This document provides an overview of the Furnace Safeguard Supervisory System (FSSS) implemented at the Butibori power project in India. It describes the hardware configuration using three systems: a Safety Manager system, DCS system, and MFT cabinet. It then summarizes the major functions and logics of the FSSS, including common control logics, fuel oil control logics, coal-fired control logics, and conditions for satisfactory boiler start up and shutdown. It also briefly discusses the run back function to reduce boiler load in the event of failures.
Furnace safegaurd supervisory system logic-1Ashvani Shukla
This document outlines the logic and conditions for a pulverized coal fired boiler. It describes 17 conditions that can trigger a manual fire trip (MFT), including issues with fans, pumps, pressures, and flame detection. It also explains the requirements and process for furnace purging after an MFT occurs. This includes conditions that must be met and interlocks in place. Additionally, it provides the process and permissives for testing for oil leaks in the heavy and light fuel oil supply pipes.
The document discusses the boiler protection system and burner management system used to safely start up and shut down boiler and burner equipment. It provides 3 sentences:
The boiler protection system and burner management system work together to protect the boiler from process faults or incorrect actions by ensuring all necessary safety interlocks are in place for safe startup and shutdown of burners. The systems follow procedures to ensure a safe operating sequence and reduce errors, and components must be regularly maintained and inspected for continued safe operation. The document outlines the various functions, sequences, conditions, protections and requirements of the systems according to industry standards.
The document describes the functions and design of a Burner Management System (BMS). The key purposes of a BMS are to safely start up and shut down fuel firing equipment, continuously monitor safety interlocks, and execute automatic shutdown if unacceptable conditions occur. It provides details on purge cycles, fuel selection permissives, trip conditions, alarms, and implementation including field devices, control electronics, and the human interface.
Boiler purge is the basic process of resetting boiler before lightup. This presentation explains the logic, schematics & working of purge procedure. For enhanced knowledge of this topic, I can be reached at tahoorkhn03@gmail.com.
Mobile transformer oil purification plant with high vacuum globecore cmm(uvm)...GlobeCore
The document describes the GlobeCore CMM (UVM) 10,0 A mobile transformer oil purification plant. It can process up to 10,000 liters per hour to remove water, gases, and particulate matter from transformer oils. The unit operates in degassing, heating, and vacuum evacuation modes using pumps, filters, a vacuum chamber, and an oil heater. It is controlled by a programmable logic controller and is designed to regenerate oils on-site to service power transformers and other high voltage equipment.
The document describes a burner management system for a recovery boiler. The system provides sequencing and safety controls for auxiliary fuel burners used to start up and supplement the main black liquor fuel. It monitors conditions and will trigger an alarm or auxiliary fuel trip if parameters exceed limits. The system is implemented using a Honeywell/Moeller IPC620 PLC and manages sequencing of equipment, interlocks, burner controls and emergency drain valves.
Globecore transformer oil purification plant with high vacuum cmm 6 dGlobeCore
The document describes the CMM-6D transformer oil purification plant. The plant removes particulate matter and purifies oil from water and gas through degassing, drying, filtration, and heating. It processes 2-6 cubic meters per hour of oil and can heat oil to 90°C. The self-contained unit is installed on a trailer and operated via an automatic control system and touchscreen interface.
The document outlines the startup sequence for a CFBC burner. It involves 14 steps: 1) satisfying pre-interlocks, 2) satisfying main interlocks, 3) satisfying purge interlocks, 4) starting purge for 5 minutes, 5) purge completing, 6) resetting MFTs, 7) satisfying gas firing permissives, 8) burners becoming ready for start, 9) starting burner A through 10 automatic commands, and 10) burner A gas firing starting. It provides details on the conditions that must be met at each step.
Furnace safegaurd supervisory system logic-1Ashvani Shukla
This document outlines the logic and conditions for a pulverized coal fired boiler. It describes 17 conditions that can trigger a manual fire trip (MFT), including issues with fans, pumps, pressures, and flame detection. It also explains the requirements and process for furnace purging after an MFT occurs. This includes conditions that must be met and interlocks in place. Additionally, it provides the process and permissives for testing for oil leaks in the heavy and light fuel oil supply pipes.
The document discusses the boiler protection system and burner management system used to safely start up and shut down boiler and burner equipment. It provides 3 sentences:
The boiler protection system and burner management system work together to protect the boiler from process faults or incorrect actions by ensuring all necessary safety interlocks are in place for safe startup and shutdown of burners. The systems follow procedures to ensure a safe operating sequence and reduce errors, and components must be regularly maintained and inspected for continued safe operation. The document outlines the various functions, sequences, conditions, protections and requirements of the systems according to industry standards.
The document describes the functions and design of a Burner Management System (BMS). The key purposes of a BMS are to safely start up and shut down fuel firing equipment, continuously monitor safety interlocks, and execute automatic shutdown if unacceptable conditions occur. It provides details on purge cycles, fuel selection permissives, trip conditions, alarms, and implementation including field devices, control electronics, and the human interface.
Boiler purge is the basic process of resetting boiler before lightup. This presentation explains the logic, schematics & working of purge procedure. For enhanced knowledge of this topic, I can be reached at tahoorkhn03@gmail.com.
Mobile transformer oil purification plant with high vacuum globecore cmm(uvm)...GlobeCore
The document describes the GlobeCore CMM (UVM) 10,0 A mobile transformer oil purification plant. It can process up to 10,000 liters per hour to remove water, gases, and particulate matter from transformer oils. The unit operates in degassing, heating, and vacuum evacuation modes using pumps, filters, a vacuum chamber, and an oil heater. It is controlled by a programmable logic controller and is designed to regenerate oils on-site to service power transformers and other high voltage equipment.
The document describes a burner management system for a recovery boiler. The system provides sequencing and safety controls for auxiliary fuel burners used to start up and supplement the main black liquor fuel. It monitors conditions and will trigger an alarm or auxiliary fuel trip if parameters exceed limits. The system is implemented using a Honeywell/Moeller IPC620 PLC and manages sequencing of equipment, interlocks, burner controls and emergency drain valves.
