SlideShare a Scribd company logo
Page 1 of 13
gasnetworks.ie
Guidelines for
Designers and Builders -
Domestic Sites
Page 2
1	 General Information and Single Occupancy Dwellings
1.1	 Introduction		 4
1.2	 How a Gas Meter is Installed		4
			 General rules	 4
1.3	 Self-Trenching Information	5
			 Gas Mains		 5
			 Gas Connection Pipe (Service Pipe)		 5
1.4	 Excavations Parallel to Walls	6
1.5	 On Site Requirements		 6
1.6	 Gas Safety on Building Sites		7
			 Do’s and Don’ts on Building Sites	 7
1.7	 Building Line		 8
1.8	 Meter Location		 9
			 Where to locate your meter	 9
			 Where not to locate your meter	 11
1.9	 Meter Box Types		 11
1.10	 Meter Box Dimensions		 12
			 Surface Mounted Meter Box with Ventilation	 12
			 Recessed Meter Box with Ventilation	 13
1.11	 Recessed Meter Box in Pillar Enclosure	14
1.12	 Foundation Requirements for Preformed Bend below ground	15
1.13	 Meter Box Internals		 16
1.14	 To-Do list Before a Meter can be Fitted	16
1.15	 Wayleave	16
			 When is a wayleave required?	 16
2	 Multi – Occupancy Dwellings
2.1	 Multi- Occupancy Dwellings - General	18
	 		 Multi-Occupancy Definition	 18
	 		 Multi-Meter Definition	 	 18
			 General Meter Requirements	 18
			 Installation up to the Meter	 18
2.2	 Option 1: External Multi – Meter Location	 19
2.3	 Option 2: Internal Multi – Meter Location - Above Ground Level	 20
			 Variation A: Meters in Common Areas	 20
2.4	 Option 2: Internal Multi–Meter Location - Below Ground Level	 21
			 Variation B: Underground Car Park or Open Basement	 21
				 Type 1: Top Entry Cabinets pre-fabricated off-site	 21
				 Type 2: On- Site Fabricated Meter Manifold.	 22
2.5	 Multi – Meter Compartment Types	23
	 		 Pre-Fabricated Meters		 23
			 Purpose Built Meter Compartment	 24
2.6	 Internal Building Dimensions for various Meter Bank Configurations	 25
3	 Conclusion & Appendices
3.1	 Checklist of Essential Information required by Design	28
3.2	 Irish Standards		 29
3.3	 Appendix - Excavations Parallel to Walls		29
Contents
Guidelines for Designers and Builders - Domestic Sites
Page 3 of 13
Siteworks Activities Manual 	
MANUAL No. AO/MN/002	 Rev. 0	 Date: February 2015
Guidelines for Designers and Builders -
Domestic Sites
1 General Information
and Single Occupancy
Dwellings
Guidelines for Designers and Builders - Domestic Sites
Section 1 - General Information and Single Occupancy Dwellings
Page 4
1.1 	 Introduction
This guide outlines the permitted locations, positions, safe depths and distances the installation of your natural gas
meter and meter box when connecting to the natural gas network.
It is designed to give guidelines for designers and builders on development sites with domestic and commercial
loads. The preferred location for Gas Networks Ireland (GNI) to locate the gas meter is externally. This is to allow
for ease of meter reading, maintenance and operation assurance. However a meter can be located internally if it
is not possible to locate it externally and if the gas is being supplied at a low pressure of 100mbar or less. For more
information on locating meters internally please consult the Industrial and Commercial Sites Booklet of this Technical
Manual.
Note: For bespoke architectural solutions or for projects requiring meters located internally please contact your
local Gas Networks Ireland sales representative.
This document is to be used for guidance purposes and references the Irish installation standards for natural gas I.S
813 (Domestic) and I.S 820 (Non- Domestic) as well as I.S. 329 “Code of Practice for Gas Distribution Mains” and I.S.
265 “Installation of Gas Service Pipes”. However it must not conflict with or be used as a substitute for the standards
should any conflict arise, the Irish standards take precedence.	
1.2 	 How a New Gas Meter is Installed
A GNI approved contractor will lay and test the gas connection pipe/
service pipe in the pre-excavated trench provided by the builder and
a top tee connection is made to the main in the path or road as
appropriate. The gas connection pipe shall have sand surround and
be reinstated as soon as practicable in order to reduce the
possibility of external damage on site. Normally 32mm (low
pressure) size polyethylene connection pipe and 25mm (medium
pressure) size polyethylene connection pipe is used.
A gas connection pipeline is laid by Gas Networks Ireland
connecting a building to the natural gas network. The natural gas
connection pipeline must be laid in a straight line to the meter
location, using the shortest most direct route and where possible
at right angles to the gas main. An illustration of this is shown in
figure 1.
Marker tape should be placed over all gas mains, gas connections
and ducting intended for gas distribution pipes.
	
General Rules
It must also be laid with a minimum of 600mm of ground cover. The proposed route of the connection pipe must be
clear when the crew arrives to carry out the work, otherwise it cannot be installed.
If the meter box is to be attached to the property wall then it must be located above the damp proof course at a
minimum of 300mm above finished ground level. A meter should not be placed within 150mm below or beside an
electricity meter.
Gas Distribution Mains
Service Top Tee
Gas Service min
600mm cover
Customers
downstream
pipework
Pavement
Roadway
GRP box containing gas meter
and pressure regulator
Figure 1: Connection from Gas Main to Residential Meter Box
Page 5
1.3 	 Self-Trenching Information
This sections illustrates how trenches should be prepared correctly before Gas Networks Ireland arrives on site.
There are different excavation requirements depending on the type of pipe that is installed i.e. gas main or gas
connection pipe / gas service.
Gas Mains
Trenches excavated for a gas main must allow for:
Sand Bed & Surround:
A 100mm bed of sand (150mm if in rock) shall be provided and installed by the customer and shall be in place before
the GNI contractor crew is required on site.
Depth (on day of installation):
	 •	 A minimum cover of 750mm to the crown/top of the pipe in roadways.
	 •	 600mm minimum cover is required beneath footpaths or landscape areas, but 750mm if trafficked.
	 •	 Gas mains must not be laid deeper than 1.2 metre unless specified and agreed in advance with Gas 	
		 Networks Ireland.
Width:
	 •	 The total trench width must be 300mm in addition to the outside diameter of gas pipe.
	 •	 A minimum of 150mm of sand must surround the gas main.
Gas Connection pipe (Service Pipe)
The gas connection pipe will be laid in a straight line to the meter location, as perpendicular to the gas main as
possible. Therefore the trench for this gas connection pipe must be excavated in a straight line. All trenches for
gas connection pipes must be excavated to allow for:
Sand Bed & Surround:
A 100mm bed of sand (150mm if in rock) shall be provided and installed by the customer and shall be in place before
the GNI contractor crew is required on site.
Depth:
	 •	 A minimum cover of 600mm for each gas connection pipe up to 1.5 metres from the meter box.
	 •	 Depth can reduce to a minimum of 375mm at the base of the GRP sleeve within the 1.5 metre distance at 	
		 the meter location only.
Width:
	 •	 The gas connection trench width should be a minimum of 300mm in addition to the outside pipe.
	 •	 A minimum of 150mm of sand should surround the gas service.
N.B. Contractors/Builders must provide their
own sand surround and reinstatement material.
The main or connection//service pipe must be
covered in surround before the Gas Networks
Ireland contractor leaves the site. The trench
must be reinstated as soon as possible after the
pipe is laid to reduce the possibility of damage
to the gas pipes.
Figure 2: Recommended gas main layout in a footpath/roadway
Guidelines for Designers and Builders - Domestic Sites
Section 1 - General Information and Single Occupancy Dwellings
Page 6
1.4 	 Excavations Parallel to Walls
When excavating trenches parallel to a wall, the stability of the wall, must be checked. This is in case walls have not
been adequately designed, altered, degraded over time or may now be used for an intention that they were not
designed for.
Care must be taken with excavation work and a risk assessment carried out if the wall is leaning, cracked or showing
any signs of instability or distress.
The stability of the wall should be checked whenever:
	 •	 the edge of a gas connection/service trench is within 0.5 m of the wall;
	 •	 the edge of a mains trench is within 1m of the wall, or
	 •	 the main is larger than 200 mm nominal diameter,
	 •	 or the main or service is to be laid at a depth greater than normal.
Please see the diagrams and further information relating to safely excavating parallel to walls in the Appendix
section.
If there are any queries relating to excavating parallel to walls please contact customer service at 1850 200 694.
1.5 	 On site Requirements
	 •	 The gas main should never be placed in an inspection chamber with other utilities, services, drainage/	
		 sewage systems.
	 •	 A distance of 300mm must be provided when a gas main is placed adjacent to an inspection chamber (see 	
	 	 figure 3)
	 •	 A minimum clearance of 300mm is required where necessary to cross or run in close proximity to any 	
		 other utility service.
	 •	 A distance of 600mm must be provided from high voltage cables and district heating pipes.
	 •	 No other services/utilities is to be placed over the gas main/service
	 •	 Gas Networks Ireland will not insert the service pipe in a sleeve or duct.
Note:
Please ensure the distance from the trench to the wall (S), is greater than the depth of the trench (H).
Note:
•	 Polyethylene mains and services may not be positioned within the Building Line (as defined by I.S. 329 / I.S. 265).
•	 For more detailed information always refer to the Gas Networks Ireland Distribution drawings specific to the project.
ng information
properties
Bord Gáis or
ctor in a pre-
the builder.
the purpose
n must allow
0mm + pipe
not be laid
0mm unless
total trench
ide diameter
and 150mm
e gas main
provided by
reinstated as
main is laid,
damage on
as main in a
Boundry Wall
300
Elec/Telecom
Ducts
150mm Compacted
Sand Surround
Gas Main
250min
Water Main
300mm
Granular Material
to DOE spec.
Clause 804
750mm minimum cover required
beneath roads
650mm minimum cover required
beneath footpaths and landscaped areas
Marker Tape
d by Bord Gáis or a Bord Gáis appointed contractor in a pre-excavated trench provided by the builder. The gas
line to the meter location, as near perpendicular to the gas main as practicable. The trench for the gas service
excavated to a depth to allow a minimum cover of 600mm for each service. In the case where the service
tes 2), 600mm minimum cover is required up to 1.5 metres from the meter box. Required cover shall reduce
e base of the GRP sleeve within the 1.5 metre distance (note fig. 3). Sand 150mm minimum shall surround
einstatement provided by builder). The service trench width shall be a minimum of 300mm. Where ducts are
s.
he gas main
on chamber
or drainage
of 300mm
gas main is
on chamber
vices may
e Building
/ I.S.265).
on, always
bution
oject.
Fig.1 Recommended Layout of Gas Main in a Footpath.
Fig.2 Safety Precautions with regards to Inspection Chambers.
Note: Other services/ducts must not be laid on top
of gas mains/services
Section Drawing
Telecom
Duct
Electrical
Duct
Gas
Main
Water
Main
Gas
Main
Water
Main
Inspection
Chamber
(Manhole)
Inspection Chamber (Manhole)
Telecom
Duct
Electrical
Duct
Gas
Main
Water
Main
Gas
Main
Water
Main
Inspection
Chamber
(Manhole)
Inspection Chamber (Manhole)
300mm
min
✕Figure 3: Safety precautions with regards to inspection chambers.
Page 7
1.6 	 Gas Safety on Building Sites
After the initial project planning stage and when a site is in progress the following safety guidelines should be
adhered to:
Do
•	 Ensure all excavations are carried out in accordance with the H.S.A Code of Practise: Avoiding Danger from	
	 Underground Services. i.e. use of maps/records, identification of pipe locations & safe digging practises.
•	 Maintain accurate on-going records of all gas mains and services laid on your site.
•	 Ensure all site personnel adhere to any exclusion zones while mains/services are under test on site.
•	 Make all operatives, including sub-contractors, aware of the presence and location of gas mains and services.
•	 Provide a safe and suitable location for the storage of gas pipes and materials
•	 Ensure that any necessary trial holes are dug carefully by hand.
•	 Ensure any personnel excavating in an area containing already existing gas mains have obtained Gas Networks 	
	 Ireland maps.
•	 Report any damage, no matter how slight, to the Gas Networks Ireland 24 hr Emergency Line 1850 20 50 50.
•	 Ensure meter cabinet is securely fitted without compromising its structural integrity.
•	 If there is a natural gas transmission pipeline on your site you must contact Gas Networks Ireland for specific 	
	guidance.
Do not
•	 Interfere with stored gas pipe or materials.
•	 Attempt to cut or un-band coils of Polyethylene (PE) gas pipe, this can only be done by gas personnel. These coils
	 contain a lot of stored energy and can cause serious injuries if interfered with.
•	 Use PE gas pipe for any other purpose, e.g. ducts, sleeves, drains.
•	 Use mechanical excavators within 1m of a gas main.
•	 Use hand held power tools, i.e. jack hammers within 0.5m of a gas main.
•	 Carry out piling work within 15m of a gas main without prior consultation with Gas Networks Ireland.
•	 Welding or hot works should not be carried out in the vicinity of an exposed gas main without prior consultation 	
	 with Gas Networks Ireland.
•	 Attempt to repair any damage to a gas main or service.
•	 Do not interfere with the meter cabinet and its structural integrity.
Guidelines for Designers and Builders - Domestic Sites
Section 1 - General Information and Single Occupancy Dwellings
Page 8
1.7 	 Building Line
Explanation and Illustration
The building line is considered the outermost extent of the building structure (archway, balcony or basement)
projected vertically on to ground level.
Gas mains, services and meters transporting gas at pressure greater than 100mbar are not permitted inside the
building line of occupied premises.
Under certain circumstances however Gas meters can be positioned inside the building line:
	 •	 The gas pipework must have a pressure of 100mbar or less.
	 •	 And there must be no available option of locating the meter externally.
	 •	 Polyethylene pipework may not be located within a building or in a space that may be potentially enclosed 	
		 at a later stage e.g. an open porch.
In figure 4 below the exclusion zone is illustrated by a dotted line:
	 •	 This exclusion zone on the left ends in line with the porch at the gable wall.
	 •	 The exclusion zone shown on the right is further out as this porch/balcony/building overhang is said to be 	
		 attached to the building.
For any queries relating to the building line/exclusion zone call 1850 200 694.
	
