The document discusses various control techniques used in project management including budgetary control, standard costing, break-even analysis, PERT, CPM, quality control and auditing. It provides examples of how to calculate earliest and latest start/finish times to determine the critical path of activities and amount of slack time using network diagrams. Control is important for ensuring plans are followed and performance is satisfactory.
This is PMBOK Guide Monitor and Control Process Group - Part Two. It includes six Knowledge Area - Project Time Management, Project Cost Management, Project Communications Management, Project Procurement Management, Project Stakeholder Management, and Project Risk Management - with six processes - Control Schedule, Control Costs, Control Communications, Control Control Procurements, Control Stakeholder Engagement and Control Risks -.
This is PMBOK Guide Monitor and Control Process Group - Part Two. It includes six Knowledge Area - Project Time Management, Project Cost Management, Project Communications Management, Project Procurement Management, Project Stakeholder Management, and Project Risk Management - with six processes - Control Schedule, Control Costs, Control Communications, Control Control Procurements, Control Stakeholder Engagement and Control Risks -.
This presentation was provided by Steph Pollock of The American Psychological Association’s Journals Program, and Damita Snow, of The American Society of Civil Engineers (ASCE), for the initial session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session One: 'Setting Expectations: a DEIA Primer,' was held June 6, 2024.
The simplified electron and muon model, Oscillating Spacetime: The Foundation...RitikBhardwaj56
Discover the Simplified Electron and Muon Model: A New Wave-Based Approach to Understanding Particles delves into a groundbreaking theory that presents electrons and muons as rotating soliton waves within oscillating spacetime. Geared towards students, researchers, and science buffs, this book breaks down complex ideas into simple explanations. It covers topics such as electron waves, temporal dynamics, and the implications of this model on particle physics. With clear illustrations and easy-to-follow explanations, readers will gain a new outlook on the universe's fundamental nature.
বাংলাদেশের অর্থনৈতিক সমীক্ষা ২০২৪ [Bangladesh Economic Review 2024 Bangla.pdf] কম্পিউটার , ট্যাব ও স্মার্ট ফোন ভার্সন সহ সম্পূর্ণ বাংলা ই-বুক বা pdf বই " সুচিপত্র ...বুকমার্ক মেনু 🔖 ও হাইপার লিংক মেনু 📝👆 যুক্ত ..
আমাদের সবার জন্য খুব খুব গুরুত্বপূর্ণ একটি বই ..বিসিএস, ব্যাংক, ইউনিভার্সিটি ভর্তি ও যে কোন প্রতিযোগিতা মূলক পরীক্ষার জন্য এর খুব ইম্পরট্যান্ট একটি বিষয় ...তাছাড়া বাংলাদেশের সাম্প্রতিক যে কোন ডাটা বা তথ্য এই বইতে পাবেন ...
তাই একজন নাগরিক হিসাবে এই তথ্য গুলো আপনার জানা প্রয়োজন ...।
বিসিএস ও ব্যাংক এর লিখিত পরীক্ষা ...+এছাড়া মাধ্যমিক ও উচ্চমাধ্যমিকের স্টুডেন্টদের জন্য অনেক কাজে আসবে ...
Strategies for Effective Upskilling is a presentation by Chinwendu Peace in a Your Skill Boost Masterclass organisation by the Excellence Foundation for South Sudan on 08th and 09th June 2024 from 1 PM to 3 PM on each day.
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Dr. Vinod Kumar Kanvaria
Exploiting Artificial Intelligence for Empowering Researchers and Faculty,
International FDP on Fundamentals of Research in Social Sciences
at Integral University, Lucknow, 06.06.2024
By Dr. Vinod Kumar Kanvaria
Executive Directors Chat Leveraging AI for Diversity, Equity, and InclusionTechSoup
Let’s explore the intersection of technology and equity in the final session of our DEI series. Discover how AI tools, like ChatGPT, can be used to support and enhance your nonprofit's DEI initiatives. Participants will gain insights into practical AI applications and get tips for leveraging technology to advance their DEI goals.