Globecore transformer oil purification plant with high vacuum cmm 6 dGlobeCore
The document describes the CMM-6D transformer oil purification plant. The plant removes particulate matter and purifies oil from water and gas through degassing, drying, filtration, and heating. It processes 2-6 cubic meters per hour of oil and can heat oil to 90°C. The self-contained unit is installed on a trailer and operated via an automatic control system and touchscreen interface.
The document outlines the startup sequence for a CFBC burner. It involves 14 steps: 1) satisfying pre-interlocks, 2) satisfying main interlocks, 3) satisfying purge interlocks, 4) starting purge for 5 minutes, 5) purge completing, 6) resetting MFTs, 7) satisfying gas firing permissives, 8) burners becoming ready for start, 9) starting burner A through 10 automatic commands, and 10) burner A gas firing starting. It provides details on the conditions that must be met at each step.
Globecore transformer oil regeneration and purification equipmentGlobeCore
This document describes various mobile oil processing equipment from GlobeCore. It summarizes the key features and specifications of different containerized mobile units for regenerating, purifying, degassing, and drying insulating oils used in electrical equipment. The units can remove contaminants, water, gases, and restore color and breakdown voltage. Specifications include minimum capacities, oil quality parameters achieved, filtration sizes, vacuum levels, power requirements and dimensions for each model.
The document describes a GlobeCore CMM-2.2 transformer oil purification plant that can purify 2,200 liters of oil per hour. It removes solids and purifies oil of water and gases using vacuum and heat. The portable unit features components like filters, pumps, a heater, and a control panel to clean insulation and lubrication oils used in electric equipment. It can filter and heat oil, perform thermo-vacuum drying, or evacuate air from other equipment under vacuum.
This document provides information about a GlobeCore transformer oil regeneration plant. It can [1] regenerate used transformer oil to restore its dielectric properties and chemical composition, [2] remove gases, water, and particles from oil, and [3] service transformers by evacuating them, heating their windings with hot oil, and removing sediment. The plant uses a degassing section to filter and vacuum treat oil, and a regeneration section uses sorbent to restore oil chemically. It can process up to 4 cubic meters of oil per hour and treat oil both online and offline from transformers.
A boiler trip command stops all fuel inputs and closes all heavy oil nozzle valves. There are two separate boiler trip commands that must both be reset before a furnace purge can begin. A boiler trip establishes a master fuel trip memory signal, indicated by red and green lights, and triggers various safety events like tripping pulverizers and fans. Boiler explosions can occur if unburned fuel accumulates in the furnace, while implosions result from rapid decreases in furnace pressure. Preventive measures include maintaining minimum air flows and slowly reducing fuel and fan speeds after a trip.
CMM-R plants are designed to regenerate transformer oil and extend the life of aging transformers. The process draws oil through Fuller's Earth, which removes sludge and degradation byproducts through molecular filtration. The plant then reactivates the Fuller's Earth to be reused up to 300 times. Treated oil shows improved parameters such as acidity level and breakdown voltage. The plant continuously circulates oil to fully automate regeneration and extend a transformer's lifespan by 25-30 years through timely oil regeneration.
www.gcequipment.com
GlobeCore CMM-R Transformer Oil Regeneration Plants are designed to improve dielectric strength and chemical composition of insulating oils. It is important to maintain oil properties within the recommended standards to prevent weakening of cellulose insulation by products of oil degradation. Since the life of the transformer is determent by the state of cellulose insulation, intervention is necessary to prevent sludge from destructing chemical bonds which hold the cellulose together. Oil Regeneration allows to remove sludge (which is formed as a result of oil degradation (aging) and consists mainly of acids, aldehydes and peroxides), improve acidity level and decrease oil’s ability to dissolve gases.
www.gcequipment.com
Tel: +380500131317
sales@gcequipment.com
Skype: stan_globecore
www.gcequipment.com
Skype:stan_globecore
Transformer oil purification plant Globecore CMM4/7 designed for tratment of tranfromer oil and provides:
• Removal of Water from 100 ppm down to 10 ppm and from 50 ppm to 5 ppm in a single pass and down to 3 ppm after 3 passes (ASTM method D-1533).
• Reduction of Gas content from fully saturated with air (10 to 12% by volume) to less than 0.1 % (ASTM D-2945).
• Removal of Particulate Matter to 5 microns
• Improvement in dielectric strength up to 75 kV
The document outlines the steps to safely shut down a 210 MW power generation unit for overhaul and maintenance. It involves gradually reducing boiler steam parameters and turbine load over several steps by cutting mills and heaters, before finally tripping the turbine. Key steps include maintaining temperature differences, ensuring availability of emergency equipment, monitoring parameters, and opening drains. The shutdown is completed by venting the boiler drum and stopping auxiliary systems once drum pressure is reduced.
The discussion on "Handling of Turbines During Emergencies" has been detailed in the ppt. Some case studies are also discussed in the session where the course participants express their difficulties while coming across the emergencies in handling the turbines at their locations.
2009 toyota venza service repair manualfjjfyjsekdmme
This document provides instructions for removing and installing cooling fan motors on a 2010 Toyota Venza. It describes removing the radiator assembly, fans, and fan motors. It also provides instructions for installing replacement fan motors and reassembling the components. Torque specifications are given for the fan motor screws. Current specifications are provided to test the fan motors during inspection.
2010 toyota venza service repair manualjjfksekdmejik
The document provides instructions for replacing the coolant in a 2010 Toyota Venza. It describes draining the old coolant, loosening drain plugs, refilling with new coolant, and bleeding air from the system. It also warns not to remove caps or drain plugs while hot and to only use Toyota Long Life Coolant.
The document describes protections and interlocks for a boiler system. It outlines conditions that will trip the boiler and actions to be taken during a unit shutdown. It also provides details on interlocks for starting and stopping components like mills, fans, dampers and air heaters to ensure safe and proper operation. Permissives must be met to start equipment and components will automatically trip under certain fault conditions.