Figure 4: Exclusion zone drawing
	 •	 Meter box is not permitted within the porch/building overhang.
	 •	 Meter box and service installations shall be in accordance with I.S. 265 and I.S. 813.
	 •	 The gas meter box shall be greater than 300mm away from a flue.
	 •	 Meter box shall not be placed more than 2 meters from the gable end of the property.
√
√
√
√
Porch/Balcony
Building Overhang
3
4
2
1
Gable Wall Screen Wall Option
2m
max
300mmmin
300mmmin
Note:
Meter not allowed in porch or
inside the exclusion zone
Exclusion zone
Page 9
	 •	 A minimum separation of 300mm from the service pipe of the gas meter to the service pipe of the ESB
		meter
	 •	 A minimum separation of 150mm from the gas meter box to the ESB box, a minimum separation of
		 400mm from an electrical distribution board and 300mm from the gas service to any other services.
1.8 	 Meter Location
Where to locate your meter
Figure 5 Minimum separation between Gas and other meters Figure 6 Minimum separation from the Gas Meter box to the
Electricity meter
Figure 7 Diagram of possible Meter Locations for a domestic property.
E.S.B.
Electricity
Service Pipe
150mm
Gas
FH. T.V.
300mm
300mm min.
Guidelines for Designers and Builders - Domestic Sites
Section 1 - General Information and Single Occupancy Dwellings
Page 10
At the front
gable end wall,
a maximum of 2
metres from the
front corner of the
building. Fig 8.
On a nib wall.
Fig 10.
On the wall that
separates
neighbours. Fig.11
i.e. boundary wall.
Figure 10 Meter box on nib wall Figure 11 Meter box between neighbours wall
On either side of the
door, Figure 13.
Note: This may
require impact
protection.
Figure 12 Meter box either side of the window Figure 13 Meter box on either side of the door
The meter box should be accessible from the front of the house. The previous figure 7 gives examples of where the
meter box can be placed:
Figure 8 Gable end of property
At the front wall of
the building – on
either side of the
front door, or on
either side of a
sealed window.
Fig 9.
Note: This can’t be
fitted directly below a
window.
At the front wall of
the building – on
either side of the
front door, or on
either side of a
sealed window.
Note: This can’t be
fitted directly below a
window.
Figure 9 Meter box either side of the window
Page 11
Where not to locate your meter
The meter box must not be placed:
•	 At the back of the house or behind a gate.
•	 Directly above or below an electricity meter.
•	 Directly above drains, airbricks, manholes, or an electricity meter.
•	 Directly under appliance vents, windows that open or an electricity meter.
•	 In a porch or under an overhang which is enclosed or could be enclosed.
•	 Where it is liable to cause an obstruction or be subject to vehicular damage.
•	 Where access to the meter box may be restricted in an emergency e.g. narrow path.
•	 On a stone boundary wall or stone garden wall.
•	 Adjacent to an electricity meter, if there is a suitable practical location for it elsewhere.
For any queries relating to meter box location please call 1850 200 694.
1.9 	 Meter Box Types
There are two types of meter boxes – surface mounted and recessed.
A surface mounted meter box is installed on the property or boundary wall as shown in figure 14. This meter box
is more suitable for installation on older buildings converting to natural gas. The meter box will be provided by Gas
Networks Ireland and will be fitted at a minimum of 300mm above finished ground level. The meter box will project
approximately 250mm outwards from the wall.
A recessed meter box is installed in the cavity wall of a building or in a pillar enclosure as shown in figure 15. This
type of meter box is generally installed by a builder in a new one-off build or as part of a new extension. The box
must be purchased from a building supplier and is not provided by Gas Networks Ireland. If this type of meter box is
damaged, Gas Networks Ireland will be unable to install the meter for safety reasons. The meter box must be built
into the wall, secured and unpunctured as per manufacturer’s instructions. The meter box will project appoximately
100mm outwards from the wall.
	
