SlideShare a Scribd company logo
Insulation Coordination
Fundamentals
Nema 8LA
Rev 0 01-16-2019
Webinar Outline
 Initial basics of Insulation Coordination Studies
 Definitions , Types, Parameters, Purposes
 Examples of an Insulation Coordination Study
 Basic Substation , Complex Substation, Transmission Line
 BIL,BSL
 The Backflash
 Traveling Wave Phenomena
 Arrester Fundamentals
 Margin of Protection
 Ground Flash Density
 The Report
Resources for this Webinar
1. Book: “Insulation Coordination of Power
Systems” by Andrew (Bob) Hileman, 1999.
2. AR Hileman Software
3. ATP and ATP Draw, XY Plot
4. IEC 60071-1,2,3,4
5. IEEE C62.82.1 and .2 Formerly 1313.1 and .2
(Insulation Coordination Standards)
6. IEEE C62.11 Arrester Test Standards
7. IEEE C62.22 Arrester Application Guide
8. IEEE 1410 and 1243 Improving Lightning
Performance of lines
Definition of Insulation Coordination
Simple Definition
Insulation coordination is the selection of the insulation
strength of a system. (Hileman)
Better One
Insulation coordination is the process where the insulation
characteristics of all components of the power system are
determined, specified and coordinated to avoid failure due
to expected internal and externally occurring surges.
(Hileman)
Arrester
Insulator
Types of Insulation Coordination Studies
 Transformer Protection
 Substation Protection Open Air and GIS
 Line Protection
 Distribution and Transmission
 Breaker Protection
 Generator Protection
 Determine clearances
 Determine Separation Distances
 Determine Arrester Energy and Voltage Ratings.
 And on and on and on
Types of Insulation Coordination Studies
 Deterministic
This is the conventional method where the minimum strength of
the insulation is equal or greater than the maximum surge stresses.
.
Transformer insulation is not
statistical in nature. It has one
lightning withstand value and
one switching withstand value.
Therefore a deterministic
analysis is all that we can do.
Types of Insulation Coordination Studies
 Probabilistic
This type of analysis consists of selecting the insulation level and
clearances based on specific reliability criterion. Since the insulation
strength of air is statistical in nature, we can only determine its
probability of Flashover for a given surge.
Studies of transmission line performance is based on a flashover
rate per year per 100km, and because the flashover parameter is
statistical, resulting levels are probabilistic.
Studies of substation performance is also probabilistic for the
same reason. For this type of study we base the performance on
MTBF (Mean Time Between Flashover). More later on this.
Types of Insulation Coordination Studies
 Lightning Surge Studies
This type of study deals strictly with lightning surges and backflash over
surges. Is completed for all system voltage levels.
 Switching Surge Studies
This type of study is usually for systems above 240kV since it is this type
of system that can produce switching surges of relevance.
If a lower voltage system has large cap banks, then a switching study is
justified.
Parameters of Importance in Studies
• Purpose of Study
• The Lightning Flash
• Ground Flash Density
• Shield Failure rate if known
• Types of Insulation
• BIL and CFO
• MTBS and MTBF
• Location and Altitude of Study
• Cable and Isophase specs
• Incoming Surge Steepness
• Backflash Rate (BFR)
• Calculating BFR
• Tower Configurations
• Circuit Physical Dimensions
• The Transformer Ratings and
Capacitance
• The Arrester
• VI Curve
• Selecting the Rating
Purpose of Insulation Coordination Studies
 Can be to design proper insulation and arrester location from scratch
 Can be to validate chosen insulation levels (Very common)
 Can be to determine where to locate arresters
 Can be to determine cause of failure of equipment (After an incident)
 Can be to determine the Width of a ROW (Switching Study)
 Can be to provide assurance that equipment is protected properly
 Can be to put in the file for future reference
 Can be to fulfill a requirement
 Can be to …………. and more……
Examples of Lightning Studies
 Simple Substation from Chapter 12 of “Insulation
Coordination of Power Systems”.
 500kV Line-Substation-Generator
 69kV Line Study