How to Build a Module in Odoo 17 Using the Scaffold MethodCeline George
Odoo provides an option for creating a module by using a single line command. By using this command the user can make a whole structure of a module. It is very easy for a beginner to make a module. There is no need to make each file manually. This slide will show how to create a module using the scaffold method.
it describes the bony anatomy including the femoral head , acetabulum, labrum . also discusses the capsule , ligaments . muscle that act on the hip joint and the range of motion are outlined. factors affecting hip joint stability and weight transmission through the joint are summarized.
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...Levi Shapiro
Letter from the Congress of the United States regarding Anti-Semitism sent June 3rd to MIT President Sally Kornbluth, MIT Corp Chair, Mark Gorenberg
Dear Dr. Kornbluth and Mr. Gorenberg,
The US House of Representatives is deeply concerned by ongoing and pervasive acts of antisemitic
harassment and intimidation at the Massachusetts Institute of Technology (MIT). Failing to act decisively to ensure a safe learning environment for all students would be a grave dereliction of your responsibilities as President of MIT and Chair of the MIT Corporation.
This Congress will not stand idly by and allow an environment hostile to Jewish students to persist. The House believes that your institution is in violation of Title VI of the Civil Rights Act, and the inability or
unwillingness to rectify this violation through action requires accountability.
Postsecondary education is a unique opportunity for students to learn and have their ideas and beliefs challenged. However, universities receiving hundreds of millions of federal funds annually have denied
students that opportunity and have been hijacked to become venues for the promotion of terrorism, antisemitic harassment and intimidation, unlawful encampments, and in some cases, assaults and riots.
The House of Representatives will not countenance the use of federal funds to indoctrinate students into hateful, antisemitic, anti-American supporters of terrorism. Investigations into campus antisemitism by the Committee on Education and the Workforce and the Committee on Ways and Means have been expanded into a Congress-wide probe across all relevant jurisdictions to address this national crisis. The undersigned Committees will conduct oversight into the use of federal funds at MIT and its learning environment under authorities granted to each Committee.
• The Committee on Education and the Workforce has been investigating your institution since December 7, 2023. The Committee has broad jurisdiction over postsecondary education, including its compliance with Title VI of the Civil Rights Act, campus safety concerns over disruptions to the learning environment, and the awarding of federal student aid under the Higher Education Act.
• The Committee on Oversight and Accountability is investigating the sources of funding and other support flowing to groups espousing pro-Hamas propaganda and engaged in antisemitic harassment and intimidation of students. The Committee on Oversight and Accountability is the principal oversight committee of the US House of Representatives and has broad authority to investigate “any matter” at “any time” under House Rule X.
• The Committee on Ways and Means has been investigating several universities since November 15, 2023, when the Committee held a hearing entitled From Ivory Towers to Dark Corners: Investigating the Nexus Between Antisemitism, Tax-Exempt Universities, and Terror Financing. The Committee followed the hearing with letters to those institutions on January 10, 202
This slide is special for master students (MIBS & MIFB) in UUM. Also useful for readers who are interested in the topic of contemporary Islamic banking.
A review of the growth of the Israel Genealogy Research Association Database Collection for the last 12 months. Our collection is now passed the 3 million mark and still growing. See which archives have contributed the most. See the different types of records we have, and which years have had records added. You can also see what we have for the future.
2. Controlling
Control consists in verifying whether everything occurs in
conformity with the plans, instructions and principles
established. – Henry Fayol
Control is checking current performance against pre-
determined standards contained in the plans, in order to
ensure adequate progress and satisfactory performance.
– E F LBrech
2
3. Features of Controlling
Controlling is a positive force.
Controlling is a dynamic and continuous process.
Controlling is goal-oriented.
Controlling is forward looking.
Control process is universal.
Control is based on planning.
Delegation is key to control.
3
5. Budgetary Control
Budgets are nothing but written plans or programs of
the future activities expressed in monetary terms.
Budgetary control is used to control the costs through
continuous appraisals of actual expenditures as against
planned costs expressed in a budget.
