This study aimed to develop a regression model to predict the final costs of Iraqi public school construction projects based on factors collected before work starts. Records from 65 completed school projects awarded between 2007-2012 were analyzed. Nine key factors thought to influence final cost were identified from expert surveys, including awarded bid price, average bid price, estimated cost, contractor rank, engineer experience, project location, number of bidders, contract year, and duration. A regression model was developed using these factors and was found to accurately predict final costs of school projects with a correlation coefficient of 93%, determination coefficient of 86.5%, and average accuracy of 92.02%.
Risk Contingency Evaluation in International Construction Projects (Real Case...IJLT EMAS
Most construction companies operating in the global construction industry would undertake international projects to maximize their profitability through benefitting from the new attractive markets and reducing the dependence upon local markets. As a result of the nature of construction works the company and project's conditions actually include massive risks and uncertainty. So the risk sensitivity of projects costs should be assessed in a realistic manner. The comprehensive risk assessment method was introduced as a decision making supporting tool to be employed for international constructive projects through applying a risk model that will aid the procedures of evaluating risks and prioritizing such projects and assessing risk contingency value. Both the Analytic Hierarchy Process (AHP), applied for evaluating risk factors weight (likelihood), and FUZZY LOGIC approach, applied for evaluating risk factors influence (Risk consequences) employing software aids such as EXECL and MATLAB software, were used for developing the risk model. The reliability of the developed software has been verified by applications on a real construction projects. The proposed methodology and decision support tool have been proved to be reliable for the estimation of cost overrun resulting from risk on basis of actual final reports of projects. Six actual case studies from different countries were chosen to determine the highest risk factors and to implement the designed models, test their results and evaluate risk cost impact. The proposed models result showed that: the highest and lowest risk contingency percentage of 48 % and 16 % were in Project no (5), (6) respectively in Egypt. On the other hand, the projects no (1, 2, 4,7) in Saudi Arabia, UAE, Libya and Jordan, the risk contingency of 29%, 39%, 20% and 28% respectively. The actual results are close to those of the proposed program.
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
This document summarizes a study on factors affecting the estimation of construction project costs. It identifies 12 key factors that influence cost estimation accuracy based on a survey of experts. These include economic instability, quality of project planning/management, experience of estimators, and availability of management/finance plans. The study develops an artificial neural network model to predict cost variance based on these factors. Testing shows the model can predict cost variance with 80% accuracy. It recommends construction parties consider the 12 identified factors when preparing estimates and assigning qualified project managers, estimators, and planners to reduce cost variance. Further research expanding the model to different project types and using a more structured project database is suggested.
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
1. The document discusses developing a cost prediction model for building projects using multiple regression analysis. It aims to identify factors affecting project cost and analyze their significance.
2. Seven major factors were selected for the cost prediction model: design related factors, time or cost related factors, parties experience related factors, financial issues related factors, bidding situations related factors, project characteristics related factors and estimating process related factors.
3. The cost prediction model will be developed using SPSS software by determining the factors governing project cost through a questionnaire survey that examines these seven factors.
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
This document summarizes a study on factors affecting the estimation of construction project costs. It identifies 12 key factors that influence cost estimation accuracy based on a questionnaire survey of experts. These include economic instability, quality of project planning, experience of the estimating team, and accuracy of bidding documents. The study develops an artificial neural network model to predict cost variance based on these factors. Testing shows the model can predict cost variance with 80% accuracy. It recommends construction parties consider the 12 identified factors when preparing cost estimates and allow for contingency based on economic conditions and project location. Further research expanding the model to different project types and using more structured cost data is suggested.
This thesis proposal examines multi-criteria bid evaluation systems for construction projects in Nepal. It discusses how the Department of Urban Development and Building Construction currently awards contracts primarily to the lowest bidder, which can lead to delays, cost overruns and quality issues. The proposal aims to identify qualification criteria beyond price to evaluate contractors. It will recommend a suitable multi-criteria evaluation model for selecting contractors through a literature review and surveys of engineers, consultants and contractors regarding their perceptions. The findings could influence procurement policies and help improve the success of public construction projects in Nepal.
This document summarizes a research study that uses differential evolution algorithm to solve the multi-objective optimization problem of balancing time, cost, and quality in construction project planning. The study models the time, cost, and quality objectives and formulations. It then applies differential evolution algorithm to analyze two case studies and compare the results to other existing approaches. The study finds that differential evolution algorithm efficiently locates optimal solutions with minimum function evaluations for the time-cost-quality tradeoff problem.
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Studyijceronline
In construction project, cost and time reduction is crucial in today’s competitive market respect. Cost and time along with quality of the project play vital role in construction project’s decision. Reduction in cost and time of projects has increased the demand of construction project in the recent years. Trade-off between different conflicting aspects of projects is one of the challenging problems often faced by construction companies. Time, cost and quality of project delivery are the important aspects of each project which lead researchers in developing time-cost trade-off model. These models are serving as important management tool for overcoming the limitation of critical path methods frequently used by company. The objective of time-cost trade-off analysis is to reduce the original project duration with possible least total cost. In this paper critical path method with a heuristic method is used to find out the crash durations and crash costs. A regression analysis is performed to identify the relationship between the times and costs in order to formulize an optimization problem model. The problem is then solved by Matlab program which yields a least cost of $60937 with duration 129.50 ≈130 days. Applying this approach, the result obtained is satisfactory, which is an indication of usefulness of this approach in construction project problems.
It is realized that Nepalese construction had undertaken a high rise in its image internationally and nationally and has been participating in various organization as an active member. Besides these, there are many rumours and conflicts about the capability of Nepalese contractors about their technical and financial ability for not completing the projects undertaken by them within the given timeframe and of standard quality. Although construction entrepreneur of Class A in Nepal, have the opportunities to withstand in construction industry (as country is still in construction phase of infrastructure development) with full enthusiasm and effort, they seems to be demoralized by the policies, rules, guidance and support from the government and procedure of procurement of donor agencies during bidding in Mega Projects.
The study has covered construction firms registered as class A construction entrepreneur. The numbers of construction firms studied were fifty one (51). Random sampling method was performed to select the respondents. A questionnaire was developed to collect the datas for the study. The close ended question, open ended question, and ranking method of prioritization was adopted to obtain the necessary datas from the respondents.
The purpose of the study was to compare the existing equipment capabilities of Class A construction entrepreneurs with the prescribed requirement as per CBA 2055 & CBR 2056 and also to determine the current capacity of the class A construction entrepreneurs in terms of technical and financial capabilities. The study also has covered the exploration of common problems and difficulties felt in criteria of achieving qualification documents during bidding procedure , receiving payment during payment schedule, , taxation part, hiring qualified human resource in different construction sector and insecure felt during stages of tender purchase, tender drop and construction site execution works by class A construction entrepreneurs.
Percentage, frequency and charts were used to analyze the data. The result has showed that, in owning equipments most of the companies have failed to meet the prescribed standard as per CBA 2055 & CBR 2056. Only few numbers of contractors are extremely satisfied with their business. There are various factors like annual turnover & similar experience part in qualification procedure, escalated amount & running bill payment in payment procedure, insecurity due to hooliganism in construction business during site execution and tender drop, taxation system during refunding of the tax deducted at source amount. The research has also shown the unavailability of human resources in tunnel sector, hydropower sector and bridge sector in construction sector in present context.
Risk Contingency Evaluation in International Construction Projects (Real Case...IJLT EMAS
Most construction companies operating in the global construction industry would undertake international projects to maximize their profitability through benefitting from the new attractive markets and reducing the dependence upon local markets. As a result of the nature of construction works the company and project's conditions actually include massive risks and uncertainty. So the risk sensitivity of projects costs should be assessed in a realistic manner. The comprehensive risk assessment method was introduced as a decision making supporting tool to be employed for international constructive projects through applying a risk model that will aid the procedures of evaluating risks and prioritizing such projects and assessing risk contingency value. Both the Analytic Hierarchy Process (AHP), applied for evaluating risk factors weight (likelihood), and FUZZY LOGIC approach, applied for evaluating risk factors influence (Risk consequences) employing software aids such as EXECL and MATLAB software, were used for developing the risk model. The reliability of the developed software has been verified by applications on a real construction projects. The proposed methodology and decision support tool have been proved to be reliable for the estimation of cost overrun resulting from risk on basis of actual final reports of projects. Six actual case studies from different countries were chosen to determine the highest risk factors and to implement the designed models, test their results and evaluate risk cost impact. The proposed models result showed that: the highest and lowest risk contingency percentage of 48 % and 16 % were in Project no (5), (6) respectively in Egypt. On the other hand, the projects no (1, 2, 4,7) in Saudi Arabia, UAE, Libya and Jordan, the risk contingency of 29%, 39%, 20% and 28% respectively. The actual results are close to those of the proposed program.
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
This document summarizes a study on factors affecting the estimation of construction project costs. It identifies 12 key factors that influence cost estimation accuracy based on a survey of experts. These include economic instability, quality of project planning/management, experience of estimators, and availability of management/finance plans. The study develops an artificial neural network model to predict cost variance based on these factors. Testing shows the model can predict cost variance with 80% accuracy. It recommends construction parties consider the 12 identified factors when preparing estimates and assigning qualified project managers, estimators, and planners to reduce cost variance. Further research expanding the model to different project types and using a more structured project database is suggested.
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
1. The document discusses developing a cost prediction model for building projects using multiple regression analysis. It aims to identify factors affecting project cost and analyze their significance.
2. Seven major factors were selected for the cost prediction model: design related factors, time or cost related factors, parties experience related factors, financial issues related factors, bidding situations related factors, project characteristics related factors and estimating process related factors.
3. The cost prediction model will be developed using SPSS software by determining the factors governing project cost through a questionnaire survey that examines these seven factors.
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
This document summarizes a study on factors affecting the estimation of construction project costs. It identifies 12 key factors that influence cost estimation accuracy based on a questionnaire survey of experts. These include economic instability, quality of project planning, experience of the estimating team, and accuracy of bidding documents. The study develops an artificial neural network model to predict cost variance based on these factors. Testing shows the model can predict cost variance with 80% accuracy. It recommends construction parties consider the 12 identified factors when preparing cost estimates and allow for contingency based on economic conditions and project location. Further research expanding the model to different project types and using more structured cost data is suggested.