Breaker
Disconnect
Switch
CT or CCVT
Station
Arresters
Power
Transformer
Overhead Shield Wire
Basic Substation
Lightning Study
Incoming Surge
Surge at Trans
Complex Study
Complex Insulation Coordination Study
Incoming
Line
Switchyard with
no
transformers
Cross over line
to Generator
Station
3 generator step
up Transformers
Three generators
69kV Sub
69kV Sub Transmission Line Study
69kV Sub Transmission Line Study
69kV Sub Transmission
Line Study
Insulator that flashes
over at a specific voltage
Underbuilt Circuit
System Fundamentals Relative to Insulation
Coordination
1. Insulation
2. Traveling Waves and
Reflections, Backflash, and
Separation Distance
3. Tower Grounds and Station
Grounds
4. Corona
5. Steepness of Surges
6. Clearances
7. Physical Dimensions
8. Ground Flash Density
9. OHGW
10. Ground Flash Density
 External Insulation
The distance in open air or across
the surfaces of solid insulation in
contact with open air that is
subjected to dielectric stress and to
the effects of the atmosphere.
Examples are porcelain or polymer
shell of a bushing, support
insulators, and disconnecting
switches.
 Self-restoring Insulation
Insulation that completely recovers
insulating properties after a
disruptive discharge (flashover)
caused by the application of a
voltage. This is generally external
insulation.
Self restoring
Insulator
Terminator with
Self-restoring
Insulation on outside
and non-self-restoring
on inside
Underground Cable with
Non-Self Restoring
Insulation
Internal Insulation
The internal solid, liquid, or
gaseous parts of the insulation of
equipment that are protected by
equipment enclosures from the
effects of the atmosphere.
Examples are transformer
insulation, internal insulation of
bushings, internal parts of
breakers and internal part of any
electrical equipment.
Non-self-restoring Insulation
Insulation that loses insulating
properties or does not recover
completely after a disruptive
discharge caused by the
application of voltage. Generally
internal insulation.
Self Restoring
Insulation
Non-Self Restoring
Insulation
Basic Lightning Impulse Insulation
Level (BIL)
The BIL level is the Dry insulation
withstand strength of insulation
expressed in kV. Is commonly used to
describe substations and distribution
system voltage withstand
characteristics.
 Statistical BIL is used for insulators means there is a
10% probability of flashover and is used for self-
restoring insulation
 Conventional BIL is used for Transformers and
Cable
is the voltage level where there is a 0% probability of
Flashover and is applied to non selfrestoring insulation
Insulator BIL is directly proportional to the
strike distance of an insulator
BIL ≈ 15kV x S(inches)
And is affected by Altitude
Note 1: Arresters do not have a BIL rating
since their external insulation is self protected
by the internal MOV disks. In a sense they
have an infinite BIL.
Note 2: Arresters close to an insulator give
the insulator infinite BIL.
Basic Switching Impulse Insulation
Level (BSL)
The BSL level is the switching surge
withstand level of the insulation in
terms of kV.
BSLs are universally tested under
Wet conditions.
 Statistical BSL of Insulators
apply to self restoring insulation and represents a 10%
probability of flashover.
 Conventional BSL of Transformers and solid
dielectrics
apply to non-self-restoring insulation and represents a 0%
probability of flashover
BSL is proportional to the strike
distance of an insulator
BSL= 1080e((0.46 x Strike Distance) + 1)
And is affected by Altitude
Note 1: Arresters do not have a BSL rating
since their external insulation is self
protected by the internal MOV disks. In a
sense they have an infinite BSL.
Note 2: Arresters close to an insulator give
the insulator infinite BSL.
Power Frequency Withstand Voltage
This is the highest power frequency
voltage an insulator can withstand under
wet conditions (low level of
contamination).
It is affected by creepage distance and strike distance.
Note 2: Arresters will go into conduction if
the AC voltage across the unit reaches a 1.25
pu MCOV and above. However they cannot
sustain this condition for very long or they
will over heat and fail.
Note 3: If the housing is highly contaminated,
the housing may flashover at levels below the
turn-on voltage of the arrester.
Note 4: In highly contaminated areas, extra
creepage distance insulators are used to
overcome this potentially low flashover
voltage. The same policy should be applied
to arresters.
Note 1: Insulator withstand voltages are
often >2-3 times their operating voltage.
Critical Flash Over (CFO) Self Restoring insulation only
This is the voltage with a 50% probability of flashover of the
insulator. It applies to both lightning and switching. It is used to
quantify insulation used on transmission and distribution lines.
Typically CFO is 4-6% higher than Statistical BIL on an insulator.
Chopped Wave Withstand (CWW)
This is a withstand level of equipment. A standard lightning
impulse is used but the surge is chopped at 3us, which means the
stress is applied for a much shorter time than a standard lightning
impulse test and must flashover near the crest of the wave instead
of on the tail as it can in BIL tests. The value of this characteristic is
about 1.10 times BIL for power transformers and 1.15 times BIL for
bushings.
Caused by insulator flashover just past crest.
Can cause winding to winding stress in some
transformers
CWW
Chopped Wave Withstand
BIL
Basic Impulse Withstand Level
BSL
Basic Switching Impulse
Withstand Level
Typical Values 70-1500kVp
Another form of Lightning
withstand is CFO
Critical Flashover Voltage
The Backflash
When the OHGW on a
transmission line is hit by
lightning, a rapid series of events
takes place.
If the system is grounded well than
the surge is transferred to earth
and there is no effect on the phase
conductors.
But occasionally a backflash will
occur, this series of slides will show
you a close up view of the
sequence of events.
The Backflash
Time = 0
The first event is the strike. Of
course there was already a great
deal of activity just to connect this
line to the cloud, but that is for
another sequence.
When the strike pins to the wire, it
sets up a voltage surge that travels
