SlideShare a Scribd company logo
ULAN WEST
UNDERGROUND
GLENCORE
3.3kV back to back failure
Incident Summary
ULAN WEST
UNDERGROUND
GLENCORE
On the 3rd November 2017, During the installation and commissioning of LW04 face equipment, A shearer
supply 3.3kV flameproof back to back coupler and plug combination, located along the monorail,
catastrophically failed under load during start-up of the shearer drums.
The investigation concluded there was a high resistance joint between the thimbles and sockets resulting
in a catastrophic phase to phase fault within the restrained plug and back to back. The plug was ejected
from the back to back causing damage to the locking mechanism and the arc flash caused severe burning
of the back to back phase pins and melting of the phase pin insulation material.
A review of the electrical protection which failed to protect the 3.3kV restrained back to back coupler and
plug combination during the internal arcing fault was carried out, focusing on the protection design,
protection settings, fault levels, and clearing times.
3
Physical Layout
ULAN WEST
UNDERGROUND
GLENCORE
Monorail Layout Overview:
5
11kV DCB
Outbye (To Longwall Substation)410M
Inbye (To Longwall Shearer)
447M
Monorail Layout Overview:
6
3.3kV DCB11kV DCB
Outbye (To Longwall Substation)410M
Inbye (To Longwall Shearer)
447M
Monorail Layout Overview:
7
3.3kV DCB11kV DCB 3.3kV Back to Back
Outbye (To Longwall Substation)
49M
410M
Inbye (To Longwall Shearer)
447M
Monorail Layout Overview:
8
3.3kV DCB11kV DCB
Outbye (To Longwall Substation)
3.3kV Back to Back
3.3kV Back to Back
49M 41M
410M
Inbye (To Longwall Shearer)
447M
Monorail Layout Overview:
9
3.3kV DCB11kV DCB
3.3kV Back to Back
Outbye (To Longwall Substation)
Inbye (To Longwall Shearer)
3.3kV Back to Back
3.3kV Back to Back
49M 41M
41M
410M
447M
Monorail Layout Overview:
10
3.3kV DCB11kV DCB
INCIDENT LOCATION
Outbye (To Longwall Substation)
3.3kV Back to Back3.3kV Back to Back
3.3kV Back to Back
49M 41M
Inbye (To Longwall Shearer)
447M
Incident Scene – As Found
ULAN WEST
UNDERGROUND
GLENCORE
12
Looking Outbye
13
3.3kV Back to Back
14
Ejected Cable
15
Ejected Cable
16
Charing
Sprayed
Copper Slag
17
Sprayed
Copper Slag
18
Sprayed
Copper Slag
19
20
21
Missing Phase Pin
22
Locking Mechanism
Damaged But Remained
Locked In Place
23
Missing Phase Pin Found
Below Back to Back
Electrical Protection Layout
ULAN WEST
UNDERGROUND
GLENCORE
Electrical Protection Layout SLD
25
• There are four layers of
overcurrent protection inline
from the supply substation
(furtherst), to the 3.3kV supply
outlet (Closest)
Understanding The Fault - Electrical Protection Review
ULAN WEST
UNDERGROUND
GLENCORE
What Protection Operated?
Two overcurrent protection relays operated during the fault and one Earth Leakage Relay.
1. The LW 11/3.3kV substation 11kV CB Sepam OCR, tripped on Instantaneous overcurrent
27
What Protection Operated?
Two overcurrent protection relays operated during the fault and one Earth Leakage Relay.
1. The LW 11/3.3kV substation 11kV CB Sepam OCR, tripped on Instantaneous overcurrent
2. The LW 11/3.3kV Txf BUELR. This relay senses a 3.3kV earth fault and trips the 11kV CB.
28
What Protection Operated?
Two overcurrent protection relays operated during the fault and one Earth Leakage Relay.
1. The LW 11/3.3kV substation 11kV CB Sepam OCR, tripped on Instantaneous overcurrent
2. The LW 11/3.3kV Txf BUELR. This relay senses a 3.3kV earth fault and trips the 11kV CB.
3. The 3.3kV BSL DCB main bus protection OCR
29
Understanding The Fault –
Layers Of Protection Review
ULAN WEST
UNDERGROUND
GLENCORE
Layers of Protection Analysis – Incident Location
31
• Following the principles of EES005 – Protection Safety Factors:• Calculated Fault Level at incident location was 5.092kA
• All Protection relays were confirmed as set correctly as per the current protection design
• Following the principles of EES005 – Protection Safety Factors:
Layers of Protection Analysis – Incident Location
32
Operated Protection
• Calculated Fault Level at incident location was 5.092kA