This thesis proposal examines multi-criteria bid evaluation systems for construction projects in Nepal. It discusses how the Department of Urban Development and Building Construction currently awards contracts primarily to the lowest bidder, which can lead to delays, cost overruns and quality issues. The proposal aims to identify qualification criteria beyond price to evaluate contractors. It will recommend a suitable multi-criteria evaluation model for selecting contractors through a literature review and surveys of engineers, consultants and contractors regarding their perceptions. The findings could influence procurement policies and help improve the success of public construction projects in Nepal.
This document summarizes a research study that uses differential evolution algorithm to solve the multi-objective optimization problem of balancing time, cost, and quality in construction project planning. The study models the time, cost, and quality objectives and formulations. It then applies differential evolution algorithm to analyze two case studies and compare the results to other existing approaches. The study finds that differential evolution algorithm efficiently locates optimal solutions with minimum function evaluations for the time-cost-quality tradeoff problem.
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Studyijceronline
In construction project, cost and time reduction is crucial in today’s competitive market respect. Cost and time along with quality of the project play vital role in construction project’s decision. Reduction in cost and time of projects has increased the demand of construction project in the recent years. Trade-off between different conflicting aspects of projects is one of the challenging problems often faced by construction companies. Time, cost and quality of project delivery are the important aspects of each project which lead researchers in developing time-cost trade-off model. These models are serving as important management tool for overcoming the limitation of critical path methods frequently used by company. The objective of time-cost trade-off analysis is to reduce the original project duration with possible least total cost. In this paper critical path method with a heuristic method is used to find out the crash durations and crash costs. A regression analysis is performed to identify the relationship between the times and costs in order to formulize an optimization problem model. The problem is then solved by Matlab program which yields a least cost of $60937 with duration 129.50 ≈130 days. Applying this approach, the result obtained is satisfactory, which is an indication of usefulness of this approach in construction project problems.
It is realized that Nepalese construction had undertaken a high rise in its image internationally and nationally and has been participating in various organization as an active member. Besides these, there are many rumours and conflicts about the capability of Nepalese contractors about their technical and financial ability for not completing the projects undertaken by them within the given timeframe and of standard quality. Although construction entrepreneur of Class A in Nepal, have the opportunities to withstand in construction industry (as country is still in construction phase of infrastructure development) with full enthusiasm and effort, they seems to be demoralized by the policies, rules, guidance and support from the government and procedure of procurement of donor agencies during bidding in Mega Projects.
The study has covered construction firms registered as class A construction entrepreneur. The numbers of construction firms studied were fifty one (51). Random sampling method was performed to select the respondents. A questionnaire was developed to collect the datas for the study. The close ended question, open ended question, and ranking method of prioritization was adopted to obtain the necessary datas from the respondents.
The purpose of the study was to compare the existing equipment capabilities of Class A construction entrepreneurs with the prescribed requirement as per CBA 2055 & CBR 2056 and also to determine the current capacity of the class A construction entrepreneurs in terms of technical and financial capabilities. The study also has covered the exploration of common problems and difficulties felt in criteria of achieving qualification documents during bidding procedure , receiving payment during payment schedule, , taxation part, hiring qualified human resource in different construction sector and insecure felt during stages of tender purchase, tender drop and construction site execution works by class A construction entrepreneurs.
Percentage, frequency and charts were used to analyze the data. The result has showed that, in owning equipments most of the companies have failed to meet the prescribed standard as per CBA 2055 & CBR 2056. Only few numbers of contractors are extremely satisfied with their business. There are various factors like annual turnover & similar experience part in qualification procedure, escalated amount & running bill payment in payment procedure, insecurity due to hooliganism in construction business during site execution and tender drop, taxation system during refunding of the tax deducted at source amount. The research has also shown the unavailability of human resources in tunnel sector, hydropower sector and bridge sector in construction sector in present context.
Factor Affecting Construction Cost and Time in road projectIRJET Journal
This document discusses factors that affect construction cost and time overruns in road projects. It analyzes data collected from literature reviews and questionnaires distributed to experts on 22 construction sites. 50 factors were identified and grouped into 7 categories: consultant, material, labor, client, equipment, contractor, and external. The factors were ranked using a fuzzy methodology based on expert opinions. The top 3 factor groups that affect cost and time were equipment, labor, and client-related. Within these, the individual top 5 factors were late equipment delivery, weather effects, high labor costs, labor shortages, and high machinery costs. Analyzing these critical factors can help minimize time and cost overruns in road construction projects.
The final cost of public school building projects, like other construction projects, is unknown
to the owner till the account closure. Artificial Neural Networks (ANN) is used in an attempt to
predict the final cost of two story (12 classes) school projects under lowest bid system of award
before work starts. A database of (65) school projects records completed in (2007-2012) are used to
develop and verify the ANN model. Based on expert opinions, nine out of eleven parameters are
considered to have the most significant impact on the magnitude of final cost. Hence they are used as
model inputs while the output of the model is going to be the final cost (FC). These parameters are;
accepted bid price, average bid price, estimated cost, contractor rank, supervising engineer
experience, project location, number of bidders, year of contracting, and contractual duration. It was
found that ANN has the ability to predict the final cost for school projects with very good degree of
accuracy having a coefficient of correlation (R) of (91%), and an average accuracy percentage of
(99.98%).
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSFredy Kurniawan
The evaluation of the financial viability for seaport projects is a critical activity for bidders and governments under traditional procurement or through private finance initiative (PFI). The aim of this research is to assist government agencies in
evaluating bids and making decision efficiently for seaport development projects through the use of an integrated project evaluation tool. The proposed tool is expected to integrate the results of the financial model and the risk sharing strategy. The
integrated project evaluation tool can be mutually used by the government agency and the sponsor(s). This paper discusses the proposed tool to be tested in future study. The research strategy uses literature review, questionnaire surveys, interviews, and document analyses in order to develop the proposed tool. The tool will be tested through case studies and experts’ opinion to validate its applicability and effectiveness. The main conclusion of this paper is that the knowledge gap between the sponsor(s) and the government agency can be improved if the government agency is provided with efficient tools that consider both the financial and the risk factors
affecting a new project.
This literature review examines risk factors that impact construction projects in Sri Lanka. It summarizes several studies on risk identification and evaluation in the construction industry in countries like Singapore, Ghana, Nigeria, the UK, and Kuwait. Key risks identified include construction methods, inflation, weather, ground conditions, poor communication, delays in approvals, scope changes, and financing problems. The review indicates that proper risk management is important for construction projects, but that adoption of risk analysis techniques is still limited, especially among small-to-medium firms. Identifying country-specific risks and improving management skills could help minimize delays and cost overruns on projects in Sri Lanka.
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
Real estate sector in present scenario is going through a lean patch, many organisations are either running in loss or with a marginal profits. As in state government and central government departments contractors are facing huge problems that are in turn tending to decrease in contractor profits. The present study focuses on study of various factors that affect contractor’s performance who have been awarded projects on the basis of lowest bid awards. The study analyses various factors and their impacts on the basis of responses collected form a survey. On the basis of overall index and relative importance index factor causing a major impact on contractor’s efficiency have been identified.
Application Of Analytic Hierarchy Process And Artificial Neural Network In Bi...IJARIDEA Journal
Abstract— An appropriate decision to bid initiates all bid preparation steps. Selective bidding will reduce the number of proposals to be submitted by the contractor and saves tender preparation time which can be utilized for refining the estimated cost. Usually in industrial engineering applications final decision will be based on the evaluation of many alternatives. This will be a very difficult problem when the criteria are expressed in different units or the pertinent data are not easily quantifiable. This paper emphasizes on the use of Analytic Hierarchy Process(AHP) for analyzing the risk degree of each factor, so that decision the can be taken accordingly in deciding an appropriate bid.AHP helps to decide the best solution from various selection criteria.The study also focuses on suggesting a much broader applicability of AHP and ANN techniques on decisions of bidding.
Keywords— Analytic Hierarchy Process(AHP), Artificial Neural Network(ANN), Consistency Index(CI),
Consistency Ratio(CR), Random Index(RI), Risk degree.
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementIJERA Editor
Although significant research work has been conducted on cash flow forecast, planning, and management, the objective is constantly the maximization of profit/final cash balance, or minimization of total project cost. This paper presents a multi-objective fuzzy linear programming model (FLP) for resolving the optimization problem of three conflicting objectives: final cash balance, cost of money, and initial cash balance. The proposed model depends on Jiang et al. (2011) Model. In the new formulation, both the advanced payment and delay of owner's progress payment one period were considered. Literature concerned with cash flow studies and models for construction projects was reviewed. Fuzzy linear programming applications in literature was presented and it's concept was then described. Jiang et al. (2011) Model is presented. The proposed model development was then presented. The proposed model was validated using an example project. An optimization of each individual objective was performed with a linear programming (LP) software (Lindo) that gave the upper and lower bounds for the multi-objective analysis. Fuzzy linear programming was then applied to optimize the solution. Four cases are considered: considering advanced payment and delay of owner's progress payment one period simultaneously, then separately, and neglecting advanced payment and delay of owner's progress payment. Penalty of delayed payment have been also considered. Analysis of the results revealed that the model is an effective decision making tool to be used by industry practitioners with reasonable accuracy.
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
This document provides a critical review of the causes of cost overruns in construction projects in developing countries. It begins with an abstract that outlines that cost overruns are a major issue for construction industries in developing nations, with few projects being completed within original estimated costs.
The document then reviews literature identifying common causes of cost overruns. It finds that factors leading to overruns include poor management, inaccurate estimates of materials and costs, and financial issues for contractors. However, it notes that not all factors are identical for every project or country.
The review examines causes of overruns for construction industries specifically in India, Nigeria, and Indonesia. Common causes identified across these developing nations include issues like rising materials prices, inaccurate designs,
This document discusses a fuzzy AHP model for risk ranking in construction projects. It begins by introducing construction projects and risk management. It then reviews literature on identifying and assessing risks in construction projects. The document discusses the analytic hierarchy process (AHP) technique and different fuzzy AHP methods. The goal is to develop a fuzzy AHP model to measure significant risks in construction projects based on project objectives.