In this paper GlobeCore presents the main operational principles of oil
regeneration plants with Fuller’s Earth reactivation facility and
demonstrate the economic advantages over replacement of used
transformer oil with new oil.
The document describes the fuel injection system used in Caterpillar 3408E/3412E engines. It contains diagrams and descriptions of the key components of the Hydraulic Electronic Unit Injection (HEUI) system, including the fuel pump, oil cooler, sensors, injectors, and Electronic Control Module (ECM). It also provides details on the synchronization calibration process, injection waveform characteristics, and operating modes like cold start and derate functions.
This document provides an electrical circuit diagram and descriptions for a Cummins ISB CM2150 diesel engine from 2007-2009. It includes:
1) A key listing abbreviations for wire colors and component names/numbers.
2) A multi-page diagram showing engine sensors, actuators and their electrical connections to the ECM and vehicle wiring.
3) Pinouts and descriptions for the ECM and other connectors.
The diagram provides technicians with information to trace circuitry and diagnose electrical issues. Abbreviations standardize the representation of colors for consistent identification.
Vertical multistage fire pump catalogue-60HZAndy Chen
Vertical multistage pump is always used for fire fighting as jockey pump, for more details, pls check http://www.firepump.cc/product/XBD-CDL-jockey-pump.html
660 mw turbo governing & protection systemAshvani Shukla
This document provides an overview of a turbine system including:
- The topics that will be covered in the presentation such as the turbine components, governing system, extraction circuits, and protection systems.
- A block diagram showing the turbine extractions and their destinations.
- The main turbine components including the high pressure turbine, intermediate pressure turbine, low pressure turbines, bearings, valves, and governing box.
- Details on the governing system, resetting procedure, operation of stop and control valves, and start up sequences.
- Instrumentation for monitoring including turbovisory instruments and the turbine stress calculation system.
- The turbine protection system with electrical and hydraulic protections tripping the turbine if operational limits are exceeded.
This document provides step-by-step instructions for starting up a 600 MW simulator power plant from a cold and shutdown state to reaching full load of 600 MW. The process involves lining up various water, fuel, air, and gas systems; filling the boiler drum; purging the boiler; lighting off and warming up the boiler; rolling the turbine; synchronizing the generator; and gradually increasing the load by putting additional systems and equipment into service as the load rises. The startup process is controlled and monitored closely to ensure stable operation and prevent issues during critical speed ranges or temperature/pressure excursions.
The document summarizes the key components and functions of a fuel firing system and burner management system for a boiler. It describes the operational functions included like furnace purge supervision, flame monitoring, and burner protection. It explains the boiler purging process and purge permissives that must be satisfied. It also outlines the start-up processes for oil elevations in pair mode and elevation mode, including establishing ignition permits. Secondary air damper control and mill start permissives are summarized as well. The document provides an overview of the safety systems and sequences used to safely start, operate, and shut down fuel firing equipment for a high capacity boiler.
The document summarizes the key components and functions of a fuel firing system and burner management system for a boiler. It describes the operational functions included like furnace purge supervision, flame monitoring, and burner protection. It explains the boiler purging process and purge permissives that must be satisfied. It also outlines the start-up sequences for oil elevations in pair mode and elevation mode. Additional details provided include secondary air damper control, mill panel functions, field equipment, and mill start permissives.
Globecore transformer oil regeneration and purification equipmentGlobeCore
This document describes various mobile oil processing equipment from GlobeCore. It summarizes the key features and specifications of different containerized mobile units for regenerating, purifying, degassing, and drying insulating oils used in electrical equipment. The units can remove contaminants, water, gases, and restore color and breakdown voltage. Specifications include minimum capacities, oil quality parameters achieved, filtration sizes, vacuum levels, power requirements and dimensions for each model.
The document describes a GlobeCore CMM-2.2 transformer oil purification plant that can purify 2,200 liters of oil per hour. It removes solids and purifies oil of water and gases using vacuum and heat. The portable unit features components like filters, pumps, a heater, and a control panel to clean insulation and lubrication oils used in electric equipment. It can filter and heat oil, perform thermo-vacuum drying, or evacuate air from other equipment under vacuum.
This document provides information about a GlobeCore transformer oil regeneration plant. It can [1] regenerate used transformer oil to restore its dielectric properties and chemical composition, [2] remove gases, water, and particles from oil, and [3] service transformers by evacuating them, heating their windings with hot oil, and removing sediment. The plant uses a degassing section to filter and vacuum treat oil, and a regeneration section uses sorbent to restore oil chemically. It can process up to 4 cubic meters of oil per hour and treat oil both online and offline from transformers.
A boiler trip command stops all fuel inputs and closes all heavy oil nozzle valves. There are two separate boiler trip commands that must both be reset before a furnace purge can begin. A boiler trip establishes a master fuel trip memory signal, indicated by red and green lights, and triggers various safety events like tripping pulverizers and fans. Boiler explosions can occur if unburned fuel accumulates in the furnace, while implosions result from rapid decreases in furnace pressure. Preventive measures include maintaining minimum air flows and slowly reducing fuel and fan speeds after a trip.
CMM-R plants are designed to regenerate transformer oil and extend the life of aging transformers. The process draws oil through Fuller's Earth, which removes sludge and degradation byproducts through molecular filtration. The plant then reactivates the Fuller's Earth to be reused up to 300 times. Treated oil shows improved parameters such as acidity level and breakdown voltage. The plant continuously circulates oil to fully automate regeneration and extend a transformer's lifespan by 25-30 years through timely oil regeneration.
www.gcequipment.com
GlobeCore CMM-R Transformer Oil Regeneration Plants are designed to improve dielectric strength and chemical composition of insulating oils. It is important to maintain oil properties within the recommended standards to prevent weakening of cellulose insulation by products of oil degradation. Since the life of the transformer is determent by the state of cellulose insulation, intervention is necessary to prevent sludge from destructing chemical bonds which hold the cellulose together. Oil Regeneration allows to remove sludge (which is formed as a result of oil degradation (aging) and consists mainly of acids, aldehydes and peroxides), improve acidity level and decrease oil’s ability to dissolve gases.
www.gcequipment.com
Tel: +380500131317
sales@gcequipment.com
Skype: stan_globecore
www.gcequipment.com
Skype:stan_globecore
Transformer oil purification plant Globecore CMM4/7 designed for tratment of tranfromer oil and provides:
• Removal of Water from 100 ppm down to 10 ppm and from 50 ppm to 5 ppm in a single pass and down to 3 ppm after 3 passes (ASTM method D-1533).
