SlideShare a Scribd company logo
1 of 64
Download to read offline
Evaluating a Single project
                              1
Introduction
In this chapter we will answer the following
  question :

 Whether a proposed capital and its expenditures
 can recovered by revenue over time in addition
 to a return on the capital sufficiently attractive in
 view of the risks .




                                                         2
Methods of Evaluating the
Economic Profitability of a
Problem Solution
 Present Worth ( PW )
 Future Worth ( FW )
 Annual Worth ( AW )
 Internal Rate of Return ( IRR )
 External Rate of Return ( ERR )




                                    3
Assumptions
1. We know the future with certainty
2. We can borrow and lend with the same i%.




                                              4
The most-used method is the
present worth method.
 The present worth (PW) is found by
 discounting all cash inflows and
 outflows to the present time at an
 interest rate that is generally the
 MARR.
 A positive PW for an investment
 project means that the project is
 acceptable (it satisfies the MARR).


                                       5
Present Worth ( PW )


                                         Eq..(5-1)
 =F0(1+i)0+F1(1+i)-1+F2(1+i)-2+………..+FN(1+i)-N



 i = effective interest rate or MARR
 K = index of each compounding period
 Fk = future cash flow at the end of period k
 N = # of compounded periods .                      6
 PW Decision Rule:


If PW (i=MARR) ≥ 0 , the project is economically
   justified




                                                   7
Note
 The higher the interest rate and the further into the
  future a cash flow occurs , the lower its PW is
 See figure 5-2
 PW of 1,000 10 years from now i =5% is $613.90
 PW of 1,000 10years from now i=10% is $385.5




                                                          8
Figure 5-2




             9
Example(PW)
Consider a project that has an initial
investment of $50,000 and that returns
$18,000 per year for the next four years.
If the MARR is 12%, is this a good
investment?
 PW = -50,000 + 18,000 (P/A, 12%, 4)
 PW = -50,000 + 18,000 (3.0373)
PW = $4,671.40  This is a good investment!

                                              10
 Example 5.1:


 A piece of new equipment has been proposed by engineers to
 increase the productivity of a certain manual welding
 operation. The investment cost $25,000 and the equipment
 will have a market value of $5,000 at the end of a study
 period of five years. Increased productivity attributable to the
 equipment will amount to $8,000 per year after extra
 operating costs have been subtracted from the revenue
 generated by the additional production. A cash flow diagram
 for this investment opportunity is given below. If the firm’s
 MARR is 20% per year, is this proposal a sound one? Use the
 PW method.

                                                             11
 Example. 5-1




 PW = PW(inflows) – PW (outflows)
 PW= $8,000(P/A,20%,5) +$5,000(P/F,20%,5)-$25,000
 PW= $934,29

                                                     12
Bond Value
 The value of the bond at any time is the PW of
   future cash receipts
 Two types of payments
1. Series of periodic interest payments (rZ)
2. A single payment = C ,When the bond is sold or
   retired .




                                                    13
VN = C(P/F, i%, N) + rZ (P/A, i%,N) Eq.5-2
  Z= Face ,or parValue,
  C = redemption or disposal price (usually = Z).
  r = bond rate (nominal interest) per interest period
  N= # of periods before redemption
  i = bond yield rate per period
  VN = PW




                                                          14
15
Example5-4




             16
The Capitalized-Worth Method
  A special variation of the PW
  To find PW for infinite length of time
  N ∞
       CW = PWN  ∞          = A ( P / A, i%, ∞ )

                  ( 1+i )N - 1
  =    A lim   ------------------   =A ( 1 / i )=A/i
           N
              ∞ i ( 1 + i )N



                                                       17
Ex. 5-5 page 219




                   18
(a)As we discussed before when N= ∞
  (p/A,i%,N)=1/i, then
   (p/A,8%,N)=1/0.08 = 12.5
go to App.C then N= 100 this assumed
  as (∞ )




                                       19
Ex. 5-5 page 219



   (b)
                                        30,000 20,000 A / F ,8%,4)
                                                      (
   CW  (100000 A / P,8%, )) / .08
             ,  (
                                                   0.08


                       30,000  20,000 ( A / F ,8%,4) 
      CW  100,000                                    $530,475
                                   0.08               




                                                                       20
Future Worth ( FW )
 Equivalent worth of all cash flows (In& Out) at the end of the
 planning horizon at MARR

                                        Eq.(5-3)

 i = effective interest rate or MARR
 K = index of each compounding period
 Fk = future cash flow at the end of period k
 N = # of compounded periods .



