Dokumen tersebut menyediakan garis panduan langkah pencegahan Covid-19 di tapak pembinaan untuk memastikan keselamatan dan mengurangkan risiko penularan. Ia meliputi langkah-langkah seperti saringan kesihatan, pengangkutan pekerja, amalan di tapak pembinaan seperti penjarakan sosial, dan kebersihan. Dokumen ini bertujuan membantu pihak berkaitan mengambil langkah berjaga-jaga di tapak
Dokumen tersebut memberikan prosedur penanganan bahan kimia yang mencakup pengadaan, bongkar muat, penyimpanan, pengangkutan, dan penggunaan bahan kimia. Prosedur tersebut bertujuan untuk mencegah kecelakaan dan menjaga keselamatan kerja.
Protokol Perkantoran yang kembali laksanakan WFORafael Ryandika
Β
Keputusan Kepala Dinas Tenaga Kerja, Transmigrasi dan Energi Provinsi DKI Jakarta menetapkan protokol pencegahan dan pengendalian Covid-19 di perkantoran dan tempat kerja selama masa transisi, termasuk pembatasan 50% karyawan masuk kantor, penyesuaian jam dan shift kerja, pengaturan fasilitas, pemantauan kesehatan, dan pemberian sanksi bagi pelanggaran protokol.
Spesifikasi teknis mencakup ketentuan umum pelaksanaan proyek, ketentuan K3, dan organisasi K3. Ketentuan umum mencakup pedoman pelaksanaan, pengawasan, dan tanggung jawab atas lingkungan dan kerusakan. Ketentuan K3 meliputi administrasi, organisasi, laporan kecelakaan, pertolongan pertama, dan biaya. Organisasi K3 membahas petugas K3, panitia K3, dan kerja sama antar penyedia jasa.
Dokumen tersebut merupakan rencana kerja dan syarat teknis untuk proyek pembangunan ruang media center di Kementerian Kelautan dan Perikanan. Dokumen tersebut menjelaskan lingkup pekerjaan, kondisi lokasi, prosedur pendahuluan, persyaratan bahan dan komponen, pekerjaan sementara, perlindungan keselamatan, dan persyaratan lainnya yang harus dipenuhi kontraktor dalam melaksanakan proyek tersebut.
SURAT EDARAN DAN GARIS PANDUAN PENGURUSAN KAWALAN PENULARAN COVID-19 KPM.pdfSOLAHMAKKIAHBINTIHAJ
Β
Garis panduan ini menjelaskan tanggungjawab Ketua Jabatan KPM dalam menguruskan premis kerajaan dan warga KPM untuk mencegah penularan COVID-19. Ia meliputi pengurusan premis, pegawai, pelanggan dan kontraktor serta memastikan semua warga KPM melengkapkan imunisasi COVID-19 atau menjalani ujian pengesanan secara berkala. Ketua Jabatan perlu memastikan protokol kesihatan dipatuhi sepenuhnya termas
Dokumen tersebut memberikan prosedur penanganan bahan kimia yang mencakup pengadaan, bongkar muat, penyimpanan, pengangkutan, dan penggunaan bahan kimia. Prosedur tersebut bertujuan untuk mencegah kecelakaan dan menjaga keselamatan kerja.
Protokol Perkantoran yang kembali laksanakan WFORafael Ryandika
Β
Keputusan Kepala Dinas Tenaga Kerja, Transmigrasi dan Energi Provinsi DKI Jakarta menetapkan protokol pencegahan dan pengendalian Covid-19 di perkantoran dan tempat kerja selama masa transisi, termasuk pembatasan 50% karyawan masuk kantor, penyesuaian jam dan shift kerja, pengaturan fasilitas, pemantauan kesehatan, dan pemberian sanksi bagi pelanggaran protokol.
Spesifikasi teknis mencakup ketentuan umum pelaksanaan proyek, ketentuan K3, dan organisasi K3. Ketentuan umum mencakup pedoman pelaksanaan, pengawasan, dan tanggung jawab atas lingkungan dan kerusakan. Ketentuan K3 meliputi administrasi, organisasi, laporan kecelakaan, pertolongan pertama, dan biaya. Organisasi K3 membahas petugas K3, panitia K3, dan kerja sama antar penyedia jasa.
Dokumen tersebut merupakan rencana kerja dan syarat teknis untuk proyek pembangunan ruang media center di Kementerian Kelautan dan Perikanan. Dokumen tersebut menjelaskan lingkup pekerjaan, kondisi lokasi, prosedur pendahuluan, persyaratan bahan dan komponen, pekerjaan sementara, perlindungan keselamatan, dan persyaratan lainnya yang harus dipenuhi kontraktor dalam melaksanakan proyek tersebut.
SURAT EDARAN DAN GARIS PANDUAN PENGURUSAN KAWALAN PENULARAN COVID-19 KPM.pdfSOLAHMAKKIAHBINTIHAJ
Β
Garis panduan ini menjelaskan tanggungjawab Ketua Jabatan KPM dalam menguruskan premis kerajaan dan warga KPM untuk mencegah penularan COVID-19. Ia meliputi pengurusan premis, pegawai, pelanggan dan kontraktor serta memastikan semua warga KPM melengkapkan imunisasi COVID-19 atau menjalani ujian pengesanan secara berkala. Ketua Jabatan perlu memastikan protokol kesihatan dipatuhi sepenuhnya termas
Dokumen tersebut memberikan ringkasan singkat tentang protokol dan aktiviti yang dibenarkan dalam sektor kebersihan, pembinaan, dan pengurusan strata selama tempoh PKP. Ia menekankan langkah pencegahan COVID-19 seperti penjarakan sosial, pemakaian topeng muka, dan pembersihan tangan serta menetapkan had kehadiran pekerja.