Figure 14 Surfaced Mounted Type Meter box Figure 15 Recessed Type Meter Box
Guidelines for Designers and Builders - Domestic Sites
Section 1 - General Information and Single Occupancy Dwellings
Page 12
1.10 	 Meter Box Dimensions
The following diagrams give dimensions for both types of meter boxes, surface mounted and recessed.
Surface Mounted Meter Box with ventilation
The new and improved surface mounted meter boxes are slimmer with additional vents that ensure it is not as
obtrusive as previously.
The addition of the cut-out to the cover will allow the cover to be closed securely, if the outlet pipe is sitting proud of
the groove in the base plate. This shall allow some additional flexibility in the location of the outlet pipe and for the
meter box cover to be secured correctly with the retaining screw.
Figure 16: New cut outs at outlet pipe and inlet pipe
Accordingly, the outlet pipework should not interfere with the closure of the meter box cover, and the retaining screw
and nut are to be secured after completion of any works.
Figure 17: Dimensions of surface mounted meter box with vents
Inlet vent
Cross
sectional
view
New outlet vent
225
489
231.5
173
404
404
Page 13
Recessed Meter Box with ventilation
Figure 18: Recessed type meter boxes with vents
Note: The meter box must not be punctured when recessed into cavity walls or voids.
Recessed meter boxes and replacement doors may be sourced from your local builder provider. A list of suppliers
can be provided by calling 1850 200 694.
Recessed Box:
140mm
210
535
510
409
365
339
595
535
510
Guidelines for Designers and Builders - Domestic Sites
Section 1 - General Information and Single Occupancy Dwellings
Page 14
1.11 	 Recessed Meter Box in Pillar Enclosure
The following drawings illustrate how a meter box would be recessed in a pillar enclosure.
Note: The meter box MUST NOT be punctured when recessed into cavity walls or voids.
Figure 19: Meter box in pillar enclosure
6mm m.s. Plate
for Brick Support
600
A
DPM
F.G.L.
Service
pipe
ELEVATION
Concrete
base
713
300
A
B
B
Meter boxes
secured to
brickwork
Voids to be
mortar
filled
SECTION A - A
440
Recessed Meter Box
Expanded metal
reinforcement
to be used every 3rd course
Figure 20 Meter box in pillar enclosure
Page 15
1.12 	 Foundation Requirements for Preformed Bend Below Ground
There are specific requirements for a preformed bend that is placed below ground. The below figures illustrate these
requirements.
The minimum depth of cover is 600mm along the entire length of the connection pipe to within 1.5m of the building
line, rising (within 1.5m of the building line or, if moling, in the exit pit) to 375mm at the preformed bend. Figures 21
and 22 show this 375 minimum depth of cover to the preformed bend.
Note: To accommodate the preformed bend the minimum depth of required cover to the top of the foundation is 450mm.
Meter box shall not be placed more than 2 meters from the gable end of the property.
Figure 21: Connection pipe with preformed bend attached to Mains showing minimum level of Cover and Foundations required.
Figure 22: A minimum cover of 375mm and minimum foundation of 450mm are necessary
P/E SDR 11
gas main
450 Min
Foundation
Level
375mm
Min Level
Of Cover
1500mm
32/25mm P/E
connection pipe
600mm Min
Level of Cover
Min 600mm
Cover to
this Point
Gas Meter Box
Min 1500mm
Min 450mm
Foundation
Level
Min 375mm
cover
300 mm
Guidelines for Designers and Builders - Domestic Sites
Section 1 - General Information and Single Occupancy Dwellings
Page 16
1.13 	 Meter Box Internals
Once the connection is finalised, Gas Networks Ireland Distribution Operations will install a meter either surface
mounted or recessed similar to figure 23 with a regulator and gas meter in the meter box as shown in figure 24.
1.14 	 To-do list Before a Meter can be Fitted
However before the meter can be fitted the following criteria must be satisfied.
	 •	 Customer must have opened an account with a preferred supplier.
	 •	 An appointment has been made with a Natural Gas Supplier to connect the meter.
	 •	 When the Gas Networks Ireland meter installer arrives to site, an accurately completed Declaration of 	
		 Conformance must be available for collection (signed by a Registered Gas Installer).
Once all of the above is in place and a visual inspection is satisfied, meter is fitted and gas is made available.
1.15 	 Wayleave
Gas Networks Ireland has statutory powers to acquire a wayleave by CPO under Section 32 of the Gas Act, 1976. A
wayleave once acquired, either by Deed or CPO, becomes a burden on the title of the land and affects all assigns/
successors. CPO’s and completed Deeds of Easement are registered in the Property Registration Authority of Ireland
or Registry of Deeds as appropriate. The Deeds provide safety protection on the land for GNI and also entitlements
for future development.
When is a wayleave required?
	 •	 Pipelines or Services that traverse private lands to connect new customers.
	 •	 Private housing estates that are not taken in charge by the Local Authority.
	 •	 The requirement exists to supply gas to more than one customer.
Note: If a Wayleave is required, the project designer(s) and builder must assist in supplying all relevant information (i.e. land
ownership) to GNI.
Figure 23: Recess Meter box Figure 24: Recessed Meter Box Internals
Registered Gas Installer: A registered gas installer is an installer or service engineer, who has completed the
required gas installation safety training and who has the necessary insurance to carry out gas installations to
the legal standard.
2 Multi-occupancy
Dwellings
Guidelines for Designers and Builders -
Domestic Sites
Guidelines for Designers and Builders - Domestic Sites
Section 2 - Multi-Occupancy Dwellings
Page 18
2.1 	 Multi-Occupancy Dwellings - General
Multi-Occupancy Definition
Multi-Occupancy dwelling: A building containing more than two dwellings units. A multiple dwelling can be any of the
following:
	 •	 A purpose built apartment building
	 •	 An existing single dwelling modified to accommodate a number of separate dwellings
	 •	 Dwelling units contained in a mixed use building e.g. shops / offices downstairs with dwelling units above
Note: A Multi-Occupancy dwelling can be serviced by an individual meter to a plant room that connects each dwelling
or a separate meter to each single dwelling.
Multi-Meter Definition
Meter cabinets/manifolds which contain a number of meters are considered multi- meters and are used for multiple
dwellings in a building which contains more than 2 dwelling units.
General Meter Requirements
Note: In all of the following cases in multi-occupancy dwellings, please contact Gas Networks Ireland at the
earliest opportunity to provide the optimum design solution for your project.
The meters must be positioned for easy access to, reading or removal. The design or location must protect the meter
and its connections against the possibility of corrosion. Meters must not be located where they may be exposed to
extreme temperatures or ignition sources (e.g. switch gear). Ventilation of pipework will have a minimum of ½ air
change per hour. Pipework and connections to meter must be located at least 0.5 metres away from any electrical
equipment or effective ignition sources.	
Installation up to the Meter
Gas Networks Ireland provide and lay all external underground gas mains, and gas connection pipework up to the
point of the meter location.
The preferred location of meter cabinets or compartments is in an enclosure, external to the building outside the
building line. Locating meters internally within the building line is only possible when:
	 •	 it is not feasible to locate meters externally
	 •	 and natural gas mains pressure is less than 100mbar.
Meters may only be located within the building when site design cannot facilitate them externally. A cabinet or
compartment can only be placed inside a building if the gas is at a low pressure of 100mbar or less. The location
should be chosen in order to allow for the shortest practicable length of gas connection pipework.
In the case of locations where multi meters are allowed there are two options available:
	•	Option 1: External Multi–Meter Location consists of locating multi-meter cabinets/manifolds around the 		
		 development outside the building line. This is preferable as it is easier to service, ensure operation and get 		
	 	 to in case of emergency. This is illustrated in figures 25-27.
	•	 Option 2: Internal Multi–Meter Location consists of meters being located inside the building line.
		 There are two variations of this option:
				Variation A: Meters located in Common Areas shown in figure 28.
				Variation B: Meters located in an Underground Car Park / Open Basement Area shown in 		
	 	 	 	 figures 29-33, which consists of :
	 	 	 	 	 •	 Type 1: Top-entry cabinets which are pre-fabricated off site.
					 •	 Type 2: On-site fabricated meter manifold. The structural housing of externally located 		
						 meters may be either.
	 •	 Prefabricated housing is illustrated in figures 34-35.
	 •	 Purpose-Built housing is illustrated in figures 36-41.
Page 19
2.2 	 Option 1: External Multi-meter Location
The preferred location for meters supplying units in a multi-occupancy building is in an enclosure, external to the
building.
Meters may only be located within the building when site design cannot facilitate them externally and the gas
pressure is ≤100mbar. The structural housing of externally located meters may be either prefabricated or purpose-
built (see further information below).
Dimensions of each six meter cabinet:
1160mm high x 750mm wide x 300mm deep.
600mm
min.
cover
Outlet Pipework
63mm P.E. service
pipe
Figure 26: Purpose-built meter manifold
Figure 27: Diagram of pipework and meter cabinet
Figure 25: Pre-fabricated meter cabinet
Isolation Valve
Should be positioned at a minimum distance
depending on pressure value.
For Medium Pressure (MP) - 4m away.
For Low Pressure (LP) - 2m away.
Guidelines for Designers and Builders - Domestic Sites
Section 2 - Multi-Occupancy Dwellings
Page 20
2.3 	 Option 2: Internal Multi-meter Location - Above Ground Level
Variation A: Meters in common areas
If the meters supplying the units in a multi-occupancy
building cannot be located externally then they may be
located within the building line subject to the following:
•	 Low pressure gas network must be available i.e. 		
	 service pressure less than 100 mbar (Natural Gas).
•	 Meters should be positioned in an area of natural 		
	 ventilation as close as possible to the external wall 	
	 where the gas service pipe enters.
•	 Meters may not be located beneath a stairs, unless 	
	 they are placed within a minimum two hour fire 	
	 resistant and sealed compartment ventilated
	 directly to the outside of the building. This
	 compartment must not obstruct exits from the
	building.
•	 Provision should be made for a steel service to
	 enter into the building through a suitable sleeve
	 where traversing a cavity or void.
•	 Care must be taken when locating the external
	 isolation valve where it is freely accessible, e.g. not
	 in a parking area where vehicles may restrict
	access.
•	 Solid access doors to the cabinet / compartment
	 must be self-closing and non-lockable.
•	 The enclosure, including access doors, must meet
	 the structural and fire resistant requirements 	 	
	 applicable to that part of the building.
•	 The ventilation to the outside atmosphere must be
	 provided through suitably sized and constructed
	 ducts, provided at high and low level. Ducts should
	 be protected and constructed to prevent fire
	damage.
•	 If the compartment is above ground level, each
	 vent should provide 5,000mm2
minimum free area 	
	 or at least 2.5% of internal floor area, unless it is only 	
	 ventilated on one side, in which case it is 3.75% of 	
	 internal floor area, depending on the number of
	 vents, or notional equivalent, whichever is greater.
	 Separation between the meters exits of each
	 ventilating duct to atmosphere must be at least
	 450mm apart. If the compartment is to be
	 positioned below ground level, Gas Networks 	
	 Ireland must be consulted for ventilation
	requirements.
•	 The dimensions required for different meter
	 arrangements is shown on page 25 of this booklet.
Ducts are required to
provide ventilation for meter
compartment. Ducts should
be sleeved through cavities,
suitably fire rated and provide
minimum air openings as
detailed above.
The enclosure, including access doors, must meet the
structural and fire retardant requirements per Building
Regulations.
Minimum
compartment
depth of 400mm
must be provided
for the manifold,
not including
provision for
enclosure or
protective barrier
External
Isolation
Valve
600mm
min
From
Mains
Area Isolation Valve
100mm min cover
At early construction provide Sleeve for Steel Service Pipe.
(Service pipe and manifold provided by Gas Networks Ireland.)
Steel Manifold
Min 2m distance
from valve
to structure
PE Pipe
Figure 28: Multiple meter within a building
Note: Meters must always be positioned to avoid the possibility of impact with impact protection provided if necessary.
Page 21
2.4 	 Option 2: Internal Multi-meter Location - Below Ground Level
Type 1: Top Entry Cabinets pre-fabricated off-site
Dimensions of each six meter cabinet:
1160mm high x 750mm wide x 300mm deep.
External
min 2m distance
from valve to structure
Isolation
Valve
600mm
minimum
cover
required P.E. Pipe
Area Isolation Valve
Natural Ventilation
600mm
min.
Contains
Six Meters
Contains Six
Meters
Top-entry cabinets open to
naturally ventilated area
1800mm
max.
At early construction provide
suitable sleeve for Steel Service
Pipe (Service pipe and manifold
provided by Gas Networks Ireland)
Steel Pipe
Figure 30: Top-entry cabinets in underground car park open basement area
Figure 29: Top entry cabinet pre-fabricated off site.
Read in conjunction with page 22.
•	 Provision should be made for the steel service to 		
	 enter into the building through an appropriate 		
	 sleeve traversing a cavity or void.
•	 The gas service must pass through a ventilated area 	
	 that is publicly accessible (i.e. providing access for 		
	 Gas Networks Ireland maintenance at all times).
•	 Electrical current carrying equipment or cables 		
	 must not be in contact with or suspended from gas 	
	 equipment or plant.
•	 Meters must always be positioned so to avoid the 	
	 possibility of impact with impact protection
	 provided if necessary.
•	 If it is required that the meters or gas service be 		
	 located in a dedicated room within the basement 		
	 or in a basement lacking natural ventilation, Gas
	 Networks Ireland must be consulted for 			
	 specifications and ventilation requirements.
•	 Care should be taken when locating the external 		
	 isolation valve so that it is freely accessible at all 		
	 times, e.g. not in a parking area where vehicles may 	
	 restrict access.
Variation B: Underground car park or open basement
Meters located in an underground car park or open basement area
must have direct access to natural ventilation. Mechanical ventilation
may not be relied upon.
There are two types of meters that can be located in an underground
car park or open basement area:
•	 Type 1: Top-entry cabinets which are pre-fabricated off site.
•	 Type 2: On-site fabricated meter manifold.
Guidelines for Designers and Builders - Domestic Sites
Section 2 - Multi-Occupancy Dwellings
Page 22
Type 2: On-site fabricated meter manifold
If manifold is at a level exposed to
possible impact, additional provision
must be made with a protective
barrier.
At early construction provide
suitable sleeve for Steel Service
Pipe (Service pipe and manifold
provided by Gas Networks Ireland)
External Isolation Valve
600mm minimum
cover required
P.E. Pipe
From
Mains
Manifold located
at high level,
minimum depth
required is
400mm.
Steel manifold open to
naturally ventilated area
Area Isolation
Valve
600 mm min
1800mm
max
Steel Pipe
Min 2m distance
from valve to
structure
Figure 31: Meters in underground car park / open basement area
Figure 32: On-site meter manifold Figure 33: Supply pipework supported at ceiling level
Read in conjunction with page 21.
However, if located internally, they must be installed at
a minimum of 300 mm above finished ground level.
•	 The meter installation must not be directly located 	
	 beneath a ventilation grille or in a position liable to 	
	 cause ingress of water, unless weather protected.
•	 If required at low level a protective barrier must be
	 placed around the meters. Sufficient impact
	 resistance provided by the builder.
•	 In the case of the steel manifold, protection from
	 tamper and impact may be provided by the
	 provision of a suitable steel cage. The use of a steel
	 mesh caging will allow for ease of meter reading.
	 The area isolation valve must remain accessible at
	 all times.
For the dimensions required for differing meter
manifold arrangements see figure 42 page 25.
External Isolation Valve
600mm minimum
cover required
From
Mains
Area Isolation
Valve
600 mm min
1800mm
max
Page 23
Figure 35: Apartment Meter Details
2.5 	 Multi-Meter Compartment Types
There are two types of meter cabinets or compartments that are used with multiple meters.
Pre-fabricated meters
A prefabricated meter cabinet is surfaced-mounted on a wall using the brackets
and bolts supplied. The GRP cabinets are pre-drilled at the back to take the threads
of the support bolts. The cabinets are to be installed a minimum of 300mm above
Finished Ground Level (F.G.L) in order to allow connection by the Distribution Mains
Crew on site using a service riser.
The multi-meter cabinet internals consist of an isolation valve, integral filter,
regulator and pre-piped manifold supplying six domestic meter points. The
heating installer connects directly to the fixed outlets outside the cabinet. It is not
permitted to recess a multi-meter cabinet into the external wall of the building,
unless all of the requirements outlined on pages 24 & 25 of this booklet are met.	
Support Brackets
750mm
L.P. / M.P.
Regulator
63mm
polyethylene
inlet pipe
Openings to suit 3
no. Outlet Pipes (3/4”
Copper)
295mm
1160mm
F.G.L
600 mm
minimum
cover
required
300mm
Figure 34: Pre-fabricated meter
cabinet
Guidelines for Designers and Builders - Domestic Sites
Section 2 - Multi-Occupancy Dwellings
Page 24
Purpose built meter compartment
A purpose-built meter compartment consists of a welded manifold with individual isolation valves, regulators and
domestic valves. The regulators and domestic meter will be installed at a later date. This meter arrangement may be
located away from the building or recessed into the outer leaf of the building structure.
Note: Purpose built compartments for gas meters are not to be used for any other purpose (e.g. storage of bins or
any other equipment.)
1.	 If recessed into the structure of the building or to be placed within the building line the meters must be in a
	 completely sealed compartment with the exception of access and ventilation provided by louvered doors to the
	 outside air. This arrangement is only permitted on a low pressure site i.e. gas pressure ≤ 100mbar.
2.	 The compartment must meet the structural and fire resistant requirements applicable to that part of the 	
	 building. All voids within and around the compartment must be fully sealed and fire proofed to prevent the
	 ingress of air or gas to the cavity wall or other voids.
Outer
leaf
Sleeve
Pipe
Temperature
Resistant Mastic
Inner leafCavity
Pipes must have
supporting brackets
For Outlet Pipe Requirements See Detail A
400mm
min.
100mm Floor Slabs
Steel Gas
Service
Ground
Level
600mm minimum cover required
300mm
min.
300mm
min.
Block / Brick Construction
Hardwood Louvred Doors complete
with Hinges and Locking Device
Valve min 2m from
structure
Figure 37: Inside meter compartment detail
Figure 39: Sleeving Detail A
Figure 36: Plan Detail
Figure 38: Elevation
Pipes must have
supporting brackets
For Outlet Pipe Requirements See Detail A
400mm
min.
Plan Detail:
Inside Meter Compartment Detail:
100mm Floor Slabs
Steel Gas
Service
Ground
Level
600mm minimum cover required
Sleeving Detail A:
Outer
leaf
Sleeve
Pipe
Temperature
Resistant Mastic
Inner leafCavity
Block / Brick Construction
Elevation:
Hardwood Louvred Doors complete
with Hinges and Locking Device
Page 25
3.	 If the enclosure opens to the outside but is set within the building structure then all pipe sleeves or entries into
	 the building must be sealed with an approved fire sealing material. Access doors should not be lockable.
	 Ventilation must be provided to atmosphere in the form of a fully louvered door or in the case of a solid door,
	 vents must be located at the top and the bottom of the door. Each vent must provide a minimum of 5,000mm2
	 free area, or at least 2.5% of internal floor area, unless it is only ventilated on one side, in which case it is 3.75% of 	
	 internal floor 	area, depending on the number of vents, or notional equivalent, whichever is greater.
4.	 Meter compartments are to be located outside apartment walls in well-ventilated areas provided by the builder.
5.	 The builder must open ground to allow for steel gas service into the meter compartment.
For internal dimensions for various meter configurations, please consult figure 42 below.
Figure 41: Purpose built meter manifold in
purpose built meter compartment block/brick
construction
Figure 40: Purpose-built meter manifold
2.6 	 Internal Building Dimensions for various Meter Bank Configurations
Note: If placing meters at low level, always allow for an extra 300mm beneath lowest meter point.
3 x 32 x 3
2200
2 x 4 3 x 4
1650
1100
550
3 x 22 x 2
2 x 1 3 x 1
6 x 35 x 34 x 3
4 x 4 5 x 4 6 x 4
5 x 24 x 2
4 x 1 5 x 1
6 x 2
6 x 1
855 1195 1535 1875 2215
7 x 3
7 x 4
7 x 2
7 x 1
2555
Figure 42: Internal Building Dimensions for Various Meter Bank Configurations
Guidelines for Designers and Builders - Domestic Sites
Section 3 - Conclusion & Appendices
Page 26
Readers Notes
Page 27
3 Conclusion &
Appendices
Guidelines for Designers and Builders -
Domestic Sites
Guidelines for Designers and Builders - Domestic Sites
Section 3 - Conclusion & Appendices
Page 28
These items are to be checked by the Sales Rep - 		 Yes/No/NA
If NO or NA please give a reason in remarks.
Comments / Remarks/ Specific Requirements – Specify as much detail as possible to aid in the design process.
3.1 	 Checklist of Essential Information required by Design
This must be supplied with the project
The following is the current essential information required for Gas Networks Design.
The list below is to outline what is required, the developer/builder must give this information to the Gas Networks
Ireland Sales representative in order to process the project.
Figure 43: Checklist of information required by Gas Networks Ireland Sales Representative.
Meter Locations	 Must be clearly marked on site layout maps or stated 			
clearly in project remarks (this includes New Housing Sites).
Site layout Plans	 All New Build / Greenfield Sites require a Detailed Site 			
Layout Plan that is compatible with Autocad 			
(including External References if required).
Elevation Drawings 	 These are required for all 4bar projects where the meter is 			
to be located on, or within 3m of the building. 			
(PDF format will suffice)
Basement Plans		 These are required for all builds where meters are to be 			
located in a basement (including New Housing / 			
Apartments site (Autocad format required).
Ventilation		 Basement works and internal meter locations require
Client confirmation of adequate natural ventilation.
Mains/Service Pipe Routing	 If known.
Builder/ Developer 	 Please provide necessary details in the remarks / log. E.g.
Specific Requirements	 Will the trench be provided on site? / What date is the gas 			
required for if known?
Page 29
3.2 	 Irish Standards
This document is to be used for guidance purposes and makes reference to the relevant Irish Standards as shown
below however it must not conflict with or be used as a substitute for the standards should any conflict arise, the
Irish standards take precedence.
For gas and main services
Gas Networks Ireland will install all gas mains and
services in accordance with the latest edition of the
following Irish Standards:
I.S. 329 “Code of Practise for Gas Distribution Mains”
and
I.S.265 “Installation of Gas Service Pipes”.
E.T.C.I. National rules for electrical installations, Part 1,
General requirements, Section 5.4.6.
RGII
Tel: 1850 454 454
www.rgii.ie
For downstream of the meter
Irish Standard I.S.813 “Domestic Gas Installations” and
I.S.820 “Non-Domestic Gas Installations” Apply to the
gas installation downstream of the point of delivery
(normally the meter).
These Standards are the code of practice for natural
gas installation requirements downstream of the point
of delivery and includes the requirements for meters,
appliances and associated pipework in single and
multiple occupancy dwelling.
All of the above standards can be obtained from the
NSAI (National Standards Authority of Ireland).
Telephone (01) 8073800
Appendix - Excavations Parallel to Walls
With reference to figure 4, dig a trial hole to determine the depth of the foundations or base of the wall, taking care to
avoid undercutting the foundation/base. Excavation work must not proceed if the wall is leaning, cracked or showing
any signs of instability or distress.
Note: Please ensure the distance from the trench to the bottom of the foundations (W), is greater than the length
from the bottom of the foundations to the pipe, (X).
Otherwise please see conditions below:
	 •	 reduce the depth of the trench, or
	 •	 provide suitable support appropriate to the type of structure, soil characteristics and depth of trench.
Figure 44: Proximity of trench to walls	 Figure 45: Proximity of walls to foundation
Otherwise please see conditions below:
	 •	 move the trench so that the distance from the trench to the wall is greater than the depth of the trench, or
	 •	 trial hole carried out.
Note: All personnel shall stay out of the area (S) during excavation work.
Page 30
Guidelines for Designers and Builders - Domestic Sites
Section 3 - Conclusion & Appendices
Readers Notes
Page 31
Disclaimer
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the publishers. The advice contained within this document is a guideline only and based on
the most authoritative information available at the date of issue. Users should ensure that it is relevant to the specific circumstances in which they seek to apply
it. Professional advice should always be sought. Although every effort has been made to ensure information is correct, no responsibility will be accepted for any
errors or omissions, nor any loss or damage which may arise from errors or omissions. Current Laws, Regulations and Standards over-ride all contents of this
guideline document. Users should ensure they have up to date information. © Gas Networks Ireland.
Page 32
The main contact details for
Gas Networks Ireland are:
General Enquiries
1850 200 694
24hr Emergency Service		
1850 20 50 50
info@gasnetworks.ie
@GasNetIRL
gasnetworks.ie
37565/02/2016