                                                            21
 FW Decision Rule:


If FW (i=MARR) ≥ 0 , the project is economically
   justified




                                                   22
 Ex 5-6 page 221




                    23
Example5-7




             24
The Annual Worth Method
 Annual worth is an equal periodic series of dollar amounts
  that is equivalent to the cash inflows and outflows, at an
  interest rate that is generally the MARR.
 The AW of a project is annual equivalent revenue or savings
  minus annual equivalent expenses, less its annual capital
  recovery (CR) amount.
 AW(i%) = R – E – CR(i%)
 R = Annual equivalent Revenue or saving
 E = Annual equivalent Expenses
 CR = Annual equivalent Capital Recovery amount


                                                                25
 AW Decision Rule:


If AW (i=MARR) ≥ 0 , the project is economically
   justified




                                                   26
CR (Capital Recovery)
  CR is the equivalent uniform annual cost of the capital
    invested that covers
 1. Loss of value of the asset.
 2. Interest on invested capital (at MARR)




                                                        27
CR
 CR (i%) = I(A/P, i%, N) – S(A/F, i%,N) Eq. 5-5
 I = initial investment for project
 S = salvage (market) value at the end of the study
  period
 N = project study period




                                                       28
 CR (i%) = (I – S)(A/F, i%, N) +I(i%)
 CR (i%) = (I –S)(A/P, i%, N) + S(i%)




                                         29
Example 5-8 page 224




                       30
Example 5-9




              31
Example 5-10




               32
Example 5-11




               33
A project requires an initial investment of
$45,000, has a salvage value of $12,000 after
six years, incurs annual expenses of $6,000,
and provides an annual revenue of $18,000.
Using a MARR of 10%, determine the AW of
this project.




 Since the AW is positive, it’s a good
 investment.
                                                34
Internal Rate Of Return Method ( IRR )

 IRR solves for the interest rate that equates the equivalent
  worth of an alternative’s cash inflows (receipts or savings) to
  the equivalent worth of cash outflows (expenditures)

 IRR is positive for a single alternative only if:
    both receipts and expenses are present in the cash flow
     diagram
    the sum of inflows exceeds the sum of outflows




                                                               35
Internal Rate of Return
 It is also called the investor’s method, the discounted
  cash flow method, and the profitability index.
 If the IRR for a project is greater than the MARR, then
  the project is acceptable.




                                                            36
INTERNAL RATE OF RETURN METHOD ( IRR )


  IRR is i’ %, using the following PW formula:



     R k = net revenues or savings for the kth year
     E k = net expenditures including investment costs for the
   kth year
     N = project life ( or study period )

 Note: FW or AW can be used instead of PW

                                                           37
Solving for the IRR is a bit more
complicated than PW, FW, or AW
 The method of solving for the i'% that equates
 revenues and expenses normally involves trial-and-
 error calculations, or solving numerically using
 mathematical software.




                                                      38
39
40
Installment Financing
 An application of IRR method
 Ex.5-14 will be discussed




                                 41
42
43
44
45
46
47
Challenges in Applying the IRR
Method.
 It is computationally difficult without proper tools.


 In rare instances multiple rates of return can be
  found(take a look to page 255 example 5-A-1).

 The IRR method must be carefully applied and
  interpreted when comparing two more mutually
  exclusive alternatives (e.g., do not directly compare
  internal rates of return).

                                                          48
The External Rate Of Return Method ( ERR )

 ERR directly takes into account the interest rate
(  ) external to a project at which net cash flows
  generated over the project life can be reinvested
  (or borrowed ).
 If the external reinvestment rate, usually the
  firm’s MARR, equals the IRR, then ERR method
  produces same results as IRR method


                                                  49
Calculating External Rate of Return ( ERR )

1. All net cash outflows are discounted to the present (time 0) at ε%
   per compounding period.
2. All net cash inflows are discounted to period N at ε %.
3. Solve for the ERR, the interest rate that establishes equivalence
    between the two quantities.
  The absolute value of the present equivalent worth of the net cash
   outflows at ε % is used in step 3.
 A project is acceptable when i ‘ % of the ERR method is greater
   than or equal to the firm’s MARR




                                                                    50
ERR is the i'% at which



 where
   Rk   =   excess of receipts over expenses in period k,
   Ek   =   excess of expenses over receipts in period k,
   N    =   project life or number of periods, and
   ε    =   external reinvestment rate per period.



                                                            51
Calculating External Rate of Return ( ERR )




                                                  2
                                              N
                                               R ( F / P,  %, N - k )
                                          k = 0k
                               0
                 1                 Time   N
        N
        E     ( P / F,  %, k )
       k=0 k                                                     52
Calculating External Rate of Return ( ERR )




                                                             2
                                                3        N
                                                          R ( F / P,  %, N - k )
                                                     k = 0k
                              0           i ‘ %= ?
                1                           Time     N
        N
         Ek ( P / F,  %, k ) ( F / P, i ‘ %, N )
       k=0                                                                  53
Example 5-17




  $25,000 (F/P,i’%,5)=$8,000(F/A,20%,5)+$5,000
  (F/P,i’%,5)= $64,532.80  2.5813  (1  i ' )5
                  $25,000
  i’ =20.88%
                                                    54
Example 5-18




               55
Example
For the cash flows given below, find the ERR when the
external reinvestment rate is ε = 12% (equal to the MARR).
Year           0         1         2         3          4
Cash Flow   -$15,000   -$7,000   $10,000   $10,000   $10,000

Expenses

Revenue

Solving, we find




                                                               56
The payback period method

  The simple payback period is the number of years
   required for cash inflows to just equal cash outflows.