• All Protection relays were confirmed as set correctly as per the current protection design
• Following the principles of EES005 – Protection Safety Factors:
Understanding The Fault –
Why didn't the closest protection relay operate?
ULAN WEST
UNDERGROUND
GLENCORE
What happened to the layers of Protection?
• Why didn’t the closest protection relay operate?
• The settings were all correct as per the current design
• The grading appeared sufficient
34
What happened to the layers of Protection?
35
• Why didn’t the closest protection relay operate?
Closest
Clearing Time Settings
36
Closest
Clearing Time Settings
37
Should have cleared
fault
Closest
What about the ACTUAL clearing time?
• A review was then conducted of protection relay operation and associated clearing times.
• The intent was to understand actual clearing times of faults based on the different hard wired circuit
arrangements in use, in order to better understand the incident energy that was clearly evident.
38
11kV Protection Relay - OPERATED
1.1 SS901 11kV side Sepam
Intentional Delay: 100mS
Sepam internal delay: 20mS
UV and S/T coils
Evolis CB 60mS
Total clearing time: 180mS
39
Closest
3.3kV BSL DCB outlets (dual feed) – DID NOT OPERATE
40
1.1 SS901 3.3kV BSL DCB outlets (dual feed)
Intentional Delay: 100mS
IPD Internal delay: 20mS
Finder relay (via MCR contact): 10mS
UV and S/T coils
Evolis CB 60mS
Total clearing time: 190mS
Closest
3.3kV BSL DCB Bus IPD protection - OPERATED
41
1.1 BSL DCB Bus IPD protection
Intentional Delay: 20mS
IPD Internal delay: 20mS
Finder relay: 10mS
Safety Relay: 60mS
UV and S/T coils
Evolis CB 60mS
Total clearing time: 170mSClosest
3.3kV Shearer Outlet – DID NOT OPERATE
42
1.1 Shearer Outlet
Intentional Delay: 100mS
IPD Internal delay: 20mS
Finder relay: 10mS
Safety Relay: 60mS
UV and S/T coils
Evolis CB 60mS
Total clearing time: 250mS
Closest
Set Versus Actuals
43
Closest
Set Versus Actuals
44
Closest
• Ulan West then engaged the original equipment manufacturer and an independent consultant to review
the current protection design, protection settings, and model the load flow to gain a better
understanding of:
• the prospective fault current,
• the arcing fault hazard based on these tripping times,
• and review the safety factors applied to protection settings
• Models were run on the current and proposed design changes.
• We focused on optimisation of the protection settings to minimising the protective circuitry time delays.
45
Conclusion – Protection Settings Optimisation
ULAN WEST
UNDERGROUND
GLENCORE
Protection Settings Optimisation
The protection as it was set for the system, operated correctly.
• The immediate improvement opportunity focused on was to reduce the incident energy by clearing the
fault quickly.
• All protective elements were able to gain improvements in clearing times of between 2.4 to 4 cycles and
this is reflected in the arc flash energy calculations.
• The results of the arc flash study show that at the cable plug fault point using a conservative working
distance of 300mm, and utilising the original settings, presented arcing energy of 27.87J/cm2, (Category
2 arcing fault).
• A final model was then used with the revised settings to demonstrate a reduction in the incident energy
to 14.06J/cm2 (Almost halving the incident energy), and the requirements drop to a Category 1 arcing
fault. (Standard U/G PPE)
47
Conclusion – Future Consideration
ULAN WEST
UNDERGROUND
GLENCORE
Our Future Consideration
• Challenge Protection Settings:
• Are they Optimised to make use of the latest protection relay software and functionality
• Are they actually ALARP
• Challenge Protection Circuit Design:
• Its easy to unintentionally accumulate in excess of
100mS of mechanical lag into an otherwise
“instantaneous” trip circuits through the addition
of indication, safety, or interposing relays.
• Do We Need More Layers of Protection
• The inclusion of Fault Limiting Fuses
• The Ultra Fast Earth Switch
49
OC Relay
Thankyou,
Peter Every-Burns
Special Thanks:
Jacob Brown, Tom Tyler, Daniel O’Keeffe, Roger Devery
ULAN WEST
UNDERGROUND
GLENCORE

