SlideShare a Scribd company logo
10 - 1
Chapter 10:
The Basics of Capital Budgeting:
Evaluating Cash Flows
Overview and “vocabulary”
Methods
Payback, discounted payback
NPV
IRR, MIRR
Profitability Index
Unequal lives
Economic life
10 - 2
What is capital budgeting?
Analysis of potential projects.
Long-term decisions; involve large
expenditures.
Very important to firm’s future.
10 - 3
Steps in Capital Budgeting
Estimate cash flows (inflows &
outflows).
Assess risk of cash flows.
Determine r = WACC for project.
Evaluate cash flows.
10 - 4
What is the difference between
independent and mutually exclusive
projects?
Projects are:
independent, if the cash flows of
one are unaffected by the
acceptance of the other.
mutually exclusive, if the cash
flows of one can be adversely
impacted by the acceptance of the
other.
10 - 5
What is the payback period?
The number of years required to
recover a project’s cost,
or how long does it take to get the
business’s money back?
10 - 6
Payback for Franchise L
(Long: Most CFs in out years)
10 8060
0 1 2 3
-100
=
CFt
Cumulative -100 -90 -30 50
PaybackL 2 + 30/80 = 2.375 years
0
100
2.4
10 - 7
Franchise S (Short: CFs come quickly)
70 2050
0 1 2 3
-100CFt
Cumulative -100 -30 20 40
PaybackS 1 + 30/50 = 1.6 years
100
0
1.6
=
10 - 8
Strengths of Payback:
1. Provides an indication of a
project’s risk and liquidity.
2. Easy to calculate and understand.
Weaknesses of Payback:
1. Ignores the TVM.
2. Ignores CFs occurring after the
payback period.
10 - 9
10 8060
0 1 2 3
CFt
Cumulative -100 -90.91 -41.32 18.79
Discounted
payback 2 + 41.32/60.11 = 2.7 yrs
Discounted Payback: Uses discounted
rather than raw CFs.
PVCFt -100
-100
10%
9.09 49.59 60.11
=
Recover invest. + cap. costs in 2.7 yrs.
10 - 10
( )
.
10
t
t
n
t r
CF
NPV
+
= ∑=
NPV: Sum of the PVs of inflows and
outflows.
Cost often is CF0 and is negative.
( )
.
1
0
1
CF
r
CF
NPV t
t
n
t
−
+
= ∑=
10 - 11
What’s Franchise L’s NPV?
10 8060
0 1 2 3
10%
Project L:
-100.00
9.09
49.59
60.11
18.79 = NPVL NPVS = $19.98.
10 - 12
Calculator Solution
Enter in CFLO for L:
-100
10
60
80
10
CF0
CF1
NPV
CF2
CF3
I = 18.78 = NPVL
10 - 13
Rationale for the NPV Method
NPV = PV inflows - Cost
= Net gain in wealth.
Accept project if NPV > 0.
Choose between mutually
exclusive projects on basis of
higher NPV. Adds most value.
10 - 14
Using NPV method, which franchise(s)
should be accepted?
If Franchise S and L are
mutually exclusive, accept S
because NPVs > NPVL .
If S & L are independent,
accept both; NPV > 0.
10 - 15
Internal Rate of Return: IRR
0 1 2 3
CF0 CF1 CF2 CF3
Cost Inflows
IRR is the discount rate that forces
PV inflows = cost. This is the same
as forcing NPV = 0.
10 - 16
( )
.
10
NPV
r
CF
t
t
n
t
=
+
∑=
( )t
n
t
t
CF
IRR=
∑
+
=
0 1
0.
NPV: Enter r, solve for NPV.
IRR: Enter NPV = 0, solve for IRR.
10 - 17
What’s Franchise L’s IRR?
10 8060
0 1 2 3
IRR = ?
-100.00
PV3
PV2
PV1
0 = NPV
Enter CFs in CFLO, then press IRR:
IRRL = 18.13%. IRRS = 23.56%.
10 - 18
40 4040
0 1 2 3
IRR = ?
Find IRR if CFs are constant:
-100
Or, with CFLO, enter CFs and press
IRR = 9.70%.
3 -100 40 0
9.70%
N I/YR PV PMT FV
INPUTS
OUTPUT
10 - 19
Rationale for the IRR Method
If IRR > WACC, then the project’s
rate of return is greater than its
cost-- some return is left over to
boost stockholders’ returns.
Example: WACC = 10%, IRR = 15%.
Profitable.
10 - 20
Decisions on Projects S and L per IRR
If S and L are independent, accept
both. IRRs > r = 10%.
If S and L are mutually exclusive,
accept S because IRRS > IRRL .
10 - 21
Construct NPV Profiles
Enter CFs in CFLO and find NPVL and
NPVS at different discount rates:
r
0
5
10
15
20
NPVL
50
33
19
7
NPVS
40
29
20
12
5(4)
10 - 22
-10
0
10
20
30
40
50
60
0 5 10 15 20 23.6
NPV ($)
Discount Rate (%)
IRRL = 18.1%
IRRS = 23.6%
Crossover
Point = 8.7%
r
0
5
10
15
20
NPVL
50
33
19
7
(4)
NPVS
40
29
20
12
5
S
L
10 - 23
NPV and IRR always lead to the same
accept/reject decision for independent
projects:
r > IRR
and NPV < 0.
Reject.
NPV ($)
r (%)
IRR
IRR > r
and NPV > 0
Accept.
10 - 24
Mutually Exclusive Projects
r 8.7 r
NPV
%
IRRS
IRRL
L
S
r < 8.7: NPVL> NPVS , IRRS > IRRL
CONFLICT
r > 8.7: NPVS> NPVL , IRRS > IRRL
NO CONFLICT
10 - 25
To Find the Crossover Rate
1. Find cash flow differences between the
projects. See data at beginning of the
case.
2. Enter these differences in CFLO register,
then press IRR. Crossover rate = 8.68%,
rounded to 8.7%.
3. Can subtract S from L or vice versa, but
better to have first CF negative.
4. If profiles don’t cross, one project
dominates the other.
10 - 26
Two Reasons NPV Profiles Cross
1. Size (scale) differences. Smaller
project frees up funds at t = 0 for
investment. The higher the opportunity
cost, the more valuable these funds, so
high r favors small projects.
2. Timing differences. Project with faster
payback provides more CF in early
years for reinvestment. If r is high,
early CF especially good, NPVS > NPVL.
10 - 27
Reinvestment Rate Assumptions
NPV assumes reinvest at r
(opportunity cost of capital).
IRR assumes reinvest at IRR.
Reinvest at opportunity cost, r, is
more realistic, so NPV method is
best. NPV should be used to choose
between mutually exclusive projects.
10 - 28
Managers like rates--prefer IRR to NPV
comparisons. Can we give them a
better IRR?
Yes, MIRR is the discount rate which
causes the PV of a project’s terminal
value (TV) to equal the PV of costs.
TV is found by compounding inflows
at WACC.
Thus, MIRR assumes cash inflows are
reinvested at WACC.
10 - 29
MIRR = 16.5%
10.0 80.060.0
0 1 2 3
10%
66.0
12.1
158.1