1. Dokumen tersebut memberikan panduan mengenai prosedur operasi standard untuk pengurusan dan pencegahan pasca COVID-19 di IPG Kampus Tengku Ampuan Afzan, Pahang.
2. Terdapat beberapa norma baharu yang perlu dipatuhi seperti menjaga jarak sosial, memakai topeng muka, dan mengamalkan kebersihan tinggi.
3. Dokumen tersebut juga menjelaskan peranan dan tanggungjawab pelbagai pihak termasuk peng
1. Dokumen membahas pentingnya penerapan K3 di tempat kerja seiring dengan era perdagangan bebas. K3 bertujuan mencegah kecelakaan kerja dan menjamin kesehatan pekerja. Pemerintah telah menetapkan peraturan tentang sistem manajemen K3 yang wajib diterapkan perusahaan.
Method Of Work Unloading Container With Forklift.docxbaronandritti
Β
Method Of Work Unloading Container with Forklift, a procedure that describes unloading empty containers with a forklift for site office purposes on a project. makes work easy and safe and includes several tools that are used and required to do it.
Sk kadis dan lampiran masa transisi (1)danudamarjati
Β
Keputusan Kepala Dinas Pariwisata dan Ekonomi Kreatif Provinsi DKI Jakarta menetapkan protokol pencegahan penularan COVID-19 di sektor usaha pariwisata pada masa transisi menuju masyarakat sehat, aman dan produktif. Protokol ini mencakup pedoman umum dan tambahan untuk berbagai jenis usaha pariwisata, serta mekanisme pengendalian protokol kesehatan internal dan eksternal. Protokol ini berlaku untuk memastikan kegiatan
Protokol K3 Konstruksi Saat Pandemi Covid-19 memberikan panduan untuk menerapkan protokol kesehatan dalam konstruksi selama pandemi, meliputi pembentukan satgas Covid-19, identifikasi bahaya penularan, dan penyediaan fasilitas kesehatan. Dokumen ini juga menjelaskan dasar hukum dan mekanisme penerapan protokol kesehatan serta kewenangan untuk menghentikan kegiatan bila diperlukan.
Surat Menteri BUMN mewajibkan setiap BUMN membentuk tim penanganan COVID-19 dan menyusun protokol penanganan serta timeline pemulihan kegiatan secara bertahap dari Mei hingga Agustus dengan mengutamakan kesehatan karyawan, pelanggan, dan pemasok.
Rencana Keselamatan Konstruksi (RKK) membahas rencana keselamatan untuk pembangunan Masjid Al Mumtaz. RKK meliputi kepemimpinan dan komitmen keselamatan, perencanaan keselamatan melalui identifikasi bahaya dan penilaian risiko, dukungan sumber daya keselamatan, operasi keselamatan, dan evaluasi kinerja keselamatan. Program keselamatan yang dirancang antara lain pemeliharaan lingkungan kerja, penggunaan alat pelind
Se sesjen nomor 20 tahun 2020 tentang sistem kerja pegawai kemendikbud dalam ...Ade Agoess
Β
Surat Edaran ini memberikan pedoman bagi pegawai Kementerian Pendidikan dan Kebudayaan dalam menyesuaikan sistem kerja di masa normal baru dengan memprioritaskan kesehatan dan produktivitas. Pedoman tersebut mencakup penyesuaian sistem kerja, penilaian kinerja, pemantauan, disiplin, dukungan infrastruktur, serta penerapan protokol kesehatan ketat di kantor dan saat perjalanan dinas.
[Ringkasan]
Dokumen tersebut membahas tentang penerapan sistem manajemen keselamatan dan kesehatan kerja (SMK3) sesuai dengan peraturan pemerintah. Ia menjelaskan 5 prinsip dasar dalam penerapan SMK3 yaitu penetapan kebijakan K3, perencanaan K3, pelaksanaan rencana K3, pemantauan dan evaluasi kinerja K3, serta peninjauan dan peningkatan kinerja SMK3. Dokumen ini juga menjelaskan
Peraturan ini mengatur tentang pelaksanaan reklamasi dan pascatambang pada kegiatan usaha pertambangan minerba. Dokumen ini menjelaskan tentang penyusunan rencana reklamasi tahap eksplorasi dan operasi produksi serta rencana pascatambang, termasuk kriteria, biaya, dan penilaian persetujuan rencana-rencana tersebut.
Dokumen tersebut merupakan bagian dari spesifikasi teknis untuk pekerjaan mekanikal pada proyek perluasan laboratorium. Ia mencakup ruang lingkup pekerjaan plumbing dan pemipaan yang meliputi sistem air bersih, air kotor, limbah, serta persyaratan material dan pemasangan pipa. Kontraktor wajib mengajukan desain dan menjamin kelayakan instalasi selama satu tahun.
Ringkasan dokumen tersebut adalah:
1. Dokumen tersebut merupakan metode pelaksanaan proyek pembangunan lapangan bola di Kecamatan Sungai Pagu yang mencakup rencana administrasi, manajemen proyek, pengadaan bahan dan peralatan, jadwal, dan pengawasan mutu pekerjaan.
2. Waktu pelaksanaan proyek ini adalah 120 hari kalender dan menguraikan pengaturan fasilitas lapangan, struktur organisasi, ko
PP No. 41 Tahun 2012 mengatur tentang jenis, standarisasi, sertifikasi, peredaran, dan penggunaan alat dan mesin peternakan serta kesehatan hewan. Dokumen ini menjelaskan ketentuan mengenai jenis alat dan mesin yang diatur, proses pengadaan, standarisasi, sertifikasi, dan pengawasan peredaran serta penggunaannya. Sanksi diberlakukan terhadap pelanggaran ketentuan dalam peraturan ini.