More Related Content

What's hot

WATER SUPPLY AND PLUMBING SERVICES
WATER SUPPLY AND PLUMBING SERVICESWATER SUPPLY AND PLUMBING SERVICES
WATER SUPPLY AND PLUMBING SERVICES
RIDDHESH VARIK
 
Building Services :Drainage, Rain Water Disposal and Harvesting
Building Services :Drainage,  Rain Water Disposal and  HarvestingBuilding Services :Drainage,  Rain Water Disposal and  Harvesting
Building Services :Drainage, Rain Water Disposal and Harvesting
Sumit Ranjan
 
Building drainage system
Building drainage systemBuilding drainage system
Building drainage system
Dipesh Jain
 
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDINGWATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
Karan Patel
 
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPSDRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
Karan Patel
 
Plumbing services in high rise building and group housing
Plumbing services in high rise building and group housingPlumbing services in high rise building and group housing
Plumbing services in high rise building and group housing
Rohit Bhatt
 
Underground car parking ventilation system
Underground car parking ventilation systemUnderground car parking ventilation system
Underground car parking ventilation system
Mohamed Hashish
 
Water supply final
Water supply finalWater supply final
Water supply final
Riya Bagchi
 
Cold water supply and pipe sizing
Cold water supply and pipe sizingCold water supply and pipe sizing
Cold water supply and pipe sizing
Humphrey Samati
 
Pipe lines in sewage system
Pipe lines in sewage systemPipe lines in sewage system
Pipe lines in sewage system
Gokul Ayyappan
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLY
RIDDHESH VARIK
 
Sewerage
SewerageSewerage
Week 06 lecture 06 water connection
Week 06 lecture 06 water connectionWeek 06 lecture 06 water connection
Week 06 lecture 06 water connection
Hena Dutt
 
Water supply systems in Architecture By Minal Palve
Water supply systems in Architecture By Minal PalveWater supply systems in Architecture By Minal Palve
Water supply systems in Architecture By Minal Palve
Minal Palve
 
Water Supply System for Town and Building
Water Supply System for Town and Building Water Supply System for Town and Building
Water Supply System for Town and Building
Aroh Thombre
 
Water supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvestingWater supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvesting
Ayushi Agrawal
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a Building
Aroh Thombre
 
Dry & Wet Riser Systems
Dry & Wet Riser SystemsDry & Wet Riser Systems
Dry & Wet Riser Systems
Lin Lin Htet Htet
 
Plumbing system for students
Plumbing system for studentsPlumbing system for students
Plumbing system for students
Kyle Mallo
 

What's hot (20)

WATER SUPPLY AND PLUMBING SERVICES
WATER SUPPLY AND PLUMBING SERVICESWATER SUPPLY AND PLUMBING SERVICES
WATER SUPPLY AND PLUMBING SERVICES
 
Building Services :Drainage, Rain Water Disposal and Harvesting
Building Services :Drainage,  Rain Water Disposal and  HarvestingBuilding Services :Drainage,  Rain Water Disposal and  Harvesting
Building Services :Drainage, Rain Water Disposal and Harvesting
 
Building drainage system
Building drainage systemBuilding drainage system
Building drainage system
 
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDINGWATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
 
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPSDRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
 
Plumbing services in high rise building and group housing
Plumbing services in high rise building and group housingPlumbing services in high rise building and group housing
Plumbing services in high rise building and group housing
 
Underground car parking ventilation system
Underground car parking ventilation systemUnderground car parking ventilation system
Underground car parking ventilation system
 
Water supply final
Water supply finalWater supply final
Water supply final
 
Cold water supply and pipe sizing
Cold water supply and pipe sizingCold water supply and pipe sizing
Cold water supply and pipe sizing
 
Pipe lines in sewage system
Pipe lines in sewage systemPipe lines in sewage system
Pipe lines in sewage system
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLY
 
Sewerage
SewerageSewerage
Sewerage
 
PIPE SYSTEMS1
PIPE SYSTEMS1PIPE SYSTEMS1
PIPE SYSTEMS1
 
Week 06 lecture 06 water connection
Week 06 lecture 06 water connectionWeek 06 lecture 06 water connection
Week 06 lecture 06 water connection
 
Water supply systems in Architecture By Minal Palve
Water supply systems in Architecture By Minal PalveWater supply systems in Architecture By Minal Palve
Water supply systems in Architecture By Minal Palve
 
Water Supply System for Town and Building
Water Supply System for Town and Building Water Supply System for Town and Building
Water Supply System for Town and Building
 
Water supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvestingWater supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvesting
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a Building
 
Dry & Wet Riser Systems
Dry & Wet Riser SystemsDry & Wet Riser Systems
Dry & Wet Riser Systems
 
Plumbing system for students
Plumbing system for studentsPlumbing system for students
Plumbing system for students
 

Viewers also liked

LIQUEFIED PETROLEUM GAS INSTALLATION
LIQUEFIED PETROLEUM GAS INSTALLATIONLIQUEFIED PETROLEUM GAS INSTALLATION
LIQUEFIED PETROLEUM GAS INSTALLATION
bluesky11
 
Advanced services - contracts and modelling
Advanced services - contracts and modellingAdvanced services - contracts and modelling
Advanced services - contracts and modelling
Shaun West
 
Anaesthesia gas cylinders & pipeline gas supply
Anaesthesia gas cylinders & pipeline gas supplyAnaesthesia gas cylinders & pipeline gas supply
Anaesthesia gas cylinders & pipeline gas supply
Unnikrishnan Prathapadas
 