MIRR for Franchise L (r = 10%)
-100.0
10%
10%
TV inflows-100.0
PV outflows
MIRRL = 16.5%
$100 =
$158.1
(1+MIRRL)3
10 - 30
To find TV with 10B, enter in CFLO:
I =
10NPV = 118.78 = PV of inflows.
Enter PV = -118.78, N = 3, I = 10, PMT =
0.
Press FV = 158.10 = FV of inflows.Enter FV = 158.10, PV = -100, PMT = 0,
N = 3.
Press I = 16.50% = MIRR.
CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80
10 - 31
Why use MIRR versus IRR?
MIRR correctly assumes reinvestment
at opportunity cost = WACC. MIRR
also avoids the problem of multiple
IRRs.
Managers like rate of return
comparisons, and MIRR is better for
this than IRR.
10 - 32
Normal Cash Flow Project:
Cost (negative CF) followed by a
series of positive cash inflows.
One change of signs.
Nonnormal Cash Flow Project:
Two or more changes of signs.
Most common: Cost (negative
CF), then string of positive CFs,
then cost to close project.
Nuclear power plant, strip mine.
10 - 33
Inflow (+) or Outflow (-) in Year
0 1 2 3 4 5 N NN
- + + + + + N
- + + + + - NN
- - - + + + N
+ + + - - - N
- + + - + - NN
10 - 34
Pavilion Project: NPV and IRR?
5,000 -5,000
0 1 2
r = 10%
-800
Enter CFs in CFLO, enter I = 10.
NPV = -386.78
IRR = ERROR. Why?
10 - 35
We got IRR = ERROR because there
are 2 IRRs. Nonnormal CFs--two sign
changes. Here’s a picture:
NPV Profile
450
-800
0
400100
IRR2 = 400%
IRR1 = 25%
r
NPV
10 - 36
Logic of Multiple IRRs
1. At very low discount rates, the PV of
CF2 is large & negative, so NPV < 0.
2. At very high discount rates, the PV of
both CF1 and CF2 are low, so CF0
dominates and again NPV < 0.
3. In between, the discount rate hits CF2
harder than CF1, so NPV > 0.
4. Result: 2 IRRs.
10 - 37
Could find IRR with calculator:
1. Enter CFs as before.
2. Enter a “guess” as to IRR by
storing the guess. Try 10%:
10 STO
IRR = 25% = lower IRR
Now guess large IRR, say, 200:
200 STO
IRR = 400% = upper IRR
10 - 38
When there are nonnormal CFs and
more than one IRR, use MIRR:
0 1 2
-800,000 5,000,000 -5,000,000
PV outflows @ 10% = -4,932,231.40.
TV inflows @ 10% = 5,500,000.00.
MIRR = 5.6%
10 - 39
Accept Project P?
NO. Reject because MIRR =
5.6% < r = 10%.
Also, if MIRR < r, NPV will be
negative: NPV = -$386,777.
10 - 40
S and L are mutually exclusive and
will be repeated. r = 10%. Which is
better? (000s)
0 1 2 3 4
Project S:
(100)
Project L:
(100)
60
33.5
60
33.5 33.5 33.5
10 - 41
S L
CF0 -100,000 -100,000
CF1 60,000 33,500
Nj 2 4
I 10 10
NPV 4,132 6,190
NPVL > NPVS. But is L better?
Can’t say yet. Need to perform
common life analysis.
10 - 42
Note that Project S could be
repeated after 2 years to generate
additional profits.
Can use either replacement chain
or equivalent annual annuity
analysis to make decision.
10 - 43
Franchise S with Replication:
NPV = $7,547.
Replacement Chain Approach (000s)
0 1 2 3 4
Franchise S:
(100)
(100)
60
60
60
(100)
(40)
60
60
60
60
10 - 44
Compare to Franchise L NPV =
$6,190.
Or, use NPVs:
0 1 2 3 4
4,132
3,415
7,547
4,132
10%
10 - 45
If the cost to repeat S in two years
rises to $105,000, which is best? (000s)
NPVS = $3,415 < NPVL = $6,190.
Now choose L.
0 1 2 3 4
Franchise S:
(100) 60 60
(105)
(45)
60 60
10 - 46
Year
0
1
2
3
CF
($5,000)
2,100
2,000
1,750
Salvage Value
$5,000
3,100
2,000
0
Consider another project with a 3-year
life. If terminated prior to Year 3, the
machinery will have positive salvage
value.
10 - 47
1.751. No termination
2. Terminate 2 years
3. Terminate 1 year
(5)
(5)
(5)
2.1
2.1
5.2
2
4
0 1 2 3
CFs Under Each Alternative (000s)
10 - 48
NPV(no) = -$123.
NPV(2) = $215.
NPV(1) = -$273.
Assuming a 10% cost of capital, what is
the project’s optimal, or economic life?
10 - 49
The project is acceptable only if
operated for 2 years.
A project’s engineering life does not
always equal its economic life.
Conclusions
10 - 50
Choosing the Optimal Capital Budget
Finance theory says to accept all
positive NPV projects.
Two problems can occur when there
is not enough internally generated
cash to fund all positive NPV projects:
An increasing marginal cost of
capital.
Capital rationing
10 - 51
Increasing Marginal Cost of Capital
Externally raised capital can have
large flotation costs, which increase
the cost of capital.
Investors often perceive large capital
budgets as being risky, which drives
up the cost of capital.
(More...)
10 - 52
If external funds will be raised, then
the NPV of all projects should be
estimated using this higher marginal
cost of capital.
10 - 53
Capital Rationing
Capital rationing occurs when a
company chooses not to fund all
positive NPV projects.
The company typically sets an
upper limit on the total amount
of capital expenditures that it will
make in the upcoming year.
(More...)
10 - 54
Reason: Companies want to avoid the
direct costs (i.e., flotation costs) and
the indirect costs of issuing new
capital.
Solution: Increase the cost of capital
by enough to reflect all of these costs,
and then accept all projects that still
have a positive NPV with the higher
cost of capital.
(More...)
10 - 55
Reason: Companies don’t have
enough managerial, marketing, or
engineering staff to implement all
positive NPV projects.
Solution: Use linear programming to
maximize NPV subject to not
exceeding the constraints on staffing.
(More...)
10 - 56
Reason: Companies believe that the
project’s managers forecast
unreasonably high cash flow estimates,
so companies “filter” out the worst
projects by limiting the total amount of
projects that can be accepted.
Solution: Implement a post-audit
process and tie the managers’
compensation to the subsequent
performance of the project.

