SlideShare a Scribd company logo
Furnace Safeguard & Supervisory
System
8 July 2020 VIPL
Avadhesh Tiwari
Furnace Safeguard Supervisory System
2
 Satisfactory Boiler start up & Shutdown
 Start up of individual oil system AB,BC,CD & EF
 Operation of fuel firing subject to certain conditions
A/B/C/D/E/F
 Protection and interlock of Oil /Coal System
8 July 2020 2
Hardware Configuration
FSSS is implemented using three different systems:
1. Safety Manager system
2. DCS System
3. MFT cabinet
In Butibori power project, totally three controllers (1S1, 1B6, 1B7 as the controller
name), 10 DCS cabinets are used for FSSS, list as below:
1. FSSS SYSTEM OVERVIEW
PHYSICAL REPRESENTATION OF PANEL
PANEL VIEW
The major functions implemented in 1S1
controller include
1. MFT/OFT processing
2. Furnace purge
3. Fuel oil leak test
4. Fuel oil burner control
These functions are all critical for safe boiler operation,
so the Safety Manager is used for 1S1 controller.
SAFETY MANAGER(1S1)
1B61, 1B62 cabinet linked with 1B6 controller & C300
IOTA cards.
1B71, 1B72 cabinet linked with 1B7 controller & C300
IOTA cards.
1BJ61 Relay cabinet for 1B6
1BJ71 Relay cabinet for 1B7
1B6 controller implements the PULVERISER A/C/E system
start/stop control.
1B7 controller implements the PULVERISER B/D/F system
start/stop control.
DCS SYSTEM(1B6/1B7)
A. Common control logic
B. Fuel oil control logics
C. Coal-fired control logics
8
FSSS logics can be broadly divided into 3
sections.
A. Common Control Logics
(a) Boiler purge logic
(b) Master fuel trip logic/Oil fuel trip
(c) Fuel oil leak test
(d) Scanner air Fans logic
9
(a) Boiler purge Logic
Purpose: :
Complete Removal of unburnt fuel from entire furnace
Procedure:
 Ensure that all fuel to furnace is cut off and all flame
is out
 Provide adequate air flow through furnace (> 30 %)
 Initiate a MANDATORY purge time cycle (5 min)
Consequence:
 Master Fuel Trip Relays are reset
 Firing of fuel into the furnace is allowed
10
Furnace purge conditions
 MFT ACTION
 ANY ID FAN RUNNING
 ANY FDF RUNNING
 ANY APH RUNNING
 BOTH PA FAN STOPPED
 ALL PULV STOPPED
 ALL COAL FEEDER STOPPED
 ALL PULV OUTLET DAMPER CLOSED
 ALL OIL/PURG/ATOM/VALVE CLOSED
 NO FLAME DETECTED
 NO MFT CONDITION
 AIR FLOW >30%,DRUM LEVEL SUITABLE & FURNACE PRESSURE
SHOULD BE ADEQUATE
 HFO AND LDO LEAK TEST OK OR BYPASS
11
(b) Master fuel trip logic
This ensures a safe shut down of the boiler in case of
any abnormal conditions in boiler.
MFT consequences
 Activate MFT trip relay
 Trips all mills
 Trips all feeders
 Trips PA fans
 Closes HFO trip valve
 Closes all elevation nozzle valves
 Close all pulveriser outlet dampers
 Closes all SH & RH spray MOVs
 Send the hardwired signal to DCS,ETS,Bypass and soot blowing system
13
14
 TURBINE TRIP AND LOAD >60%
 ALL FD FAN STOPPED
 ALL ID FAN STOPPED
 All PA FAN STOP WHILE ANY MILL IN SERVICE BUT NOT ANY GUN
 ALL SCANNER COOLING AIR FAN STOP & HEADER PRESS LOW
 SCANNER AIR FAN OUTLET HEADER PRESSURE LOW LOW (2/3 LOGIC)
 FURNACE PRESSURE HH TRIP(2/3 LOGIC)
 FURNACE PRESSURE LOW TRIP(2/3 LOGIC)
 DRUM LEVEL HH TRIP(2/3 LOGIC)
 DRUM LEVEL LOW LOW TRIP(2/3 LOGIC)
 ALL APH STOPPED
 TOTAL AIR FLOW <30%
 OPERATOR MANUAL TRIP
 REHEATER LOST PROTECTION
 LOSS OF ALL FUEL
 IGNITION DELAY
 LOSS OF ALL FLAME
The various abnormal operating conditions under which
Master Fuel Trip occurs are as follows:-
Conditions for MFT:
 Furnace pressure very high.
Tripping at : +20 mbar
 Furnace pressure very low.
Tripping at : -20 mbar
 Drum level very high.
Tripping at : +400 mm
 Drum level very Low.
Tripping at : -280 mm
Both FD fan tripped.
Both ID fan tripped.
Both APH tripped.
Secondary air flow very low
Turbine tripped & Load > 60%. (i.e. 180MW)
Both scanner cooling air fan tripped