More Related Content

What's hot

Daniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroomDaniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroom
NSW Environment and Planning
 
HMcK IEEE1584:2018 - What it Means
HMcK IEEE1584:2018 - What it MeansHMcK IEEE1584:2018 - What it Means
HMcK IEEE1584:2018 - What it Means
Brad Gradwell
 
Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002
Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002
Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002
Brad Gradwell
 
Annual report card Owen Barry
Annual report card   Owen BarryAnnual report card   Owen Barry
Annual report card Owen Barry
NSW Environment and Planning
 
Frank Conte Arc flash program
Frank Conte Arc flash programFrank Conte Arc flash program
Frank Conte Arc flash program
NSW Environment and Planning
 
Arc Flash Training
Arc Flash TrainingArc Flash Training
Arc Flash Training
Arc Flash Training
 
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeOverhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Transcat
 
Lightning Protection: Securing Higher Reliability and Meeting the New Standards
Lightning Protection: Securing Higher Reliability and Meeting the New StandardsLightning Protection: Securing Higher Reliability and Meeting the New Standards
Lightning Protection: Securing Higher Reliability and Meeting the New Standards
Sandia National Laboratories: Energy & Climate: Renewables
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
NSW Environment and Planning
 
VIV monitoring enhancing the safety of drilling operations in high current en...
VIV monitoring enhancing the safety of drilling operations in high current en...VIV monitoring enhancing the safety of drilling operations in high current en...
VIV monitoring enhancing the safety of drilling operations in high current en...
Pulse Structural Monitoring
 
Wellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case Study
Wellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case StudyWellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case Study
Wellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case Study
Pulse Structural Monitoring
 
GE Webinar: Oxygen Measurement for Chemical & Fuel Storage Safety
GE Webinar: Oxygen Measurement for Chemical & Fuel Storage SafetyGE Webinar: Oxygen Measurement for Chemical & Fuel Storage Safety
GE Webinar: Oxygen Measurement for Chemical & Fuel Storage Safety
Transcat
 
Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Electrical Condition monitoring part 1
Electrical Condition monitoring part 1
Vincent Wedelich, PE MBA
 
Condition monitoring of rotating machines ppt
Condition monitoring of rotating machines pptCondition monitoring of rotating machines ppt
Condition monitoring of rotating machines ppt
Rohit Kaushik
 
PAT NFPA 70E Compliance Presentation
PAT NFPA 70E Compliance PresentationPAT NFPA 70E Compliance Presentation
PAT NFPA 70E Compliance Presentation
Merci Flores-Magari
 
John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...
John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...
John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...
Sandia National Laboratories: Energy & Climate: Renewables
 
electrical plants & equipment's Condition Monitoring
electrical plants & equipment's Condition Monitoringelectrical plants & equipment's Condition Monitoring
electrical plants & equipment's Condition Monitoring
Marcep Inc.
 
Fault diagnosis of rotating machines using vibration
Fault diagnosis of rotating machines using vibrationFault diagnosis of rotating machines using vibration
Fault diagnosis of rotating machines using vibration
Yousof Elkhouly
 
E atomizer explosion 2013.10.26
E atomizer explosion 2013.10.26E atomizer explosion 2013.10.26
E atomizer explosion 2013.10.26
William R. Corcoran, Ph.D., P.E.
 
Asce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systemsAsce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systems
michaeljmack
 

What's hot (20)

Daniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroomDaniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroom
 
HMcK IEEE1584:2018 - What it Means
HMcK IEEE1584:2018 - What it MeansHMcK IEEE1584:2018 - What it Means
HMcK IEEE1584:2018 - What it Means
 
Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002
Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002
Hudson McKay - IEEE 1584:2018 vs IEEE 1584:2002
 
Annual report card Owen Barry
Annual report card   Owen BarryAnnual report card   Owen Barry
Annual report card Owen Barry
 
Frank Conte Arc flash program
Frank Conte Arc flash programFrank Conte Arc flash program
Frank Conte Arc flash program
 
Arc Flash Training
Arc Flash TrainingArc Flash Training
Arc Flash Training
 
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeOverhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by Amprobe
 
Lightning Protection: Securing Higher Reliability and Meeting the New Standards
Lightning Protection: Securing Higher Reliability and Meeting the New StandardsLightning Protection: Securing Higher Reliability and Meeting the New Standards
Lightning Protection: Securing Higher Reliability and Meeting the New Standards
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
 
VIV monitoring enhancing the safety of drilling operations in high current en...
VIV monitoring enhancing the safety of drilling operations in high current en...VIV monitoring enhancing the safety of drilling operations in high current en...
VIV monitoring enhancing the safety of drilling operations in high current en...
 
Wellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case Study
Wellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case StudyWellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case Study
Wellhead Fatigue Monitoring: Real-Time Drilling Riser Monitoring ROI Case Study
 
GE Webinar: Oxygen Measurement for Chemical & Fuel Storage Safety
GE Webinar: Oxygen Measurement for Chemical & Fuel Storage SafetyGE Webinar: Oxygen Measurement for Chemical & Fuel Storage Safety
GE Webinar: Oxygen Measurement for Chemical & Fuel Storage Safety
 
Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Electrical Condition monitoring part 1
Electrical Condition monitoring part 1
 
Condition monitoring of rotating machines ppt
Condition monitoring of rotating machines pptCondition monitoring of rotating machines ppt
Condition monitoring of rotating machines ppt
 
PAT NFPA 70E Compliance Presentation
PAT NFPA 70E Compliance PresentationPAT NFPA 70E Compliance Presentation
PAT NFPA 70E Compliance Presentation
 