in both directions down the line.
(1-50 million volts)
This is all happening at nearly the
speed of light and until the surge
actually finds ground, there is little
current flow.
The Backflash
Time = 1
In a few Nano-seconds, the voltage front
meets the down ground and travels toward
earth at the tower bottom. While at the
same time it is inducing a voltage on to the
phase conductors
When it reaches earth, the current begins
to flow.
The voltage along the tower increases
rapidly due to ground potential rise. This
potential rise is caused by the resistance of
the ground rod of the tower.
This tower voltage rises as the current
begins to flow.
Induced
Induced
The Backflash
Time = 2
The voltage at the base of the base
of the insulators and on the phase
conductors increases as the surge
increases in amplitude
If the voltage at the base of the
insulator increases at a faster rate
than the induced voltage on
phases, it can reach the CFO of the
insulator
The Backflash
Time = 3
The voltages continue to increase
across all components as the surge
crests.
The Backflash
Time = 4 (.5-2 µsec)
If the voltage across the insulator exceeds the
CFO, it can flashover from the pole down ground
to the phase.
This is the backflash……
It flashes from the base to the conductor which is
intuitively backward since the down ground
spends its entire life except for these few
microseconds at ground potential.
This is the part of the event that we are interested
in with insulation coordination studies. What
effect this surge will have the substation.
But its not over yet…..
The Backflash
Time = 5 (20-50 µsec)
The lightning stroke is over and
the voltages on the lines revert
back to their pre-strike levels. But
the air around the insulator is
seeping with ions and still highly
conductive.
When the AC voltage reaches a
high enough level, it now flashes
forward from the phase conductor
to the down ground.
The Backflash
Time = 6 (50 µsec to 200ms)
When the insulator flashes over for a
second time, power frequency current
flows to ground and a fault is now
underway on the circuit and will remain
there until a breaker interrupts the
event.
At that point the event is over assuming
no damage occurred on the insulator.
AC Follow current
causing a Line to
Ground Fault
Until breaker
interrupts
The Backflash
The surge that is transferred onto the phase
conductor has entered the station within a few
µsec, even before the fault was initiated.
This is the impulse that becomes the concern of
insulation coordination in substations.
Note the voltage at the
transformer is clamped by
the arresters.
Arresters
CCVTs
Arresters
Note the voltage at the
transformer is higher than
at the arresters. This is due
to traveling wave reflection
Red = Voltage @ Arrester
Green = Voltage @ Transformer
3 m separation
30 m separation
Separation
Distance
Arresters
the other half of
Insulation
Coordination
Arrester Definition
• Polymer Housing
• Metal Oxide Varistor
(MOV)
• Conductive Spacer
• Strength Member
(Fiberglass)
• Spring for Compression
• Rubber Seals
• End Vents and Diaphragms
VI Characteristics of an Arrester or Disk is the essence of the MOV.
The resistance of the MOV disk is a function of the voltage stress
across the terminals.
Example
50kV MCOV
Arrester
Typical Varistor/Arrester
V-I Characteristics
|---------------------- Breakdown Region--------------------------------|
Pre-Breakdown
Region
|--------------------------------------|
High Current Region
|---------------------------------------|
Leakage Current Region
V1ma or Reference Voltage
Region
TOV Region
Switching
Surge
Region
Lightning
Impulse
Region
Normal Operating Region
20C
200C
Physicists Terminology
Engineering Terminology
Vref or Uref
V10kA or
U10kA
MCOV or UC (peak)
Rated V or Ur peak
LPL
SPL
Arrester Discharge
Voltage Curve
Fast Front
Voltage
10kA Lightning
Protective Level
LPL
Switching Surge Protective Level
SPL
Faster Front Surges Slower Front Surges
Insulation Withstand
Curve
Arrester Discharge
Voltage Curve
Chopped Wave
Withstand CWW
Front of Wave
Voltage
FOW
BSL
BIL
10kA Lightning
Protective Level
LPL
Switching Surge Protective
Level
SPL
MP1= (CWW/FOW)-1
MP2= (BIL/LPL)-1
MP3= (BSL/SPL)-1
IEEE recommends > .15 or 15%
IEEE recommends >.15 or 15%
IEEE recommends >.20 or 20%
Clearances and Altitude
Phase to phase and phase to ground clearances
are often the purpose of a study.
They are easily calculated once the maximum
voltage on a line is determined.
With arresters, the NEC clearances can be
reduced near the arrester and along ROW if
studies are completed.
For example,
Lightning Impulse withstand
of Air at STP is a linear
function at 450kV/m
Clearance and Altitude/Elevation
0.600
0.650
0.700
0.750
0.800
0.850
0.900
0.950
1.000
0 2000 4000 6000 8000 10000 12000
Ratio
of
Altitude
to
Sea
Level
Elevation in Feet
Change in
Withstand voltage
'δ=e-A/26710
All external insulation is
affected by altitude.
Specifically in this case, the
clearance between lines
needs to be increased to
attain the same withstand
voltage at sea level.
Physical Dimensions
V
V
30 0m
NC
V
25 meters
V
2 m
AFram
LineA
5 ohms
LCC
R(i)
R(i)
Sourc
V
2uh 2 meters
5 ohms
L_imp H
L_Imp
LCC
I
V
R(i)
I
230kV
200 m
NC
20 m 2 m
Ej 230/13.8
BCT
Y
Et
V
Ea
R(i)
R(i)
R(i)
I
6.3nF
3m
Eb
V
Insulation Coordination of Power Systems
by Andrew Hileman
Line Entrance
Arrester
Transformer
Arrester
Flashover of
C-Phase close
to substation
6000ft 2000 ft 2000 ft
Surges travel at ~980ft per µs on
an overhead line.
In this elongated station, It can be
seen here that the surge first
appears at the metered points at
different times based on the
distance from the initial surge.
Backflash
6000 ft out
on the line
At Station
Entrance
At
Breaker
At
Arrester
Elongated Substation
Ground Flash Density
Ground Flash Density
Is used to calculate the
• Backflash rate on a line
• The challenge rate to a line
• The outage rate of lines
• Steepness of a surge on a line
• The MTBF of a substation
The Insulation Coordination Study Report
Webinar Overview
Subjects covered
1. Definitions
2. Examples of Studies
3. Insulation Fundamentals
4. Backflash Concept
5. Traveling Wave Concept
6. Arrester Fundamentals
7. Clearances and Physical Dimensions
8. Lighting Ground Flash Densities
9. The Report

