This Presentation made by Forth Group to fulfill assignment of Construction Method Subject in Department of Civil Engineering, Sebelas Maret University (UNS) Surakarta
This document summarizes the process and costs for a proposed 20,000 tonne per year titanium dioxide production plant using a carbochlorination process. It includes:
- A total fixed capital investment of Rs. 614.586 lakhs, including purchased equipment, installation, land, and other fixed costs.
- Total variable costs of Rs. 1,644.63 lakhs per year for raw materials, utilities, labor and other operating expenses.
- An estimated pre-tax profit of Rs. 1,309.2 lakhs per year, resulting in a payback period of 2.5 years.
- A break-even production volume of 18,000 tonnes per
Seminar 2 - Calculation Question (Excavation)Kai Yun Pang
This document provides data to calculate the cost of excavating and backfilling 4 pits for pad footings and columns. It includes hourly excavation and backfill rates for different types of excavation work in sand, daily labor rates, and adjustments needed for sand excavation, compaction, profit, and overhead to determine the total cost and unit rate per cubic meter. Skilled labor is required for excavation taking longer than 3 hours per cubic meter.
Project analysis and advanced data calculation and conditional formattingChachrist Srisuwanrat
This document discusses using Excel to simulate project risks and calculate project durations under uncertainty. It describes using Monte Carlo simulation to assign probabilistic durations to project activities, calculate early and late start/finish dates, and determine the project duration and float for multiple simulations. The results are analyzed to determine the best, most likely, and worst case project durations based on the simulations. Advanced data analysis techniques like two-way tables, conditional formatting, and data tables are demonstrated for calculating project profits and costs under different input assumptions.
This document describes maps created to illustrate the changing economic geography of the East Anglia fenlands in England over time. The maps were made by adding attribute data from historical figures documenting agricultural wealth distributions in 1087, 1327-1334, and 1641 to modern parish boundary shapefiles. Surficial geological data was also overlaid to correlate changes in land cover and wealth over periods. The maps show a migration of wealth from upland areas to the central lowlands fenlands between the time periods. The maps provide insight into how the economic geography and land use of the East Anglia fenlands region has changed through time.
This document describes a workshop on soil moisture content testing according to ASTM D-2216. The workshop covers conceptual aspects, laboratory equipment, testing procedures, calculations, and an example. Laboratory equipment includes an oven for drying samples at 110°C +/- 5°C, balances, containers, and tools. The procedure involves determining the weights of a dry container and saturated soil sample, drying the sample, and calculating moisture content as the percentage of water weight to solids weight. An example calculation is provided. Considerations for sample handling and minimum sample sizes based on particle size are also noted.
This document provides a cost estimate for a road construction project including equipment rates and estimated time calculations. It lists various equipment types needed, their hourly rates, and calculations to estimate the time and costs for trucking gravel, loading trucks, road grading, compaction, and watering. The summary provides a total estimated cost of $18,330.19 based on user-entered values for equipment hours.
This document provides details about Mitto manufacturing company which leases out machines to other companies. It asks to evaluate the leasing option for Mitto and calculate the break even and minimum lease rentals needed to earn a target NPV of Rs. 10,000.
The evaluation shows the leasing provides Mitto with a positive NPV of Rs. 21,669. The break even lease rental is calculated to be Rs. 56,265. And the minimum rental to earn the target NPV of Rs. 10,000 is Rs. 61,185.
This document contains 52 questions and answers related to the subject of Estimation and Quantity Surveying. It covers topics such as methods of calculating volumes, types of estimates, duties of quantity surveyors, components of contracts, specifications, types of contracts, and factors influencing property valuation. The document serves as a study guide for the VII semester Department of Civil Engineering course on Estimation and Quantity Surveying.
This document summarizes the process and costs for a proposed 20,000 tonne per year titanium dioxide production plant using a carbochlorination process. It includes:
- A total fixed capital investment of Rs. 614.586 lakhs, including purchased equipment, installation, land, and other fixed costs.
- Total variable costs of Rs. 1,644.63 lakhs per year for raw materials, utilities, labor and other operating expenses.
- An estimated pre-tax profit of Rs. 1,309.2 lakhs per year, resulting in a payback period of 2.5 years.
- A break-even production volume of 18,000 tonnes per
Seminar 2 - Calculation Question (Excavation)Kai Yun Pang
This document provides data to calculate the cost of excavating and backfilling 4 pits for pad footings and columns. It includes hourly excavation and backfill rates for different types of excavation work in sand, daily labor rates, and adjustments needed for sand excavation, compaction, profit, and overhead to determine the total cost and unit rate per cubic meter. Skilled labor is required for excavation taking longer than 3 hours per cubic meter.
Project analysis and advanced data calculation and conditional formattingChachrist Srisuwanrat
This document discusses using Excel to simulate project risks and calculate project durations under uncertainty. It describes using Monte Carlo simulation to assign probabilistic durations to project activities, calculate early and late start/finish dates, and determine the project duration and float for multiple simulations. The results are analyzed to determine the best, most likely, and worst case project durations based on the simulations. Advanced data analysis techniques like two-way tables, conditional formatting, and data tables are demonstrated for calculating project profits and costs under different input assumptions.
This document describes maps created to illustrate the changing economic geography of the East Anglia fenlands in England over time. The maps were made by adding attribute data from historical figures documenting agricultural wealth distributions in 1087, 1327-1334, and 1641 to modern parish boundary shapefiles. Surficial geological data was also overlaid to correlate changes in land cover and wealth over periods. The maps show a migration of wealth from upland areas to the central lowlands fenlands between the time periods. The maps provide insight into how the economic geography and land use of the East Anglia fenlands region has changed through time.