More Related Content

What's hot

Fm11 ch 09 show
Fm11 ch 09 showFm11 ch 09 show
Fm11 ch 09 show
Adi Susilo
 
Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2onurozbal
 
ch 10; cost of capital
ch 10; cost of capitalch 10; cost of capital
ch 10; cost of capital
Sathish Kumar Patturaj
 
Finanzas Coporativas
Finanzas CoporativasFinanzas Coporativas
Finanzas Coporativas
July Pereda Leyva
 
Equity Valuation
Equity ValuationEquity Valuation
Equity Valuation
cgshah
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
Rashedur Rahman
 
economy Chapter7_by louy Al hami
economy Chapter7_by louy Al hamieconomy Chapter7_by louy Al hami
economy Chapter7_by louy Al hami
Louy Alhamy
 
Fisher's rate intersection - In Capital Budgeting - NPV and IRR
Fisher's rate intersection - In Capital Budgeting - NPV and IRRFisher's rate intersection - In Capital Budgeting - NPV and IRR
Fisher's rate intersection - In Capital Budgeting - NPV and IRR
Sundar B N
 
Chap 4.pdf beta
Chap 4.pdf betaChap 4.pdf beta
Chap 4.pdf betaJaved Riza
 
Accounting assignment frederico costa
Accounting assignment frederico costaAccounting assignment frederico costa
Accounting assignment frederico costaFrederico Costa
 
financial management stock valuation chapter solution ...MOHSIN MUMTAZ
financial management stock valuation chapter solution ...MOHSIN MUMTAZfinancial management stock valuation chapter solution ...MOHSIN MUMTAZ
financial management stock valuation chapter solution ...MOHSIN MUMTAZ
mianmohsinmumtazshb
 
Equity valuation pdf
Equity valuation pdfEquity valuation pdf
Equity valuation pdf
David Keck
 
Fin 515 week 6
Fin 515 week 6Fin 515 week 6
Fin 515 week 6ecambry
 
Portfolio Risk and Return
Portfolio Risk and ReturnPortfolio Risk and Return
Portfolio Risk and Return
student_of_finance
 