Risk Severity Framework for a BOT Highway ProjectIOSRJMCE
Adequate attention needs to be given to project risk management for reaping the benefits by way of meeting the objectives of an organisation. Organisations which implement good risk management practices derive maximum advantage by way of fewer risks which are quite manageable in general and more so in infrastructure sector which is subjected to plethora of risks. The role of infrastructure in the overall development of a nation cannot be underscored. Considering this, a study has been carried out for an ongoing highway project being executed in the state of Telangana (India) under NHAI. The study was carried out by administering the questionnaire to 250 experts associated with highway sector and the response received was 110. The respondents were asked to identify the risks in four phases of a project namely Feasibility phase, Development Phase, Execution Phase and Operation phase and also the likelihood and impact of each of the identified risks. The severity of risk was determined based on the likelihood and impact of risks and was categorized accordingly. The severity of risk indicates the extent to which the project is exposed to that particular risk and the mitigation measures need to be taken accordingly to minimise the effect of risk
ER Publication,
IJETR, IJMCTR,
Journals,
International Journals,
High Impact Journals,
Monthly Journal,
Good quality Journals,
Research,
Research Papers,
Research Article,
Free Journals, Open access Journals,
erpublication.org,
Engineering Journal,
Science Journals,
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
This document discusses risk analysis and strategic evaluation of procurement processes in construction projects. It aims to identify appropriate methods for analyzing risks in procurement.
The document first provides background on procurement processes and the importance of risk management. It then reviews past literature on causes of delays in construction projects.
The research methodology section outlines the data collection process, which involved identifying risk factors through literature review and expert surveys. Two methods for analysis are described: Relative Importance Index (RII) and Importance Performance Index (IMPI).
The results section compares the output of these two methods when applied to various identified risk factors. The RII method ranks technical capability of the contractor as the top risk factor, while IMPI ranks it
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
Abstract
Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM gives an early indication that either project is delayed or not and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work. This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the Primavera P6 software is used to deals with the
project monitoring process of a seven-storey (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.
Keywords: construction cost management, construction planning, earned value management (EVM), Primavera p6, project management, project scheduling.
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...ijtsrd
In Yangon City, Myanmar, most of the building construction projects fail to meet their cost and time constraints, which will lead to low return on investment. The purpose of this paper is to understand risk management of building construction and the study area is Yangon. This study illustrates that how to manage risks in building construction to become a successful project with best possible outcome by reducing risks that delay the project. The study was conducted through a questionnaire survey administered to 39 construction projects and 148 professionals in Yangon for finding risk rating and prioritization of risk. Risk prioritization was done by Technique for Order of Preference by Similarity to Ideal Solution TOPSIS . Khin Su Yi | Kyaw Kyaw "The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Constructions Projects in Yangon" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-4 | Issue-4 , June 2020, URL: https://www.ijtsrd.com/papers/ijtsrd31557.pdf Paper Url :https://www.ijtsrd.com/management/risk-management/31557/the-rank-of-risk-factors-affecting-time-delay-and-cost-overrun-of-building-constructions-projects-in-yangon/khin-su-yi
The infrastructure construction sectors are usually complex. Zero risk construction projects are only an
assumption. The objective of this paper is to identify the risks factor associated with the urban infrastructure
construction projects causing delay. The research found that those risks are directly associated to clients,
contractors, sub-contractors that would cause delay in the construction work. Other factors are also
identified such as project, financial, political, technical, market risk, managerial, resource risk, and force
majeure. All risk factors affect the time, cost and quality performance of the construction project. From risk
management perspective, it is the process on which identifies the risks and analyzed with qualitatively and
quantitatively. All associated risks can treat by various mitigation processes and then mitigating method are
monitored to control the risks. Risk management distinguishes between success and failure of a project.
So, Nepal could use it effectively to meet its growing need of infrastructure and job opportunity
This document reviews applications of evolutionary multiobjective optimization (EMO) techniques in production research. It summarizes EMO applications in several areas of production research, including scheduling, production planning and control, cellular manufacturing, flexible manufacturing systems, and assembly-line optimization. The review finds that EMO techniques have been successfully applied to optimization problems in these areas and provide a number of non-dominated solutions. However, future research opportunities remain, such as improved integration of EMO with other metaheuristics and consideration of additional objectives.
An application of genetic algorithms to time cost-quality trade-off in constr...Alexander Decker
This document summarizes a research paper that develops an optimization model using genetic algorithms to solve the time-cost-quality trade-off problem in construction projects. The model aims to find the minimum cost for a construction project to meet certain quality levels within a given time limit. It does this by considering different activity execution modes and using genetic algorithms to efficiently explore the large solution space. The document provides background on optimization problems and techniques, an overview of the time-cost-quality trade-off problem and prior related research, and describes the objectives and approach of the developed genetic algorithms model.
by Kevin Li, Dean of Instruction at City Colleges of Chicago's Wilbur Wright College
This modularized, accelerated developmental mathematics program was awarded funding from Next Generation Learning Challenges (NGLC) to scale the program.
From Afton Partners, April 2013. An overview of NGLC financial and operational expectations, spending trends from 12/2011 – 09/2012 for 8 K-12 Breakthrough Models in their first year vs. national benchmarks, and software usage. This analysis was meant to provide information to
applicants for NGLC's "Wave IV: Breakthrough School Models" grant opportunity, as they finalized their financial and operating plans.
Open from the start - Business e Open Source con Ubuntu - Smau Milano 2010Flavia Weisghizzi
In un mondo in costante fluida modificazione è necessario saper riconoscere nuove strade. L'open source da anni si è affrancato da una dimensione di puro volontariato per diventare strumento di lavoro affidabile e fortemente personalizzabile. L'open source offre un modello alternativo di sviluppo, potente e flessibile, e inoltre un terreno che ha grandi spazi di espansione. Ubuntu, grazie alla sua semplicità, affidabilità e customizzabilità, è porta di accesso privilegiata a questa frontiera, riuscendo a conciliare lo spirito libero dell'open source e lo sguardo rivolto al mondo del business. Dal desktop all'enterprise, dell'ufficio agli applicativi mission critical, dalla ricerca al multimedia, Ubuntu permette di ritagliare su misura soluzioni umane e innovazioni tecnologiche Target: Il talk si rivolge a un pubblico che non ha esperienza nel mondo dell'open source ma è interessato a conoscerne le potenzialità
Factor Affecting Construction Cost and Time in road projectIRJET Journal
This document discusses factors that affect construction cost and time overruns in road projects. It analyzes data collected from literature reviews and questionnaires distributed to experts on 22 construction sites. 50 factors were identified and grouped into 7 categories: consultant, material, labor, client, equipment, contractor, and external. The factors were ranked using a fuzzy methodology based on expert opinions. The top 3 factor groups that affect cost and time were equipment, labor, and client-related. Within these, the individual top 5 factors were late equipment delivery, weather effects, high labor costs, labor shortages, and high machinery costs. Analyzing these critical factors can help minimize time and cost overruns in road construction projects.
The final cost of public school building projects, like other construction projects, is unknown
to the owner till the account closure. Artificial Neural Networks (ANN) is used in an attempt to
predict the final cost of two story (12 classes) school projects under lowest bid system of award
before work starts. A database of (65) school projects records completed in (2007-2012) are used to
develop and verify the ANN model. Based on expert opinions, nine out of eleven parameters are
considered to have the most significant impact on the magnitude of final cost. Hence they are used as
model inputs while the output of the model is going to be the final cost (FC). These parameters are;
accepted bid price, average bid price, estimated cost, contractor rank, supervising engineer
experience, project location, number of bidders, year of contracting, and contractual duration. It was
found that ANN has the ability to predict the final cost for school projects with very good degree of
accuracy having a coefficient of correlation (R) of (91%), and an average accuracy percentage of
(99.98%).
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSFredy Kurniawan
The evaluation of the financial viability for seaport projects is a critical activity for bidders and governments under traditional procurement or through private finance initiative (PFI). The aim of this research is to assist government agencies in
evaluating bids and making decision efficiently for seaport development projects through the use of an integrated project evaluation tool. The proposed tool is expected to integrate the results of the financial model and the risk sharing strategy. The
integrated project evaluation tool can be mutually used by the government agency and the sponsor(s). This paper discusses the proposed tool to be tested in future study. The research strategy uses literature review, questionnaire surveys, interviews, and document analyses in order to develop the proposed tool. The tool will be tested through case studies and experts’ opinion to validate its applicability and effectiveness. The main conclusion of this paper is that the knowledge gap between the sponsor(s) and the government agency can be improved if the government agency is provided with efficient tools that consider both the financial and the risk factors
affecting a new project.
This literature review examines risk factors that impact construction projects in Sri Lanka. It summarizes several studies on risk identification and evaluation in the construction industry in countries like Singapore, Ghana, Nigeria, the UK, and Kuwait. Key risks identified include construction methods, inflation, weather, ground conditions, poor communication, delays in approvals, scope changes, and financing problems. The review indicates that proper risk management is important for construction projects, but that adoption of risk analysis techniques is still limited, especially among small-to-medium firms. Identifying country-specific risks and improving management skills could help minimize delays and cost overruns on projects in Sri Lanka.
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
Real estate sector in present scenario is going through a lean patch, many organisations are either running in loss or with a marginal profits. As in state government and central government departments contractors are facing huge problems that are in turn tending to decrease in contractor profits. The present study focuses on study of various factors that affect contractor’s performance who have been awarded projects on the basis of lowest bid awards. The study analyses various factors and their impacts on the basis of responses collected form a survey. On the basis of overall index and relative importance index factor causing a major impact on contractor’s efficiency have been identified.
Application Of Analytic Hierarchy Process And Artificial Neural Network In Bi...IJARIDEA Journal
Abstract— An appropriate decision to bid initiates all bid preparation steps. Selective bidding will reduce the number of proposals to be submitted by the contractor and saves tender preparation time which can be utilized for refining the estimated cost. Usually in industrial engineering applications final decision will be based on the evaluation of many alternatives. This will be a very difficult problem when the criteria are expressed in different units or the pertinent data are not easily quantifiable. This paper emphasizes on the use of Analytic Hierarchy Process(AHP) for analyzing the risk degree of each factor, so that decision the can be taken accordingly in deciding an appropriate bid.AHP helps to decide the best solution from various selection criteria.The study also focuses on suggesting a much broader applicability of AHP and ANN techniques on decisions of bidding.