This document describes a workshop on soil moisture content testing according to ASTM D-2216. The workshop covers conceptual aspects, laboratory equipment, testing procedures, calculations, and an example. Laboratory equipment includes an oven for drying samples at 110°C +/- 5°C, balances, containers, and tools. The procedure involves determining the weights of a dry container and saturated soil sample, drying the sample, and calculating moisture content as the percentage of water weight to solids weight. An example calculation is provided. Considerations for sample handling and minimum sample sizes based on particle size are also noted.
This document provides a cost estimate for a road construction project including equipment rates and estimated time calculations. It lists various equipment types needed, their hourly rates, and calculations to estimate the time and costs for trucking gravel, loading trucks, road grading, compaction, and watering. The summary provides a total estimated cost of $18,330.19 based on user-entered values for equipment hours.
This document provides details about Mitto manufacturing company which leases out machines to other companies. It asks to evaluate the leasing option for Mitto and calculate the break even and minimum lease rentals needed to earn a target NPV of Rs. 10,000.
The evaluation shows the leasing provides Mitto with a positive NPV of Rs. 21,669. The break even lease rental is calculated to be Rs. 56,265. And the minimum rental to earn the target NPV of Rs. 10,000 is Rs. 61,185.
This document contains 52 questions and answers related to the subject of Estimation and Quantity Surveying. It covers topics such as methods of calculating volumes, types of estimates, duties of quantity surveyors, components of contracts, specifications, types of contracts, and factors influencing property valuation. The document serves as a study guide for the VII semester Department of Civil Engineering course on Estimation and Quantity Surveying.
The document discusses various topics related to facility location and layout including:
- Factors to consider for manufacturing and service location decisions such as labor costs, proximity to markets/suppliers, and quality of life.
- Three examples of approaches for evaluating potential facility locations: using weighted factors, a center of gravity model, and break-even analysis.
- Types of facility layouts including job shop and production line layouts as well as group technology cells.
- A case study demonstrating how to analyze facility layouts and optimize department relationships using closeness ratings and distance/transportation factors.
- An example of line balancing for assembling products.
The document discusses parameters for evaluating different mining methods. It focuses on three key objectives: 1) Maximum recovery of reserves while minimizing dilution and loss, 2) Maximum daily tonnage and productivity, and 3) Minimum operating costs. Some factors that impact these objectives are stope output, development requirements, personnel productivity, level of mechanization, and operating costs relative to room and pillar mining.
313440656 crane-lifting-calculation-sheetPhạm Thành
This document provides a checklist and calculation form for mobile crane lifts up to 10 tons. The form is to be completed each time the crane is set up in a new location to calculate the maximum planned lift weight and radius. It includes sections to record the crane setup details, total lift weight, crane capacity at the current setup, and sign-off from the crane operator, rigger, and supervisor.
The document discusses various methods for determining optimal facility locations, including the factor rating method, transportation method of linear programming, and centroid method. It provides an example of using the centroid method to calculate the best location for a new warehouse based on the locations and sales volumes of three existing automobile showrooms. Key factors that influence facility location planning include proximity to customers, business climate, infrastructure, labor quality, suppliers, and regulatory environment.
This document describes how heat map analysis was used to effectively summarize parking occupancy data from a study in Balmoral, Australia. The study was conducted to analyze the impacts of a new resident parking scheme. Rather than presenting the raw parking count data, heat maps were generated to provide a graphical representation of parking "density" over time. This approach allowed the data to be presented in a clear, easy to understand format that was resistant to misinterpretation compared to tabular data. The heat maps revealed parking patterns across different streets and time periods in the area to inform the ongoing review of the parking scheme.
The document discusses and compares four different location analysis methods - factor rating, weighted factor rating, load-distance, and center of gravity - to determine the best location for a new facility. The factor rating and weighted factor rating methods compare two potential mall locations based on factors like infrastructure, foot traffic, parking, etc. The load-distance method calculates load-distance scores for five census tracts based on their population and distance from two potential locations. The center of gravity method calculates the weighted average x and y coordinates of the census tracts to determine the center of gravity as a starting point for finding the optimal location.
INVENTORY CONTROL may be defined as a scientific method of finding out how much stock should be maintained in order to meet the production demands and be able to provide right type of material at right time in right quantities and at competitive prices..........
The document discusses factors to consider when determining an optimal production rate for a mine. It notes that the maximum rate yields the greatest financial return due to fixed costs, but a mine that is too small will not recover invested capital quickly enough. It also states that a larger mine size requires more upfront development time before seeing cash flow and that the mine life should be at least 7 years to allow for corrections and flexibility. Finally, it presents two formulas for relating production rate to ore reserves and annual deepening based on mine characteristics.
Soil carbon models for carbon stock estimation – where do we fail?ExternalEvents
This presentation was presented during the 2 Parallel session on Theme 1, Monitoring, mapping, measuring, reporting and verification (MRV) of SOC, of the Global Symposium on Soil Organic Carbon that took place in Rome 21-23 March 2017. The presentation was made by Mr. Aleksi Lethonen, from Natural Resources Institute - Finland, in FAO Hq, Rome
Fairfield university cost base analysis activityGraceProvenzano
This document compares the costs of three different water supply options for a community of 5,000 people over a 10-year period:
1) Purchasing and distributing water purification sachets would cost $144,309 per year, totaling $1,443,090 over 10 years.