Free Cash Flow
Free Cash FlowFree Cash Flow
Free Cash Flowyatili
 

What's hot (18)

Fm11 ch 09 show
Fm11 ch 09 showFm11 ch 09 show
Fm11 ch 09 show
 
Npv rule
Npv ruleNpv rule
Npv rule
 
Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2
 
Ch12ppt
Ch12pptCh12ppt
Ch12ppt
 
ch 10; cost of capital
ch 10; cost of capitalch 10; cost of capital
ch 10; cost of capital
 
Finanzas Coporativas
Finanzas CoporativasFinanzas Coporativas
Finanzas Coporativas
 
Equity Valuation
Equity ValuationEquity Valuation
Equity Valuation
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
economy Chapter7_by louy Al hami
economy Chapter7_by louy Al hamieconomy Chapter7_by louy Al hami
economy Chapter7_by louy Al hami
 
Fisher's rate intersection - In Capital Budgeting - NPV and IRR
Fisher's rate intersection - In Capital Budgeting - NPV and IRRFisher's rate intersection - In Capital Budgeting - NPV and IRR
Fisher's rate intersection - In Capital Budgeting - NPV and IRR
 
Chapter10solutions
Chapter10solutionsChapter10solutions
Chapter10solutions
 
Chap 4.pdf beta
Chap 4.pdf betaChap 4.pdf beta
Chap 4.pdf beta
 
Accounting assignment frederico costa
Accounting assignment frederico costaAccounting assignment frederico costa
Accounting assignment frederico costa
 
financial management stock valuation chapter solution ...MOHSIN MUMTAZ
financial management stock valuation chapter solution ...MOHSIN MUMTAZfinancial management stock valuation chapter solution ...MOHSIN MUMTAZ
financial management stock valuation chapter solution ...MOHSIN MUMTAZ
 
Equity valuation pdf
Equity valuation pdfEquity valuation pdf
Equity valuation pdf
 
Fin 515 week 6
Fin 515 week 6Fin 515 week 6
Fin 515 week 6
 
Portfolio Risk and Return
Portfolio Risk and ReturnPortfolio Risk and Return
Portfolio Risk and Return
 
Free Cash Flow
Free Cash FlowFree Cash Flow
Free Cash Flow
 

Similar to Fm11 ch 10 show

Captial bugting
Captial bugtingCaptial bugting
Captial bugting3prem
 
The_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptThe_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.ppt
FilyanFAnggriawan
 
ch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.ppt
ch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.pptch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.ppt
ch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.ppt
joycho11
 
Chapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxChapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptx
JaylouAguilar1
 
Capital budgeting unit_2
Capital budgeting unit_2Capital budgeting unit_2
Capital budgeting unit_2
PrasannaKumar848
 
capital budgeting In financial management
capital budgeting In financial managementcapital budgeting In financial management
capital budgeting In financial management
ssuserc3bdcc
 
ChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital BudgetingChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital Budgeting
JinElias52
 
0273685988 ch13
0273685988 ch130273685988 ch13
0273685988 ch13123chacko
 
Fm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysisFm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysisNhu Tuyet Tran
 
Chap009
Chap009Chap009
Chap009LUXSVB
 
Chapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxChapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptx
Saif Uddin
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniquesIan Isabel
 

Similar to Fm11 ch 10 show (20)

Captial bugting
Captial bugtingCaptial bugting
Captial bugting
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
The_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptThe_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.ppt
 
ch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.ppt
ch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.pptch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.ppt
ch1 078ugytfg877t78tyu8yg8y87y87y87y89y89y89y8y.ppt
 
Chapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxChapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptx
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Capital budgeting unit_2
Capital budgeting unit_2Capital budgeting unit_2
Capital budgeting unit_2
 
Irr(1)
Irr(1)Irr(1)
Irr(1)
 
capital budgeting In financial management
capital budgeting In financial managementcapital budgeting In financial management
capital budgeting In financial management
 
Cap budget [autosaved]
Cap budget [autosaved]Cap budget [autosaved]
Cap budget [autosaved]
 
ChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital BudgetingChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital Budgeting
 
CAPITAL BUDGETING TECHNIQUES
CAPITAL BUDGETING TECHNIQUESCAPITAL BUDGETING TECHNIQUES
CAPITAL BUDGETING TECHNIQUES
 
0273685988 ch13
0273685988 ch130273685988 ch13
0273685988 ch13
 
Fm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysisFm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysis
 
Cbt
CbtCbt
Cbt
 
Chap009
Chap009Chap009
Chap009
 
Chapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxChapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptx
 
Text solu2
Text solu2Text solu2
Text solu2
 
0273685988 ch13
0273685988 ch130273685988 ch13
0273685988 ch13
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniques
 