• Reduction of Gas content from fully saturated with air (10 to 12% by volume) to less than 0.1 % (ASTM D-2945).
• Removal of Particulate Matter to 5 microns
• Improvement in dielectric strength up to 75 kV
The document outlines the steps to safely shut down a 210 MW power generation unit for overhaul and maintenance. It involves gradually reducing boiler steam parameters and turbine load over several steps by cutting mills and heaters, before finally tripping the turbine. Key steps include maintaining temperature differences, ensuring availability of emergency equipment, monitoring parameters, and opening drains. The shutdown is completed by venting the boiler drum and stopping auxiliary systems once drum pressure is reduced.
The discussion on "Handling of Turbines During Emergencies" has been detailed in the ppt. Some case studies are also discussed in the session where the course participants express their difficulties while coming across the emergencies in handling the turbines at their locations.
2009 toyota venza service repair manualfjjfyjsekdmme
This document provides instructions for removing and installing cooling fan motors on a 2010 Toyota Venza. It describes removing the radiator assembly, fans, and fan motors. It also provides instructions for installing replacement fan motors and reassembling the components. Torque specifications are given for the fan motor screws. Current specifications are provided to test the fan motors during inspection.
2010 toyota venza service repair manualjjfksekdmejik
The document provides instructions for replacing the coolant in a 2010 Toyota Venza. It describes draining the old coolant, loosening drain plugs, refilling with new coolant, and bleeding air from the system. It also warns not to remove caps or drain plugs while hot and to only use Toyota Long Life Coolant.
The document describes protections and interlocks for a boiler system. It outlines conditions that will trip the boiler and actions to be taken during a unit shutdown. It also provides details on interlocks for starting and stopping components like mills, fans, dampers and air heaters to ensure safe and proper operation. Permissives must be met to start equipment and components will automatically trip under certain fault conditions.
In this paper GlobeCore presents the main operational principles of oil
regeneration plants with Fuller’s Earth reactivation facility and
demonstrate the economic advantages over replacement of used
transformer oil with new oil.
The document describes the fuel injection system used in Caterpillar 3408E/3412E engines. It contains diagrams and descriptions of the key components of the Hydraulic Electronic Unit Injection (HEUI) system, including the fuel pump, oil cooler, sensors, injectors, and Electronic Control Module (ECM). It also provides details on the synchronization calibration process, injection waveform characteristics, and operating modes like cold start and derate functions.
This document provides an electrical circuit diagram and descriptions for a Cummins ISB CM2150 diesel engine from 2007-2009. It includes:
1) A key listing abbreviations for wire colors and component names/numbers.
2) A multi-page diagram showing engine sensors, actuators and their electrical connections to the ECM and vehicle wiring.
3) Pinouts and descriptions for the ECM and other connectors.
The diagram provides technicians with information to trace circuitry and diagnose electrical issues. Abbreviations standardize the representation of colors for consistent identification.
Vertical multistage fire pump catalogue-60HZAndy Chen
Vertical multistage pump is always used for fire fighting as jockey pump, for more details, pls check http://www.firepump.cc/product/XBD-CDL-jockey-pump.html
660 mw turbo governing & protection systemAshvani Shukla
This document provides an overview of a turbine system including:
- The topics that will be covered in the presentation such as the turbine components, governing system, extraction circuits, and protection systems.
- A block diagram showing the turbine extractions and their destinations.
- The main turbine components including the high pressure turbine, intermediate pressure turbine, low pressure turbines, bearings, valves, and governing box.
- Details on the governing system, resetting procedure, operation of stop and control valves, and start up sequences.
- Instrumentation for monitoring including turbovisory instruments and the turbine stress calculation system.
- The turbine protection system with electrical and hydraulic protections tripping the turbine if operational limits are exceeded.
This document provides step-by-step instructions for starting up a 600 MW simulator power plant from a cold and shutdown state to reaching full load of 600 MW. The process involves lining up various water, fuel, air, and gas systems; filling the boiler drum; purging the boiler; lighting off and warming up the boiler; rolling the turbine; synchronizing the generator; and gradually increasing the load by putting additional systems and equipment into service as the load rises. The startup process is controlled and monitored closely to ensure stable operation and prevent issues during critical speed ranges or temperature/pressure excursions.
The document summarizes the key components and functions of a fuel firing system and burner management system for a boiler. It describes the operational functions included like furnace purge supervision, flame monitoring, and burner protection. It explains the boiler purging process and purge permissives that must be satisfied. It also outlines the start-up processes for oil elevations in pair mode and elevation mode, including establishing ignition permits. Secondary air damper control and mill start permissives are summarized as well. The document provides an overview of the safety systems and sequences used to safely start, operate, and shut down fuel firing equipment for a high capacity boiler.
The document summarizes the key components and functions of a fuel firing system and burner management system for a boiler. It describes the operational functions included like furnace purge supervision, flame monitoring, and burner protection. It explains the boiler purging process and purge permissives that must be satisfied. It also outlines the start-up sequences for oil elevations in pair mode and elevation mode. Additional details provided include secondary air damper control, mill panel functions, field equipment, and mill start permissives.
This document discusses the control and instrumentation system for the Jaypee Bina Thermal Power Plant's 2x250 MW furnace safeguard and supervisory system (FSSS). The FSSS is designed to safely start up and shut down the boiler and prevent operator errors. It monitors the burner block assembly and controls the furnace purge sequence, oil gun operation in pair or elevation mode, and high energy arc igniter system to safely initiate combustion. The FSSS ensures maximum safety and efficiency during plant operation.