John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...
John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...
John Schroeder - the Impact of Atmospheric Stability on Wind Structure and Tu...
 
electrical plants & equipment's Condition Monitoring
electrical plants & equipment's Condition Monitoringelectrical plants & equipment's Condition Monitoring
electrical plants & equipment's Condition Monitoring
 
Fault diagnosis of rotating machines using vibration
Fault diagnosis of rotating machines using vibrationFault diagnosis of rotating machines using vibration
Fault diagnosis of rotating machines using vibration
 
E atomizer explosion 2013.10.26
E atomizer explosion 2013.10.26E atomizer explosion 2013.10.26
E atomizer explosion 2013.10.26
 
Asce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systemsAsce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systems
 

Similar to EESS 2018 Day 1 - Peter Every-burns

Time current curves
Time current curvesTime current curves
Time current curves
Rabah Zaimeddine
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
michaeljmack
 
Insulation-Coordination-Fundamentals.pptx
Insulation-Coordination-Fundamentals.pptxInsulation-Coordination-Fundamentals.pptx
Insulation-Coordination-Fundamentals.pptx
SatriaThechildofgree
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
michaeljmack
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodination
michaeljmack
 
ms ppt.ppt
ms ppt.pptms ppt.ppt
ms ppt.ppt
RashmiSharma198147
 
DPL Transmission And Distribution
DPL Transmission And DistributionDPL Transmission And Distribution
DPL Transmission And Distribution
Subhojeet Sinha ☁
 
Slides 05
Slides 05Slides 05
Slides 05
Ryan Miller
 
Circuit Breakers Interrupting Capacity and Short-Time Current Rating
Circuit Breakers Interrupting Capacity and Short-Time Current Rating Circuit Breakers Interrupting Capacity and Short-Time Current Rating
Circuit Breakers Interrupting Capacity and Short-Time Current Rating
michaeljmack
 
L.v tech presentation 2
L.v tech presentation 2L.v tech presentation 2
Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacino
Gilberto Mejía
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
Surge current protection using superconductor ppt mahesh
Surge current protection using superconductor ppt maheshSurge current protection using superconductor ppt mahesh
Surge current protection using superconductor ppt mahesh
Kuldeep Singh
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
saurabhVEC
 
Electrical Installations, MCB, MCCB, ELCB
Electrical Installations, MCB, MCCB, ELCBElectrical Installations, MCB, MCCB, ELCB
Electrical Installations, MCB, MCCB, ELCB
MANOJ964697
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
Ritesh Kumawat
 
changwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DBchangwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DB
Sheikh Imran
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdf
ssuser564db8
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
rohit nadella
 
Components of LT Switchgear.pptx
Components of LT Switchgear.pptxComponents of LT Switchgear.pptx
Components of LT Switchgear.pptx
SwaroopMallick2
 

Similar to EESS 2018 Day 1 - Peter Every-burns (20)

Time current curves
Time current curvesTime current curves
Time current curves
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
 
Insulation-Coordination-Fundamentals.pptx
Insulation-Coordination-Fundamentals.pptxInsulation-Coordination-Fundamentals.pptx
Insulation-Coordination-Fundamentals.pptx
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodination
 
ms ppt.ppt
ms ppt.pptms ppt.ppt
ms ppt.ppt
 
DPL Transmission And Distribution
DPL Transmission And DistributionDPL Transmission And Distribution
DPL Transmission And Distribution
 
Slides 05
Slides 05Slides 05
Slides 05
 
Circuit Breakers Interrupting Capacity and Short-Time Current Rating
Circuit Breakers Interrupting Capacity and Short-Time Current Rating Circuit Breakers Interrupting Capacity and Short-Time Current Rating
Circuit Breakers Interrupting Capacity and Short-Time Current Rating
 
L.v tech presentation 2
L.v tech presentation 2L.v tech presentation 2
L.v tech presentation 2
 
Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacino
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Surge current protection using superconductor ppt mahesh
Surge current protection using superconductor ppt maheshSurge current protection using superconductor ppt mahesh
Surge current protection using superconductor ppt mahesh
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Electrical Installations, MCB, MCCB, ELCB
Electrical Installations, MCB, MCCB, ELCBElectrical Installations, MCB, MCCB, ELCB
Electrical Installations, MCB, MCCB, ELCB
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
 
changwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DBchangwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DB
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdf
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
 
Components of LT Switchgear.pptx
Components of LT Switchgear.pptxComponents of LT Switchgear.pptx
Components of LT Switchgear.pptx
 

More from NSW Environment and Planning

12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
NSW Environment and Planning
 
11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust
NSW Environment and Planning
 
09 learning from disasters
09 learning from disasters09 learning from disasters
09 learning from disasters
NSW Environment and Planning
 
13 explosives awareness
13 explosives awareness13 explosives awareness
13 explosives awareness
NSW Environment and Planning
 