More from Adi Susilo

Fm11 ch 20 show
Fm11 ch 20 showFm11 ch 20 show
Fm11 ch 20 show
Adi Susilo
 
Fm11 ch 19 show
Fm11 ch 19 showFm11 ch 19 show
Fm11 ch 19 show
Adi Susilo
 
Fm11 ch 18 show
Fm11 ch 18 showFm11 ch 18 show
Fm11 ch 18 show
Adi Susilo
 
Fm11 ch 17 show
Fm11 ch 17 showFm11 ch 17 show
Fm11 ch 17 show
Adi Susilo
 
Fm11 ch 16 show
Fm11 ch 16 showFm11 ch 16 show
Fm11 ch 16 show
Adi Susilo
 
Fm11 ch 15 show
Fm11 ch 15 showFm11 ch 15 show
Fm11 ch 15 show
Adi Susilo
 
Fm11 ch 12 show
Fm11 ch 12 showFm11 ch 12 show
Fm11 ch 12 show
Adi Susilo
 
Fm11 ch 08 show
Fm11 ch 08 showFm11 ch 08 show
Fm11 ch 08 show
Adi Susilo
 
Fm11 ch 07 show
Fm11 ch 07 showFm11 ch 07 show
Fm11 ch 07 show
Adi Susilo
 
Fm11 ch 06 show
Fm11 ch 06 showFm11 ch 06 show
Fm11 ch 06 show
Adi Susilo
 
Fm11 ch 05 show
Fm11 ch 05 showFm11 ch 05 show
Fm11 ch 05 show
Adi Susilo
 
Fm11 ch 04 show
Fm11 ch 04 showFm11 ch 04 show
Fm11 ch 04 show
Adi Susilo
 
Fm11 ch 03 show
Fm11 ch 03 showFm11 ch 03 show
Fm11 ch 03 show
Adi Susilo
 
Fm11 ch 02 show
Fm11 ch 02 showFm11 ch 02 show
Fm11 ch 02 show
Adi Susilo
 
Fm11 ch 01 show
Fm11 ch 01 showFm11 ch 01 show
Fm11 ch 01 show
Adi Susilo
 

More from Adi Susilo (15)

Fm11 ch 20 show
Fm11 ch 20 showFm11 ch 20 show
Fm11 ch 20 show
 
Fm11 ch 19 show
Fm11 ch 19 showFm11 ch 19 show
Fm11 ch 19 show
 
Fm11 ch 18 show
Fm11 ch 18 showFm11 ch 18 show
Fm11 ch 18 show
 
Fm11 ch 17 show
Fm11 ch 17 showFm11 ch 17 show
Fm11 ch 17 show
 
Fm11 ch 16 show
Fm11 ch 16 showFm11 ch 16 show
Fm11 ch 16 show
 
Fm11 ch 15 show
Fm11 ch 15 showFm11 ch 15 show
Fm11 ch 15 show
 
Fm11 ch 12 show
Fm11 ch 12 showFm11 ch 12 show
Fm11 ch 12 show
 
Fm11 ch 08 show
Fm11 ch 08 showFm11 ch 08 show
Fm11 ch 08 show
 
Fm11 ch 07 show
Fm11 ch 07 showFm11 ch 07 show
Fm11 ch 07 show
 
Fm11 ch 06 show
Fm11 ch 06 showFm11 ch 06 show
Fm11 ch 06 show
 
Fm11 ch 05 show
Fm11 ch 05 showFm11 ch 05 show
Fm11 ch 05 show
 
Fm11 ch 04 show
Fm11 ch 04 showFm11 ch 04 show
Fm11 ch 04 show
 
Fm11 ch 03 show
Fm11 ch 03 showFm11 ch 03 show
Fm11 ch 03 show
 
Fm11 ch 02 show
Fm11 ch 02 showFm11 ch 02 show
Fm11 ch 02 show
 
Fm11 ch 01 show
Fm11 ch 01 showFm11 ch 01 show
Fm11 ch 01 show
 

Recently uploaded

^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
mayaclinic18
 
Applying the Global Internal Audit Standards_AIS.pdf
Applying the Global Internal Audit Standards_AIS.pdfApplying the Global Internal Audit Standards_AIS.pdf
Applying the Global Internal Audit Standards_AIS.pdf
alexiusbrian1
 
What price will pi network be listed on exchanges
What price will pi network be listed on exchangesWhat price will pi network be listed on exchanges
What price will pi network be listed on exchanges
DOT TECH
 
5 Tips for Creating Standard Financial Reports
5 Tips for Creating Standard Financial Reports5 Tips for Creating Standard Financial Reports
5 Tips for Creating Standard Financial Reports
EasyReports
 
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
muslimdavidovich670
 
Intro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptxIntro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptx
shetivia
 
where can I find a legit pi merchant online
where can I find a legit pi merchant onlinewhere can I find a legit pi merchant online
where can I find a legit pi merchant online
DOT TECH
 
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt FinancingHow Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
Vighnesh Shashtri
 
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理
bbeucd
 
Donald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptxDonald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptx
SerdarHudaykuliyew
 
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFiTdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
nimaruinazawa258
 
G20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summitG20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summit
rohitsaxena882511
 
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptxSWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designs
egoetzinger
 
can I really make money with pi network.
can I really make money with pi network.can I really make money with pi network.
can I really make money with pi network.
DOT TECH
 
WhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller Coaster
WhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller CoasterWhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller Coaster
WhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller Coaster
muslimdavidovich670
 
2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf
Neal Brewster
 
STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...
STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...
STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...
sameer shah
 
APP I Lecture Notes to students 0f 4the year
APP I  Lecture Notes  to students 0f 4the yearAPP I  Lecture Notes  to students 0f 4the year
APP I Lecture Notes to students 0f 4the year
telilaalilemlem
 

Recently uploaded (20)

^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
^%$Zone1:+971)581248768’][* Legit & Safe #Abortion #Pills #For #Sale In #Duba...
 
