School Of Architecture, Building &
Science
Building Construction 2 (ARC 2513)
Project 1: Understanding Forces in Skeletal Structure
Prepared by:
D a n i e l Ya p C h u n g K i a t 0 3 0 9 1 0 0
L o o G i a p S h e n g 0 3 1 0 3 9 0
C h r i s t i o d y 0 3 0 4 1 9 1
Te o K e a n H u i 0 3 1 0 1 6 5
G a n C h i n B o n g 0 3 1 3 7 3 2
Content Page Page
Introduction 1
Design Process 2-3
Design Solution 4-5
Force Analysis 6-7
Model Constructed and Detail 8
Model Testing & Failure 9
Efficiency 9
Design Improvement 10-11
Conclusion 12
Introduction
Architecture, not only consisting design concept, form and
spatial quality but also the structure as it helps in constructing the
architecture. As a successful architecture, structural strength of the
architecture should be concerned during the design process. There are
various types of supporting structure but skeletal structure construction
are nowadays widely used in most of the architecture in the world as
building support. Therefore, it is important for us as an architectural
student to study how these skeletal structure works and influences the
stability of an architecture.
In this project, we are required to understand the skeletal
structure and the components and how they work. In order to show our
understanding, we were required to create a convincing structural model
to show our understanding of how a structure works under a load.
Design process
Design 1
Triangular core to distributes load could be a very strong structure. The triangular core was pre-
stressed to oppose the load force (mechanism of spring). The triangular core was joined with a
square base to maximize the base area of the structure. The tip of the triangular core are faced
up and down respectively at each level to distribute the load force evenly. The weakness of the
structure is the absence of vertical structure.
Design 2
The theory of pre-stress was still applied in this model. The square base provides larger base
area and better stability. The square base also provides maximum number of pre-stressed
column. Zigzag bracing were used to support beams meanwhile cross bracing used to maintain
the form and prevent the structure to be twisted. This design has its potential and with proper
bracing, it can be a very strong structure.
Design 3
Squared base with 8 columns at each level produce a very strong structure.
The columns are bended inwards a little to make sure it breaks inward.
Therefore, there are square bracing inside to prevent the bended column from
breaking. A-bracing is use for vertical bracing to support the beams and to
prevent the square bracing inside from breaking. Each popsicles stick are
supporting each other. This design distributes the load force to different
direction so force becomes weaker and weaker.
Design solution
Learn how is a building’s fundamental work. Besides, we also learn about pre-stretch method. Explore
how to tie to thing two string together to get maximum outcome. Learn how much loads that one popsicle
stick can handle.
Double square diagonal base
The square diagonal base give good impact and give maximum strength to the base as supporter. The
double layer of popsicle on the base support and giving stability to the vertical structure where are going
to place it on the base. The mechanism is the double layer of the popsicle stick will clip the vertical
structure so it giving more balance and stability.
The 4 pre-stretch column
The 4 pre-stretch column is giving a lot of benefit in a way to handle the load. The 4 column also became
the connector between the ground level to the next level.The mechanism is using 8 popsicle stick as the
vertical structures which tied together as two per column with leaving gap in between the structure to give
a space for the popsicle stick to stretch and support each other when the load force down from the top.
The balance slot in triangle bracing
The triangle bracing is the usual bracing that the being used by construction as structure supporter
nowadays. The slot in triangle bracing being bring into the skeletal structure. The slot in triangle bracing
giving a lot of benefit and advantages. The center part is to help the triangle bracing keep stable. The
mechanism is slot in the bracing that create a triangle shape that make the popsicle stick force each other
and force it to the 4 pre-stretch column. the bracing we put it on 4 sided of the structures and it helps a lot
on handle the load that force down to the structure.
Consistency of tying the string
Consistency is the most important thing on tying thing. For example this skeletal structure use string as
connector if the consistency and the way of tying the string is not right so the structure and connection
will decrease the strength and the stability of the structure. So for this skeletal structure the string tying
has been set like the number of tying. The mechanism of tying system is the string come from all the
sided and way with the same number of repetition with same loose-ness that given to every repetition.
Force Analysis
The characteristics of a Popsicle stick is experiment and tested. We
realized that it actually can be bent, so it has a tensile property and we have decided to
make use of it. In order to create a strong tower, we need to make use of all the
possibilities of Popsicle stick. The idea is to create a model with tensile strength and
using it to withstand the heavy load force and transfer it to other direction rather than
just acting downwards.
Pre-bent – To lead the force to the direction where it bends when force is exerted.
This is to predict the direction where the Popsicle stick breaks and from there, reinforce
it. A straight vertical column is unpredictable where the direction it breaks. Therefore it
is difficult to control the direction of force. A horizontal beam is placed at both ends to
