIS put additional heat transfer surface in the super heater to
       raise the temperature to 810 °F.

   •     Firebox Modifications:
       FIS maximized the heat transfer surface in the firebox by sealing the CO ports with water
       wall panels, and removing the refractory from the floor and the roof. The additional heat
       transfer surface in the firebox increases the radiant heat duty and lowers the firebox
       temperature that also helps in reducing NOx to a little extent.

   •     New Attemperator:
       The existing attemperator was not working. FIS installed a new attemperator to maintain
       a constant super heat temperature at all boiler loads.


             Description                    Before Revamp                After Revamp
 Stack Temperature                               460 °F                     310 °F
 Boiler Efficiency (LHV)                          87%                        90 %
 Steam Temperature Out Of Boiler             700 – 730 °F                 730 – 810 °F
 Steam Temperature after                     Not Working                  730 - 750 °F
 Attemperator
 NOx                                                                 < 0.02 Lb/MMBtu (HHV)

This project was on a fast track. Engineering and procurement of all materials was completed in
10 months. The boiler was successfully commissioned in April 2008.


Client                ConocoPhillips
Client Contact        Mr. Steven J. O'Donnell
Telephone             (806) 275-1307
Location              Borger, TX


                                                   •••




                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



                                          Case Study 266

       Alky Heater (H-2) NOx Reduction and
          Efficiency Improvement Project
Furnace Improvements (FIS) was hired to perform a
turnkey NOx Reduction revamp on an Alky Unit
Heater (H-2). The target NOx emission rate was
0.035 lb/MMBtu (HHV). The Alky Heater is a
vertical cylindrical heater with a design heat duty of
55 MMBtu/hr. The heater efficiency was very low
at 66%.

Excess Oxygen in the firebox was very high at
8.5%. The heater floor was in bad shape. The heater
did not have any stack damper for draft control.

FIS’ scope included finalization of thermal design
and engineering, procurement of material,
fabrication, supply and field installation of the
heater.

FIS scope of services included:

•   Modification of Existing Floor:
    The existing floor was in bad shape, warped and needed to be replaced. The burners were
    fitted on smaller burner circle diameter to increase the reliability of the heater by minimizing
    the flame impingement.

•   Install Eight New Ultra Low NOx Burners (ULNB):
    FIS rerated the heater using ULNB to reduce NOx emissions. The burners are fired vertically
    upwards and the NOx emissions are 0.018 lbs/MMBtu. The burners were housed in a
    common air plenum with a central air intake. The air intake was provided with a pneumatic
    damper.

•   Install New Convection Module:
    Existing convection section efficiency was very low due to a high flue gas temperature

                             Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


    leaving the section. The flue gas temperature decreased to 520o F from 680o F by replacing
    the convection section. FIS supplied and installed an upgraded convection section.
•   Installation of New Stack and Damper:
    FIS replaced the existing stack and installed O2 and temperature indicators for better control
    of the Oxygen levels and temperatures exiting the stack. The new stack was provided with
    connected ladders and platforms. The existing stack did not have a damper for draft control.
    The new stack damper is pneumatically operated. Minimum limit stop has been provided on
    linkage side of damper frame so as to prevent it from being fully closed. A position
    transmitter has been provided to know the damper opening position. The stack damper is
    provided to ensure that the draft at arch is maintained at the design level of (-) 0.1” WC
    under all operating conditions.

                                                   Before             After
                                                   Revamp            Revamp
                  Duty (MMBtu/hr)                     55                60

                  Efficiency (%)                      66               86.2

                  Firing Rate (MMBtu/hr)             83.3              69.6

                  Energy savings ($/year)              -             782,093

                  Payback Period (Years)               -               1.72


After the revamp, the efficiency increased by 20%. The total cost of the project for the design
services, engineering services, fabrication and installation was $1,560,000. The project payout
was estimated to be less than 2 years. This heater was successfully commissioned in March
2008.


Client                 ConocoPhillips
Client Contact         Mr. Hiren Yagnik
Telephone              (618) 255-2534
Location               Roxana, IL


                                                   •••




                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



                                             Case Study 269

             H-28 Vacuum Heater Performance
                   Improvement Study
A refinery was facing coking problems in their Vacuum Heater.
In addition, they also wanted to revamp the heater to handle
Canadian Crude and reduce NOx emissions. FIS did the process
study and as a result of the study, the client decided to build a
new Vacuum heater with an existing heater foundation. The new
heater is 4 ft wider.

This vacuum heater is a horizontal tube box with a convection
section. It is designed for a heat duty of 43MMBtu/hr. FIS’
scope involves design, engineering, structural analysis and
supply of this heater to the site. The heater has an efficiency of
90%.

It was successfully commissioned in March 2009. The heater
was delivered within 7 months of starting the job.

A few months after the start up, FIS received the following
feedback from the client.


“.. we talked about the performance of the VF4 H28 heater
since startup. It has been fantastic! The stack temperature is
370-380°F and the fuel gas usage has dropped about 40% from
the old heater. This is one of the most •
                                      • • efficient heaters in the
refinery. The NOx stack testing came back 0.026 lb
NOx/MMBtu, which is also outstanding. They are even trying
to reduce the O2 even lower, from 4% to 3%. It's a lot different
when you have a tight firebox. Great job!!!”
                                         -Client


Client                   ConocoPhillips
Client Contact           Mr. Hiren Yagnik
Telephone                (618) 255-2534
Location                 Roxana, IL


                                Revamping - Training – Troubleshooting

                                             www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                                  •••

                                       Case Study 279

                    Hot Oil Heater, Wyoming
Furnace Improvements (FIS) was employed to perform
an engineering study on a Hot Oil Heater (HT-501) at a
gas plant.

The heater was originally designed for a 25 MMBtu/hr
duty. FIS analyzed the design and existing condition of
the heater and developed these options:

1. Replacing the heater with a new vertical cylindrical
   heater.
2. Replacing the heater with a new cabin heater having
   the same plot area as of existing heater.
3. Revamping existing heater
       • Replacing the radiant coils, refractory and
           radiant tube supports.
       • Replacing the existing convection section
           with a new improved convection section.
       • Replacing burners

The client opted for option 1 and awarded FIS with a
contract for the turnkey supply of new Hot Oil Heater
for their gas plant.

FIS executed the heater process and mechanical design, structural analysis, material
procurement, fabrication and installation of the Hot Oil Heater in 8 months schedule.

FIS also supplied the burner management system and procured all the instrumentation controls of
the heater. The heater was designed for an increased efficiency of 85% and it was commissioned
in August 2007.

Client               Devon Energy
Client Contact       Mr. Craig Shaw / Mr. Richard Myal
Telephone            (307) 857-2291 / (405) 228-8895

                           Revamping - Training – Troubleshooting

                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


Location              Riverton, WY

                                                   •••
                                        Case Study 280

   CDHDS Reboiler Heater (H-60) Efficiency
          Improvement Project
Furnace Improvements (FIS) was employed to develop an efficiency improvement scheme for
CDHDS reboiler heater (H-60).

The CDHDS reboiler heater is a vertical cylindrical
natural draft heater built in 2002. The CDHDS reboiler
heater (H-60) was designed for a process duty of
72 MMBtu/hr, with a design efficiency of 81%. The
heater was operating at an efficiency of 79%, with the
flue gas stack temperature of 780°F.

FIS reviewed the design and proposed the following
changes to improve the efficiency:
   • Adding six rows of steam generation coil in
       convection section
   • New stack transition cone
   • 25 ft of stack extension

In this scheme, 71,000 lb/hr of 450 # steam condensate
is flashed to 150 # 2 phase, vapor-liquid stream.
Flashing is completed before it enters the convection
section.

The total heat duty of the heater was increased to 82 MMBtu/hr. The extra 10 MMBtu/hr is absorbed
in steam generation coil. Flue gas temperature leaving the stack was reduced at 400°F.

The efficiency of the heater was increased to 90%, which brought energy savings of
approximately USD $ 590,550 per year. The payback period is 1 year 3 months.

This project has been successfully commissioned in October 2007.


                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


Client                 Valero
Client Contact         Mr. Steven Guillory
Telephone              (409) 948-7463
Location               Texas City, TX                                •••
                                        Case Study 283

   Vacuum Heater Capacity Increase Project
Furnace Improvements (FIS) was employed to
conduct an engineering study for a refinery
vacuum heater (200-H4) in Indiana. As part of
their expansion project, the refinery needed to
increase the capacity of a cabin vacuum heater.
This heater was originally installed in 1949.


FIS developed four modification options to
increase the capacity of the vacuum heater. The
client opted for revamping the radiant section coil,
new burners and a new stack.


With these modifications, the capacity of the
heater was increased from 8,200 to 9,500 BPD.


The Heater was successfully commissioned and is
working with increased capacity since May 2008.




Client                 CountryMark
Client Contact         Mr. Tariq Asrar
Telephone              (812) 833-3640 / (812) 838-8186
Location               Mt. Vernon, IN

                                                       •••

                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



                                         Case Study 286

                                Hot Oil Heater
Furnace Improvements (FIS) was employed to perform
an engineering study on a Hot Oil Heater (H-3) in
Roxana, IL. FIS submitted the design and was awarded a
contract for the turnkey supply of new Hot Oil Heater for
their BEU unit.

The BEU Heater (H-3) is a natural draft, vertical
cylindrical heater with a radiant section, convection
section and stack. The heater is used to heat hot oil. The
heater is designed for a total heat duty of 165 MMBtu/hr.

FIS executed the heater process, mechanical design,
structural analysis, material procurement and fabrication
of this hot oil heater.

The client requested an expedited delivery for this heater
to meet their turnaround schedule.

   •   This heater was delivered to the site within 9
       months of receipt of order.
   •   The fabrication was done to such an extent that
       there were no structural welds at the site. All the
       connections were designed to be bolted
       connections.
   •   This is a 6 pass heater and radiant panels were
       designed for each pass to fit in each radiant panel.
   •   The stack outside diameter is 11’ 3 5/8” and the
       height is 97’ 2”. This stack was shipped in two
       pieces, which were bolted at the site.

This heater was succesfully commissioned in May 2009.



Client                ConocoPhillips
Client Contact        Mr. Hiren Yagnik
Telephone             (618) 255-2534
Location              Roxana, IL


                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                                  •••

                                        Case Study 287

          CO Boiler Convection Replacement
An Illinois refinery had a CO boiler in their Fluid Catalytic Cracking (FCC) Unit. The CO boiler
was more than 40 years old. The CO boiler’s convection section is used to preheat the FCC
charge and also generate superheated steam at 600 psig and 710°F.

The boiler had three main problems:
   • Low economizer tube metal temperatures reaching dew point levels
   • High super heated steam temperature
   • Problems with tube supports in the hottest zone

The refinery approached Furnace Improvements (FIS) to provide a new thermal design for
replacing the convection section of the CO boiler. FIS conducted a detailed operation analysis of
the existing CO boiler and built a model of the existing design. With the model built, we were
able to simulate the current operating conditions and predict the heater performance for the
future operating conditions.

We developed a better design overcoming the drawbacks in the existing CO heater. The
convection section was redesigned to:
   • Increase FCC feed flow                   CO Boiler Convection Section
   • Improve CO Boiler efficiency                       Replacement
   • Prevent cold end corrosion of                               Before   After
                                      Item              Units
       economizer                                                Revamp Revamp
   • Eliminate flow distribution      Process Heat Duty MMBtu/hr   81.55   104.91
       problems                       Steam Heat Duty   MMBtu/hr  100.90   115.92
                                           Process Flow             BPD    41,995      48,000
The new design was developed
                                           Stack Temp.              °F       636         577
retaining the existing soot blower
                                           Efficiency               %        68.0        72.6
locations and platform elevations.
                                                                               0.55 Million*
                                           Fuel Savings       $ / annum
                                                                             [ $3.0/MM Btu]

It was estimated to save the client almost $550,000 per year. The project was successfully
executed in February 2008.