Applying the Global Internal Audit Standards_AIS.pdf
Applying the Global Internal Audit Standards_AIS.pdfApplying the Global Internal Audit Standards_AIS.pdf
Applying the Global Internal Audit Standards_AIS.pdf
 
What price will pi network be listed on exchanges
What price will pi network be listed on exchangesWhat price will pi network be listed on exchanges
What price will pi network be listed on exchanges
 
5 Tips for Creating Standard Financial Reports
5 Tips for Creating Standard Financial Reports5 Tips for Creating Standard Financial Reports
5 Tips for Creating Standard Financial Reports
 
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
The WhatsPump Pseudonym Problem and the Hilarious Downfall of Artificial Enga...
 
Intro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptxIntro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptx
 
where can I find a legit pi merchant online
where can I find a legit pi merchant onlinewhere can I find a legit pi merchant online
where can I find a legit pi merchant online
 
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt FinancingHow Non-Banking Financial Companies Empower Startups With Venture Debt Financing
How Non-Banking Financial Companies Empower Startups With Venture Debt Financing
 
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
 
一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB毕业证)圣芭芭拉分校毕业证如何办理
 
Donald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptxDonald Trump Presentation and his life.pptx
Donald Trump Presentation and his life.pptx
 
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFiTdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
 
G20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summitG20 summit held in India. Proper presentation for G20 summit
G20 summit held in India. Proper presentation for G20 summit
 
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptxSWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designs
 
can I really make money with pi network.
can I really make money with pi network.can I really make money with pi network.
can I really make money with pi network.
 
WhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller Coaster
WhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller CoasterWhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller Coaster
WhatsPump Thriving in the Whirlwind of Biden’s Crypto Roller Coaster
 
2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf
 
STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...
STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...
STREETONOMICS: Exploring the Uncharted Territories of Informal Markets throug...
 
APP I Lecture Notes to students 0f 4the year
APP I  Lecture Notes  to students 0f 4the yearAPP I  Lecture Notes  to students 0f 4the year
APP I Lecture Notes to students 0f 4the year
 