hold them firmly and preventing them from shaking.( Shown in diagram beside)
Load
Force
Another shorter pre-bent Popsicle stick is placed in between two pre-bent
columns to carry the force transferred from the columns. By doing so, the originally
weakest point of the column now separate the entire column into two, making it harder
to bend. Just by adding a beam in the middle between two pre-bent columns
significantly enhances the strength.
The way it works is that the load force coming from top will compress the pre-
bend columns. After a pre-bend beam is added in between the middle of two pre-bend
columns, the heavy force transferred is reduced due to the tensile property countering
the force. The reason of using a pre-bend beam is to make is easily bendable in its
already bent position. This way it reduces the overall load force, like a spring.
To further enhance it, an inverted ‘V’ shape bracing is used in all sides of the
structure. Not only it shares the load by making use of the horizontal beam to transfer
the load, it also prevents the whole structure to tilt to 1 side. Besides, it holds the shorter
pre-bent beam from bending too much and break.
The idea is to be able to reduce the load force and to direct the force
experienced to all directions instead of just acting downwards.
Load
Load
ForceForce
Model Constructed and Detailed
After finish testing mock up model which only giving
unsatisfied result which became challenging thing to find out the problem
and solve it with the 4 method. After found out the problem, the 4 method
that became our specialty and best method to construct the skeletal structure.
84 popsicle stick is the number to construct the skeletal structure. after
counting the popsicle stick start to weighing the structure which the weight
reach exactly 100 grams and the height of the tower also reach the
requirement height or the minimum height that has been stated which is 30
cm.
First Experimental Model
Model Testing & Failure
The first testing is going smoothly. The structure handle 104 kilogram
without cracking any of the popsicle stick or structure. Stop at 104 kilogram
because out of loads at that time. After that, the lecturer require a test for
submission. Unlucky the lecture only bring 40 kilogram load to the studio.
After testing on studio the structure still can handle without cracking
anything. So all of the group member doing the final test at gym which
supply more loads. Then for the final test, the structure end up with satisfied
result which can handle load more than 100 kilogram which exactly 108.75
kilogram. About the structure it’s not breaking the popsicle stick it’s only fall
down because of the structure tilting at the moment and make the bracing all
pop out from the place where it should be.
Efficiency
Efficiency =
Height X Load_______________
Mass
=
_______________30.0 X 108.75
100
= 32.625
Design improvement
Our initial design was to use pre-stressed column to execute opposite force from the load. We
used 8 columns for every level and stressed the sticks (to create the mechanism of spring). Then
we have zigzag bracing as our vertical bracing and cross bracing for horizontal bracing. The
methods of both bracing are slotted-in. It gives us unsatisfied result. We used 66 sticks and it
breaks at 30KG.
We replay the mock up video to observe and analysis how and why the model were crushed. We
then knew that our structure was not crushed directly vertical because the upper structure actually
slide off aside causing the middle structure to gets imbalanced and it crushed downwards. We
checked on the crushed structure and noticed that there weren't any broken stick. The major
problems are not the structure is weak itself, it was the positioning and equilibrium that twisted
the structure. The structure did not maximize its load endurance. The factor behind the structure
failure were the inappropriate bracing applied and inconsistency of workmanship caused the
structure to be tilted aside.
We got aware of the importance of workmanship therefore, we made up several systems
and methods in model making to ensure every one using the same way. We then
realised that the pre-stressed column are not as strong as pure vertical column so we
changed our plan. We decided to stressed the stick a little inwards to force the stick to
break inwards rather than using it as pre-stressed. This method ensured that if the
column breaks, it would definitely break inwards.
We then strengthen the inner side by adding bracing into the weakest point of the
bended column which is the middle of the stick. Moreover, we improved our zigzag
bracing to A-bracing. The A-bracing functioned as two; supporting the bracing of the
bended column and to maintain the beam in its position. This method distributes the
force from the load to many and different directions, minimizing the force each time it
changes direction. We have improved from the theory of opposing its force to
distributing load force to different directions.
Conclusion
In the conclusion, a lots of experiences and
understandings have been gain through this structural model making.
Throughout this project, we have learnt how a skeletal structure works under
loading. In order to maximize the load handled by a structure, several
experiments have been carried out. We have tried different ways of bracing,
different way of tithing method and also different types of structure.
After been through these experiments, we have learnt that
bracings are needed to strengthen the structure as they play an important role
in maintain the original shape of the structure.
Besides that, our creativity have also been aroused to create
different kinds of structure and test them to their limit. This project have
indirectly help us to realize that how an organic structure can possibly
construct in different skeletal structure.