Scanner cooling air fan pressure very low.
Tripping at : < 32.5 mbar
Loss of all flame trip:
Any one coal feeder running
And
All coal layers no flame
And
BC all corners no flame
And
AB all corners no flame
And
CD all corners no flame
And
EF all corners no flame.
Loss of all Fuel trip:
All LDO layer oil valve closed.
And
All coal feeder stopped.
Ignition delay trip:
After MFT reset no any gun taken in service
within 60 mins.
OR
After MFT reset, any BC gun not proven in
consecutives 3 attempt.
Both PA fan tripped
And
All mills not stopped
And
Any OIL corner is not running
Reheater protection trip:
 Total Fuel flow > 40Ton with any of the following
conditions.
1. Turbine’s all TV or GV closed & HP
bypass closed.
OR
2. Turbine’s all IV or RSV closed & LP
bypass closed.
Operator manual trip-
If operator wants stop boiler for maintenance
or for some other reason, he can do that by
pressing two MFT push buttons together.
Oil fuel trip (OFT)
28
 Oil fuel trip logic(OFT) inspects the fuel oil
parameters. On any dangerous situations
which will keep boiler from safe operation
occures, OFT will fast cutoff the running oil
burners and close the oil supply shutoff valve.
 FSSS continuously supervise the OFT
conditions and will trigger the OFT if any
conditions occures
LDO OFT CONDITIONS
 Manual trip. Operator close command to the
LDO supply shut off valve.
 MFT
 Ldo shut-off valve not opened pulse
 Ldo supply line pressure LL with 5sec and
any burner oil valve is opened
 Ldo atomosing pressure LL with 5sec and any
burner oil valve is opened
29
LDO OFT WILL BE RESET UNDER
FOLLOWING CONDITIONS
 No any LDO OFT condition exits
 LDO supply shut-off valve is closed
 All LDO burner oil valve closed
 LDO oil leak test complete
30
HFO OFT CONDITIONS
 Manual trip. Operator close command to the
HFO supply shut off valve.
 MFT
 HFO shut-off valve not opened pulse
 HFO supply line pressure LL with 5sec and
any burner oil valve is opened
 HFO atomosing pressure LL with 5sec and
any burner oil valve is opened
31
HFO OFT WILL BE RESET UNDER
FOLLOWING CONDITIONS
 No any HFO OFT condition exits
 HFO supply shut-off valve is closed
 All HFO burner oil valve closed
 HFO oil leak test complete
32
LDO ignition conditions
 MFT RESET
 LDO OFT reset
 LDO supply shut-off valve opened
 Flame detector fan cooling air pressure normal
 Atomizing air pressure normal
 Boiler drum level normal or RB action
 Furnace pressure normal or RB action
33
HFO ignition conditions
 MFT RESET
 HFO OFT reset
 HFO supply shut-off valve opened
 Flame detector fan cooling air pressure normal
 Atomizing steam pressure normal
 Boiler drum level normal
 Furnace pressure normal
 HFO supply oil temperature normal
 LDO BC layer running or any coal layer running
34
(d) Scanner air fan logic
1.SAF start permissive-
(i) SAF-A in remote & no any local fault.
2. Auto start condition-
(i) The cooling air fan B protection trip
(ii)Any of flame detector air header pressure low
3. Stop permissive-
(i) The cooling air fan B running and fan A in
remote
(ii)MFT occurs and fan A in remote
35
Coal fired control logics-
 All six layers mill system sequence control
 Single device interlock control like coal
feeder,pulverizer & relevant dampers
 Coal fired control logic accomplishes the mill
system start/stop control,supervision of every
running coal layer parameters and fast cut off
of coal if necessary to ensure the furnace in
safety condition.
36
Coal ignition conditions
37
 MFT is reset
 The DP of furnace and secondary air wind-
box is normal
 The DP of furnace and hot primary air header
not low
 Hot secondary air temperature >160 deg
 Any primary air fan running
 Swaying burner tilt position horizontal or any
coal layer in service
Coal layers ignition energy requirements