Fm11 ch 10 show

  • 1. 10 - 1 Chapter 10: The Basics of Capital Budgeting: Evaluating Cash Flows Overview and “vocabulary” Methods Payback, discounted payback NPV IRR, MIRR Profitability Index Unequal lives Economic life
  • 2. 10 - 2 What is capital budgeting? Analysis of potential projects. Long-term decisions; involve large expenditures. Very important to firm’s future.
  • 3. 10 - 3 Steps in Capital Budgeting Estimate cash flows (inflows & outflows). Assess risk of cash flows. Determine r = WACC for project. Evaluate cash flows.
  • 4. 10 - 4 What is the difference between independent and mutually exclusive projects? Projects are: independent, if the cash flows of one are unaffected by the acceptance of the other. mutually exclusive, if the cash flows of one can be adversely impacted by the acceptance of the other.
  • 5. 10 - 5 What is the payback period? The number of years required to recover a project’s cost, or how long does it take to get the business’s money back?
  • 6. 10 - 6 Payback for Franchise L (Long: Most CFs in out years) 10 8060 0 1 2 3 -100 = CFt Cumulative -100 -90 -30 50 PaybackL 2 + 30/80 = 2.375 years 0 100 2.4
  • 7. 10 - 7 Franchise S (Short: CFs come quickly) 70 2050 0 1 2 3 -100CFt Cumulative -100 -30 20 40 PaybackS 1 + 30/50 = 1.6 years 100 0 1.6 =
  • 8. 10 - 8 Strengths of Payback: 1. Provides an indication of a project’s risk and liquidity. 2. Easy to calculate and understand. Weaknesses of Payback: 1. Ignores the TVM. 2. Ignores CFs occurring after the payback period.
  • 9. 10 - 9 10 8060 0 1 2 3 CFt Cumulative -100 -90.91 -41.32 18.79 Discounted payback 2 + 41.32/60.11 = 2.7 yrs Discounted Payback: Uses discounted rather than raw CFs. PVCFt -100 -100 10% 9.09 49.59 60.11 = Recover invest. + cap. costs in 2.7 yrs.
  • 10. 10 - 10 ( ) . 10 t t n t r CF NPV + = ∑= NPV: Sum of the PVs of inflows and outflows. Cost often is CF0 and is negative. ( ) . 1 0 1 CF r CF NPV t t n t − + = ∑=
  • 11. 10 - 11 What’s Franchise L’s NPV? 10 8060 0 1 2 3 10% Project L: -100.00 9.09 49.59 60.11 18.79 = NPVL NPVS = $19.98.
  • 12. 10 - 12 Calculator Solution Enter in CFLO for L: -100 10 60 80 10 CF0 CF1 NPV CF2 CF3 I = 18.78 = NPVL
  • 13. 10 - 13 Rationale for the NPV Method NPV = PV inflows - Cost = Net gain in wealth. Accept project if NPV > 0. Choose between mutually exclusive projects on basis of higher NPV. Adds most value.
  • 14. 10 - 14 Using NPV method, which franchise(s) should be accepted? If Franchise S and L are mutually exclusive, accept S because NPVs > NPVL . If S & L are independent, accept both; NPV > 0.
  • 15. 10 - 15 Internal Rate of Return: IRR 0 1 2 3 CF0 CF1 CF2 CF3 Cost Inflows IRR is the discount rate that forces PV inflows = cost. This is the same as forcing NPV = 0.
  • 16. 10 - 16 ( ) . 10 NPV r CF t t n t = + ∑= ( )t n t t CF IRR= ∑ + = 0 1 0. NPV: Enter r, solve for NPV. IRR: Enter NPV = 0, solve for IRR.
  • 17. 10 - 17 What’s Franchise L’s IRR? 10 8060 0 1 2 3 IRR = ? -100.00 PV3 PV2 PV1 0 = NPV Enter CFs in CFLO, then press IRR: IRRL = 18.13%. IRRS = 23.56%.
  • 18. 10 - 18 40 4040 0 1 2 3 IRR = ? Find IRR if CFs are constant: -100 Or, with CFLO, enter CFs and press IRR = 9.70%. 3 -100 40 0 9.70% N I/YR PV PMT FV INPUTS OUTPUT
  • 19. 10 - 19 Rationale for the IRR Method If IRR > WACC, then the project’s rate of return is greater than its cost-- some return is left over to boost stockholders’ returns. Example: WACC = 10%, IRR = 15%. Profitable.
  • 20. 10 - 20 Decisions on Projects S and L per IRR If S and L are independent, accept both. IRRs > r = 10%. If S and L are mutually exclusive, accept S because IRRS > IRRL .
  • 21. 10 - 21 Construct NPV Profiles Enter CFs in CFLO and find NPVL and NPVS at different discount rates: r 0 5 10 15 20 NPVL 50 33 19 7 NPVS 40 29 20 12 5(4)
  • 22. 10 - 22 -10 0 10 20 30 40 50 60 0 5 10 15 20 23.6 NPV ($) Discount Rate (%) IRRL = 18.1% IRRS = 23.6% Crossover Point = 8.7% r 0 5 10 15 20 NPVL 50 33 19 7 (4) NPVS 40 29 20 12 5 S L
  • 23. 10 - 23 NPV and IRR always lead to the same accept/reject decision for independent projects: r > IRR and NPV < 0. Reject. NPV ($) r (%) IRR IRR > r and NPV > 0 Accept.
  • 24. 10 - 24 Mutually Exclusive Projects r 8.7 r NPV % IRRS IRRL L S r < 8.7: NPVL> NPVS , IRRS > IRRL CONFLICT r > 8.7: NPVS> NPVL , IRRS > IRRL NO CONFLICT
  • 25. 10 - 25 To Find the Crossover Rate 1. Find cash flow differences between the projects. See data at beginning of the case. 2. Enter these differences in CFLO register, then press IRR. Crossover rate = 8.68%, rounded to 8.7%. 3. Can subtract S from L or vice versa, but better to have first CF negative. 4. If profiles don’t cross, one project dominates the other.
  • 26. 10 - 26 Two Reasons NPV Profiles Cross 1. Size (scale) differences. Smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so high r favors small projects. 2. Timing differences. Project with faster payback provides more CF in early years for reinvestment. If r is high, early CF especially good, NPVS > NPVL.
  • 27. 10 - 27 Reinvestment Rate Assumptions NPV assumes reinvest at r (opportunity cost of capital). IRR assumes reinvest at IRR. Reinvest at opportunity cost, r, is more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.
  • 28. 10 - 28 Managers like rates--prefer IRR to NPV comparisons. Can we give them a better IRR? Yes, MIRR is the discount rate which causes the PV of a project’s terminal value (TV) to equal the PV of costs. TV is found by compounding inflows at WACC. Thus, MIRR assumes cash inflows are reinvested at WACC.
  • 29. 10 - 29 MIRR = 16.5% 10.0 80.060.0 0 1 2 3 10% 66.0 12.1 158.1 MIRR for Franchise L (r = 10%) -100.0 10% 10% TV inflows-100.0 PV outflows MIRRL = 16.5% $100 = $158.1 (1+MIRRL)3