The document discusses the master fuel trip (MFT) logic for a circulating fluidized bed boiler. It provides details on the MFT including: conditions that generate an MFT, post-MFT actions, and special situations for boiler fans after an MFT. An MFT is generated by trips like both supply fans stopping, high or low furnace pressure, low air flow, and more. After an MFT, all coal feeders and burners shut off and fans may trip depending on furnace pressure. The document also reviews boiler hazards and protections.
The document describes the ball and tube mill used in stage-II coal milling. It discusses the key components and operating principles of the mill, including:
- The mill is a low-speed horizontal cylindrical tube that rotates and grinds coal using steel balls.
- It has a shell diameter of 4.7 meters and length of 7.2 meters, lined with steel liners and charged with 90 tons of balls or forgings for grinding.
- The mill uses instrumentation to measure critical parameters like differential pressure (DP) levels, lubrication systems, noise levels and other automatic controls to optimize mill operation.
The operations carried out to Light up the Boiler, from Air Cycle Establishment, Oil Handling Plant, Scanner air fans and Igniter Air Fans, Boiler Purging.
This document provides instructions for operating a thermal power plant over the course of a day. It includes starting various systems like the coal handling plant, primary air fans, mills and coal feeders to start producing power. It also details increasing the load by bringing additional mills online and adjusting support systems. The goal is to eventually reach full load of 210 MW by following the specified procedures.
This document describes the functions and operating sequences of a Boiler Protection System (BPS) and Burner Management System (BMS) that work together to safely start up, operate, and shut down boiler and burner equipment. The systems ensure proper sequencing and interlocks are in place. They monitor conditions like flame presence, fuel and air pressures, and will initiate a Master Fuel Trip (MFT) if unsafe conditions occur. The document outlines the specific permissives, sequences, and conditions required by NFPA 8501 for a safe furnace purge and startup of various boiler types including oil, AFBC, and CFBC boilers.
MS Lines, Turbine Casings and rotors and other steam lines including Steam Stop Valves, MSV, CV, ESV heating, Turbine Rolling, Flange and Stud heating, Turbovisory and speeding the turbine to 3000 RPM.
This document provides instructions for operating and maintaining a wall-mounted gas boiler. It includes diagrams of the boiler components and control panel. The summary describes the boiler's main features, including adjustable heating output between 6,000-20,000 kcal/h and hot water output if equipped. It outlines the control panel buttons and display symbols. It provides directions for starting up the boiler, selecting services, adjusting temperatures, and responding to error codes. Maintenance requirements and permanent frost protection functions are also summarized.
210 mw LMZ Turbine rolling and its GOVERNING Nitin Patel
This document provides information about the startup procedure for a 210 MW thermal power station turbine. It involves gradually heating the turbine components like casings and steam pipes before admitting steam. Steam is initially rolled through bypass lines to heat the turbine. Valves are then opened slowly to admit steam into the high pressure and intermediate pressure turbines. Speed is raised gradually while monitoring parameters like temperature, vibration and differential expansion. Once the turbine is rolled up to operating speed, it is ready for synchronization and loading.
The document discusses gas turbines used at an NFL power plant in Vijaipur. It provides details on the models, ratings, and loads of three gas turbine generators (GTGs). It then discusses heavy duty gas turbines from GE in terms of their configurations, frame sizes, speeds, and applications. The rest of the document goes into extensive technical details about the components, workings, inspections, and factors that influence gas turbines, including compressors, combustion systems, turbines, bearings, and more.
The document discusses differential pressure controls types MP 54, 55, and 55A.
It provides information on their use as safety switches to protect compressors from insufficient lubricating oil pressure. If oil pressure fails, the differential pressure control will stop the compressor after a set time delay.
The MP 54 has a fixed differential pressure setting and built-in time delay relay. The MP 55 and 55A have adjustable differential pressures and can be supplied with or without time delay relays.
This document provides information about a heater used in a crude distillation unit (CDU). It describes the key components and operating parameters of the heater. The heater uses fuel gas and fuel oil to heat crude oil from 310°C to 365°C. It discusses the radiant and convection sections, tubes, insulation, draft, and combustion controls. Safety instrumentation is outlined to isolate fuel in emergencies or if operating limits are exceeded.
General overview of HVAC Technology
General overview of VRF Technology
Benefits of VRF
General overview of Refrigerant
General overview of Ton
General overview of Compressor
This document provides startup procedures and protection settings for various components of a pulverized coal fired boiler, including:
- Induced draft fans, including startup permissives, interlocks, and protections
- Forced draft fans, including startup permissives and protections
- Primary air fans, including startup permissives, interlocks, and protections
- Bowl mills, including startup permissives, interlocks, and protections
It details the startup sequence and operating parameters for key auxiliary equipment to safely start and operate the boiler. Protective functions are defined to trip components if critical parameters like temperature, pressure, or vibration exceed limits.
This document provides specifications for a QX1401VD compressor model, including:
1. Drawings and lists of accessory parts for the compressor.
2. Technical parameters for the compressor such as voltage, current, power output.
3. Instructions for installation, application, and troubleshooting of the compressor.
Woodpecker training workshop jan'11 presentationensightbioenergy
This document summarizes a training workshop for Woodpecker Energy's pellet boilers. It outlines the agenda which includes introductions, an overview of Woodpecker's product range and new products, a discussion of domestic and commercial boiler systems, and training on boiler construction, controls, commissioning, servicing, troubleshooting, and Q&A. The commissioning section provides details on pre-commissioning checks, startup procedures, and conducting flue gas analysis to ensure proper boiler operation.
MR not building up due to issues with angle cocks, body bogie hoses, or air dryer bypass needing adjustment. BP not charging due to potential issues with cab setup, emergency brake handle position, TPWS cocks, or leaks from emergency exhaust or pneumatic panel. Check relevant isolating cocks, air pressures, cab modes, and fault codes to diagnose and resolve air pressure drops.
Dr. Sean Tan, Head of Data Science, Changi Airport Group
Discover how Changi Airport Group (CAG) leverages graph technologies and generative AI to revolutionize their search capabilities. This session delves into the unique search needs of CAG’s diverse passengers and customers, showcasing how graph data structures enhance the accuracy and relevance of AI-generated search results, mitigating the risk of “hallucinations” and improving the overall customer journey.