Client                ConocoPhillips

                           Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


Client Contact         Mr. Hiren Yagnik
Telephone              (618) 255-2534
Location               Roxana, IL                                                           •••
                                          Case Study 299

      Convection Section Modification in CO
       (CCU-1 & CCU-2) Heater for SCR
                  Installation

A Refinery has CO heater (CCU/2) in their
FCC unit. It is used to combust the FCC off
gas (mainly CO gas) from the spent catalyst
regenerator unit. The hot flue gases
generated from combustion of FCC off gas
are used to preheat the oil and generate
super heated.

The client was installing a new SCR unit
downstream of the CO Heater as a part of
the consent decree agreement to reduce the
NOx emissions. The new SCR requires a
specific flue gas inlet temperature, which
will require reconfiguring the heat transfer
surface in the convection section.

FIS modeled the convection section for 5 proposed cases and provided a revised design. The
proposed cases were so extreme in nature that it was very difficult to meet the flue gas
temperature requirement for all the 5 cases for one design. So, FIS designed the last coil as a trim
coil. The last coil will be use in service when the flue gas temperature exceeds the higher limit
and it will be run dry when the flue gas temperature drops below the lower limit. FIS also
provided a revised configuration for the oil pre heat coil to limit the oil outlet temperature below
730 Deg F to prevent coking.

The client wanted the super heated steam temperature to be close to the design so FIS
reconfigured the super heater surface and provided a revised design. The client approved FIS
design to revamp the convection section. The project was successfully comissioned in August
2009.

Client                 ConocoPhillips
Client Contact         Mr. Hiren Yagnik

                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


Telephone             (618) 255-2534
Location              Roxana, IL

                                                   •••
                                        Case Study 290

           NOx Reduction of Six Fired Heaters
Furnace Improvements was requested to develop a NOx reduction study on six heaters. The
client wanted their NOx emissions to be reduced to 0.025 lb NOx/MMBtu. These heaters were
also needed to be rerated for new operating conditions.

FIS analyzed all the heaters thoroughly, evaluated different schemes and arrived at a conclusion
of replacing the existing burners with Ultra Low NOx burners.

       •    Platformer Heater (009-0920,30,40)
       •    Preflash Reboiler Heater (004-0095)
       •    Vacuum Heater (004-0096)
       •    Cat Cracker Heater (007-0093)
       •    Charge & Stripper Reboiler Heater (009-0910)
       •    Charge Heater (012-0090)



Preflash Reboiler
The heater was built in 1979 as a vertical cylindrical
heater with an absorbed duty of 25 MMBtu/hr and a feed
rate of 135,827 lb/hr.

Charge / Stripper Reboiler
The heater was built in 1958 and was revamped in 1979
with 15 burners on the charge side and 13 burners on the
Stripper reboiler side.

The charge heater has an absorbed heat duty of 10.09
MMBtu/hr and a feed rate of 135,501 lb/hr. The stripper
reboiler has an absorbed heat duty of 15.49 MMBtu/hr and a feed rate of 264,494 lb/hr.

Platformer Heater

                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


The Platformer was built in 1979 on process requirements set forth by UOP. This Platformer
Heater is a vertical arbor (“U”) tube heater with 3 radiant sections and a common convection
section and a stack .The heater has an absorbed duty of 115.9 MMBtu/hr.

   •   The numbers of burners will be increased from 30 to 52.

Vacuum Heater
Vacuum heater is a horizontal tube cabin heater built in 1995. The heater is designed for a feed
rate of 351,000 lb/hr and an absorbed duty of 42 MMBtu/hr. This heater had high stack
temperatures.

   •   The numbers of burners will be increased from 6 to 9 burners.

Charge Heater
The heater was built as a vertical cylindrical heater in
1964, upgraded in 1979, and purchased, rerated and
relocated from California to El Dorado refinery in 1993.
The heater is designed for a feed rate of 26,930 BPD and
an absorbed heat duty of 26.48 MMBtu/hr.

Cat Cracker Heater
The Cat Cracker was built as a vertical cylindrical heater
in 1978. The heater was designed for a feed rate of 22,570
BPD and an absorbed heat duty of 40 MMBtu/hr.


Client                Lion Oil
Client Contact        Mr. Jeff Carr
Telephone             (870) 864 1240
Location              El Dorado, AR


                                                   •••




                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



                                         Case Study 296

    Hydrogen Heater Capacity Improvement
                   Project
Furnace Improvements (FIS) carried out a Hydrogen
Heater (77-H-001) revamp project. The Hydrogen
Heater is a vertical cylindrical heater, built in 1990.
The heater was revamped in 2003, for a heat duty of
12.48 MMBtu/hr. The heater was operating at
efficiency of 78% and an absorbed duty of 11.6
MMBtu/hr. The revamp heater design heat duty is
14.77 MMBtu/hr.

Operating data analysis indicated the following:

•   Convection section fins are burned out/ fouled,
    resulting in higher flue gas temperature leaving
    the convection section.

•   Flue gas temperature leaving the convection
    section increases continuously with time.
    Currently, it is around 100ºF higher than the
    clean conditions flue gas temperature.


The conventional revamp scheme (to preheat the
feed in the convection section) resulted in very high
fluid pressure drop. High fluid pressure drop was not
feasible.

FIS redesigned the convection section with FIS patented “Split Flow Technology”. In this
scheme the feed was heated parallel in the convection and radiant section. The pressure drop
across the heater reduced even at higher capacity, due to this parallel processing.




                             Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                Hydrogen Heater Data Comparison


        Item            Units           Design              Operating         After Revamp

   Capacity         lb/hr                22,383               16,400              24,560
   Absorbed
                    MMBtu/hr             12.46                 11.6                14.77
   Duty
   Heat Release     MMBtu/hr             16.82                 14.9                17.17
   Stack Temp.      °F                    796                  790                  478
   Efficiency       %                     74.1                 77.8                  86

FIS carried out the entire scope of activities from conceptualization to commissioning of this
heater revamp. The heater was successfully commissioned in May 2009. After revamp, the
thermal efficiency of this heater increased from 78% to 86%.



Client                Alon USA
Client Contact        Mr. Steve Mattingley / Mr. Jeff Broman
Telephone             (432) 263-9333/ (432) 263-9237
Location              Big Spring, TX


                                                   •••




                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                       Case Study 303

     Capacity Increase and Efficiency
Improvement in Naphtha Stabilizer Reboiler

A Texan Refinery requested FIS to rerate the NSR for new
process conditions. The natural draft heater is a vertical
cylindrical with convection section and mounted stack. It had
a heat duty of 8.6 MMBtu/hr with an efficiency of 83%.

FIS observed that the firebox was small and volumetric heat
release was high. The proposed process conditions weren’t
feasible with the existing radiant section. Convection section
temperatures were high and the stack height was limiting with
the new firing conditions.

FIS approach was to extend the radiant section and install a
new radiant coil with 50% more radiant area. The heat duty
increase to 10.8 MMBtu/hr and the efficiency went up to 88%
giving fuel savings of US$270,000 per year.

FIS worked on the design, detail engineering, fabrication and
supply of the new convection section, stack and radiant coils.
This project was completed in a fast track and it was
successfully commissioned on September 2009.




Client                Alon USA
Client Contact        Mr. Steve Mattingley / Mr. Jeff Broman
Telephone             (432) 263-9333/ (432) 263-9237
Location              Big Spring, TX

                           Revamping - Training – Troubleshooting

                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



                                               •••




                        Revamping - Training – Troubleshooting

                                    www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                          Case Study 314

       Capacity Increase for Naphtha Splitter
                 Reboiler Service
Furnace Improvements (FIS) was employed by a Refinery in
Indiana to carry out a heat duty increase project for the
Naphtha Splitter Reboiler service. Operating heat duty was
around 11.74 MMBtu/hr. This was being supplied by Naphtha
Splitter Reboiler Heater and by Platformer Heater Convection
Coil. Naphtha Splitter Reboiler service heat duty needs to be
increased by 5 MMBtu/hr.


FIS reviewed the design and operating data for the Naphtha
Splitter Reboiler heater (900-H-1) and modeled the heater
operation. Any heat duty increase in this heater is not viable.
FIS reviewed also the design and operating data for Platformer
Heater (300-H1/H2/H3). In this heater there are 3 radiant cells
and a common convection section. It is possible to shift part of
the #1 Inter Heater duty to the radiant cell of the heater and use
part of this convection coil to provide heat duty of Naphtha
Splitter service. This will require an increase in the firing rate
of the Inter Heater cell. It will need new burners of a higher
capacity.


Client has an Old Platformer Charge Heater (900-HXX). The heater was abandoned in the favor
of the new Platformer heater (300-H1/H2/H3). The inspection of the Old Platformer Charge
Heater from outside showed that it is in good condition. FIS proposes using this heater for
providing the required heat duty requirement for Naphtha Splitter Reboiler service.

FIS revamped the old Platformer Charge Heater adding a new radiant section with tubes and
hangers and a small convection section. The stack was reused. The capacity was increase from
8.38 MMBtu/hr (Naphtha Splitter Reboiler) to 20.12 MMBtu/hr (old Platform Charge Heater).



                             Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



FIS scope of work includes process design, detail engineering, structural design, mechanical
design, GA drawings, Shop fabrication drawings, erection and commissioning supervision.


The heater was successfully commissioned in November 2009.

Client               CountryMark
Client Contact       Mr. Tariq Asrar
Telephone            (812) 833-3640
Location             Mt. Vernon, IN


                                                 •••




                          Revamping - Training – Troubleshooting

                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                        Case Study 329

        NOx Reduction and Capacity Increase of
              H-102 and H-205 Heaters
FIS was employed by a texan Refinery to
develop a NOx reduction study for Depantanizer
Reboilers (H-102 and H-205). Client wished to
reduce the NOx emissions from their heaters by
installing Ultra Low NOx Burners. The targeted
NOx emissions from these heaters are 0.035
lb/MMBtu (HHV basis).


Both heaters are vertical cylindrical heaters with
horizontal convection section and a top mounted
stack. They are design for an absorbed heat duty
of 33 and 46 MMBtu/hr.


FIS performed the study and found out that the
convection sections were fouled. FIS suggest to
revamp the heaters with patented “Split Flow
Technology” to increase capacity by 10%. FIS
also suggest to install the ULNB with patented
“inclined firing system” to eliminate fouling
problems.


FIS is currently working on this project. The
heaters will be commissioned on beginning of 2011.


Client                Alon USA
Client Contact        Mr. Steve Mattingley
Telephone             (432) 263-9333
Location              Big Spring, TX

                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters


                                                 •••
                                      Case Study 333

          Capacity Increase on CDU-2; Crude &
             Vacuum Heaters (11/12-F-01)
Furnace Improvements (FIS) was employed by an Indian
Refinery at Visakhapatnam, to provide recommendations
to increase the capacity of the Crude Heater (11-F-01)
and Vacuum Heater (12-F-01) by 15%.


The crude heater was commissioned in 1985 for a heat
duty of 60 MMBtu/hr. The existing heater was operating
at a thermal efficiency of around 83% which client
wished to improve. The average flue gas temperature
leaving the stack was around 342°C. This was 110°C
higher than the design stack temperature of 230°C.