  It is a measure of liquidity rather than a measure of
   profitability.




                                                            57
Payback is simple to calculate.
 The payback period is the smallest value of θ (θ ≤ N) for
 which the relationship below is satisfied.




For discounted payback future cash flows are discounted
back to the present, so the relationship to satisfy becomes




                                                              58
 A low- valued pay back period is considered desirable




                                                          59
Finding the simple        End
                                 End of
                                            Net      Cumulat    Present    Cumulati
                           of              Cash      ive PW     worth at   ve PW at
and discounted            Year
                                  Year
                                           Flow       at 0%      i = 6%       6%
payback period for a
set of cash flows.         0       0      -$42,000   -$42,000   -$42,000   -$42,000

The cumulative cash
                           1       1      $12,000    -$30,000   11,320.8   -$30,679
flows in the table were
calculated using the
formulas for simple        2       2      $11,000    -$19,000    9,790     -$20,889

and discounted
payback.                   3       3      $10,000    -$9,000     8,396     -$12,493


From the calculations      4       4      $10,000    $1,000      7,921     -$4,572

θ = 4 years and θ' = 5
years.                     5       5      $9,000                6,725.7     $2,153



                                                                              60
Col.3:
EOF1= -42,000-12,000=-30,000         End of Net Cash Cumulative Cumulative
                                     End     Net   Cumulat Present Cumulati
                                      Year Cash
                                      of       Flow ive PW at 0% at PW at 6%
                                                         PW worth    ve PW at
EOF2 : 11,000-30,000=-19,000         Year   Flow     at 0%   i = 6%     6%
EOF3 : 10,000-19,000=-9,000
                                      00   -$42,000 -$42,000 -$42,000 -$42,000
                                              -$42,000     -$42,000     -$42,000
EOF4 : 10,000-9,000=1,000>0
θ=4
Col.4:                                11   $12,000 -$30,000 11,320.8 -$30,679
                                              $12,000     -$30,000     -$30,679
12,000 (p/F,6%,1) =
12,000* 0.9434= 113,208               22      $11,000     -$19,000
                                           $11,000 -$19,000     9,790     -$20,889
                                                                            -$20,889
11,000 (p/F,6%,2) = 11,000*0.8900=
9,790
                                      33      $10,000
                                           $10,000 -$9,000-$9,000
                                                                8,396     -$12,493
                                                                            -$12,493
10,000*(P/F,6%,3) =
10,000*0.8396= 8,396
                                      44      $10,000$1,000 $1,000
                                           $10,000               7,921    -$4,572
                                                                            -$4,572
10,000*(P/F,6%,4) =
10,000*0.7921 =7,921
9,000*(P/F,6%,5) =                    55       $9,000
                                           $9,000               6,725.7   $2,153
                                                                           $2,153
9,000*0.7473 = 6,725.7

                                                                                61
End      Net     Cumulat    Present    Cumulati
Col.5:                             of     Cash     ive PW     worth at   ve PW at
                                  Year    Flow      at 0%      i = 6%       6%
EOF1:
 -42,000 + 11,320.8 = -30,679.2    0     -$42,000 -$42,000    -$42,000   -$42,000

EOF2 :
                                   1     $12,000   -$30,000   11,320.8   -$30,679
9,790 -30,679.2 = -20,889.2
EOF3 :
                                   2     $11,000   -$19,000    9,790     -$20,889
8,396 -20,889.2 = -12,493.2
EOF4 :                             3     $10,000   -$9,000     8,396     -$12,493
7,921-12,493.2 = -4,572.2 <0
EOF5 :                             4     $10,000   $1,000      7,921     -$4,572
6,725.7 -4,572.2 = 2,153.5 >0
                                   5     $9,000               6,725.7     $2,153



                                                                             62
Problems with the payback period method.

 It doesn’t reflect any cash flows occurring after θ, or θ'.


 It doesn’t indicate anything about project desirability except
  the speed with which the initial investment is recovered.

 Recommendation: use the payback period only as
  supplemental information in conjunction with one or more
  of the other methods in this chapter.