Any of the following conditions satisfied means Coal
layer A ignition energy sufficient
 AB oil layer in service
 Coal layer B federate >50% under boiler load >30%
 Any two coal layers in service under boiler load >60%
Any of the following conditions satisfied means Coal
layer B ignition energy sufficient
 AB oil layer in service
 BC oil layer in service
 Coal layer A federate >50% under boiler load >30%
 Any two coal layer in service under boiler load>60%
38
Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer C ignition energy sufficient
 BC oil layer in service
 CD oil layer in service
 Coal layer B federate >50% under boiler load
>30%
 Coal layer D federate >50% under boiler load
>30%
 Any two coal layers in service under boiler
load >60% 39
Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer D ignition energy sufficient
 CD oil layer in service
 Coal layer C federate >50% under boiler load >30%
 Coal layer E federate >50% under boiler load >30%
 Any two coal layer in service under boiler load>60%
40
Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer E ignition energy sufficient
 EF oil layer in service
 Coal layer D federate >50% under boiler load >30%
 Coal layer F federate >50% under boiler load >30%
 Any two coal layer in service under boiler load>60%
41
Coal layers ignition energy requirements
Any of the following conditions satisfied means
Coal layer F ignition energy sufficient
 EF oil layer in service
 Coal layer E federate >50% under boiler load >30%
 Any two coal layer in service under boiler load>60%
42
Coal feeder A
The following conditions are the permissive
conditions for feeder start up:-
 Pulverizer A is running
 Coal layer ignition condition exits
 Coal layer A ignition energy satisfied
 Coal feeder A sealing air damper is opened
 Coal feeder A outlet vavle opened
 Coal feeder A feedrate is minimum
 Pulverizer A outlet temp ok(b/w 65 to 82deg)
 Coal feeder A in remote control
 No any coal layer trip conditions exits
44
Coal feeder A auto stop under following
conditions-
 Pulverizer A stopped under coal feeder A
running
 Any pulverizer A trip condition
 Coal feeder A outlet vavle closed with 5sec
delay
 Coal feeder A outlet blokage with 20sec delay
 Coal feeder A belt zero coal with 5sec delay
 Coal feeder A inner over temperature with
3sec delay
45
Thank You
 Run Back (RB) is a function initiated by CCS system when the
boiler could not operate with the set load due to the failure of
major auxiliary device of the boiler such as water feed pump,
forced/induced air fan, primary air fan, etc. in case the unit
load is above 50%.
 The purpose of RB function is to reduce the input fuel fast and
keep the boiler in safe operating condition.
 FSSS system will perform the RB action only when more than
three coal layers are in service; the logic will remove the
upper coal layers in service from top to bottom preferentially
in proper time interval to match the boiler load and the boiler
auxiliary device’s contribution.
Run Back
Actions after RB:
When more than three coal layers are in service, if FSSS received the RB
command, the following will be performed:
 Fast start the LDO BC oil layer with pair mode.
 Override close the return LDO shut off valve.
 Remove coal layer F, E and D from top to bottom layer. Coal layer F will
be shutdown first. Coal layer E will be shutdown if still more than three
coal layers are in service at the moment 2 seconds adjustable after coal
layer F shutdown.
 The process will continue in that way until coal layer D is shutdown.
RB Reset Condition:
The following conditions will reset the RB signal (or):
 Operate cancels the RB function.
 The RB succeeded with the unit load less than the predefined RB target.