More Related Content

What's hot

ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
Himmelstern
 
ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12
Himmelstern
 
Instalacion electrica y sistema puesta a tierra calvo
Instalacion electrica y sistema puesta a tierra calvoInstalacion electrica y sistema puesta a tierra calvo
Instalacion electrica y sistema puesta a tierra calvo
Monito Solo Rap
 
Cálculo de sistema a tierra
Cálculo de sistema a tierraCálculo de sistema a tierra
Cálculo de sistema a tierra
Karla Salami
 
Caida de tension trifasica
Caida de tension trifasicaCaida de tension trifasica
Caida de tension trifasica
71rudy
 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
Himmelstern
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Power System Operation
 
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATIONAUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
Power System Operation
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
SARAVANAN A
 
Breaker_Failure_Protection.ppt
Breaker_Failure_Protection.pptBreaker_Failure_Protection.ppt
Breaker_Failure_Protection.ppt
Thien Phan Bản
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protection
SaifUrrehman183
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1
Himmelstern
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.
Parth Patel
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
SARAVANAN A
 
Manual de sistemas de protecciones
Manual de sistemas de proteccionesManual de sistemas de protecciones
Manual de sistemas de protecciones
Alejandro Alfonso
 
Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - Example
Leonardo ENERGY
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
Power System Operation
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
Shaik Abdullah Adam
 

What's hot (20)

ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
 
ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12
 
Instalacion electrica y sistema puesta a tierra calvo
Instalacion electrica y sistema puesta a tierra calvoInstalacion electrica y sistema puesta a tierra calvo
Instalacion electrica y sistema puesta a tierra calvo
 
75181713.pdf
75181713.pdf75181713.pdf
75181713.pdf
 
Cálculo de sistema a tierra
Cálculo de sistema a tierraCálculo de sistema a tierra
Cálculo de sistema a tierra
 
Caida de tension trifasica
Caida de tension trifasicaCaida de tension trifasica
Caida de tension trifasica
 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
 
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATIONAUTO-RECLOSING & LOCAL SYSTEM RESTORATION
AUTO-RECLOSING & LOCAL SYSTEM RESTORATION
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
 
Breaker_Failure_Protection.ppt
Breaker_Failure_Protection.pptBreaker_Failure_Protection.ppt
Breaker_Failure_Protection.ppt
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protection
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.
 