The vacuum heater was commissioned in 1985 for a heat
duty of 184 MMBtu/hr. The existing heater was
operating at a thermal efficiency of around 83% and the
client wished to improve the same. The average flue gas
temperature leaving stack was around 308°C. This was
78°C higher than the design stack temperature of 230°C.

The client was already planning to install a new in-kind
convection section, new stack, and a new tight shut-off
damper during the forthcoming shutdown. FIS analyzed
the design of the Crude Heater (11-F-01) and developed a
scheme to increase the capacity and improve the
efficiency of both Heaters.


FIS proposed to add a new convection section below the
new-in kind convection for both heaters. The proposed

                          Revamping - Training – Troubleshooting

                                      www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



convection will increase the absorbed duty across the convection and will help in reducing the
stack temperature to around 276°C in crude heater and 165°C for vacuum heater.


The results in both heaters were:
    Capacity Increase by 15%
    Heat duty Increase by 15%
    Efficiency Improve to >90%
    Stack Temperature reduction


The heaters were successfully commissioned on July 2010.



Client               HPCL
Client Contact       Mr. S. Bharathan
Telephone            (+)91-891-2894814
Location             Visakhapatnam, India

                                                 …




                           Revamping - Training – Troubleshooting

                                       www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                         Case Study 335

  Platformer Heaters Capacity Improvement
         and NOx Reduction Project
Furnace Improvements (FIS) was
employed to re-rate Heater process using
Low NOx Burners and increase the
Capacity on Platformer Heaters (H-4 /
H-5).

The heaters were originally built in
1959. The heaters were changed to
forced draft in 1977. Common air pre-
heater, induced draft and forced draft fan
were added to pre-heat the combustion
air. Process fluid is heated in radiant
sections. Convection section is used for
steam generation.

Heaters design capacity is 32 MBPD. The client wanted to revamp the heaters for a higher
capacity of 40 MBPD.

The conventional revamp option has following disadvantages:
              • Very high cost
              • Requires large size manifolds and piping
              • Total pressure drop was very high

FIS’ recommended increasing the capacity of the heater using our patented “Split Flow
technology”.

Advantages of revamped design based on split flow are as follows:
              • Lower heat flux
              • Lower firing rates
              • Lower pressure drop
              • No radiant section modification

                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                             Design Heat           Revamp Heat              Extra Duty
       Heater Section           Duty                  Duty                   Required
                                                     MMBtu/hr
      Process Duty
      H-4                         73.8                    82.7                  8.9
      H-5                         72.0                    80.5                  8.5
      H-6                         37.5                    42.1                  4.6
      Total                      183.3                    205.3                22.0
      Steam
                                  80.5                    51.4                   -
      Generation
      Firing Rate                292.2                    283.7                (-)8.5

The process heat duty increased by 22.0 MMBtu/hr. The revamp heaters firing rate shall be 8.5
MMBtu/hr lower than existing design. The new design reduces the air preheat temperature to
270°F from operating temperature of 600-700°F.

FIS carried out the entire scope of activities from conceptualization to commissioning of these
heaters. The project is currently in the execution phase. It is schedule to be commissioned on first
quarter of 2011.


Client                 ConocoPhillips
Client Contact         Mr. Hiren Yagnik
Telephone              (618) 255-2534
Location               Roxana, IL




                                                    •••




                            Revamping - Training – Troubleshooting

                                         www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                        Case Study 338

         Performance Improvement Project on 3
                  Platform Heaters

A Wyoming Refinery approached Furnace Improvements (FIS) to carry out an engineering study
for a capacity increase of 3 platformer heaters. The three heaters (H-1003/4/5) were built by
Radco in 1990 and were relocated in 2006 to the Refinery. The middle heater (#1 Reheater) has a
common convection and stack for all three heaters.These heaters are draft limiting. The heaters
are not able to achieve the desired throughput.


FIS analyzed the existing design data and drawings of the Heaters (H-1003/4/5). The
observations are as follows:
   • The existing heaters are deficient in design. Arch pressure is positive on all three heaters
       at design conditions. The arch pressure is (+)0.603 in WC, (+)0.103 in WC and (+)0.123
       in WC for H-1003, H-1004 & H-1005 heaters respectively.


In this study, FIS proposes 5 recommendations for the revamp of Charge Heater (H-1003), #1
Reheater (H-1004) and #2 Reheater (H-1005). The recommendations are based on improving the
draft in all the three heaters. FIS also proposes a recommendation for increasing the capacity of
the heaters to the target capacity.




                            Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




Client chose the stack modification as a revamp option. FIS carried the following major
modifications:
    • The existing stack and transition cone shall be replaced with a new stack and new
       transition cone.
    • The new stack shall be wider and taller than the existing stack. The new stack length shall
       be 95 ft and 7’-6” outside metal diameter.
    • The new stack will have new dampers (4 blades) and platforms.

FIS scope of work included process design, detail engineering, structural design, mechanical
design, GA drawings, Shop fabrication drawings, and supply of new transition cone, stack and
platforms.




Client                Sinclair
Client Contact        Mr. Mike Palumbo
Telephone             (307) 328-3549
Location              Casper, WY



                                                 …




                           Revamping - Training – Troubleshooting

                                        www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters




                                     Case Study 339

       Capacity Improvement for FRE-APS and
           FRE-VPS Heaters (31/32-F-01)
      FIS carried out a Crude Heater Capacity
      Improvement project for an Indian Refinery
      in Mumbai. The Client wanted to increase
      the heater capacity by 15% with a thermal
      efficiency of more than 90%.

      FIS proposed addition of a small convection
      section on top of the existing heater
      convection section and addition of burners
      to the heater. The convection section had a
      coil for vacuum heater as well and the
      capacity of vacuum heater was increased by
      15% too.

      The study was carried out in 2 weeks and
      the detail engineering was carried out in 8
      weeks. The heater was successfully
      commissioned on May 2010.




Client              HPCL
Client Contact      Mr. Anamitra Upadhya
Telephone           (+)91-22-25076496
Location            Mumbai



                         Revamping - Training – Troubleshooting

                                     www.heatflux.com
Furnace Improvements
Low Cost Solutions for Fired Heaters



                                              …




                        Revamping - Training – Troubleshooting

                                    www.heatflux.com

More Related Content

What's hot

AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
Ashutosh Garg
 
Improving Performance of Coker Heaters
Improving Performance of Coker HeatersImproving Performance of Coker Heaters
Improving Performance of Coker Heaters
Ashutosh Garg
 
Air Preheat System Upgrade on Coker Heaters
Air Preheat System Upgrade on Coker HeatersAir Preheat System Upgrade on Coker Heaters
Air Preheat System Upgrade on Coker Heaters
Ashutosh Garg
 
Improve shale oil crude heater performance summary slideshare
Improve shale oil crude heater performance summary slideshareImprove shale oil crude heater performance summary slideshare
Improve shale oil crude heater performance summary slideshare
Ashutosh Garg
 
Burner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsBurner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia Plants
Gerard B. Hawkins
 
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired HeatersAIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
Ashutosh Garg
 
Improving Shale Oil Crude Heater Performance- India 2018
Improving Shale Oil Crude Heater  Performance- India 2018Improving Shale Oil Crude Heater  Performance- India 2018
Improving Shale Oil Crude Heater Performance- India 2018
Abhinanda Das
 
Fired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From YokogawaFired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From Yokogawa
Miller Energy, Inc.
 
Introduction of Fired heaters
Introduction of Fired heatersIntroduction of Fired heaters
Introduction of Fired heaters
Héctor Nguema Ondo
 
Heater operation
Heater operationHeater operation
Heater operation
JOMON M.C
 
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsFired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Ashutosh Garg
 
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Belilove Company-Engineers
 
A new approach to improving heater efficiency
A new approach to improving heater efficiencyA new approach to improving heater efficiency
A new approach to improving heater efficiencyAshutosh Garg
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen Plants
Gerard B. Hawkins
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
National Productivity Council, Hyderabad, India
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
National Productivity Council, Hyderabad, India
 
Efficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHREfficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHR
National Productivity Council, Hyderabad, India
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
Gerard B. Hawkins
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
National Productivity Council, Hyderabad, India
 
Catalyst Catastrophes in Syngas Production - II
Catalyst Catastrophes in Syngas Production - IICatalyst Catastrophes in Syngas Production - II
Catalyst Catastrophes in Syngas Production - II
Gerard B. Hawkins
 

What's hot (20)

AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
 
Improving Performance of Coker Heaters
Improving Performance of Coker HeatersImproving Performance of Coker Heaters
Improving Performance of Coker Heaters
 
Air Preheat System Upgrade on Coker Heaters
Air Preheat System Upgrade on Coker HeatersAir Preheat System Upgrade on Coker Heaters
Air Preheat System Upgrade on Coker Heaters
 
Improve shale oil crude heater performance summary slideshare
Improve shale oil crude heater performance summary slideshareImprove shale oil crude heater performance summary slideshare
Improve shale oil crude heater performance summary slideshare
 
Burner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsBurner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia Plants
 
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired HeatersAIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
 
Improving Shale Oil Crude Heater Performance- India 2018
Improving Shale Oil Crude Heater  Performance- India 2018Improving Shale Oil Crude Heater  Performance- India 2018
Improving Shale Oil Crude Heater Performance- India 2018
 
Fired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From YokogawaFired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From Yokogawa
 
Introduction of Fired heaters
Introduction of Fired heatersIntroduction of Fired heaters
Introduction of Fired heaters
 
Heater operation
Heater operationHeater operation
Heater operation
 
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsFired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
 
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
 
A new approach to improving heater efficiency
A new approach to improving heater efficiencyA new approach to improving heater efficiency
A new approach to improving heater efficiency
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen Plants
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
 
Efficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHREfficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHR
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
 
Catalyst Catastrophes in Syngas Production - II
Catalyst Catastrophes in Syngas Production - IICatalyst Catastrophes in Syngas Production - II
Catalyst Catastrophes in Syngas Production - II
 

Similar to FIS Case Studies- Executed Projects Only

Bioenergy-Insight
Bioenergy-InsightBioenergy-Insight
Bioenergy-InsightSamit Pethe
 
BCE SUPERCIRC Heater
BCE SUPERCIRC HeaterBCE SUPERCIRC Heater
BCE SUPERCIRC Heater
Belilove Company-Engineers
 
Heat ventilation for diesel generator shelter.pptx
Heat ventilation for diesel generator shelter.pptxHeat ventilation for diesel generator shelter.pptx
Heat ventilation for diesel generator shelter.pptx
business info
 
Condensing Boilers: Are they cost effective?
Condensing Boilers: Are they cost effective?Condensing Boilers: Are they cost effective?
Condensing Boilers: Are they cost effective?
Center for Energy and Environment
 
Heat Pump case studies Aspiration Energy
Heat Pump case studies   Aspiration EnergyHeat Pump case studies   Aspiration Energy
Heat Pump case studies Aspiration Energy
Aspiration Cleantech Ventures
 
Burners & fire boxes
Burners & fire boxesBurners & fire boxes
Burners & fire boxes
Sabbir Ahasan
 
Avoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operationAvoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operation
Gerard B. Hawkins
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
Gerard B. Hawkins
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperiencePooja Agarwal
 
Oil fired boiler | diesel fired boiler | furnace oil fired boiler | high s...
Oil fired boiler  | diesel fired boiler  | furnace oil fired boiler  | high s...Oil fired boiler  | diesel fired boiler  | furnace oil fired boiler  | high s...
Oil fired boiler | diesel fired boiler | furnace oil fired boiler | high s...
Ravindra Dhumal
 