  • 30. 10 - 30 To find TV with 10B, enter in CFLO: I = 10NPV = 118.78 = PV of inflows. Enter PV = -118.78, N = 3, I = 10, PMT = 0. Press FV = 158.10 = FV of inflows.Enter FV = 158.10, PV = -100, PMT = 0, N = 3. Press I = 16.50% = MIRR. CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80
  • 31. 10 - 31 Why use MIRR versus IRR? MIRR correctly assumes reinvestment at opportunity cost = WACC. MIRR also avoids the problem of multiple IRRs. Managers like rate of return comparisons, and MIRR is better for this than IRR.
  • 32. 10 - 32 Normal Cash Flow Project: Cost (negative CF) followed by a series of positive cash inflows. One change of signs. Nonnormal Cash Flow Project: Two or more changes of signs. Most common: Cost (negative CF), then string of positive CFs, then cost to close project. Nuclear power plant, strip mine.
  • 33. 10 - 33 Inflow (+) or Outflow (-) in Year 0 1 2 3 4 5 N NN - + + + + + N - + + + + - NN - - - + + + N + + + - - - N - + + - + - NN
  • 34. 10 - 34 Pavilion Project: NPV and IRR? 5,000 -5,000 0 1 2 r = 10% -800 Enter CFs in CFLO, enter I = 10. NPV = -386.78 IRR = ERROR. Why?
  • 35. 10 - 35 We got IRR = ERROR because there are 2 IRRs. Nonnormal CFs--two sign changes. Here’s a picture: NPV Profile 450 -800 0 400100 IRR2 = 400% IRR1 = 25% r NPV
  • 36. 10 - 36 Logic of Multiple IRRs 1. At very low discount rates, the PV of CF2 is large & negative, so NPV < 0. 2. At very high discount rates, the PV of both CF1 and CF2 are low, so CF0 dominates and again NPV < 0. 3. In between, the discount rate hits CF2 harder than CF1, so NPV > 0. 4. Result: 2 IRRs.
  • 37. 10 - 37 Could find IRR with calculator: 1. Enter CFs as before. 2. Enter a “guess” as to IRR by storing the guess. Try 10%: 10 STO IRR = 25% = lower IRR Now guess large IRR, say, 200: 200 STO IRR = 400% = upper IRR
  • 38. 10 - 38 When there are nonnormal CFs and more than one IRR, use MIRR: 0 1 2 -800,000 5,000,000 -5,000,000 PV outflows @ 10% = -4,932,231.40. TV inflows @ 10% = 5,500,000.00. MIRR = 5.6%
  • 39. 10 - 39 Accept Project P? NO. Reject because MIRR = 5.6% < r = 10%. Also, if MIRR < r, NPV will be negative: NPV = -$386,777.
  • 40. 10 - 40 S and L are mutually exclusive and will be repeated. r = 10%. Which is better? (000s) 0 1 2 3 4 Project S: (100) Project L: (100) 60 33.5 60 33.5 33.5 33.5
  • 41. 10 - 41 S L CF0 -100,000 -100,000 CF1 60,000 33,500 Nj 2 4 I 10 10 NPV 4,132 6,190 NPVL > NPVS. But is L better? Can’t say yet. Need to perform common life analysis.
  • 42. 10 - 42 Note that Project S could be repeated after 2 years to generate additional profits. Can use either replacement chain or equivalent annual annuity analysis to make decision.
  • 43. 10 - 43 Franchise S with Replication: NPV = $7,547. Replacement Chain Approach (000s) 0 1 2 3 4 Franchise S: (100) (100) 60 60 60 (100) (40) 60 60 60 60
  • 44. 10 - 44 Compare to Franchise L NPV = $6,190. Or, use NPVs: 0 1 2 3 4 4,132 3,415 7,547 4,132 10%
  • 45. 10 - 45 If the cost to repeat S in two years rises to $105,000, which is best? (000s) NPVS = $3,415 < NPVL = $6,190. Now choose L. 0 1 2 3 4 Franchise S: (100) 60 60 (105) (45) 60 60
  • 46. 10 - 46 Year 0 1 2 3 CF ($5,000) 2,100 2,000 1,750 Salvage Value $5,000 3,100 2,000 0 Consider another project with a 3-year life. If terminated prior to Year 3, the machinery will have positive salvage value.
  • 47. 10 - 47 1.751. No termination 2. Terminate 2 years 3. Terminate 1 year (5) (5) (5) 2.1 2.1 5.2 2 4 0 1 2 3 CFs Under Each Alternative (000s)
  • 48. 10 - 48 NPV(no) = -$123. NPV(2) = $215. NPV(1) = -$273. Assuming a 10% cost of capital, what is the project’s optimal, or economic life?
  • 49. 10 - 49 The project is acceptable only if operated for 2 years. A project’s engineering life does not always equal its economic life. Conclusions
  • 50. 10 - 50 Choosing the Optimal Capital Budget Finance theory says to accept all positive NPV projects. Two problems can occur when there is not enough internally generated cash to fund all positive NPV projects: An increasing marginal cost of capital. Capital rationing
  • 51. 10 - 51 Increasing Marginal Cost of Capital Externally raised capital can have large flotation costs, which increase the cost of capital. Investors often perceive large capital budgets as being risky, which drives up the cost of capital. (More...)
  • 52. 10 - 52 If external funds will be raised, then the NPV of all projects should be estimated using this higher marginal cost of capital.
  • 53. 10 - 53 Capital Rationing Capital rationing occurs when a company chooses not to fund all positive NPV projects. The company typically sets an upper limit on the total amount of capital expenditures that it will make in the upcoming year. (More...)
  • 54. 10 - 54 Reason: Companies want to avoid the direct costs (i.e., flotation costs) and the indirect costs of issuing new capital. Solution: Increase the cost of capital by enough to reflect all of these costs, and then accept all projects that still have a positive NPV with the higher cost of capital. (More...)
  • 55. 10 - 55 Reason: Companies don’t have enough managerial, marketing, or engineering staff to implement all positive NPV projects. Solution: Use linear programming to maximize NPV subject to not exceeding the constraints on staffing. (More...)
  • 56. 10 - 56 Reason: Companies believe that the project’s managers forecast unreasonably high cash flow estimates, so companies “filter” out the worst projects by limiting the total amount of projects that can be accepted. Solution: Implement a post-audit process and tie the managers’ compensation to the subsequent performance of the project.