Coluna montante
Coluna montanteColuna montante
Coluna montante
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
 
Manual de sistemas de protecciones
Manual de sistemas de proteccionesManual de sistemas de protecciones
Manual de sistemas de protecciones
 
Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - Example
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
 

Similar to Insulation-Coordination-Fundamentals.pptx

Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacino
Gilberto Mejía
 
Electrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltageElectrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltage
Power System Operation
 
Short-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptShort-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.ppt
JatmylHarnero1
 
[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf
[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf
[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf
williamaro2
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordinationRui Zhang
 
Electrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAPElectrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAPJorge I. Villacis Gallo
 
03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer
prasadkappala
 
The sheath voltage_limiter
The sheath voltage_limiterThe sheath voltage_limiter
The sheath voltage_limiter
Gilberto Mejía
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
rohit nadella
 
Ce31533536
Ce31533536Ce31533536
Ce31533536
IJERA Editor
 
Gss report
Gss reportGss report
Gss report
utkarsh saxena
 
Switchgear.pptx
Switchgear.pptxSwitchgear.pptx
Switchgear.pptx
satabdi8
 
PSG_unit3_motor protection.ppt
PSG_unit3_motor protection.pptPSG_unit3_motor protection.ppt
PSG_unit3_motor protection.ppt
RajaDesingu2
 
Ch6 import
Ch6 importCh6 import
Ch6 importphamly10
 
Tecnical aplicacion1 abb
Tecnical aplicacion1 abbTecnical aplicacion1 abb
Tecnical aplicacion1 abbisaac diaz said
 
Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)
Dhrumil Maniar
 
30167865-Short-Circuit-Ppt-Slides.ppt
30167865-Short-Circuit-Ppt-Slides.ppt30167865-Short-Circuit-Ppt-Slides.ppt
30167865-Short-Circuit-Ppt-Slides.ppt
HassanAli10937
 
Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)
Jaydeep Chauhan
 
newswitchgearandprotection-130925105559-phpapp02.pptx
newswitchgearandprotection-130925105559-phpapp02.pptxnewswitchgearandprotection-130925105559-phpapp02.pptx
newswitchgearandprotection-130925105559-phpapp02.pptx
DrNiveditaSingh3
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdf
ssuser564db8
 

Similar to Insulation-Coordination-Fundamentals.pptx (20)

Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacino
 
Electrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltageElectrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltage
 
Short-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptShort-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.ppt
 
[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf
[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf
[Gönen,_Turan]_Electrical_power_transmission_system2-95-132.pdf
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination
 
Electrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAPElectrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAP
 
03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer
 
The sheath voltage_limiter
The sheath voltage_limiterThe sheath voltage_limiter
The sheath voltage_limiter
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
 
Ce31533536
Ce31533536Ce31533536
Ce31533536
 
Gss report
Gss reportGss report
Gss report
 
Switchgear.pptx
Switchgear.pptxSwitchgear.pptx
Switchgear.pptx
 
PSG_unit3_motor protection.ppt
PSG_unit3_motor protection.pptPSG_unit3_motor protection.ppt
PSG_unit3_motor protection.ppt
 
Ch6 import
Ch6 importCh6 import
Ch6 import
 
Tecnical aplicacion1 abb
Tecnical aplicacion1 abbTecnical aplicacion1 abb
Tecnical aplicacion1 abb
 
Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)
 
30167865-Short-Circuit-Ppt-Slides.ppt
30167865-Short-Circuit-Ppt-Slides.ppt30167865-Short-Circuit-Ppt-Slides.ppt
30167865-Short-Circuit-Ppt-Slides.ppt
 
Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)
 
newswitchgearandprotection-130925105559-phpapp02.pptx
newswitchgearandprotection-130925105559-phpapp02.pptxnewswitchgearandprotection-130925105559-phpapp02.pptx
newswitchgearandprotection-130925105559-phpapp02.pptx
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdf
 

Recently uploaded

Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 

Recently uploaded (20)

Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 

Insulation-Coordination-Fundamentals.pptx

  • 2. Webinar Outline  Initial basics of Insulation Coordination Studies  Definitions , Types, Parameters, Purposes  Examples of an Insulation Coordination Study  Basic Substation , Complex Substation, Transmission Line  BIL,BSL  The Backflash  Traveling Wave Phenomena  Arrester Fundamentals  Margin of Protection  Ground Flash Density  The Report
  • 3. Resources for this Webinar 1. Book: “Insulation Coordination of Power Systems” by Andrew (Bob) Hileman, 1999. 2. AR Hileman Software 3. ATP and ATP Draw, XY Plot 4. IEC 60071-1,2,3,4 5. IEEE C62.82.1 and .2 Formerly 1313.1 and .2 (Insulation Coordination Standards) 6. IEEE C62.11 Arrester Test Standards 7. IEEE C62.22 Arrester Application Guide 8. IEEE 1410 and 1243 Improving Lightning Performance of lines
  • 4. Definition of Insulation Coordination Simple Definition Insulation coordination is the selection of the insulation strength of a system. (Hileman) Better One Insulation coordination is the process where the insulation characteristics of all components of the power system are determined, specified and coordinated to avoid failure due to expected internal and externally occurring surges. (Hileman) Arrester Insulator
  • 5. Types of Insulation Coordination Studies  Transformer Protection  Substation Protection Open Air and GIS  Line Protection  Distribution and Transmission  Breaker Protection  Generator Protection  Determine clearances  Determine Separation Distances  Determine Arrester Energy and Voltage Ratings.  And on and on and on
  • 6. Types of Insulation Coordination Studies  Deterministic This is the conventional method where the minimum strength of the insulation is equal or greater than the maximum surge stresses. . Transformer insulation is not statistical in nature. It has one lightning withstand value and one switching withstand value. Therefore a deterministic analysis is all that we can do.
  • 7. Types of Insulation Coordination Studies  Probabilistic This type of analysis consists of selecting the insulation level and clearances based on specific reliability criterion. Since the insulation strength of air is statistical in nature, we can only determine its probability of Flashover for a given surge. Studies of transmission line performance is based on a flashover rate per year per 100km, and because the flashover parameter is statistical, resulting levels are probabilistic. Studies of substation performance is also probabilistic for the same reason. For this type of study we base the performance on MTBF (Mean Time Between Flashover). More later on this.
  • 8. Types of Insulation Coordination Studies  Lightning Surge Studies This type of study deals strictly with lightning surges and backflash over surges. Is completed for all system voltage levels.  Switching Surge Studies This type of study is usually for systems above 240kV since it is this type of system that can produce switching surges of relevance. If a lower voltage system has large cap banks, then a switching study is justified.
  • 9. Parameters of Importance in Studies • Purpose of Study • The Lightning Flash • Ground Flash Density • Shield Failure rate if known • Types of Insulation • BIL and CFO • MTBS and MTBF • Location and Altitude of Study • Cable and Isophase specs • Incoming Surge Steepness • Backflash Rate (BFR) • Calculating BFR • Tower Configurations • Circuit Physical Dimensions • The Transformer Ratings and Capacitance • The Arrester • VI Curve • Selecting the Rating
  • 10. Purpose of Insulation Coordination Studies  Can be to design proper insulation and arrester location from scratch  Can be to validate chosen insulation levels (Very common)  Can be to determine where to locate arresters  Can be to determine cause of failure of equipment (After an incident)  Can be to determine the Width of a ROW (Switching Study)  Can be to provide assurance that equipment is protected properly  Can be to put in the file for future reference  Can be to fulfill a requirement  Can be to …………. and more……
  • 11. Examples of Lightning Studies  Simple Substation from Chapter 12 of “Insulation Coordination of Power Systems”.  500kV Line-Substation-Generator  69kV Line Study
  • 15. Complex Insulation Coordination Study Incoming Line Switchyard with no transformers Cross over line to Generator Station 3 generator step up Transformers Three generators
  • 16. 69kV Sub 69kV Sub Transmission Line Study
  • 17. 69kV Sub Transmission Line Study
  • 18. 69kV Sub Transmission Line Study Insulator that flashes over at a specific voltage Underbuilt Circuit
  • 19. System Fundamentals Relative to Insulation Coordination 1. Insulation 2. Traveling Waves and Reflections, Backflash, and Separation Distance 3. Tower Grounds and Station Grounds 4. Corona 5. Steepness of Surges 6. Clearances 7. Physical Dimensions 8. Ground Flash Density 9. OHGW 10. Ground Flash Density
  • 20.  External Insulation The distance in open air or across the surfaces of solid insulation in contact with open air that is subjected to dielectric stress and to the effects of the atmosphere. Examples are porcelain or polymer shell of a bushing, support insulators, and disconnecting switches.  Self-restoring Insulation Insulation that completely recovers insulating properties after a disruptive discharge (flashover) caused by the application of a voltage. This is generally external insulation. Self restoring Insulator Terminator with Self-restoring Insulation on outside and non-self-restoring on inside Underground Cable with Non-Self Restoring Insulation