Industrial oil or gas fired boiler
Industrial  oil or  gas fired boilerIndustrial  oil or  gas fired boiler
Industrial oil or gas fired boiler
Ravindra Dhumal
 
DESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGER
DESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGERDESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGER
DESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGER
hemantnehete
 
Paper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmizationPaper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmization
CANDHARE
 
Air to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat PumpAir to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat Pump
Center for Sustainable Energy
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
Center for Energy and Environment
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
Center for Energy and Environment
 
Farm-Scale Char Production: Affordable 4C Kilns for Biochar
Farm-Scale Char Production: Affordable 4C Kilns for BiocharFarm-Scale Char Production: Affordable 4C Kilns for Biochar
Farm-Scale Char Production: Affordable 4C Kilns for Biochar
bitmaxim
 
MEC 422 - Energy Recovery from an Electrical Generating Facility
MEC 422 - Energy Recovery from an Electrical Generating FacilityMEC 422 - Energy Recovery from an Electrical Generating Facility
MEC 422 - Energy Recovery from an Electrical Generating FacilityLuis Lituma
 

Similar to FIS Case Studies- Executed Projects Only (20)

Appsolu
AppsoluAppsolu
Appsolu
 
Bioenergy-Insight
Bioenergy-InsightBioenergy-Insight
Bioenergy-Insight
 
BCE SUPERCIRC Heater
BCE SUPERCIRC HeaterBCE SUPERCIRC Heater
BCE SUPERCIRC Heater
 
Heat ventilation for diesel generator shelter.pptx
Heat ventilation for diesel generator shelter.pptxHeat ventilation for diesel generator shelter.pptx
Heat ventilation for diesel generator shelter.pptx
 
Condensing Boilers: Are they cost effective?
Condensing Boilers: Are they cost effective?Condensing Boilers: Are they cost effective?
Condensing Boilers: Are they cost effective?
 
Heat Pump case studies Aspiration Energy
Heat Pump case studies   Aspiration EnergyHeat Pump case studies   Aspiration Energy
Heat Pump case studies Aspiration Energy
 
Burners & fire boxes
Burners & fire boxesBurners & fire boxes
Burners & fire boxes
 
Avoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operationAvoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operation
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field Experience
 
Oil fired boiler | diesel fired boiler | furnace oil fired boiler | high s...
Oil fired boiler  | diesel fired boiler  | furnace oil fired boiler  | high s...Oil fired boiler  | diesel fired boiler  | furnace oil fired boiler  | high s...
Oil fired boiler | diesel fired boiler | furnace oil fired boiler | high s...
 
Industrial oil or gas fired boiler
Industrial  oil or  gas fired boilerIndustrial  oil or  gas fired boiler
Industrial oil or gas fired boiler
 
DESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGER
DESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGERDESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGER
DESIGN AND FABRICATION OF HELICAL TUBE IN COIL TYPE HEAT EXCHANGER
 
Paper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmizationPaper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmization
 
Air to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat PumpAir to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat Pump
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Farm-Scale Char Production: Affordable 4C Kilns for Biochar
Farm-Scale Char Production: Affordable 4C Kilns for BiocharFarm-Scale Char Production: Affordable 4C Kilns for Biochar
Farm-Scale Char Production: Affordable 4C Kilns for Biochar
 
MEC 422 - Energy Recovery from an Electrical Generating Facility
MEC 422 - Energy Recovery from an Electrical Generating FacilityMEC 422 - Energy Recovery from an Electrical Generating Facility
MEC 422 - Energy Recovery from an Electrical Generating Facility
 
Biofule
BiofuleBiofule
Biofule
 

Recently uploaded

Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 

Recently uploaded (20)

Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 

FIS Case Studies- Executed Projects Only

  • 1. Furnace Improvements Services Low Cost Value Added Solutions for Fired Heaters Project Case Studies  Increased Capacity  Higher Efficiency  Longer Run Lengths  Lower NOx Emissions Furnace Improvements Services Inc. A.G. Furnace Improvements Pvt. Ltd. 1600 Highway 6, Suite 480 K-33, Kalkaji Sugar Land, TX 77478 New Delhi – 110019 Tel: (281)980-0325 Tel 1: 91-11-405 8 8696 Fax: (832) 886-1665 Tel 2: 91-11-262-8 6775 Email: info@heatflux.com Web: www.heatflux.com Case Study 183
  • 2. Furnace Improvements Low Cost Solutions for Fired Heaters No. 4 Platformer Heater Capacity Improvement In October 2000, FIS carried out a Platformer Heater Revamp Project for a refinery in Corpus Christi, TX. The four-cell Reformer Heater was originally designed for a heat duty of 181.32 MMBtu/hr, in 1970. The heater was operating at 67% thermal efficiency. Client wanted to increase the capacity and improve the efficiency of this heater but didn’t want an air preheater system and neither generates steam. The refinery approached the original designer of the heater. They proposed a conventional scheme to preheat the feed in the convection section. The scheme had four major drawbacks: • Increased of fluid pressure drop • Required grade mounted stack • Required large diameter piping • Cost was very high FIS was contacted by the refinery to develop an economical scheme for improving efficiency. FIS redesigned the heater with our patented “Split Flow Technology” scheme. In this scheme the feed is heated parallel in the convection and radiant sections. This design works very well to increase capacity and minimizing the pressure drop during the process. FIS scheme was able to increase capacity, FIS Split Flow* Technology applied to Platform Heater and improve efficiency with the following advantages: • Fluid pressure drop decreases • Existing stacks were reused. • Additional piping was only half the size of conventional scheme. • Scheme was nearly half the cost of conventional revamp. Revamping - Training – Troubleshooting www.heatflux.com
  • 3. Furnace Improvements Low Cost Solutions for Fired Heaters FIS carried out the entire scope of activities from Reformer Heater Data Comparison conceptualization to Before Revamp Item Units After Revamp commissioning of this (Operating) heater revamp. The heater Capacity BPD 18,000 26,000 was successfully commissioned in October Heat Release MM Btu/hr 234 225 2002. After revamp, the Stack Temp. °F 1,092 478 capacity of this heater was improved from 18,000 BPD Fuel MSCFH 244 242.8 Consumption to 26,000 BPD. The client is 5.8 Million * very pleased with the heater Fuel Savings $/annum * Based on $6.0 / MMBtu performance. The heater has been running successfully since 2002. Reformer Heater Before and After Revamp *Split Flow Patented Technology – US 7204 966B2 Client CITGO Client Contact Mr. Ed De La Cruz Telephone (361) 844-5741 Location Corpus Christi, TX Revamping - Training – Troubleshooting www.heatflux.com
  • 4. Furnace Improvements Low Cost Solutions for Fired Heaters ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 5. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 185 CFHT Efficiency Improvement and NOx Reduction Project A northern refinery had a Catalytic Feed Hydrotreater Heater (CFHT) in their Fluid Catalytic Cracking (FCC) unit. It is a natural draft vertical cylindrical furnace, with a horizontal overhead convection section and three up fired low NOx natural draft burners. Client was having tube failures in this heater and decided to contact Furnace Improvements (FIS). They also wanted to replace the burners. Furnace Improvements carried out a thorough analysis of the heater. The existing convection section was designed with very tight design parameters. It also had a very high heat flux leading to high skin temperatures and subsequent tube failures. The burners had a very high heat release rate, and were leading to long flames and flame impingement. FIS redesigned the convection section within one week with a better design overcoming the drawbacks in the existing design. FIS also replaced the existing burners with six new low NOx burners and re-rate the heater. FIS developed the detail engineering and fabrication drawings for the convection section and burners replacement. FIS also developed material and burner specifications, evaluated the vendor quotations, and witnessed the burner test. CFHT Heater Parameters Before After Parameter Units Revamp Revamp Heat Duty MMBtu/hr 16.70 16.70 Heat Release MMBtu/hr 21.64 19.45 Skin Temp. °F 740 675 Efficiency % 79.57 85.87 Stack Temp. °F 764 537 Revamping - Training – Troubleshooting www.heatflux.com
  • 6. Furnace Improvements Low Cost Solutions for Fired Heaters After the revamp job, the performance of the heater improved as expected. The some of the results were: • Radiant section skin temperature was reduced from 740°F to 675°F. • Thermal efficiency was improved from 79.5% to 86%. • Stack flue gas temperature was reduced from 764°F to 537°F. The heater was successfully commissioned in October 2003. Client ConocoPhillips Client Contact Mr. Hiren Yagnik Telephone (618) 255-2534 Location Roxana, IL ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 7. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 187 Reboiler Trim Heaters Efficiency Improvement Project There were two trim heaters, stripper and stabilizer reboiler, in STABILIZER REBOILER HEATER a reforming plant. Convection Section #1 #2 The heaters were originally designed for a heat duty of 12 and 13.8 MM Btu/hr respectively. The convection sections in these heaters were in poor condition. They were operating at very #1 #2 low efficiency. Client contacted Furnace Improvements (FIS) 12'- 5" looking to improve the performance of these trim heaters. 9'- 8" FIS studied the design and operating conditions of the heaters. FIS solution was to replace the existing convection sections #1 #2 #1 #2 and provide new stacks to increase the capacity of the heaters 5'- 3 1/4" Convection Section 5'- 3 1/4" Convection Section Before and After Revamp (Before Revamp) (After Revamp) by 10% and improve their thermal efficiency by 7-8%. Trim Heaters Parameters (Stripper / Stabilizer) Before After Before After Parameter Units Parameter Units Revamp Revamp Revamp Revamp MMBtu/ MMBtu/ Heat Duty 13.78 15.14 Heat Duty 12.0 13.20 hr hr Heat MMBtu/ Heat MMBtu/ 18.06 18.29 16.13 16.10 Release hr Release hr Efficiency % 76.4 83.2 Efficiency % 74.4 82.0 Stack Stack °F 813 572 °F 832 575 Temp. Temp. FIS carried out process design, detailed engineering, fabrication drawings, engineering specifications, material requisitions, and supervised field activities. The heaters are running with the enhanced capacity and efficiency since October 2002. Client CITGO Client Contact Mr. Ed De La Cruz Telephone (361) 844-5741 Location Corpus Christi, TX ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 8. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 204 Crude Furnace NOx Reduction and Capacity Increase Project An Ohio refinery has a Crude Heater in their Crude Unit. The Crude Heater is a balanced draft, box type, horizontal tube radiant heater, having a common convection section on top. The heater was originally built in 1968 for 423.2 MMBtu/hr heat duty. The convection section is designed to preheat oil feed and also super heat steam from 371°F to 450°F. This furnace had 84 up-fired burners having a total heat release of about 500 MMBtu/hr. Client contacted Furnace Improvements (FIS) to perform an engineering study for NOx reduction on this furnace and modeled the furnace with Ultra Low NOx Burners. During the study it was found that the radiant tubes in this heater had been suffering from high tube metal temperature and flame impingement. The convection section was inefficient; the air preheater operating temperature was reaching their metallurgical limits and the flue gas temperature leaving the convection section was 300°F higher than design. Furnace Improvements modified the convection section and reduced relative coking rates. The relative coking rates in the existing convection section and the proposed retubed convection section are shown in the graph below. The Client accepted our recommendations and immediately assigned FIS the NOx reduction and performance improvement project. FIS Revamp consists of: • Modifying the radiant section • Retubing the convection section • Burners replacement with Ultra Low NOx burners Revamping - Training – Troubleshooting www.heatflux.com
  • 9. Furnace Improvements Low Cost Solutions for Fired Heaters Relative Coking Rates in Convection Section 0.3 0.25 Relative Coking Rate 0.2 Existing 0.15 Proposed 0.1 0.05 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Tube No. FIS developed the detailed engineering and fabrication drawings for this revamp. We also developed the detailed specifications for tubes, finning, tube supports, burners, burner supports, fabrication and erection. We floated enquires, evaluated vendor proposals, and made recommendations for placing a direct purchase order to the vendors. We carried out testing on the burners and checked the parameters while the heater was running with full capacity. Parameters Units Pre Revamp Post Revamp Capacity BPD 155,900 160,000 Heater Duty (Process + Steam) MMBtu/hr 443.1 450.46 Maximum TMT (rad. /conv.) °F 996 / 1,130 801 / 746 The client is able to process more throughput than expected. The tube skin temperatures are very low. The NOx emissions were reduced to ≈ 0.05 lb/MMBtu. The heater was commissioned in Revamping - Training – Troubleshooting www.heatflux.com
  • 10. Furnace Improvements Low Cost Solutions for Fired Heaters April 2004 and has been running successfully ever since. Client Premcor Client Contact Mr. Jim Prorok Telephone (419) 226 2610 Location Lima, OH ••• Case Study 210 No.2 Reformer Heater NOx Reduction Project A Reformer Heater was designed as a multi-cell heater consisting of five radiant cells, a common convection section and five stacks. The heater was originally designed for 12,000 BPD charge rate. It was revamped several times. The existing heater is rated to process 24,000 BPD of feed (Naphtha) at an absorbed heat duty of 160.6 MM Btu/hr, an efficiency of 86.9% with a total of 62 burners. Furnace Improvements (FIS) was approached to do the study and develop options to reduce NOx emissions. FIS reviewed the design and operating data and recommended replacing the existing burners with Next Generation Ultra Low NOx Burners. Two of the cells have staged fuel burners and other three-cells have premix burners. The four cells (A, B, C, & D) have 14 burners each and the last cell (E) has only 6 burners. FIS installed 15 burners in cells A, B, C, & D. The burners were installed on a staggered pattern to allow maximum flue gas recirculation. Cell E, have the same number of burners as existing. FIS carried out the entire scope of activities from conceptualization to commissioning of this heater revamp. The heater was successfully commissioned in October 2004. The NOx emissions Revamping - Training – Troubleshooting www.heatflux.com
  • 11. Furnace Improvements Low Cost Solutions for Fired Heaters were reduced to less than 0.03 lbs Btu. Client ConocoPhillips Client Contact Mr. Brent Colle Telephone (580) 767 2499 Location Ponca City, OK ••• Case Study 242 NHT and Platformer Heater Capacity Increase Project The Platformer Heater (H-20/21/22) was originally designed for 12,000 BPD operation and rated for 119.6 MMBtu/hr process heat duty. The design thermal efficiency of the heater was ~ 88% but it was operating only at 80 – 81%. There are three vertical Cylindrical Heaters along with the Platformer Heaters, which share a common convection section and a stack. They are the Hydrotreater Charge Heater (H-18), Hydrotreater Stripper Reboiler (H-19) and Depropaniser Reboiler (H-23). The heaters were running at 13,000 to 15,000 BPD charge rate. Client wished to revamp the heaters to 18,000 BPD capacity. Furnace Improvements (FIS) was employed to develop the best capacity improvement scheme for a #2 Platformer Heater and NHT Heaters. The conventional revamp option was to extend the existing radiant cells. The other option was to install a new heater for extra duty required. Both options require a big amount of space and high cost. Heater Existing Heat Revamped Extra Duty Duty Duty FIS’ recommendation was to increase the H-18 11.97 13.50 1.53 capacity of the heater based on FIS patented H-19 18.45 23.50 5.05 “Split Flow Technology”. The heaters were H-20 27.29 42.50 15.21 Revamping - TrainingH-21 – Troubleshooting 25.10 30.90 5.30 H-22 www.heatflux.com 21.70 23.10 1.40 H-23 15.15 17.40 2.25 Total 119.7 150.90 30.74
  • 12. Furnace Improvements Low Cost Solutions for Fired Heaters revamped for 18,000 BPD capacity and a design heat duty of 150.4 MMBtu/hr. The revamp cost was one fourth of the alternate design. The heater firing was limited to the design firing rate. The thermal efficiency of the heaters was increased from 80% to 89%. FIS Revamp consists of: • Replacement of Coils • New Burners and Radiant Floor • New Convection Section • Replacement of Stack Damper The heater was revamped not only for increased capacity but also for improved thermal efficiency and improved reliability. In addition to this, the Platformer Heater’s burners were replaced with new Ultra Low NOx flat flame burners and the calculated fuel consumption savings are $876,700 per year. Before Revamp After Revamp FIS carried out the entire scope of activities from conceptualization to commissioning of this heater revamp. The heater was successfully commissioned in November 2005 and has been Revamping - Training – Troubleshooting www.heatflux.com