Threats to mobile devices are more prevalent and increasing in scope and complexity. Users of mobile devices desire to take full advantage of the features
available on those devices, but many of the features provide convenience and capability but sacrifice security. This best practices guide outlines steps the users can take to better protect personal devices and information.
Sudheer Mechineni, Head of Application Frameworks, Standard Chartered Bank
Discover how Standard Chartered Bank harnessed the power of Neo4j to transform complex data access challenges into a dynamic, scalable graph database solution. This keynote will cover their journey from initial adoption to deploying a fully automated, enterprise-grade causal cluster, highlighting key strategies for modelling organisational changes and ensuring robust disaster recovery. Learn how these innovations have not only enhanced Standard Chartered Bank’s data infrastructure but also positioned them as pioneers in the banking sector’s adoption of graph technology.
How to Get CNIC Information System with Paksim Ga.pptxdanishmna97
Pakdata Cf is a groundbreaking system designed to streamline and facilitate access to CNIC information. This innovative platform leverages advanced technology to provide users with efficient and secure access to their CNIC details.
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Albert Hoitingh
In this session I delve into the encryption technology used in Microsoft 365 and Microsoft Purview. Including the concepts of Customer Key and Double Key Encryption.
A tale of scale & speed: How the US Navy is enabling software delivery from l...sonjaschweigert1
Rapid and secure feature delivery is a goal across every application team and every branch of the DoD. The Navy’s DevSecOps platform, Party Barge, has achieved:
- Reduction in onboarding time from 5 weeks to 1 day
- Improved developer experience and productivity through actionable findings and reduction of false positives
- Maintenance of superior security standards and inherent policy enforcement with Authorization to Operate (ATO)
Development teams can ship efficiently and ensure applications are cyber ready for Navy Authorizing Officials (AOs). In this webinar, Sigma Defense and Anchore will give attendees a look behind the scenes and demo secure pipeline automation and security artifacts that speed up application ATO and time to production.
We will cover:
- How to remove silos in DevSecOps
- How to build efficient development pipeline roles and component templates
- How to deliver security artifacts that matter for ATO’s (SBOMs, vulnerability reports, and policy evidence)
- How to streamline operations with automated policy checks on container images
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Zilliz
Join us to introduce Milvus Lite, a vector database that can run on notebooks and laptops, share the same API with Milvus, and integrate with every popular GenAI framework. This webinar is perfect for developers seeking easy-to-use, well-integrated vector databases for their GenAI apps.
Climate Impact of Software Testing at Nordic Testing DaysKari Kakkonen
My slides at Nordic Testing Days 6.6.2024
Climate impact / sustainability of software testing discussed on the talk. ICT and testing must carry their part of global responsibility to help with the climat warming. We can minimize the carbon footprint but we can also have a carbon handprint, a positive impact on the climate. Quality characteristics can be added with sustainability, and then measured continuously. Test environments can be used less, and in smaller scale and on demand. Test techniques can be used in optimizing or minimizing number of tests. Test automation can be used to speed up testing.
Maruthi Prithivirajan, Head of ASEAN & IN Solution Architecture, Neo4j
Get an inside look at the latest Neo4j innovations that enable relationship-driven intelligence at scale. Learn more about the newest cloud integrations and product enhancements that make Neo4j an essential choice for developers building apps with interconnected data and generative AI.
Communications Mining Series - Zero to Hero - Session 1DianaGray10
This session provides introduction to UiPath Communication Mining, importance and platform overview. You will acquire a good understand of the phases in Communication Mining as we go over the platform with you. Topics covered:
• Communication Mining Overview
• Why is it important?
• How can it help today’s business and the benefits
• Phases in Communication Mining
• Demo on Platform overview
• Q/A
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...SOFTTECHHUB
The choice of an operating system plays a pivotal role in shaping our computing experience. For decades, Microsoft's Windows has dominated the market, offering a familiar and widely adopted platform for personal and professional use. However, as technological advancements continue to push the boundaries of innovation, alternative operating systems have emerged, challenging the status quo and offering users a fresh perspective on computing.
One such alternative that has garnered significant attention and acclaim is Nitrux Linux 3.5.0, a sleek, powerful, and user-friendly Linux distribution that promises to redefine the way we interact with our devices. With its focus on performance, security, and customization, Nitrux Linux presents a compelling case for those seeking to break free from the constraints of proprietary software and embrace the freedom and flexibility of open-source computing.
“An Outlook of the Ongoing and Future Relationship between Blockchain Technologies and Process-aware Information Systems.” Invited talk at the joint workshop on Blockchain for Information Systems (BC4IS) and Blockchain for Trusted Data Sharing (B4TDS), co-located with with the 36th International Conference on Advanced Information Systems Engineering (CAiSE), 3 June 2024, Limassol, Cyprus.
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfPaige Cruz
Monitoring and observability aren’t traditionally found in software curriculums and many of us cobble this knowledge together from whatever vendor or ecosystem we were first introduced to and whatever is a part of your current company’s observability stack.
While the dev and ops silo continues to crumble….many organizations still relegate monitoring & observability as the purview of ops, infra and SRE teams. This is a mistake - achieving a highly observable system requires collaboration up and down the stack.
I, a former op, would like to extend an invitation to all application developers to join the observability party will share these foundational concepts to build on:
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!SOFTTECHHUB
As the digital landscape continually evolves, operating systems play a critical role in shaping user experiences and productivity. The launch of Nitrux Linux 3.5.0 marks a significant milestone, offering a robust alternative to traditional systems such as Windows 11. This article delves into the essence of Nitrux Linux 3.5.0, exploring its unique features, advantages, and how it stands as a compelling choice for both casual users and tech enthusiasts.
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc
How does your privacy program stack up against your peers? What challenges are privacy teams tackling and prioritizing in 2024?