  • 21. Internal Insulation The internal solid, liquid, or gaseous parts of the insulation of equipment that are protected by equipment enclosures from the effects of the atmosphere. Examples are transformer insulation, internal insulation of bushings, internal parts of breakers and internal part of any electrical equipment. Non-self-restoring Insulation Insulation that loses insulating properties or does not recover completely after a disruptive discharge caused by the application of voltage. Generally internal insulation. Self Restoring Insulation Non-Self Restoring Insulation
  • 22. Basic Lightning Impulse Insulation Level (BIL) The BIL level is the Dry insulation withstand strength of insulation expressed in kV. Is commonly used to describe substations and distribution system voltage withstand characteristics.  Statistical BIL is used for insulators means there is a 10% probability of flashover and is used for self- restoring insulation  Conventional BIL is used for Transformers and Cable is the voltage level where there is a 0% probability of Flashover and is applied to non selfrestoring insulation Insulator BIL is directly proportional to the strike distance of an insulator BIL ≈ 15kV x S(inches) And is affected by Altitude Note 1: Arresters do not have a BIL rating since their external insulation is self protected by the internal MOV disks. In a sense they have an infinite BIL. Note 2: Arresters close to an insulator give the insulator infinite BIL.
  • 23. Basic Switching Impulse Insulation Level (BSL) The BSL level is the switching surge withstand level of the insulation in terms of kV. BSLs are universally tested under Wet conditions.  Statistical BSL of Insulators apply to self restoring insulation and represents a 10% probability of flashover.  Conventional BSL of Transformers and solid dielectrics apply to non-self-restoring insulation and represents a 0% probability of flashover BSL is proportional to the strike distance of an insulator BSL= 1080e((0.46 x Strike Distance) + 1) And is affected by Altitude Note 1: Arresters do not have a BSL rating since their external insulation is self protected by the internal MOV disks. In a sense they have an infinite BSL. Note 2: Arresters close to an insulator give the insulator infinite BSL.
  • 24. Power Frequency Withstand Voltage This is the highest power frequency voltage an insulator can withstand under wet conditions (low level of contamination). It is affected by creepage distance and strike distance. Note 2: Arresters will go into conduction if the AC voltage across the unit reaches a 1.25 pu MCOV and above. However they cannot sustain this condition for very long or they will over heat and fail. Note 3: If the housing is highly contaminated, the housing may flashover at levels below the turn-on voltage of the arrester. Note 4: In highly contaminated areas, extra creepage distance insulators are used to overcome this potentially low flashover voltage. The same policy should be applied to arresters. Note 1: Insulator withstand voltages are often >2-3 times their operating voltage.
  • 25. Critical Flash Over (CFO) Self Restoring insulation only This is the voltage with a 50% probability of flashover of the insulator. It applies to both lightning and switching. It is used to quantify insulation used on transmission and distribution lines. Typically CFO is 4-6% higher than Statistical BIL on an insulator. Chopped Wave Withstand (CWW) This is a withstand level of equipment. A standard lightning impulse is used but the surge is chopped at 3us, which means the stress is applied for a much shorter time than a standard lightning impulse test and must flashover near the crest of the wave instead of on the tail as it can in BIL tests. The value of this characteristic is about 1.10 times BIL for power transformers and 1.15 times BIL for bushings. Caused by insulator flashover just past crest. Can cause winding to winding stress in some transformers
  • 26. CWW Chopped Wave Withstand BIL Basic Impulse Withstand Level BSL Basic Switching Impulse Withstand Level Typical Values 70-1500kVp Another form of Lightning withstand is CFO Critical Flashover Voltage
  • 27. The Backflash When the OHGW on a transmission line is hit by lightning, a rapid series of events takes place. If the system is grounded well than the surge is transferred to earth and there is no effect on the phase conductors. But occasionally a backflash will occur, this series of slides will show you a close up view of the sequence of events.
  • 28. The Backflash Time = 0 The first event is the strike. Of course there was already a great deal of activity just to connect this line to the cloud, but that is for another sequence. When the strike pins to the wire, it sets up a voltage surge that travels in both directions down the line. (1-50 million volts) This is all happening at nearly the speed of light and until the surge actually finds ground, there is little current flow.
  • 29. The Backflash Time = 1 In a few Nano-seconds, the voltage front meets the down ground and travels toward earth at the tower bottom. While at the same time it is inducing a voltage on to the phase conductors When it reaches earth, the current begins to flow. The voltage along the tower increases rapidly due to ground potential rise. This potential rise is caused by the resistance of the ground rod of the tower. This tower voltage rises as the current begins to flow. Induced Induced