2) Installing an industrial water treatment system capable of serving around 50,000 people would have an initial cost of $1,290,000, with total maintenance and operation costs of $3,225,000 over 10 years.
3) Installing 11 borehole wells with 5,000L storage tanks each would have an initial cost of $269,273 and total costs of $305,579
Towards a Tier 3 approach to estimate SOC stocks at sub-regional scale in Sou...ExternalEvents
This presentation was presented during the 2 Parallel session on Theme 1, Monitoring, mapping, measuring, reporting and verification (MRV) of SOC, of the Global Symposium on Soil Organic Carbon that took place in Rome 21-23 March 2017. The presentation was made by Ms. Roberta Farina, from CREA - Italy, in FAO Hq, Rome
The Petrojarl Knarr is a floating production, storage and offloading (FPSO) vessel designed to operate on the Knarr field located in the North Sea off the coast of Norway. It has a production capacity of 63,000 barrels of oil per day, 84,000 barrels of produced water per day, and can store 800,000 barrels of oil. The Petrojarl Knarr was delivered in 2014 and has a turret mooring system to operate in 410 meters of water for client BG Norge.
This document defines rate analysis in civil engineering projects as determining the rate of work like earthwork, concrete work, etc. It discusses factors that influence rates like material specifications, quantities, labor costs, transportation costs, and profit. Rate analysis is important to determine actual unit costs, economical use of materials, cost of extra work, and revising rates due to cost changes. The document provides examples of labor classification, lead statements to calculate material transportation costs, and defines lead and lift terms for earthwork.
This document provides an analysis of rates for various civil engineering works including excavation, sand filling, brick masonry, concrete works, and reinforced cement concrete works. It includes calculations of quantities of materials required and rates analysis for a unit quantity (typically 1 cubic meter or 10 cubic meters) with breakdown of material and labor costs. Factors affecting rates and data required for rate analysis are also discussed.
This document discusses sizing vessels for batch plants producing single and multiple products. For a single product plant producing 500,000 lbs/year, the cycle time and number of batches are calculated to determine the required vessel sizes. For a two-product plant, the production time for each product is determined based on demand to calculate the batch size and optimal vessel sizes for each stage.
New Measurement and Mapping of SOC in Australia supports national carbon acco...ExternalEvents
This presentation was presented during the 3 Parallel session on Theme 1, Monitoring, mapping, measuring, reporting and verification (MRV) of SOC, of the Global Symposium on Soil Organic Carbon that took place in Rome 21-23 March 2017. The presentation was made by Mr. Raphael Viscarra-Rossel from CSIRO - Australia, in FAO Hq, Rome
This document provides a cost breakdown for construction materials and supplies from Ozan Construction Company. It lists various materials like cement, plaster, lime, and adhesives, along with the unit price and quantity of each. The total cost before adding 20% profit is £5,466, and after adding profit the total cost is £6,559. It also lists the cost per unit for each material.
This document summarizes new and enhanced features in Digimap services from 2015-2016. Key updates include a refreshed homepage, responsive design for tablets, a new historic downloader application, marine chart roam with updated data, additions to ancient roam, land cover vector data, and improvements to geology, marine, and OS data. Usability and performance enhancements were also made, such as improved geo-referencing, easier use of 3D data, and a more reliable backend system. Feedback from users helped inform priority quality improvements.
The document provides an overview of campus safety at Daniel Webster College. It describes the main responsibilities of campus safety which include campus security, policy enforcement, and parking/vehicle regulation. It then outlines the qualifications of the 6 campus safety officers, including previous law enforcement experience. Finally, it details some of the technologies and services campus safety utilizes like emergency phones, patrols, an anonymous tip line, and emergency text alerts.
The document summarizes the green initiatives undertaken by the Parking and Transportation department at UC Berkeley. It discusses replacing the enforcement and maintenance fleet with hybrid and alternative fuel vehicles like Toyota Priuses and Ford trucks. It also describes the implementation of a ridesharing program called Cal Zimride and upgrades to the campus shuttle system, including the purchase of green buses and vans.
The document discusses parking facilities and businesses in Sector 5, Kolkata. It provides data on the number of vehicles parked and revenues generated for different parking operators in the area. It analyzes the average income and number of employees for these businesses. The median daily income across operators is calculated to be INR 1034. Parking in Sector 5 is a booming business generating significant revenues and employment opportunities. With the growing demand, more establishments and development in this sector can be expected going forward.
The term road traffic safety is an indication of how safe individual users are on some particular road, or on the roads belonging to some region.
It is sharing of knowledge for education purpose for road users - By Bimal Chandra Das / Kolkata / Bokaro
The document discusses various topics related to facility location and layout including:
- Factors to consider for manufacturing and service location decisions such as labor costs, proximity to markets/suppliers, and quality of life.
- Three examples of approaches for evaluating potential facility locations: using weighted factors, a center of gravity model, and break-even analysis.
- Types of facility layouts including job shop and production line layouts as well as group technology cells.
- A case study demonstrating how to analyze facility layouts and optimize department relationships using closeness ratings and distance/transportation factors.
- An example of line balancing for assembling products.
The document discusses parameters for evaluating different mining methods. It focuses on three key objectives: 1) Maximum recovery of reserves while minimizing dilution and loss, 2) Maximum daily tonnage and productivity, and 3) Minimum operating costs. Some factors that impact these objectives are stope output, development requirements, personnel productivity, level of mechanization, and operating costs relative to room and pillar mining.