More Related Content

What's hot

Analysis of outrigger system for tall vertical irregularites structures subje...
Analysis of outrigger system for tall vertical irregularites structures subje...Analysis of outrigger system for tall vertical irregularites structures subje...
Analysis of outrigger system for tall vertical irregularites structures subje...eSAT Journals
 
Seismic behavior of beam column Joint
Seismic behavior of beam column JointSeismic behavior of beam column Joint
Seismic behavior of beam column JointPavan Kumar N
 
Retrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column JointRetrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column JointDishamk
 
Earthquake resistant buildings (1)
Earthquake resistant buildings (1)Earthquake resistant buildings (1)
Earthquake resistant buildings (1)KartikYadav79
 
Sesmic strengthining of multi storey building with soft storey week 2
Sesmic strengthining of multi storey building with soft storey  week 2Sesmic strengthining of multi storey building with soft storey  week 2
Sesmic strengthining of multi storey building with soft storey week 2SVMohtesham
 
Performance Based Analysis of Concealed Beam in Reinforced Concrete Structure
Performance Based Analysis of Concealed Beam in Reinforced Concrete StructurePerformance Based Analysis of Concealed Beam in Reinforced Concrete Structure
Performance Based Analysis of Concealed Beam in Reinforced Concrete StructureIRJET Journal
 
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...shankar kumar
 
parametric study of effect of column shapes on earthquake resistance of build...
parametric study of effect of column shapes on earthquake resistance of build...parametric study of effect of column shapes on earthquake resistance of build...
parametric study of effect of column shapes on earthquake resistance of build...Solcon Technologies LLP
 
A study on behaviour of outrigger system on high rise steel structure by vary...
A study on behaviour of outrigger system on high rise steel structure by vary...A study on behaviour of outrigger system on high rise steel structure by vary...
A study on behaviour of outrigger system on high rise steel structure by vary...eSAT Journals
 
Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...
Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...
Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...IRJET Journal
 
Seismic Analysis of regular & Irregular RCC frame structures
Seismic Analysis of regular & Irregular RCC frame structuresSeismic Analysis of regular & Irregular RCC frame structures
Seismic Analysis of regular & Irregular RCC frame structuresDaanish Zama
 
Seismic Retrofitting of RC Building with Jacketing and Shear Wall Seismic Ret...
Seismic Retrofitting of RC Buildingwith Jacketing and Shear Wall Seismic Ret...Seismic Retrofitting of RC Buildingwith Jacketing and Shear Wall Seismic Ret...
Seismic Retrofitting of RC Building with Jacketing and Shear Wall Seismic Ret...Bala murali
 

What's hot (18)

Analysis of outrigger system for tall vertical irregularites structures subje...
Analysis of outrigger system for tall vertical irregularites structures subje...Analysis of outrigger system for tall vertical irregularites structures subje...
Analysis of outrigger system for tall vertical irregularites structures subje...
 
Seismic behavior of beam column Joint
Seismic behavior of beam column JointSeismic behavior of beam column Joint
Seismic behavior of beam column Joint
 
FinalChairpaper
FinalChairpaperFinalChairpaper
FinalChairpaper
 
Retrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column JointRetrofitting of RC Beam Column Joint
Retrofitting of RC Beam Column Joint
 
Earthquake resistant buildings (1)
Earthquake resistant buildings (1)Earthquake resistant buildings (1)
Earthquake resistant buildings (1)
 
Sesmic strengthining of multi storey building with soft storey week 2
Sesmic strengthining of multi storey building with soft storey  week 2Sesmic strengthining of multi storey building with soft storey  week 2
Sesmic strengthining of multi storey building with soft storey week 2
 
PROJECT
PROJECTPROJECT
PROJECT
 
Rcc jacketing
Rcc jacketingRcc jacketing
Rcc jacketing
 
Performance Based Analysis of Concealed Beam in Reinforced Concrete Structure
Performance Based Analysis of Concealed Beam in Reinforced Concrete StructurePerformance Based Analysis of Concealed Beam in Reinforced Concrete Structure
Performance Based Analysis of Concealed Beam in Reinforced Concrete Structure
 
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...
 