Role of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in IndiaRole of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in IndiaKrittika Walia
 
ARCHITECT'S ACT 1972
ARCHITECT'S ACT 1972ARCHITECT'S ACT 1972
ARCHITECT'S ACT 1972
Gagan Jain
 
SPA Professional Practice I
SPA Professional Practice ISPA Professional Practice I
SPA Professional Practice I
Design Action Group
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
Ar. Mukunda K.S
 
SPA Professional Practice II
SPA Professional Practice IISPA Professional Practice II
SPA Professional Practice II
Design Action Group
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of Work
Volker Hirsch
 

Viewers also liked (12)

LIQUEFIED PETROLEUM GAS INSTALLATION
LIQUEFIED PETROLEUM GAS INSTALLATIONLIQUEFIED PETROLEUM GAS INSTALLATION
LIQUEFIED PETROLEUM GAS INSTALLATION
 
RP CONSTRUCTION.ppt 1
RP CONSTRUCTION.ppt 1RP CONSTRUCTION.ppt 1
RP CONSTRUCTION.ppt 1
 
Advanced services - contracts and modelling
Advanced services - contracts and modellingAdvanced services - contracts and modelling
Advanced services - contracts and modelling
 
Anaesthesia gas cylinders & pipeline gas supply
Anaesthesia gas cylinders & pipeline gas supplyAnaesthesia gas cylinders & pipeline gas supply
Anaesthesia gas cylinders & pipeline gas supply
 
Role of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in IndiaRole of Indian Institute of Architects as a professional body in India
Role of Indian Institute of Architects as a professional body in India
 
ARCHITECT'S ACT 1972
ARCHITECT'S ACT 1972ARCHITECT'S ACT 1972
ARCHITECT'S ACT 1972
 
The architects act, 1972
The architects act, 1972The architects act, 1972
The architects act, 1972
 
SPA Professional Practice I
SPA Professional Practice ISPA Professional Practice I
SPA Professional Practice I
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
 
National Building Code 2005
National Building Code 2005National Building Code 2005
National Building Code 2005
 
SPA Professional Practice II
SPA Professional Practice IISPA Professional Practice II
SPA Professional Practice II
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of Work
 

Similar to Gas Installation Guidelines for Designers and Builders - Domestic Sites

Prima Plus flue system installation instructions
Prima Plus flue system installation instructionsPrima Plus flue system installation instructions
Prima Plus flue system installation instructions
Schiedel UK
 
Gas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural GasGas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland
 
Prima Smooth flue system installation instructions
Prima Smooth flue system installation instructionsPrima Smooth flue system installation instructions
Prima Smooth flue system installation instructions
Schiedel UK
 
Sample GPS Application Guide Gas
Sample GPS Application Guide Gas Sample GPS Application Guide Gas
Sample GPS Application Guide Gas
BHD Creative Ltd
 
The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2
خالد محمود
 
Site Report
Site ReportSite Report
Site Report
ShavneelChand
 
Agilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resAgilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resgunalan7
 
Isokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsIsokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructions
Schiedel UK
 
Fire dampers installation
Fire dampers installationFire dampers installation
Fire dampers installation
Construction Technical Services Arabia
 
Pigging Pipelines.pdf
Pigging Pipelines.pdfPigging Pipelines.pdf
Pigging Pipelines.pdf
Fast name Last name
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Gaurav Singh Rajput
 
UK Plus Brochure
UK Plus Brochure UK Plus Brochure
UK Plus Brochure
Schiedel UK
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestationYousef Riad
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1
Elsayed Amer
 
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer line
RAMPRASAD KUMAWAT
 
ZSM-Connection_Brochure_english
ZSM-Connection_Brochure_englishZSM-Connection_Brochure_english
ZSM-Connection_Brochure_englishChris Munnick
 
Grp installation procedure
Grp installation procedureGrp installation procedure
Grp installation procedure
kaustav mukherjee
 
Ashghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manualAshghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manual
syedfaisalali_50
 
Contech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial MarketsContech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial Markets
Contech Engineered Solutions
 

Similar to Gas Installation Guidelines for Designers and Builders - Domestic Sites (20)

Prima Plus flue system installation instructions
Prima Plus flue system installation instructionsPrima Plus flue system installation instructions
Prima Plus flue system installation instructions
 
Gas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural GasGas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural Gas
 
Prima Smooth flue system installation instructions
Prima Smooth flue system installation instructionsPrima Smooth flue system installation instructions
Prima Smooth flue system installation instructions
 
Sample GPS Application Guide Gas
Sample GPS Application Guide Gas Sample GPS Application Guide Gas
Sample GPS Application Guide Gas
 
The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2
 
Site Report
Site ReportSite Report
Site Report
 
15-0478_WD_B
15-0478_WD_B15-0478_WD_B
15-0478_WD_B
 
Agilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resAgilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_res
 
Isokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsIsokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructions
 
Fire dampers installation
Fire dampers installationFire dampers installation
Fire dampers installation
 
Pigging Pipelines.pdf
Pigging Pipelines.pdfPigging Pipelines.pdf
Pigging Pipelines.pdf
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
UK Plus Brochure
UK Plus Brochure UK Plus Brochure
UK Plus Brochure
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestation
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1
 
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer line
 
ZSM-Connection_Brochure_english
ZSM-Connection_Brochure_englishZSM-Connection_Brochure_english
ZSM-Connection_Brochure_english
 
Grp installation procedure
Grp installation procedureGrp installation procedure
Grp installation procedure
 
Ashghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manualAshghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manual
 
Contech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial MarketsContech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial Markets
 

More from Gas Networks Ireland

Transport Ireland conference 2018
Transport Ireland conference 2018 Transport Ireland conference 2018
Transport Ireland conference 2018
Gas Networks Ireland
 
Harnessing Customer Feedback for Outstanding Customer Experience
Harnessing Customer Feedback for Outstanding Customer ExperienceHarnessing Customer Feedback for Outstanding Customer Experience
Harnessing Customer Feedback for Outstanding Customer Experience
Gas Networks Ireland
 
Business Plus magazine feature
Business Plus magazine feature Business Plus magazine feature
Business Plus magazine feature
Gas Networks Ireland
 
The Future of Gas Infrastructure in Ireland
The Future of Gas Infrastructure in IrelandThe Future of Gas Infrastructure in Ireland
The Future of Gas Infrastructure in Ireland
Gas Networks Ireland
 
Natural Gas Power Conference
Natural Gas Power ConferenceNatural Gas Power Conference
Natural Gas Power Conference
Gas Networks Ireland
 
Ormonde Hotel case study
Ormonde Hotel case studyOrmonde Hotel case study
Ormonde Hotel case study
Gas Networks Ireland
 
Grantstown Nurseries case study
Grantstown Nurseries case studyGrantstown Nurseries case study
Grantstown Nurseries case study
Gas Networks Ireland
 
Renewable Gas: Unique Heat & De-carbonisation Opportunity for Ireland
Renewable Gas: Unique Heat & De-carbonisation Opportunity for IrelandRenewable Gas: Unique Heat & De-carbonisation Opportunity for Ireland
Renewable Gas: Unique Heat & De-carbonisation Opportunity for Ireland
Gas Networks Ireland
 
The Benefits of Switching to Natural Gas
The Benefits of Switching to Natural GasThe Benefits of Switching to Natural Gas
The Benefits of Switching to Natural Gas
Gas Networks Ireland
 

More from Gas Networks Ireland (9)

Transport Ireland conference 2018
Transport Ireland conference 2018 Transport Ireland conference 2018
Transport Ireland conference 2018
 
Harnessing Customer Feedback for Outstanding Customer Experience
Harnessing Customer Feedback for Outstanding Customer ExperienceHarnessing Customer Feedback for Outstanding Customer Experience
Harnessing Customer Feedback for Outstanding Customer Experience
 
Business Plus magazine feature
Business Plus magazine feature Business Plus magazine feature
Business Plus magazine feature
 
The Future of Gas Infrastructure in Ireland
The Future of Gas Infrastructure in IrelandThe Future of Gas Infrastructure in Ireland
The Future of Gas Infrastructure in Ireland
 
Natural Gas Power Conference
Natural Gas Power ConferenceNatural Gas Power Conference
Natural Gas Power Conference
 
Ormonde Hotel case study
Ormonde Hotel case studyOrmonde Hotel case study
Ormonde Hotel case study
 
Grantstown Nurseries case study
Grantstown Nurseries case studyGrantstown Nurseries case study
Grantstown Nurseries case study
 
Renewable Gas: Unique Heat & De-carbonisation Opportunity for Ireland
Renewable Gas: Unique Heat & De-carbonisation Opportunity for IrelandRenewable Gas: Unique Heat & De-carbonisation Opportunity for Ireland
Renewable Gas: Unique Heat & De-carbonisation Opportunity for Ireland
 
The Benefits of Switching to Natural Gas
The Benefits of Switching to Natural GasThe Benefits of Switching to Natural Gas
The Benefits of Switching to Natural Gas
 

Recently uploaded

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 

Recently uploaded (20)