313440656 crane-lifting-calculation-sheetPhạm Thành
This document provides a checklist and calculation form for mobile crane lifts up to 10 tons. The form is to be completed each time the crane is set up in a new location to calculate the maximum planned lift weight and radius. It includes sections to record the crane setup details, total lift weight, crane capacity at the current setup, and sign-off from the crane operator, rigger, and supervisor.
The document discusses various methods for determining optimal facility locations, including the factor rating method, transportation method of linear programming, and centroid method. It provides an example of using the centroid method to calculate the best location for a new warehouse based on the locations and sales volumes of three existing automobile showrooms. Key factors that influence facility location planning include proximity to customers, business climate, infrastructure, labor quality, suppliers, and regulatory environment.
This document describes how heat map analysis was used to effectively summarize parking occupancy data from a study in Balmoral, Australia. The study was conducted to analyze the impacts of a new resident parking scheme. Rather than presenting the raw parking count data, heat maps were generated to provide a graphical representation of parking "density" over time. This approach allowed the data to be presented in a clear, easy to understand format that was resistant to misinterpretation compared to tabular data. The heat maps revealed parking patterns across different streets and time periods in the area to inform the ongoing review of the parking scheme.
The document discusses and compares four different location analysis methods - factor rating, weighted factor rating, load-distance, and center of gravity - to determine the best location for a new facility. The factor rating and weighted factor rating methods compare two potential mall locations based on factors like infrastructure, foot traffic, parking, etc. The load-distance method calculates load-distance scores for five census tracts based on their population and distance from two potential locations. The center of gravity method calculates the weighted average x and y coordinates of the census tracts to determine the center of gravity as a starting point for finding the optimal location.
INVENTORY CONTROL may be defined as a scientific method of finding out how much stock should be maintained in order to meet the production demands and be able to provide right type of material at right time in right quantities and at competitive prices..........
The document discusses factors to consider when determining an optimal production rate for a mine. It notes that the maximum rate yields the greatest financial return due to fixed costs, but a mine that is too small will not recover invested capital quickly enough. It also states that a larger mine size requires more upfront development time before seeing cash flow and that the mine life should be at least 7 years to allow for corrections and flexibility. Finally, it presents two formulas for relating production rate to ore reserves and annual deepening based on mine characteristics.
Soil carbon models for carbon stock estimation – where do we fail?ExternalEvents
This presentation was presented during the 2 Parallel session on Theme 1, Monitoring, mapping, measuring, reporting and verification (MRV) of SOC, of the Global Symposium on Soil Organic Carbon that took place in Rome 21-23 March 2017. The presentation was made by Mr. Aleksi Lethonen, from Natural Resources Institute - Finland, in FAO Hq, Rome
Fairfield university cost base analysis activityGraceProvenzano
This document compares the costs of three different water supply options for a community of 5,000 people over a 10-year period:
1) Purchasing and distributing water purification sachets would cost $144,309 per year, totaling $1,443,090 over 10 years.
2) Installing an industrial water treatment system capable of serving around 50,000 people would have an initial cost of $1,290,000, with total maintenance and operation costs of $3,225,000 over 10 years.
3) Installing 11 borehole wells with 5,000L storage tanks each would have an initial cost of $269,273 and total costs of $305,579
Towards a Tier 3 approach to estimate SOC stocks at sub-regional scale in Sou...ExternalEvents
This presentation was presented during the 2 Parallel session on Theme 1, Monitoring, mapping, measuring, reporting and verification (MRV) of SOC, of the Global Symposium on Soil Organic Carbon that took place in Rome 21-23 March 2017. The presentation was made by Ms. Roberta Farina, from CREA - Italy, in FAO Hq, Rome
The Petrojarl Knarr is a floating production, storage and offloading (FPSO) vessel designed to operate on the Knarr field located in the North Sea off the coast of Norway. It has a production capacity of 63,000 barrels of oil per day, 84,000 barrels of produced water per day, and can store 800,000 barrels of oil. The Petrojarl Knarr was delivered in 2014 and has a turret mooring system to operate in 410 meters of water for client BG Norge.
This document defines rate analysis in civil engineering projects as determining the rate of work like earthwork, concrete work, etc. It discusses factors that influence rates like material specifications, quantities, labor costs, transportation costs, and profit. Rate analysis is important to determine actual unit costs, economical use of materials, cost of extra work, and revising rates due to cost changes. The document provides examples of labor classification, lead statements to calculate material transportation costs, and defines lead and lift terms for earthwork.
This document provides an analysis of rates for various civil engineering works including excavation, sand filling, brick masonry, concrete works, and reinforced cement concrete works. It includes calculations of quantities of materials required and rates analysis for a unit quantity (typically 1 cubic meter or 10 cubic meters) with breakdown of material and labor costs. Factors affecting rates and data required for rate analysis are also discussed.
This document discusses sizing vessels for batch plants producing single and multiple products. For a single product plant producing 500,000 lbs/year, the cycle time and number of batches are calculated to determine the required vessel sizes. For a two-product plant, the production time for each product is determined based on demand to calculate the batch size and optimal vessel sizes for each stage.
New Measurement and Mapping of SOC in Australia supports national carbon acco...ExternalEvents
This presentation was presented during the 3 Parallel session on Theme 1, Monitoring, mapping, measuring, reporting and verification (MRV) of SOC, of the Global Symposium on Soil Organic Carbon that took place in Rome 21-23 March 2017. The presentation was made by Mr. Raphael Viscarra-Rossel from CSIRO - Australia, in FAO Hq, Rome
This document provides a cost breakdown for construction materials and supplies from Ozan Construction Company. It lists various materials like cement, plaster, lime, and adhesives, along with the unit price and quantity of each. The total cost before adding 20% profit is £5,466, and after adding profit the total cost is £6,559. It also lists the cost per unit for each material.