Sistem Penilaian Keselamatan dan Kesihatan dalam Pembinaan atau SHASSIC bertujuan menilai prestasi kontraktor dalam pengurusan keselamatan dan kesihatan di tapak pembinaan. Ia terdiri daripada 3 komponen utama: semakan dokumen, pemeriksaan tapak kerja, dan temubual pekerja. SHASSIC memberi manfaat kepada kontraktor untuk mengenal pasti kelemahan dan meningkatkan amalan keselamatan melalui latihan.
This document outlines the agenda and content for a training session on the Safety Health Assessment System in Construction (SHASSIC). The agenda covers an overview of SHASSIC and the construction industry, SHASSIC assessment approaches including document review, workplace inspection, and employee interviews. It also discusses the SHASSIC scoring methodology and provides examples of score calculations. The training aims to guide participants on how to assess construction project safety and health performance using the SHASSIC framework.
Dokumen tersebut memberikan ringkasan singkat tentang protokol dan aktiviti yang dibenarkan dalam sektor kebersihan, pembinaan, dan pengurusan strata selama tempoh PKP. Ia menekankan langkah pencegahan COVID-19 seperti penjarakan sosial, pemakaian topeng muka, dan pembersihan tangan serta menetapkan had kehadiran pekerja.
1. Dokumen tersebut memberikan panduan mengenai prosedur operasi standard untuk pengurusan dan pencegahan pasca COVID-19 di IPG Kampus Tengku Ampuan Afzan, Pahang.
2. Terdapat beberapa norma baharu yang perlu dipatuhi seperti menjaga jarak sosial, memakai topeng muka, dan mengamalkan kebersihan tinggi.
3. Dokumen tersebut juga menjelaskan peranan dan tanggungjawab pelbagai pihak termasuk peng
1. Dokumen membahas pentingnya penerapan K3 di tempat kerja seiring dengan era perdagangan bebas. K3 bertujuan mencegah kecelakaan kerja dan menjamin kesehatan pekerja. Pemerintah telah menetapkan peraturan tentang sistem manajemen K3 yang wajib diterapkan perusahaan.
Method Of Work Unloading Container With Forklift.docxbaronandritti
Β
Method Of Work Unloading Container with Forklift, a procedure that describes unloading empty containers with a forklift for site office purposes on a project. makes work easy and safe and includes several tools that are used and required to do it.
Sk kadis dan lampiran masa transisi (1)danudamarjati
Β
Keputusan Kepala Dinas Pariwisata dan Ekonomi Kreatif Provinsi DKI Jakarta menetapkan protokol pencegahan penularan COVID-19 di sektor usaha pariwisata pada masa transisi menuju masyarakat sehat, aman dan produktif. Protokol ini mencakup pedoman umum dan tambahan untuk berbagai jenis usaha pariwisata, serta mekanisme pengendalian protokol kesehatan internal dan eksternal. Protokol ini berlaku untuk memastikan kegiatan
Protokol K3 Konstruksi Saat Pandemi Covid-19 memberikan panduan untuk menerapkan protokol kesehatan dalam konstruksi selama pandemi, meliputi pembentukan satgas Covid-19, identifikasi bahaya penularan, dan penyediaan fasilitas kesehatan. Dokumen ini juga menjelaskan dasar hukum dan mekanisme penerapan protokol kesehatan serta kewenangan untuk menghentikan kegiatan bila diperlukan.
Surat Menteri BUMN mewajibkan setiap BUMN membentuk tim penanganan COVID-19 dan menyusun protokol penanganan serta timeline pemulihan kegiatan secara bertahap dari Mei hingga Agustus dengan mengutamakan kesehatan karyawan, pelanggan, dan pemasok.
Rencana Keselamatan Konstruksi (RKK) membahas rencana keselamatan untuk pembangunan Masjid Al Mumtaz. RKK meliputi kepemimpinan dan komitmen keselamatan, perencanaan keselamatan melalui identifikasi bahaya dan penilaian risiko, dukungan sumber daya keselamatan, operasi keselamatan, dan evaluasi kinerja keselamatan. Program keselamatan yang dirancang antara lain pemeliharaan lingkungan kerja, penggunaan alat pelind
Se sesjen nomor 20 tahun 2020 tentang sistem kerja pegawai kemendikbud dalam ...Ade Agoess
Β
Surat Edaran ini memberikan pedoman bagi pegawai Kementerian Pendidikan dan Kebudayaan dalam menyesuaikan sistem kerja di masa normal baru dengan memprioritaskan kesehatan dan produktivitas. Pedoman tersebut mencakup penyesuaian sistem kerja, penilaian kinerja, pemantauan, disiplin, dukungan infrastruktur, serta penerapan protokol kesehatan ketat di kantor dan saat perjalanan dinas.
[Ringkasan]
Dokumen tersebut membahas tentang penerapan sistem manajemen keselamatan dan kesehatan kerja (SMK3) sesuai dengan peraturan pemerintah. Ia menjelaskan 5 prinsip dasar dalam penerapan SMK3 yaitu penetapan kebijakan K3, perencanaan K3, pelaksanaan rencana K3, pemantauan dan evaluasi kinerja K3, serta peninjauan dan peningkatan kinerja SMK3. Dokumen ini juga menjelaskan
Peraturan ini mengatur tentang pelaksanaan reklamasi dan pascatambang pada kegiatan usaha pertambangan minerba. Dokumen ini menjelaskan tentang penyusunan rencana reklamasi tahap eksplorasi dan operasi produksi serta rencana pascatambang, termasuk kriteria, biaya, dan penilaian persetujuan rencana-rencana tersebut.
Dokumen tersebut merupakan bagian dari spesifikasi teknis untuk pekerjaan mekanikal pada proyek perluasan laboratorium. Ia mencakup ruang lingkup pekerjaan plumbing dan pemipaan yang meliputi sistem air bersih, air kotor, limbah, serta persyaratan material dan pemasangan pipa. Kontraktor wajib mengajukan desain dan menjamin kelayakan instalasi selama satu tahun.