10 incident reporting to the regulator 2020
10 incident reporting to the regulator 202010 incident reporting to the regulator 2020
10 incident reporting to the regulator 2020
NSW Environment and Planning
 
08 dust safety and health surveillance
08 dust safety and health surveillance08 dust safety and health surveillance
08 dust safety and health surveillance
NSW Environment and Planning
 
07 feedback and consultation
07 feedback and consultation07 feedback and consultation
07 feedback and consultation
NSW Environment and Planning
 
06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industry
NSW Environment and Planning
 
05 reviewing your SMS
05 reviewing your SMS05 reviewing your SMS
05 reviewing your SMS
NSW Environment and Planning
 
04. slinging and lifting equipment
04. slinging and lifting equipment04. slinging and lifting equipment
04. slinging and lifting equipment
NSW Environment and Planning
 
Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)
NSW Environment and Planning
 
Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)
NSW Environment and Planning
 
Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)
NSW Environment and Planning
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)
NSW Environment and Planning
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)
NSW Environment and Planning
 
Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)
NSW Environment and Planning
 
Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)
NSW Environment and Planning
 
Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)
NSW Environment and Planning
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)
NSW Environment and Planning
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...
NSW Environment and Planning
 

More from NSW Environment and Planning (20)

12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
 
11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust
 
09 learning from disasters
09 learning from disasters09 learning from disasters
09 learning from disasters
 
13 explosives awareness
13 explosives awareness13 explosives awareness
13 explosives awareness
 
10 incident reporting to the regulator 2020
10 incident reporting to the regulator 202010 incident reporting to the regulator 2020
10 incident reporting to the regulator 2020
 
08 dust safety and health surveillance
08 dust safety and health surveillance08 dust safety and health surveillance
08 dust safety and health surveillance
 
07 feedback and consultation
07 feedback and consultation07 feedback and consultation
07 feedback and consultation
 
06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industry
 
05 reviewing your SMS
05 reviewing your SMS05 reviewing your SMS
05 reviewing your SMS
 
04. slinging and lifting equipment
04. slinging and lifting equipment04. slinging and lifting equipment
04. slinging and lifting equipment
 
Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)
 
Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)
 
Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)
 
Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)
 
Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)
 
Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...
 

Recently uploaded

Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...
Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...
Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...
DAISY Global
 
Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...
Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...
Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...
DAISY Global
 
Find Sim Owner Details | +447490809237 | Paid Sim Details
Find Sim Owner Details | +447490809237 | Paid Sim DetailsFind Sim Owner Details | +447490809237 | Paid Sim Details
Find Sim Owner Details | +447490809237 | Paid Sim Details
ownerdetailssim
 
#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price
#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price
#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price
ownerdetailssim i11
 
Alauddin Trust | Charity Empowering People in Need
Alauddin Trust | Charity Empowering People in NeedAlauddin Trust | Charity Empowering People in Need
Alauddin Trust | Charity Empowering People in Need
contactalauddintrust
 
Verified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable Price
Verified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable PriceVerified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable Price
Verified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable Price
ownerdetailssim i11
 
Findlay Evans Waterproofing with AIW - Article April 2017
Findlay Evans Waterproofing with AIW - Article April 2017Findlay Evans Waterproofing with AIW - Article April 2017
Findlay Evans Waterproofing with AIW - Article April 2017
MELBOURNE Commercial Waterproofers - Findlay-Evans Waterproofing
 
OpenText Vulnerability Assessment & Penetration Testing
OpenText Vulnerability Assessment & Penetration TestingOpenText Vulnerability Assessment & Penetration Testing
OpenText Vulnerability Assessment & Penetration Testing
Marc St-Pierre
 
Findlay Evans Waterproofing with AIW - Article November 2017
Findlay Evans Waterproofing with AIW - Article November 2017Findlay Evans Waterproofing with AIW - Article November 2017
Findlay Evans Waterproofing with AIW - Article November 2017
MELBOURNE Commercial Waterproofers - Findlay-Evans Waterproofing
 
Findlay Evans Waterproofing with AIW - Article July 2019
Findlay Evans Waterproofing with AIW - Article July 2019Findlay Evans Waterproofing with AIW - Article July 2019
Findlay Evans Waterproofing with AIW - Article July 2019
MELBOURNE Commercial Waterproofers - Findlay-Evans Waterproofing
 
sim owner details | +923099554040 | sim owner details pakistan
sim owner details | +923099554040 | sim owner details pakistansim owner details | +923099554040 | sim owner details pakistan
sim owner details | +923099554040 | sim owner details pakistan
ownerdetailssim
 
Findlay Evans Waterproofing with AIW - Article August 2017
Findlay Evans Waterproofing with AIW - Article August 2017Findlay Evans Waterproofing with AIW - Article August 2017
Findlay Evans Waterproofing with AIW - Article August 2017
MELBOURNE Commercial Waterproofers - Findlay-Evans Waterproofing
 