More Related Content

What's hot

Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
Ashvani Shukla
 
Globecore transformer oil regeneration and purification equipment
Globecore transformer oil regeneration and purification equipmentGlobecore transformer oil regeneration and purification equipment
Globecore transformer oil regeneration and purification equipment
GlobeCore
 
Globecore transformer oil purification plant cmm 2,2
Globecore transformer oil purification plant cmm  2,2Globecore transformer oil purification plant cmm  2,2
Globecore transformer oil purification plant cmm 2,2
GlobeCore
 
GlobeCore transformer oil regeneration plant CMM 12R_ 4000
GlobeCore transformer oil regeneration plant CMM 12R_ 4000 GlobeCore transformer oil regeneration plant CMM 12R_ 4000
GlobeCore transformer oil regeneration plant CMM 12R_ 4000
GlobeCore
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
mitravanu mishra
 
Transformer oil regeneration plant CMM R
Transformer oil regeneration plant CMM RTransformer oil regeneration plant CMM R
Transformer oil regeneration plant CMM R
GlobeCore
 
Transformer oil regeneration plant globecore cmm r
Transformer oil regeneration plant globecore cmm rTransformer oil regeneration plant globecore cmm r
Transformer oil regeneration plant globecore cmm r
GlobeCore
 
Transformer oil purification plant globecore CMM(UVM) 4-7
Transformer oil purification plant globecore CMM(UVM) 4-7Transformer oil purification plant globecore CMM(UVM) 4-7
Transformer oil purification plant globecore CMM(UVM) 4-7
GlobeCore
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
Nitin Patel
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
Manohar Tatwawadi
 
2009 toyota venza service repair manual
2009 toyota venza service repair manual2009 toyota venza service repair manual
2009 toyota venza service repair manual
fjjfyjsekdmme
 
2010 toyota venza service repair manual
2010 toyota venza service repair manual2010 toyota venza service repair manual
2010 toyota venza service repair manual
jjfksekdmejik
 
Boiler p&i
Boiler p&iBoiler p&i
Boiler p&i
Akhilesh Kushwaha
 
GlobeCore. Oil regeneration presentation paper
GlobeCore. Oil regeneration presentation paperGlobeCore. Oil regeneration presentation paper
GlobeCore. Oil regeneration presentation paper
GlobeCore
 
Tegas Industrial Group
Tegas Industrial GroupTegas Industrial Group
Caterpillar heui-controles-de-motor-3408 e-3412
Caterpillar heui-controles-de-motor-3408 e-3412Caterpillar heui-controles-de-motor-3408 e-3412
Caterpillar heui-controles-de-motor-3408 e-3412
erick
 
Cummins isb6.7 cm2150 (2007-09)
Cummins   isb6.7 cm2150 (2007-09)Cummins   isb6.7 cm2150 (2007-09)
Cummins isb6.7 cm2150 (2007-09)
DiegoLira32
 
Vertical multistage fire pump catalogue-60HZ
Vertical multistage fire pump catalogue-60HZVertical multistage fire pump catalogue-60HZ
Vertical multistage fire pump catalogue-60HZ
Andy Chen
 
660 mw turbo governing &amp; protection system
660 mw turbo  governing &amp; protection system660 mw turbo  governing &amp; protection system
660 mw turbo governing &amp; protection system
Ashvani Shukla
 
600 MW Simulator operating procedure
600 MW Simulator operating procedure600 MW Simulator operating procedure
600 MW Simulator operating procedure
MOHAMMAD ASIF
 

What's hot (20)

Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Globecore transformer oil regeneration and purification equipment
Globecore transformer oil regeneration and purification equipmentGlobecore transformer oil regeneration and purification equipment
Globecore transformer oil regeneration and purification equipment
 
Globecore transformer oil purification plant cmm 2,2
Globecore transformer oil purification plant cmm  2,2Globecore transformer oil purification plant cmm  2,2
Globecore transformer oil purification plant cmm 2,2
 
GlobeCore transformer oil regeneration plant CMM 12R_ 4000
GlobeCore transformer oil regeneration plant CMM 12R_ 4000 GlobeCore transformer oil regeneration plant CMM 12R_ 4000
GlobeCore transformer oil regeneration plant CMM 12R_ 4000
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
Transformer oil regeneration plant CMM R
Transformer oil regeneration plant CMM RTransformer oil regeneration plant CMM R
Transformer oil regeneration plant CMM R
 
Transformer oil regeneration plant globecore cmm r
Transformer oil regeneration plant globecore cmm rTransformer oil regeneration plant globecore cmm r
Transformer oil regeneration plant globecore cmm r
 
Transformer oil purification plant globecore CMM(UVM) 4-7
Transformer oil purification plant globecore CMM(UVM) 4-7Transformer oil purification plant globecore CMM(UVM) 4-7
Transformer oil purification plant globecore CMM(UVM) 4-7
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
2009 toyota venza service repair manual
2009 toyota venza service repair manual2009 toyota venza service repair manual
2009 toyota venza service repair manual
 
2010 toyota venza service repair manual
2010 toyota venza service repair manual2010 toyota venza service repair manual
2010 toyota venza service repair manual
 
Boiler p&i
Boiler p&iBoiler p&i
Boiler p&i
 
GlobeCore. Oil regeneration presentation paper
GlobeCore. Oil regeneration presentation paperGlobeCore. Oil regeneration presentation paper
GlobeCore. Oil regeneration presentation paper
 
Tegas Industrial Group
Tegas Industrial GroupTegas Industrial Group
Tegas Industrial Group
 
Caterpillar heui-controles-de-motor-3408 e-3412
Caterpillar heui-controles-de-motor-3408 e-3412Caterpillar heui-controles-de-motor-3408 e-3412
Caterpillar heui-controles-de-motor-3408 e-3412
 