Ringkasan dokumen tersebut adalah:
1. Dokumen tersebut merupakan metode pelaksanaan proyek pembangunan lapangan bola di Kecamatan Sungai Pagu yang mencakup rencana administrasi, manajemen proyek, pengadaan bahan dan peralatan, jadwal, dan pengawasan mutu pekerjaan.
2. Waktu pelaksanaan proyek ini adalah 120 hari kalender dan menguraikan pengaturan fasilitas lapangan, struktur organisasi, ko
PP No. 41 Tahun 2012 mengatur tentang jenis, standarisasi, sertifikasi, peredaran, dan penggunaan alat dan mesin peternakan serta kesehatan hewan. Dokumen ini menjelaskan ketentuan mengenai jenis alat dan mesin yang diatur, proses pengadaan, standarisasi, sertifikasi, dan pengawasan peredaran serta penggunaannya. Sanksi diberlakukan terhadap pelanggaran ketentuan dalam peraturan ini.
Sistem Penilaian Keselamatan dan Kesihatan dalam Pembinaan atau SHASSIC bertujuan menilai prestasi kontraktor dalam pengurusan keselamatan dan kesihatan di tapak pembinaan. Ia terdiri daripada 3 komponen utama: semakan dokumen, pemeriksaan tapak kerja, dan temubual pekerja. SHASSIC memberi manfaat kepada kontraktor untuk mengenal pasti kelemahan dan meningkatkan amalan keselamatan melalui latihan.
This document outlines the agenda and content for a training session on the Safety Health Assessment System in Construction (SHASSIC). The agenda covers an overview of SHASSIC and the construction industry, SHASSIC assessment approaches including document review, workplace inspection, and employee interviews. It also discusses the SHASSIC scoring methodology and provides examples of score calculations. The training aims to guide participants on how to assess construction project safety and health performance using the SHASSIC framework.
This document contains a machinery inspection checklist used to inspect various types of construction equipment. The checklist includes items like body structure, hydraulic hoses, leakages, lights, fire extinguishers, brakes, lubrication levels, and safety equipment. Mechanics use this checklist to systematically inspect equipment, note any issues found, and get supervisor approval.
This document contains information relating to a SHASSIC (Safety and Health Assessment System in Construction) assessment for a construction project. It includes an agenda for the assessment activities over one day, which involves document review, questionnaires for different levels of staff, and a site inspection. Forms are provided to record attendance, document checklist results, and collect information on the project and SHASSIC assessment. The document aims to provide structure and records for conducting the SHASSIC assessment of the construction project's safety and health system and performance.
Sistem Penilaian Keselamatan dan Kesihatan dalam Pembinaan atau SHASSIC bertujuan menilai prestasi kontraktor dalam pengurusan keselamatan dan kesihatan di tapak pembinaan. Ia terdiri daripada 3 komponen utama: semakan dokumen, pemeriksaan tapak kerja, dan temubual pekerja. SHASSIC memberi manfaat kepada kontraktor untuk mengenal pasti kelemahan dan meningkatkan amalan keselamatan melalui latihan.
Dokumen ini memberikan panduan untuk pengawal bendera dalam mengawal lalulintas di tapak pembinaan. Ia menjelaskan tanggungjawab pengawal bendera untuk mengekalkan kecekapan dan keselamatan lalulintas dengan menggunakan peralatan seperti bendera, baton cahaya dan pakaian reflektif. Dokumen ini juga memberikan panduan untuk tindakan seperti memberi isyarat untuk memperlahankan, menghentikan
Heat stroke is a life-threatening condition caused by the body overheating, usually as a result of prolonged exposure to or physical exertion in high temperatures. It is characterized by an elevated core body temperature above 40Β°C and alterations in the central nervous system. Left untreated, heat stroke can cause death or permanent disability. Those at highest risk include children, the elderly, those with chronic illnesses, athletes, and outdoor workers. To prevent heat stroke, it is important to stay hydrated, limit strenuous activity during hot weather, wear loose-fitting clothing, and monitor for symptoms in high-risk groups. Immediate cooling of the body and medical help are needed if heat stroke occurs.
This document discusses the health effects of cigarette smoking. It notes that cigarettes contain over 7,000 chemical compounds, including 70 that are carcinogenic. The four worst diseases caused by smoking are heart disease, stroke, COPD, and lung cancer. Quitting smoking is difficult due to nicotine addiction but can significantly improve health outcomes over time by reducing risks of these and other smoking-related diseases. The document also covers the dangers of secondhand and thirdhand smoke exposure.
The document provides information on a training program on Safety Health Assessment System in Construction (SHASSIC). It includes an agenda for the training with topics such as Construction Industry Overview, SHASSIC Overview, Assessors Guide for Document Check, Workplace Inspection and Interview. It also includes formulas and examples for calculating SHASSIC scores based on compliance and non-compliance during the Document Check and Workplace Inspection assessments. Special situations with different number of high risk activities are also covered.
This document presents the Construction Industry Standard (CIS 10:2020) for the Safety and Health Assessment System in Construction (SHASSIC) in Malaysia. SHASSIC provides a standardized method to assess and evaluate contractors' occupational safety and health performance on construction projects. It involves assessing documentation, inspecting workplaces, and interviewing employees. The assessment covers various safety and health aspects such as policies, hazard identification, training, emergency response, and performance monitoring. Compliance with SHASSIC helps contractors improve their safety practices but does not guarantee legal compliance. The standard references several Malaysian occupational safety laws and regulations.
This handbook provides guidance on worker safety for riggers and signalmen. It outlines proper attire and safety equipment, roles and responsibilities, good and bad rigging practices, inspections of lifting equipment, and crane hand signals. The handbook aims to help riggers and signalmen understand their roles to ensure safe lifting operations through correct rigging, inspections, communication and following recommended signals. Maintaining good communication between all parties is emphasized.