  • 13. Furnace Improvements Low Cost Solutions for Fired Heaters running ever since. Client Valero Client Contact Mr. Steven Guillory Telephone (409) 948-7463 Location Texas City, TX ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 14. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 247 Combined Feed Heater The first new heater job by Furnace Improvements (FIS) was for a Corpus Christi refinery. The new vertical cylindrical heater is a combined feed heater with a natural draft. It is used to heat a mixture of hydrocarbon and hydrogen. The heater was designed for: • Absorbed heat duty - 40MMBtu/hr • Feed Flow Rate – 450,995 lb/hr • 6 Ultra Low NOx Burners • Efficiency - 82% FIS’ scope of services for this heater included design, engineering, fabrication, procurement, supply and project services. The heater was successfully commissioned in August 2005. Client CITGO Client Contact Mr. Ed De La Cruz Telephone (361) 844-5741 Location Corpus Christi, TX ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 15. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 248 Platformer Heater Capacity Improvement Project Furnace Improvements (FIS) was employed by a refinery in California to perform a capacity improvement on a Platformer Heater (H-70-01/02/03). The heater was originally built in 1979. It was designed for 12 MBPD and rated for 135.58 MMBtu/hr of heat duty and 84.03 MMBtu/hr of process heat duty. The heater was running at 13,000 to 15,000 BPD charge rate. Client was seeking to revamp the heater for 18,000 BPD and process heat duty of 113.01 MMBtu/hr and total heat duty of 160.86 MMBtu/hr. The design thermal efficiency of the heater was ~ 88% and was operating at 80- 81%. The stack temperature was higher by almost 300°F than design. The conventional revamp option was to extend the existing radiant cells. Extending the radiant cells has the following disadvantages: • Space limitation • Higher firing rates • Very high cost ( requires radiant tubes and new manifolds) FIS’ recommended increasing the capacity of the heater using our patented “Split Flow Technology”. Advantages of revamped design based on split flow are as follows: • Lower heat flux • Lower firing rates • No radiant section modification • No civil works Revamping - Training – Troubleshooting www.heatflux.com
  • 16. Furnace Improvements Low Cost Solutions for Fired Heaters Design Revamp Extra Duty Re-Rated Convection Heater Heat Duty Heat Duty Required Radiant Duty Duty Section MMBtu/hr 70-H-1 27.68 37.47 9.79 29.01 8.46 70-H-2 33.42 44.66 11.24 34.45 10.21 70-H-3 22.93 30.88 7.95 24.35 6.53 Steam 51.58 47.85 - - 47.85 Generation Total Process 84.03 113.01 28.08 87.81 25.2 Duty The overall heater efficiency was improved 9%. There was an increased heat duty by 28.08 MMBtu/hr, about 33% more than the original design values. The firing rate was well within the original firing rate. FIS carried out the entire scope of activities from conceptualization to commissioning of this heater revamp. The heater was successfully commissioned in February 2008. Client Valero Client Contact Mr. Pat Leyel Telephone (562) - 491-7256 Location Wilmington, CA ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 17. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 254 Crude Heater NOx Reduction Project A refinery has a Crude Heater (191-H-1) in its Atmospheric Vacuum Unit AVU-191. The heater was built in 1969 and designed for 160,000 BPD at a total heat duty of 490.7 MMBtu/hr. The heater was later revamped to process 178,500 BPD of crude and 31,500 BPD of slip stream at total heat duty of 612.4 MMBtu/hr. Furnace Improvements (FIS) was approached to modify the existing Crude Heater (191-H-1) to enable it to be retrofitted with a selective Catalytic Reduction Unit (SCR) to reduce NOx emissions to less than 0.010 lb/MMBtu. A new SCR and Waste Heat Recovery (WHR) are installed to accomplish these changes. FIS also performed the CFD analysis to ensure there is proper mixing of Ammonia with flue gases in the SCR unit and there is uniform distribution of flue gases over the catalyst bed. In the proposed option FIS designed the heater for 260,000 BPD at a firing rate of 727 MMBtu/hr (LHV). Crude feed to 191-H-1 is split into two streams: A hot stream (main crude charge) at 215,000 BPD, 456° F and a cold stream (slip crude stream) at 45,000 BPD, 240° F. The total absorbed heat duty of the Crude Heater is 672.2 MMBtu/hr. The WHR section is designed to reduce the flue gas temperature to 300° F as opposed to the current 350° F to 385° F. FIS’ scope included providing engineering services, designing equipment and supplying materials needed to modify the existing Crude Heater and auxiliary equipments. FIS’ scope included the supply of a new waste heat recovery unit, modify the existing heater convection, and upgrade of the FD and ID Fans. The new waste heat recovery is installed and connected to the new SCR and existing Crude Heater. Crude Heater Revamp The existing slip crude stream in the convection section has 24 rows. Fourteen rows are removed from service to achieve the required temperature window for SCR operation. The convection Revamping - Training – Troubleshooting www.heatflux.com
  • 18. Furnace Improvements Low Cost Solutions for Fired Heaters section is divided into two sections: lower and upper, by installing a new horizontal baffle plate. The plate acts as a barrier and forces the flue gases to exit from the lower section to the SCR, WHR and return to the upper section. The blanking plate is a new concept and it’s being done for the 1st time. This design saved our client between $5- $6 Million. Waste Heat Recovery Unit The Crude Heater (191-H-1) is supplemented with an outboard WHR unit. The unit is located downstream of the SCR unit. The heat transfer area was removed from the heater convection section to achieve the required temperature window. This was done to avoid condensation recovered in the WHR. The design slip crude flow rate through the WHR will be 45,000 BPD (560,000 lb/hr). The outboard WHR unit will heat slip crude stream from 240° F to 470° F. The calculated pressure drop across the WHR is 46.9 psig. The flue gas enters the WHR at a temperature of 700° F and leaves at 300° F. Soot Blowers Twenty-eight electric-motor driven soot blowers are provided in the WHR unit. The soot blowers are installed in the WHR to clean the surfaces for any ammonium bisulphate deposits resulting from the reaction of excess NH3 and SO3. FD & ID Fans The FD fans are upgraded to increase capacity and reduce the noise across the combustion systems. The fans are retrofitted with a new impeller, shaft, inlet vanes, inlet cones to match new rotor, inlet damper and silencer and intake hood. The motor is also being upgraded from a 400 HP to 500 HP motor. Similarly the four ID fans and motors are upgraded. Dampers There are a total of 16 dampers being provided in the Crude Heater. All the 16 dampers are replaced because they were not in working condition. The new dampers are installed at the existing damper locations. Finger Ducts & Expansion Joints New duct work is installed to the north side of the Crude Heater. The hot flue gas ducting is designed to optimally fit from the heater to the new SCR and also from SCR to WHR. The hot flue gas enters the duct, passes through the Ammonia Injection Grid (AIG) and enters the SCR. Expansion joints were also provided on each duct. Cold flue gas ducting was designed to fully integrate with the WHR system with the existing convection box (below the existing ID fans). The six cold flue gas ducts tie into heater above the blanking plate. Revamping - Training – Troubleshooting www.heatflux.com
  • 19. Furnace Improvements Low Cost Solutions for Fired Heaters Ammonia Injection Grid The new AIG was installed in the hot flue gas finger ducts. The AIG is located 10 ft from the heater casing. Ammonia is injected from the bottom through these pipes in the direction of the flue gas flow. NOx in the flue gases reacts with Ammonia over a catalyst to form Nitrogen and water vapor. Description Before Revamp After Revamp Total Heat Duty, MMbtu/Hr 612.4 672.2 Heater Efficiency (LHV), % 91 92.4 Stack Temperature, °F 350 – 385 300 NOx, lb/MMbtu < 0.01 lb/MMBtu The total cost of the project for design, engineering, fabrication and supply was $7 Million. Erection has been completed and the heater was commissioned in February 2009. Client ConocoPhillips Client Contact Mr. David Burkholder Telephone 504-656-3427 Location Belle Chasse, LA ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 20. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 255 Reactor Charge Heater (B-301) Capacity Increase Project A Port Arthur Refinery has a reactor charge heater in the GFU Unit. The charge heater is a vertical cylindrical heater built in 1981 with an air preheating system. It was designed for a total heat duty of 60 MM Btu/hr. Furnace Improvements (FIS) was employed in March 2005 to rerate the heater. The rerating was to be done with new process conditions to minimize the pressure drop. FIS rerated the heater for new process conditions using our patented “Split Flow Technology”. FIS also utilized the convectional series flow technology to minimize the pressure drop and hardware changes, therefore, overall minimizing project cost. FIS recommended rearrangement of the number of passes or the replacement of the radiant and convection sections. FIS carried out the entire scope of activities from conceptualization to commissioning of this heater revamp. The heater was successfully revamped in December 2006 and restarted operation in January 2007. The client is very pleased with the heater performance. Before Revamp Client Valero Client Contact Mr. Steve Henderson Telephone (409) 985-1135 Location Port Arthur, TX Revamping - Training – Troubleshooting www.heatflux.com
  • 21. Furnace Improvements Low Cost Solutions for Fired Heaters ••• Case Study 260 Capacity Improvement for Reactor Charge Heater (080-H-001) Furnace Improvements (FIS) was employed to carry out a capacity improvement of the Reactor Charge Heater (080-H-001). The client wanted to increase the process heat duty from 29.95 MMBtu/hr to 37 MMBtu/hr. The maximum firing rate limitation was 54 MMBtu/hr. This heater was originally built in 1965 as a natural draft all radiant heater. It was modified in 1980 to increase its thermal efficiency from 55% to 89% by adding a convection section for steam generation. The heater was operating at 85% efficiency. The revamp options to increase the capacity of the heater were: • Replace existing radiant coil and put in a new convection to preheat the process feed. • Revamp using FIS Split Flow Technology. In this option, the process feed is split and heated parallel in radiant and convections sections. The two parallel streams are then combined at the outlet. FIS revamped the heater, for increasing the processing capacity, using “Split Flow Technology.” Revamping - Training – Troubleshooting www.heatflux.com
  • 22. Furnace Improvements Low Cost Solutions for Fired Heaters Parameter Units Design Operating Revamp Total Absorbed Duty MMBtu/hr 47.63 55.48 42.4 Process Duty (Total) MMBtu/hr 29.99 37.68 37.01 Process Radiant Duty MMBtu/hr 29.99 37.68 25.01 Process Convection Duty MMBtu/hr - - 12 Total Fuel Firing Rate MMBtu/hr 53.47 64.83 49.87 Firebox Temperature °F 1540 1630 1511 Radiant Average Heat Btu/hr/ft2 11,820 14,850 11,480 Flux Advantages of the revamped design based on Split Flow are as follows: a) No radiant section modification – Existing tubes and supports can be used b) Steam generation system can be reused with minimum modifications c) Lowest cost d) Shortest turn-around time The heater is operating successfully after revamp. FIS carried out the entire scope of activities from conceptualization to commissioning of this heater revamp. Client Alon USA Client Contact Mr. Steve Mattingley / Mr. Jeff Broman Telephone (432) 263-9333/ (432) 263-9237 Location Big Spring, TX ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 23. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 263B N 744 Boiler NOx Reduction Project Furnace Improvements (FIS) was approached to convert a CO boiler in Unit 40 to be a standalone refinery fuel gas fired boiler, and reduce NOx emissions. The existing boiler was revamped into a fuel gas fired boiler with a maximum capacity of 400,000 lb/hr of steam @ 625 psig, 750 °F and reduced the NOx emissions down to 0.02 lb/MMBTU (16 ppm). FIS developed a heat transfer model of the boiler. Analyzed the performance of the boiler with NOx reduction and provided the client with various options for NOx reduction. They selected the option of ultra low NOx burners with external flue gas recirculation and steam injection into the burners. FIS scope of services included the following: • NOx Reduction System - Ultra Low NOx Burners and FGR Fan: The burners required about 16-17% FGR and 20,000 Lbs/Hr steam injection to reduce the NOx emissions to 0.02 Lb/MMBtu. FIS procured the FGR fan. FIS performed the CFD modeling of the ducting and combustion air – FGR mixbox to ensure that FGR and combustion air are thoroughly mixed before it enters the burners. FIS also performed the CFD modeling of the existing and new ultra low NOx burners to predict the overall combustion scenario, flame patterns, flame lengths etc. • New Economizer: The existing economizer was heavily fouled and the stack temperatures were running about 460 °F. FIS installed a new economizer which increased the efficiency of the boiler by 3%. The additional fuel savings due to increased efficiency will pay out the new economizer in about one year and six months. The lower stack temperature (310 °F) with the new economizer also reduced the size of the FGR fan. • Steam Super Heater Modifications: Revamping - Training – Troubleshooting www.heatflux.com
  • 24. Furnace Improvements Low Cost Solutions for Fired Heaters FIS performed the heat transfer modeling of the steam super heater and found that the existing heat transfer surface was inadequate and steam temperature will drop to about 680 °F after the revamp. FIS put additional heat transfer surface in the super heater to raise the temperature to 810 °F. • Firebox Modifications: FIS maximized the heat transfer surface in the firebox by sealing the CO ports with water wall panels, and removing the refractory from the floor and the roof. The additional heat transfer surface in the firebox increases the radiant heat duty and lowers the firebox temperature that also helps in reducing NOx to a little extent. • New Attemperator: The existing attemperator was not working. FIS installed a new attemperator to maintain a constant super heat temperature at all boiler loads. Description Before Revamp After Revamp Stack Temperature 460 °F 310 °F Boiler Efficiency (LHV) 87% 90 % Steam Temperature Out Of Boiler 700 – 730 °F 730 – 810 °F Steam Temperature after Not Working 730 - 750 °F Attemperator NOx < 0.02 Lb/MMBtu (HHV) This project was on a fast track. Engineering and procurement of all materials was completed in 10 months. The boiler was successfully commissioned in April 2008. Client ConocoPhillips Client Contact Mr. Steven J. O'Donnell Telephone (806) 275-1307 Location Borger, TX ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 25. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 266 Alky Heater (H-2) NOx Reduction and Efficiency Improvement Project Furnace Improvements (FIS) was hired to perform a turnkey NOx Reduction revamp on an Alky Unit Heater (H-2). The target NOx emission rate was 0.035 lb/MMBtu (HHV). The Alky Heater is a vertical cylindrical heater with a design heat duty of 55 MMBtu/hr. The heater efficiency was very low at 66%. Excess Oxygen in the firebox was very high at 8.5%. The heater floor was in bad shape. The heater did not have any stack damper for draft control. FIS’ scope included finalization of thermal design and engineering, procurement of material, fabrication, supply and field installation of the heater. FIS scope of services included: • Modification of Existing Floor: The existing floor was in bad shape, warped and needed to be replaced. The burners were fitted on smaller burner circle diameter to increase the reliability of the heater by minimizing the flame impingement. • Install Eight New Ultra Low NOx Burners (ULNB): FIS rerated the heater using ULNB to reduce NOx emissions. The burners are fired vertically upwards and the NOx emissions are 0.018 lbs/MMBtu. The burners were housed in a common air plenum with a central air intake. The air intake was provided with a pneumatic damper. • Install New Convection Module: Existing convection section efficiency was very low due to a high flue gas temperature Revamping - Training – Troubleshooting www.heatflux.com