Keywords— Analytic Hierarchy Process(AHP), Artificial Neural Network(ANN), Consistency Index(CI),
Consistency Ratio(CR), Random Index(RI), Risk degree.
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementIJERA Editor
Although significant research work has been conducted on cash flow forecast, planning, and management, the objective is constantly the maximization of profit/final cash balance, or minimization of total project cost. This paper presents a multi-objective fuzzy linear programming model (FLP) for resolving the optimization problem of three conflicting objectives: final cash balance, cost of money, and initial cash balance. The proposed model depends on Jiang et al. (2011) Model. In the new formulation, both the advanced payment and delay of owner's progress payment one period were considered. Literature concerned with cash flow studies and models for construction projects was reviewed. Fuzzy linear programming applications in literature was presented and it's concept was then described. Jiang et al. (2011) Model is presented. The proposed model development was then presented. The proposed model was validated using an example project. An optimization of each individual objective was performed with a linear programming (LP) software (Lindo) that gave the upper and lower bounds for the multi-objective analysis. Fuzzy linear programming was then applied to optimize the solution. Four cases are considered: considering advanced payment and delay of owner's progress payment one period simultaneously, then separately, and neglecting advanced payment and delay of owner's progress payment. Penalty of delayed payment have been also considered. Analysis of the results revealed that the model is an effective decision making tool to be used by industry practitioners with reasonable accuracy.
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
This document provides a critical review of the causes of cost overruns in construction projects in developing countries. It begins with an abstract that outlines that cost overruns are a major issue for construction industries in developing nations, with few projects being completed within original estimated costs.
The document then reviews literature identifying common causes of cost overruns. It finds that factors leading to overruns include poor management, inaccurate estimates of materials and costs, and financial issues for contractors. However, it notes that not all factors are identical for every project or country.
The review examines causes of overruns for construction industries specifically in India, Nigeria, and Indonesia. Common causes identified across these developing nations include issues like rising materials prices, inaccurate designs,
This document discusses a fuzzy AHP model for risk ranking in construction projects. It begins by introducing construction projects and risk management. It then reviews literature on identifying and assessing risks in construction projects. The document discusses the analytic hierarchy process (AHP) technique and different fuzzy AHP methods. The goal is to develop a fuzzy AHP model to measure significant risks in construction projects based on project objectives.
Risk Severity Framework for a BOT Highway ProjectIOSRJMCE
Adequate attention needs to be given to project risk management for reaping the benefits by way of meeting the objectives of an organisation. Organisations which implement good risk management practices derive maximum advantage by way of fewer risks which are quite manageable in general and more so in infrastructure sector which is subjected to plethora of risks. The role of infrastructure in the overall development of a nation cannot be underscored. Considering this, a study has been carried out for an ongoing highway project being executed in the state of Telangana (India) under NHAI. The study was carried out by administering the questionnaire to 250 experts associated with highway sector and the response received was 110. The respondents were asked to identify the risks in four phases of a project namely Feasibility phase, Development Phase, Execution Phase and Operation phase and also the likelihood and impact of each of the identified risks. The severity of risk was determined based on the likelihood and impact of risks and was categorized accordingly. The severity of risk indicates the extent to which the project is exposed to that particular risk and the mitigation measures need to be taken accordingly to minimise the effect of risk
ER Publication,
IJETR, IJMCTR,
Journals,
International Journals,
High Impact Journals,
Monthly Journal,
Good quality Journals,
Research,
Research Papers,
Research Article,
Free Journals, Open access Journals,
erpublication.org,
Engineering Journal,
Science Journals,
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
This document discusses risk analysis and strategic evaluation of procurement processes in construction projects. It aims to identify appropriate methods for analyzing risks in procurement.
The document first provides background on procurement processes and the importance of risk management. It then reviews past literature on causes of delays in construction projects.
The research methodology section outlines the data collection process, which involved identifying risk factors through literature review and expert surveys. Two methods for analysis are described: Relative Importance Index (RII) and Importance Performance Index (IMPI).
The results section compares the output of these two methods when applied to various identified risk factors. The RII method ranks technical capability of the contractor as the top risk factor, while IMPI ranks it
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
Abstract
Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM gives an early indication that either project is delayed or not and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work. This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the Primavera P6 software is used to deals with the
project monitoring process of a seven-storey (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.
Keywords: construction cost management, construction planning, earned value management (EVM), Primavera p6, project management, project scheduling.
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...ijtsrd
In Yangon City, Myanmar, most of the building construction projects fail to meet their cost and time constraints, which will lead to low return on investment. The purpose of this paper is to understand risk management of building construction and the study area is Yangon. This study illustrates that how to manage risks in building construction to become a successful project with best possible outcome by reducing risks that delay the project. The study was conducted through a questionnaire survey administered to 39 construction projects and 148 professionals in Yangon for finding risk rating and prioritization of risk. Risk prioritization was done by Technique for Order of Preference by Similarity to Ideal Solution TOPSIS . Khin Su Yi | Kyaw Kyaw "The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Constructions Projects in Yangon" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-4 | Issue-4 , June 2020, URL: https://www.ijtsrd.com/papers/ijtsrd31557.pdf Paper Url :https://www.ijtsrd.com/management/risk-management/31557/the-rank-of-risk-factors-affecting-time-delay-and-cost-overrun-of-building-constructions-projects-in-yangon/khin-su-yi
The infrastructure construction sectors are usually complex. Zero risk construction projects are only an
assumption. The objective of this paper is to identify the risks factor associated with the urban infrastructure
construction projects causing delay. The research found that those risks are directly associated to clients,
contractors, sub-contractors that would cause delay in the construction work. Other factors are also
identified such as project, financial, political, technical, market risk, managerial, resource risk, and force
majeure. All risk factors affect the time, cost and quality performance of the construction project. From risk
management perspective, it is the process on which identifies the risks and analyzed with qualitatively and
quantitatively. All associated risks can treat by various mitigation processes and then mitigating method are
monitored to control the risks. Risk management distinguishes between success and failure of a project.
So, Nepal could use it effectively to meet its growing need of infrastructure and job opportunity
This document reviews applications of evolutionary multiobjective optimization (EMO) techniques in production research. It summarizes EMO applications in several areas of production research, including scheduling, production planning and control, cellular manufacturing, flexible manufacturing systems, and assembly-line optimization. The review finds that EMO techniques have been successfully applied to optimization problems in these areas and provide a number of non-dominated solutions. However, future research opportunities remain, such as improved integration of EMO with other metaheuristics and consideration of additional objectives.
An application of genetic algorithms to time cost-quality trade-off in constr...Alexander Decker
This document summarizes a research paper that develops an optimization model using genetic algorithms to solve the time-cost-quality trade-off problem in construction projects. The model aims to find the minimum cost for a construction project to meet certain quality levels within a given time limit. It does this by considering different activity execution modes and using genetic algorithms to efficiently explore the large solution space. The document provides background on optimization problems and techniques, an overview of the time-cost-quality trade-off problem and prior related research, and describes the objectives and approach of the developed genetic algorithms model.
by Kevin Li, Dean of Instruction at City Colleges of Chicago's Wilbur Wright College
This modularized, accelerated developmental mathematics program was awarded funding from Next Generation Learning Challenges (NGLC) to scale the program.
From Afton Partners, April 2013. An overview of NGLC financial and operational expectations, spending trends from 12/2011 – 09/2012 for 8 K-12 Breakthrough Models in their first year vs. national benchmarks, and software usage. This analysis was meant to provide information to
applicants for NGLC's "Wave IV: Breakthrough School Models" grant opportunity, as they finalized their financial and operating plans.
Open from the start - Business e Open Source con Ubuntu - Smau Milano 2010Flavia Weisghizzi
In un mondo in costante fluida modificazione è necessario saper riconoscere nuove strade. L'open source da anni si è affrancato da una dimensione di puro volontariato per diventare strumento di lavoro affidabile e fortemente personalizzabile. L'open source offre un modello alternativo di sviluppo, potente e flessibile, e inoltre un terreno che ha grandi spazi di espansione. Ubuntu, grazie alla sua semplicità, affidabilità e customizzabilità, è porta di accesso privilegiata a questa frontiera, riuscendo a conciliare lo spirito libero dell'open source e lo sguardo rivolto al mondo del business. Dal desktop all'enterprise, dell'ufficio agli applicativi mission critical, dalla ricerca al multimedia, Ubuntu permette di ritagliare su misura soluzioni umane e innovazioni tecnologiche Target: Il talk si rivolge a un pubblico che non ha esperienza nel mondo dell'open source ma è interessato a conoscerne le potenzialità
Diversity has been a key topic of first CLSxItaly, hold in Milan, on February 26th. Numbers of female participation in FLOSS and tips and ideas to growth female involvement coming from international FLOSS communities.
Modeling final costs of iraqi public school projectsGafel Kareem
The document describes a study that uses artificial neural networks to model and predict the final costs of Iraqi public school construction projects. Researchers collected data from 65 completed school projects and identified 9 influential parameters to use as inputs for the neural network model, including accepted bid price, estimated cost, contractor rank, and number of bidders. The model was able to predict final costs with a correlation of 91% and accuracy of 99.98% when validated on data not used in training. The study aims to improve early cost estimation for school projects and reduce cost overruns.
This document appears to be a collection of various pieces of text and images with no clear overall theme or narrative. It includes snippets about adventures, productions, interviews, places visited, personal details, and love with various dates and numbers. The document jumps between unrelated topics and lacks coherent connections between the different sections.
Women currently make up only 5% of contributors to Ubuntu, 2% of Debian, and 1.5% of other FLOSS projects. The document calls for higher participation of women in FLOSS, noting that diversity and multiple perspectives are valuable resources. It discusses reducing prejudices as a reason for low participation, and provides information on initiatives like ubuntu-women.com to involve more women in Ubuntu and other open source projects in Italy through collaboration.