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 

Gas Installation Guidelines for Designers and Builders - Domestic Sites

  • 1. Page 1 of 13 gasnetworks.ie Guidelines for Designers and Builders - Domestic Sites
  • 2. Page 2 1 General Information and Single Occupancy Dwellings 1.1 Introduction 4 1.2 How a Gas Meter is Installed 4 General rules 4 1.3 Self-Trenching Information 5 Gas Mains 5 Gas Connection Pipe (Service Pipe) 5 1.4 Excavations Parallel to Walls 6 1.5 On Site Requirements 6 1.6 Gas Safety on Building Sites 7 Do’s and Don’ts on Building Sites 7 1.7 Building Line 8 1.8 Meter Location 9 Where to locate your meter 9 Where not to locate your meter 11 1.9 Meter Box Types 11 1.10 Meter Box Dimensions 12 Surface Mounted Meter Box with Ventilation 12 Recessed Meter Box with Ventilation 13 1.11 Recessed Meter Box in Pillar Enclosure 14 1.12 Foundation Requirements for Preformed Bend below ground 15 1.13 Meter Box Internals 16 1.14 To-Do list Before a Meter can be Fitted 16 1.15 Wayleave 16 When is a wayleave required? 16 2 Multi – Occupancy Dwellings 2.1 Multi- Occupancy Dwellings - General 18 Multi-Occupancy Definition 18 Multi-Meter Definition 18 General Meter Requirements 18 Installation up to the Meter 18 2.2 Option 1: External Multi – Meter Location 19 2.3 Option 2: Internal Multi – Meter Location - Above Ground Level 20 Variation A: Meters in Common Areas 20 2.4 Option 2: Internal Multi–Meter Location - Below Ground Level 21 Variation B: Underground Car Park or Open Basement 21 Type 1: Top Entry Cabinets pre-fabricated off-site 21 Type 2: On- Site Fabricated Meter Manifold. 22 2.5 Multi – Meter Compartment Types 23 Pre-Fabricated Meters 23 Purpose Built Meter Compartment 24 2.6 Internal Building Dimensions for various Meter Bank Configurations 25 3 Conclusion & Appendices 3.1 Checklist of Essential Information required by Design 28 3.2 Irish Standards 29 3.3 Appendix - Excavations Parallel to Walls 29 Contents Guidelines for Designers and Builders - Domestic Sites
  • 3. Page 3 of 13 Siteworks Activities Manual MANUAL No. AO/MN/002 Rev. 0 Date: February 2015 Guidelines for Designers and Builders - Domestic Sites 1 General Information and Single Occupancy Dwellings
  • 4. Guidelines for Designers and Builders - Domestic Sites Section 1 - General Information and Single Occupancy Dwellings Page 4 1.1 Introduction This guide outlines the permitted locations, positions, safe depths and distances the installation of your natural gas meter and meter box when connecting to the natural gas network. It is designed to give guidelines for designers and builders on development sites with domestic and commercial loads. The preferred location for Gas Networks Ireland (GNI) to locate the gas meter is externally. This is to allow for ease of meter reading, maintenance and operation assurance. However a meter can be located internally if it is not possible to locate it externally and if the gas is being supplied at a low pressure of 100mbar or less. For more information on locating meters internally please consult the Industrial and Commercial Sites Booklet of this Technical Manual. Note: For bespoke architectural solutions or for projects requiring meters located internally please contact your local Gas Networks Ireland sales representative. This document is to be used for guidance purposes and references the Irish installation standards for natural gas I.S 813 (Domestic) and I.S 820 (Non- Domestic) as well as I.S. 329 “Code of Practice for Gas Distribution Mains” and I.S. 265 “Installation of Gas Service Pipes”. However it must not conflict with or be used as a substitute for the standards should any conflict arise, the Irish standards take precedence. 1.2 How a New Gas Meter is Installed A GNI approved contractor will lay and test the gas connection pipe/ service pipe in the pre-excavated trench provided by the builder and a top tee connection is made to the main in the path or road as appropriate. The gas connection pipe shall have sand surround and be reinstated as soon as practicable in order to reduce the possibility of external damage on site. Normally 32mm (low pressure) size polyethylene connection pipe and 25mm (medium pressure) size polyethylene connection pipe is used. A gas connection pipeline is laid by Gas Networks Ireland connecting a building to the natural gas network. The natural gas connection pipeline must be laid in a straight line to the meter location, using the shortest most direct route and where possible at right angles to the gas main. An illustration of this is shown in figure 1. Marker tape should be placed over all gas mains, gas connections and ducting intended for gas distribution pipes. General Rules It must also be laid with a minimum of 600mm of ground cover. The proposed route of the connection pipe must be clear when the crew arrives to carry out the work, otherwise it cannot be installed. If the meter box is to be attached to the property wall then it must be located above the damp proof course at a minimum of 300mm above finished ground level. A meter should not be placed within 150mm below or beside an electricity meter. Gas Distribution Mains Service Top Tee Gas Service min 600mm cover Customers downstream pipework Pavement Roadway GRP box containing gas meter and pressure regulator Figure 1: Connection from Gas Main to Residential Meter Box
  • 5. Page 5 1.3 Self-Trenching Information This sections illustrates how trenches should be prepared correctly before Gas Networks Ireland arrives on site. There are different excavation requirements depending on the type of pipe that is installed i.e. gas main or gas connection pipe / gas service. Gas Mains Trenches excavated for a gas main must allow for: Sand Bed & Surround: A 100mm bed of sand (150mm if in rock) shall be provided and installed by the customer and shall be in place before the GNI contractor crew is required on site. Depth (on day of installation): • A minimum cover of 750mm to the crown/top of the pipe in roadways. • 600mm minimum cover is required beneath footpaths or landscape areas, but 750mm if trafficked. • Gas mains must not be laid deeper than 1.2 metre unless specified and agreed in advance with Gas Networks Ireland. Width: • The total trench width must be 300mm in addition to the outside diameter of gas pipe. • A minimum of 150mm of sand must surround the gas main. Gas Connection pipe (Service Pipe) The gas connection pipe will be laid in a straight line to the meter location, as perpendicular to the gas main as possible. Therefore the trench for this gas connection pipe must be excavated in a straight line. All trenches for gas connection pipes must be excavated to allow for: Sand Bed & Surround: A 100mm bed of sand (150mm if in rock) shall be provided and installed by the customer and shall be in place before the GNI contractor crew is required on site. Depth: • A minimum cover of 600mm for each gas connection pipe up to 1.5 metres from the meter box. • Depth can reduce to a minimum of 375mm at the base of the GRP sleeve within the 1.5 metre distance at the meter location only. Width: • The gas connection trench width should be a minimum of 300mm in addition to the outside pipe. • A minimum of 150mm of sand should surround the gas service. N.B. Contractors/Builders must provide their own sand surround and reinstatement material. The main or connection//service pipe must be covered in surround before the Gas Networks Ireland contractor leaves the site. The trench must be reinstated as soon as possible after the pipe is laid to reduce the possibility of damage to the gas pipes. Figure 2: Recommended gas main layout in a footpath/roadway
  • 6. Guidelines for Designers and Builders - Domestic Sites Section 1 - General Information and Single Occupancy Dwellings Page 6 1.4 Excavations Parallel to Walls When excavating trenches parallel to a wall, the stability of the wall, must be checked. This is in case walls have not been adequately designed, altered, degraded over time or may now be used for an intention that they were not designed for. Care must be taken with excavation work and a risk assessment carried out if the wall is leaning, cracked or showing any signs of instability or distress. The stability of the wall should be checked whenever: • the edge of a gas connection/service trench is within 0.5 m of the wall; • the edge of a mains trench is within 1m of the wall, or • the main is larger than 200 mm nominal diameter, • or the main or service is to be laid at a depth greater than normal. Please see the diagrams and further information relating to safely excavating parallel to walls in the Appendix section. If there are any queries relating to excavating parallel to walls please contact customer service at 1850 200 694. 1.5 On site Requirements • The gas main should never be placed in an inspection chamber with other utilities, services, drainage/ sewage systems. • A distance of 300mm must be provided when a gas main is placed adjacent to an inspection chamber (see figure 3) • A minimum clearance of 300mm is required where necessary to cross or run in close proximity to any other utility service. • A distance of 600mm must be provided from high voltage cables and district heating pipes. • No other services/utilities is to be placed over the gas main/service • Gas Networks Ireland will not insert the service pipe in a sleeve or duct. Note: Please ensure the distance from the trench to the wall (S), is greater than the depth of the trench (H). Note: • Polyethylene mains and services may not be positioned within the Building Line (as defined by I.S. 329 / I.S. 265). • For more detailed information always refer to the Gas Networks Ireland Distribution drawings specific to the project. ng information properties Bord Gáis or ctor in a pre- the builder. the purpose n must allow 0mm + pipe not be laid 0mm unless total trench ide diameter and 150mm e gas main provided by reinstated as main is laid, damage on as main in a Boundry Wall 300 Elec/Telecom Ducts 150mm Compacted Sand Surround Gas Main 250min Water Main 300mm Granular Material to DOE spec. Clause 804 750mm minimum cover required beneath roads 650mm minimum cover required beneath footpaths and landscaped areas Marker Tape d by Bord Gáis or a Bord Gáis appointed contractor in a pre-excavated trench provided by the builder. The gas line to the meter location, as near perpendicular to the gas main as practicable. The trench for the gas service excavated to a depth to allow a minimum cover of 600mm for each service. In the case where the service tes 2), 600mm minimum cover is required up to 1.5 metres from the meter box. Required cover shall reduce e base of the GRP sleeve within the 1.5 metre distance (note fig. 3). Sand 150mm minimum shall surround einstatement provided by builder). The service trench width shall be a minimum of 300mm. Where ducts are s. he gas main on chamber or drainage of 300mm gas main is on chamber vices may e Building / I.S.265). on, always bution oject. Fig.1 Recommended Layout of Gas Main in a Footpath. Fig.2 Safety Precautions with regards to Inspection Chambers. Note: Other services/ducts must not be laid on top of gas mains/services Section Drawing Telecom Duct Electrical Duct Gas Main Water Main Gas Main Water Main Inspection Chamber (Manhole) Inspection Chamber (Manhole) Telecom Duct Electrical Duct Gas Main Water Main Gas Main Water Main Inspection Chamber (Manhole) Inspection Chamber (Manhole) 300mm min ✕Figure 3: Safety precautions with regards to inspection chambers.
  • 7. Page 7 1.6 Gas Safety on Building Sites After the initial project planning stage and when a site is in progress the following safety guidelines should be adhered to: Do • Ensure all excavations are carried out in accordance with the H.S.A Code of Practise: Avoiding Danger from Underground Services. i.e. use of maps/records, identification of pipe locations & safe digging practises. • Maintain accurate on-going records of all gas mains and services laid on your site. • Ensure all site personnel adhere to any exclusion zones while mains/services are under test on site. • Make all operatives, including sub-contractors, aware of the presence and location of gas mains and services. • Provide a safe and suitable location for the storage of gas pipes and materials • Ensure that any necessary trial holes are dug carefully by hand. • Ensure any personnel excavating in an area containing already existing gas mains have obtained Gas Networks Ireland maps. • Report any damage, no matter how slight, to the Gas Networks Ireland 24 hr Emergency Line 1850 20 50 50. • Ensure meter cabinet is securely fitted without compromising its structural integrity. • If there is a natural gas transmission pipeline on your site you must contact Gas Networks Ireland for specific guidance. Do not • Interfere with stored gas pipe or materials. • Attempt to cut or un-band coils of Polyethylene (PE) gas pipe, this can only be done by gas personnel. These coils contain a lot of stored energy and can cause serious injuries if interfered with. • Use PE gas pipe for any other purpose, e.g. ducts, sleeves, drains. • Use mechanical excavators within 1m of a gas main. • Use hand held power tools, i.e. jack hammers within 0.5m of a gas main. • Carry out piling work within 15m of a gas main without prior consultation with Gas Networks Ireland. • Welding or hot works should not be carried out in the vicinity of an exposed gas main without prior consultation with Gas Networks Ireland. • Attempt to repair any damage to a gas main or service. • Do not interfere with the meter cabinet and its structural integrity.
  • 8. Guidelines for Designers and Builders - Domestic Sites Section 1 - General Information and Single Occupancy Dwellings Page 8 1.7 Building Line Explanation and Illustration The building line is considered the outermost extent of the building structure (archway, balcony or basement) projected vertically on to ground level. Gas mains, services and meters transporting gas at pressure greater than 100mbar are not permitted inside the building line of occupied premises. Under certain circumstances however Gas meters can be positioned inside the building line: • The gas pipework must have a pressure of 100mbar or less. • And there must be no available option of locating the meter externally. • Polyethylene pipework may not be located within a building or in a space that may be potentially enclosed at a later stage e.g. an open porch. In figure 4 below the exclusion zone is illustrated by a dotted line: • This exclusion zone on the left ends in line with the porch at the gable wall. • The exclusion zone shown on the right is further out as this porch/balcony/building overhang is said to be attached to the building. For any queries relating to the building line/exclusion zone call 1850 200 694. Figure 4: Exclusion zone drawing • Meter box is not permitted within the porch/building overhang. • Meter box and service installations shall be in accordance with I.S. 265 and I.S. 813. • The gas meter box shall be greater than 300mm away from a flue. • Meter box shall not be placed more than 2 meters from the gable end of the property. √ √ √ √ Porch/Balcony Building Overhang 3 4 2 1 Gable Wall Screen Wall Option 2m max 300mmmin 300mmmin Note: Meter not allowed in porch or inside the exclusion zone Exclusion zone