  • 26. Furnace Improvements Low Cost Solutions for Fired Heaters leaving the section. The flue gas temperature decreased to 520o F from 680o F by replacing the convection section. FIS supplied and installed an upgraded convection section. • Installation of New Stack and Damper: FIS replaced the existing stack and installed O2 and temperature indicators for better control of the Oxygen levels and temperatures exiting the stack. The new stack was provided with connected ladders and platforms. The existing stack did not have a damper for draft control. The new stack damper is pneumatically operated. Minimum limit stop has been provided on linkage side of damper frame so as to prevent it from being fully closed. A position transmitter has been provided to know the damper opening position. The stack damper is provided to ensure that the draft at arch is maintained at the design level of (-) 0.1” WC under all operating conditions. Before After Revamp Revamp Duty (MMBtu/hr) 55 60 Efficiency (%) 66 86.2 Firing Rate (MMBtu/hr) 83.3 69.6 Energy savings ($/year) - 782,093 Payback Period (Years) - 1.72 After the revamp, the efficiency increased by 20%. The total cost of the project for the design services, engineering services, fabrication and installation was $1,560,000. The project payout was estimated to be less than 2 years. This heater was successfully commissioned in March 2008. Client ConocoPhillips Client Contact Mr. Hiren Yagnik Telephone (618) 255-2534 Location Roxana, IL ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 27. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 269 H-28 Vacuum Heater Performance Improvement Study A refinery was facing coking problems in their Vacuum Heater. In addition, they also wanted to revamp the heater to handle Canadian Crude and reduce NOx emissions. FIS did the process study and as a result of the study, the client decided to build a new Vacuum heater with an existing heater foundation. The new heater is 4 ft wider. This vacuum heater is a horizontal tube box with a convection section. It is designed for a heat duty of 43MMBtu/hr. FIS’ scope involves design, engineering, structural analysis and supply of this heater to the site. The heater has an efficiency of 90%. It was successfully commissioned in March 2009. The heater was delivered within 7 months of starting the job. A few months after the start up, FIS received the following feedback from the client. “.. we talked about the performance of the VF4 H28 heater since startup. It has been fantastic! The stack temperature is 370-380°F and the fuel gas usage has dropped about 40% from the old heater. This is one of the most • • • efficient heaters in the refinery. The NOx stack testing came back 0.026 lb NOx/MMBtu, which is also outstanding. They are even trying to reduce the O2 even lower, from 4% to 3%. It's a lot different when you have a tight firebox. Great job!!!” -Client Client ConocoPhillips Client Contact Mr. Hiren Yagnik Telephone (618) 255-2534 Location Roxana, IL Revamping - Training – Troubleshooting www.heatflux.com
  • 28. Furnace Improvements Low Cost Solutions for Fired Heaters ••• Case Study 279 Hot Oil Heater, Wyoming Furnace Improvements (FIS) was employed to perform an engineering study on a Hot Oil Heater (HT-501) at a gas plant. The heater was originally designed for a 25 MMBtu/hr duty. FIS analyzed the design and existing condition of the heater and developed these options: 1. Replacing the heater with a new vertical cylindrical heater. 2. Replacing the heater with a new cabin heater having the same plot area as of existing heater. 3. Revamping existing heater • Replacing the radiant coils, refractory and radiant tube supports. • Replacing the existing convection section with a new improved convection section. • Replacing burners The client opted for option 1 and awarded FIS with a contract for the turnkey supply of new Hot Oil Heater for their gas plant. FIS executed the heater process and mechanical design, structural analysis, material procurement, fabrication and installation of the Hot Oil Heater in 8 months schedule. FIS also supplied the burner management system and procured all the instrumentation controls of the heater. The heater was designed for an increased efficiency of 85% and it was commissioned in August 2007. Client Devon Energy Client Contact Mr. Craig Shaw / Mr. Richard Myal Telephone (307) 857-2291 / (405) 228-8895 Revamping - Training – Troubleshooting www.heatflux.com
  • 29. Furnace Improvements Low Cost Solutions for Fired Heaters Location Riverton, WY ••• Case Study 280 CDHDS Reboiler Heater (H-60) Efficiency Improvement Project Furnace Improvements (FIS) was employed to develop an efficiency improvement scheme for CDHDS reboiler heater (H-60). The CDHDS reboiler heater is a vertical cylindrical natural draft heater built in 2002. The CDHDS reboiler heater (H-60) was designed for a process duty of 72 MMBtu/hr, with a design efficiency of 81%. The heater was operating at an efficiency of 79%, with the flue gas stack temperature of 780°F. FIS reviewed the design and proposed the following changes to improve the efficiency: • Adding six rows of steam generation coil in convection section • New stack transition cone • 25 ft of stack extension In this scheme, 71,000 lb/hr of 450 # steam condensate is flashed to 150 # 2 phase, vapor-liquid stream. Flashing is completed before it enters the convection section. The total heat duty of the heater was increased to 82 MMBtu/hr. The extra 10 MMBtu/hr is absorbed in steam generation coil. Flue gas temperature leaving the stack was reduced at 400°F. The efficiency of the heater was increased to 90%, which brought energy savings of approximately USD $ 590,550 per year. The payback period is 1 year 3 months. This project has been successfully commissioned in October 2007. Revamping - Training – Troubleshooting www.heatflux.com
  • 30. Furnace Improvements Low Cost Solutions for Fired Heaters Client Valero Client Contact Mr. Steven Guillory Telephone (409) 948-7463 Location Texas City, TX ••• Case Study 283 Vacuum Heater Capacity Increase Project Furnace Improvements (FIS) was employed to conduct an engineering study for a refinery vacuum heater (200-H4) in Indiana. As part of their expansion project, the refinery needed to increase the capacity of a cabin vacuum heater. This heater was originally installed in 1949. FIS developed four modification options to increase the capacity of the vacuum heater. The client opted for revamping the radiant section coil, new burners and a new stack. With these modifications, the capacity of the heater was increased from 8,200 to 9,500 BPD. The Heater was successfully commissioned and is working with increased capacity since May 2008. Client CountryMark Client Contact Mr. Tariq Asrar Telephone (812) 833-3640 / (812) 838-8186 Location Mt. Vernon, IN ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 31. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 286 Hot Oil Heater Furnace Improvements (FIS) was employed to perform an engineering study on a Hot Oil Heater (H-3) in Roxana, IL. FIS submitted the design and was awarded a contract for the turnkey supply of new Hot Oil Heater for their BEU unit. The BEU Heater (H-3) is a natural draft, vertical cylindrical heater with a radiant section, convection section and stack. The heater is used to heat hot oil. The heater is designed for a total heat duty of 165 MMBtu/hr. FIS executed the heater process, mechanical design, structural analysis, material procurement and fabrication of this hot oil heater. The client requested an expedited delivery for this heater to meet their turnaround schedule. • This heater was delivered to the site within 9 months of receipt of order. • The fabrication was done to such an extent that there were no structural welds at the site. All the connections were designed to be bolted connections. • This is a 6 pass heater and radiant panels were designed for each pass to fit in each radiant panel. • The stack outside diameter is 11’ 3 5/8” and the height is 97’ 2”. This stack was shipped in two pieces, which were bolted at the site. This heater was succesfully commissioned in May 2009. Client ConocoPhillips Client Contact Mr. Hiren Yagnik Telephone (618) 255-2534 Location Roxana, IL Revamping - Training – Troubleshooting www.heatflux.com
  • 32. Furnace Improvements Low Cost Solutions for Fired Heaters ••• Case Study 287 CO Boiler Convection Replacement An Illinois refinery had a CO boiler in their Fluid Catalytic Cracking (FCC) Unit. The CO boiler was more than 40 years old. The CO boiler’s convection section is used to preheat the FCC charge and also generate superheated steam at 600 psig and 710°F. The boiler had three main problems: • Low economizer tube metal temperatures reaching dew point levels • High super heated steam temperature • Problems with tube supports in the hottest zone The refinery approached Furnace Improvements (FIS) to provide a new thermal design for replacing the convection section of the CO boiler. FIS conducted a detailed operation analysis of the existing CO boiler and built a model of the existing design. With the model built, we were able to simulate the current operating conditions and predict the heater performance for the future operating conditions. We developed a better design overcoming the drawbacks in the existing CO heater. The convection section was redesigned to: • Increase FCC feed flow CO Boiler Convection Section • Improve CO Boiler efficiency Replacement • Prevent cold end corrosion of Before After Item Units economizer Revamp Revamp • Eliminate flow distribution Process Heat Duty MMBtu/hr 81.55 104.91 problems Steam Heat Duty MMBtu/hr 100.90 115.92 Process Flow BPD 41,995 48,000 The new design was developed Stack Temp. °F 636 577 retaining the existing soot blower Efficiency % 68.0 72.6 locations and platform elevations. 0.55 Million* Fuel Savings $ / annum [ $3.0/MM Btu] It was estimated to save the client almost $550,000 per year. The project was successfully executed in February 2008. Client ConocoPhillips Revamping - Training – Troubleshooting www.heatflux.com
  • 33. Furnace Improvements Low Cost Solutions for Fired Heaters Client Contact Mr. Hiren Yagnik Telephone (618) 255-2534 Location Roxana, IL ••• Case Study 299 Convection Section Modification in CO (CCU-1 & CCU-2) Heater for SCR Installation A Refinery has CO heater (CCU/2) in their FCC unit. It is used to combust the FCC off gas (mainly CO gas) from the spent catalyst regenerator unit. The hot flue gases generated from combustion of FCC off gas are used to preheat the oil and generate super heated. The client was installing a new SCR unit downstream of the CO Heater as a part of the consent decree agreement to reduce the NOx emissions. The new SCR requires a specific flue gas inlet temperature, which will require reconfiguring the heat transfer surface in the convection section. FIS modeled the convection section for 5 proposed cases and provided a revised design. The proposed cases were so extreme in nature that it was very difficult to meet the flue gas temperature requirement for all the 5 cases for one design. So, FIS designed the last coil as a trim coil. The last coil will be use in service when the flue gas temperature exceeds the higher limit and it will be run dry when the flue gas temperature drops below the lower limit. FIS also provided a revised configuration for the oil pre heat coil to limit the oil outlet temperature below 730 Deg F to prevent coking. The client wanted the super heated steam temperature to be close to the design so FIS reconfigured the super heater surface and provided a revised design. The client approved FIS design to revamp the convection section. The project was successfully comissioned in August 2009. Client ConocoPhillips Client Contact Mr. Hiren Yagnik Revamping - Training – Troubleshooting www.heatflux.com
  • 34. Furnace Improvements Low Cost Solutions for Fired Heaters Telephone (618) 255-2534 Location Roxana, IL ••• Case Study 290 NOx Reduction of Six Fired Heaters Furnace Improvements was requested to develop a NOx reduction study on six heaters. The client wanted their NOx emissions to be reduced to 0.025 lb NOx/MMBtu. These heaters were also needed to be rerated for new operating conditions. FIS analyzed all the heaters thoroughly, evaluated different schemes and arrived at a conclusion of replacing the existing burners with Ultra Low NOx burners. • Platformer Heater (009-0920,30,40) • Preflash Reboiler Heater (004-0095) • Vacuum Heater (004-0096) • Cat Cracker Heater (007-0093) • Charge & Stripper Reboiler Heater (009-0910) • Charge Heater (012-0090) Preflash Reboiler The heater was built in 1979 as a vertical cylindrical heater with an absorbed duty of 25 MMBtu/hr and a feed rate of 135,827 lb/hr. Charge / Stripper Reboiler The heater was built in 1958 and was revamped in 1979 with 15 burners on the charge side and 13 burners on the Stripper reboiler side. The charge heater has an absorbed heat duty of 10.09 MMBtu/hr and a feed rate of 135,501 lb/hr. The stripper reboiler has an absorbed heat duty of 15.49 MMBtu/hr and a feed rate of 264,494 lb/hr. Platformer Heater Revamping - Training – Troubleshooting www.heatflux.com