The document consists of repetitions of the name "HASNIZAM BIN MD SAAD" appearing on different lines without any other context or information provided.
This document outlines safety requirements and procedures for formwork structures used in concrete construction. It specifies that a professional engineer must design complex or tall formwork structures and provide documentation. Requirements include using sound materials, bracing, fall protection, inspection, and following the engineer's design and dismantling procedures. The formwork must safely support all loads and be constructed, concreted, and dismantled safely according to the engineer's specifications and risk assessments.
The document recommends wearing face masks, using hand sanitizer, practicing social distancing, and maintaining personal space for safety and health. It is signed by Hasnizam Md Saad, an occupational safety and health practitioner, suggesting these are guidelines for protecting against illness.
This document provides guidance from MRCB Group of Companies on preventing the spread of COVID-19 at construction project sites. It outlines procedures for monitoring the virus situation, producing a business continuity plan, preventing infection through hand hygiene and distancing measures, and certifying sick leave. The guidance is intended to safeguard workers and operations during the COVID-19 outbreak while following the latest advisories from Malaysian health authorities.
Program SoHELP bertujuan untuk meningkatkan tahap kepatuhan terhadap kesihatan pekerjaan terutamanya dalam pengurusan bahan kimia, bunyi dan ergonomi. Ia melibatkan kerjasama antara pihak berkuasa kesihatan dan keselamatan pekerjaan dengan syarikat untuk menilai dan meningkatkan amalan kesihatan pekerjaan melalui lima peringkat pelaksanaan.
The document contains safety guidelines and requirements for working at heights from Hasnizam Md Saad, the Safety & Health Officer at MRCB Learning Development Centre in Kuala Lumpur. It addresses the need to use proper personal protective equipment when working over 3 meters high or on scaffolding. Checklists are provided on roles and responsibilities, competence training, signage requirements, and examples of unsafe conditions like missing guardrails or unstable scaffolding. Contact details for Hasnizam are listed for any safety-related questions.
The document discusses project S210 to construct elevated stations and associated works at Cyberjaya City Centre and Putrajaya Sentral on the Mass Rapid Transit Line 2 from Sungai Buloh to Serdang to Putrajaya. It includes contract details and discusses safe forklift operation procedures such as pre-operation checks, fueling, loading, unloading, and trailer operations to prevent accidents and injuries.
This document outlines the safe operating procedure for lifting using excavators on the Sungai Besi - Ulu Kelang (SUKE) Highway Project. It lists requirements such as possessing a valid lifting machinery certificate, clearly marking the safe working load, using an original manufacturer lifting hook, deploying a signalman, only travelling with the arm and boom retracted, having loads rigged by trained riggers under supervision, and requiring operators and riggers to be trained and competent. The procedure is part of MRCB Builders' efforts to ensure excavator lifting is done safely according to regulations on the highway construction project.
Workshop "CSR & Community Development (ISO 26000)"_di BALI, 26-28 Juni 2024Kanaidi ken
Β
Dlm wktu dekat, Pelatihan/WORKSHOP βCSR/TJSL & Community Development (ISO 26000)β akn diselenggarakan di Swiss-BelHotel β BALI (26-28 Juni 2024)...
Dgn materi yg mupuni & Narasumber yg kompeten...akn banyak manfaat dan keuntungan yg didpt mengikuti Pelatihan menarik ini.
Boleh jga info iniπ utk dishare_kan lgi kpda tmn2 lain/sanak keluarga yg sekiranya membutuhkan training tsb.
Smga Bermanfaat
Thanks Ken Kanaidi
Ppt landasan pendidikan Pai 9 _20240604_231000_0000.pdffadlurrahman260903
Β
Ppt landasan pendidikan tentang pendidikan seumur hidup.
Prodi pendidikan agama Islam
Fakultas tarbiyah dan ilmu keguruan
Universitas Islam negeri syekh Ali Hasan Ahmad addary Padangsidimpuan
Pendidikan sepanjang hayat atau pendidikan seumur hidup adalah sebuah system konsepkonsep pendidikan yang menerangkan keseluruhan peristiwa-peristiwa kegiatan belajarmengajar yang berlangsung dalam keseluruhan kehidupan manusia. Pendidikan sepanjang
hayat memandang jauh ke depan, berusaha untuk menghasilkan manusia dan masyarakat yang
baru, merupakan suatu proyek masyarakat yang sangat besar. Pendidikan sepanjang hayat
merupakan asas pendidikan yang cocok bagi orang-orang yang hidup dalam dunia
transformasi dan informasi, yaitu masyarakat modern. Manusia harus lebih bisa menyesuaikan
dirinya secara terus menerus dengan situasi yang baru.
Laporan Pembina Pramuka SD dalam format doc dapat anda jadikan sebagai rujukan dalam membuat laporan. silakan download di sini https://unduhperangkatku.com/contoh-laporan-kegiatan-pramuka-format-word/
Modul Ajar Matematika Kelas 11 Fase F Kurikulum MerdekaFathan Emran
Β
Modul Ajar Matematika Kelas 11 SMA/MA Fase F Kurikulum Merdeka - abdiera.com. Modul Ajar Matematika Kelas 11 SMA/MA Fase F Kurikulum Merdeka. Modul Ajar Matematika Kelas 11 SMA/MA Fase F Kurikulum Merdeka. Modul Ajar Matematika Kelas 11 SMA/MA Fase F Kurikulum Merdeka. Modul Ajar Matematika Kelas 11 SMA/MA Fase F Kurikulum Merdeka.
