Project Management
Important Equations for the
Final and Assignment Test
Mahesh Kodituwakku
EV = budget cost * % of work done
Scheduled Variance
SV = EV - PV
If SV < 0
Project is behind the Scheduled
Cost Variance
CV = EV - AC
If CV < 0
Cost over run
Account Variance
AV = PV - AC
Difference between current budget and
the actual expenditure
Performance Index
Scheduled Performance Index
SPI = EV / PV
Cost Performance Index
CPI = EV / AC
If
SPI and CPI >1.0
Work head of scheduled and under
budget
Study following details given below and find the
EV,SV,CV,AV ,SPI and CPI of the project
Answer

Project Management-Important Equations