Shear wall
Shear wallShear wall
Shear wall
 
Retrofitting
RetrofittingRetrofitting
Retrofitting
 
parametric study of effect of column shapes on earthquake resistance of build...
parametric study of effect of column shapes on earthquake resistance of build...parametric study of effect of column shapes on earthquake resistance of build...
parametric study of effect of column shapes on earthquake resistance of build...
 
A study on behaviour of outrigger system on high rise steel structure by vary...
A study on behaviour of outrigger system on high rise steel structure by vary...A study on behaviour of outrigger system on high rise steel structure by vary...
A study on behaviour of outrigger system on high rise steel structure by vary...
 
Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...
Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...
Seismic Analysis of Multistoreyed RC Building Due to Mass Irregularity by Tim...
 
Bs8110 design notes
Bs8110 design notesBs8110 design notes
Bs8110 design notes
 
Seismic Analysis of regular & Irregular RCC frame structures
Seismic Analysis of regular & Irregular RCC frame structuresSeismic Analysis of regular & Irregular RCC frame structures
Seismic Analysis of regular & Irregular RCC frame structures
 
Seismic Retrofitting of RC Building with Jacketing and Shear Wall Seismic Ret...
Seismic Retrofitting of RC Buildingwith Jacketing and Shear Wall Seismic Ret...Seismic Retrofitting of RC Buildingwith Jacketing and Shear Wall Seismic Ret...
Seismic Retrofitting of RC Building with Jacketing and Shear Wall Seismic Ret...
 

Viewers also liked

презентация от лица учителя
презентация от лица учителяпрезентация от лица учителя
презентация от лица учителяVictoriaNefedova
 
ALC-7-Ways to Launch NB
ALC-7-Ways to Launch NBALC-7-Ways to Launch NB
ALC-7-Ways to Launch NBNicole Baker
 

Viewers also liked (6)

Lehoia
LehoiaLehoia
Lehoia
 
презентация от лица учителя
презентация от лица учителяпрезентация от лица учителя
презентация от лица учителя
 
O2 booklet
O2 bookletO2 booklet
O2 booklet
 
genral physis
genral physisgenral physis
genral physis
 
ALC-7-Ways to Launch NB
ALC-7-Ways to Launch NBALC-7-Ways to Launch NB
ALC-7-Ways to Launch NB
 
Slideshare
SlideshareSlideshare
Slideshare
 

Similar to Bcon report final

Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Reporthiewyennee
 
Assignment 1 bcons 2 report
Assignment 1 bcons 2 reportAssignment 1 bcons 2 report
Assignment 1 bcons 2 reportYaseen Syed
 
Building Construction Project 1 Report
Building Construction Project 1 ReportBuilding Construction Project 1 Report
Building Construction Project 1 ReportSürayyn Selvan
 
Building construction report
Building construction reportBuilding construction report
Building construction reportJannah Jailani
 
Building construction report
Building construction reportBuilding construction report
Building construction reportSoh Shing
 
Building Construction 2
Building Construction 2 Building Construction 2
Building Construction 2 leejanicee
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 reportYq Chong
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportForestedTiger
 
Fettucine Truss Bridge Report
Fettucine Truss Bridge ReportFettucine Truss Bridge Report
Fettucine Truss Bridge Reportkimberlywjs
 
Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Esther Lau
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)Prince Pathania
 
Bcon project 1 pdf report
Bcon project 1 pdf reportBcon project 1 pdf report
Bcon project 1 pdf reportAnderson Wong
 
FORM ACTIVE.pptx
FORM ACTIVE.pptxFORM ACTIVE.pptx
FORM ACTIVE.pptxTaranJot7
 
FORM ACTIVE.pdf
FORM ACTIVE.pdfFORM ACTIVE.pdf
FORM ACTIVE.pdfTaranJot7
 

Similar to Bcon report final (20)

Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Report
 
Structures
StructuresStructures
Structures
 
Assignment 1 bcons 2 report
Assignment 1 bcons 2 reportAssignment 1 bcons 2 report
Assignment 1 bcons 2 report
 
Building Construction Project 1 Report
Building Construction Project 1 ReportBuilding Construction Project 1 Report
Building Construction Project 1 Report
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Merged
MergedMerged
Merged
 
