SlideShare a Scribd company logo
 Definition
 Factors
 Importance
 Terminology
 Examples
 The process of determining rate of any work in
Civil Engineering project like earthwork,
concrete work, brickwork, plastering, painting
etc. is known as Analysis of Rates or simply Rate
Analysis.
 The rates of these works further help in
determining cost of particular work and in turn
cost of the project.
 The rate of any process or work depends on
various factors.
The various factors that are involved in determining
rate of any process or work are mentioned below :
 Specifications of works and material about their
quality, proportion and constructional operation
method.
 Quantity of materials and their costs.
 Cost of labour and their wages.
 Location of site of work and the distances from
source and conveyance charges.
 Overhead and establishment charges
 Profit
 To determine the actual cost per unit of the
items.
 To work out the economical use of materials and
processes in completing the particulars item.
 To calculate the cost of extra items which are
not provided in the contract bond, but are to be
executed as per the directions of the
department.
 To revise the schedule of rates due to increase in
the cost of material and labour or due to change
in technique.
 Labour : May be classified into three types.
 Skilled Ist class
 Skilled IInd class
 Unskilled
Labour charges can be obtained from Schedule of Rates. 30% of
the skilled labour in data should be taken as Ist class and
remaining 70% as IInd class.
 Lead Statement :The distance between the source of
availability of material and construction site is known as
Lead and is calculated in km.The conveyance cost of
material depends on lead
 The lead statement will give the total cost of materials per unit
item including first cost, conveyance loading-unloading,
stacking charges etc.
S.No. Materials Cost at
Source
Per Lead in Km Conveyance
charges per
Km
1 Rough Stone 260.00 cum 18 5.00/cum
2 Sand 12.00 cum 25 4.00/cum
3 Cement 2100.00 tonn Local -
S.No. Mtls. Cost at
Source
Per Lead
in
Km
Conveyance
charges Rs.
Total
Conveyance
charges Rs.
Total Cost
Rs.
1 Rough
Stone
260.00 cum 18 5.00/cum 5×18= 90.00 260+90=
350.00
2 Sand 12.00 cum 25 4.00/cum 4×25= 100.00 100+12=
112.00
3 Cement 2100.00 tonn Local - - 2100/
tonn
Analysis of Rates from Lead Statement
 Lead : During the earthwork, the average horizontal
distance between center of excavation to the center
of deposition is known as Lead.
 Lead is normally calculated in multiple of 50m
 Lift : Similarly during the earthwork, the average
height through which soil has to be lifted from source
to the place of spreading(also known as heaping) is
known as Lift.
 The first Lift is taken upto 2m.
 The extra lift is counted for upto 1m after the first lift and
so on.
Let us say we need to calculate number of lifts
when soil is to be lifted 3.5m from the source.
 Upto 2m : 1 Lift
 1m : 1 Lift
 0.5m : 1 Lift
Total number of Lifts are 3 in this case.
For practicing how to carry out Rate Analysis ,
please refer the following books :
 Estimating and Costing by B.N. Datta, UBSPD,
New Delhi
 Estimating and Costing by G.S. Birdie, Dhanpat
Rai Publication New Delhi
 Estimating and Costing byV.N. Chakravorty,
Calcutta
 Civil Engg. Contracts & Estimates by B.S. Patil,
Orient-Longman Ltd., New Delhi
THANK YOU

More Related Content

What's hot

Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
Japtyesh Singh
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 
rate analysis
rate analysisrate analysis
rate analysis
Ganesh Tatikonda
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
ArunRavi43
 
Advanced construction equipments and techniques
Advanced construction equipments and techniquesAdvanced construction equipments and techniques
Advanced construction equipments and techniques
selva ganesh
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
Raj Shah
 
Valuation
ValuationValuation
Valuation
gayu pandian
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
EQS - RATE ANALYSIS.pdf
EQS -  RATE ANALYSIS.pdfEQS -  RATE ANALYSIS.pdf
EQS - RATE ANALYSIS.pdf
GovindarajuluBadana
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
GAURAV. H .TANDON
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Prasad Manerikar
 
Earthwork
EarthworkEarthwork
Earthwork
Rajiva Gupta
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
Sahl Buhary
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
Avinash Kumar Gupta
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
DhavalMithaiwala
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
AyushHajare
 
Rate analysis vansheika
Rate analysis   vansheikaRate analysis   vansheika
Rate analysis vansheika
VansheikaThakur
 

What's hot (20)

Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
rate analysis
rate analysisrate analysis
rate analysis
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
Advanced construction equipments and techniques
Advanced construction equipments and techniquesAdvanced construction equipments and techniques
Advanced construction equipments and techniques
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Valuation
ValuationValuation
Valuation
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
EQS - RATE ANALYSIS.pdf
EQS -  RATE ANALYSIS.pdfEQS -  RATE ANALYSIS.pdf
EQS - RATE ANALYSIS.pdf
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Earthwork
EarthworkEarthwork
Earthwork
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Estimation
EstimationEstimation
Estimation
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Rate analysis vansheika
Rate analysis   vansheikaRate analysis   vansheika
Rate analysis vansheika
 