                                                                63
Suggested Problems
 4, 10, 16, 21, 25, 36, 46, 49, 55, 60




                                          64

More Related Content

What's hot

Chapter 4-internal loadings developed in structural members
Chapter 4-internal loadings developed in structural membersChapter 4-internal loadings developed in structural members
Chapter 4-internal loadings developed in structural membersISET NABEUL
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_IPralhad Kore
 
Chapter-4 Time value of money
Chapter-4  Time value of moneyChapter-4  Time value of money
Chapter-4 Time value of moneyBibek Paudyal
 
Fluid mechanic white (cap2.1)
Fluid mechanic   white (cap2.1)Fluid mechanic   white (cap2.1)
Fluid mechanic white (cap2.1)Raul Garcia
 
Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]Mohsin Siddique
 
Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)Syed Muhammad Bilal
 
Simple and Compound Interest
Simple and Compound InterestSimple and Compound Interest
Simple and Compound InterestHector Tibo
 
Fluid Mechanic Lab - Venturi Meter
Fluid Mechanic Lab - Venturi MeterFluid Mechanic Lab - Venturi Meter
Fluid Mechanic Lab - Venturi MeterMuhammadSRaniYah
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solutionHaris Hassan
 
Engineering Economy (Practice Final Exam)
Engineering Economy (Practice Final Exam)Engineering Economy (Practice Final Exam)
Engineering Economy (Practice Final Exam)Le Nguyen Truong Giang
 
LECTURE 5 FLUID FLOW MEASUREMENT.pptx
LECTURE 5 FLUID FLOW MEASUREMENT.pptxLECTURE 5 FLUID FLOW MEASUREMENT.pptx
LECTURE 5 FLUID FLOW MEASUREMENT.pptxVanJasperCastillo
 

What's hot (20)

Chapter 4-internal loadings developed in structural members
Chapter 4-internal loadings developed in structural membersChapter 4-internal loadings developed in structural members
Chapter 4-internal loadings developed in structural members
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
Chap 03
Chap 03Chap 03
Chap 03
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_I
 
Chapter-4 Time value of money
Chapter-4  Time value of moneyChapter-4  Time value of money
Chapter-4 Time value of money
 
Lo 2 b factors
Lo 2 b   factorsLo 2 b   factors
Lo 2 b factors
 
Fluid mechanic white (cap2.1)
Fluid mechanic   white (cap2.1)Fluid mechanic   white (cap2.1)
Fluid mechanic white (cap2.1)
 
Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]
 
Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)
 
Simple and Compound Interest
Simple and Compound InterestSimple and Compound Interest
Simple and Compound Interest
 
Hydrostatic forces on plane surfaces
Hydrostatic forces on plane surfacesHydrostatic forces on plane surfaces
Hydrostatic forces on plane surfaces
 
6 shearing stresses
6 shearing stresses6 shearing stresses
6 shearing stresses
 
Fluid Mechanic Lab - Venturi Meter
Fluid Mechanic Lab - Venturi MeterFluid Mechanic Lab - Venturi Meter
Fluid Mechanic Lab - Venturi Meter
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solution
 
Truss examples
Truss examplesTruss examples
Truss examples
 
The 7 principles of Engineering Economy
The 7 principles of Engineering EconomyThe 7 principles of Engineering Economy
The 7 principles of Engineering Economy
 
Engineering Economy (Practice Final Exam)
Engineering Economy (Practice Final Exam)Engineering Economy (Practice Final Exam)
Engineering Economy (Practice Final Exam)
 
LECTURE 5 FLUID FLOW MEASUREMENT.pptx
LECTURE 5 FLUID FLOW MEASUREMENT.pptxLECTURE 5 FLUID FLOW MEASUREMENT.pptx
LECTURE 5 FLUID FLOW MEASUREMENT.pptx
 
Economic pipe size
Economic pipe sizeEconomic pipe size
Economic pipe size
 

Viewers also liked

economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami Louy Alhamy
 
economy Ch4 part.1 _by louy Alhami
economy Ch4 part.1 _by louy Alhamieconomy Ch4 part.1 _by louy Alhami
economy Ch4 part.1 _by louy AlhamiLouy Alhamy
 
economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami Louy Alhamy
 
economy Chapter4 part3_by louy al hami
economy Chapter4 part3_by louy al hami economy Chapter4 part3_by louy al hami
economy Chapter4 part3_by louy al hami Louy Alhamy
 
economy Chapter7_by louy Al hami
economy Chapter7_by louy Al hamieconomy Chapter7_by louy Al hami
economy Chapter7_by louy Al hamiLouy Alhamy
 
economy Ch4part2_by louy Al hami
economy Ch4part2_by louy Al hami economy Ch4part2_by louy Al hami
economy Ch4part2_by louy Al hami Louy Alhamy
 
hydro chapter_11_hydrology_by louy al hami
hydro  chapter_11_hydrology_by louy al hami hydro  chapter_11_hydrology_by louy al hami
hydro chapter_11_hydrology_by louy al hami Louy Alhamy
 
Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2onurozbal
 
hydro chapter_7_groundwater_by louy Al hami
hydro chapter_7_groundwater_by louy Al hami hydro chapter_7_groundwater_by louy Al hami
hydro chapter_7_groundwater_by louy Al hami Louy Alhamy
 
hydro chapter_4_b_pipe_network_by louy Al hami
hydro  chapter_4_b_pipe_network_by louy Al hami hydro  chapter_4_b_pipe_network_by louy Al hami
hydro chapter_4_b_pipe_network_by louy Al hami Louy Alhamy
 
hydro chapter_4_a_by louy al hami
hydro chapter_4_a_by louy al hami hydro chapter_4_a_by louy al hami
hydro chapter_4_a_by louy al hami Louy Alhamy
 
hydro chapter_5_a_by louy Al hami
hydro chapter_5_a_by louy Al hami hydro chapter_5_a_by louy Al hami
hydro chapter_5_a_by louy Al hami Louy Alhamy
 
hydro chapter_3 by louy Al hami
hydro chapter_3 by louy Al hami hydro chapter_3 by louy Al hami
hydro chapter_3 by louy Al hami Louy Alhamy
 
footing
footingfooting
footingillpa
 
Pipe network analysis with examples
Pipe network analysis with examplesPipe network analysis with examples
Pipe network analysis with examplesMohsin Siddique
 

Viewers also liked (16)

economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami
 
economy Ch4 part.1 _by louy Alhami
economy Ch4 part.1 _by louy Alhamieconomy Ch4 part.1 _by louy Alhami
economy Ch4 part.1 _by louy Alhami
 
economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami
 
economy Chapter4 part3_by louy al hami
economy Chapter4 part3_by louy al hami economy Chapter4 part3_by louy al hami
economy Chapter4 part3_by louy al hami
 
economy Chapter7_by louy Al hami
economy Chapter7_by louy Al hamieconomy Chapter7_by louy Al hami
economy Chapter7_by louy Al hami
 
economy Ch4part2_by louy Al hami
economy Ch4part2_by louy Al hami economy Ch4part2_by louy Al hami
economy Ch4part2_by louy Al hami
 
hydro chapter_11_hydrology_by louy al hami
hydro  chapter_11_hydrology_by louy al hami hydro  chapter_11_hydrology_by louy al hami
hydro chapter_11_hydrology_by louy al hami
 
Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2Ie242 ch5-supplement-per2
Ie242 ch5-supplement-per2
 
hydro chapter_7_groundwater_by louy Al hami
hydro chapter_7_groundwater_by louy Al hami hydro chapter_7_groundwater_by louy Al hami
hydro chapter_7_groundwater_by louy Al hami
 
hydro chapter_4_b_pipe_network_by louy Al hami
hydro  chapter_4_b_pipe_network_by louy Al hami hydro  chapter_4_b_pipe_network_by louy Al hami
hydro chapter_4_b_pipe_network_by louy Al hami
 
hydro chapter_4_a_by louy al hami
hydro chapter_4_a_by louy al hami hydro chapter_4_a_by louy al hami
hydro chapter_4_a_by louy al hami
 
hydro chapter_5_a_by louy Al hami
hydro chapter_5_a_by louy Al hami hydro chapter_5_a_by louy Al hami
hydro chapter_5_a_by louy Al hami
 
hydro chapter_3 by louy Al hami
hydro chapter_3 by louy Al hami hydro chapter_3 by louy Al hami
hydro chapter_3 by louy Al hami
 
Introduction to engineering economy
Introduction to engineering economyIntroduction to engineering economy
Introduction to engineering economy
 
footing
footingfooting
footing
 
Pipe network analysis with examples
Pipe network analysis with examplesPipe network analysis with examples
Pipe network analysis with examples
 

Similar to Evaluating a Single Project

Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
PPAM-AK PPT.pptx
PPAM-AK PPT.pptxPPAM-AK PPT.pptx
PPAM-AK PPT.pptxShyam273559
 
Chapter13 specialdecisionsituations
Chapter13 specialdecisionsituationsChapter13 specialdecisionsituations
Chapter13 specialdecisionsituationsAKSHAYA0000
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3bAbdulaziz AlSuwaidi
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3bAbdulaziz AlSuwaidi
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
8 150316005531-conversion-gate01
8 150316005531-conversion-gate018 150316005531-conversion-gate01
8 150316005531-conversion-gate01abidiqbal55
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteriaAKSHAYA0000
 
Risk In Capital Budgeting
Risk In Capital BudgetingRisk In Capital Budgeting
Risk In Capital BudgetingNoman
 
Gs503 vcf lecture 4 valuation ii 090215
Gs503 vcf lecture 4 valuation ii  090215Gs503 vcf lecture 4 valuation ii  090215
Gs503 vcf lecture 4 valuation ii 090215Stephen Ong
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting3prem
 
04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.ppt
04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.ppt04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.ppt
04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.pptAliAbdulla63
 