This document summarizes new and enhanced features in Digimap services from 2015-2016. Key updates include a refreshed homepage, responsive design for tablets, a new historic downloader application, marine chart roam with updated data, additions to ancient roam, land cover vector data, and improvements to geology, marine, and OS data. Usability and performance enhancements were also made, such as improved geo-referencing, easier use of 3D data, and a more reliable backend system. Feedback from users helped inform priority quality improvements.
The document provides an overview of campus safety at Daniel Webster College. It describes the main responsibilities of campus safety which include campus security, policy enforcement, and parking/vehicle regulation. It then outlines the qualifications of the 6 campus safety officers, including previous law enforcement experience. Finally, it details some of the technologies and services campus safety utilizes like emergency phones, patrols, an anonymous tip line, and emergency text alerts.
The document summarizes the green initiatives undertaken by the Parking and Transportation department at UC Berkeley. It discusses replacing the enforcement and maintenance fleet with hybrid and alternative fuel vehicles like Toyota Priuses and Ford trucks. It also describes the implementation of a ridesharing program called Cal Zimride and upgrades to the campus shuttle system, including the purchase of green buses and vans.
The document discusses parking facilities and businesses in Sector 5, Kolkata. It provides data on the number of vehicles parked and revenues generated for different parking operators in the area. It analyzes the average income and number of employees for these businesses. The median daily income across operators is calculated to be INR 1034. Parking in Sector 5 is a booming business generating significant revenues and employment opportunities. With the growing demand, more establishments and development in this sector can be expected going forward.
The term road traffic safety is an indication of how safe individual users are on some particular road, or on the roads belonging to some region.
It is sharing of knowledge for education purpose for road users - By Bimal Chandra Das / Kolkata / Bokaro
The document provides details on calculating earthwork for a road construction project in Tank Road, D.I. Khan, Pakistan. It describes measuring cross-sectional areas along the road to determine cut and fill volumes needed. Cross sections were taken every 25 meters using a total station. The cut and fill areas were calculated in AutoCAD and exported to Excel to determine total cubic meters of earthwork. The results tables show the cut and fill volumes calculated for 40 cross sections along 1 kilometer of roadway.
Stabilizing slides and Road embankments
The spider excavator is an exceptional tool that can walk up steep slopes not accessible by normal tracked excavators.
they can safely work on 45 slopes and with cable stays can work on steeper slopes(using built-in winch)
Removal of continually failing headscarps is a concern for continued ravelling of a slope, and the raveled materials contributing to environmental degredation by entering water streams and also by plugging roadside ditches and diverting water flows across a road.
Contour drainage is used to "dry up" a moving slope and eliminate further mass slope movement(creep).
Traffic studies are carried out to analyze traffic characteristics and help decide geometric design and traffic control measures. The main traffic studies include traffic volume, speed, origin-destination, traffic flow characteristics, capacity, and accident studies. Traffic volume studies measure the number of vehicles on a road section over time and are used for planning, operations, and analysis. Speed studies measure the speeds of vehicles using methods like short-distance timing or radar guns.
Area and Volume Survey Engineering (RZ)Riezat Zainal
This document provides information on calculating areas and volumes for engineering projects. It begins by outlining the general and specific objectives of understanding basic area and volume calculation concepts and methods. It then discusses the importance of area and volume estimation in engineering works like route alignment and construction projects. Different methods for calculating areas are described, including rectilinear areas from chain or traversing surveys using triangles, trapezoidal approximation of irregular areas between survey lines, and using coordinates. Calculating volume is also briefly mentioned. Specific examples are provided to demonstrate calculating areas from field dimensions and coordinates.
Introduction; Application of Cut-and-Fill (C & F) stoping; The activity cycle of the (C & F) method; Stages of the production cycle of the C & F method; Sequences of extracting ore bodies; Filling in C & F Method; About filling of stopes; Functions of filler; Types of fillers; Advantages and disadvantages of the C & F method
This document provides an overview of earthwork planning, design, guidelines and regulatory requirements for a Bachelor of Civil Engineering course. It discusses definitions of earthwork, typical types of earthworks projects and problems associated with earthworks. It also outlines the objectives and content for the course, which will cover earthwork masterplanning, preliminary design, detail design, regulatory approvals, construction and post-construction stages. Design considerations like drainage, soil conditions, flood levels and slope stability are addressed. Methods for volume calculations and balancing cut and fill volumes are also summarized.
The document discusses the process of conducting procurements for a project. It describes the inputs, tools and techniques, and outputs of this process. The key inputs include the project management plan, procurement documents, source selection criteria, and seller proposals. Tools and techniques involve activities like bidder conferences, proposal evaluation, and procurement negotiations. The main outputs are selected sellers, agreements, resource calendars, and updates to the project management plan and documents.
information on types of beams, different methods to calculate beam stress, design for shear, analysis for SRB flexure, design for flexure, Design procedure for doubly reinforced beam,
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxRajeshKumar25548
This document discusses the planning, analysis, and design of a proposed three-story shopping mall building in Pollachi, India. Key aspects include:
1. The site is located on flat land near transport and utility infrastructure. Plans include parking, food courts, shops, and other facilities across three floors.