How our Rebranding Succeeds in Instilling trust in Every Agri Citizen
How our Rebranding Succeeds in Instilling trust in Every Agri CitizenHow our Rebranding Succeeds in Instilling trust in Every Agri Citizen
How our Rebranding Succeeds in Instilling trust in Every Agri Citizen
Ninja Cart
 
BU毕业证书挂科购买
BU毕业证书挂科购买BU毕业证书挂科购买
BU毕业证书挂科购买
utasoba
 
QuickBooks Unrecoverable Error...........
QuickBooks Unrecoverable Error...........QuickBooks Unrecoverable Error...........
QuickBooks Unrecoverable Error...........
lilya092000
 
Discover the Art of Outdoor Spaces: Landscape Architects in Melbourne
Discover the Art of Outdoor Spaces: Landscape Architects in MelbourneDiscover the Art of Outdoor Spaces: Landscape Architects in Melbourne
Discover the Art of Outdoor Spaces: Landscape Architects in Melbourne
Outdoor Home Decor Company
 
BOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdf
BOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdfBOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdf
BOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdf
Ashwin Pk
 
Check CNIC Information | 03099554040 | CNIC Details Checker
Check CNIC Information | 03099554040 | CNIC Details CheckerCheck CNIC Information | 03099554040 | CNIC Details Checker
Check CNIC Information | 03099554040 | CNIC Details Checker
ownerdetailssim
 
The 5 Most Important Pipefitter Tools.pdf
The 5 Most Important Pipefitter Tools.pdfThe 5 Most Important Pipefitter Tools.pdf
The 5 Most Important Pipefitter Tools.pdf
SchulteSupply
 
9861615390 Satta Dpboss Sattamatka matka
9861615390 Satta Dpboss Sattamatka matka9861615390 Satta Dpboss Sattamatka matka

Recently uploaded (20)

Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...
Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...
Decentralized Crowdfunding with Professionals at DAISY_ Redefining Fundraisin...
 
Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...
Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...
Decentralized Crowdfunding vs. Traditional Crowdfunding_ A Comparison by Expe...
 
Find Sim Owner Details | +447490809237 | Paid Sim Details
Find Sim Owner Details | +447490809237 | Paid Sim DetailsFind Sim Owner Details | +447490809237 | Paid Sim Details
Find Sim Owner Details | +447490809237 | Paid Sim Details
 
#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price
#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price
#1 Call Girls in Mumbai || +919004268417 || Quick Booking at Affordable Price
 
Alauddin Trust | Charity Empowering People in Need
Alauddin Trust | Charity Empowering People in NeedAlauddin Trust | Charity Empowering People in Need
Alauddin Trust | Charity Empowering People in Need
 
Verified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable Price
Verified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable PriceVerified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable Price
Verified Call Girls Mumbai || +919920725232 || Quick Booking at Affordable Price
 
Findlay Evans Waterproofing with AIW - Article April 2017
Findlay Evans Waterproofing with AIW - Article April 2017Findlay Evans Waterproofing with AIW - Article April 2017
Findlay Evans Waterproofing with AIW - Article April 2017
 
OpenText Vulnerability Assessment & Penetration Testing
OpenText Vulnerability Assessment & Penetration TestingOpenText Vulnerability Assessment & Penetration Testing
OpenText Vulnerability Assessment & Penetration Testing
 
Findlay Evans Waterproofing with AIW - Article November 2017
Findlay Evans Waterproofing with AIW - Article November 2017Findlay Evans Waterproofing with AIW - Article November 2017
Findlay Evans Waterproofing with AIW - Article November 2017
 
Findlay Evans Waterproofing with AIW - Article July 2019
Findlay Evans Waterproofing with AIW - Article July 2019Findlay Evans Waterproofing with AIW - Article July 2019
Findlay Evans Waterproofing with AIW - Article July 2019
 
sim owner details | +923099554040 | sim owner details pakistan
sim owner details | +923099554040 | sim owner details pakistansim owner details | +923099554040 | sim owner details pakistan
sim owner details | +923099554040 | sim owner details pakistan
 
Findlay Evans Waterproofing with AIW - Article August 2017
Findlay Evans Waterproofing with AIW - Article August 2017Findlay Evans Waterproofing with AIW - Article August 2017
Findlay Evans Waterproofing with AIW - Article August 2017
 
How our Rebranding Succeeds in Instilling trust in Every Agri Citizen
How our Rebranding Succeeds in Instilling trust in Every Agri CitizenHow our Rebranding Succeeds in Instilling trust in Every Agri Citizen
How our Rebranding Succeeds in Instilling trust in Every Agri Citizen
 
BU毕业证书挂科购买
BU毕业证书挂科购买BU毕业证书挂科购买
BU毕业证书挂科购买
 
QuickBooks Unrecoverable Error...........
QuickBooks Unrecoverable Error...........QuickBooks Unrecoverable Error...........
QuickBooks Unrecoverable Error...........
 