  • 9. Page 9 • A minimum separation of 300mm from the service pipe of the gas meter to the service pipe of the ESB meter • A minimum separation of 150mm from the gas meter box to the ESB box, a minimum separation of 400mm from an electrical distribution board and 300mm from the gas service to any other services. 1.8 Meter Location Where to locate your meter Figure 5 Minimum separation between Gas and other meters Figure 6 Minimum separation from the Gas Meter box to the Electricity meter Figure 7 Diagram of possible Meter Locations for a domestic property. E.S.B. Electricity Service Pipe 150mm Gas FH. T.V. 300mm 300mm min.
  • 10. Guidelines for Designers and Builders - Domestic Sites Section 1 - General Information and Single Occupancy Dwellings Page 10 At the front gable end wall, a maximum of 2 metres from the front corner of the building. Fig 8. On a nib wall. Fig 10. On the wall that separates neighbours. Fig.11 i.e. boundary wall. Figure 10 Meter box on nib wall Figure 11 Meter box between neighbours wall On either side of the door, Figure 13. Note: This may require impact protection. Figure 12 Meter box either side of the window Figure 13 Meter box on either side of the door The meter box should be accessible from the front of the house. The previous figure 7 gives examples of where the meter box can be placed: Figure 8 Gable end of property At the front wall of the building – on either side of the front door, or on either side of a sealed window. Fig 9. Note: This can’t be fitted directly below a window. At the front wall of the building – on either side of the front door, or on either side of a sealed window. Note: This can’t be fitted directly below a window. Figure 9 Meter box either side of the window
  • 11. Page 11 Where not to locate your meter The meter box must not be placed: • At the back of the house or behind a gate. • Directly above or below an electricity meter. • Directly above drains, airbricks, manholes, or an electricity meter. • Directly under appliance vents, windows that open or an electricity meter. • In a porch or under an overhang which is enclosed or could be enclosed. • Where it is liable to cause an obstruction or be subject to vehicular damage. • Where access to the meter box may be restricted in an emergency e.g. narrow path. • On a stone boundary wall or stone garden wall. • Adjacent to an electricity meter, if there is a suitable practical location for it elsewhere. For any queries relating to meter box location please call 1850 200 694. 1.9 Meter Box Types There are two types of meter boxes – surface mounted and recessed. A surface mounted meter box is installed on the property or boundary wall as shown in figure 14. This meter box is more suitable for installation on older buildings converting to natural gas. The meter box will be provided by Gas Networks Ireland and will be fitted at a minimum of 300mm above finished ground level. The meter box will project approximately 250mm outwards from the wall. A recessed meter box is installed in the cavity wall of a building or in a pillar enclosure as shown in figure 15. This type of meter box is generally installed by a builder in a new one-off build or as part of a new extension. The box must be purchased from a building supplier and is not provided by Gas Networks Ireland. If this type of meter box is damaged, Gas Networks Ireland will be unable to install the meter for safety reasons. The meter box must be built into the wall, secured and unpunctured as per manufacturer’s instructions. The meter box will project appoximately 100mm outwards from the wall. Figure 14 Surfaced Mounted Type Meter box Figure 15 Recessed Type Meter Box
  • 12. Guidelines for Designers and Builders - Domestic Sites Section 1 - General Information and Single Occupancy Dwellings Page 12 1.10 Meter Box Dimensions The following diagrams give dimensions for both types of meter boxes, surface mounted and recessed. Surface Mounted Meter Box with ventilation The new and improved surface mounted meter boxes are slimmer with additional vents that ensure it is not as obtrusive as previously. The addition of the cut-out to the cover will allow the cover to be closed securely, if the outlet pipe is sitting proud of the groove in the base plate. This shall allow some additional flexibility in the location of the outlet pipe and for the meter box cover to be secured correctly with the retaining screw. Figure 16: New cut outs at outlet pipe and inlet pipe Accordingly, the outlet pipework should not interfere with the closure of the meter box cover, and the retaining screw and nut are to be secured after completion of any works. Figure 17: Dimensions of surface mounted meter box with vents Inlet vent Cross sectional view New outlet vent 225 489 231.5 173 404 404
  • 13. Page 13 Recessed Meter Box with ventilation Figure 18: Recessed type meter boxes with vents Note: The meter box must not be punctured when recessed into cavity walls or voids. Recessed meter boxes and replacement doors may be sourced from your local builder provider. A list of suppliers can be provided by calling 1850 200 694. Recessed Box: 140mm 210 535 510 409 365 339 595 535 510
  • 14. Guidelines for Designers and Builders - Domestic Sites Section 1 - General Information and Single Occupancy Dwellings Page 14 1.11 Recessed Meter Box in Pillar Enclosure The following drawings illustrate how a meter box would be recessed in a pillar enclosure. Note: The meter box MUST NOT be punctured when recessed into cavity walls or voids. Figure 19: Meter box in pillar enclosure 6mm m.s. Plate for Brick Support 600 A DPM F.G.L. Service pipe ELEVATION Concrete base 713 300 A B B Meter boxes secured to brickwork Voids to be mortar filled SECTION A - A 440 Recessed Meter Box Expanded metal reinforcement to be used every 3rd course Figure 20 Meter box in pillar enclosure
  • 15. Page 15 1.12 Foundation Requirements for Preformed Bend Below Ground There are specific requirements for a preformed bend that is placed below ground. The below figures illustrate these requirements. The minimum depth of cover is 600mm along the entire length of the connection pipe to within 1.5m of the building line, rising (within 1.5m of the building line or, if moling, in the exit pit) to 375mm at the preformed bend. Figures 21 and 22 show this 375 minimum depth of cover to the preformed bend. Note: To accommodate the preformed bend the minimum depth of required cover to the top of the foundation is 450mm. Meter box shall not be placed more than 2 meters from the gable end of the property. Figure 21: Connection pipe with preformed bend attached to Mains showing minimum level of Cover and Foundations required. Figure 22: A minimum cover of 375mm and minimum foundation of 450mm are necessary P/E SDR 11 gas main 450 Min Foundation Level 375mm Min Level Of Cover 1500mm 32/25mm P/E connection pipe 600mm Min Level of Cover Min 600mm Cover to this Point Gas Meter Box Min 1500mm Min 450mm Foundation Level Min 375mm cover 300 mm
  • 16. Guidelines for Designers and Builders - Domestic Sites Section 1 - General Information and Single Occupancy Dwellings Page 16 1.13 Meter Box Internals Once the connection is finalised, Gas Networks Ireland Distribution Operations will install a meter either surface mounted or recessed similar to figure 23 with a regulator and gas meter in the meter box as shown in figure 24. 1.14 To-do list Before a Meter can be Fitted However before the meter can be fitted the following criteria must be satisfied. • Customer must have opened an account with a preferred supplier. • An appointment has been made with a Natural Gas Supplier to connect the meter. • When the Gas Networks Ireland meter installer arrives to site, an accurately completed Declaration of Conformance must be available for collection (signed by a Registered Gas Installer). Once all of the above is in place and a visual inspection is satisfied, meter is fitted and gas is made available. 1.15 Wayleave Gas Networks Ireland has statutory powers to acquire a wayleave by CPO under Section 32 of the Gas Act, 1976. A wayleave once acquired, either by Deed or CPO, becomes a burden on the title of the land and affects all assigns/ successors. CPO’s and completed Deeds of Easement are registered in the Property Registration Authority of Ireland or Registry of Deeds as appropriate. The Deeds provide safety protection on the land for GNI and also entitlements for future development. When is a wayleave required? • Pipelines or Services that traverse private lands to connect new customers. • Private housing estates that are not taken in charge by the Local Authority. • The requirement exists to supply gas to more than one customer. Note: If a Wayleave is required, the project designer(s) and builder must assist in supplying all relevant information (i.e. land ownership) to GNI. Figure 23: Recess Meter box Figure 24: Recessed Meter Box Internals Registered Gas Installer: A registered gas installer is an installer or service engineer, who has completed the required gas installation safety training and who has the necessary insurance to carry out gas installations to the legal standard.
  • 17. 2 Multi-occupancy Dwellings Guidelines for Designers and Builders - Domestic Sites
  • 18. Guidelines for Designers and Builders - Domestic Sites Section 2 - Multi-Occupancy Dwellings Page 18 2.1 Multi-Occupancy Dwellings - General Multi-Occupancy Definition Multi-Occupancy dwelling: A building containing more than two dwellings units. A multiple dwelling can be any of the following: • A purpose built apartment building • An existing single dwelling modified to accommodate a number of separate dwellings • Dwelling units contained in a mixed use building e.g. shops / offices downstairs with dwelling units above Note: A Multi-Occupancy dwelling can be serviced by an individual meter to a plant room that connects each dwelling or a separate meter to each single dwelling. Multi-Meter Definition Meter cabinets/manifolds which contain a number of meters are considered multi- meters and are used for multiple dwellings in a building which contains more than 2 dwelling units. General Meter Requirements Note: In all of the following cases in multi-occupancy dwellings, please contact Gas Networks Ireland at the earliest opportunity to provide the optimum design solution for your project. The meters must be positioned for easy access to, reading or removal. The design or location must protect the meter and its connections against the possibility of corrosion. Meters must not be located where they may be exposed to extreme temperatures or ignition sources (e.g. switch gear). Ventilation of pipework will have a minimum of ½ air change per hour. Pipework and connections to meter must be located at least 0.5 metres away from any electrical equipment or effective ignition sources. Installation up to the Meter Gas Networks Ireland provide and lay all external underground gas mains, and gas connection pipework up to the point of the meter location. The preferred location of meter cabinets or compartments is in an enclosure, external to the building outside the building line. Locating meters internally within the building line is only possible when: • it is not feasible to locate meters externally • and natural gas mains pressure is less than 100mbar. Meters may only be located within the building when site design cannot facilitate them externally. A cabinet or compartment can only be placed inside a building if the gas is at a low pressure of 100mbar or less. The location should be chosen in order to allow for the shortest practicable length of gas connection pipework. In the case of locations where multi meters are allowed there are two options available: • Option 1: External Multi–Meter Location consists of locating multi-meter cabinets/manifolds around the development outside the building line. This is preferable as it is easier to service, ensure operation and get to in case of emergency. This is illustrated in figures 25-27. • Option 2: Internal Multi–Meter Location consists of meters being located inside the building line. There are two variations of this option: Variation A: Meters located in Common Areas shown in figure 28. Variation B: Meters located in an Underground Car Park / Open Basement Area shown in figures 29-33, which consists of : • Type 1: Top-entry cabinets which are pre-fabricated off site. • Type 2: On-site fabricated meter manifold. The structural housing of externally located meters may be either. • Prefabricated housing is illustrated in figures 34-35. • Purpose-Built housing is illustrated in figures 36-41.
  • 19. Page 19 2.2 Option 1: External Multi-meter Location The preferred location for meters supplying units in a multi-occupancy building is in an enclosure, external to the building. Meters may only be located within the building when site design cannot facilitate them externally and the gas pressure is ≤100mbar. The structural housing of externally located meters may be either prefabricated or purpose- built (see further information below). Dimensions of each six meter cabinet: 1160mm high x 750mm wide x 300mm deep. 600mm min. cover Outlet Pipework 63mm P.E. service pipe Figure 26: Purpose-built meter manifold Figure 27: Diagram of pipework and meter cabinet Figure 25: Pre-fabricated meter cabinet Isolation Valve Should be positioned at a minimum distance depending on pressure value. For Medium Pressure (MP) - 4m away. For Low Pressure (LP) - 2m away.
  • 20. Guidelines for Designers and Builders - Domestic Sites Section 2 - Multi-Occupancy Dwellings Page 20 2.3 Option 2: Internal Multi-meter Location - Above Ground Level Variation A: Meters in common areas If the meters supplying the units in a multi-occupancy building cannot be located externally then they may be located within the building line subject to the following: • Low pressure gas network must be available i.e. service pressure less than 100 mbar (Natural Gas). • Meters should be positioned in an area of natural ventilation as close as possible to the external wall where the gas service pipe enters. • Meters may not be located beneath a stairs, unless they are placed within a minimum two hour fire resistant and sealed compartment ventilated directly to the outside of the building. This compartment must not obstruct exits from the building. • Provision should be made for a steel service to enter into the building through a suitable sleeve where traversing a cavity or void. • Care must be taken when locating the external isolation valve where it is freely accessible, e.g. not in a parking area where vehicles may restrict access. • Solid access doors to the cabinet / compartment must be self-closing and non-lockable. • The enclosure, including access doors, must meet the structural and fire resistant requirements applicable to that part of the building. • The ventilation to the outside atmosphere must be provided through suitably sized and constructed ducts, provided at high and low level. Ducts should be protected and constructed to prevent fire damage. • If the compartment is above ground level, each vent should provide 5,000mm2 minimum free area or at least 2.5% of internal floor area, unless it is only ventilated on one side, in which case it is 3.75% of internal floor area, depending on the number of vents, or notional equivalent, whichever is greater. Separation between the meters exits of each ventilating duct to atmosphere must be at least 450mm apart. If the compartment is to be positioned below ground level, Gas Networks Ireland must be consulted for ventilation requirements. • The dimensions required for different meter arrangements is shown on page 25 of this booklet. Ducts are required to provide ventilation for meter compartment. Ducts should be sleeved through cavities, suitably fire rated and provide minimum air openings as detailed above. The enclosure, including access doors, must meet the structural and fire retardant requirements per Building Regulations. Minimum compartment depth of 400mm must be provided for the manifold, not including provision for enclosure or protective barrier External Isolation Valve 600mm min From Mains Area Isolation Valve 100mm min cover At early construction provide Sleeve for Steel Service Pipe. (Service pipe and manifold provided by Gas Networks Ireland.) Steel Manifold Min 2m distance from valve to structure PE Pipe Figure 28: Multiple meter within a building Note: Meters must always be positioned to avoid the possibility of impact with impact protection provided if necessary.