  • 30. The Backflash Time = 2 The voltage at the base of the base of the insulators and on the phase conductors increases as the surge increases in amplitude If the voltage at the base of the insulator increases at a faster rate than the induced voltage on phases, it can reach the CFO of the insulator
  • 31. The Backflash Time = 3 The voltages continue to increase across all components as the surge crests.
  • 32. The Backflash Time = 4 (.5-2 µsec) If the voltage across the insulator exceeds the CFO, it can flashover from the pole down ground to the phase. This is the backflash…… It flashes from the base to the conductor which is intuitively backward since the down ground spends its entire life except for these few microseconds at ground potential. This is the part of the event that we are interested in with insulation coordination studies. What effect this surge will have the substation. But its not over yet…..
  • 33. The Backflash Time = 5 (20-50 µsec) The lightning stroke is over and the voltages on the lines revert back to their pre-strike levels. But the air around the insulator is seeping with ions and still highly conductive. When the AC voltage reaches a high enough level, it now flashes forward from the phase conductor to the down ground.
  • 34. The Backflash Time = 6 (50 µsec to 200ms) When the insulator flashes over for a second time, power frequency current flows to ground and a fault is now underway on the circuit and will remain there until a breaker interrupts the event. At that point the event is over assuming no damage occurred on the insulator. AC Follow current causing a Line to Ground Fault Until breaker interrupts
  • 35. The Backflash The surge that is transferred onto the phase conductor has entered the station within a few µsec, even before the fault was initiated. This is the impulse that becomes the concern of insulation coordination in substations.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41. Note the voltage at the transformer is clamped by the arresters. Arresters CCVTs
  • 42.
  • 43.
  • 44. Arresters Note the voltage at the transformer is higher than at the arresters. This is due to traveling wave reflection Red = Voltage @ Arrester Green = Voltage @ Transformer 3 m separation 30 m separation Separation Distance
  • 45. Arresters the other half of Insulation Coordination
  • 47. • Polymer Housing • Metal Oxide Varistor (MOV) • Conductive Spacer • Strength Member (Fiberglass) • Spring for Compression • Rubber Seals • End Vents and Diaphragms
  • 48. VI Characteristics of an Arrester or Disk is the essence of the MOV. The resistance of the MOV disk is a function of the voltage stress across the terminals. Example 50kV MCOV Arrester
  • 49. Typical Varistor/Arrester V-I Characteristics |---------------------- Breakdown Region--------------------------------| Pre-Breakdown Region |--------------------------------------| High Current Region |---------------------------------------| Leakage Current Region V1ma or Reference Voltage Region TOV Region Switching Surge Region Lightning Impulse Region Normal Operating Region 20C 200C Physicists Terminology Engineering Terminology Vref or Uref V10kA or U10kA MCOV or UC (peak) Rated V or Ur peak LPL SPL
  • 50. Arrester Discharge Voltage Curve Fast Front Voltage 10kA Lightning Protective Level LPL Switching Surge Protective Level SPL Faster Front Surges Slower Front Surges
  • 51. Insulation Withstand Curve Arrester Discharge Voltage Curve Chopped Wave Withstand CWW Front of Wave Voltage FOW BSL BIL 10kA Lightning Protective Level LPL Switching Surge Protective Level SPL MP1= (CWW/FOW)-1 MP2= (BIL/LPL)-1 MP3= (BSL/SPL)-1 IEEE recommends > .15 or 15% IEEE recommends >.15 or 15% IEEE recommends >.20 or 20%
  • 53. Phase to phase and phase to ground clearances are often the purpose of a study. They are easily calculated once the maximum voltage on a line is determined. With arresters, the NEC clearances can be reduced near the arrester and along ROW if studies are completed. For example, Lightning Impulse withstand of Air at STP is a linear function at 450kV/m
  • 54. Clearance and Altitude/Elevation 0.600 0.650 0.700 0.750 0.800 0.850 0.900 0.950 1.000 0 2000 4000 6000 8000 10000 12000 Ratio of Altitude to Sea Level Elevation in Feet Change in Withstand voltage 'δ=e-A/26710 All external insulation is affected by altitude. Specifically in this case, the clearance between lines needs to be increased to attain the same withstand voltage at sea level.
  • 56. V V 30 0m NC V 25 meters V 2 m AFram LineA 5 ohms LCC R(i) R(i) Sourc V 2uh 2 meters 5 ohms L_imp H L_Imp LCC I V R(i) I 230kV 200 m NC 20 m 2 m Ej 230/13.8 BCT Y Et V Ea R(i) R(i) R(i) I 6.3nF 3m Eb V Insulation Coordination of Power Systems by Andrew Hileman Line Entrance Arrester Transformer Arrester Flashover of C-Phase close to substation 6000ft 2000 ft 2000 ft Surges travel at ~980ft per µs on an overhead line. In this elongated station, It can be seen here that the surge first appears at the metered points at different times based on the distance from the initial surge. Backflash 6000 ft out on the line At Station Entrance At Breaker At Arrester Elongated Substation
  • 58.
  • 59.
  • 60. Ground Flash Density Is used to calculate the • Backflash rate on a line • The challenge rate to a line • The outage rate of lines • Steepness of a surge on a line • The MTBF of a substation
  • 62. Webinar Overview Subjects covered 1. Definitions 2. Examples of Studies 3. Insulation Fundamentals 4. Backflash Concept 5. Traveling Wave Concept 6. Arrester Fundamentals 7. Clearances and Physical Dimensions 8. Lighting Ground Flash Densities 9. The Report