As former intern of OPW program, I’d like to share my work about FOSS community outreaches, focusing my talk on problems volunteers could encounter in approaching FOSS communities and how to support their outreaches at best, with particular attention on GNOME.
This work was presented at GUADEC 2013 conference, whitin the community outreach tracks.
Award Winning Exhibit Company. Exhibitors, join us in making your next exhibit design project a major success. Browse our impressive exhibit design portfolio and trade show booths.For More Information, Visit: http://www.catalystexhibit.com/
All About Dev Community - Tips & Tricks for wannabe startupsFlavia Weisghizzi
Are you a startup? Are you looking for a top-notch developer able to code your ideas? Don’t miss our next “Startup Europe & TWIST” webinar! Flavia Weisghizzi, Communication Manager at Codemotion, will introduce you to all the tips and tricks to interact with developers and engage them to work with you to develop your startup!
Welcome CoC - 10 verità e bugie sul Codice di Condotta - Flavia Weisghizzi - ...Flavia Weisghizzi
Il codice di condotta è il cuore del "contratto" di rispetto reciproco necessario in una community, un'azienda o una conferenza. Eppure ancora oggi fa discutere, pochi lo conoscono e ancor meno realtà ne hanno uno. Ne parliamo al Community Leader Summit a Roma.
O documento resume os principais pontos da Aula 2 sobre legislação trabalhista e previdenciária ministrada pelo professor Rogério Duarte. Ele aborda as espécies de empregados como aprendiz, menor, mulher, doméstico, rural e público, bem como as espécies de trabalhadores como temporário, autônomo, eventual, avulso e estagiário.
4. Fixed and Variable Costs in Distance EducationAlaa Sadik
The document summarizes the costs associated with developing and delivering an online wired class. It breaks costs down into capital costs, development costs, tuition/maintenance costs, and server costs. Fixed costs make up 48% of total costs and variable costs 52%. While initial per-course costs are high, the unit cost per course decreases as more courses are added due to sharing of fixed infrastructure costs.
This document discusses using an artificial neural network (ANN) to model and predict the final costs of Iraqi public school construction projects. It begins by outlining the research objectives, justification, and hypotheses. The research methodology included collecting data from 65 completed school projects, developing an ANN model using Neuframe software, and evaluating the model. Experts identified 9 important parameters to use as inputs to the ANN model, including accepted bid price, estimated cost, contractor rank, and project location. The ANN model was able to accurately predict final costs for new projects, with a correlation of 91% between predicted and actual costs. This shows promise for using ANN to improve cost estimating efficiency for public school projects in Iraq.
Analysis and prediction of cost and time overrun ofAlexander Decker
The document analyzes cost and time overruns of 25 Millennium Development Goals (MDGs) construction projects in Nigeria from 2006-2009. It finds that all projects experienced cost and time overruns, with maximum overruns of 58.33% for time and 48.89% for cost. Statistical analysis finds a significant difference between estimated and actual project duration and cost. Models are developed to predict cost and time overruns on future MDGs projects based on initial estimates and historical data. The study aims to help the government improve strategic planning and management of construction projects to better achieve MDGs targets.
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET Journal
This document discusses factors that affect the accuracy of construction project cost estimation. It begins by outlining the importance of accurate cost estimation for construction projects. It then reviews previous literature that has identified various factors such as ineffective planning, design changes, weather, and material cost fluctuations.
The document describes the objectives of the study, which are to explore common cost estimation practices and identify significant cost estimation factors. It then provides more detail on the literature review, outlining several previous studies that examined factors like demand, time effects, use of rough set theory and neural networks in cost models, and factors relevant at different project stages.
The literature review discusses previous research identifying factors such as experience, project complexity, scope definition, cost data
Review Application of value engineering in construction project.IRJET Journal
This document reviews the application of value engineering in construction projects. It discusses how value engineering aims to improve value by focusing on functions rather than minimizing costs alone. The value engineering process involves information collection, alternative generation, evaluation, and presentation of alternatives. Previous research studies how value engineering can help reduce construction time and costs through techniques like Mivan technology and CLC bricks. Value engineering analysis is estimated to reduce total project costs by 5-10% by identifying unnecessary expenditures. The literature review concludes that value engineering is an effective management method that can increase value and reduce costs in the construction sector.
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...IJERA Editor
It is well known that decisions at early stages of a construction project have great impact on subsequent project performance. Conceptual cost estimate is a challenging task that is done with limited information at the early stages of a project life where many factors affecting the project costs are still unknown. The objective of this paper is to support decision makers in predicting the conceptual cost of highway construction projects in Libya. Initially, the factors that significantly influence highway construction are identified. Then, an artificial neural network model is developed for predicting the cost. The network is trained and tested with a total of 67 projects historical data. Training of the model is administered via back-propagation algorithm. The model is coded ad implemented using MATLAB® to facilitate its use. An optimization module is also added to the Neural Network model with the objective of minimizing the error of the predicted cost. The model is then validated and the results show better predictions of conceptual cost of highway projects in Libya.
Application of value engineering in constructionDr Ezzat Mansour
The document discusses the application of value engineering (VE) in construction projects. It provides an overview of VE, including its definition, methodology, and when it should be applied. The document then discusses how VE was used in the Bregana-Zagreb-Dubrovnik Motorway project in Croatia. VE studies identified opportunities to reduce costs and accelerate the project schedule. Specific changes included increasing the length of climbing forms for viaducts from 4m to 5m, which reduced formwork costs. Overall, approximately $43 million and 12 months were saved through VE applications on the project.
- The document is a fourth-year project report submitted to Kyambogo University investigating the impact of construction-related rework on cost and schedule.
- It identifies rework as a major issue causing cost and schedule overruns in the Ugandan construction industry. However, little is known about the causes and effects of rework.
- The study aims to identify the critical factors causing rework and evaluate their impact on construction cost and schedule based on a case study of the KIIDP2 project in Kampala.
Attributes affecting success of the residential projects – a reviewA Makwana
Construction industry is complex in nature and construction projects in India face many challenges and complex issues, such as time, cost, safety, quality and stakeholder satisfaction. According to Construction scenario there are various factors that affecting the residential project. These review paper shows the selection of criteria based on by giving the importance to other researcher’s research. The criteria were curtailed down according to literature review studied in this paper, interaction with stakeholder which are Engineers, Project managers, Architects, Consultants, Developers and educational experts, of Surat and Vadodara city in Gujarat.
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
This document reviews literature on developing a model for effective risk allocation and handling in construction projects. It identifies several key risks studied in previous research, including insufficient planning, currency price changes, and worker strikes. The literature review found that optimal risk allocation where the best positioned party manages risk can reduce overall project costs. However, previous studies did not assess the effectiveness of risk allocation methods. This paper aims to develop a model to allocate risks to stakeholders and propose mitigation strategies. A mixed methodology is used, including interviews, questionnaires, and qualitative data analysis. The model will help construction parties better allocate responsibilities to manage risks and control impacts on time and cost objectives.
The document discusses risk factors that influence construction procurement performance in Nigeria. It identifies 20 risk factors through a literature review. A questionnaire was distributed to construction professionals to evaluate the significance of these factors. Corruption, conflict of interest, ineffective project feasibility studies, and lack of transparency were found to be the most significant factors limiting procurement performance. Communication barriers and unconfidential tender evaluations were considered less important. The findings can help improve risk management and procurement systems in Nigeria to enhance overall project performance.
This document discusses a study on risk management practices in construction projects in Pakistan. The study aims to investigate current risk management practices, identify and prioritize key risks and success factors, and examine the relationship between effective risk management and project success. Data was collected through surveys of 22 contractor firms working on 100 diverse projects. The analysis found that risk management has been implemented at a low level locally. It also revealed a strong correlation between effective risk management and project success, highlighting the importance of risk management techniques and their impact on construction project outcomes from the contractor's perspective.
Cost Effective Methods in Construction Engineeringcivejjour
The economic impact of construction cost overrun is a possible loss of the economic justification for the
project. The financial impact of a cost overrun results in demand for construction investment credits.
Therefore reliable estimates of construction cost are an important aspect to the contemporary construction
companies especially during the conceptual phase of lifecycle management. In this paper a cost-effective
analysis is done using one of the cost effective construction technique called Rat Trap Bond versus Flemish
bond and when estimated with CPWD 2012 schedule of rates it is proved that Low cost techniques such as
rat trap bond provides better cost effectiveness as compared to conventional Flemish bond construction
method.
Cost Effective Methods in Construction Engineeringcivejjour
The economic impact of construction cost overrun is a possible loss of the economic justification for the project. The financial impact of a cost overrun results in demand for construction investment credits. Therefore reliable estimates of construction cost are an important aspect to the contemporary construction companies especially during the conceptual phase of lifecycle management. In this paper a cost-effective analysis is done using one of the cost effective construction technique called Rat Trap Bond versus Flemish bond and when estimated with CPWD 2012 schedule of rates it is proved that Low cost techniques such as rat trap bond provides better cost effectiveness as compared to conventional Flemish bond construction method.
An Integrated Project Evaluation Tool for PFI Seaport ProjectFredy Kurniawan
The evaluation of the financial viability for seaport projects is a critical activity for bidders and governments under traditional procurement or through private finance initiative (PFI). The aim of this research is to assist government agencies in
evaluating bids and making decision efficiently for seaport development projects through the use of an integrated project evaluation tool. The proposed tool is expected to integrate the results of the financial model and the risk sharing strategy. The integrated project evaluation tool can be mutually used by the government agency and
the sponsor(s). This paper discusses the proposed tool to be tested in future study. The research strategy uses literature review, questionnaire surveys, interviews, and document analyses in order to develop the proposed tool. The tool will be tested
through case studies and experts’ opinion to validate its applicability and
effectiveness. The main conclusion of this paper is that the knowledge gap between
the sponsor(s) and the government agency can be improved if the government agency is provided with efficient tools that consider both the financial and the risk factors affecting a new project
Strategic Cost Management for Construction Project Success : A Systematic Studycivej
Large construction projects are inherently complex and dynamic. Many projects start with good ideas,
huge investments and great efforts. However, most of them do not achieve much success. A major
contribution to unsuccessful projects is the lack of understanding on scope, time, cost and quality. Projects
as powerful strategic weapons when initiated create economic value and competitive advantage. The
objective of the research is to explicitly declare the scope of the research to by considering only the scope,
time, cost and quality as process success parameters and how specifically the cost element would influence
the project success when all other elements or factors other than cost are represented in terms of cost
factor along with the contract conditions as basic rules or constraints that drive the strategic cost based on
applying the CRASP methodology concept. The concept of benchmarking would provide right meaning of
project success when allowing to properly distributing the meaning of customer profitability to the project
providers (project owner and contractors).