  • 21. Page 21 2.4 Option 2: Internal Multi-meter Location - Below Ground Level Type 1: Top Entry Cabinets pre-fabricated off-site Dimensions of each six meter cabinet: 1160mm high x 750mm wide x 300mm deep. External min 2m distance from valve to structure Isolation Valve 600mm minimum cover required P.E. Pipe Area Isolation Valve Natural Ventilation 600mm min. Contains Six Meters Contains Six Meters Top-entry cabinets open to naturally ventilated area 1800mm max. At early construction provide suitable sleeve for Steel Service Pipe (Service pipe and manifold provided by Gas Networks Ireland) Steel Pipe Figure 30: Top-entry cabinets in underground car park open basement area Figure 29: Top entry cabinet pre-fabricated off site. Read in conjunction with page 22. • Provision should be made for the steel service to enter into the building through an appropriate sleeve traversing a cavity or void. • The gas service must pass through a ventilated area that is publicly accessible (i.e. providing access for Gas Networks Ireland maintenance at all times). • Electrical current carrying equipment or cables must not be in contact with or suspended from gas equipment or plant. • Meters must always be positioned so to avoid the possibility of impact with impact protection provided if necessary. • If it is required that the meters or gas service be located in a dedicated room within the basement or in a basement lacking natural ventilation, Gas Networks Ireland must be consulted for specifications and ventilation requirements. • Care should be taken when locating the external isolation valve so that it is freely accessible at all times, e.g. not in a parking area where vehicles may restrict access. Variation B: Underground car park or open basement Meters located in an underground car park or open basement area must have direct access to natural ventilation. Mechanical ventilation may not be relied upon. There are two types of meters that can be located in an underground car park or open basement area: • Type 1: Top-entry cabinets which are pre-fabricated off site. • Type 2: On-site fabricated meter manifold.
  • 22. Guidelines for Designers and Builders - Domestic Sites Section 2 - Multi-Occupancy Dwellings Page 22 Type 2: On-site fabricated meter manifold If manifold is at a level exposed to possible impact, additional provision must be made with a protective barrier. At early construction provide suitable sleeve for Steel Service Pipe (Service pipe and manifold provided by Gas Networks Ireland) External Isolation Valve 600mm minimum cover required P.E. Pipe From Mains Manifold located at high level, minimum depth required is 400mm. Steel manifold open to naturally ventilated area Area Isolation Valve 600 mm min 1800mm max Steel Pipe Min 2m distance from valve to structure Figure 31: Meters in underground car park / open basement area Figure 32: On-site meter manifold Figure 33: Supply pipework supported at ceiling level Read in conjunction with page 21. However, if located internally, they must be installed at a minimum of 300 mm above finished ground level. • The meter installation must not be directly located beneath a ventilation grille or in a position liable to cause ingress of water, unless weather protected. • If required at low level a protective barrier must be placed around the meters. Sufficient impact resistance provided by the builder. • In the case of the steel manifold, protection from tamper and impact may be provided by the provision of a suitable steel cage. The use of a steel mesh caging will allow for ease of meter reading. The area isolation valve must remain accessible at all times. For the dimensions required for differing meter manifold arrangements see figure 42 page 25. External Isolation Valve 600mm minimum cover required From Mains Area Isolation Valve 600 mm min 1800mm max
  • 23. Page 23 Figure 35: Apartment Meter Details 2.5 Multi-Meter Compartment Types There are two types of meter cabinets or compartments that are used with multiple meters. Pre-fabricated meters A prefabricated meter cabinet is surfaced-mounted on a wall using the brackets and bolts supplied. The GRP cabinets are pre-drilled at the back to take the threads of the support bolts. The cabinets are to be installed a minimum of 300mm above Finished Ground Level (F.G.L) in order to allow connection by the Distribution Mains Crew on site using a service riser. The multi-meter cabinet internals consist of an isolation valve, integral filter, regulator and pre-piped manifold supplying six domestic meter points. The heating installer connects directly to the fixed outlets outside the cabinet. It is not permitted to recess a multi-meter cabinet into the external wall of the building, unless all of the requirements outlined on pages 24 & 25 of this booklet are met. Support Brackets 750mm L.P. / M.P. Regulator 63mm polyethylene inlet pipe Openings to suit 3 no. Outlet Pipes (3/4” Copper) 295mm 1160mm F.G.L 600 mm minimum cover required 300mm Figure 34: Pre-fabricated meter cabinet
  • 24. Guidelines for Designers and Builders - Domestic Sites Section 2 - Multi-Occupancy Dwellings Page 24 Purpose built meter compartment A purpose-built meter compartment consists of a welded manifold with individual isolation valves, regulators and domestic valves. The regulators and domestic meter will be installed at a later date. This meter arrangement may be located away from the building or recessed into the outer leaf of the building structure. Note: Purpose built compartments for gas meters are not to be used for any other purpose (e.g. storage of bins or any other equipment.) 1. If recessed into the structure of the building or to be placed within the building line the meters must be in a completely sealed compartment with the exception of access and ventilation provided by louvered doors to the outside air. This arrangement is only permitted on a low pressure site i.e. gas pressure ≤ 100mbar. 2. The compartment must meet the structural and fire resistant requirements applicable to that part of the building. All voids within and around the compartment must be fully sealed and fire proofed to prevent the ingress of air or gas to the cavity wall or other voids. Outer leaf Sleeve Pipe Temperature Resistant Mastic Inner leafCavity Pipes must have supporting brackets For Outlet Pipe Requirements See Detail A 400mm min. 100mm Floor Slabs Steel Gas Service Ground Level 600mm minimum cover required 300mm min. 300mm min. Block / Brick Construction Hardwood Louvred Doors complete with Hinges and Locking Device Valve min 2m from structure Figure 37: Inside meter compartment detail Figure 39: Sleeving Detail A Figure 36: Plan Detail Figure 38: Elevation Pipes must have supporting brackets For Outlet Pipe Requirements See Detail A 400mm min. Plan Detail: Inside Meter Compartment Detail: 100mm Floor Slabs Steel Gas Service Ground Level 600mm minimum cover required Sleeving Detail A: Outer leaf Sleeve Pipe Temperature Resistant Mastic Inner leafCavity Block / Brick Construction Elevation: Hardwood Louvred Doors complete with Hinges and Locking Device
  • 25. Page 25 3. If the enclosure opens to the outside but is set within the building structure then all pipe sleeves or entries into the building must be sealed with an approved fire sealing material. Access doors should not be lockable. Ventilation must be provided to atmosphere in the form of a fully louvered door or in the case of a solid door, vents must be located at the top and the bottom of the door. Each vent must provide a minimum of 5,000mm2 free area, or at least 2.5% of internal floor area, unless it is only ventilated on one side, in which case it is 3.75% of internal floor area, depending on the number of vents, or notional equivalent, whichever is greater. 4. Meter compartments are to be located outside apartment walls in well-ventilated areas provided by the builder. 5. The builder must open ground to allow for steel gas service into the meter compartment. For internal dimensions for various meter configurations, please consult figure 42 below. Figure 41: Purpose built meter manifold in purpose built meter compartment block/brick construction Figure 40: Purpose-built meter manifold 2.6 Internal Building Dimensions for various Meter Bank Configurations Note: If placing meters at low level, always allow for an extra 300mm beneath lowest meter point. 3 x 32 x 3 2200 2 x 4 3 x 4 1650 1100 550 3 x 22 x 2 2 x 1 3 x 1 6 x 35 x 34 x 3 4 x 4 5 x 4 6 x 4 5 x 24 x 2 4 x 1 5 x 1 6 x 2 6 x 1 855 1195 1535 1875 2215 7 x 3 7 x 4 7 x 2 7 x 1 2555 Figure 42: Internal Building Dimensions for Various Meter Bank Configurations
  • 26. Guidelines for Designers and Builders - Domestic Sites Section 3 - Conclusion & Appendices Page 26 Readers Notes
  • 27. Page 27 3 Conclusion & Appendices Guidelines for Designers and Builders - Domestic Sites
  • 28. Guidelines for Designers and Builders - Domestic Sites Section 3 - Conclusion & Appendices Page 28 These items are to be checked by the Sales Rep - Yes/No/NA If NO or NA please give a reason in remarks. Comments / Remarks/ Specific Requirements – Specify as much detail as possible to aid in the design process. 3.1 Checklist of Essential Information required by Design This must be supplied with the project The following is the current essential information required for Gas Networks Design. The list below is to outline what is required, the developer/builder must give this information to the Gas Networks Ireland Sales representative in order to process the project. Figure 43: Checklist of information required by Gas Networks Ireland Sales Representative. Meter Locations Must be clearly marked on site layout maps or stated clearly in project remarks (this includes New Housing Sites). Site layout Plans All New Build / Greenfield Sites require a Detailed Site Layout Plan that is compatible with Autocad (including External References if required). Elevation Drawings These are required for all 4bar projects where the meter is to be located on, or within 3m of the building. (PDF format will suffice) Basement Plans These are required for all builds where meters are to be located in a basement (including New Housing / Apartments site (Autocad format required). Ventilation Basement works and internal meter locations require Client confirmation of adequate natural ventilation. Mains/Service Pipe Routing If known. Builder/ Developer Please provide necessary details in the remarks / log. E.g. Specific Requirements Will the trench be provided on site? / What date is the gas required for if known?
  • 29. Page 29 3.2 Irish Standards This document is to be used for guidance purposes and makes reference to the relevant Irish Standards as shown below however it must not conflict with or be used as a substitute for the standards should any conflict arise, the Irish standards take precedence. For gas and main services Gas Networks Ireland will install all gas mains and services in accordance with the latest edition of the following Irish Standards: I.S. 329 “Code of Practise for Gas Distribution Mains” and I.S.265 “Installation of Gas Service Pipes”. E.T.C.I. National rules for electrical installations, Part 1, General requirements, Section 5.4.6. RGII Tel: 1850 454 454 www.rgii.ie For downstream of the meter Irish Standard I.S.813 “Domestic Gas Installations” and I.S.820 “Non-Domestic Gas Installations” Apply to the gas installation downstream of the point of delivery (normally the meter). These Standards are the code of practice for natural gas installation requirements downstream of the point of delivery and includes the requirements for meters, appliances and associated pipework in single and multiple occupancy dwelling. All of the above standards can be obtained from the NSAI (National Standards Authority of Ireland). Telephone (01) 8073800 Appendix - Excavations Parallel to Walls With reference to figure 4, dig a trial hole to determine the depth of the foundations or base of the wall, taking care to avoid undercutting the foundation/base. Excavation work must not proceed if the wall is leaning, cracked or showing any signs of instability or distress. Note: Please ensure the distance from the trench to the bottom of the foundations (W), is greater than the length from the bottom of the foundations to the pipe, (X). Otherwise please see conditions below: • reduce the depth of the trench, or • provide suitable support appropriate to the type of structure, soil characteristics and depth of trench. Figure 44: Proximity of trench to walls Figure 45: Proximity of walls to foundation Otherwise please see conditions below: • move the trench so that the distance from the trench to the wall is greater than the depth of the trench, or • trial hole carried out. Note: All personnel shall stay out of the area (S) during excavation work.
  • 30. Page 30 Guidelines for Designers and Builders - Domestic Sites Section 3 - Conclusion & Appendices Readers Notes
  • 31. Page 31 Disclaimer All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the publishers. The advice contained within this document is a guideline only and based on the most authoritative information available at the date of issue. Users should ensure that it is relevant to the specific circumstances in which they seek to apply it. Professional advice should always be sought. Although every effort has been made to ensure information is correct, no responsibility will be accepted for any errors or omissions, nor any loss or damage which may arise from errors or omissions. Current Laws, Regulations and Standards over-ride all contents of this guideline document. Users should ensure they have up to date information. © Gas Networks Ireland.
  • 32. Page 32 The main contact details for Gas Networks Ireland are: General Enquiries 1850 200 694 24hr Emergency Service 1850 20 50 50 info@gasnetworks.ie @GasNetIRL gasnetworks.ie 37565/02/2016