  • 35. Furnace Improvements Low Cost Solutions for Fired Heaters The Platformer was built in 1979 on process requirements set forth by UOP. This Platformer Heater is a vertical arbor (“U”) tube heater with 3 radiant sections and a common convection section and a stack .The heater has an absorbed duty of 115.9 MMBtu/hr. • The numbers of burners will be increased from 30 to 52. Vacuum Heater Vacuum heater is a horizontal tube cabin heater built in 1995. The heater is designed for a feed rate of 351,000 lb/hr and an absorbed duty of 42 MMBtu/hr. This heater had high stack temperatures. • The numbers of burners will be increased from 6 to 9 burners. Charge Heater The heater was built as a vertical cylindrical heater in 1964, upgraded in 1979, and purchased, rerated and relocated from California to El Dorado refinery in 1993. The heater is designed for a feed rate of 26,930 BPD and an absorbed heat duty of 26.48 MMBtu/hr. Cat Cracker Heater The Cat Cracker was built as a vertical cylindrical heater in 1978. The heater was designed for a feed rate of 22,570 BPD and an absorbed heat duty of 40 MMBtu/hr. Client Lion Oil Client Contact Mr. Jeff Carr Telephone (870) 864 1240 Location El Dorado, AR ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 36. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 296 Hydrogen Heater Capacity Improvement Project Furnace Improvements (FIS) carried out a Hydrogen Heater (77-H-001) revamp project. The Hydrogen Heater is a vertical cylindrical heater, built in 1990. The heater was revamped in 2003, for a heat duty of 12.48 MMBtu/hr. The heater was operating at efficiency of 78% and an absorbed duty of 11.6 MMBtu/hr. The revamp heater design heat duty is 14.77 MMBtu/hr. Operating data analysis indicated the following: • Convection section fins are burned out/ fouled, resulting in higher flue gas temperature leaving the convection section. • Flue gas temperature leaving the convection section increases continuously with time. Currently, it is around 100ºF higher than the clean conditions flue gas temperature. The conventional revamp scheme (to preheat the feed in the convection section) resulted in very high fluid pressure drop. High fluid pressure drop was not feasible. FIS redesigned the convection section with FIS patented “Split Flow Technology”. In this scheme the feed was heated parallel in the convection and radiant section. The pressure drop across the heater reduced even at higher capacity, due to this parallel processing. Revamping - Training – Troubleshooting www.heatflux.com
  • 37. Furnace Improvements Low Cost Solutions for Fired Heaters Hydrogen Heater Data Comparison Item Units Design Operating After Revamp Capacity lb/hr 22,383 16,400 24,560 Absorbed MMBtu/hr 12.46 11.6 14.77 Duty Heat Release MMBtu/hr 16.82 14.9 17.17 Stack Temp. °F 796 790 478 Efficiency % 74.1 77.8 86 FIS carried out the entire scope of activities from conceptualization to commissioning of this heater revamp. The heater was successfully commissioned in May 2009. After revamp, the thermal efficiency of this heater increased from 78% to 86%. Client Alon USA Client Contact Mr. Steve Mattingley / Mr. Jeff Broman Telephone (432) 263-9333/ (432) 263-9237 Location Big Spring, TX ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 38. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 303 Capacity Increase and Efficiency Improvement in Naphtha Stabilizer Reboiler A Texan Refinery requested FIS to rerate the NSR for new process conditions. The natural draft heater is a vertical cylindrical with convection section and mounted stack. It had a heat duty of 8.6 MMBtu/hr with an efficiency of 83%. FIS observed that the firebox was small and volumetric heat release was high. The proposed process conditions weren’t feasible with the existing radiant section. Convection section temperatures were high and the stack height was limiting with the new firing conditions. FIS approach was to extend the radiant section and install a new radiant coil with 50% more radiant area. The heat duty increase to 10.8 MMBtu/hr and the efficiency went up to 88% giving fuel savings of US$270,000 per year. FIS worked on the design, detail engineering, fabrication and supply of the new convection section, stack and radiant coils. This project was completed in a fast track and it was successfully commissioned on September 2009. Client Alon USA Client Contact Mr. Steve Mattingley / Mr. Jeff Broman Telephone (432) 263-9333/ (432) 263-9237 Location Big Spring, TX Revamping - Training – Troubleshooting www.heatflux.com
  • 39. Furnace Improvements Low Cost Solutions for Fired Heaters ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 40. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 314 Capacity Increase for Naphtha Splitter Reboiler Service Furnace Improvements (FIS) was employed by a Refinery in Indiana to carry out a heat duty increase project for the Naphtha Splitter Reboiler service. Operating heat duty was around 11.74 MMBtu/hr. This was being supplied by Naphtha Splitter Reboiler Heater and by Platformer Heater Convection Coil. Naphtha Splitter Reboiler service heat duty needs to be increased by 5 MMBtu/hr. FIS reviewed the design and operating data for the Naphtha Splitter Reboiler heater (900-H-1) and modeled the heater operation. Any heat duty increase in this heater is not viable. FIS reviewed also the design and operating data for Platformer Heater (300-H1/H2/H3). In this heater there are 3 radiant cells and a common convection section. It is possible to shift part of the #1 Inter Heater duty to the radiant cell of the heater and use part of this convection coil to provide heat duty of Naphtha Splitter service. This will require an increase in the firing rate of the Inter Heater cell. It will need new burners of a higher capacity. Client has an Old Platformer Charge Heater (900-HXX). The heater was abandoned in the favor of the new Platformer heater (300-H1/H2/H3). The inspection of the Old Platformer Charge Heater from outside showed that it is in good condition. FIS proposes using this heater for providing the required heat duty requirement for Naphtha Splitter Reboiler service. FIS revamped the old Platformer Charge Heater adding a new radiant section with tubes and hangers and a small convection section. The stack was reused. The capacity was increase from 8.38 MMBtu/hr (Naphtha Splitter Reboiler) to 20.12 MMBtu/hr (old Platform Charge Heater). Revamping - Training – Troubleshooting www.heatflux.com
  • 41. Furnace Improvements Low Cost Solutions for Fired Heaters FIS scope of work includes process design, detail engineering, structural design, mechanical design, GA drawings, Shop fabrication drawings, erection and commissioning supervision. The heater was successfully commissioned in November 2009. Client CountryMark Client Contact Mr. Tariq Asrar Telephone (812) 833-3640 Location Mt. Vernon, IN ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 42. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 329 NOx Reduction and Capacity Increase of H-102 and H-205 Heaters FIS was employed by a texan Refinery to develop a NOx reduction study for Depantanizer Reboilers (H-102 and H-205). Client wished to reduce the NOx emissions from their heaters by installing Ultra Low NOx Burners. The targeted NOx emissions from these heaters are 0.035 lb/MMBtu (HHV basis). Both heaters are vertical cylindrical heaters with horizontal convection section and a top mounted stack. They are design for an absorbed heat duty of 33 and 46 MMBtu/hr. FIS performed the study and found out that the convection sections were fouled. FIS suggest to revamp the heaters with patented “Split Flow Technology” to increase capacity by 10%. FIS also suggest to install the ULNB with patented “inclined firing system” to eliminate fouling problems. FIS is currently working on this project. The heaters will be commissioned on beginning of 2011. Client Alon USA Client Contact Mr. Steve Mattingley Telephone (432) 263-9333 Location Big Spring, TX Revamping - Training – Troubleshooting www.heatflux.com
  • 43. Furnace Improvements Low Cost Solutions for Fired Heaters ••• Case Study 333 Capacity Increase on CDU-2; Crude & Vacuum Heaters (11/12-F-01) Furnace Improvements (FIS) was employed by an Indian Refinery at Visakhapatnam, to provide recommendations to increase the capacity of the Crude Heater (11-F-01) and Vacuum Heater (12-F-01) by 15%. The crude heater was commissioned in 1985 for a heat duty of 60 MMBtu/hr. The existing heater was operating at a thermal efficiency of around 83% which client wished to improve. The average flue gas temperature leaving the stack was around 342°C. This was 110°C higher than the design stack temperature of 230°C. The vacuum heater was commissioned in 1985 for a heat duty of 184 MMBtu/hr. The existing heater was operating at a thermal efficiency of around 83% and the client wished to improve the same. The average flue gas temperature leaving stack was around 308°C. This was 78°C higher than the design stack temperature of 230°C. The client was already planning to install a new in-kind convection section, new stack, and a new tight shut-off damper during the forthcoming shutdown. FIS analyzed the design of the Crude Heater (11-F-01) and developed a scheme to increase the capacity and improve the efficiency of both Heaters. FIS proposed to add a new convection section below the new-in kind convection for both heaters. The proposed Revamping - Training – Troubleshooting www.heatflux.com
  • 44. Furnace Improvements Low Cost Solutions for Fired Heaters convection will increase the absorbed duty across the convection and will help in reducing the stack temperature to around 276°C in crude heater and 165°C for vacuum heater. The results in both heaters were:  Capacity Increase by 15%  Heat duty Increase by 15%  Efficiency Improve to >90%  Stack Temperature reduction The heaters were successfully commissioned on July 2010. Client HPCL Client Contact Mr. S. Bharathan Telephone (+)91-891-2894814 Location Visakhapatnam, India … Revamping - Training – Troubleshooting www.heatflux.com
  • 45. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 335 Platformer Heaters Capacity Improvement and NOx Reduction Project Furnace Improvements (FIS) was employed to re-rate Heater process using Low NOx Burners and increase the Capacity on Platformer Heaters (H-4 / H-5). The heaters were originally built in 1959. The heaters were changed to forced draft in 1977. Common air pre- heater, induced draft and forced draft fan were added to pre-heat the combustion air. Process fluid is heated in radiant sections. Convection section is used for steam generation. Heaters design capacity is 32 MBPD. The client wanted to revamp the heaters for a higher capacity of 40 MBPD. The conventional revamp option has following disadvantages: • Very high cost • Requires large size manifolds and piping • Total pressure drop was very high FIS’ recommended increasing the capacity of the heater using our patented “Split Flow technology”. Advantages of revamped design based on split flow are as follows: • Lower heat flux • Lower firing rates • Lower pressure drop • No radiant section modification Revamping - Training – Troubleshooting www.heatflux.com
  • 46. Furnace Improvements Low Cost Solutions for Fired Heaters Design Heat Revamp Heat Extra Duty Heater Section Duty Duty Required MMBtu/hr Process Duty H-4 73.8 82.7 8.9 H-5 72.0 80.5 8.5 H-6 37.5 42.1 4.6 Total 183.3 205.3 22.0 Steam 80.5 51.4 - Generation Firing Rate 292.2 283.7 (-)8.5 The process heat duty increased by 22.0 MMBtu/hr. The revamp heaters firing rate shall be 8.5 MMBtu/hr lower than existing design. The new design reduces the air preheat temperature to 270°F from operating temperature of 600-700°F. FIS carried out the entire scope of activities from conceptualization to commissioning of these heaters. The project is currently in the execution phase. It is schedule to be commissioned on first quarter of 2011. Client ConocoPhillips Client Contact Mr. Hiren Yagnik Telephone (618) 255-2534 Location Roxana, IL ••• Revamping - Training – Troubleshooting www.heatflux.com
  • 47. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 338 Performance Improvement Project on 3 Platform Heaters A Wyoming Refinery approached Furnace Improvements (FIS) to carry out an engineering study for a capacity increase of 3 platformer heaters. The three heaters (H-1003/4/5) were built by Radco in 1990 and were relocated in 2006 to the Refinery. The middle heater (#1 Reheater) has a common convection and stack for all three heaters.These heaters are draft limiting. The heaters are not able to achieve the desired throughput. FIS analyzed the existing design data and drawings of the Heaters (H-1003/4/5). The observations are as follows: • The existing heaters are deficient in design. Arch pressure is positive on all three heaters at design conditions. The arch pressure is (+)0.603 in WC, (+)0.103 in WC and (+)0.123 in WC for H-1003, H-1004 & H-1005 heaters respectively. In this study, FIS proposes 5 recommendations for the revamp of Charge Heater (H-1003), #1 Reheater (H-1004) and #2 Reheater (H-1005). The recommendations are based on improving the draft in all the three heaters. FIS also proposes a recommendation for increasing the capacity of the heaters to the target capacity. Revamping - Training – Troubleshooting www.heatflux.com
  • 48. Furnace Improvements Low Cost Solutions for Fired Heaters Client chose the stack modification as a revamp option. FIS carried the following major modifications: • The existing stack and transition cone shall be replaced with a new stack and new transition cone. • The new stack shall be wider and taller than the existing stack. The new stack length shall be 95 ft and 7’-6” outside metal diameter. • The new stack will have new dampers (4 blades) and platforms. FIS scope of work included process design, detail engineering, structural design, mechanical design, GA drawings, Shop fabrication drawings, and supply of new transition cone, stack and platforms. Client Sinclair Client Contact Mr. Mike Palumbo Telephone (307) 328-3549 Location Casper, WY … Revamping - Training – Troubleshooting www.heatflux.com
  • 49. Furnace Improvements Low Cost Solutions for Fired Heaters Case Study 339 Capacity Improvement for FRE-APS and FRE-VPS Heaters (31/32-F-01) FIS carried out a Crude Heater Capacity Improvement project for an Indian Refinery in Mumbai. The Client wanted to increase the heater capacity by 15% with a thermal efficiency of more than 90%. FIS proposed addition of a small convection section on top of the existing heater convection section and addition of burners to the heater. The convection section had a coil for vacuum heater as well and the capacity of vacuum heater was increased by 15% too. The study was carried out in 2 weeks and the detail engineering was carried out in 8 weeks. The heater was successfully commissioned on May 2010. Client HPCL Client Contact Mr. Anamitra Upadhya Telephone (+)91-22-25076496 Location Mumbai Revamping - Training – Troubleshooting www.heatflux.com
  • 50. Furnace Improvements Low Cost Solutions for Fired Heaters … Revamping - Training – Troubleshooting www.heatflux.com