5
6. Budgetary Control Cont..
Maximization of profit
T
ool for measuring
performance
Reduced costs
Determine weaknesses
Corrective action
Revision required
Uncertain future
6
Depends
support
upon the
of top
management
Conflicts among the
departments
Advantages Limitations
7. Standard Costing
Standard costing is a method of estimating the right
cost or the most efficient cost of manufacturing a
product.
Standard costing is an important activity to determine
the efficiency of cost controlling in an industry.
7
8. Modern Control Techniques
1. Break-even analysis.
2. PERT - Program Evaluation ReviewTechnique
3. CPM - Critical Path Method
4. SQC - Statistical Quality Control
5. Internal audit
6. MIS - Management Information System
7. Quality circles
8
9. Break-Even Analysis
Break even analysis involves
understanding the costs involved
in producing a product and
thereby fix the selling price in
order to make a particular profit.
9
10. Break-Even Analysis Cont..
Break even analysis is used:
To find the effect of varying selling price upon profit.
Tofind the effect of fixed costs and variable cost upon
profit.
Tofind the minimum production required to break-even
i.e., no loss-no profit.
To compare two or more products with respect to their
profitability and cost of production.
Tofind what quantity of production leads to what costs.
10
11. PERT – Program Evaluation Review Technique
In PERT activities are
precedence relationships
11
shown as a network of
using activity-on-arrow
network construction
Multiple time estimates
Probabilistic activity times
Used in: Project management - for non-repetitive jobs
(research and development work), where the time and
cost estimates tend to be quite uncertain. This
technique uses probabilistic time estimates.
12. CPM – Critical Path Method
In CPM activities are shown as a network of
precedence relationships using activity-on-node
network construction
Single estimate of activity time
Deterministic activity times
Used in : Production management - for the jobs of
repetitive in nature where the activity time estimates
can be predicted with considerable certainty due to the
existence of past experience.
12
13. SQC – Statistical Quality Control
SQC involves the application of statistical techniques
to study deviation in actual performance against
established standards. The results are analyzed and
interpreted in order to help take corrective measures.
13
14. MIS – Management Information System
MIS is a computer based system that provides
information and support for effective managerial
decision making.
14
15. Internal Audit
An audit is a systematic and impartial examination,
analysis and appraisal of management’s overall
performance.
It is an independent and critical evaluation of the entire
management process.
An audit may be undertaken by the management itself
or it may be carried out with the help of management
consultants.
15
16. Quality Circles
A quality circle is a small group of employees who
meet periodically to identify, analyze and solve quality
and other work related problems in their area of
operation.
16
17. Other Control Techniques
1. Policies and procedures
2. Standing rules, limitation and orders
3. Self-control
4. Group control
5. Personal observations or MBWA
6. Disciplinary action
17
18. Policies
Policies are guidelines set up by the company for
managerial decision making.
‘A policy is a verbal, written or implied overall guide
setting up boundaries that supply the general limits and
directions in which managerial actions will take place’.
For Example,
Policy of recruiting only MBA’sfrom top 10 institutes.
Policy of promotion of in-house employees.
Policy on selling goods only for cash and not credit.
18
19. Procedures
Procedures are action guidelines which specify how
particular activity has to take place.
Procedures provide chronological step-by-step
sequence of required actions in order to achieve a
certain goal or policy.
A procedure lays down the manner and method by
which work is to be performed in a standard or uniform
way.
19
20. Standing Rules, Limitation and Orders
These act as important control devices. When sub -ordinates
are given freedom to make certain decisions on behalf of
superiors, it beomes necessary to lay down limits for them.
Standing orders are those which apply to every one in the
organization and which are helpful in having
discipline.
For Example: No smoking, No walking on the lawn etc.
20
21. Self Control
Self-Control means self-directed control.Aperson is given
freedom to set his own targets, evaluate his own
performance and take corrective measures as and when
required. Self-control is especially required for top level
managers because they do not like external control.
21
23. Personal Observations or MBWA
MBWA refers to a controlling techniques in which a
manager spends a significant amount of his time
regularly in the work area, and interacts directly with
employees.
Managing by walking around requires, personal
involvement, good listening skills, and the recognition
that most people in an organization want to contribute
to its success.