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDYcivejjour
Large construction projects are inherently complex and dynamic. Many projects start with good ideas, huge investments and great efforts. However, most of them do not achieve much success. A major contribution to unsuccessful projects is the lack of understanding on scope, time, cost and quality. Projects as powerful strategic weapons when initiated create economic value and competitive advantage. The objective of the research is to explicitly declare the scope of the research to by considering only the scope, time, cost and quality as process success parameters and how specifically the cost element would influence the project success when all other elements or factors other than cost are represented in terms of cost factor along with the contract conditions as basic rules or constraints that drive the strategic cost based on applying the CRASP methodology concept. The concept of benchmarking would provide right meaning of project success when allowing to properly distributing the meaning of customer profitability to the project providers (project owner and contractors).
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDYcivejjour
Large construction projects are inherently complex and dynamic. Many projects start with good ideas, huge investments and great efforts. However, most of them do not achieve much success. A major contribution to unsuccessful projects is the lack of understanding on scope, time, cost and quality. Projects
as powerful strategic weapons when initiated create economic value and competitive advantage.
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...Vamsi Kovalam
The development of a new building material based on vetiver grass ash for use in the rural areas of the developing countries is experimentally investigated.
The properties of VGA were experimentally studied to consider the possibility of using VGA as a pozzolanic material.
Many developing countries are attempting to develop substitutes for cement from locally available raw materials like agricultural and industrial waste.
Fly ash ,rice husk ash and rice straw ash have been proven to be economical partial substitutes for cement
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
This document summarizes a research paper that aimed to identify and evaluate the most significant causes of cost overrun related to the design phase of construction projects in Egypt. Through a literature review and expert interviews, the researchers developed a list of potential cost overrun causes. They then conducted a survey with 101 industry professionals to quantitatively assess the frequency and impact of each cause. The results showed that the most important causes were design changes/variations and unrealistic construction time estimates. The degree of agreement between owners, contractors, architects, and project managers was also analyzed to identify any conflicting perspectives on the causes.
Similar to Forecasting the final cost of iraqi public school projects using regression analysis (20)
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Forecasting the final cost of iraqi public school projects using regression analysis
1. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015
477
Forecasting the Final Cost of Iraqi Public School Projects
Using Regression Analysis
Dr. Zeyad S. M. Khaled
Engineering College, University of Alnahrian / Baghdad.
Dr. Qais Jawad Frayyeh
Building and Construction Engineering Department, University of Technology/ Baghdad.
Gafel Kareem Aswed
Building and Construction Engineering Department, University of Technology/ Baghdad.
Email:gafelkareem@gmail.com
Received on:29/5/2014 & Accepted on:8/1/2015
ABSTRACT
The actual final cost of public school building projects, like other construction
projects, is unknown to the owner till the final account statement is prepared. An
attempt to predict the final cost of such projects before work starts, using backward
elimination regression analysis technique is carried out. The study covers two story
(12 classes) school projects awarded by the lowest bid system. Records of (65) school
projects completed during (2007-2012) are employed to develop and verify the
regression model. Based on experts ‘convictions, nine factors are considered to have
the most significant impact on the final cost. Hence they are used as model input
parameters. These factors are; awarded bid price, average bid price, estimated cost,
contractor rank, resident engineer experience, project location, number of bidders,
year of contracting, and contractual project duration. It was found that the developed
regression model have the ability to predict the final cost (FC) for school projects, as
an output, with a very good accuracy having a correlation coefficient (R) of (93%),
determination coefficient (R2
)of(86.5%)and average accuracy percentage of(92.02%).
Keywords: cost estimation, cost modeling, regression analysis, and school project.
اﻟﻌﺮاﻗﯿﺔ اﻟﻤﺪارس ﻟﻤﺸﺎرﯾﻊ اﻟﻨﮭﺎﺋﯿﺔ ﺑﺎﻟﻜﻠﻔﺔ اﻟﺘﻨﺒﺆاﻟﺤﻜﻮﻣﯿﺔﺑﻄﺮﯾﻘﺔﺗﺤﻠﯿﻞاﻻﻧﺤﺪار
اﻟﺨﻼﺻﺔ
ﺗﺒﻘﻰاﻟﻨﮭﺎﺋﯿﺔ اﻟﻜﻠﻔﺔاﻟﺤﻘﯿﻘﯿﺔاﻟﻤﺪارس ﻟﻤﺸﺎرﯾﻊ،ﻣﻦ ﻛﻐﯿﺮھﺎاﻟﻤﺸﺎرﯾﻊاﻹﻧﺸﺎﺋﯿﺔ،اﻟﻌﻤﻠ ﻟﺮب ﻣﻌﺮوﻓﺔ ﻏﯿﺮﺤﺘﻰ
ﯾﺘﻤﺎﻋﺪاداﻟﺤﺴﺎﺑﺎﺗﺎﻟﺨﺘﺎﻣﯿﺔ.ﺗﻢاﺳﺘﺨﺪ اﻟﺒﺤﺚ ھﺬا ﻓﻲامﺗﻘﻨﯿﺔاﻻﻧﺤﺪارﺑ ﺗﺤﻠﯿﻞﻄﺮﯾﻘﺔاﻟﺤﺬفﻷﺟﻞاﻟﺘﻨﺑﺎﻟﻜﻠﻔﺔ ﺒﺆ
ﺑﺎﻟﻤﺸﺮوع اﻟﻌﻤﻞ ﺑﺪء ﻗﺒﻞ اﻟﻤﺪارس ﻟﻤﺸﺎرﯾﻊ اﻟﻨﮭﺎﺋﯿﺔ.ﺷﻤﻠﺖ وﻗﺪاﻟﺪراﺳﺔﺑﯿﺎﻧﺎت ﺗﺤﻠﯿﻞ)٦٥(ﻣﺪرﺳﺔ ﻣﺸﺮوع
ﺑﻄﺎﺑﻘﯿﻦ،ذات)١٢(ﺻﻒ،ا ﺑﻨﻈﺎم ﻣﺤﺎﻟﺔﻹاﻟﻌﻄﺎءات ﻷوﻃﺄ ﺣﺎﻟﺔ.ﺟﻤﯿﻌﮭﺎاﻟﺒﻨﺎء ﻣﻜﺘﻤﻠﺔوﻣﺴﺘﻠﻤﺔًﺎاﺳﺘﻼﻣًﺎﻧﮭﺎﺋﯿ
اﻟﻌﻤﻞ رب ﻗﺒﻞ ﻣﻦا ﺧﻼلﻟﺴﻨﻮات)٢٠٠٧-٢٠١٢(.وﻗﺪﺗﺤﺪﯾﺪ ﺗﻢﺗﺴﻊﻋﻮاﻣﻞاﻟﻨﮭﺎﺋﯿﺔ اﻟﻜﻠﻔﺔ ﻓﻲ ﻣﺆﺛﺮة اﺳﺎﺳﯿﺔ
ھﺬه ﻟﻤﺜﻞاﻟواﻻﺧﺘﺼﺎص،و اﻟﺨﺒﺮة ذوي أراء اﺳﺘﺒﯿﺎن ﺧﻼل ﻣﻦ وذﻟﻚ ،ﻤﺸﺎرﯾﻊاﺳﺘﺨﺪا ﺗﻢﺑﻨﺎء ﻓﻲ ﻛﻤﺪﺧﻼت ﻣﮭﺎ
اﻟﺮﯾﺎﺿﻲ اﻟﻨﻤﻮذجاﻟﻨﮭﺎﺋﯿﺔ ﺑﺎﻟﻜﻠﻔﺔ ﻟﻠﺘﻨﺒﺆ.وھﻲ اﻟﻌﻮاﻣﻞ ھﺬه:اﻟﻔﺎﺋﺰ اﻟﻌﻄﺎء ﺳﻌﺮ،واﻟﻌﻄﺎءات اﺳﻌﺎر ﻣﻌﺪل،واﻟﻜﻠﻔﺔ
اﻟﺘﺨﻤﯿﻨﯿﺔ،واﻟﻤﻘﺎول ﺗﺼﻨﯿﻒ درﺟﺔ،واﻟﻤﮭﻨﺪس ﺧﺒﺮةاﻟﻤﻘﯿﻢ،واﻟﻤﺸﺮوع ﻣﻮﻗﻊ،واﻟﻤﻨﺎﻗﺼﯿﻦ ﻋﺪد،واﻟﺘﻌﺎﻗﺪ ﺳﻨﺔ،وﻣﺪة
2. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
478
اﻟﺘﻨﻔﯿﺬاﻟﺘﻌﺎﻗﺪﯾﺔ.وﻟﻘﺪﻣﻦ ﺗﺒﯿﻦاﻟﺪراﺳﺔأﻧﺎﻟﻨﻤﻮذجاﻟﻤﻌﺘﻤﺪﻟﮭﺎاﻟﻘﺪرةﻋﻠﻰاﻟﺘﻨﺒﺆﺑﺎﻟﻜﻠﻔﺔاﻟﻨﮭﺎﺋﯿﺔﻟﻤﺸﺎرﯾﻊاﻟﻤﺪارس،
،ﻟﻠﻨﻤﻮذج ﻛﻤﺨﺮجﺑﺪرﺟﺔﻋﺎﻟﯿﺔﻣﻦاﻟﺪﻗﺔوﺑﻤﻌﺎﻣﻞارﺗﺒﺎطﯾﺴﺎوي)٩٣٪(،ﺗﺤﺪﯾﺪ وﻣﻌﺎﻣﻞﯾﺴﺎوي)٨٦.٥٪(،
وﻣﺘﻮﺳﻂﻧﺴﺒﺔدﻗﺔﯾﺴﺎوي)٩٢.٠٢٪(.
