The document outlines the erection sequence for an electro static precipitator (ESP). It involves assembling the ground assembly, erecting components like hoppers, casings, and frames. Electrodes and collecting plates are then erected and assembled. The pent house and rapping assembly are erected. Pre-commissioning activities are then carried out like air leak testing and gas distribution testing before final commissioning.