Discover the Art of Outdoor Spaces: Landscape Architects in Melbourne
Discover the Art of Outdoor Spaces: Landscape Architects in MelbourneDiscover the Art of Outdoor Spaces: Landscape Architects in Melbourne
Discover the Art of Outdoor Spaces: Landscape Architects in Melbourne
 
BOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdf
BOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdfBOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdf
BOOST YOUR CREDIBILITY & TRUST WITH VIDEO TESTIMONIALS.pdf
 
Check CNIC Information | 03099554040 | CNIC Details Checker
Check CNIC Information | 03099554040 | CNIC Details CheckerCheck CNIC Information | 03099554040 | CNIC Details Checker
Check CNIC Information | 03099554040 | CNIC Details Checker
 
The 5 Most Important Pipefitter Tools.pdf
The 5 Most Important Pipefitter Tools.pdfThe 5 Most Important Pipefitter Tools.pdf
The 5 Most Important Pipefitter Tools.pdf
 
9861615390 Satta Dpboss Sattamatka matka
9861615390 Satta Dpboss Sattamatka matka9861615390 Satta Dpboss Sattamatka matka
9861615390 Satta Dpboss Sattamatka matka
 

EESS 2018 Day 1 - Peter Every-burns

  • 3. On the 3rd November 2017, During the installation and commissioning of LW04 face equipment, A shearer supply 3.3kV flameproof back to back coupler and plug combination, located along the monorail, catastrophically failed under load during start-up of the shearer drums. The investigation concluded there was a high resistance joint between the thimbles and sockets resulting in a catastrophic phase to phase fault within the restrained plug and back to back. The plug was ejected from the back to back causing damage to the locking mechanism and the arc flash caused severe burning of the back to back phase pins and melting of the phase pin insulation material. A review of the electrical protection which failed to protect the 3.3kV restrained back to back coupler and plug combination during the internal arcing fault was carried out, focusing on the protection design, protection settings, fault levels, and clearing times. 3
  • 5. Monorail Layout Overview: 5 11kV DCB Outbye (To Longwall Substation)410M Inbye (To Longwall Shearer) 447M
  • 6. Monorail Layout Overview: 6 3.3kV DCB11kV DCB Outbye (To Longwall Substation)410M Inbye (To Longwall Shearer) 447M
  • 7. Monorail Layout Overview: 7 3.3kV DCB11kV DCB 3.3kV Back to Back Outbye (To Longwall Substation) 49M 410M Inbye (To Longwall Shearer) 447M
  • 8. Monorail Layout Overview: 8 3.3kV DCB11kV DCB Outbye (To Longwall Substation) 3.3kV Back to Back 3.3kV Back to Back 49M 41M 410M Inbye (To Longwall Shearer) 447M
  • 9. Monorail Layout Overview: 9 3.3kV DCB11kV DCB 3.3kV Back to Back Outbye (To Longwall Substation) Inbye (To Longwall Shearer) 3.3kV Back to Back 3.3kV Back to Back 49M 41M 41M 410M 447M
  • 10. Monorail Layout Overview: 10 3.3kV DCB11kV DCB INCIDENT LOCATION Outbye (To Longwall Substation) 3.3kV Back to Back3.3kV Back to Back 3.3kV Back to Back 49M 41M Inbye (To Longwall Shearer) 447M
  • 11. Incident Scene – As Found ULAN WEST UNDERGROUND GLENCORE
  • 19. 19
  • 20. 20
  • 22. 22 Locking Mechanism Damaged But Remained Locked In Place
  • 23. 23 Missing Phase Pin Found Below Back to Back
  • 25. Electrical Protection Layout SLD 25 • There are four layers of overcurrent protection inline from the supply substation (furtherst), to the 3.3kV supply outlet (Closest)
  • 26. Understanding The Fault - Electrical Protection Review ULAN WEST UNDERGROUND GLENCORE
  • 27. What Protection Operated? Two overcurrent protection relays operated during the fault and one Earth Leakage Relay. 1. The LW 11/3.3kV substation 11kV CB Sepam OCR, tripped on Instantaneous overcurrent 27
  • 28. What Protection Operated? Two overcurrent protection relays operated during the fault and one Earth Leakage Relay. 1. The LW 11/3.3kV substation 11kV CB Sepam OCR, tripped on Instantaneous overcurrent 2. The LW 11/3.3kV Txf BUELR. This relay senses a 3.3kV earth fault and trips the 11kV CB. 28
  • 29. What Protection Operated? Two overcurrent protection relays operated during the fault and one Earth Leakage Relay. 1. The LW 11/3.3kV substation 11kV CB Sepam OCR, tripped on Instantaneous overcurrent 2. The LW 11/3.3kV Txf BUELR. This relay senses a 3.3kV earth fault and trips the 11kV CB. 3. The 3.3kV BSL DCB main bus protection OCR 29
  • 30. Understanding The Fault – Layers Of Protection Review ULAN WEST UNDERGROUND GLENCORE