INTRODUCTION
onstruction projects costs are influenced by several factors. These factors are
related to project characteristics, construction teams and market conditions.
When unexpected events occur during the execution phase of construction
projects, their final costs are driven up. Most of such events are uncontrollable factors
that increase the gap between the contract award price and the final completion cost.
It is greatly important that the client should know what contingencies he must have in
hand to ensure his project final completion in time. Lack of information about these
factors, lack of relevant data, and weak expectations of possible circumstances to be
faced by the project are the main challenges facing researchers in this essence. This
research attempts to use real measurable parameters, to be in hand before the project
starts, as predictors for the expected final cost of school projects.
Research Objectives
This research aims at the following objectives:
• To explore the factors that can be used to predict the final cost of school
building projects before starting works.
• To raise the efficiency of estimating initial costs using data already in hand.
• To build a mathematical model using multiple regression analysis to predict
cost deviation in school building projects before starting works.
Research Hypothesis
At the project start phase, it can be said that awarded bid price, average bid price,
estimated cost, contractor rank, resident engineer experience, project location,
number of bidders, year of contracting, and contractual project duration are good
predictors to the final cost of public school building projects before starting works.
Research Justification
The reasons for carrying out this research are:
• The large number of under construction school projects accompanied with
everlasting cost overrun and the ever growing demand on additional school buildings
in Iraq.
• The need of knowing an accurate anticipated final cost of a construction
projects before starting works, is highly essential in budgeting concerns, especially in
contingency allocation.
Suitability Of Multiple Regression
The objective of most parametric costs estimating approaches is to use some
historical cost data and try to find a functional relationship between changes in cost
and the factors affecting the final cost. The regression technique is a statistical
modeling method that can be used for analysis and prediction in different knowledge
domains. Multiple regression estimation models are well established and widely used
in cost estimation. They are effective due to their well-defined mathematical
procedure, as well as being able to explain the significance of each variable and the
C
3. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
479
relationships between them. Basically, regression models are intended to find the
linear combination of variables which best correlates with dependent variables. The
general regression equation is expressed as follows[1]:
Y = Ao + A1I1 + A2I2 +…. AnIn (1)
Where
Y is the total estimated final result, Ao is a constant estimated by regression
analysis, A1, A2, … An are coefficients also estimated by regression analysis, given
the availability of some relevant dataI1, I2,…In as measured distinguishable variables
that may help in estimating Y [2].
Literature Review
Literature review shows a variety of ways used to predict the project final cost and
deviations. Many variables were used as predictors in those studies.
Williams [3] concluded five mathematical models to predict the final cost of highway
construction using low bids in five states in USA as independent variable. From
competitive bidding of highway construction projects, the low bid price and the cost
of the completed contract were obtained for each project. These models aimed at
predicting the project final cost according to the low bid as the only input.
Wibowo and Warranty[4]studied education building projects in Indonesia to prepare
early stage cost estimate models. They found that the estimated cost at earlier stages
could be predicted according to the total project area.
Olatunji[5] collected data of (137) public contract projects executed between
(2003) and (2007) in Nigeria. Lowest/winner bid, average bid, consultant’s cost
estimate, gross floor are a were the model variables to predict the final construction
cost. The conducted regression model has an adjusted R2
value of (0.949).
Mahamid and Amund [6] investigated the statistical relationship between actual and
estimated cost of road construction projects. Data collected from (169) road
construction projects awarded in the West Bank in Palestine over the years (2004–
2008) were analyzed. The study concluded that (100%) of road projects in Palestine
suffer from cost deviation. The developed a regression model with a coefficient of
determination (R2
)of (0.96).
Bedford[7] studied the risks of excessive competition in the Canadian public sector
that award contracts solely to the low bid. It has been concluded that the bidding
process is a good indicator to the final cost and possible cost escalations.
Ganiyu and Zubairu [8] developed a predictive cost model for public building
projects in Nigeria using principal components regression. The study showed that the
project cost basically depends on factors related to; adequacy of equipment,
experience in similar projects, time allowed for bidding, level of technology, client
commitment to time, repetitive work, design complexity, communications, project
scope, construction complexity, and previous relationship with the client.
Mohd et al.[9]studied the historical data of (83) school projects in the Malaysian
public sector. Multiple regression analysis was used to predict the effect of the lowest
bid, average tender price, and the winning tender in the interpretation of the deviation
in cost estimation. The regression model from mean bids showed that the project size,
number of tenders, type of schools, and location are the best-fitted predictors to
explain biased estimates.
Aziz[10] investigated and ranked factors perceived to affect cost variation in the
Egyptian wastewater projects. It was discovered that factors such as: lowest bid
4. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
480
procurement method, additional works, bureaucracy in bidding, tendering method,
wrong method of cost estimation, and funding problems were crucial in causing cost
variation, while, inaccurate cost estimation, mode of payments, unexpected ground
conditions, inflation, and price fluctuation are less important.
Data collaction
The initial parameters that are intended to be used in the model were collected
from the literature review of previous studies as shown in Table (1). A questionnaire
form has been directed to (50) local experts in order to determine the most significant
factors in predicting the final cost of school projects before they start. Fifty
questionnaires were directed to owner's representative engineers in the public sector.
Thirty two respondents forms, forming (64%) of the total number of questionnaires,
have successfully been submitted. The respondents were asked to select the
parameters that they believe are most important in developing the mathematical
model. Likert’s scale of five ordinal measures of importance (from 1 to 5) is used. An
effort had been made to limit the number of variables that affect the cost model. Nine
out of eleven variables were identified and analyzed as independent variables of the
regression equation based on the respondents' opinions. These variables are: (I1)
accepted bid price, (I2) average bid price, (I3) estimated cost, (I4) contractor rank, (I5)
experience of the resident engineer (R.E), (I6) location of project, (I7) number of
bidders, (I8) year of contracting, and (I9) project duration. To build the regression
model historical data are collected from (68) completed schools projects in Karbala
province. These projects are executed during the years (2007-2012). By eliminating
the incomplete records, the number of projects put under consideration for the final
selected model became (65) projects. The projects were awarded under the lowest bid
tendering system having the same design and number of classrooms.
Table (1): Influential factors affecting the final cost of school projects
Influential Factors Supporting Previous Studies
I1 Accepted bid price Elhag [11],Williams[3], Olatunji[5]
I2 Average bid price Olatunji[5], (Mohd et al.[9]
I3 Estimated cost Olatunji [5], Mahamid and Amund[6]
I4 Contractor rank Ganiyu and Zubairu[8]
I5 Experience of R. E. Ganiyu and Zubairu[8]
I6 Project location Mohd et al.[9],
I7 Number of bidders Mohd et al. [9]
I8 Year of contracting Al-zwainy [12]
I9 Contractor duration Elhag [11]
I11 Owner duration Ayman et al. [13]
I12 Second lowest bid Bordat et al. [14]
Model formulation
Previous studies showed different methods used to study the relation between the
final cost and factors believed to influence that final cost. In this research a back
elimination regression technique is adopted to analyze historical cost data in order to
provide a powerful model to assist budgeting and cost estimating before work starts.
The Statistical Package for Social Science SPSS and MS Excel are used to develop a
suitable model. In order to remove linear trend from the data, transformations by
5. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
481
taking the natural logs of some of the variables reapplied. Then a simple linear model
is developed using in each run, the natural log of the final project cost (FC) as the
dependent variable, the natural logs of; accepted bid price (I1), average bid price (I2),
estimated cost (I3), and the untransformed parameters of; contractor rank (I4),
experience of R.E. (I5), location of project (I6), number of bidders (I7), year of
contracting (I8), contractor duration (I9) as independent variables.
SPSS (version 20) is used for data analysis. Backward elimination technique is
adopted to develop the regression model as in Tables(2) and (3). The procedure of
this technique is to enter all nine variables in the model equation first, then
sequentially remove the variable with the smallest partial correlation with the
dependent variable in each run.
Table (2): Summary of Analysis Results
FC-Model R R2
Adjusted R2
Standard Error Residual Mean Square
1 0.930a 0.865 0.841 0.1232519 0.015
2 0.930b 0.865 0.844 0.1220738 0.015
3 0.930c 0.865 0.847 0.1209313 0.015
4 0.930d 0.865 0.850 0.1198686 0.014
5 0.929e 0.862 0.850 0.1199525 0.014
6 0.927f 0.860 0.850 0.1199546 0.014
7 0.926g 0.857 0.849 0.1201290 0.014
Where
a. Predictors: (Constant), I9, I4, I6, I7, I5, I2, I8, I3, I1
b. Predictors: (Constant), I9, I4, I6, I7, I5, I8, I3, I1
c. Predictors: (Constant), I9, I4, I7, I5, I8, I3, I1
d. Predictors: (Constant), I9, I4, I7, I5, I3, I1(the best model)
e. Predictors: (Constant), I4, I7, I5, I3, I1
f. Predictors: (Constant), I4, I7, I3, I1
g. Predictors: (Constant), I7, I3, I1
h.Dependent Variable: FC
Table (3): Model Coefficients
Model
Un standardized
Coefficients
Standardized
Coefficients
t Sig.(p-Value)
B Std. Error Beta
(Constant) 2.032 1.235 1.646 0.106
I1 0.344 0.147 0.358 2.343 0.023
I3 0.569 0.147 0.560 3.860 0.00031
I4 -0.025 0.020 -0.067 -1.283 0.205
I5 0.004 0.004 0.059 1.111 0.272
I7 -0.028 0.013 -0.109 -2.096 0.041
I9 0.00022 0.000 0.065 1.037 0.304
6. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
482
Resulted Equation
After applying multiple regression analysis on the historical data of the whole
(60)school projects, the resulted final construction cost estimation equation is:
FC= 2.032 + 0.344I1+ 0.569I3- 0.023I4+ 0.004I5- 0.028I7+ 0.00022I9 …. (2)
This model is chosen based on the smallest Standard Error of Estimate which is
(0.1198686) and the Residual Mean Square which is(0.014).