Cummins isb6.7 cm2150 (2007-09)
Cummins   isb6.7 cm2150 (2007-09)Cummins   isb6.7 cm2150 (2007-09)
Cummins isb6.7 cm2150 (2007-09)
 
Vertical multistage fire pump catalogue-60HZ
Vertical multistage fire pump catalogue-60HZVertical multistage fire pump catalogue-60HZ
Vertical multistage fire pump catalogue-60HZ
 
660 mw turbo governing &amp; protection system
660 mw turbo  governing &amp; protection system660 mw turbo  governing &amp; protection system
660 mw turbo governing &amp; protection system
 
600 MW Simulator operating procedure
600 MW Simulator operating procedure600 MW Simulator operating procedure
600 MW Simulator operating procedure
 

Similar to Fsss

BMS FSSS.pptx
BMS FSSS.pptxBMS FSSS.pptx
BMS FSSS.pptx
ManzoorAlam40
 
Burner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptxBurner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptx
ManzoorAlam40
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
Jaypee power ventures limited
 
FSSS_Logic Presentation - Modified_v11.pptx
FSSS_Logic Presentation - Modified_v11.pptxFSSS_Logic Presentation - Modified_v11.pptx
FSSS_Logic Presentation - Modified_v11.pptx
MuhammadAsif771197
 
Boi_5_ST-2 Ball and Tube Mill .ppt
Boi_5_ST-2 Ball and Tube Mill  .pptBoi_5_ST-2 Ball and Tube Mill  .ppt
Boi_5_ST-2 Ball and Tube Mill .ppt
TravelTechnology1
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
SHIVAJI CHOUDHURY
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations Training
Manohar Tatwawadi
 
210 MW simulator, loading to full 210 MW
210 MW simulator, loading to full 210 MW210 MW simulator, loading to full 210 MW
210 MW simulator, loading to full 210 MW
Manohar Tatwawadi
 
Boiler purge
Boiler purge Boiler purge
Boiler purge
S V Nagesh
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
Manohar Tatwawadi
 
Caldeira Roca R-20/20
Caldeira Roca R-20/20Caldeira Roca R-20/20
Caldeira Roca R-20/20
Tiago Bettencourt
 
210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING
Nitin Patel
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
Prem Baboo
 
960649.pdf
960649.pdf960649.pdf
960649.pdf
Genaro Caruzzo
 
220446610-Heaters-Nice-Presetation.pptx
220446610-Heaters-Nice-Presetation.pptx220446610-Heaters-Nice-Presetation.pptx
220446610-Heaters-Nice-Presetation.pptx
jesscastillo67
 
Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation) Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation)
SYED KHURSHID ALAM ARZOO
 
pulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptxpulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptx
Narhari1
 
QX1401 VDL(H) spec.
QX1401 VDL(H) spec.QX1401 VDL(H) spec.
QX1401 VDL(H) spec.
Ann Wee (RIGID HVAC)
 
Woodpecker training workshop jan'11 presentation
Woodpecker training workshop jan'11 presentationWoodpecker training workshop jan'11 presentation
Woodpecker training workshop jan'11 presentation
ensightbioenergy
 
E70 CCB2 Brake system for WAG 9 Locomotive.pptx
E70 CCB2 Brake system for WAG 9 Locomotive.pptxE70 CCB2 Brake system for WAG 9 Locomotive.pptx
E70 CCB2 Brake system for WAG 9 Locomotive.pptx
SATYANARAYANABODDULA
 

Similar to Fsss (20)

BMS FSSS.pptx
BMS FSSS.pptxBMS FSSS.pptx
BMS FSSS.pptx
 
Burner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptxBurner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptx
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
FSSS_Logic Presentation - Modified_v11.pptx
FSSS_Logic Presentation - Modified_v11.pptxFSSS_Logic Presentation - Modified_v11.pptx
FSSS_Logic Presentation - Modified_v11.pptx
 
Boi_5_ST-2 Ball and Tube Mill .ppt
Boi_5_ST-2 Ball and Tube Mill  .pptBoi_5_ST-2 Ball and Tube Mill  .ppt
Boi_5_ST-2 Ball and Tube Mill .ppt
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations Training
 
210 MW simulator, loading to full 210 MW
210 MW simulator, loading to full 210 MW210 MW simulator, loading to full 210 MW
210 MW simulator, loading to full 210 MW
 
Boiler purge
Boiler purge Boiler purge
Boiler purge
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
Caldeira Roca R-20/20
Caldeira Roca R-20/20Caldeira Roca R-20/20
Caldeira Roca R-20/20
 
210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
960649.pdf
960649.pdf960649.pdf
960649.pdf
 
220446610-Heaters-Nice-Presetation.pptx
220446610-Heaters-Nice-Presetation.pptx220446610-Heaters-Nice-Presetation.pptx
220446610-Heaters-Nice-Presetation.pptx
 
Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation) Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation)
 
pulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptxpulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptx
 
QX1401 VDL(H) spec.
QX1401 VDL(H) spec.QX1401 VDL(H) spec.
QX1401 VDL(H) spec.
 