Similar to Evaluating a Single Project (20)

unit 4.pdf
unit 4.pdfunit 4.pdf
unit 4.pdf
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Chap. 7.pptx
Chap. 7.pptxChap. 7.pptx
Chap. 7.pptx
 
PPAM-AK PPT.pptx
PPAM-AK PPT.pptxPPAM-AK PPT.pptx
PPAM-AK PPT.pptx
 
Capital budgeting unit_2
Capital budgeting unit_2Capital budgeting unit_2
Capital budgeting unit_2
 
Chapter13 specialdecisionsituations
Chapter13 specialdecisionsituationsChapter13 specialdecisionsituations
Chapter13 specialdecisionsituations
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
8 150316005531-conversion-gate01
8 150316005531-conversion-gate018 150316005531-conversion-gate01
8 150316005531-conversion-gate01
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
 
Updated IRR PPT
Updated IRR PPTUpdated IRR PPT
Updated IRR PPT
 
Risk In Capital Budgeting
Risk In Capital BudgetingRisk In Capital Budgeting
Risk In Capital Budgeting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Gs503 vcf lecture 4 valuation ii 090215
Gs503 vcf lecture 4 valuation ii  090215Gs503 vcf lecture 4 valuation ii  090215
Gs503 vcf lecture 4 valuation ii 090215
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting
 
04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.ppt
04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.ppt04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.ppt
04 EMSE 6410-LectureNotes-Evaluating a Single Project-Fall2022 (1) ch5&6.ppt
 

Recently uploaded

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 

Recently uploaded (20)