According to Tabachnick and Fidell[1]advice, the relative importance of the
independent variables is assessed by examining their respective standardized
coefficients i.e. Beta values in Table (3). Predictors with higher standardized
coefficients such as: ln accepted bid price (I1), ln estimated cost (I3) and number of
bidders (I7) are more important to the regression equation than those with lower
values such as contractor rank (I4), experience of R.E. (I5) and contractor duration
(I9).Therefore values of I1, I3, andI7indicate a highly significant regression fit. It can
be concluded that I1,I3, and I7contribute significantly to the regression model. The
small constants of I5 and I9in the model equation refer to the small effect of
experience of R.E and the contractor duration. The exclusion of the average bid price
(I2), location (I6) and the year of contracting (I8) parameters is because of their
insignificance.
Multi-Collinearity Assessment
To assess multi-collinearity among the variables, tolerances and variance inflation
factors (VIF) are examined as shown in Table (4). Tolerance refers to the proportion
of the variance of that variable that is not accounted for by other predictors in the
model and is calculated using the formula (1–R2
) for each variable. The range of
tolerances is from (0)i.e. perfect collinearity, to (1)i.e. no collinearity. A tolerance
with values less than (0.1) typically indicates a multi-collinearity problem. Variance
inflation factor (VIF) is another index for the diagnostic of multi-collinearity which is
just the inverse of the tolerance value. The high value of (VIF) for a variable indicates
that there is a strong association between that variable and other remaining predictors
[1].Variables that have high tolerances will definitely have small variance inflation
factors. A variance inflation factor in excess of (10) indicates a multi-collinearity
problem [15]. Since the final cost model predictors have to lerances and (VIF) values
that do not violate the for ementioned criteria, therefore, multi-collinearity is not a
serious problem in this analysis.
Table (4): Collinearity test
Model VIF Tolerance
I1 9.180 .109
I3 8.276 .121
I4 1.070 .934
I5 1.091 .916
I7 1.069 .936
I9 1.538 .650
7. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
483
Model Validation
One of the most important steps in developing a cost model is to test its accuracy
and validity. This process is also refers to as the model validation. It involves testing
and evaluating the developed model with some test or validation data. The validation
data should be some representative data from the targeted population but haven't been
used in the development of the model. In this study, the validation data are extracted
from the same historical data file but for five randomly selected additional projects.
They are not a part of the (60) projects used in the development of the model. The
predicted cost of these five projects computed using the model equation are compared
with real cost records and the results of this comparison are shown in Table (5). It is
evident now that the model performed very well. Its predictions deviate only by (–
8.702%) to (6.513%).
Table (5): Comparison of predicted and observed final costs
FC(observed) in IQD FC (predicted) in IQD *Deviation %
688482184.5 733325333.7 6.513335
1158046071 1057263708 -8.70279
832546804.6 760502532.7 -8.65348
1852866989 1877430643 1.325711
1594777396 1473269621 -7.61911
*Deviation %= {(Predicted cost – Observed cost)/Observed cost*100}[16].
To assess the validity of the derived equation of the model for the final cost of
school project (FC), the natural logarithm (Ln) of predicted values of (FC) is plotted
against the natural logarithm (Ln) of real values for validation data set as shown in
Figure (1).
Figure (1): Comparison of Predicted and Actual Final Costs
The coefficient of determination (R2
) is found to be (97%), therefore it can be
concluded that this model shows a good agreement with the actual measurements. It
is finally clear that this model for school building projects in Iraq has the
generalization capability for any data set used within the range of data used in the
development of the (MR) model.
20.2
20.4
20.6
20.8
21
21.2
21.4
21.6
20 20.5 21 21.5
Ln(predictedfinalcost)
Ln (actual final cost)
Y
PredictedY
8. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
484
Model Evaluation
The statistical measures used to measure the performance of themodels
included[17]:
i. Mean Percentage Error (MPE)which is one of the most important measures of
accuracy of a proposed model. It is the mean of the absolute percentage differences
ii. between the predicted and the actual values:
= ∑ / ∗ 100 …(3)
Where:
A = actual value
E = estimated value (predicted value)
n = total number of cases (5 for validation)
iii. Root Mean Squared Error (RMSE)
=
∑ ( )
… (4)
iv. Mean Absolute Percentage Error (MAPE),
MAPE =
∑
| |
∗
… (5)
Average accuracy percentage (AA %):
AA% = 100% -MAPE …(6)
v. The Coefficient of Determination (R2)
vi. The Coefficient of Correlation (R) is a measure that is used to determine the relative
correlation and the goodness-of-fit between the predicted and observed data and show
how well the model outputs match the target value.
These statistical measures of the regression Model (FC) in equation (2) are presented
in Table (6).
Table (6):Statistical Measures Results For Regression model
Description Statistical parameters
MPE 3.98%
RMSE 0.83
MAPE 7.97%
AA% 92.02%
R2
86.5%
R 93%
The(MAPE) and (AA) generated by (MR) model of (FC) are found to be (7.97%)
and (92.02%) respectively. The (R2
) value is (86.5%) which indicates that the most
variability in the total cost is explained by the terms in the model. Therefore, it can be
concluded that this (MR) model of (FC)shows good agreement with theactual
measurements.
CONCLUSIONS
1. Backward elimination techniques are used to develop the regression model on
the historical data of the school projects, resulting in the final construction cost
perdition equation with (R2
=86.5%).
9. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
485
2. The most significant model parameters are: accepted bid price (I1), estimated
cost (I3), Contractor rank (I4), resident engineer experiencein years(I5), number of
bidders (I7), and contractor duration (I9).
3. The developed model shows agood agreement with theactual measurements
based on the accuracy measurements.
4. It can easily calculate the expected cost deviation which is the difference
between contractual sums and predicted final costs obtained from the developed
regression model.
5. Other future work estimating parameters like cost per unit area, unit volume,
classroom, or pupil can be calculated.
Recommendations
1. Data for another design of schools can be studied to further confirm the
relationship between the independent parameters and final cost.
2. The developed model can be checked for applicability on other typical type
of school projects such as (14), (16) and (18) classes.
3. Attention must be given to the documentation and feedback of data in order
to achieve efficient and effective updated information and to audit a deferent
accounting and financial procedures.
REFERANCES
[1].Tabachnick, Barbara G. and Fidell, Linda S., “Using Multivariate Statistics”, fifth
Edition, 2007,Pearson Education Inc.
[2].Stevens, I. James P., “Applied multivariate statistics for the social sciences”
2009, 5th edition- Taylor & Francis Group, LLC.
[3].Williams, Trefor P., “Predicting Final Cost for Competitively Bid Construction
Projects Using Regression Models”, International Journal of Project Management,
Vol. 21, 2003, Pp. 593–599.
[4].Wibowo, A. and Wuryanti, W., “Capacity Factor Based Cost Models for
Buildings of Various Functions”, Civil Engineering Dimension, Vol. 9, No. 2, 2007,
Thomson Gale TM, Pp. 70–76.
[5].Olatunji, O. A., “A Comparative Analysis of Tender Sums and Final Costs of
Public Construction and Supply Projects in Nigeria”, Journal of Financial
Management of Property and Construction, 13(1), 2008, Emerald Group Publishing
Limited, Pp. 60-79.
[6].Mahamid, I and Amund, B “Cost deviation in road construction projects: the case
of Palestine”, Australasian Journal of Construction Economics and Building, 12 (1),
2012, Pp. 58-71.
[7].Bedford, Thomas, “Analysis of the Low-Bid Award System in Public Sector
Construction Procurement”, MSc. thesis in Civil Engineering, 2009, University of
Toronto.
[8].Ganiyu, B. O. and Zubairu, I. K., “Project Cost Prediction Model Using Principal
Component Regression for Public Building Projects in Nigeria”, Journal of Building
Performance, Vol. 1 Issue 1, 2010, Pp. 21-28.
[9].Mohd Azrai Azman, Zulkiflee, A. S., Suraya Ismail, “The Accuracy of
Preliminary Cost Estimates in Public Works Department (PWD) of Peninsular
Malaysia”, International Journal of Project Management Vol. 31, 2013, Elsevier, Pp.
994-1005.
10. Eng. &Tech.Journal, Vol.33,Part (A),No.2, 2015 Forecasting the Final Cost of Iraqi Public School
Projects Using Regression Analysis
486
[10].Aziz, Remon Fayek, “Factors Causing Cost Variation for Constructing Waste
Water Projects in Egypt”, Alexandria Eng.Journal Vol.52, 2013, p. 51–66.
[11].Elhag, Taha Mahmoud Salih, “Tender Price Modeling: Artificial Neural
Networks and Regression Techniques”, PhD Dissertation, 2002, University of
Liverpool.
[12].Al-Zwainy, Fai’q Mohammed Sarhan, “The Use of Artificial Neural Network for
Estimating Total Cost for Highway Construction Projects”, Ph.D. Thesis, 2008,
College of Engineering, University of Baghdad.
[13].Ayman, A. Abu Hammad, Souma M. Alhaj Ali, Ghaleb J. Sweis and Adnan
Bashir, “Prediction Model for Construction Cost and Duration in Jordan”, Jordan
Journal of Civil Engineering, Volume 2, No. 3, 2008,Pp. 250-266.
[14].Bordat, C., B. G. McCullouch, S. Labi, and K. C. Sinha, “An Analysis of Cost
Overruns and Time Delays of INDOT Projects”, Publication FHWA/IN/JTRP-
2004/07.Joint Transportation Research Program, Indiana Department of
Transportation and Purdue University, West Lafayette, Indiana,.
[15].Pallant, Julie, “SPSS Survival Manual a step by step guide to data analysis using
SPSS”, 4th edition, 2011, Allen & Unwin, Australia.
[16].Memon, A. H., “Structural Modeling of Cost Overrun Factors in Construction
Industry”, PhD dissertation, faculty of Civil and Environmental Engineering,
University Tun Hussein Onn Malaysia, 2013.
[17].Sulewska, Maria J., “Applying Artificial Neural Networks for analysis of
geotechnical problems”, Computer Assisted Mechanics and Engineering Sciences,
18, 2011, Pp.231–241.