Woodpecker training workshop jan'11 presentation
Woodpecker training workshop jan'11 presentationWoodpecker training workshop jan'11 presentation
Woodpecker training workshop jan'11 presentation
 
E70 CCB2 Brake system for WAG 9 Locomotive.pptx
E70 CCB2 Brake system for WAG 9 Locomotive.pptxE70 CCB2 Brake system for WAG 9 Locomotive.pptx
E70 CCB2 Brake system for WAG 9 Locomotive.pptx
 

Recently uploaded

GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
Neo4j
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
Neo4j
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Zilliz
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
Kari Kakkonen
 
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
Neo4j
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
DianaGray10
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
SOFTTECHHUB
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
Claudio Di Ciccio
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Paige Cruz
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
TIPNGVN2
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
mikeeftimakis1
 
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
SOFTTECHHUB
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 

Recently uploaded (20)

GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
 
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
 
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 

Fsss

  • 1. Furnace Safeguard & Supervisory System 8 July 2020 VIPL Avadhesh Tiwari
  • 2. Furnace Safeguard Supervisory System 2  Satisfactory Boiler start up & Shutdown  Start up of individual oil system AB,BC,CD & EF  Operation of fuel firing subject to certain conditions A/B/C/D/E/F  Protection and interlock of Oil /Coal System 8 July 2020 2
  • 3. Hardware Configuration FSSS is implemented using three different systems: 1. Safety Manager system 2. DCS System 3. MFT cabinet In Butibori power project, totally three controllers (1S1, 1B6, 1B7 as the controller name), 10 DCS cabinets are used for FSSS, list as below: 1. FSSS SYSTEM OVERVIEW
  • 6. The major functions implemented in 1S1 controller include 1. MFT/OFT processing 2. Furnace purge 3. Fuel oil leak test 4. Fuel oil burner control These functions are all critical for safe boiler operation, so the Safety Manager is used for 1S1 controller. SAFETY MANAGER(1S1)
  • 7. 1B61, 1B62 cabinet linked with 1B6 controller & C300 IOTA cards. 1B71, 1B72 cabinet linked with 1B7 controller & C300 IOTA cards. 1BJ61 Relay cabinet for 1B6 1BJ71 Relay cabinet for 1B7 1B6 controller implements the PULVERISER A/C/E system start/stop control. 1B7 controller implements the PULVERISER B/D/F system start/stop control. DCS SYSTEM(1B6/1B7)
  • 8. A. Common control logic B. Fuel oil control logics C. Coal-fired control logics 8 FSSS logics can be broadly divided into 3 sections.
  • 9. A. Common Control Logics (a) Boiler purge logic (b) Master fuel trip logic/Oil fuel trip (c) Fuel oil leak test (d) Scanner air Fans logic 9
  • 10. (a) Boiler purge Logic Purpose: : Complete Removal of unburnt fuel from entire furnace Procedure:  Ensure that all fuel to furnace is cut off and all flame is out  Provide adequate air flow through furnace (> 30 %)  Initiate a MANDATORY purge time cycle (5 min) Consequence:  Master Fuel Trip Relays are reset  Firing of fuel into the furnace is allowed 10
  • 11. Furnace purge conditions  MFT ACTION  ANY ID FAN RUNNING  ANY FDF RUNNING  ANY APH RUNNING  BOTH PA FAN STOPPED  ALL PULV STOPPED  ALL COAL FEEDER STOPPED  ALL PULV OUTLET DAMPER CLOSED  ALL OIL/PURG/ATOM/VALVE CLOSED  NO FLAME DETECTED  NO MFT CONDITION  AIR FLOW >30%,DRUM LEVEL SUITABLE & FURNACE PRESSURE SHOULD BE ADEQUATE  HFO AND LDO LEAK TEST OK OR BYPASS 11
  • 12.
  • 13. (b) Master fuel trip logic This ensures a safe shut down of the boiler in case of any abnormal conditions in boiler. MFT consequences  Activate MFT trip relay  Trips all mills  Trips all feeders  Trips PA fans  Closes HFO trip valve  Closes all elevation nozzle valves  Close all pulveriser outlet dampers  Closes all SH & RH spray MOVs  Send the hardwired signal to DCS,ETS,Bypass and soot blowing system 13