Building Construction 2
Building Construction 2 Building Construction 2
Building Construction 2
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Report
 
Fettucine Truss Bridge Report
Fettucine Truss Bridge ReportFettucine Truss Bridge Report
Fettucine Truss Bridge Report
 
Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Report - Project 1 [BCON2]
Report - Project 1 [BCON2]
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)
 
bus shelter
bus shelterbus shelter
bus shelter
 
Bcon project 1 pdf report
Bcon project 1 pdf reportBcon project 1 pdf report
Bcon project 1 pdf report
 
BCON II PROJECT 1
BCON II PROJECT 1BCON II PROJECT 1
BCON II PROJECT 1
 
Clamping mechanism
Clamping mechanismClamping mechanism
Clamping mechanism
 
FORM ACTIVE.pptx
FORM ACTIVE.pptxFORM ACTIVE.pptx
FORM ACTIVE.pptx
 
FORM ACTIVE.pdf
FORM ACTIVE.pdfFORM ACTIVE.pdf
FORM ACTIVE.pdf
 
Final project mec e 3
Final project mec e 3Final project mec e 3
Final project mec e 3
 

More from Daniel Yap

Theory of Architecture & Urbanism Part 2
Theory of Architecture & Urbanism Part 2Theory of Architecture & Urbanism Part 2
Theory of Architecture & Urbanism Part 2Daniel Yap
 
Site c site analysis plan a2 size completed
Site c site analysis plan a2 size completedSite c site analysis plan a2 size completed
Site c site analysis plan a2 size completedDaniel Yap
 
Jewish museum precedent study
Jewish museum precedent studyJewish museum precedent study
Jewish museum precedent studyDaniel Yap
 
B.science report pinnacle
B.science report pinnacleB.science report pinnacle
B.science report pinnacleDaniel Yap
 
B.science report solaris
B.science report solarisB.science report solaris
B.science report solarisDaniel Yap
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis ReportDaniel Yap
 
history 2 essay
history 2 essay history 2 essay
history 2 essay Daniel Yap
 
Site b site analysis
Site b site analysisSite b site analysis
Site b site analysisDaniel Yap
 
Essay assignment
Essay assignmentEssay assignment
Essay assignmentDaniel Yap
 
Comparative research report (final)
Comparative research report (final)Comparative research report (final)
Comparative research report (final)Daniel Yap
 
Assignment 1 part 2
Assignment 1 part 2Assignment 1 part 2
Assignment 1 part 2Daniel Yap
 
Culture and Civilization Assignment
Culture and Civilization AssignmentCulture and Civilization Assignment
Culture and Civilization AssignmentDaniel Yap
 

More from Daniel Yap (13)

Theory of Architecture & Urbanism Part 2
Theory of Architecture & Urbanism Part 2Theory of Architecture & Urbanism Part 2
Theory of Architecture & Urbanism Part 2
 
Site c site analysis plan a2 size completed
Site c site analysis plan a2 size completedSite c site analysis plan a2 size completed
Site c site analysis plan a2 size completed
 
Jewish museum precedent study
Jewish museum precedent studyJewish museum precedent study
Jewish museum precedent study
 
B.science report pinnacle
B.science report pinnacleB.science report pinnacle
B.science report pinnacle
 
B.science report solaris
B.science report solarisB.science report solaris
B.science report solaris
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis Report
 
history 2 essay
history 2 essay history 2 essay
history 2 essay
 
Site b site analysis
Site b site analysisSite b site analysis
Site b site analysis
 
Essay assignment
Essay assignmentEssay assignment
Essay assignment
 
Comparative research report (final)
Comparative research report (final)Comparative research report (final)
Comparative research report (final)
 
Assignment 1 part 2
Assignment 1 part 2Assignment 1 part 2
Assignment 1 part 2
 
Compare essay
Compare essayCompare essay
Compare essay
 
Culture and Civilization Assignment
Culture and Civilization AssignmentCulture and Civilization Assignment
Culture and Civilization Assignment
 

Recently uploaded

Bur Dubai Call Girls O58993O4O2 Call Girls in Bur Dubai
Bur Dubai Call Girls O58993O4O2 Call Girls in Bur DubaiBur Dubai Call Girls O58993O4O2 Call Girls in Bur Dubai
Bur Dubai Call Girls O58993O4O2 Call Girls in Bur Dubaidajasot375
 
Zagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdfZagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdfStripovizijacom
 