2. Structural elements like slabs, beams, columns, footings, and staircases were designed according to Indian codes and specifications. Materials include concrete, steel, and manufactured sand.
3. Analysis of the building was conducted using STAAD-Pro to determine loads, stresses, and required reinforcements. Seismic, wind, dead, and live loads were considered.
4.
Ready Mix Concrete (RMC) Production EfficiencyRushikesh Kolhe
This document analyzes the production efficiency of the ISM RMC Plant in Islampur. It finds that the plant is not operating at full capacity, with efficiencies ranging from 36.5-80.93% depending on delivery site. Long delivery distances and insufficient number of transit trucks are identified as causes of low efficiency. Recommendations include limiting delivery sites to within 10km of the plant and increasing the number of transit trucks to optimize production.
This document discusses various topics related to earthwork construction including:
1. Definitions of bank cubic yards, loose cubic yards, and compacted cubic yards and how they relate to soil volume changes during excavation and compaction.
2. Methods for calculating swell, shrinkage, load factors, and shrinkage factors to account for soil behavior during earthwork calculations.
3. Traditional and modern methods for calculating earthwork volumes for sitework, highways, and trenches using grids, cross sections, and software.
4. Key factors that influence soil compaction including moisture content, compactive effort, lift thickness, and compaction methods.
- A 4.6 m3 shovel with 35 tonne dumpers can produce 1.4 MT of material annually, requiring 2 shovels and 26 dumpers to handle 3 MT total.
- The productivity of each dumper is calculated to be 0.1116 MT.
- Proper synchronization of shovels and dumpers, measured by the match factor, is necessary to optimize production capacity and costs.
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
The document describes the excavator planning process at Drayton Mine in Australia. It involves 8 steps: 1) mine activity design, 2) 16 week schedule, 3) monthly operating plan design review, 4) MOP delivery plan meeting, 5) excavator plan sign off process, 6) weekly plan process and pack, 7) daily pit communication, and 8) dig area reviews. The comprehensive process focuses on long-term and short-term planning, communication, and continuous improvement to efficiently uncover coal while ensuring safety.
This document provides details about the construction of a multi-specialty Apollo hospital in Navi Mumbai, India. It discusses the project details including location, built-up area, completion timeline, and objectives. It also outlines the scope of work, quantities, agencies involved, construction activities and progress updates. Key aspects covered include the contract details, material information, construction methodology, quality testing procedures, and status of work completed.
Master Student Presentation in Construction Technology CourseSevar Dilkhaz
A barrage construction project requires careful planning and use of heavy equipment. The project will construct a large barrage to dam a river and maintain a predetermined water level. Equipment needs are estimated based on excavating 5.64 billion liters of loose soil over 8 years using 30 hydraulic shovels, 1440 trucks, 13 dozers, and 56 compactors. The total estimated cost of the project is $10.8 billion which covers equipment costs, fuel, maintenance, labor, and storage over the 8 year construction period.
Presentation on Summer internship on Road ConstructionSelf-employed
This is an presentation on training in LODHA Palava, In this internship, I learned about an overview of the road construction which I mentioned in this presentation.
The document discusses dozers, including their performance characteristics, production estimating, and safety. It classifies dozers based on their running gear as either crawler or wheel types. It explains how dozer production is estimated using blade capacity, efficiency, and total cycle time, which includes push, return, and maneuver times. The document provides an example calculation of estimated dozer production. It concludes with techniques to improve dozing efficiency, such as downhill dozing, slot dozing, and blade-to-blade dozing.
This presentation summarizes the key aspects of drilling a well, including:
1. Determining fracture gradients using Eaton's method and selecting casing depths. Proposing a casing program including 20" conductor, 13 3/8" surface, and 9 5/8" intermediate casing.
2. Designing the casing strings to withstand collapse, burst, and tensile pressures. Selecting H-40 casing for all strings.
3. Outlining a mud plan to maintain well control and hole stability using seawater and bentonite clay mixtures.
4. Proposing a bit plan including hole openers, tricone roller, and PDC bits suitable for hole sizes.
5. Estimating the drilling
The document outlines the aims, operations, and analysis of MJ Logistic Services Limited. The key objectives are to efficiently track warehouse operations, improve loading/unloading time and productivity, and increase storage space. MJ Logistic provides warehousing, transportation, distribution, and cold storage across multiple locations in North India. Analyses include ABC analysis of goods, FSN analysis of inventory categories, SWOT analysis of the company, and Porter's Five Forces analysis of the logistics industry in India.
This document provides an introduction and overview of the Jebel Ali Terminal 4, Phase 1 project located in Dubai, UAE. The scope of work includes dredging, construction of a 400m quay wall, reclamation areas, two causeways totaling over 2km, a 420m bridge, 5km of roads, buildings, and utilities for a general cargo yard. The 18.5 month project schedule is fast-tracked and will require 24 hour operations for some activities. An environmental impact assessment was conducted to determine baseline conditions and ensure the project does not adversely affect the environment.
Joint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptxHafidzQadli1
This document provides a mining plan for a 28 hectare joint operation over the first month. It includes production targets and equipment requirements for overburden removal, ore getting and hauling, and barging of ore. The total monthly cost is estimated at Rp 3,094,759,233.50 (USD 220,000) including costs for equipment, fuel, labor, and support. The profit is estimated based on shipping 6 barges of nickel ore at a price of USD 17 per tonne of nickel content.