  • 14. 14  TURBINE TRIP AND LOAD >60%  ALL FD FAN STOPPED  ALL ID FAN STOPPED  All PA FAN STOP WHILE ANY MILL IN SERVICE BUT NOT ANY GUN  ALL SCANNER COOLING AIR FAN STOP & HEADER PRESS LOW  SCANNER AIR FAN OUTLET HEADER PRESSURE LOW LOW (2/3 LOGIC)  FURNACE PRESSURE HH TRIP(2/3 LOGIC)  FURNACE PRESSURE LOW TRIP(2/3 LOGIC)  DRUM LEVEL HH TRIP(2/3 LOGIC)  DRUM LEVEL LOW LOW TRIP(2/3 LOGIC)  ALL APH STOPPED  TOTAL AIR FLOW <30%  OPERATOR MANUAL TRIP  REHEATER LOST PROTECTION  LOSS OF ALL FUEL  IGNITION DELAY  LOSS OF ALL FLAME The various abnormal operating conditions under which Master Fuel Trip occurs are as follows:-
  • 15. Conditions for MFT:  Furnace pressure very high. Tripping at : +20 mbar  Furnace pressure very low. Tripping at : -20 mbar  Drum level very high. Tripping at : +400 mm  Drum level very Low. Tripping at : -280 mm
  • 16. Both FD fan tripped.
  • 17. Both ID fan tripped.
  • 19. Secondary air flow very low
  • 20. Turbine tripped & Load > 60%. (i.e. 180MW)
  • 21. Both scanner cooling air fan tripped
  • 22. Scanner cooling air fan pressure very low. Tripping at : < 32.5 mbar
  • 23. Loss of all flame trip: Any one coal feeder running And All coal layers no flame And BC all corners no flame And AB all corners no flame And CD all corners no flame And EF all corners no flame.
  • 24. Loss of all Fuel trip: All LDO layer oil valve closed. And All coal feeder stopped. Ignition delay trip: After MFT reset no any gun taken in service within 60 mins. OR After MFT reset, any BC gun not proven in consecutives 3 attempt.
  • 25. Both PA fan tripped And All mills not stopped And Any OIL corner is not running
  • 26. Reheater protection trip:  Total Fuel flow > 40Ton with any of the following conditions. 1. Turbine’s all TV or GV closed & HP bypass closed. OR 2. Turbine’s all IV or RSV closed & LP bypass closed.
  • 27. Operator manual trip- If operator wants stop boiler for maintenance or for some other reason, he can do that by pressing two MFT push buttons together.
  • 28. Oil fuel trip (OFT) 28  Oil fuel trip logic(OFT) inspects the fuel oil parameters. On any dangerous situations which will keep boiler from safe operation occures, OFT will fast cutoff the running oil burners and close the oil supply shutoff valve.  FSSS continuously supervise the OFT conditions and will trigger the OFT if any conditions occures
  • 29. LDO OFT CONDITIONS  Manual trip. Operator close command to the LDO supply shut off valve.  MFT  Ldo shut-off valve not opened pulse  Ldo supply line pressure LL with 5sec and any burner oil valve is opened  Ldo atomosing pressure LL with 5sec and any burner oil valve is opened 29
  • 30. LDO OFT WILL BE RESET UNDER FOLLOWING CONDITIONS  No any LDO OFT condition exits  LDO supply shut-off valve is closed  All LDO burner oil valve closed  LDO oil leak test complete 30
  • 31. HFO OFT CONDITIONS  Manual trip. Operator close command to the HFO supply shut off valve.  MFT  HFO shut-off valve not opened pulse  HFO supply line pressure LL with 5sec and any burner oil valve is opened  HFO atomosing pressure LL with 5sec and any burner oil valve is opened 31
  • 32. HFO OFT WILL BE RESET UNDER FOLLOWING CONDITIONS  No any HFO OFT condition exits  HFO supply shut-off valve is closed  All HFO burner oil valve closed  HFO oil leak test complete 32
  • 33. LDO ignition conditions  MFT RESET  LDO OFT reset  LDO supply shut-off valve opened  Flame detector fan cooling air pressure normal  Atomizing air pressure normal  Boiler drum level normal or RB action  Furnace pressure normal or RB action 33
  • 34. HFO ignition conditions  MFT RESET  HFO OFT reset  HFO supply shut-off valve opened  Flame detector fan cooling air pressure normal  Atomizing steam pressure normal  Boiler drum level normal  Furnace pressure normal  HFO supply oil temperature normal  LDO BC layer running or any coal layer running 34
  • 35. (d) Scanner air fan logic 1.SAF start permissive- (i) SAF-A in remote & no any local fault. 2. Auto start condition- (i) The cooling air fan B protection trip (ii)Any of flame detector air header pressure low 3. Stop permissive- (i) The cooling air fan B running and fan A in remote (ii)MFT occurs and fan A in remote 35
  • 36. Coal fired control logics-  All six layers mill system sequence control  Single device interlock control like coal feeder,pulverizer & relevant dampers  Coal fired control logic accomplishes the mill system start/stop control,supervision of every running coal layer parameters and fast cut off of coal if necessary to ensure the furnace in safety condition. 36