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiFULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiMalviyaNagarCallGirl
 
Burari Call Girls : ☎ 8527673949, Low rate Call Girls
Burari Call Girls : ☎ 8527673949, Low rate Call GirlsBurari Call Girls : ☎ 8527673949, Low rate Call Girls
Burari Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Russian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts Service
Russian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts ServiceRussian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts Service
Russian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts Servicedoor45step
 
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call GirlsFaridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Strip Zagor Extra 322 - Dva ortaka.pdf
Strip   Zagor Extra 322 - Dva ortaka.pdfStrip   Zagor Extra 322 - Dva ortaka.pdf
Strip Zagor Extra 322 - Dva ortaka.pdfStripovizijacom
 
Turn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel JohnsonTurn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel Johnsonthephillipta
 
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call GirlsLaxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Govindpuri Call Girls : ☎ 8527673949, Low rate Call Girls
Govindpuri Call Girls : ☎ 8527673949, Low rate Call GirlsGovindpuri Call Girls : ☎ 8527673949, Low rate Call Girls
Govindpuri Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...
Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...
Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...dajasot375
 
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...akbard9823
 
FULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | DelhiFULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | DelhiMalviyaNagarCallGirl
 
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call GirlsMandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857delhimodel235
 
Retail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College ParkRetail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College Parkjosebenzaquen
 
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in DowntownDowntown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtowndajasot375
 
9654467111 Call Girls In Noida Sector 62 Short 1500 Night 6000
9654467111 Call Girls In Noida Sector 62 Short 1500 Night 60009654467111 Call Girls In Noida Sector 62 Short 1500 Night 6000
9654467111 Call Girls In Noida Sector 62 Short 1500 Night 6000Sapana Sha
 
Roadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMRoadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMroute66connected
 
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | DelhiMalviyaNagarCallGirl
 

Recently uploaded (20)

Bur Dubai Call Girls O58993O4O2 Call Girls in Bur Dubai
Bur Dubai Call Girls O58993O4O2 Call Girls in Bur DubaiBur Dubai Call Girls O58993O4O2 Call Girls in Bur Dubai
Bur Dubai Call Girls O58993O4O2 Call Girls in Bur Dubai
 
Zagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdfZagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdf
 
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiFULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
 
Burari Call Girls : ☎ 8527673949, Low rate Call Girls
Burari Call Girls : ☎ 8527673949, Low rate Call GirlsBurari Call Girls : ☎ 8527673949, Low rate Call Girls
Burari Call Girls : ☎ 8527673949, Low rate Call Girls
 
Russian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts Service
Russian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts ServiceRussian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts Service
Russian⚡ Call Girls In Sector 104 Noida✨8375860717⚡Escorts Service
 
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call GirlsFaridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girls
 
Strip Zagor Extra 322 - Dva ortaka.pdf
Strip   Zagor Extra 322 - Dva ortaka.pdfStrip   Zagor Extra 322 - Dva ortaka.pdf
Strip Zagor Extra 322 - Dva ortaka.pdf
 
Turn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel JohnsonTurn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel Johnson
 
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call GirlsLaxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
 
Govindpuri Call Girls : ☎ 8527673949, Low rate Call Girls
Govindpuri Call Girls : ☎ 8527673949, Low rate Call GirlsGovindpuri Call Girls : ☎ 8527673949, Low rate Call Girls
Govindpuri Call Girls : ☎ 8527673949, Low rate Call Girls
 
Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...
Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...
Call Girl in Bur Dubai O5286O4116 Indian Call Girls in Bur Dubai By VIP Bur D...
 
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...
 
FULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | DelhiFULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | Delhi
 
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call GirlsMandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
 
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
 
Retail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College ParkRetail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College Park
 
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in DowntownDowntown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtown
 
9654467111 Call Girls In Noida Sector 62 Short 1500 Night 6000
9654467111 Call Girls In Noida Sector 62 Short 1500 Night 60009654467111 Call Girls In Noida Sector 62 Short 1500 Night 6000
9654467111 Call Girls In Noida Sector 62 Short 1500 Night 6000
 
Roadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMRoadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NM
 