This document provides an overview of mechanized construction and various types of construction equipment. It discusses the phases and benefits of mechanization for construction projects. Various earthmoving equipment are described in detail, including excavators, loaders, graders, backhoes, bulldozers, trenchers, scrapers, shovels, and draglines. Their uses, applications, and selection criteria for different project needs are explained. The document serves as a reference for understanding fundamental mechanical concepts and commonly used equipment in mechanized construction.
This document discusses optimizing the transportation of municipal waste from four dumping sites to two power plants to minimize costs. The dumping sites, transportation costs between each site and plant, available waste at each site, and requirements at each plant are provided. The objective is to minimize the total transportation cost using linear programming with constraints on waste availability and plant requirements. The problem is solved using the simplex method, with the minimum cost found to be 1909.1 thousand. The problem is then modified with different objective coefficients and waste availability, finding a minimum cost of 1567.1 thousand.
Massive Advantage in Mining - Using Scrapers for Efficient Material Transport...K-Tec Earthmovers Inc
As Presented By K-Tec Earthmovers at MinExpo 2016:
Scrapers are a valuable, yet underrated asset in mines and quarries. A scraper can pick-up, transport, and eject material with a single operator and power-unit. Find out how in some applications, the elimination of both an excavator and a dozer from a jobsite is possible, while obtaining a higher production output with a single scraper unit! This presentation will reveal jobsite scenarios to portray the labor, maintenance, and fuel efficiency savings, and corresponding cycle-times of using earthmoving scrapers for a successful mining application and wise return on investment.
Scrapers have been proven to work effectively in gravel quarries, coal & gypsum mines, while also being key for removing overburden and maintaining haul roads.
This presentation will also investigate new industry trend and technologies where, mining companies have been using Articulated Dump Trucks as the power-units to pull scrapers. The removal of the dump box and attachment of the scraper to the truck chassis is a helpful way to get more versatility out of an existing fleet of mining equipment.
Learn how to incorporate your own massive advantage in your mining operation by incorporating scrapers into your fleet.
http://www.ktec.com
Everything You Need To Know About Your Tank RemovalSREC_tanks
This document provides information about oil tank removal, including:
- Steve Rich Env. has over 30 years of experience removing more than 30,000 tanks with professional, background-checked workers.
- Tank removal is done in 13 steps: determining the tank's location, obtaining permits, emptying the tank, excavating, sampling soil if contamination is found, and proper disposal.
- It is important to remove old, corroded tanks to prevent expensive soil contamination from leaks, especially if the property is being sold. Soil sampling determines if remediation of contaminated soil is needed.
The document outlines proposed improvements to increase vehicle dispatch efficiency from 800 to 1200 bikes per day at a vehicle warehouse. Current issues include inconsistent backflushing of vehicles, slow bike movement between storage and dispatch areas, and bottleneck of loading one bike every 105 seconds using one scissor lift. Proposed improvements are to standardize backflushing at 60 vehicles per hour, add two-way doors to vehicle racks to reduce bike movement time to 31 seconds, and use two scissor lifts simultaneously to load one bike every 47 seconds. These changes would allow dispatch of 1200 bikes per day in three shifts while increasing bike storage capacity.
The CBC machine is a common diagnostic tool used by doctors to measure a patient's red blood cell count, white blood cell count and platelet count. The machine uses a small sample of the patient's blood, which is then placed into special tubes and analyzed. The results of the analysis are then displayed on a screen for the doctor to review. The CBC machine is an important tool for diagnosing various conditions, such as anemia, infection and leukemia. It can also help to monitor a patient's response to treatment.
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
Literature Review Basics and Understanding Reference Management.pptxDr Ramhari Poudyal
Three-day training on academic research focuses on analytical tools at United Technical College, supported by the University Grant Commission, Nepal. 24-26 May 2024
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
Advanced control scheme of doubly fed induction generator for wind turbine us...IJECEIAES
This paper describes a speed control device for generating electrical energy on an electricity network based on the doubly fed induction generator (DFIG) used for wind power conversion systems. At first, a double-fed induction generator model was constructed. A control law is formulated to govern the flow of energy between the stator of a DFIG and the energy network using three types of controllers: proportional integral (PI), sliding mode controller (SMC) and second order sliding mode controller (SOSMC). Their different results in terms of power reference tracking, reaction to unexpected speed fluctuations, sensitivity to perturbations, and resilience against machine parameter alterations are compared. MATLAB/Simulink was used to conduct the simulations for the preceding study. Multiple simulations have shown very satisfying results, and the investigations demonstrate the efficacy and power-enhancing capabilities of the suggested control system.
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Sinan KOZAK
Sinan from the Delivery Hero mobile infrastructure engineering team shares a deep dive into performance acceleration with Gradle build cache optimizations. Sinan shares their journey into solving complex build-cache problems that affect Gradle builds. By understanding the challenges and solutions found in our journey, we aim to demonstrate the possibilities for faster builds. The case study reveals how overlapping outputs and cache misconfigurations led to significant increases in build times, especially as the project scaled up with numerous modules using Paparazzi tests. The journey from diagnosing to defeating cache issues offers invaluable lessons on maintaining cache integrity without sacrificing functionality.
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...shadow0702a
This document serves as a comprehensive step-by-step guide on how to effectively use PyCharm for remote debugging of the Windows Subsystem for Linux (WSL) on a local Windows machine. It meticulously outlines several critical steps in the process, starting with the crucial task of enabling permissions, followed by the installation and configuration of WSL.
The guide then proceeds to explain how to set up the SSH service within the WSL environment, an integral part of the process. Alongside this, it also provides detailed instructions on how to modify the inbound rules of the Windows firewall to facilitate the process, ensuring that there are no connectivity issues that could potentially hinder the debugging process.