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 

Evaluating a Single Project

  • 2. Introduction In this chapter we will answer the following question : Whether a proposed capital and its expenditures can recovered by revenue over time in addition to a return on the capital sufficiently attractive in view of the risks . 2
  • 3. Methods of Evaluating the Economic Profitability of a Problem Solution  Present Worth ( PW )  Future Worth ( FW )  Annual Worth ( AW )  Internal Rate of Return ( IRR )  External Rate of Return ( ERR ) 3
  • 4. Assumptions 1. We know the future with certainty 2. We can borrow and lend with the same i%. 4
  • 5. The most-used method is the present worth method. The present worth (PW) is found by discounting all cash inflows and outflows to the present time at an interest rate that is generally the MARR. A positive PW for an investment project means that the project is acceptable (it satisfies the MARR). 5
  • 6. Present Worth ( PW ) Eq..(5-1)  =F0(1+i)0+F1(1+i)-1+F2(1+i)-2+………..+FN(1+i)-N  i = effective interest rate or MARR  K = index of each compounding period  Fk = future cash flow at the end of period k  N = # of compounded periods . 6
  • 7.  PW Decision Rule: If PW (i=MARR) ≥ 0 , the project is economically justified 7
  • 8. Note  The higher the interest rate and the further into the future a cash flow occurs , the lower its PW is  See figure 5-2  PW of 1,000 10 years from now i =5% is $613.90  PW of 1,000 10years from now i=10% is $385.5 8
  • 10. Example(PW) Consider a project that has an initial investment of $50,000 and that returns $18,000 per year for the next four years. If the MARR is 12%, is this a good investment? PW = -50,000 + 18,000 (P/A, 12%, 4) PW = -50,000 + 18,000 (3.0373) PW = $4,671.40  This is a good investment! 10
  • 11.  Example 5.1:  A piece of new equipment has been proposed by engineers to increase the productivity of a certain manual welding operation. The investment cost $25,000 and the equipment will have a market value of $5,000 at the end of a study period of five years. Increased productivity attributable to the equipment will amount to $8,000 per year after extra operating costs have been subtracted from the revenue generated by the additional production. A cash flow diagram for this investment opportunity is given below. If the firm’s MARR is 20% per year, is this proposal a sound one? Use the PW method. 11
  • 12.  Example. 5-1  PW = PW(inflows) – PW (outflows)  PW= $8,000(P/A,20%,5) +$5,000(P/F,20%,5)-$25,000  PW= $934,29 12
  • 13. Bond Value  The value of the bond at any time is the PW of future cash receipts  Two types of payments 1. Series of periodic interest payments (rZ) 2. A single payment = C ,When the bond is sold or retired . 13
  • 14. VN = C(P/F, i%, N) + rZ (P/A, i%,N) Eq.5-2  Z= Face ,or parValue,  C = redemption or disposal price (usually = Z).  r = bond rate (nominal interest) per interest period  N= # of periods before redemption  i = bond yield rate per period  VN = PW 14
  • 15. 15
  • 17. The Capitalized-Worth Method  A special variation of the PW  To find PW for infinite length of time  N ∞ CW = PWN  ∞ = A ( P / A, i%, ∞ ) ( 1+i )N - 1 = A lim ------------------ =A ( 1 / i )=A/i N ∞ i ( 1 + i )N 17
  • 18. Ex. 5-5 page 219 18
  • 19. (a)As we discussed before when N= ∞ (p/A,i%,N)=1/i, then (p/A,8%,N)=1/0.08 = 12.5 go to App.C then N= 100 this assumed as (∞ ) 19
  • 20. Ex. 5-5 page 219 (b) 30,000 20,000 A / F ,8%,4) ( CW  (100000 A / P,8%, )) / .08 , ( 0.08  30,000  20,000 ( A / F ,8%,4)  CW  100,000     $530,475  0.08  20
  • 21. Future Worth ( FW )  Equivalent worth of all cash flows (In& Out) at the end of the planning horizon at MARR Eq.(5-3)  i = effective interest rate or MARR  K = index of each compounding period  Fk = future cash flow at the end of period k  N = # of compounded periods . 21
  • 22.  FW Decision Rule: If FW (i=MARR) ≥ 0 , the project is economically justified 22
  • 23.  Ex 5-6 page 221 23
  • 25. The Annual Worth Method  Annual worth is an equal periodic series of dollar amounts that is equivalent to the cash inflows and outflows, at an interest rate that is generally the MARR.  The AW of a project is annual equivalent revenue or savings minus annual equivalent expenses, less its annual capital recovery (CR) amount.  AW(i%) = R – E – CR(i%)  R = Annual equivalent Revenue or saving  E = Annual equivalent Expenses  CR = Annual equivalent Capital Recovery amount 25
  • 26.  AW Decision Rule: If AW (i=MARR) ≥ 0 , the project is economically justified 26
  • 27. CR (Capital Recovery)  CR is the equivalent uniform annual cost of the capital invested that covers 1. Loss of value of the asset. 2. Interest on invested capital (at MARR) 27
  • 28. CR  CR (i%) = I(A/P, i%, N) – S(A/F, i%,N) Eq. 5-5  I = initial investment for project  S = salvage (market) value at the end of the study period  N = project study period 28
  • 29.  CR (i%) = (I – S)(A/F, i%, N) +I(i%)  CR (i%) = (I –S)(A/P, i%, N) + S(i%) 29
  • 34. A project requires an initial investment of $45,000, has a salvage value of $12,000 after six years, incurs annual expenses of $6,000, and provides an annual revenue of $18,000. Using a MARR of 10%, determine the AW of this project. Since the AW is positive, it’s a good investment. 34
  • 35. Internal Rate Of Return Method ( IRR )  IRR solves for the interest rate that equates the equivalent worth of an alternative’s cash inflows (receipts or savings) to the equivalent worth of cash outflows (expenditures)  IRR is positive for a single alternative only if:  both receipts and expenses are present in the cash flow diagram  the sum of inflows exceeds the sum of outflows 35
  • 36. Internal Rate of Return  It is also called the investor’s method, the discounted cash flow method, and the profitability index.  If the IRR for a project is greater than the MARR, then the project is acceptable. 36