In the fifth annual Global Privacy Benchmarks Survey, we asked over 1,800 global privacy professionals and business executives to share their perspectives on the current state of privacy inside and outside of their organizations. This year’s report focused on emerging areas of importance for privacy and compliance professionals, including considerations and implications of Artificial Intelligence (AI) technologies, building brand trust, and different approaches for achieving higher privacy competence scores.
See how organizational priorities and strategic approaches to data security and privacy are evolving around the globe.
This webinar will review:
- The top 10 privacy insights from the fifth annual Global Privacy Benchmarks Survey
- The top challenges for privacy leaders, practitioners, and organizations in 2024
- Key themes to consider in developing and maintaining your privacy program
2. Furnace Safeguard Supervisory System
2
Satisfactory Boiler start up & Shutdown
Start up of individual oil system AB,BC,CD & EF
Operation of fuel firing subject to certain conditions
A/B/C/D/E/F
Protection and interlock of Oil /Coal System
8 July 2020 2
3. Hardware Configuration
FSSS is implemented using three different systems:
1. Safety Manager system
2. DCS System
3. MFT cabinet
In Butibori power project, totally three controllers (1S1, 1B6, 1B7 as the controller
name), 10 DCS cabinets are used for FSSS, list as below:
1. FSSS SYSTEM OVERVIEW
6. The major functions implemented in 1S1
controller include
1. MFT/OFT processing
2. Furnace purge
3. Fuel oil leak test
4. Fuel oil burner control
These functions are all critical for safe boiler operation,
so the Safety Manager is used for 1S1 controller.
SAFETY MANAGER(1S1)
7. 1B61, 1B62 cabinet linked with 1B6 controller & C300
IOTA cards.
1B71, 1B72 cabinet linked with 1B7 controller & C300
IOTA cards.
1BJ61 Relay cabinet for 1B6
1BJ71 Relay cabinet for 1B7
1B6 controller implements the PULVERISER A/C/E system
start/stop control.
1B7 controller implements the PULVERISER B/D/F system
start/stop control.
DCS SYSTEM(1B6/1B7)
8. A. Common control logic
B. Fuel oil control logics
C. Coal-fired control logics
8
FSSS logics can be broadly divided into 3
sections.
9. A. Common Control Logics
(a) Boiler purge logic
(b) Master fuel trip logic/Oil fuel trip
(c) Fuel oil leak test
(d) Scanner air Fans logic
9
10. (a) Boiler purge Logic
Purpose: :
Complete Removal of unburnt fuel from entire furnace
Procedure:
Ensure that all fuel to furnace is cut off and all flame
is out
Provide adequate air flow through furnace (> 30 %)
Initiate a MANDATORY purge time cycle (5 min)
Consequence:
Master Fuel Trip Relays are reset
Firing of fuel into the furnace is allowed
10
11. Furnace purge conditions
MFT ACTION
ANY ID FAN RUNNING
ANY FDF RUNNING
ANY APH RUNNING
BOTH PA FAN STOPPED
ALL PULV STOPPED
ALL COAL FEEDER STOPPED
ALL PULV OUTLET DAMPER CLOSED
ALL OIL/PURG/ATOM/VALVE CLOSED
NO FLAME DETECTED
NO MFT CONDITION
AIR FLOW >30%,DRUM LEVEL SUITABLE & FURNACE PRESSURE
SHOULD BE ADEQUATE
HFO AND LDO LEAK TEST OK OR BYPASS
11
12.
13. (b) Master fuel trip logic
This ensures a safe shut down of the boiler in case of
any abnormal conditions in boiler.
MFT consequences
Activate MFT trip relay
Trips all mills
Trips all feeders
Trips PA fans
Closes HFO trip valve
Closes all elevation nozzle valves
Close all pulveriser outlet dampers
Closes all SH & RH spray MOVs
Send the hardwired signal to DCS,ETS,Bypass and soot blowing system
13
14. 14
TURBINE TRIP AND LOAD >60%
ALL FD FAN STOPPED
ALL ID FAN STOPPED
All PA FAN STOP WHILE ANY MILL IN SERVICE BUT NOT ANY GUN
ALL SCANNER COOLING AIR FAN STOP & HEADER PRESS LOW
SCANNER AIR FAN OUTLET HEADER PRESSURE LOW LOW (2/3 LOGIC)
FURNACE PRESSURE HH TRIP(2/3 LOGIC)
FURNACE PRESSURE LOW TRIP(2/3 LOGIC)
DRUM LEVEL HH TRIP(2/3 LOGIC)
DRUM LEVEL LOW LOW TRIP(2/3 LOGIC)
ALL APH STOPPED
TOTAL AIR FLOW <30%
OPERATOR MANUAL TRIP
REHEATER LOST PROTECTION
LOSS OF ALL FUEL
IGNITION DELAY
LOSS OF ALL FLAME
The various abnormal operating conditions under which
Master Fuel Trip occurs are as follows:-
15. Conditions for MFT:
Furnace pressure very high.
Tripping at : +20 mbar
Furnace pressure very low.
Tripping at : -20 mbar
Drum level very high.
Tripping at : +400 mm
Drum level very Low.
Tripping at : -280 mm
23. Loss of all flame trip:
Any one coal feeder running
And
All coal layers no flame
And
BC all corners no flame
And
AB all corners no flame
And
CD all corners no flame
And
EF all corners no flame.
24. Loss of all Fuel trip:
All LDO layer oil valve closed.
And
All coal feeder stopped.
Ignition delay trip:
After MFT reset no any gun taken in service
within 60 mins.
OR
After MFT reset, any BC gun not proven in
consecutives 3 attempt.
25. Both PA fan tripped
And
All mills not stopped
And
Any OIL corner is not running
26. Reheater protection trip:
Total Fuel flow > 40Ton with any of the following
conditions.
1. Turbine’s all TV or GV closed & HP
bypass closed.
OR
2. Turbine’s all IV or RSV closed & LP
bypass closed.
27. Operator manual trip-
If operator wants stop boiler for maintenance
or for some other reason, he can do that by
pressing two MFT push buttons together.
