2. Which of the following statements is not true about risk identification?
A. The WBS plays an important role in identifying risks.
B. The data about risks is assessed during identifying risks to ensure it is qualified for
further use.
C. The risk breakdown structure is helpful in identifying risks.
D. The project team is involved in identifying risks.
HINT: Remember that performing risk data quality assessment is part of the Perform
Qualitative Risk Analysis process.
QUESTION:
3. The correct answer is B.
The Identify Risks process is where risks that may affect the project are documented along
with their characteristics. Risks are identified by reviewing the work breakdown structure
(WBS), risk breakdown structure, and their components. All project team members should
be involved in this process to incorporate different views about the project risks and to
create the sense of responsibility for addressing project risks. The quality of risk data is
reviewed and assessed during the Perform Qualitative Risk Analysis and Perform
Quantitative Risk Analysis processes.
ANSWER:
4. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.