  • 37. INTERNAL RATE OF RETURN METHOD ( IRR )  IRR is i’ %, using the following PW formula: R k = net revenues or savings for the kth year E k = net expenditures including investment costs for the kth year N = project life ( or study period ) Note: FW or AW can be used instead of PW 37
  • 38. Solving for the IRR is a bit more complicated than PW, FW, or AW  The method of solving for the i'% that equates revenues and expenses normally involves trial-and- error calculations, or solving numerically using mathematical software. 38
  • 39. 39
  • 40. 40
  • 41. Installment Financing  An application of IRR method  Ex.5-14 will be discussed 41
  • 42. 42
  • 43. 43
  • 44. 44
  • 45. 45
  • 46. 46
  • 47. 47
  • 48. Challenges in Applying the IRR Method.  It is computationally difficult without proper tools.  In rare instances multiple rates of return can be found(take a look to page 255 example 5-A-1).  The IRR method must be carefully applied and interpreted when comparing two more mutually exclusive alternatives (e.g., do not directly compare internal rates of return). 48
  • 49. The External Rate Of Return Method ( ERR )  ERR directly takes into account the interest rate (  ) external to a project at which net cash flows generated over the project life can be reinvested (or borrowed ).  If the external reinvestment rate, usually the firm’s MARR, equals the IRR, then ERR method produces same results as IRR method 49
  • 50. Calculating External Rate of Return ( ERR ) 1. All net cash outflows are discounted to the present (time 0) at ε% per compounding period. 2. All net cash inflows are discounted to period N at ε %. 3. Solve for the ERR, the interest rate that establishes equivalence between the two quantities. The absolute value of the present equivalent worth of the net cash outflows at ε % is used in step 3.  A project is acceptable when i ‘ % of the ERR method is greater than or equal to the firm’s MARR 50
  • 51. ERR is the i'% at which where Rk = excess of receipts over expenses in period k, Ek = excess of expenses over receipts in period k, N = project life or number of periods, and ε = external reinvestment rate per period. 51
  • 52. Calculating External Rate of Return ( ERR ) 2 N  R ( F / P,  %, N - k ) k = 0k 0 1 Time N N E ( P / F,  %, k ) k=0 k 52
  • 53. Calculating External Rate of Return ( ERR ) 2 3 N  R ( F / P,  %, N - k ) k = 0k 0 i ‘ %= ? 1 Time N N  Ek ( P / F,  %, k ) ( F / P, i ‘ %, N ) k=0 53
  • 54. Example 5-17  $25,000 (F/P,i’%,5)=$8,000(F/A,20%,5)+$5,000  (F/P,i’%,5)= $64,532.80  2.5813  (1  i ' )5 $25,000  i’ =20.88% 54
  • 56. Example For the cash flows given below, find the ERR when the external reinvestment rate is ε = 12% (equal to the MARR). Year 0 1 2 3 4 Cash Flow -$15,000 -$7,000 $10,000 $10,000 $10,000 Expenses Revenue Solving, we find 56
  • 57. The payback period method  The simple payback period is the number of years required for cash inflows to just equal cash outflows.  It is a measure of liquidity rather than a measure of profitability. 57
  • 58. Payback is simple to calculate. The payback period is the smallest value of θ (θ ≤ N) for which the relationship below is satisfied. For discounted payback future cash flows are discounted back to the present, so the relationship to satisfy becomes 58
  • 59.  A low- valued pay back period is considered desirable 59
  • 60. Finding the simple End End of Net Cumulat Present Cumulati of Cash ive PW worth at ve PW at and discounted Year Year Flow at 0% i = 6% 6% payback period for a set of cash flows. 0 0 -$42,000 -$42,000 -$42,000 -$42,000 The cumulative cash 1 1 $12,000 -$30,000 11,320.8 -$30,679 flows in the table were calculated using the formulas for simple 2 2 $11,000 -$19,000 9,790 -$20,889 and discounted payback. 3 3 $10,000 -$9,000 8,396 -$12,493 From the calculations 4 4 $10,000 $1,000 7,921 -$4,572 θ = 4 years and θ' = 5 years. 5 5 $9,000 6,725.7 $2,153 60
  • 61. Col.3: EOF1= -42,000-12,000=-30,000 End of Net Cash Cumulative Cumulative End Net Cumulat Present Cumulati Year Cash of Flow ive PW at 0% at PW at 6% PW worth ve PW at EOF2 : 11,000-30,000=-19,000 Year Flow at 0% i = 6% 6% EOF3 : 10,000-19,000=-9,000 00 -$42,000 -$42,000 -$42,000 -$42,000 -$42,000 -$42,000 -$42,000 EOF4 : 10,000-9,000=1,000>0 θ=4 Col.4: 11 $12,000 -$30,000 11,320.8 -$30,679 $12,000 -$30,000 -$30,679 12,000 (p/F,6%,1) = 12,000* 0.9434= 113,208 22 $11,000 -$19,000 $11,000 -$19,000 9,790 -$20,889 -$20,889 11,000 (p/F,6%,2) = 11,000*0.8900= 9,790 33 $10,000 $10,000 -$9,000-$9,000 8,396 -$12,493 -$12,493 10,000*(P/F,6%,3) = 10,000*0.8396= 8,396 44 $10,000$1,000 $1,000 $10,000 7,921 -$4,572 -$4,572 10,000*(P/F,6%,4) = 10,000*0.7921 =7,921 9,000*(P/F,6%,5) = 55 $9,000 $9,000 6,725.7 $2,153 $2,153 9,000*0.7473 = 6,725.7 61
  • 62. End Net Cumulat Present Cumulati Col.5: of Cash ive PW worth at ve PW at Year Flow at 0% i = 6% 6% EOF1: -42,000 + 11,320.8 = -30,679.2 0 -$42,000 -$42,000 -$42,000 -$42,000 EOF2 : 1 $12,000 -$30,000 11,320.8 -$30,679 9,790 -30,679.2 = -20,889.2 EOF3 : 2 $11,000 -$19,000 9,790 -$20,889 8,396 -20,889.2 = -12,493.2 EOF4 : 3 $10,000 -$9,000 8,396 -$12,493 7,921-12,493.2 = -4,572.2 <0 EOF5 : 4 $10,000 $1,000 7,921 -$4,572 6,725.7 -4,572.2 = 2,153.5 >0 5 $9,000 6,725.7 $2,153 62
  • 63. Problems with the payback period method.  It doesn’t reflect any cash flows occurring after θ, or θ'.  It doesn’t indicate anything about project desirability except the speed with which the initial investment is recovered.  Recommendation: use the payback period only as supplemental information in conjunction with one or more of the other methods in this chapter. 63
  • 64. Suggested Problems  4, 10, 16, 21, 25, 36, 46, 49, 55, 60 64