Similar to Analysis of rates

Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
ashoklalwani6
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
NaumanIjaz12
 
UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
AkashM725543
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structures
Ayan Sengupta
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
Padmasinh Patil
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
BALAMURUGANR53
 
Construction Estimating.pdf
Construction Estimating.pdfConstruction Estimating.pdf
Construction Estimating.pdf
SoniaGandhi26
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
NSHYAMANANDASINGH
 
Basics of estimation
Basics of estimation Basics of estimation
Basics of estimation
ddscte
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
SOUMITRAMUDI
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing book
Subash Pathak
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
sooricivil
 
Rate Analysis.pptx
Rate Analysis.pptxRate Analysis.pptx
Rate Analysis.pptx
ShubhamVERMA324448
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
cricketreview
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
Padmasinh Patil
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
TauheedKhan45
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
AHMADAHMAD735251
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
hlksd
 

Similar to Analysis of rates (20)

Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structures
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Construction Estimating.pdf
Construction Estimating.pdfConstruction Estimating.pdf
Construction Estimating.pdf
 
Ecv
EcvEcv
Ecv
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
Basics of estimation
Basics of estimation Basics of estimation
Basics of estimation
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing book
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Rate Analysis.pptx
Rate Analysis.pptxRate Analysis.pptx
Rate Analysis.pptx
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
 

Recently uploaded

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 

Recently uploaded (20)

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 

Analysis of rates

  • 1.
  • 2.  Definition  Factors  Importance  Terminology  Examples
  • 3.  The process of determining rate of any work in Civil Engineering project like earthwork, concrete work, brickwork, plastering, painting etc. is known as Analysis of Rates or simply Rate Analysis.  The rates of these works further help in determining cost of particular work and in turn cost of the project.  The rate of any process or work depends on various factors.
  • 4. The various factors that are involved in determining rate of any process or work are mentioned below :  Specifications of works and material about their quality, proportion and constructional operation method.  Quantity of materials and their costs.  Cost of labour and their wages.  Location of site of work and the distances from source and conveyance charges.  Overhead and establishment charges  Profit
  • 5.  To determine the actual cost per unit of the items.  To work out the economical use of materials and processes in completing the particulars item.  To calculate the cost of extra items which are not provided in the contract bond, but are to be executed as per the directions of the department.  To revise the schedule of rates due to increase in the cost of material and labour or due to change in technique.
  • 6.  Labour : May be classified into three types.  Skilled Ist class  Skilled IInd class  Unskilled Labour charges can be obtained from Schedule of Rates. 30% of the skilled labour in data should be taken as Ist class and remaining 70% as IInd class.  Lead Statement :The distance between the source of availability of material and construction site is known as Lead and is calculated in km.The conveyance cost of material depends on lead  The lead statement will give the total cost of materials per unit item including first cost, conveyance loading-unloading, stacking charges etc.
  • 7. S.No. Materials Cost at Source Per Lead in Km Conveyance charges per Km 1 Rough Stone 260.00 cum 18 5.00/cum 2 Sand 12.00 cum 25 4.00/cum 3 Cement 2100.00 tonn Local - S.No. Mtls. Cost at Source Per Lead in Km Conveyance charges Rs. Total Conveyance charges Rs. Total Cost Rs. 1 Rough Stone 260.00 cum 18 5.00/cum 5×18= 90.00 260+90= 350.00 2 Sand 12.00 cum 25 4.00/cum 4×25= 100.00 100+12= 112.00 3 Cement 2100.00 tonn Local - - 2100/ tonn Analysis of Rates from Lead Statement
  • 8.  Lead : During the earthwork, the average horizontal distance between center of excavation to the center of deposition is known as Lead.  Lead is normally calculated in multiple of 50m  Lift : Similarly during the earthwork, the average height through which soil has to be lifted from source to the place of spreading(also known as heaping) is known as Lift.  The first Lift is taken upto 2m.  The extra lift is counted for upto 1m after the first lift and so on.
  • 9. Let us say we need to calculate number of lifts when soil is to be lifted 3.5m from the source.  Upto 2m : 1 Lift  1m : 1 Lift  0.5m : 1 Lift Total number of Lifts are 3 in this case.
  • 10. For practicing how to carry out Rate Analysis , please refer the following books :  Estimating and Costing by B.N. Datta, UBSPD, New Delhi  Estimating and Costing by G.S. Birdie, Dhanpat Rai Publication New Delhi  Estimating and Costing byV.N. Chakravorty, Calcutta  Civil Engg. Contracts & Estimates by B.S. Patil, Orient-Longman Ltd., New Delhi