  • 31. Layers of Protection Analysis – Incident Location 31 • Following the principles of EES005 – Protection Safety Factors:• Calculated Fault Level at incident location was 5.092kA • All Protection relays were confirmed as set correctly as per the current protection design • Following the principles of EES005 – Protection Safety Factors:
  • 32. Layers of Protection Analysis – Incident Location 32 Operated Protection • Calculated Fault Level at incident location was 5.092kA • All Protection relays were confirmed as set correctly as per the current protection design • Following the principles of EES005 – Protection Safety Factors:
  • 33. Understanding The Fault – Why didn't the closest protection relay operate? ULAN WEST UNDERGROUND GLENCORE
  • 34. What happened to the layers of Protection? • Why didn’t the closest protection relay operate? • The settings were all correct as per the current design • The grading appeared sufficient 34
  • 35. What happened to the layers of Protection? 35 • Why didn’t the closest protection relay operate? Closest
  • 37. Clearing Time Settings 37 Should have cleared fault Closest
  • 38. What about the ACTUAL clearing time? • A review was then conducted of protection relay operation and associated clearing times. • The intent was to understand actual clearing times of faults based on the different hard wired circuit arrangements in use, in order to better understand the incident energy that was clearly evident. 38
  • 39. 11kV Protection Relay - OPERATED 1.1 SS901 11kV side Sepam Intentional Delay: 100mS Sepam internal delay: 20mS UV and S/T coils Evolis CB 60mS Total clearing time: 180mS 39 Closest
  • 40. 3.3kV BSL DCB outlets (dual feed) – DID NOT OPERATE 40 1.1 SS901 3.3kV BSL DCB outlets (dual feed) Intentional Delay: 100mS IPD Internal delay: 20mS Finder relay (via MCR contact): 10mS UV and S/T coils Evolis CB 60mS Total clearing time: 190mS Closest
  • 41. 3.3kV BSL DCB Bus IPD protection - OPERATED 41 1.1 BSL DCB Bus IPD protection Intentional Delay: 20mS IPD Internal delay: 20mS Finder relay: 10mS Safety Relay: 60mS UV and S/T coils Evolis CB 60mS Total clearing time: 170mSClosest
  • 42. 3.3kV Shearer Outlet – DID NOT OPERATE 42 1.1 Shearer Outlet Intentional Delay: 100mS IPD Internal delay: 20mS Finder relay: 10mS Safety Relay: 60mS UV and S/T coils Evolis CB 60mS Total clearing time: 250mS Closest
  • 45. • Ulan West then engaged the original equipment manufacturer and an independent consultant to review the current protection design, protection settings, and model the load flow to gain a better understanding of: • the prospective fault current, • the arcing fault hazard based on these tripping times, • and review the safety factors applied to protection settings • Models were run on the current and proposed design changes. • We focused on optimisation of the protection settings to minimising the protective circuitry time delays. 45
  • 46. Conclusion – Protection Settings Optimisation ULAN WEST UNDERGROUND GLENCORE
  • 47. Protection Settings Optimisation The protection as it was set for the system, operated correctly. • The immediate improvement opportunity focused on was to reduce the incident energy by clearing the fault quickly. • All protective elements were able to gain improvements in clearing times of between 2.4 to 4 cycles and this is reflected in the arc flash energy calculations. • The results of the arc flash study show that at the cable plug fault point using a conservative working distance of 300mm, and utilising the original settings, presented arcing energy of 27.87J/cm2, (Category 2 arcing fault). • A final model was then used with the revised settings to demonstrate a reduction in the incident energy to 14.06J/cm2 (Almost halving the incident energy), and the requirements drop to a Category 1 arcing fault. (Standard U/G PPE) 47
  • 48. Conclusion – Future Consideration ULAN WEST UNDERGROUND GLENCORE
  • 49. Our Future Consideration • Challenge Protection Settings: • Are they Optimised to make use of the latest protection relay software and functionality • Are they actually ALARP • Challenge Protection Circuit Design: • Its easy to unintentionally accumulate in excess of 100mS of mechanical lag into an otherwise “instantaneous” trip circuits through the addition of indication, safety, or interposing relays. • Do We Need More Layers of Protection • The inclusion of Fault Limiting Fuses • The Ultra Fast Earth Switch 49 OC Relay
  • 50. Thankyou, Peter Every-Burns Special Thanks: Jacob Brown, Tom Tyler, Daniel O’Keeffe, Roger Devery ULAN WEST UNDERGROUND GLENCORE