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
 

Bcon report final

  • 1. School Of Architecture, Building & Science Building Construction 2 (ARC 2513) Project 1: Understanding Forces in Skeletal Structure Prepared by: D a n i e l Ya p C h u n g K i a t 0 3 0 9 1 0 0 L o o G i a p S h e n g 0 3 1 0 3 9 0 C h r i s t i o d y 0 3 0 4 1 9 1 Te o K e a n H u i 0 3 1 0 1 6 5 G a n C h i n B o n g 0 3 1 3 7 3 2
  • 2. Content Page Page Introduction 1 Design Process 2-3 Design Solution 4-5 Force Analysis 6-7 Model Constructed and Detail 8 Model Testing & Failure 9 Efficiency 9 Design Improvement 10-11 Conclusion 12
  • 3. Introduction Architecture, not only consisting design concept, form and spatial quality but also the structure as it helps in constructing the architecture. As a successful architecture, structural strength of the architecture should be concerned during the design process. There are various types of supporting structure but skeletal structure construction are nowadays widely used in most of the architecture in the world as building support. Therefore, it is important for us as an architectural student to study how these skeletal structure works and influences the stability of an architecture. In this project, we are required to understand the skeletal structure and the components and how they work. In order to show our understanding, we were required to create a convincing structural model to show our understanding of how a structure works under a load.
  • 4. Design process Design 1 Triangular core to distributes load could be a very strong structure. The triangular core was pre- stressed to oppose the load force (mechanism of spring). The triangular core was joined with a square base to maximize the base area of the structure. The tip of the triangular core are faced up and down respectively at each level to distribute the load force evenly. The weakness of the structure is the absence of vertical structure. Design 2 The theory of pre-stress was still applied in this model. The square base provides larger base area and better stability. The square base also provides maximum number of pre-stressed column. Zigzag bracing were used to support beams meanwhile cross bracing used to maintain the form and prevent the structure to be twisted. This design has its potential and with proper bracing, it can be a very strong structure.
  • 5. Design 3 Squared base with 8 columns at each level produce a very strong structure. The columns are bended inwards a little to make sure it breaks inward. Therefore, there are square bracing inside to prevent the bended column from breaking. A-bracing is use for vertical bracing to support the beams and to prevent the square bracing inside from breaking. Each popsicles stick are supporting each other. This design distributes the load force to different direction so force becomes weaker and weaker.
  • 6. Design solution Learn how is a building’s fundamental work. Besides, we also learn about pre-stretch method. Explore how to tie to thing two string together to get maximum outcome. Learn how much loads that one popsicle stick can handle. Double square diagonal base The square diagonal base give good impact and give maximum strength to the base as supporter. The double layer of popsicle on the base support and giving stability to the vertical structure where are going to place it on the base. The mechanism is the double layer of the popsicle stick will clip the vertical structure so it giving more balance and stability. The 4 pre-stretch column The 4 pre-stretch column is giving a lot of benefit in a way to handle the load. The 4 column also became the connector between the ground level to the next level.The mechanism is using 8 popsicle stick as the vertical structures which tied together as two per column with leaving gap in between the structure to give a space for the popsicle stick to stretch and support each other when the load force down from the top.
  • 7. The balance slot in triangle bracing The triangle bracing is the usual bracing that the being used by construction as structure supporter nowadays. The slot in triangle bracing being bring into the skeletal structure. The slot in triangle bracing giving a lot of benefit and advantages. The center part is to help the triangle bracing keep stable. The mechanism is slot in the bracing that create a triangle shape that make the popsicle stick force each other and force it to the 4 pre-stretch column. the bracing we put it on 4 sided of the structures and it helps a lot on handle the load that force down to the structure. Consistency of tying the string Consistency is the most important thing on tying thing. For example this skeletal structure use string as connector if the consistency and the way of tying the string is not right so the structure and connection will decrease the strength and the stability of the structure. So for this skeletal structure the string tying has been set like the number of tying. The mechanism of tying system is the string come from all the sided and way with the same number of repetition with same loose-ness that given to every repetition.
  • 8. Force Analysis The characteristics of a Popsicle stick is experiment and tested. We realized that it actually can be bent, so it has a tensile property and we have decided to make use of it. In order to create a strong tower, we need to make use of all the possibilities of Popsicle stick. The idea is to create a model with tensile strength and using it to withstand the heavy load force and transfer it to other direction rather than just acting downwards. Pre-bent – To lead the force to the direction where it bends when force is exerted. This is to predict the direction where the Popsicle stick breaks and from there, reinforce it. A straight vertical column is unpredictable where the direction it breaks. Therefore it is difficult to control the direction of force. A horizontal beam is placed at both ends to hold them firmly and preventing them from shaking.( Shown in diagram beside) Load Force