The document further emphasizes on the importance of checking the connection between the Windows and WSL environments, providing instructions on how to ensure that the connection is optimal and ready for remote debugging.
It also offers an in-depth guide on how to configure the WSL interpreter and files within the PyCharm environment. This is essential for ensuring that the debugging process is set up correctly and that the program can be run effectively within the WSL terminal.
Additionally, the document provides guidance on how to set up breakpoints for debugging, a fundamental aspect of the debugging process which allows the developer to stop the execution of their code at certain points and inspect their program at those stages.
Finally, the document concludes by providing a link to a reference blog. This blog offers additional information and guidance on configuring the remote Python interpreter in PyCharm, providing the reader with a well-rounded understanding of the process.
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...IJECEIAES
Climate change's impact on the planet forced the United Nations and governments to promote green energies and electric transportation. The deployments of photovoltaic (PV) and electric vehicle (EV) systems gained stronger momentum due to their numerous advantages over fossil fuel types. The advantages go beyond sustainability to reach financial support and stability. The work in this paper introduces the hybrid system between PV and EV to support industrial and commercial plants. This paper covers the theoretical framework of the proposed hybrid system including the required equation to complete the cost analysis when PV and EV are present. In addition, the proposed design diagram which sets the priorities and requirements of the system is presented. The proposed approach allows setup to advance their power stability, especially during power outages. The presented information supports researchers and plant owners to complete the necessary analysis while promoting the deployment of clean energy. The result of a case study that represents a dairy milk farmer supports the theoretical works and highlights its advanced benefits to existing plants. The short return on investment of the proposed approach supports the paper's novelty approach for the sustainable electrical system. In addition, the proposed system allows for an isolated power setup without the need for a transmission line which enhances the safety of the electrical network
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesChristina Lin
Traditionally, dealing with real-time data pipelines has involved significant overhead, even for straightforward tasks like data transformation or masking. However, in this talk, we’ll venture into the dynamic realm of WebAssembly (WASM) and discover how it can revolutionize the creation of stateless streaming pipelines within a Kafka (Redpanda) broker. These pipelines are adept at managing low-latency, high-data-volume scenarios.
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELgerogepatton
As digital technology becomes more deeply embedded in power systems, protecting the communication
networks of Smart Grids (SG) has emerged as a critical concern. Distributed Network Protocol 3 (DNP3)
represents a multi-tiered application layer protocol extensively utilized in Supervisory Control and Data
Acquisition (SCADA)-based smart grids to facilitate real-time data gathering and control functionalities.
Robust Intrusion Detection Systems (IDS) are necessary for early threat detection and mitigation because
of the interconnection of these networks, which makes them vulnerable to a variety of cyberattacks. To
solve this issue, this paper develops a hybrid Deep Learning (DL) model specifically designed for intrusion
detection in smart grids. The proposed approach is a combination of the Convolutional Neural Network
(CNN) and the Long-Short-Term Memory algorithms (LSTM). We employed a recent intrusion detection
dataset (DNP3), which focuses on unauthorized commands and Denial of Service (DoS) cyberattacks, to
train and test our model. The results of our experiments show that our CNN-LSTM method is much better
at finding smart grid intrusions than other deep learning algorithms used for classification. In addition,
our proposed approach improves accuracy, precision, recall, and F1 score, achieving a high detection
accuracy rate of 99.50%.
2. Introductions
Nowadays, Parking Area has become one of infrastructures
needed along increasingly of vehicles volume especially at
Engineering Faculty. Problems arising from the provision of
parking space itself is vacant land needed. Vacant land
located in the north of 4th Building requires an efficient
construction methods that can be implemented practically
3. Work Plan
Step 1 • Identification
Step 2 • Working Method Selection
Step 3 • Heavy Equipment Analysis
Step 4 • Cost Plan Analysis
Step 5 • Scheduling
Step 6 • Working Simulation
6. Identification
The following are main working items:
• Land clearing and top soil stripping
The purpose is for clearing the area from organics, therefore it
will ready for next work.
• Soil heap work
This work is done by collecting soil from the excavation to be
made as a pile of soil on the surface of the ground that has
lower elevation than planned.
7. Identification
• Total Volume = Area x Depth
= 610,13 x 1,65
= 1006,715 m3
• Stripping Volume = Area x Stripping Depth
= 610,13 x 0,15
= 91,5195 m3
• Digging Volume = Total Volume – Stripping Volume
= 1006,715 – 91,5195
= 915,195 m3
9. Working Method
• Land clearing and top soil stripping
Using the excavator as the primary heavy equipment which is
used for stripping and digging. The main idea is to use heavy
equipment as little as possible, but efficient.
• Soil heap work
LM that are transported by trucks to hauling site will condense
by the compactor. The results are expected not to exceed a
schedule of excavator.
25. Total Cost
No. Work
Equipme
nt
Number
of
Equipme
nt
Cost
(Rp)
Mob
deMob
(Rp)
Total Cost
(Rp)
1 Stripping
Backhoe
Komatsu
PC 60-1
1 1.330.000 1.500.000 2.830.000
2 Digging
Backhoe
Komatsu
PC 60-1
1 7.030.000 - 7.030.000
3 Loading Truck 2 7.700.000 - 7.700.000
4
Compactin
g
Vibro 10
ton
1 8.400.000 1.500.000 9.900.000
10 % of Total Cost 2.746.000
TOTAL 30.206.000