28. Oil fuel trip (OFT)
28
Oil fuel trip logic(OFT) inspects the fuel oil
parameters. On any dangerous situations
which will keep boiler from safe operation
occures, OFT will fast cutoff the running oil
burners and close the oil supply shutoff valve.
FSSS continuously supervise the OFT
conditions and will trigger the OFT if any
conditions occures
29. LDO OFT CONDITIONS
Manual trip. Operator close command to the
LDO supply shut off valve.
MFT
Ldo shut-off valve not opened pulse
Ldo supply line pressure LL with 5sec and
any burner oil valve is opened
Ldo atomosing pressure LL with 5sec and any
burner oil valve is opened
29
30. LDO OFT WILL BE RESET UNDER
FOLLOWING CONDITIONS
No any LDO OFT condition exits
LDO supply shut-off valve is closed
All LDO burner oil valve closed
LDO oil leak test complete
30
31. HFO OFT CONDITIONS
Manual trip. Operator close command to the
HFO supply shut off valve.
MFT
HFO shut-off valve not opened pulse
HFO supply line pressure LL with 5sec and
any burner oil valve is opened
HFO atomosing pressure LL with 5sec and
any burner oil valve is opened
31
32. HFO OFT WILL BE RESET UNDER
FOLLOWING CONDITIONS
No any HFO OFT condition exits
HFO supply shut-off valve is closed
All HFO burner oil valve closed
HFO oil leak test complete
32
33. LDO ignition conditions
MFT RESET
LDO OFT reset
LDO supply shut-off valve opened
Flame detector fan cooling air pressure normal
Atomizing air pressure normal
Boiler drum level normal or RB action
Furnace pressure normal or RB action
33
34. HFO ignition conditions
MFT RESET
HFO OFT reset
HFO supply shut-off valve opened
Flame detector fan cooling air pressure normal
Atomizing steam pressure normal
Boiler drum level normal
Furnace pressure normal
HFO supply oil temperature normal
LDO BC layer running or any coal layer running
34
35. (d) Scanner air fan logic
1.SAF start permissive-
(i) SAF-A in remote & no any local fault.
2. Auto start condition-
(i) The cooling air fan B protection trip
(ii)Any of flame detector air header pressure low
3. Stop permissive-
(i) The cooling air fan B running and fan A in
remote
(ii)MFT occurs and fan A in remote
35
36. Coal fired control logics-
All six layers mill system sequence control
Single device interlock control like coal
feeder,pulverizer & relevant dampers
Coal fired control logic accomplishes the mill
system start/stop control,supervision of every
running coal layer parameters and fast cut off
of coal if necessary to ensure the furnace in
safety condition.
36
37. Coal ignition conditions
37
MFT is reset
The DP of furnace and secondary air wind-
box is normal
The DP of furnace and hot primary air header
not low
Hot secondary air temperature >160 deg
Any primary air fan running
Swaying burner tilt position horizontal or any
coal layer in service
38. Coal layers ignition energy requirements
Any of the following conditions satisfied means Coal
layer A ignition energy sufficient
AB oil layer in service
Coal layer B federate >50% under boiler load >30%
Any two coal layers in service under boiler load >60%
Any of the following conditions satisfied means Coal
layer B ignition energy sufficient
AB oil layer in service
BC oil layer in service
Coal layer A federate >50% under boiler load >30%
Any two coal layer in service under boiler load>60%
38
39. Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer C ignition energy sufficient
BC oil layer in service
CD oil layer in service
Coal layer B federate >50% under boiler load
>30%
Coal layer D federate >50% under boiler load
>30%
Any two coal layers in service under boiler
load >60% 39
40. Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer D ignition energy sufficient
CD oil layer in service
Coal layer C federate >50% under boiler load >30%
Coal layer E federate >50% under boiler load >30%
Any two coal layer in service under boiler load>60%
40
41. Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer E ignition energy sufficient
EF oil layer in service
Coal layer D federate >50% under boiler load >30%
Coal layer F federate >50% under boiler load >30%
Any two coal layer in service under boiler load>60%
41
42. Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer F ignition energy sufficient
EF oil layer in service
Coal layer E federate >50% under boiler load >30%
Any two coal layer in service under boiler load>60%
42
43. Coal feeder A
The following conditions are the permissive
conditions for feeder start up:-
Pulverizer A is running
Coal layer ignition condition exits
Coal layer A ignition energy satisfied
Coal feeder A sealing air damper is opened
Coal feeder A outlet vavle opened
Coal feeder A feedrate is minimum
Pulverizer A outlet temp ok(b/w 65 to 82deg)
Coal feeder A in remote control
No any coal layer trip conditions exits
44
44. Coal feeder A auto stop under following
conditions-
Pulverizer A stopped under coal feeder A
running
Any pulverizer A trip condition
Coal feeder A outlet vavle closed with 5sec
delay
Coal feeder A outlet blokage with 20sec delay
Coal feeder A belt zero coal with 5sec delay
Coal feeder A inner over temperature with
3sec delay
45
46. Run Back (RB) is a function initiated by CCS system when the
boiler could not operate with the set load due to the failure of
major auxiliary device of the boiler such as water feed pump,
forced/induced air fan, primary air fan, etc. in case the unit
load is above 50%.
The purpose of RB function is to reduce the input fuel fast and
keep the boiler in safe operating condition.
FSSS system will perform the RB action only when more than
three coal layers are in service; the logic will remove the
upper coal layers in service from top to bottom preferentially
in proper time interval to match the boiler load and the boiler
auxiliary device’s contribution.
Run Back
47. Actions after RB:
When more than three coal layers are in service, if FSSS received the RB
command, the following will be performed:
Fast start the LDO BC oil layer with pair mode.
Override close the return LDO shut off valve.
Remove coal layer F, E and D from top to bottom layer. Coal layer F will
be shutdown first. Coal layer E will be shutdown if still more than three
coal layers are in service at the moment 2 seconds adjustable after coal
layer F shutdown.
The process will continue in that way until coal layer D is shutdown.
RB Reset Condition:
The following conditions will reset the RB signal (or):
Operate cancels the RB function.
The RB succeeded with the unit load less than the predefined RB target.