  • 37. Coal ignition conditions 37  MFT is reset  The DP of furnace and secondary air wind- box is normal  The DP of furnace and hot primary air header not low  Hot secondary air temperature >160 deg  Any primary air fan running  Swaying burner tilt position horizontal or any coal layer in service
  • 38. Coal layers ignition energy requirements Any of the following conditions satisfied means Coal layer A ignition energy sufficient  AB oil layer in service  Coal layer B federate >50% under boiler load >30%  Any two coal layers in service under boiler load >60% Any of the following conditions satisfied means Coal layer B ignition energy sufficient  AB oil layer in service  BC oil layer in service  Coal layer A federate >50% under boiler load >30%  Any two coal layer in service under boiler load>60% 38
  • 39. Coal layers ignition energy requirements Any of the following conditions satisfied means Coal layer C ignition energy sufficient  BC oil layer in service  CD oil layer in service  Coal layer B federate >50% under boiler load >30%  Coal layer D federate >50% under boiler load >30%  Any two coal layers in service under boiler load >60% 39
  • 40. Coal layers ignition energy requirements Any of the following conditions satisfied means Coal layer D ignition energy sufficient  CD oil layer in service  Coal layer C federate >50% under boiler load >30%  Coal layer E federate >50% under boiler load >30%  Any two coal layer in service under boiler load>60% 40
  • 41. Coal layers ignition energy requirements Any of the following conditions satisfied means Coal layer E ignition energy sufficient  EF oil layer in service  Coal layer D federate >50% under boiler load >30%  Coal layer F federate >50% under boiler load >30%  Any two coal layer in service under boiler load>60% 41
  • 42. Coal layers ignition energy requirements Any of the following conditions satisfied means Coal layer F ignition energy sufficient  EF oil layer in service  Coal layer E federate >50% under boiler load >30%  Any two coal layer in service under boiler load>60% 42
  • 43. Coal feeder A The following conditions are the permissive conditions for feeder start up:-  Pulverizer A is running  Coal layer ignition condition exits  Coal layer A ignition energy satisfied  Coal feeder A sealing air damper is opened  Coal feeder A outlet vavle opened  Coal feeder A feedrate is minimum  Pulverizer A outlet temp ok(b/w 65 to 82deg)  Coal feeder A in remote control  No any coal layer trip conditions exits 44
  • 44. Coal feeder A auto stop under following conditions-  Pulverizer A stopped under coal feeder A running  Any pulverizer A trip condition  Coal feeder A outlet vavle closed with 5sec delay  Coal feeder A outlet blokage with 20sec delay  Coal feeder A belt zero coal with 5sec delay  Coal feeder A inner over temperature with 3sec delay 45
  • 46.  Run Back (RB) is a function initiated by CCS system when the boiler could not operate with the set load due to the failure of major auxiliary device of the boiler such as water feed pump, forced/induced air fan, primary air fan, etc. in case the unit load is above 50%.  The purpose of RB function is to reduce the input fuel fast and keep the boiler in safe operating condition.  FSSS system will perform the RB action only when more than three coal layers are in service; the logic will remove the upper coal layers in service from top to bottom preferentially in proper time interval to match the boiler load and the boiler auxiliary device’s contribution. Run Back
  • 47. Actions after RB: When more than three coal layers are in service, if FSSS received the RB command, the following will be performed:  Fast start the LDO BC oil layer with pair mode.  Override close the return LDO shut off valve.  Remove coal layer F, E and D from top to bottom layer. Coal layer F will be shutdown first. Coal layer E will be shutdown if still more than three coal layers are in service at the moment 2 seconds adjustable after coal layer F shutdown.  The process will continue in that way until coal layer D is shutdown. RB Reset Condition: The following conditions will reset the RB signal (or):  Operate cancels the RB function.  The RB succeeded with the unit load less than the predefined RB target.