  • 9. Another shorter pre-bent Popsicle stick is placed in between two pre-bent columns to carry the force transferred from the columns. By doing so, the originally weakest point of the column now separate the entire column into two, making it harder to bend. Just by adding a beam in the middle between two pre-bent columns significantly enhances the strength. The way it works is that the load force coming from top will compress the pre- bend columns. After a pre-bend beam is added in between the middle of two pre-bend columns, the heavy force transferred is reduced due to the tensile property countering the force. The reason of using a pre-bend beam is to make is easily bendable in its already bent position. This way it reduces the overall load force, like a spring. To further enhance it, an inverted ‘V’ shape bracing is used in all sides of the structure. Not only it shares the load by making use of the horizontal beam to transfer the load, it also prevents the whole structure to tilt to 1 side. Besides, it holds the shorter pre-bent beam from bending too much and break. The idea is to be able to reduce the load force and to direct the force experienced to all directions instead of just acting downwards. Load Load ForceForce
  • 10. Model Constructed and Detailed After finish testing mock up model which only giving unsatisfied result which became challenging thing to find out the problem and solve it with the 4 method. After found out the problem, the 4 method that became our specialty and best method to construct the skeletal structure. 84 popsicle stick is the number to construct the skeletal structure. after counting the popsicle stick start to weighing the structure which the weight reach exactly 100 grams and the height of the tower also reach the requirement height or the minimum height that has been stated which is 30 cm. First Experimental Model
  • 11. Model Testing & Failure The first testing is going smoothly. The structure handle 104 kilogram without cracking any of the popsicle stick or structure. Stop at 104 kilogram because out of loads at that time. After that, the lecturer require a test for submission. Unlucky the lecture only bring 40 kilogram load to the studio. After testing on studio the structure still can handle without cracking anything. So all of the group member doing the final test at gym which supply more loads. Then for the final test, the structure end up with satisfied result which can handle load more than 100 kilogram which exactly 108.75 kilogram. About the structure it’s not breaking the popsicle stick it’s only fall down because of the structure tilting at the moment and make the bracing all pop out from the place where it should be. Efficiency Efficiency = Height X Load_______________ Mass = _______________30.0 X 108.75 100 = 32.625
  • 12. Design improvement Our initial design was to use pre-stressed column to execute opposite force from the load. We used 8 columns for every level and stressed the sticks (to create the mechanism of spring). Then we have zigzag bracing as our vertical bracing and cross bracing for horizontal bracing. The methods of both bracing are slotted-in. It gives us unsatisfied result. We used 66 sticks and it breaks at 30KG. We replay the mock up video to observe and analysis how and why the model were crushed. We then knew that our structure was not crushed directly vertical because the upper structure actually slide off aside causing the middle structure to gets imbalanced and it crushed downwards. We checked on the crushed structure and noticed that there weren't any broken stick. The major problems are not the structure is weak itself, it was the positioning and equilibrium that twisted the structure. The structure did not maximize its load endurance. The factor behind the structure failure were the inappropriate bracing applied and inconsistency of workmanship caused the structure to be tilted aside.
  • 13. We got aware of the importance of workmanship therefore, we made up several systems and methods in model making to ensure every one using the same way. We then realised that the pre-stressed column are not as strong as pure vertical column so we changed our plan. We decided to stressed the stick a little inwards to force the stick to break inwards rather than using it as pre-stressed. This method ensured that if the column breaks, it would definitely break inwards. We then strengthen the inner side by adding bracing into the weakest point of the bended column which is the middle of the stick. Moreover, we improved our zigzag bracing to A-bracing. The A-bracing functioned as two; supporting the bracing of the bended column and to maintain the beam in its position. This method distributes the force from the load to many and different directions, minimizing the force each time it changes direction. We have improved from the theory of opposing its force to distributing load force to different directions.
  • 14. Conclusion In the conclusion, a lots of experiences and understandings have been gain through this structural model making. Throughout this project, we have learnt how a skeletal structure works under loading. In order to maximize the load handled by a structure, several experiments have been carried out. We have tried different ways of bracing, different way of tithing method and also different types of structure. After been through these experiments, we have learnt that bracings are needed to strengthen the structure as they play an important role in maintain the original shape of the structure. Besides that, our creativity have also been aroused to create different kinds of structure and test them to their limit. This project have indirectly help us to realize that how an organic structure can possibly construct in different skeletal structure.