Modul Ajar Bahasa Indonesia Kelas 7 Fase D Kurikulum Merdeka - [abdiera.com]Fathan Emran
Β
Modul Ajar Bahasa Indonesia Kelas 7 SMP/MTs Fase D Kurikulum Merdeka - abdiera.com. Modul Ajar Bahasa Indonesia Kelas 7 SMP/MTs Fase D Kurikulum Merdeka. Modul Ajar Bahasa Indonesia Kelas 7 SMP/MTs Fase D Kurikulum Merdeka. Modul Ajar Bahasa Indonesia Kelas 7 SMP/MTs Fase D Kurikulum Merdeka. Modul Ajar Bahasa Indonesia Kelas 7 SMP/MTs Fase D Kurikulum Merdeka. Modul Ajar Bahasa Indonesia Kelas 7 SMP/MTs Fase D Kurikulum Merdeka.
Materi Feedback (umpan balik) kelas Psikologi Komunikasi
Β
Garispanduan pkp pembinaan
1. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
GARIS PANDUAN AMALAN LANGKAH PENCEGAHAN COVID-19
DI TAPAK BINA (DOKUMEN 2)
KEMENTERIAN KERJA RAYA / LEMBAGA PEMBANGUNAN INDUSTRI
PEMBINAAN MALAYSIA (CIDB)
2. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
GARIS PANDUAN AMALAN LANGKAH PENCEGAHAN COVID-19 DI TAPAK BINA
DALAM TEMPOH PERINTAH KAWALAN PERGERAKAN (PKP)
1. PENDAHULUAN
Lembaga Pembangunan Industri Pembinaan (CIDB) Malaysia sentiasa mengikuti perkembangan
dan mengambil serius terhadap penularan wabak Covid-19 yang berlaku di negara ini. Selaras
dengan perkembangan terkini, CIDB telah menyediakan Garis Panduan Amalan Langkah
Pencegahan Covid-19 di tapak bina bagi meminimakan risiko penularan Covid-19 dan memastikan
persekitaran tapak bina adalah selamat, kondusif dan terkawal di tapak bina.
2. PEMAKAIAN
Garis Panduan ini hendaklah digunapakai oleh SEMUA Kontraktor dan Pekerja Binaan dalam
menjalankan kerja-kerja pembinaan di Malaysia, sebagai amalan langkah pencegahan wabak
Covid-19. Garis panduan ini juga hendaklah dibaca dengan SOP dan arahan berkaitan pengawalan
Covid-19 oleh kerajaan dan agensi berkaitan yang diberi kuasa dan mana-mana undang-undang
bertulis yang berkuatkuasa.
3. OBJEKTIF
3.1. Membantu pihak-pihak berkaitan mengambil langkah pencegahan penularan di tapak bina.
3.2. Mengurangkan risiko penularan wabak Covid-19 di tapak bina.
3.3. Menyeragamkan tindakan awal pencegahan wabak di tapak bina yang boleh diamalkan oleh
pihak-pihak berkaitan.
3.4. Memastikan kepatuhan kontraktor terhadap undang-undang bertulis yang berkuatkuasa di
Malaysia, selaras dengan keadaan semasa iaitu ketika penularan Covid-19.
4. AMALAN UMUM
4.1. Kontraktor hendaklah peka terhadap perkembangan terkini dan mematuhi prosedur
pencegahan Covid-19 yang telah ditetapkan oleh Kementerian Kesihatan Malaysia (KKM) dan
Majlis Keselamatan Negara (MKN) yang dikeluarkan dari semasa ke semasa.
4.2. Sekiranya terdapat pekerja-pekerja yang berada di bawah pemerhatian KKM (person under
investigation & person under surviellance), pekerja terbabit tidak dibenarkan datang bekerja
dan perlu menjalani tempoh pengasingan yang ditetapkan oleh KKM.
3. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
4.3. Sepanjang tempoh Perintah Kawalan Pergerakan (PKP) berkuatkuasa, pekerja-pekerja asing
yang berada di luar Malaysia adalah tidak dibenarkan masuk ke tapak bina dan bekerja
walaupun majikan atau pihak-pihak berkaitan telah diberi kebenaran menjalankan kerja-
kerja pembinaan.
4.4. Pekerja-pekerja yang baru pulang dari luar negara pula dalam tempoh PKP, tidak dibenarkan
bekerja dan masuk ke tapak bina dalam tempoh empat belas (14) hari bermula dari tarikh
sampai ke Malaysia. Ini adalah untuk membolehkan mereka menjalani proses kuarantin
selaras dengan arahan KKM.
4.5. Sepanjang tempoh PKP, waktu bekerja adalah dari jam 8.00 pagi hingga 5.30 petang sahaja, 5
hari seminggu.
Nota:
a) Hari Bekerja Isnin β Jumaat adalah bagi Wilayah Persekutuan, Perlis, Pulau Pinang, Perak, Selangor, Negeri
Sembilan, Melaka, Pahang, Sabah dan Sarawak.
b) Hari Bekerja Ahad β Khamis adalah bagi Kedah, Kelantan, Terengganu dan Johor
5. LANGKAH PENCEGAHAN
Amalan langkah pencegahan Covid-19 di tapak bina adalah dirangka berdasarkan rutin harian
yang akan dilaksanakan oleh kontraktor bermula dari tempat kediaman, tapak bina dan pulang
semula ke tempat kediaman.
5.1. Langkah 1 β SARINGAN DARI CLQ/TEMPAT PENGINAPAN
i. Kontraktor hendaklah memastikan pekerja adalah sihat dan tidak menunjukkan gejala
berkaitan Covid-19 seperti demam, batuk, sakit tekak atau kesukaran bernafas.
ii. Setiap pekerja perlu memuat turun aplikasi KKM (MySejahtera App) bagi tujuan
contact tracing.
iii. Kontraktor perlu melakukan saringan kesihatan dengan menjalankan pemeriksaan
suhu badan kepada semua pekerja pada setiap hari sebelum menaiki kenderaan untuk
bergerak ke tapak bina dan direkodkan.
iv. Kontraktor perlu memastikan pekerja yang disaring bebas daripada gejala-gejala
Covid-19.
v. Pekerja yang mempunyai suhu badan tinggi (37.5Β° Celcius atau lebih) atau mempunyai
gejala yang ditetapkan oleh KKM perlu dirujuk dengan segera ke klinik panel syarikat
atau klinik yang bersesuaian.
vi. Pekerja yang disyaki menghidapi gejala-gejala Covid-19 dan kontak rapat pekerja
tersebut hendaklah seberapa segera diasingkan dan tidak dibenarkan bekerja.
4. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
vii. Kontraktor hendaklah memastikan tempat penginapan samada di tapak atau lain-lain
adalah selamat dan menepati Garis Panduan Operasi Centralised Labour Quarters
(CLQ) dan Penginapan Pekerja Binaan Semasa PKP.
viii. Bagi tapak bina dengan kuarters atau kediaman pekerja di dalam tapak bina,
kebersihan dan pemantauan pergerakan pekerja hendaklah dilaksanakan secara
berterusan. Pergerakan pekerja keluar masuk hendaklah dihadkan.
5.2. Langkah 2 β PENGANGKUTAN PEKERJA/ BAHAN BINAAN
5.2.1. Proses Pergerakan Pekerja ke Tapak Bina
i. Kontraktor hendaklah menyediakan kenderaan bagi pengangkutan pekerja ke tapak
bina. Penggunaan kenderaan awam tidak dibenarkan sama sekali.
ii. Pekerja yang tinggal berdekatan dengan tapak bina digalakkan untuk berjalan kaki ke
tapak bina.
iii. Kontraktor hendaklah memastikan kenderaan telah menjalani proses nyah kuman
setiap kali sebelum digunakan untuk mengangkut pekerja. Proses nyah kuman perlu
dilaksanakan secara berkala dan direkod untuk tujuan pemeriksaan.
iv. Kenderaan pekerja yang disediakan oleh Kontraktor/ Syarikat hanya dibenarkan untuk
mengangkut pekerja di dalam daerah/ zon berkenaan sahaja dan tidak dibenarkan
untuk melintasi sempadan daerah/ zon.
v. Kontraktor/ Syarikat perlu menyediakan kenderaan pengangkutan bagi pergerakan
pekerja dengan menerapkan penjarakkan sosial/ safe distancing dan kenderaan yang
digunakan perlu dinyah cemar kuman setiap kali digunakan.
5.2.2. Proses Pergerakan Bahan Binaan ke Tapak Bina
i. Kontraktor perlu memaklumkan kepada semua pembekal barangan dan perkhidmatan
(supply chain) yang berurusan dengan mereka supaya mendapat kelulusan beroperasi
dan pergerakan yang sewajarnya serta mematuhi dan mengamalkan langkah
pencegahan Covid-19 yang ditetapkan oleh KKM.
ii. Pergerakan masuk bahan ke tapak bina hendaklah direkodkan dengan lengkap.
iii. Pemandu kenderaan membawa bahan masuk juga perlu disaring dengan mengambil
suhu badan dan menggunakan hand sanitizer.
5. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
5.3. Langkah 3 β DI TAPAK BINA
5.3.1. Di Pintu Masuk Tapak
i. Kontraktor perlu memastikan Surat Kebenaran Beroperasi dipamerkan dengan jelas di
pintu masuk tapak bina untuk rujukan pihak berkuasa yang mengadakan pemeriksaan.
ii. Kontraktor WAJIB mengisytiharkan senarai lengkap pekerja yang akan berada di tapak
bina semasa memohon kebenaran memulakan operasi kerja-kerja pembinaan. Senarai
tersebut perlu disediakan di tapak bina untuk rujukan pihak berkuasa.
iii. Hanya pekerja yang tiba dengan kenderaan yang disediakan oleh kontraktor boleh
masuk ke tapak bina.
iv. Setiap pelawat atau pihak yang berurusan perlulah disaring dengan mengambil suhu
badan dan diperiksa tahap kesihatan mereka sebelum masuk ke tapak bina. Pelawat
yang bergejala Covid-19 tidak dibenarkan sama sekali masuk ke tapak bina.
v. Pencuci tangan (hand sanitizer) hendaklah digunakan di pintu masuk bagi semua
pekerja dan pihak yang berurusan dengan tapak bina.
vi. Kontraktor adalah bertanggungjawab memastikan dan membantu pihak yang
diberikuasa untuk melakukan sebarang pemeriksaan ke atas tapak pembinaan dan
pekerjanya.
5.3.2. Aktiviti Kerja
i. Bilangan pekerja binaan hendaklah dikurangkan kepada tahap paling minima atau
kurang 50% dari bilangan biasa semasa tempoh PKP berkuatkuasa.
ii. Kontraktor perlu mewujudkan satu pasukan petugas khas diketuai oleh seorang ketua
yang dipertanggungjawabkan bagi menguruskan risiko penularan wabak di tapak bina.
iii. Kontraktor perlu menyediakan laluan pergerakan keluar masuk terkawal di tapak bina
untuk memantau pergerakan pekerja.
iv. Setiap pelaksanaan kerja di tapak bina hendaklah dirancang dengan mengambilkira
bilangan pekerja yang seminima mungkin selaras dengan syarat kelulusan.
v. Penilaian semula risiko dengan memasukkan elemen risiko jangkitan Covid-19
hendaklah dilaksanakan sebelum memulakan kerja di tapak bina oleh pegawai yang
bertanggungjawab.
vi. Penjarakkan sosial seperti yang disarankan oleh KKM iaitu 1.0 meter hendaklah
dilaksanakan di tapak bina agar pekerja tidak berada atau bekerja berdekatan antara
satu sama lain dalam tempoh yang lama. Semua pekerjaan di ruangan tertutup
hendaklah diminimakan.
6. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
vii. Sebarang mesyuarat, sekiranya ada, hendaklah dilaksanakan di ruangan yang sesuai
serta mematuhi kehendak penjarakkan sosial.
viii. Kontraktor perlu memantau semua pekerja yang bekerja di tapak bina setiap masa
agar tidak duduk berkumpul dan sentiasa mengamalkan penjarakkan sosial.
ix. Kontraktor hendaklah mewujudkan kesedaran mengenai gejala Covid-19, menjaga
kebersihan dan kesihatan diri, amalan kerap membasuh tangan dengan air sabun dan
etika batuk yang baik kepada pekerja-pekerja binaan.
x. Setiap pekerja dibekalkan alat pelindung diri bersesuaian seperti penutup hidung,
topeng muka dan sarung tangan yang bersesuaian secukupnya mengikut keperluan.
xi. Topeng muka hendaklah sentiasa dipakai semasa bekerja termasuklah ketika berada di
tandas.
xii. Kontraktor perlu menyediakan kemudahan untuk mencuci tangan dengan
menggunakan air, sabun dan bahan pencuci tangan (hand sanitizer).
xiii. Kontraktor juga dikehendaki memberi peringatan lebih kerap dan berterusan di tapak
bina seperti melalui siar raya atau menampal poster peringatan Covid-19.
xiv. Sekiranya terdapat jangkitan di tapak bina, proses nyah kuman adalah menjadi
tanggungjawab kontraktor dan hendaklah dilaksanakan dengan kadar segera mengikut
tatacara yang ditetapkan oleh KKM.
xv. Kontraktor hendaklah melaporkan kepada KKM dengan segera sekiranya terdapat
pekerja yang disyaki menghidapi gejala Covid-19 dan seterusnya perlu mematuhi
arahan dan nasihat selanjutnya daripada KKM.
xvi. Tandas di tapak bina hendaklah dalam keadaan sempurna dan sentiasa dibersihkan.
xvii. Kebersihan tandas hendaklah diberi keutamaan dengan menjalankan proses nyah
kuman secara berjadual dan kerap.
xviii. Pekerja yang menguruskan kebersihan tandas perlu membersihkan tandas dan
menjalankan proses nyah kuman dengan teliti dan menyeluruh.
5.3.3. Masa Rehat
i. Waktu rehat perlu disusun agar tidak menyebabkan kesesakan di kantin dengan
pembahagian waktu rehat dalam kumpulan kecil.
ii. Penjarakkan sosial juga perlu dipastikan pematuhannya di semua kawasan rehat,
kantin dan ruang solat.
iii. Kafeteria/kantin di dalam tapak yang dibenarkan beroperasi perlulah menyediakan
makanan berbungkus yang disediakan oleh pengendali makanan yang memakai
topeng muka dan sarung tangan.
7. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
iv. Pekerja perlu kerap diingatkan supaya tidak duduk berkumpul dan mematuhi
penjarakkan sosial.
5.3.4. Balik Kerja
i. Kontraktor hendaklah memastikan bahawa semua pergerakan balik pekerja ke tempat
kediaman, CLQ atau lain-lain adalah dengan menggunakan kenderaan yang
disediakan.
ii. Sebaik sahaja tiba di tempat kediaman pekerja hendaklah terus mandi menggunakan
air bersih dan sabun serta membasuh pakaian yang telah digunakan.
iii. Adalah diingatkan sekiranya terdapat sebarang masalah kesihatan setelah pulang
bekerja, ianya perlulah dimaklumkan dengan segera kepada Ketua Pasukan petugas
khas untuk tindakan sewajarnya.
5.4. Langkah 4 β REKOD
i. Kontraktor hendaklah mengurus dan menyimpan rekod pekerja berikut:-
a. Rekod kehadiran pekerja;
b. Rekod saringan kesihatan;
c. Rekod pergerakan pekerja;
d. Rekod butiran peribadi pekerja;
ii. Kontraktor juga perlu menyediakan rekod pengurusan kebersihan tapak seperti:-
a. Rekod proses nyah kuman kawasan tandas.
b. Rekod pembersihan kawasan tapak bina.
iii. Kontraktor juga perlu menyediakan rekod pengurusan tapak seperti berikut:-
a. Rekod pengurusan risiko dan
b. Rekod pergerakan keluar masuk tapak oleh penyedia barangan dan perkhidmatan.
c. Rekod pemeriksaan Pihak Berkuasa
iv. Semua rekod hendaklah sentiasa lengkap dan sedia untuk diperiksa oleh pihak
berwajib pada bila-bila masa jika diperlukan
8. PROJEK PENSWASTAAN LEBUHRAYA BERTINGKAT
SUNGAI BESI β ULU KELANG (SUKE) : PACKAGE CA2
TENDERNO:TURNPIKE-SUKE-T-A-ML-CA2-011(Rev.1)
Doc. No. SUKE/CA2/ESH/SOP/01
Rev. No. 0
Rev. Date APRIL 2020
SAFE OPERATING PROCEDURE
_______________________________________________________________________________
Hasnizam Md Saad
MRCBBUILDERS SDN BHD(COMPANY NO: 300947-T)
6. KETIDAKPATUHAN
Mana-mana kontraktor yang tidak mematuhi garis panduan Amalan Langkah Pencegahan Covid-
19 ini boleh diambil tindakan selaras dengan Akta Lembaga Industri Pembinaan Malaysia (Akta
520). Kerajaan berhak menarik balik kelulusan yang diberikan selain meminda syarat-syarat di
atas tanpa sebarang notis dan tertakluk kepada situasi semasa.
Garis Panduan Amalan Langkah Pencegahan Covid-19 di tapak bina ini boleh dipinda oleh CIDB pada bila-bila masa
mengikut keperluan