23
24. Disciplinary Action
Disciplinary action is a negative approach to
controlling function but nevertheless necessary.
Disciplinary action becomes effective when the
employees controlled are unskilled, rustic, brash, and
unweilding.
24
25. PERT and CPM Network Scheduling Problem
Basic Network Definitions,
Activity: Any portions of project (tasks) which required by
project, uses up resource and consumes time – may involve labor,
paper work, contractual negotiations, machinery operations
Event : Beginning or ending points of one or more activities,
instantaneous point in time, also called ‘nodes’
Network: Combination of all project activities and the events
Activity
Proceeding Successor
25
Event
26. Scheduling Activity: Problem1
Consider the scheduling activity,
26
Activity Immediate Predecessors Completion Time (Week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
27. Calculation of ES and EF Time (Problem 1)
Starting at the network’s origin (node 1) and using a
starting time of 0, we compute an earliest start (ES)
and earliest finish (EF) time for each activity in the
network.
The expression EF = ES + t can be used to find
the earliest finish time for a given activity.
For example, for activityA, ES = 0 and t = 5; thus the
earliest finish time for activityAis, EF = 0 + 5 =5
27
28. Arc with ES and EF Time (Problem 1)
1
ES = earliest start time
EF = earliest finish time
Activity
2
t = expected activity time
28
29. Network with ES and EF time (Problem 1)
1
4
2
5
7
6
D[5,8]
3
3
Earliest start time rule: The earliest start time for an
activity leaving a particular node is equal to the largest of
the earliest finish times for all activities entering the node.
29
30. Calculation of LS and LF (Problem 1)
To find the critical path we need a backward pass
calculation.
Starting at the completion point (node 7) and using a latest
finish time (LF) of 26 for activity I, we trace back through
the network computing a latest start (LS) and latest finish
time for each activity
The expression LS = LF – t can be used to calculate latest
start time for each activity. For example, for activity I, LF =
26 and t = 2, thus the latest start time for activity I is LS = 26
– 2 = 24.
30
31. Activity, Duration, ES, EF, LS and LF (Problem 1)
2
ES = earliest start time
EF = earliest finish time
Activity
3
LF = latest finish time
LS = latest start time
t = expected activity time
31
32. Network with ES, EF, LS and LF Time (Problem 1)
1
4
2
5
7
6
3
Latest finish time rule:
The latest finish time for an activity entering a particular node
is equal to the smallest of the latest start times for all
activities leaving the node.
32
34. Slack or Free Time or Float (Problem 1)
ES
5
LS EF
8 9
LF-EF= 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
LF
12
2
3
Slack is the length of time an activity can be delayed without affecting the
completion date for the entire project.
For example, slack for C = 3 weeks, i.e.Activity C can be delayed up to 3 weeks
34
(start anywhere between weeks 5 and 8).
35. Activity Schedule (Problem 1)
Activity Earliest
Start
(ES)
Latest
Start
(LS)
Earliest
Finish
(EF)
Latest
Finish
(LF)
Slack
(LS-ES)
Critical
Path
A 0 0 5 5 0 Yes
B 0 6 6 12 6 -
C 5 8 9 12 3 -
D 5 7 8 10 2 -
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3 -
I 24 24 26 26 0 Yes
35
36. Scheduling Activity: Problem2
Consider the scheduling activity,
36
Number Activity Predecessor Duration
1 Design house and obtain
financing
-- 3 months
2 Lay foundation 1 2 months
3 Order and receive materials 1 1 month
4 Build house 2,3 3 months
5 Select paint 2, 3 1 month
6 Select carpet 5 1 month
7 Finish work 4, 6 1 month
39. Network with ES and EF Time (Problem 2)
Initially for start node ES = 0 and then ES is calculated as follows,
ES = Maximum EF {immediate predecessor}
EF = ES + t
39
40. Network with ES, EF, LS and LF Time (Problem 1)
LF and LS is computed in backward pass, initially for last node
LF is equal to its EF, for rest of the nodes LF and LS are computed
as follows,
LS = LF – t and LF = Minimum LS {followingactivity}
40